Sie sind auf Seite 1von 120

N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 1 of 66 JAN-2012

POWER SYSTEM OPERATION CORPORATION LTD











Reactive Power Management a resource handbook





N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 2 of 66 JAN-2012




































N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 3 of 66 JAN-2012




INDEX

1. Introduction
2. Statutory provisions for reactive power management & voltage control
3. Reactive power & voltage control - basic concepts
4. Transmission lines and reactive power compensation
5. Series and shunt capacitorstheir effect on reactive power
6. Transformer tap changer effect on reactive power
7. HVDC operation effect on reactive power
8. FACTS & reactive power control
9. Generator reactive power capability
10. Reactive power management and renewable energy
11. Ready Reckoner
12. References











N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 4 of 66 JAN-2012



ANNEXURES:

1. Inter regional transmission lines(400kV & above AC)
2. All India reactive power compensation details
3. Estimated MVAr relief available when line is opened
4. 400 & 765kV reactors installed capacity-All India level.
5. Fault level of substations.
6. Surge Impedance Loading (SIL) of transmission lines.
7. List of 765kV lines to be commissioned during 2012
8. Shunt capacitors installed capacity-All India level.
9. Series compensation and SVC All India level
10. ICT tap position details
11. Typical transformer tap changer online/offline detail
12. List of synchronous condensers.


























N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 5 of 66 JAN-2012


1. Introduction

1.1 The objective of this Reactive Power Management resource handbook is to
place before the load dispatch centre personnel a handy reference document
to facilitate reliable operation of the Indian power system through optimal
utilization of the available reactive power resources

1.2 Developments in power sector have seen more high voltage transmission
lines at 765 kV and HVDC systems, large generating stations coming up,
which makes the Indian grid more and more complex. Indian grid has
interconnection with neighbouring countries also. Hence the need was felt
to develop the written document for the guidance of real time operator on
reactive power management for day to day operation.

1.3 No special reactive compensation devices were used in the early AC power
systems, because the generators were situated close to the loads. As
networks became more widespread, there was a need for development of
reactive power compensation devices.


1.4 In an integrated power system, efficient management of active and reactive
power flow is very important. Quality of power supply is judged from the
frequency and voltage of the power supply made available to the
consumers. While frequency is the measure of balance between power
generated (and power available) and MW demand impinged on the system,
the voltage is indicative of reactive power flows.

1.5 During the steady-state operation of an AC power system, the active power
production must match the consumption plus the losses otherwise the
frequency will change. There is an equally strong relationship between the
reactive power balance of a power system and the voltages

1.6 Control of voltage and reactive power should satisfy the following
objectives:
a) Control the power flow in the system to an optimal level in order to reduce
losses. This ensures that the transmission system operates efficiently.
b) Maintain power supply quality by maintaining bus voltages close to
nominal value.
c) To control the reserve reactive power in order to ensure its sufficiency
during normal and emergency conditions to prevent voltage collapse.
d) System stability is enhanced to maximize utilization of the transmission
system. Voltage and reactive power control have a significant impact on
system stability.
e) Maximize the existing reactive power resources to minimize investment in
additional facilities.

N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 6 of 66 JAN-2012


1.7 Since reactive power cannot be transmitted over long distances, voltage
control has to be effected by using special devices dispersed throughout the
system.

1.8 Reactive power (VAR) is required to maintain the voltage to deliver active
power (watts) through transmission lines. Motor loads and other loads
require reactive power to convert the flow of electrons into useful work.
When there is not enough reactive power, the voltage sags down and it is
not possible to push the power demanded by loads through the lines.

1.9 A great many loads consume not only active but also reactive power. The
electric network itself both consumes and produces reactive power.
Transmission and distribution of electric power involve reactive power
losses due to the series inductance of transformers, overhead lines and
underground cables. The generation of power also contains reactive
components. Hence it is important to monitor and control reactive power
resources and reactive power consuming elements to maintain proper
voltages in the grid within safe and secure limits

1.10 This document covers the basic concepts of reactive power, production and
absorption of reactive power, Methods of voltage control, Applications of
Reactor, capacitor and FACTS/SVC to the transmission system,
Synchronous condenser, Application of tap changing of Transformer etc.

1.11 NLDC/RLDCs shall follow up and examine reactive power absorption and
injection sources to ensure the sufficiency of reactive power absorption and
injection sources in their areas in order to maintain voltage levels at all
points during normal and emergency conditions. RLDCs/NLDC needs to
compile the constantly updated information concerning the availability of
relevant equipment.

1.12 This document is in particular focusing on reactive power management at
All India Level. Hence this document is to be read in conjunction with
respective RLDC reactive power document for respective regions reactive
power resource details.










N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 7 of 66 JAN-2012


2. Statutory provisions for reactive power management &
voltage control

2.1 PROVISION IN THE IEGC

2.1.1 As per sec 3.5 of IEGC planning criterion general philosophy:

3.5 Planning Criterion
General philosophy
a) The planning criterion are based on the security philosophy on which
the ISTS has been planned. The security philosophy may be as per the
Transmission Planning Criteria and other guidelines as given by CEA.
The general policy shall be as detailed below:
i) As a general rule, the ISTS shall be capable of withstanding and be
secured against the following contingency outages.
a) without necessitating load shedding or rescheduling of generation
during Steady State Operation:
- Outage of a 132 kV D/C line or,
- Outage of a 220 kV D/C line or,
- Outage of a 400 kV S/C line or,
- Outage of single Interconnecting Transformer, or
- Outage of one pole of HVDC Bipole line, or one pole of HVDC
back to back Station or
- Outage of 765 kV S/C line.
b) without necessitating load shedding but could be with rescheduling
of generation during steady state operation-
- Outage of a 400 kV S/C line with TCSC, or
- Outage of a 400kV D/C line, or
- Outage of both pole of HVDC Bipole line or both poles of HVDC
back to back Station or
- Outage of a 765kV S/C line with series compensation.

ii) The above contingencies shall be considered assuming a pre-contingency
system depletion (Planned outage) of another 220 kV D/C line or 400 kV
S/C line in another corridor and not emanating from the same substation.
The planning study would assume that all the Generating Units may
operate within their reactive capability curves and the network voltage
profile shall also be maintained within voltage limits specified.

e) CTU shall carry out planning studies for Reactive Power compensation of
ISTS including reactive power compensation requirement at the
generators /bulk consumers switchyard and for connectivity of new
generator/ bulk consumer to the ISTS in accordance with Central
Electricity Regulatory Commission (Grant of Connectivity, Long-term
N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 8 of 66 JAN-2012


Access and Medium-term Open Access in inter-state Transmission and
related matters) Regulations, 2009.



2.1.2 IEGC Section 4.6.1 Important Technical Requirements for Connectivity:

4.6.1 Reactive Power Compensation
a) Reactive Power compensation and/or other facilities shall be provided by
STUs, and Users connected to ISTS as far as possible in the low voltage
systems close to the load points thereby avoiding the need for exchange of
Reactive Power to/from ISTS and to maintain ISTS voltage within the
specified range.
b) The person already connected to the grid shall also provide additional
reactive compensation as per the quantum and time frame decided by
respective RPC in consultation with RLDC. The Users and STUs shall
provide information to RPC and RLDC regarding the installation and
healthiness of the reactive compensation equipment on regular basis. RPC
shall regularly monitor the status in this regard.


2.1.3 IEGC Section 5.2 System Security Aspects

5.2 System Security Aspects

(s) All Users, RLDC, SLDC/STUs, CTU and NLDC shall take all possible
measures to ensure that the grid voltage always remains within the
following operating range.

Voltage (kV-rms)
Nominal Minimum Maximum
765 728 800
400 380 420
220 198 245
132 122 145
110 99 121
66 60 72
33 30 36

t) All Users, CTU and STUs shall provide adequate voltage control measures
through voltage relay as finalized by RPC, to prevent voltage collapse and
shall ensure its effective application to prevent voltage collapse/cascade
tripping.

(u) Special requirements for Solar/ wind generators

N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 9 of 66 JAN-2012


(i) SLDC/RLDC may direct a wind farm to curtail its VAr drawl/injection
in case the security of grid or safety of any equipment or personnel is
endangered.
(ii) During the wind generator start-up, the wind generator shall ensure that
the reactive power drawl (inrush currents in case of induction
generators shall not affect the grid performance.


2.1.4 IEGC Section 5.3(g) Demand Estimation for Operational Purposes

5.3 Demand Estimation for Operational Purposes

g) The SLDC shall take into account the Wind Energy forecasting to meet
the active and reactive power requirement.

2.1.5 IEGC Section 6. Scheduling and Despatch Code

6.6 Reactive Power and Voltage Control

1) Reactive power compensation should ideally be provided locally, by
generating reactive power as close to the reactive power consumption as
possible. The Regional Entities except Generating Stations are therefore
expected to provide local VAr compensation/generation such that they do
not draw VArs from the EHV grid, particularly under low-voltage
condition. To discourage VAr drawals by Regional Entities except
Generating Stations, VAr exchanges with ISTS shall be priced as follows:
- The Regional Entity except Generating Stations pays for VAr drawl when
voltage at the metering point is below 97%
- The Regional Entity except Generating Stations gets paid for VAr return
when voltage is below 97%
- The Regional Entity except Generating Stations gets paid for VAr drawl
when voltage is above103%
The Regional Entity except Generating Stations pays for VAr return when
voltage is above 103%, Provided that there shall be no charge/payment for
VAr drawl/return by a Regional Entity except Generating Stations on its
own line emanating directly from an ISGS.

2) The charge for VArh shall be at the rate of 10 paisa/kVArh w.e.f. 1.4.2010,
and this will be applicable between the Regional Entity, except Generating
Stations, and the regional pool account for VAr interchanges. This rate shall
be escalated at 0.5paise/kVArh per year hereafter, unless otherwise revised
by the Commission.

3) Notwithstanding the above, RLDC may direct a Regional Entity except
Generating Stations to curtail its VAr drawl/injection in case the security of
grid or safety of any equipment is endangered.
N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 10 of 66 JAN-2012



4) In general, the Regional Entities except Generating Stations shall endeavor
to minimize the VAr drawl at an interchange point when the voltage at that
point is below 95% of rated, and shall not return VAr when the voltage is
above 105%. ICT taps at the respective drawal points may be changed to
control the VAr interchange as per a Regional Entity except Generating
Stations request to the RLDC, but only at reasonable intervals.

5) Switching in/out of all 400 kV bus and line Reactors throughout the grid
shall be carried out as per instructions of RLDC. Tap changing on all
400/220 kV ICTs shall also be done as per RLDCs instructions only.

6) The ISGS and other generating stations connected to regional grid shall
generate/absorb reactive power as per instructions of RLDC, within
capability limits of the respective generating units, that is without sacrificing
on the active generation required at that time. No payments shall be made
to the generating companies for such VAr generation/absorption.

7) VAr exchange directly between two Regional Entities except Generating
Stations on the interconnecting lines owned by them (singly or jointly)
generally address or cause a local voltage problem, and generally do not
have an impact on the voltage profile of the regional grid. Accordingly, the
management/control and commercial handling of the VAr exchanges on
such lines shall be as per following provisions, on case-by-case basis:

i) The two concerned Regional Entities except Generating Stations may
mutually agree not to have any charge/payment for VAr exchanges
between them on an interconnecting line.

ii) The two concerned Regional Entities except Generating Stations may
mutually agree to adopt a payment rate/scheme for VAr exchanges
between them identical to or at variance from that specified by CERC
for VAr exchanges with ISTS. If the agreed scheme requires any
additional metering, the same shall be arranged by the concerned
Beneficiaries.

iii) In case of a disagreement between the concerned Regional Entities
except Generating Stations (e.g. one party wanting to have the
charge/payment for VAr exchanges, and the other party refusing to
have the scheme), the scheme as specified in Annexure-2 shall be
applied. The per kVArh rate shall be as specified by CERC for VAr
exchanges with ISTS.

iv) The computation and payments for such VAr exchanges shall be
effected as mutually agreed between the two Beneficiaries.

N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 11 of 66 JAN-2012


2.2 PROVISION IN THE CENTRAL ELECTRICITY AUTHORITY
(TECHNICAL STANDARD FOR CONNECTIVITY TO THE GRID)
REGULATIONS 2007:
Extracts from this standards is as reproduced below for ready reference.

Part II: Grid Connectivity Standards applicable to the Generating Units
The units at a generating station proposed to be connected to the grid shall
comply with the following requirements besides the general connectivity
conditions given in the regulations and general requirements given in part-I
of the Schedule:-
1. New Generation Units
Hydro generating units having rated capacity of 50MW and above shall
be capable of operating in synchronous condenser mode, where ever
feasible.

2. Existing Units
For thermal generating unit having rated capacity of 200 MW and above
and hydro units having rated capacity of 100 MW and above, the
following facilities would be provided at the time of renovation and
modernization.
(1) Every generating unit shall have Automatic Voltage Regulator.
Generators having rated capacity of 100 MW and above shall have
Automatic Voltage Regulator with two separate with two separate
channels having independent inputs and automatic changeover.






















N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 12 of 66 JAN-2012


3. Reactive power & voltage control - Basic concepts

3.1 REACTIVE POWER

3.1.1 Reactive power is defined for AC systems only. Reactive power is produced
when the current waveform is out of phase with the voltage waveform due
to inductive or capacitive loads. Current lags voltage with an inductive load
and leads voltage with a capacitive load. Only the component of current in
phase with voltage produces real or active power that does real work like
running motors, heating etc. Current is in phase with voltage for a resistive
load like an incandescent light bulb. Reactive power is necessary for
producing the electric and magnetic fields in capacitors and inductors.

3.1.2 Reactive power is present when the voltage and current are not in phase,
one waveform leads the other, Phase angle not equal to zero and power
factor less than unity. It is measured in volt-ampere reactive (VAR). It is
produced when the current waveform leads voltage waveform (Leading
power factor). Vice versa, consumed when the current waveform lags
voltage (lagging power factor).













Power Triangle



3.1.3 Real and reactive power is in quadrature (90 degrees out of phase) and
hence the letter Q is commonly used to designate reactive power. Real
power is commonly designated as P.

N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 13 of 66 JAN-2012




3.1.4 Analogy #1 for Active Power and Reactive power is the bicycle analogy.
Power stations, producing electrical energy, are represented by bikers. At
the backseat of the bike there are passengers, the consumers of electrical
energy (the loads). A reactive load can be represented by a passenger
leaning to one side. The fact that the passenger is leaning to one side, does
not influence directly the work that the biker has to deliver, but without
compensation, the bike might fall over. The biker compensates the
movement of his passenger by leaning in opposite direction (= by
generating reactive power).
Consequences:
A pedaling figure leaning to one side cannot work as comfortably as
before i.e. limiting capacity of transmission line
The bike catches more head wind i.e. extra losses.



BICYCLE ANALOGY

3.1.5 Another analogy for understanding the Reactive power concept is the Beer
Mug analogy, a bit simplistic. Reactive power takes up space on
transmission lines. Here reactive power is like the head on a beer because it
takes up space in the glass leaving less room for the real beer. For a
transmission line, the square of the real power plus the square of the
reactive power must be less than the square of the thermal capacity
(measured in volt-amperes) of the line. When thermal capacity is exceeded
significantly for a long time, the line will sag, possibly into vegetation,
causing a short circuit, or anneal,. Since power is the algebraic product of
voltage and current, the same power at high voltages has a lower current,
and hence, has lower losses.

Power Factor = Active power/Apparent power = kW/kVA
= Active power/\ (Active Power
2
+Reactive Power
2
)
= kW/\ (kW
2
+kVAr
2
)
= Beer/(Beer +Foam)

N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 14 of 66 JAN-2012




The more foam (higher kVAr) indicates low power factor and vice versa.

3.1.6 The additional current flow associated with reactive power can cause
increased losses and excessive voltage sags. Transmission system operators
have to ensure that reactive reserves are available to handle system
contingencies such as the loss of a generator or transmission line because
increased current flow after the occurrence of contingencies can produce
greatly increased reactive power absorption in transmission lines.

3.1.7 The transmission lines generate VARS under No load or less loaded
conditions and consume VARS under loaded conditions. At any given point
of time the power system can experience different voltage levels at various
locations.

3.1.8 In general, under peak load conditions, voltages are high at reactive source
points and are low at load points and the direction of reactive power flow is
from source to the load, whereas, under the off peak conditions, the reactive
power flow is from load points to source.

3.1.9 The transmission of VARS over transmission elements during peak load
conditions further burdens the transmission elements and as a result, the
voltages at the load end become further less. Hence it is desirable to meet
the reactive power requirement locally and necessary planning of reactive
compensation to be carried out. Even at nominal frequency and satisfactory
voltage operating conditions, voltage collapse cannot be ruled out as voltage
is a local phenomenon.

3.1.10 System voltage levels are directly related to the availability of reactive
power. System events, such as the loss of a transmission line, create an
instantaneous change in the reactive power demand. Shunt capacitors are
not able to switch fast enough to supply the increase in demand and prevent
further voltage decline. Therefore, generators must have some capability to
immediately respond to system events by providing additional reactive
power to the system.

N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 15 of 66 JAN-2012


3.1.11 Contrary to the active power balance, which has to be affected by means of
the generators alone, a proper reactive power balance can and often has to
be effected both by the generators and by dispersed special reactive devices,
producing or absorbing reactive power. The reactive power sources are
classified into two types, static and dynamic. The static type consists of
shunt capacitor, and shunt reactor. The dynamic type is the source of
reactive power produced by generators, SVC, and OLTC.


Sources (Q- Generation) Sinks (Q Absorption)

Static:
Shunt capacitors
Transmission Lines - charging
Under ground cables
Filter banks
- Loads -Capacitive
Dynamic:
Gen. Over excited
Synchronous condensers
Static Thyristor based devices
(SVC)

Loads
Induction motors (pumps,
fans etc)
Inductive loads (chokes etc)
Transformers
Transmission lines
Static Thyristor based devices
(SVC)
Reactors
Synchronous machines


Table 1- Sources and Sinks of Reactive Power

3.1.12 Static: Capacitors and inductors (or reactors) supply and consume static
reactive power, respectively. These are called static devices since they have
no active control of the reactive power output in response to the system
voltage. They cannot quickly change their reactive output level with
respect to system change.

Dynamic: Synchronous generators, synchronous condensers, Flexible AC
Transmission Systems (FACTS) including static var compensators (SVC),
static compensators (STATCOM), Dynamic Var (D-var) and Super VAR are
considered as dynamic reactive power devices capable of changing their
output according to pre-set limits in response to the changing system
voltages. Under normal operating conditions, dynamic reactive power
supplies should operate with substantial reactive power reserves in order to
quickly provide reactive support to the system during power system
disturbances. Various sources and sinks of reactive power are given in
table 1.
N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 16 of 66 JAN-2012








3.1.13 The reactive power capability from static sources is less valuable than from
dynamic sources, because dynamic sources can adjust their production or
consumption of reactive power much more quickly as needed to maintain
voltage and prevent a voltage collapse.
N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 17 of 66 JAN-2012


3.1.14 RLDC shall have database containing information on reactive power sources
in the responsible control area. The information consists of:
Reactive capability curves of generators;
Synchronous condensers;
Static VAR compensators;
Shunt reactor and shunt capacitors;
HVDC Operation in Reactive power control.
Transformer Tap changer settings;
SVC & FACTS details
Static synchronous compensator (STATCOM)
Other reactive power sources such as transmission lines.
3.1.15 RLDCs shall know current MVAR values, maximum and minimum MVAR
absorption/injection capabilities, and operating restriction (if applicable) of
each equipment so that the levels of reserve reactive power are accurate for
all time. Information concerning equipment, which can significantly affect
neighboring power systems, shall be available for each other.

3.2 DIFFERENT TYPE OF LOADS AND ITS REACTIVE POWER
CONSUMPTION

3.2.1 A great many loads consume not only active but also reactive power. The
Industry wise power factor is generally observed to be as follows:

INDUSTRY POWER FACTOR
Textiles 0.65/0.75
Chemical 0.75/0.85
Machine shop 0.4 / 0.65
Arc Welding 0.35/ 0.4
Arc Furnaces 0.7 / 0.9
Coreless induction furnaces and heaters 0.15/0.4
Cement plants 0.78/0.8
Garment factories 0.35/0.6
Breweries 0.75/0.8
Steel Plants 0.6 / 0.85
Collieries 0.65/0.85
Brick Works 0.6 / 0.75
Cold Storage 0.7 / 0.8
Foundries 0.5 / 0.7
Plastic moulding plants 0.6 / 0.75
Printing 0.55/0.7
Quarries 0.5 / 0.7
Rolling Mills (i.e. ,Paper, Steel , etc.) 0.3 / 0.75
N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 18 of 66 JAN-2012



3.2.2 Some typical values of reactive power consumption of individual loads are
given below:
- Induction motors 0.5 to 1.1 Kvar/KW, at rated output.
- Uncontrolled rectifiers 0.3 Kvar/KW.
- Controlled rectifiers usually consume much more Kvar/KW than
uncontrolled ones and with dependence on the rectifier delay angle.
- Arc furnaces around 1 Kvar/KW.

3.2.3 Both controlled rectifiers and arc furnaces of steel mills have a reactive
power consumption characterized by a high average value and fast
variations. Purely resistive loads, like filament lamps and electric heaters, do
not, of course, consume reactive power.

3.2.4 The synchronous motor is the only type of individual load, which can
produce reactive power. It consumes reactive power when under excited
and produces reactive power when overexcited. Synchronous motors are
usually operated overexcited and thus usually produce reactive power.

3.3 VOLTAGE MANAGEMENT

3.3.1 Control of voltage levels is accomplished by controlling the production,
absorption, and flow of reactive power at all levels in the system. Unlike
system frequency, which is consistent throughout an interconnected system
in the steady state, voltages experienced at points across the system
form a "voltage profile" which is uniquely related to local generation and
demand at that instant, and is also affected by the prevailing network
arrangements.

3.3.2 Controlling the voltage is a local problem. In other words, the voltage
3.3.2 control problems need to be solved separately by each control area. This
can be achieved by providing sufficient reactive power sources for
controlling voltage level as specified in IEGC. The voltage controlling
problems can be divided into two situations, which are normal situation
and emergency situation.

3.3.3 Voltage changes continuously according to the varying electrical demand,
transmission lines utilization etc. Reactive power (VAR) is required to
maintain the voltage to deliver active power (watts) through transmission
lines. When there is not enough reactive power, the voltage sags down and
it is not possible to push the power demanded by loads through the lines.

Excess of MVAr high voltage
Deficit of MVAr Low Voltage
MVAR balance Good voltage low system losses
N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 19 of 66 JAN-2012



3.3.4 Voltage control (keeping voltage within defined limits) in an electric power
system is important for proper operation of electric power equipment and
saving it from imminent damage from overheating, to reduce transmission
losses and to maintain the ability of the system to withstand disturbances
and prevent voltage collapse. In general terms, decreasing reactive power
causes voltages to fall, while increasing reactive power causes voltages to
rise.

3.3.5 Voltage stability
a) Voltage stability is the ability of the power system to maintain steady
acceptable voltages at all buses in the system under normal operating
conditions and after being subjected to disturbance. A system enters steady
voltage instability when a disturbance (An increase in load demand, or
change in system conditions) causes a progressive and uncontrolled drop in
voltage.

b) A system is voltage unstable, if for at least one bus in the system, the bus
voltage magnitude decreases as the reactive power injection in the same bus
is increased.

c) Voltage Instability is basically caused by non-availability of reactive power
support in some nodes of the network, where the voltage uncontrollably
falls. Lack of reactive power may essentially have two origins,
i. Gradual increase of power demand where the reactive requirement at
some buses cannot be met.
ii. Sudden change of network topology redirecting the power flows
in such a way that the reactive power cannot be delivered at some buses.

d) The increased load is always accompanied by a decrease of voltage except in
the case of a capacitive load. When the loading is further increased, the
maximum loadability point is reached, from which no additional power can
be transmitted under those conditions.
In case of constant power loads, the voltage in the nodes become
uncontrollable and rapidly decreases.

3.3.6 VOLTAGE COLLAPSE:

a) When voltages in an area are significantly low or blackout occurs due to the
cascading events accompanying voltage instability, the problem is
considered to be a voltage collapse phenomenon. Voltage collapse normally
takes place when a power system is heavily loaded and/or has limited
reactive power to support the load. The limiting factor could be the lack of
reactive power (SVC and generators hit limits) production or the inability to
transmit reactive power through the transmission lines.

N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 20 of 66 JAN-2012


b) The main limitation in the transmission lines is the loss of large amounts of
reactive power and also line outages, which limit the transfer capacity of
reactive power through the system.




c) In the early stages of analysis, voltage collapse was viewed as a static
problem but it is now considered to be a non linear dynamic phenomenon.
The dynamics in power systems involve the loads and voltage stability is
directly related to the loads. Hence, voltage stability is also referred to as
load stability.

3.3.7 PROCEDURES FOR CONTROLLING VOLTAGE AND REACTIVE
POWER:-

a) The control of voltage level is accomplished by controlling the production,
absorption and flow of reactive power at all levels in the system. (Refer
Table 1 for sources and sinks of reactive power.)

b) Primary Voltage Control: RLDCs shall control primary voltage by
providing specific voltage levels to generators according to the requirement.
The generators shall adjust the AVR which will vary the excitation of
generating units in order to achieve the specified voltage levels. For other
voltage control equipment such as SVCs or automatic tap changing
transformers, they are considered to be a part of primary voltage control. All
equipment that is used for the primary voltage control is considered to be
dynamic.

c) Secondary Voltage Control: The control centers shall employ voltage
control mechanism by managing static reactive power sources, both
N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 21 of 66 JAN-2012


absorption and injection, for examples, shunt reactors, capacitor bank, etc,
all of which are within the considered zones in cooperate with the first step
for voltage control in order to maintain specified voltage levels at essential
delivery points that represent the zones.

d) As defined in the IEGC Section 5.2(s), the operating range of the voltages at
various voltage levels of the grid are as follows:

Voltage (kV-rms)
Nominal Minimum Maximum
765 728 800
400 380 420
220 198 245
132 122 145
110 99 121
66 60 72
33 30 36

The maximum and minimum values in the above table are the outer limits
and all the regions shall endeavour to maintain the voltage level within the
above limits. The steady state voltage is maintained within the limits given
in above table. However, the step change in voltage may exceed the
above limits where simultaneous double circuit outage of 400 kV lines are
considered. In such cases, it may be necessary to supplement dynamic VAR
resources at sensitive nodes.

e) SLDC/RLDC may direct a wind farm to curtail its VAr drawal/Injection on
considering system security or safety of personnel/equipments.

f) The control centers shall apply the following mechanism for voltage control
in general.

i) Generating units of all the region shall keep their Automatic Voltage
Regulators (AVRs) in operation and power system stabilizers (PSS) in AVRs
shall be tuned in line with clause 5.2(k) of IEGC.

ii) The transformer tap positions on different 765kV, 400kV & 220kV class ICTs
& GTs shall be changed as per requirements in order to improve the grid
voltage.

iii) Disconnecting transmission lines:-This procedure shall be mainly used
during light load period, and it shall not reduce system security below N -1
criteria. For other periods, this procedure shall not be used.
iv) Adjusting synchronous condensers.
v) Opening or closing shunt reactors and capacitor banks.

N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 22 of 66 JAN-2012


g) Switching off of the lines in case of high voltage:-

i) In the event of persistent high voltage conditions when all other reactive
control measures as mentioned earlier including opening of redundant HT
lines within the state system by the concerned SLDCs have been exhausted,
selected 400 / 230 / 220 / 132 / 110 KV lines shall be opened for voltage
control measures.
ii) The opening of lines and reviving them back in such an event would be
carried out as per the instructions issued by RLDC/NLDC in real time and
as per the standing instructions issued from time to time. While taking such
action, RLDC/NLDC would duly consider that to the extent possible the
same does not result in affecting ISGS generation as well as the system
security & reliability is not affected.

h) VAR Exchange by regional constituents for Voltage and Reactive Control:

i. Each constituent shall provide for the supply of its reactive requirements
including appropriate reactive reserves, and its share of the reactive
requirements to support safe and secure power transfer on interconnecting
transmission circuits.
ii. The RLDC and constituent states shall take action in regard to VAR
exchange with the grid looking at the topology and voltage profile of the
exchange point. In general, the beneficiaries shall endeavour to minimize the
VAR drawl at interchange point when the voltage at that point is below the
nominal value and shall not inject VARs when the voltage is above the
nominal value. In fact, the beneficiaries are expected to provide local VAR
compensation so that they do not draw any VARs from the grid during low
voltage conditions and do not inject any VARs to the grid during high
voltage conditions.


i) VAR generation / absorption by generating units: - In order to improve the
overall voltage profile, the generators shall run in a manner so as to have
counter balancing action corresponding to low/high backbone grid voltage
and to bring it towards the nominal value. In order to achieve the same, all
generators shall generate reactive power during low voltage conditions and
absorb reactive power during high voltage conditions as per the capability
limit of the respecting generating units.

j) Load Management for controlling the Voltage:- All the regions shall
identify the radial feeders in their areas in consultation with SLDCs which
have significant reactive drawls and which can be disconnected in order to
improve the voltage conditions in the event of voltage dropping to low
levels. The details of all such feeders shall be kept ready in the respective
control rooms of RLDC/SLDC and standing instruction would be given to
N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 23 of 66 JAN-2012


the operating personnel to ensure the relief in the hour of crisis by
disconnecting such feeders.

k) Following corrective measures shall be taken in the event of voltage going
high / low:-

1. In the event of high voltage (when the bus voltage going above 410 kV),
following specific steps would be taken by the respective grid
substation/generating station at their own, unless specifically mentioned by
NLDC/RLDC/SLDCs.

i) The bus reactor be switched in
ii) The manually switchable capacitor banks be taken out
iii) The switchable line/tertiary reactors are taken in.
iv) Optimize the filter banks at HVDC terminal
v) All the generating units on bar shall absorb reactive power within the
capability curve.
vi) Operate synchronous condensers wherever available for VAR absorption.
vii) Operate hydro generator / gas turbine as synchronous condenser for VAR
absorption wherever such facilities are available.
viii) Bring down power flow on HVDC terminals so that loading on parallel
EHV network goes up resulting in drop in voltage.
ix) Open lightly loaded lines in consultation with RLDC/SLDC for ensuring
security of the balanced network.

2. In the event of low voltage (when the bus voltage going down below
390kV), following specific steps would be taken by the respective grid
substation/generating station at their own, unless specifically mentioned by
NLDC/RLDC/SLDCs.

i) Close the lines which were opened to control high voltage in consultation
with RLDC/SLDC.
ii) The bus reactor be switched out
iii) The manually switchable capacitor banks are switched in.
iv) The switchable line/tertiary reactor are taken out
v) Optimize the filter banks at HVDC terminal.
vi) All the generating units on bar shall generate reactive power within
capability curve.
vii) Operate synchronous condenser for VAR generation.
viii) Operate hydro generator / gas turbine as synchronous condenser for VAR
generation wherever such facilities are available.
ix) Increase power flow on HVDC terminals so that loading on parallel EHV
network goes down resulting in rise in voltage.



N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 24 of 66 JAN-2012


l) SYSTEM FREQUENCY & VOLTAGE CONTROL:-

i) This option is rarely used say for example when two islands has to be
synchronized and voltage has to be controlled at the end where line has to
be synchronized.

ii) Voltage of the large interconnected grid can also be controlled by controlling
the system frequency. As per Modern Power Station Practice, System
Operation Volume-I (2), the general synchronous machine equations shows
that voltage levels are directly proportional to frequency and for good
voltage control extremes of system frequency must be avoided.
E=4.44f N. Where: E is the EMF Generated; f is the Frequency, the flux.

iii) Times of low frequency are usually associated with plant shortage. The
reactive capability is low as the units are running at rated MW capacity; any
increase in reactive power would only be at the cost of reduction in MW
output, something that is not usually allowed as per the Indian Electricity
Grid Code section 6.6 Para 6.

m) Adverse weather conditions and voltage control
As per Modern Power Station Practice, System Operation Volume-L [2], Fog
or other conditions of high humidity give an increased risk of insulation
flashover which can be minimised by reducing voltage levels. However
under critically loaded conditions, it is judged that the risk of running with
reduced voltage levels outweighs the risk of tripping and the technique of
lowering the voltage shall not be used.




















N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 25 of 66 JAN-2012


4.Transmission lines and reactive power compensation

4.1 INTRODUCTION

4.1.1 Transmission lines are characterized by a series resistance, inductance, and
shunt capacitance per unit length. These values determine the power-
carrying capacity of the transmission line and the voltage drop across it at
full load. AC resistance of a conductor is always higher than its DC
resistance due to the skin effect forcing more current flow near the outer
surface of the conductor.

4.1.2 In moving power from generators to loads, the transmission network
introduces both real and reactive losses. Housekeeping loads at substations
(such as security lighting and space conditioning) and transformer
excitation losses are roughly constant (i.e., independent of the power flows
on the transmission system). Transmission-line losses, on the other hand,
depend strongly on the amount of power being transmitted.

4.1.3 The series inductive reactance of a transmission line depends on both the
inductance of the line and the frequency of the power system.

4.1.4 Transmission lines are characterized by their distributed parameters:
distributed resistance, inductance, and capacitance. The distributed series
and shunt elements of the transmission line make it harder to model. Such
parameters may be approximated by many small discrete resistors,
capacitors, and inductors.

Transmission line model

4.1.5 The consumption of reactive power by transmission line increases with the
square of current i.e., the transmission of reactive power requires an
additional demand for reactive power in the system components.

4.1.6 Thus, when it is critically needed during large power transfers, reactive
power is the most difficult to transport. In order to obtain an acceptable
voltage level, reactive power generation and consumption have to be
situated as close to each other as possible to avoid excessive transmission.

4.1.7 When reactive losses are negative, the line is supplying reactive power;
when they are positive, it is consuming reactive power.
N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 26 of 66 JAN-2012



4.2 SURGE IMPEDANCE LOADING (SIL)

4.2.1 Transmission lines and cables generate and consume reactive power at the
same time. The transmission lines have both capacitive and inductive
properties. The reactive power generation is almost constant, because the
capacitance of the line is usually constant, and the lines reactive power
consumption depends on the current or load connected to the line that is
variable. So at the heavy load conditions transmission lines consume
reactive power, decreasing the line voltage, and in the low load conditions
generate reactive power, increasing line voltage.

4.2.2 The case when lines reactive power produced by the line capacitance is
equal to the reactive power consumed by the line inductance is called
natural loading or Surge Impedance Loading (SIL) meaning that the line
provides exactly the amount of MVAr needed to support its voltage. The
balance point at which the inductive and capacitive effects cancel each other
is typically about 40% of the lines thermal capacity. Lines loaded above SIL
consume reactive power, while lines loaded below SIL supply reactive
power.

4.2.3 Impedance which is connected to the line at the Surge Impedance loading is
called Characteristic Impedance (Surge Impedance) (Zc) and is equal to
=sqrt (X/B) where X is the reactance and B is the susceptance of the
transmission line in per unit. Defining in terms of inductance (L) and
capacitance (C), Surge impedance (SI) would be equal to sqrt (L/C).

4.2.4 The amount of reactive power consumed by a line is related to the current
flowing on the line or the voltage drop along the line. The amount of
reactive power supplied by a line is related to the line voltage. An ideal line
with zero resistance (zero real losses) that is loaded at its surge impedance
loading will have the same voltage at both ends because it is not supplying
or consuming reactive power.

4.2.5 The surge impedance loading of a 400 kV twin Moose uncompensated line
would be 517 MW as shown in below example 4.1.
Example-4.1
For a twin Moose 400 kV line the SIL can be worked out as follows:-

Susceptance of 400kV Twin Moose per Km=3.46874E-06 Mho
Converting to per unit B in pu is
= 3.46874E-06*400*400/100
= 0.00554998
Reactance(X) of a 400kV Twin Moose per Km = 0.332 Ohms.
Converting to per unit X in pu is
= 0.332*100/(400*400)
N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 27 of 66 JAN-2012


= 0.0002075
Zc =Sqrt (X/B) = 0.19335

SIL in MW = 100/ Zc= 517.17 MW
4.2.6 A 400 kV, line generates approximately 55 MVAR per 100 km/Ckt, when it
is idle charged due to line charging susceptance. This implies a 300 km
line generates about 165 MVAR when it is idle charged.

4.3 SIL FOR DIFFERENT CONDUCTORS AND VOLTAGES



N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 28 of 66 JAN-2012


4.4 LINE LOADING AS FUNCTION OF LENGTH AND COMPENSATION
& ST. CLAIRES CURVE

4.4.1 The SIL is usually much lower than the thermal rating. Below 69 kV the line
charging is usually negligible while it is a significant source of reactive
power for long lines of higher system voltages. The maximum permissible
line loadings derived from St. Clairs curve. SIL given in table above is for
uncompensated line. Further in order to take into account the compensation,
SIL has to be recalculated. After that, the modified SIL has to be multiplied
by the factor derived from St. Clair's curve.

4.4.2 Compensation using a Shunt Reactor
If k is the compensation then:
In case of compensation (Shunt reactors and series capacitors) the SIL of
the line changes. Shunt reactors cause the SIL to decrease by a factor of
.(1-k), where k is the degree of compensation defined as (S+R)/C
Where
S is sending end reactor converted to 400 kV (MVAR)
R is receiving end reactor converted to 400 kV (MVAR)
C is the charging MVAR of the line (MVAR)
Hence SILmodified= SILuncomp * (1-k)
4.4.3 Compensation using a Series Capacitor
Series capacitor causes the SIL to increase by a factor divisible by. (1-
k) where k is degree of compensation.
Hence SILmodified = SILuncomp / (1-k)
Finally the derived steady state limit for a line would be
= SIL modified x factor from St. Clair's curve

From the example 4.1, the SIL calculated for 400 kV twin Moose
uncompensated line without considering the length is 517MW.

In the below example 4.2, the SIL of 400kV twin moose has been calculated
by considering length and shunt reactive compensation.

4.4.4 Example-4.2
Let us now consider a 300 KM, Twin Moose Conductor, 400 kV S/C line
with 50 MVAR Reactor at both ends. The Reactors are rated for 420 kV and
hence have to be converted to 400 kV
Reac(NEW) = Reac(old) X (400^2)/ (420^2)= 45.35 MVAR
The Charging MVAR for a 300 kM long line is 165 MVAR (at 55MVAR per
100 KMS)
In case of Shunt Compensated lines, the degree of compensation (k) is the
sum of Reactors at both ends divided by line charging MVAR, which
is equal to (45.35+45.35)/165 = 0.55
N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 29 of 66 JAN-2012



The new Steady State Limit would then be
=517 MW * (1-k)* St Claire Curve Point
=517 MW * (1-k)* 1.3
where k= 0.55 and 517 MW is the SIL without compensation & 1.3 is the St
Claires Curve point corresponding to 300 Kms as shown in the figure
below.
= 347 MW * 1.3
= 451 MW



ST. CLAIRES CURVE


4.5 SHUNT REACTORS AND REACTIVE POWER CONTROL

4.5.1 Electric transmission lines have both capacitive and inductive properties.
Shunt reactors are used to compensate for the effects of line capacitance,
particularly to limit voltage rise on open circuit or light load and switching
operations. They are usually required for EHV overhead lines longer
than 200 km. A shorter overhead line may also require shunt reactors if the
line is supplied from a weak system (Low short circuit Capacity).

4.5.2 The use of shunt reactive devices. i.e. shunt compensation, is a
straightforward reactive-power compensation method. The shunt reactors
are sized in such a way that under steady state condition, switching on and
off of the reactors shall not cause a voltage change exceeding 5 %.

4.5.3 In the event of persistent low voltage conditions, some of the line reactors
are to be selected on the basis of line length, grid conditions, network
N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 30 of 66 JAN-2012


topology etc. by each region which can be switched off in order to improve
the system voltage profile. The switching off of such line reactors and
reviving them back would be carried out as per the instructions issued by
RLDCs/SLDCs.

4.5.4 The standard sizes of the reactors are



4.5.5 A shunt Reactor of sufficient size must be permanently connected to the line
to limit fundamental-frequency temporary over voltage to about 1.5 pu for a
duration of less than 1 second. Such line connected reactors also serve to
limit energization over voltage (switching transients). Additional shunt
reactors (i.e. Bus Reactors) may be connected to the EHV bus or to the
tertiary windings of adjacent transformers to maintain normal voltage under
light-load conditions. During heavy loading conditions when system
voltage is low, some of the line/bus reactors (those are switchable i.e.
provided with circuit breaker) may have to be disconnected.

4.5.6 Shunt reactors are similar in construction to transformers, but have a single
winding (per phase) on an iron core with air gaps and immersed in oil. They
may be either single phase or three phase construction. Normally there are
two types of shunt reactors Line reactor and bus reactor. Line reactors
functionality is to avoid the switching and load rejection over voltages
where as Bus reactors are used to avoid the steady state over voltage during
light load conditions.

4.5.7 They can be either permanently connected to the system or switchable one.
Use of shunt rectors at normal operating condition may reduce system
voltage and increase losses. Hence switchable reactors are better choice since
they can be switched off whenever it is not required.

4.5.8 The degree of compensation being decided by an economic point of view
between the capitalized cost of compensator and the capitalized cost of
reactive power from supply system over a period of time. In practice a
compensator such as a bank of capacitors (or inductors) can be divided into
parallel sections, each switched separately, so that discrete changes in the
compensating reactive power may be made, according to the requirements
of the load.




kV Level Size in MVAr 3-Phase/1 Phase
400 kV 50,63,80,93, 125 3-Phase Units
765 50,63,80,110 1-Phase units
N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 31 of 66 JAN-2012


4.5.9 Voltage change at bus due to removal / addition of reactor :-
The approximate percentage voltage rise/fall of a bus due to
removal/addition of a reactor of capacity Q MVAR is as follows:
= Q*100 / Fault MVA of the Bus
For example removing a 80 MVAR bus reactor at a bus of 5000 MVA SC
level would cause the voltage to rise by 1.6% i.e. 400*1.6/100 =6.4 KV

4.5.10 List of inter regional lines ( 400kV and above) with reactor details is given in
Annexure 1.

4.5.11 In Annexure 2, the details about total reactive compensation available
through bus reactors and line reactors at all India Level are explained.

4.5.12 Selection of lightly loaded lines for voltage control:- When a particular
line is opened, the MVAR relief available for that line opening is estimated
for all the 400kV and above transmission lines for all the region.

In addition to that, if the line has the provision for using line reactor as bus
reactor by manually or through switching arrangements, then the MVAR
relief available for those lines also calculated. This is explained in
Annexure 3.

4.5.13 400kV & 765kV Reactors installed capacity at all India level is attached as
Annexure 4.

4.5.14 Fault level in substation:- Fault level of substation besides giving an idea
about the maximum breaking current possible of that substation, it also
gives an idea about sensitivity of bus voltage to the reactive power injection
or drawl. Fault level of 400kV & above Buses is attached as Annexure 5.

4.5.15 Surge Impedance Loading of the transmission lines is given in
Annexure 6.

4.5.16 List of 765kV lines to be commissioned during 2012 is given in Annexure 7.













N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 32 of 66 JAN-2012



5. Series and shunt capacitorstheir effect on reactive power

5.1 SHUNT CAPACITORS

5.1.1 There has been a phenomenal growth in the use of shunt capacitors as a
means of local provisions of reactive power, particularly within
distribution systems. Shunt capacitors supply reactive power and boost
local voltages thereby enhancing the system capacity and reducing the
losses.

5.1.2 The presence of these in distribution system reduces the transfer of reactive
power from EHV system, thereby contributes to efficiency of power
transmission & distribution.

5.1.3 They are used throughout the system and are applied in a wide range of
sizes. Shunt capacitors are used to compensate for the I
2
X losses in
transmission system and to ensure satisfactory voltage levels during
heavy loading conditions.

5.1.4 The advantages of shunt capacitors are their low cost compared to SVCs
and their flexibility of installation and operation.

5.1.5 The principal disadvantage of shunt capacitors is that their reactive power
output is proportional to the square of the voltage. The reactive power
output is reduced at low voltages when it is likely to be needed most. As
the voltage falls the reactive power supplied by the capacitors decreases
according to the square of the voltage, causing voltage to fall further.

5.1.6 Precise and speedy control of voltage is not possible as capacitor banks are
discrete devices, but they are often configured with several steps to provide
a limited amount of variable control.

5.1.7 Objective of shunt capacitor units are :
Increase voltage level at the load
Improves voltage regulation if the capacitor units are properly switched.
Reduces I
2
R power loss in the system because of reduction in current.
Increases power factor of the source generator.
Decrease kVA loading on the source generators and circuits to relieve an
overloaded condition or release capacity for additional load growth.
By reducing kVA loading on the source generators additional kilowatt
loading may be placed on the generation if turbine capacity is available.

N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 33 of 66 JAN-2012


5.1.8 Capacitor Banks are sets of capacitors which are connected to the system
through mechanical switches of circuit breakers and their real power losses
are very small. The capacitors in a bank are switched in blocks. Switching of
capacitor banks provides a convenient means of controlling transmission
system voltages. Switched capacitors cannot smoothly adjust their reactive
power output because they rely on mechanical switches and take several
cycles (less than one second) to operate.

5.1.9 When capacitors are switched out, they must be discharged before
reconnection, normally with discharge time ranging from two to fifteen
minutes. In some special applications, capacitor banks are equipped with
fast discharge reactors. Hence switching speeds can be quite fast with
current limiting reactors to minimize switching transients that will
discharge the capacitors in about 120 milliseconds(ms) thus enabling them
to be reconnected to provide voltage support to the power system.

5.1.10 Capacitor banks at the distribution level are often not switched off at high
voltages as the operators are reluctant to interrupt capacitive currents
(perceived maintenance issues) or the high voltages in the super-grid have
not percolated to the distribution level due to sub-optimal taps. Though
switching off the capacitors is more of a pre-emptive and administrative
issue rather than a real time undertaking, a judicious action in the matter
can certainly alleviate the problem of high voltage.

5.2 SERIES CAPACITORS

5.2.1 In series capacitors the reactive power is proportional to the square of the
load current, thus generating reactive power when it is most needed
whereas in shunt capacitors it is proportional to the square of the
voltage.
S
5.2.2 OBJECTIVES OF SERIES COMPENSATION
Reduction in line voltage drop Although the line voltage drop is
reduced during high load periods the voltage at the receiving end will
rise during light load periods.
Effect on the load flow in parallel lines As the impedance of the
compensated line is reduced, loading of parallel lines is reduced.
Increase of transmission capability The compensated line can be
loaded closer to its thermal limit. Increase of stability margin For the
same power flow, the angular separation of the bus voltages across the
compensated line will be less.

5.2.3 The reactive power produced by a series capacitor increases with increasing
power transfer. Series capacitors are normally installed in 220kV and above
systems. They reduce net transmission line inductive reactance.

N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 34 of 66 JAN-2012


5.2.4 Series capacitors are connected in series with the line conductors to
compensate for the inductive reactance of the line. Series capacitors
compensation is usually applied for long transmission lines and transient
stability improvement. The reactive generation I
2
X
C
compensates for the
reactive consumption I
2
X
L
of the transmission line. This is a self-regulating
nature of series capacitors. But at light loads series capacitors have little
effect.

5.2.5 There are certain unfavorable aspects of series capacitors. Generally the cost
of installing series capacitors is higher than that of a corresponding
installation of a shunt capacitor. This is because the protective equipment
for a series capacitor is often more complicated.

5.2.6 Typical degrees of compensation vary from 30% to 70% of the line
impedance. Values below 30% do not contribute substantially to any
improvement. Values beyond 70% endanger the stability of the network.

5.2.7 Subsynchronous resonance (SSR):- Subsynchronous resonance (SSR) is a
dynamic phenomenon of interest in power systems that have certain special
characteristics. The formal definition of SSR provided by the IEEE is
Subsynchronous resonance is an electric power system condition where the
electric network exchanges energy with a turbine generator at one or more
of the natural frequencies of the combined system below the synchronous
frequency of the system.
The definition includes any system condition that provides the opportunity
for an exchange of energy at a given subsynchronous frequency.
This includes what might be considered "natural" modes of oscillation that
are due to the inherent system characteristics, as well as "forced" modes of
oscillation that are driven by a particular device or control system. The most
common example of the natural mode of subsynchronous oscillation is due
to networks that include series capacitor compensated transmission lines.


5.2.8 Comparison between shunt and series compensation is shown in the below
table.
S.
N
Shunt compensation Series compensation
1. The shunt unit is connected in
parallel across full line voltage. The
current through the shunt capacitor is
nearly constant as the supply
terminal voltage and its reactance are
constant.
The series unit is connected in series in
the circuit and therefore conducts full
current
2. The voltage across the shunt
capacitor is substantially constant as
The voltage across the series capacitor
changes instantaneously as it depends on
N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 35 of 66 JAN-2012


S.
N
Shunt compensation Series compensation
it is equal to the system voltage and
generally within certain limits of say
0.9 to 1.1 pu.
the load current through it, which varies
from 0 to ILmax
3. The power developed across the
shunt capacitor is
Csh KVAR =
Csh cSH
x
v
v
x
v
2
. =
|
|
.
|

\
|

The power developed across the series
capacitor is
Cse KVAR = (IL XCse) (IL)= I
L
2
XCse
4. The shunt capacitor supplies lagging
reactive power to the system. Hence
directly compensating the lagging
KVAR load. It improves the load
power factor substantially. Hence its
main purpose is to compensate the
load Power factor
The series capacitor reduces the line
reactance as it introduces leading
reactance in series of the line. Thus series
capacitor at rated frequency Compensates
for the drop, through inductive reactance
of the feeder. Hence it is used to increase
the line transmission capacity.
5. The size and capacity of shunt
capacitor is generally higher for the
same voltage regulation
The size and capacity of a series capacitor
is relatively lesser for the same voltage
regulation
6. Not suitable for transient voltage
drops caused by say, frequent motor
starting, electric welding etc.
The voltage regulation due to series
capacitor is proportional to the IL2 hence
it meets the requirements of transient
voltage changes
7. Performance is dependent on
terminal voltage. Hence not effective
in fluctuating voltage conditions.
The performance does not depend on the
system voltage variations. But depends
on system load current. Hence gives full
output under low voltage and heavily
loaded conditions
8. The shunt capacitor need not be on
the source side. But closer to the load
point
The series capacitor should always be on
the source side of the load.
9. The rating is based on
KVARCsh = KW(Tan|1 - Tan|2)
where |1 is the power factor angle
before correction, |2 is the pf angle
after correction
The rating is based on percentage
compensation of the line reactance.
Generally XCse = 0.3 to 0.4 of Xline Ex:
A 220KV, 0.4O/km, 100km line, 40%, XL
= 0.4 X 100 = 40O, Xcse = 0.4 x
40 = 16O = 1/2tfCse Cse =
F F
x
x
200
16 314
10 1
6
~

10. The Ferranti effect is aggravated by
shunt compensation
The Ferranti effect is reduced by the
series capacitor
N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 36 of 66 JAN-2012


S.
N
Shunt compensation Series compensation
11. Power transferred through a line
P=
o Sin
X
V V
r s

with shunt capacitor, Vr increases
P increases
With Cse, Vr increases and X decreases
hence P increases much more.
12. The shunt compensation does not
require special protection
arrangements as the terminal voltage
of the capacitor bank falls under fault
conditions
The voltage across series capacitor
abnormally rises due to flow of fault
current through it. Hence it requires
special protection schemes.

5.2.9 Shunt capacitors installed capacity at all India level is attached as
Annexure 8.
5.2.10 List of Series Compensation schemes at all India level is attached as
Annexure 9.




























N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 37 of 66 JAN-2012



6.Transformer tap changer effect on reactive power

6.1 In line with IEGC clause 6.6.5 & 6.6.4, the transformer tap positions on
different 765kV, 400kV & 220kV class ICTs & GTs shall be changed as per
requirements in order to improve the grid voltage. RLDCs shall coordinate
and advise the settings of different tap position and any change in their
positions shall be carried out after consultation with RLDC. Normally tap
position of all the ICTs shall be reviewed/changed at every three month
interval.

6.2 Transformers with tap-changing facilities constitute an important means of
controlling voltage throughout the system at all voltage levels. Coordinated
control of the tap changers of all the transformers interconnecting the
subsystems is required if the general level of voltage is to be changed.

6.3 The OLTC allows voltage regulation and/or phase shifting by varying the
turns ratio under load without interruption. Large power transformers are
generally equipped with voltage tap changers, sometimes called taps
with tap settings to control the voltages either on the primary or secondary
sides of the transformer by changing the amount and direction of reactive
power flow through the transformers. Transformer taps can be controlled
automatically based on local system conditions or manually.

6.4 Generating Transformer: - Power generated at generating station (usually
at the range of 11kV to 25kV) is stepped up by generating transformer to the
voltage level of 220, 400, 765kV for transmission. It is one of the important
and most critical components of power system. They are generally provided
with off circuit tap changer with a small variation in voltage because the
voltage can always be controlled by the field of generator. Generating
Transformer with OLTC also used for reactive power control.

6.5 Interconnecting Transformer: - Normally autotransformers are used to
interconnect two grid/systems operating at two different voltage levels (400
and 220kV). They are normally located between generating transformer and
receiving end transformer. In autotransformer there is no electrical
isolation between primary and secondary. Some volt-amperes are
conductively transformed and some are inductively transformed.
Synchronous condenser or shunt reactors are connected to the tertiary for
reactive compensation if required. Normally 400/220kV ICTs having the
following tap setting:

- 1 to 17 taps and 5 kV per tap
N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 38 of 66 JAN-2012


- 10% range
Nominal tap at 9

6.6 The OLTC alters the power transformer turns ratio in a number of pre
defined steps and in that way changes the secondary side voltage.
Transformer-tap changers can be used for voltage control, but the control
differs from that provided by reactive sources. Transformer taps can force
voltage up (or down) on one side of a transformer, but it is at the expense of
reducing (or raising) the voltage on the other side. Tap changers do not
consume or supply reactive power.

6.7 To increase reactive power output and raise system voltage levels at the
substation to which the generator is connected, the generator transformer
(GT) is tapped (usually off load) in a direction to increase its transformation
ratio. This will depress the stator volts which are immediately restored by
the AVR increasing the machine excitation.

6.8 Typically a 500 MW generator transformer will have 15 taps and a no load
voltage regulation of +2% to 16%, the asymmetry reflecting the higher
MVAr generation (as opposed to absorption) capability. Tap 1 is usually the
position of highest transformation ratio and MVAr output, and tap 15 the
position of lowest ratio and maximum MVAr absorption.

6.9 The taps of all the plants directly connected to 400 kV or 200 kV level
networks in an area are simultaneously changed. The theory behind this is
that when generating stations are acting independently to control their local
substation voltages, an individual station reaching its reactive generation
limit may tap to reduce its reactive output. Such action will be at the
expenses of neighboring stations and net effect is to reduce system voltage
levels and increase the total reactive generation required by reason of higher
circuit reactive losses.

6.10 Coordinated action instead by all stations to tap in a direction to increase the
system voltage level will reduce the network reactive demand (lower I
2
X,
increase B
2
V) and move all generators away from their lagging reactive
limits. Thus simultaneous tap changing avoids a situation whereby MVArs
produced at one station are negatively compensated at others.

6.11 The reactive power consumption of a transformer at rated current is within
the range 0.05 to 0.2 p.u. based on the transformer ratings. Fixed taps are
useful when compensating for load growth and other long term shifts in
system use. LTCs are used for more-rapid adjustments, such as
compensating for the voltage fluctuations associated with the daily load
cycle. While LTCs could potentially provide rapid voltage control, their
performance is normally intentionally degraded. With an LTC, tap changing
N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 39 of 66 JAN-2012


is accomplished by opening and closing contacts within the transformers
tap changing mechanism.


6.12 The ICTs TAP position details at all India level is given in Annexure 10.

6.13 Typical Transformer Tap changer both online/offline is given in
Annexure 11.

6.14 The below fig illustrates possible the transformer tap operating zones which
gives best results.




















N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 40 of 66 JAN-2012


7. HVDC operation effect on reactive power
7.1 For transferring power over a long distance, High voltage DC transmission
lines (HVDC) are preferred. They normally consist of two converter
terminals connected by a DC transmission line and in some applications,
multi-terminal HVDC with interconnected DC transmission lines. Back-to-
Back DC and Voltage Source Converter based (VSC) HVDC are specific
types of HVDC systems. VSC based HVDC system uses new cable and
converter technologies and is economical at lower power levels than
traditional HVDC.

7.2 Back-to-Back HVDC is used for asynchronous connection of two AC
systems with different system characteristics (for example between N-E-
W grid AND Southern Grid in India at Gazuwaka and Bhadrawati) or
within an AC system for AC power flow regulation on the parallel AC
network (for example at Vindhyachal and Pusauli in N-E-W grid).

7.3 The converter terminals consist of thyristor based converters, converter
transformers, filters and capacitors all of which facilitate conversion from
power from AC to DC and vice versa. In addition to voltage conversion, the
converters are capable of controlling the amount of power flows and
direction over the DC transmission line.

7.4 Because DC transmission lines are transmitting power at zero hertz, the
reactive power consumption on the line is zero. The converters require
reactive power for the conversion process typically in the range of 40% of
the power rating of each of the converter terminals. Therefore, for a 1000
MW HVDC transmission, 400 MVAR is typically required at each terminal.

7.5 The reactive power is required to compensate for the reactive power
consumption in the converter transformers and to maintain an acceptable
AC voltage level on the AC side of the converter terminals. Much of this
reactive power requirement is provided by shunt capacitors and filters,
which are required to filter out or reduce the harmonic currents resulting
from AC waveform chopping in the AC-DC conversion processes.

7.6 Therefore, a properly designed HVDC system is essentially self-sufficient in
reactive power. Due to its inherently fast electronic control, it is also capable
of supporting the AC terminal voltages by controlling the DC power flow
over the line and consequently the reactive power consumption in the
converter transformers.

7.7 It may be further noted that while the reactive power generated by the
switching of filters varies in steps, the reactive power requirement by the
Converter transformer varies continuously (not in steps) with the power
N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 41 of 66 JAN-2012


level. Hence while selecting and/or varying the power level, corresponding
to each point there may be an excess/deficit reactive power at the HVDC
station and the same would eventually get injected/ drawn to/from the
Grid causing voltage rise/drop. Depending upon whether voltage is
required to be increased or decreased, the set point may be decided
accordingly.

7.8 While deciding the quantum of diversion/wheeling, the different power
levels at which the filters get switched on/off may be kept in mind, so that
voltage can be maintained at desired level. For this purpose the
following two points are important in this regard:
Reactive Power generation at HVDC bipole stations at different Power
levels vis--vis MVAR requirement of the Converter transformer is to be
considered. Based on this , when a particular set point is required, the same
may be optimized to the nearest threshold value so that number of filters
that get switched on/off would control the Bus voltage at other end
substation to the desired level.

7.9 At any point of time filter banks at HVDC stations in service depends on
power flow magnitude and / or direction of power flow. Therefore, the
power order on HVDC bi-pole could be kept at appropriate level to bring in
or take a filter bank in services.

7.10 The table 7.1 shows the information about HVDC TALCHER/KOLAR bi-
pole filter details and reactive power generation.



Table 7.1 REACTIVE POWER GENERATION AT TALCHER/KOLAR
HVDC STATIONS AT DIFFERENT POWER LEVELS



N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 42 of 66 JAN-2012


7.11 VOLTAGE SOURCE CONVERTERS

7.11.1 Voltage source converters technology use high power self-turn off type
semiconductor devices such as IGBT. The use of IGBTs in VSC technology
eliminates the need of active commutation voltage and also allow for higher
switching frequencies which reduces the harmonic content. A higher
switching frequency reduces the filter requirement on AC side when
compared to conventional HVDC. Pulse width modulation is used for
switching of semiconductor devices in VSC based HVDC transmission.

7.11.2 VSC converters combined with an energy storage source permits
continuous and independent control of real and reactive power in power
transmission. Reactive power control can be used for dynamic voltage
regulation to support the interconnecting ac system following contingencies.
This capability can increase the overall transfer levels. Forced commutation
with VSC permits black start, i.e., the converter can be used to synthesize a
balanced set of three phase voltages much like a synchronous machine.

7.11.3 Some of the advantages of VSC based transmission are:
a) Independent control of reactive and active power
b) Reactive control independent of other terminal
c) Simpler interface with ac system
d) Compact filters
e) Provides continuous ac voltage regulation
f) No minimum power restriction
g) Operation in extremely weak systems
h) No commutation failures
i) No restriction on multiple infeeds
j) No polarity reversal needed to reverse power
k) Black-start capability
l) Variable frequency

7.12 Interaction between two neighbouring HVDC system:-

7.12.1 HVDC systems have traditionally been operated in relative electrical
isolation from each other. Two or more HVDC links operating electrically
close to each other is referred to as Multi-Infeed HVDC system. Multi-
infeed converters either share a common ac bus or connected to buses that
are electrically close. The operation of adjacent dc terminals poses serious
N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 43 of 66 JAN-2012


concerns for mutual interaction following a disturbance in either dc systems
or in the common AC system.

7.12.2 The main potential problems arising from Multi-Infeed HVDC systems
include small signal stability, commutation failure, voltage instability and
collapse. In order to cope with the possible adverse interactions, Co-
ordination between the HVDC controls is the most effective solution. Co-
ordination between controls includes equipping converters with voltage
stabilizing controls, using of adequate series and shunt reactive power
compensation devices at the critical AC transmission lines and also using
fast power flow controllers.

7.13 HVDC BIPOLE CONFIGURATION

7.13.1 In bipolar transmission a pair of conductors is used, each at a high potential
with respect to ground, in opposite polarity. Since these conductors must be
insulated for the full voltage, transmission line cost is higher than a
monopole with a return conductor. However, there are a number of
advantages to bipolar transmission which can make it the attractive option.

7.13.2 Under normal load, negligible earth-current flows, as in the case of mono
polar transmission with a metallic earth-return. This reduces earth return
loss and environmental effects. When a fault develops in a line, with earth
return electrodes installed at each end of the line, approximately half the
rated power can continue to flow using the earth as a return path, operating
in mono polar mode.

7.13.3 Since for a given total power rating each conductor of a bipolar line carries
only half the current of mono polar lines, the cost of the second
conductor is reduced compared to a mono polar line of the same rating. In
very adverse terrain, the second conductor may be carried on an
independent set of transmission towers, so that some power may continue
to be transmitted even if one line is damaged.

7.13.4 A bipolar system may also be installed with a metallic earth return
conductor as being envisaged for future HVDC projects such as Chamba-
Kurukshetra etc. This is considering the adverse effect of even small ground
currents on equipments such as pipelines etc.

7.13.5 The following bipole HVDC systems are in operation.

a) HVDC Rihand-Dadri bipole: Capacity 2 X 750 MW, +/- 500 kV DC, 815 km
b) HVDC Chandrapur-Padge bipole: Capacity 2X750MW, +/-500kV DC

c) HVDC Talcher - Kolar bipole: Capacity 2 X 1250 MW, +/- 500 kV DC,
1440 km
N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 44 of 66 JAN-2012


d) HVDC Balia-Bhiwadi bipole: Capacity 2X1000MW, +/-500kV DC, 790km

7.13.6 800 KV HVDC BI-POLE:- The first 800kV HVDC bi-pole line in INDIA has
been planned from pooling substation at Bishwanath Chariyali in North -
eastern Region to Agra in Northern region. This is being programmed for
commissioning matching with Subansiri Lower HEP in 2012-13. The
transmission line would be for 6000 MW capacity and HVDC terminal
capacity would be 3000 MW between Bishwanath Chariyali and Agra. In the
second phase, for transmission of power from hydro projects at Sikkim and
Bhutan pooled at Siliguri, another 3000 MW terminal modules would be
added between Siliguri and Agra. It is envisaged to take-up the proposed
800kV, 6000MW HVDC bi-pole line from Bishwanath Chariyali to Agra
under a scheme titled Inter-regional Transmission system for power
export from NER to NR/WR which is under execution.



7.14 HVDC BACK TO BACK CONFIGURATION:-

7.14.1 A back-to-back station (or B2B for short) is a plant in which both static
inverters and rectifiers are in the same area, usually in the same building.
The length of the direct current line is kept as short as possible.

7.14.2 HVDC back-to-back stations are used for Coupling of electricity mains of
different frequency (as in INDIA; the interconnection between NEW GRID
and SR GRID through 1000 MW HVDC BHADRAVATI and 1000 MW
HVDC GAZUWAKA). In the past, power systems in India were planned on
regional basis with asynchronous interconnection through HVDC back-to-
back for facilitating opportunity power transaction.


7.14.3 The DC voltage in the intermediate circuit can be selected freely at HVDC
back-to-back stations because of the short conductor length. The DC
voltage is as low as possible, in order to build a small valve hall and to
avoid series connections of valves. For this reason at HVDC back-to-back
stations valves with the highest available current rating are used.

7.14.4 A high voltage direct current (HVDC) link consists of a rectifier and an
inverter. The rectifier side of the HVDC link is equivalent to a load
consuming positive real and reactive power and the inverter side of the
HVDC link as a generator providing positive real power and negative
reactive power (i.e. absorbing positive reactive power).

7.14.5 Thyristor based HVDC converters always consume reactive power when
in operation. A DC line itself does not require reactive power and voltage
drop on the line is only the IR drop where I is the DC current. The
N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 45 of 66 JAN-2012


converters at the both ends of the line, however, draw reactive power
from the AC system. The reactive power consumption of the HVDC
converter/inverter is 50-60 % of the active power converted. It is
independent of the length of the line.

7.14.6 Both AC and DC harmonics are generated in HVDC converters. AC
harmonics are injected into the AC system and DC harmonics are injected
into the DC line. These harmonics have the following harmful effects:
Interference in communication system.
Extra power losses in machines and capacitors connected in the
system.
Some harmonics may produce resonance in AC circuits resulting in
over voltages.
Instability of converter controls.

7.14.7 Harmonics are normally minimized by using filters. The following types of
filters are used:
AC filters.
DC filters.
High frequency filters.

7.14.8 AC Filters:- AC filters are RLC circuits connected between phase and earth.
They offer low impedance to harmonic frequencies. Thus, AC harmonic
currents are passed to earth. Both tuned and damped filter arrangements are
used. The AC harmonic filters also provide reactive power required for
satisfactory operation of converters and also partly injects reactive power
into the system.

7.14.9 DC Filters :- DC filters are similar to AC filters. A DC filter is connected
between pole bus and neutral bus. It diverts DC harmonics to earth and
prevents them from entering DC lines. Such a filter does not supply reactive
power as DC line does not require reactive power.

7.14.10 HIGH FREQUENCY FILTERS:- HVDC converters may produce electrical
noise in the carrier frequency band from 20 Khz to 490 Khz. They also
generate radio interference noise in the mega hertz range of frequencies.
High frequency (PLC-RI) filters are used to minimize noise and interference
with PLCC. Such filters are connected between the converter transformer
and the station AC bus.


7.14.11 The following back to back HVDC systems are in operation.

a) HVDC back to back Vindhyachal: Between Northern Region and Western
Region: Capacity 2 X 250 MW
N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 46 of 66 JAN-2012


b) HVDC back to back Pusauli: Between Northern Region and Eastern Region:
Capacity 1 X 500 MW
c) HVDC back to back Gazuvakka: Between Eastern Region and Southern
Region: Capacity 2 X 500 MW
d) HVDC back to back Bhatravati: Between Western Region and Southern
Region: Capacity 2 X 500 MW






































N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 47 of 66 JAN-2012


8. FACTS & Reactive power control
8.1 INTRODUCTION

8.1.1 The demand of lower power losses, faster response to system parameter
change, and higher stability of system have stimulated the development
of the Flexible AC Transmission systems (FACTS). Based on the success
of research in power electronics switching devices and advanced control
technology, FACTS has become the technology of choice in voltage
control, reactive/active power flow control, transient and steady-state
stabilization that improves the operation and functionality of existing
power transmission and distribution system.

8.1.2 The achievement of these studies enlarge the efficiency of the existing
generator units, reduce the overall generation capacity and fuel
consumption, and minimize the operation cost. The power electronics
based switches in the functional blocks of FACTS can usually be operated
repeatedly and the switching time is a portion of a periodic cycle, which is
much shorter than the conventional mechanical switches.

8.1.3 The advances in semiconductors increases the switching frequency and
voltage-ampere ratings of the solid switches and facilitates the applications.
For example, the switching frequencies of Insulated Gate Bipolar Transistors
(IGBTs) are from 3 kHz to 10 kHz which is several hundred times the utility
frequency of power system (50~60Hz). Gate turnoff thyristors (GTOs) have a
switching frequency lower than 1 kHz, but the voltage and current rating
can reach 5-8 kV and 6 kA respectively.

8.2 STATIC VAR COMPENSATORS (SVC) :-

8.2.1 Static VAR compensators combine capacitors and inductors with fast
switching (sub cycle, such as <1/50 sec) timeframe capability. In this
voltage is regulated according to a slope (droop) characteristic.
8.2.2 Static Var Compensator is a shunt-connected static Var generator or
absorber whose output is adjusted to exchange capacitive or inductive
current so as to maintain or control specific parameters of the electrical
power system (typically bus voltage) . SVC is based on thyristors without
gate turn-off capability. The adjective static means that, unlike the
synchronous compensator, it has no moving primary part. Similar to
capacitors, the reactive output of an SVC varies according to the square of
the connected bus voltage.

8.2.3 The only SVC in EHV network in the country was constructed by ABB in
year 1992 at 400 kV Kanpur substation of Power Grid Corporation of India
Limited. In early nineties, the fault level at this critical station was low and
N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 48 of 66 JAN-2012


it was a major load center.

8.2.4 FUNCTIONS OF SVC:-
It helps the power system in the following ways :
Improve voltage regulation
- Dynamic Mvar Support to the system
Enhancing transmission line power carrying capacity
Improving Dynamic stability of the Integrated Grid
Damping power oscillation on the associated AC lines
Improves & Smoothen Voltage profile

8.3 OPERATING PRINCIPAL AND CHARACTERISTICS OF SVC:-

8.3.1 Two types of Thyristor-controlled elements are used in SVCs:
TSC Thyristor-switched capacitor
TCR Thyristor- controlled reactor
From a power-frequency point of view they can both be considered as a
variable reactance, capacitive or inductive, respectively.

8.3.2 Figure 8.1 shows the diagram of SVC. TCR and TSR are both composed
of a shunt-connected reactor controlled by two parallel, reverse-connected
thyristors. TCR is controlled with proper firing angle input to operate in a
continuous manner, while TSR is controlled without firing angle control
which results in a step change in reactance.

8.3.3 TSC shares similar composition and same operational mode as TSR, but the
reactor is replaced by a capacitor. The reactance can only be either fully
connected or fully disconnected zero due to the characteristic of capacitor.
With different combinations of TCR/TSR, TSC and fixed capacitors, a SVC
can meet various requirements to absorb/supply reactive power from/to
the transmission line.

Fig 8.1. Static VAR Compensators (SVC):

N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 49 of 66 JAN-2012


8.3.4 The SVC at Kanpur consists of two identical Static VAR Compensators
(SVCs) SVC-I and II. It is installed at the voltage level of 10.56 kV bus
through 400/10/56 kV coupling transformer.

8.3.5 The operator decides a certain voltage level (Voltage reference) and the SVC
produces sufficient reactive power to maintain the desired voltage level. The
two SVCs can be controlled individually or in parallel in so called joint
control.

8.3.6 The technical parameters per compensator are as follows:
Connection voltage 400 kV, 3 Phase, 50 Hz
Rated capacitive generation 140 MVAR
Rated inductive generation 140 MVAR
The reactive power is 3-phase continuous variable. In voltage control
mode the reference voltage can be adjusted 400 kV +5-5%
TCR 1 and 2 rated power 95 MVAR
TSC 1 rated power 90 MVAR
7th harmonic filter bank 10 MVAR
5th harmonic filter bank 40 MVAR

8.3.7 Some of the control functions not influenced by operator actions are given
below:-

8.3.8 SYSTEM UNDER VOLTAGE SUPERVISON :
The SVC control system provides the following automatic control functions
in case of under voltage on the 400 kV bus.
The SVC output is controlled to 0 Mvar at undervoltage but returns to
normal operation if the voltage comes back within 1 second.
The SVC regulator is blocked if the voltage remains low after 1 second.
However, the SVC returns to normal operation if the voltage comes back
within 2.5 seconds.
The SVC is tripped if the voltage remains low after 2.5 seconds. However,
the SVC is automatically started if the voltage returns within 5 minutes.

8.3.9 SYSTEM FREQUENCY SUPERVISION :
Abnormal system frequencies have the following impact on SVC operation :
47.5 52 Hz Normal Operation
42-47.5/ 52-53 Hz TSC/TCR block after 0.3-2 seconds
<42/ >53 Hz SVC Trip

8.3.10 SVC configuration at maximum & minimum output
The voltage on the connecting 400 kV bus is controlled by means of two
thyristor controlled reactor (TCRs) and one thyristor switched capacitor
TSC). SVC outpur can be any value between 140 MVAR to + 140 MVAR.
SVC configuration at maximum and minimum outputs is as tabulated
below:
N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 50 of 66 JAN-2012



SVC Elements MVAR rating Maximum
Output
Minimum
Output
7th Harmonic Filter Bank (Capacitor)
10 10 10
5th Harmonic Filter Bank (Capacitor)
40 40 40
Thyristor Switched Capacitor
90 90
Thyristor Controlled Reactor-1
-95 -95
Thyristor Controlled Reactor-2
-95 -95
Total
-50 140 -140

SVC configuration at Maximum & Minimum output

8.3.11 DIFFERENT MODES OF SVC OPERATION:

a) Automatic voltage Control Mode: In NORMAL OPERATION the SVC is
voltage controlled. In this mode the desired Voltage reference is set and the
calculated value of the SVC current is fed to the voltage regulator. This will
cause a load dependent SVC voltage a slope control. Vref can be set at 400
kV +5% of -5%. Typical SVC characteristics with V ref 400 kV and slope 3%,
4%, 5% is shown at plot-1 & plot-2 and with V ref 390 kV and slope 3%, 4%,
5% is shown at plot-3 and plot-4.

b) Manual VAR control mode: In Manual mode the SVC is Mvar controlled.
The desired MVAR level is set.

c) Forced Manual Mode: If the control system loses the voltage response signal
the compensator is automatically switched to MANUAL mode. The MVAR
outpur at the time of switching will remain. The Mvar output can be
adjusted, if needed, in MANUAL mode.

d) No Bus Mode (Emergency Mode) : In case of a fault in the var control
computer the system is transferred to NO BUS mode. In this mode the TCR
Mvar output is controlled and the TSC steps can be switched in an out.

8.3.12 Susceptance (B) control :

a) In addition to the voltage and var control modes described above the
operator can order the susceptance control function. Voltage control mode
allows SVC to reach its reactive power limits too frequently in order to
maintain Vref. This may leave with no scope for dynamic compensation in
the event of disturbance.

b) The slow susceptance control corrects the voltage reference in order to
maintain a fixed reactive power generation under steady state conditions
This function can be ordered ON and OFF. In this mode the var output is
fixed within the prescribed dead band presently set at +2% and -3% of 400
N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 51 of 66 JAN-2012


kV. The var output in this band can be +/-40% of 140 MVAR.
SVC at Kanpur shall be normally runs in this mode, primarily due to
following reasons.
Substantial reduction in requirement of reactive power.
Prevention of SVC operation at 100% capacity in normal conditions.
Maintains reserves to support under disturbance.


Plot 1: SVC characteristics with V ref 400 kV in Voltage Control Mode
SVC Characterstics in Voltage Control Mode
-150
-100
-50
0
50
100
150
380 384 388 392 396 400 404 408 412 416 420
Bus Voltage in kV
S
V
C

o
u
t
p
u
t

i
n

M
V
A
R
Setting:
Mode: Voltage Control
V ref: 400 kV
Slope: 3% or 11.67 MVAR per kV
4% or 08.75 MVAR per kV
5% or 07.00 MVAR per kV
Slope 5 %
Slope 3 %
Slope 4 %




Plot 2: SVC characteristics with V ref 390 kV in Voltage Control Mode
SVC Characterstics in Voltage Control Mode
-150
-100
-50
0
50
100
150
380 384 388 392 396 400 404 408 412 416 420
Bus Voltage in kV
S
V
C

o
u
t
p
u
t

i
n

M
V
A
R
Setting:
Mode: Voltage Control
V ref: 390 kV
Slope: 3% or 11.67 MVAR per kV
4% or 08.75 MVAR per kV
5% or 07.00 MVAR per kV
Slope 5 %
Slope 3 %
Slope 4 %



N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 52 of 66 JAN-2012


Plot 3 : SVC Responce to Fault on 400 kV Agra Muradnagar on 6-7-05

-291 MVAR
238 MVAR
-350
-250
-150
-50
50
150
250
350
360
370
380
390
400
410
420
1
:
0
0
:
0
0

A
M
1
:
0
5
:
4
0

A
M
1
:
1
1
:
2
0

A
M
1
:
1
7
:
0
0

A
M
1
:
2
2
:
4
0

A
M
1
:
2
8
:
2
0

A
M
1
:
3
4
:
0
0

A
M
1
:
3
9
:
4
0

A
M
1
:
4
5
:
2
0

A
M
1
:
5
1
:
0
0

A
M
1
:
5
6
:
4
0

A
M
2
:
0
2
:
2
0

A
M
2
:
0
8
:
0
0

A
M
2
:
1
3
:
4
0

A
M
2
:
1
9
:
2
0

A
M
2
:
2
5
:
0
0

A
M
2
:
3
0
:
4
0

A
M
2
:
3
6
:
2
0

A
M
2
:
4
2
:
0
0

A
M
2
:
4
7
:
4
0

A
M
2
:
5
3
:
2
0

A
M
2
:
5
9
:
0
0

A
M
3
:
0
4
:
4
0

A
M
3
:
1
0
:
2
0

A
M
3
:
1
6
:
0
0

A
M
3
:
2
1
:
4
0

A
M
3
:
2
7
:
2
0

A
M
3
:
3
3
:
0
0

A
M
3
:
3
8
:
4
0

A
M
3
:
4
4
:
2
0

A
M
3
:
5
0
:
0
0

A
M
3
:
5
5
:
4
0

A
M
S
V
C

O
u
t
p
u
t

i
n

M
V
A
R
V
o
l
t
a
g
e

i
n

k
V
SVC Response during 63 minute fault feeding on 400 kV Agra -Muradnagar fault on 6th July
2005
SVCs at Kanpur came into action providing a dynamic support of 529 MVAR
(recorded at NRLDC)
Output of SVC s changed from 291 MVAR reactive to 238 MVAR capacitive.
(recorded at NRLDC)


Plot 4 : SVC Response during fault at Rihand STPS on 1
st
June 2010








N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 53 of 66 JAN-2012


8.2.13 CONVERTER-BASED COMPENSATOR :-

a) Static Synchronous Compensator (STATCOM) is one of the key Converter-
based Compensators which are usually based on the voltage source
inverter (VSI) or current source inverter (CSI), as shown in Figure 8.2.

b) Unlike SVC, STATCOM controls the output current independently of the
AC system voltage, while the DC side voltage is automatically maintained
to serve as a voltage source. Mostly, STATCOM is designed based on the
VSI (Voltage Source Inverter).


Fig 8.2. STATCOM topologies: (a) STATCOM based on VSI and CSI
(b) STATCOM with storage.

c) Compared with SVC, the topology of a STATCOM is more complicated.
The switching device of a VSI is usually a gate turn-off device paralleled
by a reverse diode; this function endows the VSI advanced controllability.
Various combinations of the switching devices and appropriate topology
make it possible for a STATCOM to vary the AC output voltage in both
magnitude and phase. Also, the combination of STATCOM with a different
storage device or power source (as shown in Figure 8.2) endows the
STATCOM the ability to control the real power output.

d) STATCOM has much better dynamic performance than conventional
reactive power compensators like SVC. The gate turn-off ability shortens the
dynamic response time from several utility period cycles to a portion of a
period cycle. STATCOM is also much faster in improving the transient
response than a SVC. This advantage also brings higher reliability and
larger operating range.


8.2.14 SERIES-CONNECTED CONTROLLERS:-

As shunt-connected controllers, series-connected FACTS controllers can also
be divided into either impedance type or converter type. The former
N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 54 of 66 JAN-2012


includes Thyristor-Switched Series Capacitor (TSSC), Thyristor- Controlled
Series Capacitor (TCSC), Thyristor- Switched Series Reactor, and
Thyristor-Controlled Series Reactor.
The latter, based on VSI, is usually in the Compensator (SSSC). The
composition and operation of different types are similar to the operation of
the shunt connected peers. Figure shows the diagrams of various series-
connected controllers.




Fig 8.3. Series-connected FACTS controllers:
(a) TCSR and TSSR; (b) TSSC; (c) SSSC











N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 55 of 66 JAN-2012


9. Generator reactive power capability
9.1 A generators output capabilities depend on the thermal limits of various
parts of the generator and on system stability limits. Thermal limits are
physical limits of materials such as copper, iron and insulation, if the
generator overheats, insulation begins to degrade and over time this could
result in equipment damage. Increasingly real power output of a generator
heats up the armature. Increasing reactive power output heats up the field
windings and the armature.

9.2 Power Generators shall be able to supply or absorb reactive power
according to the reactive power capability curve that is defined in
connection agreement and shall perform yearly inspection to ensure that
generators can perform according to the reactive power capability curve.

9.3 To supply reactive power, the generator must increase the magnetic field to
raise the voltage it is supplying to the power system; this means increasing
the current in the filed windings, which is limited by the thermal properties
of the metal and insulation. The field current is supplied by the generator
exciter, which is a DC power supply connected to the generator. The field
current can be quickly adjusted by automatic control or with a dial to
change the reactive power supplied or consumed by the generator.

9.4 At any given field setting, the generator has a specific terminal voltage it
is attempting to hold. If the system voltage declines, the generator will
inject reactive power into the power system, tending to raise system
voltage. If the system voltage rises, the reactive output of the generator
will drop and ultimately reactive power will flow into the generator,
tending to lower system voltage.

9.5 The voltage regulator will accentuate this behavior by driving the field
current in the appropriate direction to obtain the desired system voltage.
Because most of the reactive limits are thermal limits associated with
large pieces of equipment, significant short-term extra reactive-power
capability usually exists.

9.6 Power-system stabilizers also control generator field current and reactive-
power output in response to oscillations on the power system. This function
is a part of the network-stability ancillary service.

9.7 Stability limits are determined by the ability of the power system to accept
delivery of power from the connected generator under a defined set of
system conditions including recognized contingencies. All generators
connected to a power system operate at the same electrical frequency; if a
generator loses synchronism with the rest of the system, it will trip offline
N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 56 of 66 JAN-2012


to protect itself.
9.8 Capacitors supply reactive power and have leading power factors, while
inductors consume reactive power and have lagging power factors. The
convention for generators is the reverse. When the generator is supplying
reactive power, it has a lagging power factor and its mode of operation is
referred to as overexcited. When a generator consumes reactive power, it
has a leading power factor region and is under-excited.

9.9 The capability-set limits are thermal limits for different parts of the
generator, if the generator output approaches these limits, an alarm will
notify the generator operator of the problem; if the operator does not bring
the generator back to a safe operating point, the generators protection
scheme (relays, circuit breakers, fuses) will operate, resulting in
disconnection of the generator from the network; finally, if the protection
equipment fails and the operator does not act in time, the generator will
overheat, potentially causing equipment damage. Because generators are
expensive, generator operators generally will not operate the generator in a
way that risks damaging the equipment and losing revenue during repair.

9.10 The ability of a generator to provide reactive support depends on its real-
power production which is represented in the form of generator capability
curve or D - curve. Figure 9.1 shows the combined limits on real and
reactive production for a typical generator. Like most electric equipment,
generators are limited by their current-carrying capability. Near rated
voltage, this capability becomes an MVA limit for the armature of the
generator rather than a MW limitation, shown as the armature heating limit
in the Figure.



Fig 9.1 GENERATOR CAPABILITY CURVE or D CURVE
N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 57 of 66 JAN-2012



9.11 At the edges of the D-curve, the opportunity cost of extending generator real
or reactive power supply amounts to the millions of rupees that would be
needed to replace damaged generator equipment and lost revenue during
repair. The characteristics of the generator step-up transformer that connects
the generator to the electric transmission system, as well as operational
policies of the transmission system, may impose further limits on generator
output.

9.12 Generator capability may be extended by the coolant used in the generator.
A more efficient coolant allows the generator to dissipate more heat, thereby
extending thermal limits. Most large generators are cooled with hydrogen;
increasing the hydrogen pressure cools the generator equipment more
effectively, increasing the generators capability.


9.13 SYNCHRONOUS CONDENSERS:

9.13.1. Synchronous condenser is another reactive power device, traditionally in
use since 1920s. A synchronous Condenser is a synchronous machine
running without a prime mover or a mechanical load. Like generators,
they can be over-exited or under-exited by varying their field current in
order to generate or absorb reactive power, synchronous condensers
can continuously regulate reactive power to ensure steady transmission
voltage, under varying load conditions.

9.13.2. They are especially suited for emergency voltage control under loss of load,
generation or transmission, because of their fast short-time response.
Synchronous condensers provide necessary reactive power even exceeding
their rating for short duration, to arrest voltage collapse and to improve
system stability. It draws a small amount of active power (about 3%) from
the power system to supply losses.

9.13.3. Synchronous machines that are designed exclusively to provide reactive
support are called synchronous condensers. Synchronous condensers
have all of the response speed and controllability advantages of
generators without the need to construct the rest of the power plant (e.g.,
fuel-handling equipment and boilers). Because they are rotating machines
with moving parts and auxiliary systems, they may require significantly
more maintenance than static alternatives. They also consume real power
equal to about 3% of the machines reactive-power rating. That is, a 50-
MVAR synchronous condenser requires about 1.5 MW of real power.

9.14 Synonymous terms are synchronous compensator and synchronous phase
modifier. The synchronous compensator is the traditional means for
Continuous control of reactive power. Synchronous compensators are used
N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 58 of 66 JAN-2012


in transmission systems: at the receiving end of long transmissions, in
important substations and in conjunction with HVDC inverter stations.
Small synchronous compensators have also been installed in high-power
industrial networks of steel mills; few of these are in use today.
Synchronous compensators in use range in size from a few MVA up to
hundreds of MVA.

9.15 Some hydro/gas generators can operate as synchronous condensers. Such
gas based units are often equipped with clutches which can be used to
disconnect the turbine from the generator when active power is not required
from them. In case of hydro, water supply is blocked and units run with
loads of only air friction

9.16 A synchronous Compensator has several advantages over static
compensators. Synchronous compensators contribute to system short circuit
capacity. Their reactive power production is not affected by the system
voltage. During power swings (electro mechanical oscillations) there is an
exchange of kinetic energy between a synchronous condenser and the
power system.

9.17 During such power swings, a synchronous condenser can supply a large
amount of reactive power, perhaps twice its continuous rating. Unlike
other forms of shunt compensation, it has an internal voltage source and is
better to cope with the low voltage conditions. Because of their high
purchase and operating costs, they have been largely superseded by static
var compensators.

9.17 In recent years the synchronous compensator has been practically ruled out
by the SVC, in the case of new installations, due to benefits in cost
performance and reliability of the latter. One exception is HVDC inverter
stations, in cases where the short-circuit capacity has to be increased. The
synchronous compensators can do this, but not the SVC.

9.18 Comparison between Synchronous Condenser and shunt capacitor is
explained in the below table :-


Sl.No Synchronous condenser Shunt capacitor
1. Synchronous condenser can
supply kVAR equal to its rating
and can absorb up to 100% of its
KVA rating
Shunt capacitor should be associated
with a reactor to give that
performance
2. This has fine control with AVR This operates in steps
N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 59 of 66 JAN-2012


Sl.No Synchronous condenser Shunt capacitor
3. The output is not limited by the
system voltage condition. This
gives out its full capacity even
when system voltage decreases
The capacitor output is proportional
to V
2
of the system. Hence its
performance decreases under low
voltage conditions
4. For short periods the synchronous
condenser can supply KVAR in
excess of its rating at nominal
voltage
The capacitor can not supply more
than its capacity at nominal voltage.
Its output is proportional to V
2
.
5. The full load losses are above 3%
of its capacity
The capacitor losses are about 0.2%
6. These can not be economically
deployed at several locations in
distribution
The capacitor banks can be deployed
at several locations economically in
distribution
7. The synchronous condenser
ratings can not be modular
The capacitors are modular. They can
be deployed as and when system
requirements change
8. A failure in the synchronous
condenser can remove the entire
unit ability to produce KVAR.
However failures are rare in
synchronous condensers
compared to capacitors
A failure of a single fused unit in a
bank of capacitors affects only that
unit and does not affect the entire
bank
9. They add to the short circuit
current of a system and therefore
increase the size of (11kV etc.)
breakers in the neighbour-hood.
The capacitors do not increase the
short circuit capacity of the system, as
their output is proportional to V
2

10. This is a rotating device. Hence
the O&M problems are more
These are static and simple devices.
Hence O&M problems are negligible


9.19 As per planning philosophy and general guidelines in the Manual
on Transmission planning criteria issued by CEA (MOP, India), Thermal /
Nuclear Generating Units shall normally not run at leading power factor.
However for the purpose of charging unit may be allowed to operate at
leading power factor as per the respective capability curve.

9.20 List of synchronous condenser at all India level is given in Annexure 12.



N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 60 of 66 JAN-2012


10.Reactive power management and renewable energy

10.1 INTRODUCTION

10..1 Due to depleting nature of these reserves, efforts are on worldwide to ensure
energy security through alternate technologies for electric power generation.
Global demand for energy is increasing at a breathtaking pace, which will
require significant investment in new power generation capacity and grid
infrastructure. Wind energy, however, is a massive indigenous power source
which is available virtually everywhere in the world. There are no fuel costs,
no geo-political risk and no supply import dependency.

10.2 IEGC recommends the following requirements on renewables.

1. As per IEGC Section 5.2 System Security Aspects :-

5.2 System Security Aspects
(u) Special requirements for Solar/ wind generators

(i) SLDC/RLDC may direct a wind farm to curtail its VAr drawl/injection
in case the security of grid or safety of any equipment or personnel is
endangered.
(ii) During the wind generator start-up, the wind generator shall ensure that
the reactive power drawl (inrush currents in case of induction
generators shall not affect the grid performance.


10.3 RE Technologies :

10.3.1 Various types of RE :
1. Wind (On-shore, Off shore)
2. Solar (Solar PhotoVoltaic, Solar Thermal)
3. Micro Hydro (with Pondage , without Pondage )
4. Biomass (Bagasse, other bio-mass material like rice husk, cotton
stalk, mustard stalk, groundnut shell, coconut fronds, waste cotton
stalks, bark, roots of trees, cane trash, arecanut shells, Prosopis
juliflora, poultry litter)
5. Non fossil fuel based co generation
Wind is most predominantly used technology world-wise, hence we focus
more on it in this discussion.


N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 61 of 66 JAN-2012




10.4 Technology of Wind Generators

Wind power systems convert the movement of air into electricity by means
of a rotating turbine and a generator. There are two types of Wind
generators viz On- and off-shore. In the beginning, generators of a few kW
typically 250kW were manufactured. Nowadays with advancement in
technology very large wind turbines (up to 5 MW) are in operation.
Offshore windfarms are expected to have higher load factors.

10.5 Types of Wind Generators :

1. Induction (Type-1)
a squirrel cage induction generator that is driven through a gearbox. It
operates within a very narrow speed range and is now obsolete. Generally
fixed speed is achieved through a gear box.

2. Variable-slip Induction Generator (Type-2)
It includes a wound rotor and a mechanism to quickly control the current in
the rotor and results in better response to fast dynamic events.

3. Doubly Fed Induction Generator (DFIG) (Type-3)
The turbine-generator power output passes through two components
1) about 70% through a mechanism that produces a variable-frequency
current in the rotor circuit 2) AC-DC-AC power converters
The first mechanism enables the wind turbine generator to operate at a
variable speed typically about 2:1 range from max to min speed). This
improves the power conversion efficiency and controllability of the wind
turbine generator.
The AC-DC-AC power converters need only be rated to carry a fraction,
typically 30%, of the total wind turbine-generator power output.

4. Full conversion Wind Turbine-Generator (Type-4)
The entire turbine power output through an AC-DC-AC power electronic
converter system. the output current of a Type 4 wind turbine generators
can be electronically modulated to zero; thereby limiting its short-circuiting
current contribution and reducing the short-circuit duty of standard
protection equipment. It has a comparable inertial response/ performance
to a conventional generator.

Out of the above, type 1 and 2 are now obsolete and type 3 & 4 are being
more popular.

N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 62 of 66 JAN-2012


10.6 Variable generation plants are often located in remote areas of the network
where the short circuit level is weak and, as a result, problems such as
under-/over-voltages, harmonics or voltage unbalances may be observed.

10.7 Wind Farm : A group of wind generators located in an area connected to a
common pooling station is called a Wind Farm. Its aggregated capacity
ranges from 25-50MW.

10.8 Reactive requirement:
a) The type-1 and Type-2 machines being induction generators can not
participate in voltage regulation and require switched shunt capacitor
banks for reactive compensation.

b) Due to variable speed, WTG depend on AC-DC-AC convertors which will
provide an asynchronous link between the WTG and Grid. These power
electronic devices generally have inherent control of reactive power and can
participate in voltage regulation. Due to restriction on drawl of reactive
power from Grid, a combination of switched capacitor banks and/or
power electronic transmission technologies such as SVC/STATCOM are
provided for Reactive support and power factor control.

c) The reactive compensation system of wind farms shall be such that Wind
farms shall maintain power factor between 0.95 lagging and 0.95 leading at
the connection point.


10.9 CIGRE 293 report of Working Group C1.3 on Electric Power System
Planning with the Uncertainty of Wind generation studied the following :
Plant tolerance to voltage and frequency variation

- plant capability regards
tolerance to system faults and performance during and after
faults
reactive power
active power management
power quality
- control capability to manage
power ramping up
response
voltage and power factor control


N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 63 of 66 JAN-2012


10.10 The Wind generating machines shall have the operating region as shown in
Figure given below during system faults. Wind farms can be disconnected if
the operating point falls below the line in the below Figure 10.1 .



FIGURE 10.1 Fault Ride through characteristics

10.11 Wind farms connected to high voltage transmission system must stay
connected when a voltage dip occurs in the grid, otherwise, the sudden
disconnection of a large amount of wind power may contribute to the
voltage dip, with adverse consequences. Wind farms must remain
connected when the voltage dip profile is above the line shown in the figure.
The per unit voltage at the point of connection to the grid is shown in the
vertical axis and the duration (seconds) of the fault in the horizontal axis.
This code requires Fault Ride-Through (FRT) capability during voltage
drops in Transmission System to 15% of nominal voltage during 300 ms
with recovery up to 80% of nominal voltage after 3 sec, with the slope
shown in figure given above.

10.12 The wind generating machines shall be equipped with fault ride through
capability. During a Fault Ride through, the Reactive power drawl from
Grid shall be minimum and active power generation shall be in proportion
to the retained grid voltage. They should have the capability to withstand
repetitive faults.

N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 64 of 66 JAN-2012


11.Ready Reckoner

1. Change in voltage at a bus

V = Q .
V Fault Level of the Bus

Units: V & V (kV), Q (MVAR), Fault Level (MVA)

2. Fault contribution at HT bus of Unit Transformer:

Sl No. Unit Size(MW) Type 3 MVA Contribution
1 60 Hydro 280
2 120 Thermal 490
3 210 Thermal 735
4 500 Thermal 1800

Thumb Rule: Short circuit level contribution of a generating unit is 3-4 times its MVA rating.

3. Line Charging MVAR:

Sl. No.
Voltage Level
(kV)
Conductor Type
Line Charging MVAR/100
km/ckt
1 132 Panther 5
2 220 Zebra 13.5
3 400 Twin Moose 55.5
4 400 Quad Moose 74
5 400 Quad Bersimis (Delhi ring) 74.6
6 765 at 400 Triple Snow Bird 65.6
6 765 Quad Bersimis 291
Source: CEA: Manual on Transmission Planning Criterion, 1994

4. Line Current

Sl No. Voltage Level (kV) Ampere/MVA
1 132 4.4
2 220 2.6
3 400 1.4

5. Voltage rise at receiving end of uncompensated line

Sl No. Voltage
Level(kV)
Conductor Type
(Single circuit)
Voltage Rise
(kV) per
100km
1 132 Panther 0.75
2 220 Zebra 1.5
3 400 Twin Moose 3






N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 65 of 66 JAN-2012


6. Rated breaking Current Capability of Switch Gear


Source: CEA: Manual on Transmission Planning Criterion, 1994

7. MW vs. Current (ampere)
Sl. No. Voltage Level (kV) MW
1 400 =2/3 * current (amp)
2 220 =1/3 * current (amp)
3 132 =1/4 * current (amp)

8. Impact of 1000 amp flow on a 100 km Ling 400 kV Line (Unity p.f.)
a) I
2
X loss -100 MVAR
b) I
2
R loss -10 MW
c) Potential drop (V
s
-Vr) -3.3 kV

9. Line Charging Guidelines:

- In case, line reactor is available at only one end, it is preferable to charge the line from the
end without reactor and synchronize at the end with reactor. If the line is to be opened, open
from the end where line reactor is available.
Thumb rule is synchronize or open from the end where line reactor
is available.
- The line should be charged from the end with higher fault level (3 phase short circuit MVA) in
order to limit the over voltage at charging end.
- If two buses have almost same short circuit level (3-ph) and neither is a generation station,
charge the line from the bus with lower voltage. At the charging end, all measures should be
taken to control high voltage
a) Bus reactors may be taken in to service
b) Generators at the charging end may be operated at reduced voltage (less than 1 p.u.)
and in lagging power factor mode
c) Suitable measures may be taken to avoid large frequency variations
d) Loads may be taken into service in small steps.

10. Line Equivalent of a Transformer:

Conductor Type
500 MVA
Transformer is
equivalent to
transmission
line (in km)
315 MVA
Transformer
is equivalent
to
transmission
line (in km)
250 MVA
Transformer
is equivalent
to
transmission
line (in km)
765 KV Quad Bersimis 559 887 1117
400 kV Quad Bersimis 153 242 305
400 kV Quad Moose Tala 159 253 319
400 kV Triple Snowbird 145 230 290
400 kV Twin Moose 120 191 241
220 kV Zebra 30 48 61



Sl No. Voltage Level (kV) Kilo ampere
1 765 40
2 400 40
3 220 31.5/40
4 132 25/31
N L D C R E A C T I V E P O W E R M A N A G E M E N T - a r e s o u r c e h a n d b o o k Page 66 of 66 JAN-2012



12. References
12.1 Indian Electricity Grid Code, India, May 2010
12.2 The Central Electricity Authority (Technical Standard for Connectivity to
the Grid) Regulations 2007.
12.3 Manual on Transmission Planning Criteria, CEA, Govt of India, June 1994
12.4 Principles of efficient and reliable reactive power supply and consumption,
staff report, FERC, Docket No. AD05-1-000, February 4, 2005
12.5 Power System Stability and Control by P. Kundur, Tata McGraw Hill, New
Delhi, 2007
12.6 Reactive Power Control in Electric Systems, Edited by Timothy j. e. Miller ,
Wiley- Interscience
12.7 Power system Restoration : Methodologies and Implementation Strategy By
M.M. Adibi, IEEE Press
12.8 Modern Power Station Practice, System Operation Volume L, 3rd Edition,
British Electricity International.

12.9 Reactive Capability Limitations of Synchronous Machine, M.M. Adibi et
al.,(IEEE Transactions on Power System, February 1994)
12.10 Reactive Power Management and Voltage Control in Northern Region.
12.11 Reactive Power Management and Voltage Control in Southern Region.
12.12 Document on Reactive Power by Western Region.
12.13 Reactive Power Management and Voltage Control in Eastern Region.
12.14 Reactive Power Management and Voltage Control in North Eastern Region.
12.15 Operating procedure manual of NLDC




ANNEXURE 1
INTER REGIONAL LINES 400kV and above
Sl.
No
Voltage
in kV
FROM TO
CKT
ID
Ckt. Type
(Tower)
Line
Length
(in km)
Type of
conductor
From End
Shunt
Reactor
rated for
400kV
From End
reactor used as
Bus Reactor
(Yes=1, No=-1)
To End
Shunt
Reactor
rated for
400kV
To End reactor
used as Bus
Reactor
(Yes=1, No=-1)
SIL
Line
charging
Mvar/km
Total Line
Charging
Mvar of
the line
Remarks
1 400 ALLAHABAD SASARAM 1 D/C 212 Twin Moose 0.00 57.14 1 515 0.555 117.7
2 400 BALIA BIHARSHARIFF 1 D/C 242 Quad Moose 45.35 -1 0.00 687 0.740 179.1
3 400 BALIA BIHARSHARIFF 2 D/C 242 Quad Moose 45.35 -1 0.00 687 0.740 179.1
4 400 BALIA PATNA 1 D/C 198 Quad Moose 0.00 0.00 687 0.740 146.5
5 400 BALIA PATNA 2 D/C 198 Quad Moose 0.00 0.00 687 0.740 146.5
6 400 BALIA BARH 1 D/C 244 Quad Moose 0.00 0.00 687 0.740 180.6
7 400 BALIA BARH 2 D/C 244 Quad Moose 0.00 0.00 687 0.740 180.6
8 400 GORAKHPUR-PG MUZAFFARPUR 1 D/C 261 Quad Moose 0.00 57.14 1 687 0.740 193.1
9 400 GORAKHPUR-PG MUZAFFARPUR 2 D/C 261 Quad Moose 0.00 57.14 1 687 0.740 193.1
10 400 SARNATH SASARAM 1 D/C 76 Twin Moose 0.00 57.14 1 515 0.555 42.2
11 765 AGRA GWALIOR 1 S/C 129 Quad Bersimis 0.00 0.00 633 0.730 94.2
12 765 AGRA GWALIOR 2 S/C 128 Quad Bersimis 0.00 0.00 633 0.730 93.4
13 400 BHINMAL ZERDA 1 S/C 143 Twin Moose 0.00 45.35 -1 515 0.555 79.3
14 400 KANKROLI ZERDA 1 S/C 234 Twin Moose 45.35 -1 45.35 -1 515 0.555 129.7
15 400 RAIGARH(PG) ROURKELA (PG) 1 D/C 212 Twin Moose 0.00 57.14 515 0.555 117.7
16 400 RAIGARH(PG) ROURKELA (PG) 2 D/C 212 Twin Moose 0.00 57.14 515 0.555 117.7
17 400 RAIGARH(PG) ROURKELA (PG) 3 D/C 212 Twin Moose 0.00 0.00 515 0.555 117.7
18 400 STERLITE RAIGARH 1 D/C 114 Twin Moose 0.00 0.00 515 0.555 63.3
19 400 RANCHI SIPAT 1 D/C 406 Twin Moose 72.56 1 0.00 515 0.555 225.3
20 400 RANCHI SIPAT 2 D/C 406 Twin Moose 72.56 1 0.00 515 0.555 225.3
21 400 JEYPORE (PG) GAZUWAKA (PG-SR) 1 D/C 220 Twin Moose 0.00 72.56 -1 515 0.555 122.1
22 400 JEYPORE (PG) GAZUWAKA (PG-SR) 2 D/C 220 Twin Moose 0.00 72.56 -1 515 0.555 122.1
23 400 BINAGURI (PG) BONGAIGAON (NER) 1 D/C 216 Twin Moose 57.14 -1 57.14 -1 515 0.555 119.9
24 400 BINAGURI (PG) BONGAIGAON (NER) 2 D/C 216 Twin Moose 0.00 57.14 -1 515 0.555 119.9
400KV AND ABOVE AC LINES
*Series
compensated line
(30%) +TCSC
INTER REGIONAL LINES 400KV and above
NLDC,2012 REACTIVE POWER MANAGEMENT -a resource handbook 1 OF 1
ANNEXURE 2
All India Reactive power compensation details for the transmission system
Sl.
No
Region
(A)
NO of 400 &
above lines
(B)
CIRCUIT.
KMS
(C)
Total Mvar
Generated
by the line
@ 1.0 p.u
voltage
(D)
No of line
Reactors
(E)
line
Reactors
Mvar
(F)
No of Bus
Reactors
(G)
Bus
Reactors
Mvar
(H)
%
Compensation
Line Raectors
(F/D)
% Compensation
Bus Reactors
(H/D)
Total
Compensation
Mvar
(F+H)
% Compensation
Line + Bus reactor
(F+H)
*
1
Inter
Regional
24 5246 3305.9 18 1200.00 36.30 0.00 1200 36
2 Northern 215 29335 16886.1 112 6684.52 50 3301.00 39.59 19.55 9986 59
3 Western 216 36060 22077.8 100 5869.00 52 3041.00 26.58 13.77 8910 40
4 Southern 147 19267 10825.2 60 3323.00 28 1559.00 30.70 14.40 4882 45
5 Eastern 74 10871 6367.4 50 2318.00 25 1417.00 36.40 22.25 3735 59
6
North
Eastern
6 1103 612.1 8 426.00 4 200.00 69.59 32.67 626 102
TOTAL 682 101882 60074.4 348 19820.52 159 9518 32.99 15.84 29339 49

Estimation of losses on account of reators in the system:
1)
2)
* It may be noted that the reactor rating is generally @1.05 p.u. voltage. So ideally col. 'D' would be 1.1025 times the value mentioned if we take 1.05 p.u. voltage.
Approximate loss = 29339 MVAR/550 = 54 MW ( 36MW on account of line reactors and 18 MW on account of bus reactor)
`
ALL INDIA REACTIVE POWER COMPENSATION DETAILS
As on 31-12-2011
Typical X/R ratio of bus reactos = 550
NLDC, 2012 REACTIVE POWER MANAGEMENT-a resource handbook
1 OF 1
ANNEXURE 3
ESTIMATED MVAR RELIEF AVAILABLE WHEN LINE IS OPENED
Sl.
No
Voltage
in kV
FROM TO
CKT
ID
Ckt. Type
(Tower)
Line
Length
(in km)
Type of
conductor
From End
Shunt
Reactor
rated for
400kV
From End
reactor used as
Bus Reactor
(Yes=1, No=-1)
To End
Shunt
Reactor
rated for
400kV
To End reactor
used as Bus
Reactor (Yes=1,
No=-1)
SIL
Line
charging
Mvar/km
Total Line
Charging
Mvar of
the line
MVAR relief
available
when line is
opened
MVAR relief
available when line
is opened & Line
Reactor is used as
Bus Reactor
Remarks
1 765 AGRA GWALIOR 1 S/C 129 Quad Bersimis 0.00 0.00 633 0.730 94.2 94.17 94.17
2 765 AGRA GWALIOR 2 S/C 128 Quad Bersimis 0.00 0.00 633 0.730 93.4 93.44 93.44
3 400 BHINMAL ZERDA 1 S/C 143 Twin Moose 0.00 45.35 -1 515 0.555 79.3 33.90 33.90
4 400 KANKROLI ZERDA 1 S/C 234 Twin Moose 45.35 -1 45.35 -1 515 0.555 129.7 39.00 39.00
5 400 ALLAHABAD SASARAM 1 D/C 212 Twin Moose 0.00 57.14 -1 515 0.555 117.7 60.52 60.52
6 400 BALIA BIHARSHARIFF 1 D/C 242 Quad Moose 45.35 -1 0.00 687 0.740 179.1 133.73 133.73
7 400 BALIA BIHARSHARIFF 2 D/C 242 Quad Moose 45.35 -1 0.00 687 0.740 179.1 133.73 133.73
8 400 BALIA PATNA 1 D/C 198 Quad Moose 0.00 0.00 687 0.740 146.5 146.52 146.52
9 400 BALIA PATNA 2 D/C 198 Quad Moose 0.00 0.00 687 0.740 146.5 146.52 146.52
10 400 BALIA BARH 1 D/C 244 Quad Moose 0.00 0.00 687 0.740 180.6 180.56 180.56
11 400 BALIA BARH 2 D/C 244 Quad Moose 0.00 0.00 687 0.740 180.6 180.56 180.56
12 400 GORAKHPUR-PG MUZAFFARPUR 1 D/C 261 Quad Moose 0.00 57.14 -1 687 0.740 193.1 136.00 136.00
13 400 GORAKHPUR-PG MUZAFFARPUR 2 D/C 261 Quad Moose 0.00 57.14 -1 687 0.740 193.1 136.00 136.00
14 400 SARNATH SASARAM 1 D/C 76 Twin Moose 0.00 57.14 -1 515 0.555 42.2 -14.96 -14.96
15 400 RAIGARH(PG) ROURKELA (PG) 1 D/C 212 Twin Moose 0.00 57.14 515 0.555 117.7 60.52 117.66
16 400 RAIGARH(PG) ROURKELA (PG) 2 D/C 212 Twin Moose 0.00 57.14 515 0.555 117.7 60.52 117.66
17 400 RAIGARH(PG) ROURKELA (PG) 3 D/C 212 Twin Moose 0.00 0.00 515 0.555 117.7 117.66 117.66
18 400 STERLITE RAIGARH 1 D/C 114 Twin Moose 0.00 0.00 515 0.555 63.3 63.27 63.27
19 400 RANCHI SIPAT 1 D/C 406 Twin Moose 72.56 1 0.00 515 0.555 225.3 152.77 225.33
20 400 RANCHI SIPAT 2 D/C 406 Twin Moose 72.56 1 0.00 515 0.555 225.3 152.77 225.33
21 400 JEYPORE (PG) GAJUWAKAKA (PG-SR) 1 D/C 220 Twin Moose 0.00 72.56 -1 515 0.555 122.1 49.54 49.54
22 400 JEYPORE (PG) GAJUWAKAKA (PG-SR) 2 D/C 220 Twin Moose 0.00 72.56 -1 515 0.555 122.1 49.54 49.54
23 400 BINAGURI (PG) BONGAIGAON (NER) 1 D/C 216 Twin Moose 57.14 -1 57.14 -1 515 0.555 119.9 5.59 5.59
24 400 BINAGURI (PG) BONGAIGAON (NER) 2 D/C 216 Twin Moose 0.00 57.14 -1 515 0.555 119.9 62.74 62.74
5246 338.3 693.0 3305.9 2274.6 2534.0 TOTAL
INTER REGIONAL LINK
NLDC, 2012 REACTIVE POWER MANAGEMENT-a resource handbook
1 OF 26
ANNEXURE 3
ESTIMATED MVAR RELIEF AVAILABLE WHEN LINE IS OPENED
NORTHERN REGION
Sl.
No
Voltage
in kV
FROM TO
CKT
ID
Ckt.
Type
(Tower)
Line
Length
(in km)
Type of
conductor
From End
Shunt
Reactor
rated for
400kV
From End
reactor used
as Bus Reactor
(Yes=1, No=-1)
To End
Shunt
Reactor
rated for
400kV
To End
reactor used
as Bus
Reactor
(Yes=1, No=-
1)
SIL
Line
charging
Mvar/km
Total Line
Charging
Mvar of the
line
MVAR relief
available
when line is
opened
MVAR relief
available when
line is opened &
Line Reactor is
used as Bus
Reactor
Remarks
1 400 Abdullapur Bawana 1 D/C 167 Triple Snowbird 0.00 0.00 605 0.656 109.3 109.3 109.3
2 400 Abdullapur Bawana 2 D/C 167 Triple Snowbird 0.00 0.00 605 0.656 109.3 109.3 109.3
3 400 Abdullapur Sonepat 1 D/C 150 Triple Snowbird 0.00 0.00 605 0.656 98.4 98.4 98.4
4 400 Abdullapur Sonepat 2 D/C 150 Triple Snowbird 0.00 0.00 605 0.656 98.4 98.4 98.4
5 400 Agra Agra(UP) 1 D/C 30 Twin Moose 0.00 0.00 515 0.555 16.7 16.7 16.7
6 400 Agra Agra(UP) 2 D/C 30 Twin Moose 0.00 0.00 515 0.555 16.7 16.7 16.7
7 400 Agra Ballabgarh 1 S/C 181 Twin Moose 45.35 -1 45.35 -1 515 0.555 100.5 9.8 9.8
8 400 Agra Bassi 1 S/C 211 Twin Moose 45.35 -1 45.35 -1 515 0.555 117.3 26.6 26.6
9 400 Agra Bassi 2 S/C 217 Twin Moose 45.35 -1 45.35 -1 515 0.555 120.7 30.0 30.0
10 400 Agra Bassi 3 S/C 217 Twin Moose 45.35 -1 45.35 -1 515 0.555 120.7 30.0 30.0
11 400 Agra Bhiwadi 1 D/C 209 Twin Moose 45.35 -1 0.00 515 0.555 116.0 70.6 70.6
12 400 Agra Bhiwadi 2 D/C 210 Twin Moose 0.00 0.00 515 0.555 116.3 116.3 116.3
13 400 Allahabad Kanpur 1 S/C 225 Twin Moose 0.00 0.00 515 0.555 124.9 124.9 124.9
14 400 Allahabad Fatehpur 3 S/C 155 Twin Moose 0.00 0.00 515 0.555 86.0 86.0 86.0
15 400 Allahabad Mainpuri 1 D/C 363 Twin Moose 45.35 -1 72.56 1 515 0.555 201.7 83.8 156.3
*Series
compensated line
(Degree of comp-
40%)
16 400 Allahabad Mainpuri 2 D/C 363 Twin Moose 45.35 -1 72.56 1 515 0.555 201.7 83.8 156.3
*Series
compensated line
(Degree of comp-
17 400 Amritsar Amritsar 1 S/C 60 Twin Moose 0.00 0.00 515 0.555 33.1 33.1 33.1
18 400 Auraiya Agra 1 D/C 166 Twin Moose 0.00 45.35 -1 515 0.555 92.0 46.7 46.7
19 400 Auraiya Agra 2 D/C 166 Twin Moose 0.00 45.35 -1 515 0.555 92.0 46.7 46.7
20 400 Bahadurgarh Bhiwani 1 D/C 84 Twin Moose 0.00 0.00 515 0.555 46.8 46.8 46.8
21 400 Bahadurgarh
Mahindergarh
HVDC
1 D/C 42 Twin Moose 0.00 0.00 515 0.555 23.3 23.3 23.3
22 400 Bhiwani
Mahindergarh
HVDC
1 D/C 42 Twin Moose 0.00 0.00 515 0.555 23.3 23.3 23.3
23 400 Bahadurgarh Sonepat 1 D/C 52 Triple Snowbird 0.00 0.00 605 0.656 34.1 34.1 34.1
24 400 Bahadurgarh Sonepat 2 D/C 52 Triple Snowbird 0.00 0.00 605 0.656 34.1 34.1 34.1
25 400 Balia Lucknow PG 1 D/C 316 Twin Moose 57.14 -1 57.14 -1 515 0.555 175.5 61.2 61.2
*Series
compensated line
(Degree of comp-
40%)
26 400 Balia Lucknow PG 2 D/C 316 Twin Moose 57.14 -1 45.35 -1 515 0.555 175.5 73.0 73.0
*Series
compensated line
(Degree of comp-
40%)
A. POWERGRID
NLDC 2012 REACTIVE POWER MANAGEMENT-a resource handbook 2 OF 26
ANNEXURE 3
ESTIMATED MVAR RELIEF AVAILABLE WHEN LINE IS OPENED
NORTHERN REGION
Sl.
No
Voltage
in kV
FROM TO
CKT
ID
Ckt.
Type
(Tower)
Line
Length
(in km)
Type of
conductor
From End
Shunt
Reactor
rated for
400kV
From End
reactor used
as Bus Reactor
(Yes=1, No=-1)
To End
Shunt
Reactor
rated for
400kV
To End
reactor used
as Bus
Reactor
(Yes=1, No=-
1)
SIL
Line
charging
Mvar/km
Total Line
Charging
Mvar of the
line
MVAR relief
available
when line is
opened
MVAR relief
available when
line is opened &
Line Reactor is
used as Bus
Reactor
Remarks
27 400 Balia Mau 1 D/C 9 Twin Moose 0.00 0.00 515 0.555 5.1 5.1 5.1
28 400 Balia Mau 2 D/C 9 Twin Moose 0.00 0.00 515 0.555 5.1 5.1 5.1
29 400 Ballabgarh G.Noida 1 D/C 43 Quad Bersimis 0.00 0.00 691 0.746 31.9 31.9 31.9
30 400 Ballabgarh Gurgaon 1 S/C 43 Twin Moose 0.00 0.00 515 0.555 23.7 23.7 23.7
31 400 Ballabgarh Maharanibagh 1 D/C 61 Quad Bersimis 0.00 0.00 691 0.746 45.3 45.3 45.3
32 400 Bareilly PG Moradabad 1 S/C 93 Twin Moose 0.00 0.00 515 0.555 51.4 51.4 51.4
33 400 Bareilly PG Moradabad 2 S/C 92 Twin Moose 0.00 0.00 515 0.555 50.9 50.9 50.9
34 400 Bareilly UP Bareilly PG 1 D/C 14 Twin Moose 45.35 -1 45.35 -1 515 0.555 7.9 -82.8 -82.8
35 400 Bareilly UP Bareilly PG 2 D/C 14 Twin Moose 45.35 -1 45.35 -1 515 0.555 7.9 -82.8 -82.8
36 400 Bassi Bhiwadi 1 S/C 235 Twin Moose 45.35 1 0.00 515 0.555 130.4 85.1 130.4
37 400 Bassi Bhiwadi 2 S/C 220 Twin Moose 45.35 1 0.00 515 0.555 122.3 76.9 122.3
38 400 Bassi Heerapura 1 S/C 48 Twin Moose 0.00 0.00 515 0.555 26.5 26.5 26.5
39 400 Bassi Heerapura 2 S/C 49 Twin Moose 0.00 0.00 515 0.555 27.2 27.2 27.2
40 400 Bawana (CCGT) Bahadurgarh 1 D/C 49 Twin Moose 0.00 0.00 515 0.555 27.2 27.2 27.2
41 400 Bawana (CCGT) Hisar 1 S/C 132 Twin Moose 0.00 0.00 515 0.555 73.1 73.1 73.1
42 400 Bhinmal Kankroli 1 D/C 202 Twin Moose 45.35 -1 45.35 1 515 0.555 112.0 21.3 66.6
43 400 Bhiwadi Gurgaon 1 S/C 83 Twin Moose 0.00 0.00 515 0.555 46.0 46.0 46.0
44 400 Bhiwadi Hissar 1 S/C 212 Twin Moose 0.00 45.35 1 515 0.555 117.4 72.1 117.4
45 400 Bhiwadi Moga 1 D/C 350 Twin Moose 0.00 57.14 -1 515 0.555 194.3 137.1 137.1
46 400 Bhiwadi Moga 2 D/C 350 Twin Moose 0.00 57.14 -1 515 0.555 194.3 137.1 137.1
47 400 Chamera-II Chamera-I 1 S/C 36 Twin Moose 0.00 0.00 515 0.555 20.1 20.1 20.1
48 400 Chamera-II Kishenpur 1 S/C 135 Twin Moose 0.00 0.00 515 0.555 74.8 74.8 74.8
49 400 Chamera-II Chamba 1 S/C 0.375 Twin Moose 0.00 0.00 515 0.555 0.2 0.2 0.2
50 400 Chamera-I Jalandhar 1 D/C 152 Twin ACAR 45.35 -1 0.00 557 0.555 84.4 39.1 39.1
51 400 Chamera-I Jalandhar 2 D/C 152 Twin ACAR 45.35 -1 0.00 557 0.555 84.4 39.1 39.1
52 400 Dadri NCTPP G.Noida 1 D/C 13 Quad Bersimis 0.00 0.00 691 0.746 9.9 9.9 9.9
53 400 Dadri NCTPP Maharanibagh 1 D/C 54 Quad Bersimis 0.00 0.00 691 0.746 40.6 40.6 40.6
54 400 Dadri NCTPP Malerkotla 1 S/C 297 Twin Moose 0.00 57.14 -1 515 0.555 164.9 107.8 107.8
55 400 Dadri NCTPP Mandola 1 D/C 46 Quad Bersimis 0.00 0.00 691 0.746 34.5 34.5 34.5
56 400 Dadri NCTPP Mandola 2 D/C 46 Quad Bersimis 0.00 0.00 691 0.746 34.5 34.5 34.5
NLDC 2012 REACTIVE POWER MANAGEMENT-a resource handbook 3 OF 26
ANNEXURE 3
ESTIMATED MVAR RELIEF AVAILABLE WHEN LINE IS OPENED
NORTHERN REGION
Sl.
No
Voltage
in kV
FROM TO
CKT
ID
Ckt.
Type
(Tower)
Line
Length
(in km)
Type of
conductor
From End
Shunt
Reactor
rated for
400kV
From End
reactor used
as Bus Reactor
(Yes=1, No=-1)
To End
Shunt
Reactor
rated for
400kV
To End
reactor used
as Bus
Reactor
(Yes=1, No=-
1)
SIL
Line
charging
Mvar/km
Total Line
Charging
Mvar of the
line
MVAR relief
available
when line is
opened
MVAR relief
available when
line is opened &
Line Reactor is
used as Bus
Reactor
Remarks
57 400 Dadri NCTPP Muradnagar 1 S/C 33 Twin Moose 0.00 0.00 515 0.555 18.4 18.4 18.4
58 400 Dadri NCTPP Panipat 1 S/C 112 Twin Moose 0.00 0.00 515 0.555 62.3 62.3 62.3
59 400 Dadri NCTPP Panipat 2 S/C 117 Twin Moose 0.00 0.00 515 0.555 64.8 64.8 64.8
60 400 Dulhasti Kishenpur 1 S/C 120 Twin Moose 0.00 0.00 515 0.555 66.5 66.5 66.5
61 400 Fatehabad Hissar 1 D/C 89 Twin Moose 0.00 0.00 515 0.555 49.2 49.2 49.2
62 400 Gorakhpur PG Gorakhpur UP 1 D/C 46 Twin Moose 0.00 0.00 515 0.555 25.5 25.5 25.5
63 400 Gorakhpur PG Gorakhpur UP 2 D/C 46 Twin Moose 0.00 0.00 515 0.555 25.5 25.5 25.5
64 400 Gorakhpur PG Lucknow PG 3 D/C 262 Twin Moose 57.14 1 57.14 1 515 0.555 145.4 31.1 145.4
65 400 Gorakhpur PG Lucknow PG 4 D/C 262 Twin Moose 57.14 1 57.14 1 515 0.555 145.4 31.1 145.4
66 400 Kaithal Hissar 1 S/C 113 Triple Snowbird 0.00 45.35 1 605 0.656 74.1 28.8 74.1
67 400 Kaithal Hissar 2 S/C 113 Triple Snowbird 0.00 0.00 605 0.656 74.2 74.2 74.2
68 400 Kankroli Jodhpur 1 S/C 187 Twin Moose 45.35 -1 0.00 515 0.555 103.8 58.4 58.4
69 400 Kanpur Agra 1 S/C 240 Twin Moose 45.35 -1 45.35 -1 515 0.555 133.2 42.5 42.5
70 400 Kanpur Auraiya 1 D/C 73 Twin Moose 0.00 0.00 515 0.555 40.3 40.3 40.3
71 400 Kanpur Auraiya 2 D/C 73 Twin Moose 0.00 0.00 515 0.555 40.6 40.6 40.6
72 400 Kanpur Ballabgarh 1 S/C 386 Twin Moose 72.56 -1 72.56 -1 515 0.555 214.1 68.9 68.9
73 400 Kanpur Ballabgarh 2 D/C 372 Twin Moose 72.56 -1 515 0.555 206.2 133.6 133.6
74 400 Kanpur Ballabgarh 3 D/C 372 Twin Moose 72.56 -1 72.56 -1 515 0.555 206.2 61.1 61.1
75 400 Kanpur Fatehpur 2 S/C 100 Twin Moose 0.00 0.00 515 0.555 55.5 55.5 55.5
76 400 Kanpur Panki 1 S/C 6 Twin Moose 0.00 0.00 515 0.555 3.1 3.1 3.1
77 400 Kanpur Panki 2 S/C 6 Twin Moose 0.00 0.00 515 0.555 3.2 3.2 3.2
78 400 Kishenpur Wagoora 1 D/C 183 Twin Moose 0.00 45.35 1 515 0.555 101.3 56.0 101.3
79 400 Kishenpur Wagoora 2 D/C 183 Twin Moose 0.00 45.35 1 515 0.555 101.3 56.0 101.3
80 400 Kota Merta 1 D/C 256 Twin Moose 45.35 -1 45.35 -1 515 0.555 141.9 51.2 51.2
81 400 Lucknow PG Bareilly PG 1 D/C 256 Twin Moose 45.35 -1 45.35 -1 515 0.555 141.8 51.1 51.1
82 400 Lucknow PG Bareilly PG 2 D/C 256 Twin Moose 45.35 -1 45.35 -1 515 0.555 141.8 51.1 51.1
83 400 Lucknow PG Lucknow UP 1 S/C 63 Twin Moose 0.00 0.00 515 0.555 35.0 35.0 35.0
84 400 Lucknow PG Unnao 1 D/C 74 Twin Moose 0.00 0.00 515 0.555 41.0 41.0 41.0
85 400 Lucknow PG Unnao 2 D/C 74 Twin Moose 0.00 0.00 515 0.555 41.0 41.0 41.0
*Series
Compensated
lines,Ckt 1- 35%,
Ckt-2 & 3-40%
NLDC 2012 REACTIVE POWER MANAGEMENT-a resource handbook 4 OF 26
ANNEXURE 3
ESTIMATED MVAR RELIEF AVAILABLE WHEN LINE IS OPENED
NORTHERN REGION
Sl.
No
Voltage
in kV
FROM TO
CKT
ID
Ckt.
Type
(Tower)
Line
Length
(in km)
Type of
conductor
From End
Shunt
Reactor
rated for
400kV
From End
reactor used
as Bus Reactor
(Yes=1, No=-1)
To End
Shunt
Reactor
rated for
400kV
To End
reactor used
as Bus
Reactor
(Yes=1, No=-
1)
SIL
Line
charging
Mvar/km
Total Line
Charging
Mvar of the
line
MVAR relief
available
when line is
opened
MVAR relief
available when
line is opened &
Line Reactor is
used as Bus
Reactor
Remarks
86 400 Lucknow UP Bareilly PG 1 S/C 279 Twin Moose 0.00 0.00 515 0.555 154.7 154.7 154.7
87 400 Ludhiana Jalandhar 1 S/C 85 Twin Moose 0.00 0.00 515 0.555 47.1 47.1 47.1
88 400 Ludhiana Malerkotla 1 S/C 36 Twin Moose 0.00 0.00 515 0.555 19.8 19.8 19.8
89 400 Ludhiana Patiala 1 D/C 78 Twin Moose 0.00 0.00 515 0.555 43.3 43.3 43.3
90 400 Ludhiana Patiala 2 D/C 78 Twin Moose 0.00 0.00 515 0.555 43.3 43.3 43.3
91 400 Mainpuri Ballabgarh 1 D/C 236 Twin Moose 0.00 0.00 515 0.555 130.9 130.9 130.9
92 400 Mainpuri Ballabgarh 2 D/C 236 Twin Moose 0.00 0.00 515 0.555 130.9 130.9 130.9
93 400 Malerkotla Patiala 1 S/C 63 Twin Moose 0.00 0.00 515 0.555 34.7 34.7 34.7
94 400 Meerut Kaithal 1 D/C 164 Quad Moose 0.00 45.35 -1 687 0.740 121.0 75.6 75.6
95 400 Meerut Kaithal 2 D/C 164 Quad Moose 0.00 45.35 -1 687 0.740 121.0 75.6 75.6
96 400 Meerut Mandola 1 D/C 60 Twin Moose 0.00 0.00 515 0.555 33.2 33.2 33.2
97 400 Meerut Mandola 2 D/C 60 Twin Moose 0.00 0.00 515 0.555 33.2 33.2 33.2
98 400 Meerut Muzzafarnagar 1 S/C 37 Twin Moose 0.00 0.00 515 0.555 20.8 20.8 20.8
99 400 Moga Fatehabad 1 D/C 179 Twin Moose 0.00 57.14 1 515 0.555 99.5 42.4 99.5
100 400 Moga Hissar 1 D/C 209 Twin Moose 0.00 45.35 1 515 0.555 116.2 70.9 116.2
101 400 Moga Jalandhar 1 D/C 85 Twin Moose 0.00 0.00 515 0.555 47.3 47.3 47.3
102 400 Moga Jalandhar 2 D/C 85 Twin Moose 0.00 0.00 515 0.555 47.3 47.3 47.3
103 400 Moradabad Muradnagar 1 S/C 133 Twin Moose 0.00 0.00 515 0.555 73.8 73.8 73.8
104 400 Nalagarh Patiala 1 D/C 94 Triple Snowbird 0.00 0.00 605 0.656 61.5 61.5 61.5
105 400 Nalagarh Patiala 2 D/C 94 Triple Snowbird 0.00 0.00 605 0.656 61.7 61.7 61.7
106 400 Nathpa Jhakri Abdullapur 1 D/C 180 Triple Snowbird 0.00 45.35 1 605 0.656 118.0 72.7 118.0
107 400 Nathpa Jhakri Abdullapur 2 D/C 180 Triple Snowbird 0.00 45.35 1 605 0.656 118.0 72.7 118.0
108 400 Nathpa Jhakri Nalagarh 1 D/C 144 Triple Snowbird 0.00 45.35 1 605 0.656 94.5 49.1 94.5
109 400 Nathpa Jhakri Nalagarh 2 D/C 144 Triple Snowbird 0.00 45.35 1 605 0.656 94.5 49.1 94.5
110 400 Patiala Kaithal 1 D/C 126 Triple Snowbird 0.00 0.00 605 0.656 82.7 82.7 82.7
111 400 Patiala Kaithal 2 D/C 126 Triple Snowbird 0.00 0.00 605 0.656 82.7 82.7 82.7
112 400 RAPS-C Kankroli 1 D/C 199 Twin Moose 0.00 45.35 1 515 0.555 110.2 64.8 110.2
113 400 RAPS-C Kankroli 2 D/C 199 Twin Moose 0.00 45.35 1 515 0.555 110.2 64.8 110.2
114 400 RAPS-C Kota 1 S/C 51 Twin Moose 0.00 0.00 515 0.555 28.0 28.0 28.0
115 400 Rihand Allahabad 1 D/C 279 Twin Moose 0.00 45.35 1 515 0.555 155.0 109.7 155.0
116 400 Rihand Allahabad 2 D/C 279 Twin Moose 0.00 45.35 1 515 0.555 155.0 109.7 155.0
NLDC 2012 REACTIVE POWER MANAGEMENT-a resource handbook 5 OF 26
ANNEXURE 3
ESTIMATED MVAR RELIEF AVAILABLE WHEN LINE IS OPENED
NORTHERN REGION
Sl.
No
Voltage
in kV
FROM TO
CKT
ID
Ckt.
Type
(Tower)
Line
Length
(in km)
Type of
conductor
From End
Shunt
Reactor
rated for
400kV
From End
reactor used
as Bus Reactor
(Yes=1, No=-1)
To End
Shunt
Reactor
rated for
400kV
To End
reactor used
as Bus
Reactor
(Yes=1, No=-
1)
SIL
Line
charging
Mvar/km
Total Line
Charging
Mvar of the
line
MVAR relief
available
when line is
opened
MVAR relief
available when
line is opened &
Line Reactor is
used as Bus
Reactor
Remarks
117 400 Sarnath Allahabad 1 D/C 144 Twin Moose 0.00 0.00 515 0.555 79.9 79.9 79.9
118 400 Singrauli Allahabad 1 S/C 224 Twin Moose 72.56 -1 0.00 515 0.555 124.3 51.8 51.8
119 400 Singrauli Allahabad 2 S/C 202 Twin Moose 72.56 -1 0.00 515 0.555 112.1 39.5 39.5
120 400 Singrauli Anpara 1 S/C 25 Twin Moose 0.00 0.00 515 0.555 13.9 13.9 13.9
121 400 Singrauli Anpara 1 S/C 398 Twin Moose 0.00 0.00 515 0.555 220.9 220.9 220.9
122 400 Singrauli Lucknow UP 1 S/C 409 Twin Moose 57.14 -1 57.14 -1 515 0.555 226.8 112.5 112.5
123 400 Singrauli Rihand 1 S/C 42 Twin Moose 0.00 0.00 515 0.555 23.3 23.3 23.3
124 400 Singrauli Rihand 2 S/C 44 Twin Moose 0.00 0.00 515 0.555 24.4 24.4 24.4
125 400 Singrauli Vindhyachal 1 S/C 3 Twin Moose 0.00 0.00 515 0.555 1.8 1.8 1.8
126 400 Singrauli Vindhyachal 2 S/C 5 Twin Moose 0.00 0.00 515 0.555 2.7 2.7 2.7
127 400 Shree Cement Kota 1 D/C 207 Twin Moose 0.00 45.35 -1 515 0.555 114.9 69.5 69.5
128 400 Shree Cement Merta 2 D/C 103 Twin Moose 0.00 45.35 -1 515 0.555 57.2 11.8 11.8
129 400 Tehri pooling Koteswar 1 D/C 3 Twin Moose 0.00 0.00 515 0.555 1.4 1.4 1.4
130 400 Tehri pooling Koteswar 2 D/C 3 Twin Moose 0.00 0.00 515 0.555 1.4 1.4 1.4
131 400 Uri-I Wagoora 1 D/C 95 Twin Moose 45.35 -1 0.00 515 0.555 52.7 7.4 7.4
132 400 Uri-I Wagoora 2 D/C 95 Twin Moose 45.35 -1 0.00 515 0.555 52.7 7.4 7.4
133 400 Kishenpur Moga 1 S/C 275 Quad Bersimis 57.14 1 57.14 1 633 0.730 201.0 86.8 201.0
765kV Line Charged
at 400kV
134 400 Kishenpur Moga 2 S/C 287 Quad Bersimis 57.14 1 57.14 1 633 0.730 209.6 95.3 209.6
765kV Line Charged
at 400kV
135 400 Koteshwar Pooling Meerut 1 S/C 161 Quad Bersimis 0.00 45.35 -1 633 0.730 117.5 72.2 72.2
765kV Line Charged
at 400kV
136 400 Koteshwar Pooling Meerut 2 S/C 161 Quad Bersimis 0.00 45.35 -1 633 0.730 117.2 71.8 71.8
765kV Line Charged
at 400kV
137 400
Koteshwar
Pooling
Tehri 1 S/C 25 Quad Bersimis 0.00 0.00 633 0.730 18.3 18.3 18.3
765kV Line Charged
at 400kV
138 400
Koteshwar
Pooling
Tehri 2 S/C 25 Quad Bersimis 0.00 0.00 633 0.730 18.3 18.3 18.3
765kV Line Charged
at 400kV
139 400
Koteshwar
Pooling
Koteshwar HEP 1 S/C 3 Quad Bersimis 0.00 0.00 633 0.746 2.2 2.2 2.2
140 400
Koteshwar
Pooling
Koteshwar HEP 2 S/C 3 Quad Bersimis 0.00 0.00 633 0.746 2.2 2.2 2.2
141 400 Dhauliganga Bareilly(UP) 1 D/C 235 Twin Moose 22.68 -1 515 0.555 130.2 107.5 107.5
142 400 Dhauliganga Pithoragarh 1 D/C 59 Twin Moose 0.00 0.00 515 0.555 32.7 32.7 32.7
143 400 Pithoragarh Bareilly(UP) 1 D/C 178 Twin Moose 0.00 0.00 515 0.555 98.7 98.7 98.7
LILO portion is of
Shree Cement
NLDC 2012 REACTIVE POWER MANAGEMENT-a resource handbook 6 OF 26
ANNEXURE 3
ESTIMATED MVAR RELIEF AVAILABLE WHEN LINE IS OPENED
NORTHERN REGION
Sl.
No
Voltage
in kV
FROM TO
CKT
ID
Ckt.
Type
(Tower)
Line
Length
(in km)
Type of
conductor
From End
Shunt
Reactor
rated for
400kV
From End
reactor used
as Bus Reactor
(Yes=1, No=-1)
To End
Shunt
Reactor
rated for
400kV
To End
reactor used
as Bus
Reactor
(Yes=1, No=-
1)
SIL
Line
charging
Mvar/km
Total Line
Charging
Mvar of the
line
MVAR relief
available
when line is
opened
MVAR relief
available when
line is opened &
Line Reactor is
used as Bus
Reactor
Remarks
0.0 0.0
144 400 Bareilly PG Mandola 1 D/C 241 Twin Moose 45.35 -1 45.35 -1 515 0.555 133.7 43.0 43.0
145 400 Bareilly PG Mandola 2 D/C 241 Twin Moose 45.35 -1 45.35 -1 515 0.555 133.7 43.0 43.0
146 400 Gorakhpur PG Lucknow PG 1 D/C 246 Twin Moose 0.00 0.00 515 0.555 136.5 136.5 136.5
147 400 Gorakhpur PG Lucknow PG 2 D/C 246 Twin Moose 0.00 0.00 515 0.555 136.5 136.5 136.5
148 400 Dehar Bhiwani 1 S/C 312 Twin Morkulla 0.00 45.35 -1 515 0.555 173.2 127.8 127.8
149 400 Dehar Panipat 1 S/C 262 Twin Morkulla 0.00 65.00 -1 515 0.555 145.4 80.4 80.4
150 400 Bawana Mundka 1 D/C 22 Quad bersimis 0.00 0.00 691 0.746 16.4 16.4 16.4
151 400 Bawana Mundka 2 D/C 20 Quad bersimis 0.00 0.00 691 0.746 14.9 14.9 14.9
152 400 Ballabgarh Bamnoli 1 D/C 53 Quad bersimis 0.00 0.00 691 0.746 39.4 39.4 39.4
153 400 Ballabgarh Bamnoli 2 D/C 53 Quad bersimis 0.00 0.00 691 0.746 39.4 39.4 39.4
154 400 Bamnoli Mundka 1 D/C 17 Quad bersimis 0.00 0.00 691 0.746 12.7 12.7 12.7
155 400 Bamnoli Mundka 2 D/C 17 Quad bersimis 0.00 0.00 691 0.746 12.7 12.7 12.7
156 400 Mandola Bawana 1 D/C 24 Quad bersimis 0.00 0.00 691 0.746 17.8 17.8 17.8
157 400 Mandola Bawana 2 D/C 24 Quad bersimis 0.00 0.00 691 0.746 17.8 17.8 17.8
E. HVPNL
158 400 Jhajjar Daulatabad 1 D/C 64 Twin Moose 0.00 0.00 515 0.555 35.5 35.5 35.5
159 400 Jhajjar Jhajjar New 1 D/C 30 Twin Moose 0.00 0.00 515 0.555 16.7 16.7 16.7
160 400 Jhajjar Daulatabad 1 D/C 34 Twin Moose 0.00 0.00 515 0.555 18.9 18.9 18.9
161 400 Khedar Fathehabad 1 D/C 40 Twin Moose 0.00 0.00 515 0.555 22.2 22.2 22.2
162 400 Khedar Fathehabad 2 D/C 40 Twin Moose 0.00 0.00 515 0.555 22.0 22.0 22.0
163 400 Khedar Kirori 1 D/C 6 Twin Moose 0.00 0.00 515 0.555 3.4 3.4 3.4
164 400 Khedar Kirori 2 D/C 7 Twin Moose 0.00 0.00 515 0.555 3.6 3.6 3.6
B. POWERLINK
*Series
compensated line
(30%)
C. BBMB
D. DTL
NLDC 2012 REACTIVE POWER MANAGEMENT-a resource handbook 7 OF 26
ANNEXURE 3
ESTIMATED MVAR RELIEF AVAILABLE WHEN LINE IS OPENED
NORTHERN REGION
Sl.
No
Voltage
in kV
FROM TO
CKT
ID
Ckt.
Type
(Tower)
Line
Length
(in km)
Type of
conductor
From End
Shunt
Reactor
rated for
400kV
From End
reactor used
as Bus Reactor
(Yes=1, No=-1)
To End
Shunt
Reactor
rated for
400kV
To End
reactor used
as Bus
Reactor
(Yes=1, No=-
1)
SIL
Line
charging
Mvar/km
Total Line
Charging
Mvar of the
line
MVAR relief
available
when line is
opened
MVAR relief
available when
line is opened &
Line Reactor is
used as Bus
Reactor
Remarks
165 400 Jhajjar (IGSTPS) Mundka 1 D/C 66 Twin Moose 0.00 0.00 515 0.555 36.6 36.6 36.6
166 400 Jhajjar (IGSTPS) Mundka 2 D/C 66 Twin Moose 0.00 0.00 515 0.555 36.6 36.6 36.6
167 400 Baglihar Kishenpur 1 D/C 68 Twin Moose 0.00 0.00 515 0.555 37.7 37.7 37.7
168 400 Baglihar Kishenpur 2 D/C 68 Twin Moose 0.00 0.00 515 0.555 37.7 37.7 37.7
169 400 Barmer Rajwest 1 D/C 20 Twin Moose 0.00 0.00 515 0.555 11.1 11.1 11.1
170 400 Barmer Rajwest 2 D/C 20 Twin Moose 0.00 0.00 515 0.555 11.1 11.1 11.1
171 400 Bhilwara Chhabra 1 S/C 285 Twin Moose 45.35 -1 45.35 -1 515 0.555 158.2 67.5 67.5
172 400 Heerapura Hindaun 1 S/C 192 Twin Moose 45.35 -1 0.00 515 0.555 106.6 61.2 61.2
173 400 Hindaun Chhabra 1 S/C 305 Twin Moose 45.35 -1 45.35 -1 515 0.555 169.3 78.6 78.6
174 400 Merta Heerapura 1 S/C 180 Twin Moose 0.00 0.00 515 0.555 99.9 99.9 99.9
175 400 Merta Jodhpur 1 S/C 120 Twin Moose 0.00 0.00 515 0.555 66.6 66.6 66.6
176 400 Merta Ratangarh 1 S/C 180 Twin Moose 0.00 0.00 515 0.555 99.9 99.9 99.9
177 400 Rajwest Jodhpur 1 D/C 220 Twin Moose 0.00 0.00 515 0.555 122.1 122.1 122.1
178 400 Rajwest Jodhpur 2 D/C 220 Twin Moose 0.00 0.00 515 0.555 122.1 122.1 122.1
179 400 Suratgarh Bikaner 1 S/C 162 Twin Moose 0.00 0.00 515 0.555 89.9 89.9 89.9
180 400 Suratgarh Ratangarh 1 S/C 144 Twin Moose 0.00 0.00 515 0.555 79.9 79.9 79.9
181 400 Suratgarh Ratangarh 2 S/C 144 Twin Moose 0.00 0.00 515 0.555 79.9 79.9 79.9
182 400 Akal Barmer 1 S/C 130 Twin Moose 0.00 0.00 515 0.555 72.2 72.2 72.2
183 400 Dholpur Hindaun 1 S/C 100 Twin Moose 0.00 0.00 515 0.555 55.5 55.5 55.5 Charged at 220kV
184 400 Kota(PG) KTPS 1 S/C 5 Twin Moose 0.00 0.00 515 0.555 2.8 2.8 2.8 Charged at 220kV
185 400 Kota(PG) KTPS 1 S/C 5 Twin Moose 0.00 0.00 515 0.555 2.8 2.8 2.8 Charged at 220kV
I. PTCUL 0.0 0.0
186 400 Muradabad Kashipur 1 S/C 108 Twin Moose 0.00 0.00 515 0.555 59.8 59.8 59.8
187 400 Rishikesh Kashipur 1 S/C 172 Twin Moose 0.00 0.00 515 0.555 95.5 95.5 95.5
188 400 Roorkee Rishikesh 1 S/C 50 Twin Moose 0.00 0.00 515 0.555 27.7 27.7 27.7
F. APCPL (Aravali Power corporation pvt ltd.)
G. PDD (Jammu & Kashmir)
H. RRVPNL
NLDC 2012 REACTIVE POWER MANAGEMENT-a resource handbook 8 OF 26
ANNEXURE 3
ESTIMATED MVAR RELIEF AVAILABLE WHEN LINE IS OPENED
NORTHERN REGION
Sl.
No
Voltage
in kV
FROM TO
CKT
ID
Ckt.
Type
(Tower)
Line
Length
(in km)
Type of
conductor
From End
Shunt
Reactor
rated for
400kV
From End
reactor used
as Bus Reactor
(Yes=1, No=-1)
To End
Shunt
Reactor
rated for
400kV
To End
reactor used
as Bus
Reactor
(Yes=1, No=-
1)
SIL
Line
charging
Mvar/km
Total Line
Charging
Mvar of the
line
MVAR relief
available
when line is
opened
MVAR relief
available when
line is opened &
Line Reactor is
used as Bus
Reactor
Remarks
0.0 0.0
189 400 Agra UP Muradnagar 1 S/C 194 Twin Moose 0.00 0.00 515 0.555 107.7 107.7 107.7
190 400 Agra UP Unnao 1 S/C 279 Twin Moose 45.35 -1 45.35 -1 515 0.555 154.9 64.2 64.2
191 400 Anpara Mau 1 S/C 262 Twin Moose 57.14 -1 0.00 515 0.555 145.6 88.4 88.4
192 400 Anpara Obra 1 S/C 40 Twin Moose 0.00 0.00 515 0.555 22.2 22.2 22.2
193 400 Anpara Sarnath 1 D/C 158 Twin Moose 0.00 0.00 515 0.555 87.5 87.5 87.5
194 400 Anpara Sarnath 2 D/C 158 Twin Moose 0.00 0.00 515 0.555 87.5 87.5 87.5
195 400 Azamgarh Mau 1 S/C 48 Twin Moose 0.00 0.00 515 0.555 26.8 26.8 26.8
196 400 Azamgarh Sultanpur 1 S/C 126 Twin Moose 0.00 0.00 515 0.555 69.7 69.7 69.7
197 400 Bareilly UP Unnao 1 D/C 271 Twin Moose 45.35 -1 45.35 -1 515 0.555 150.4 59.7 59.7
198 400 Bareilly UP Unnao 2 D/C 271 Twin Moose 45.35 -1 45.35 -1 515 0.555 150.4 59.7 59.7
199 400 Gorakhpur UP Azamgarh 1 S/C 90 Twin Moose 0.00 0.00 515 0.555 50.0 50.0 50.0
200 400 Muzzafarnagar Muradnagar 1 S/C 72 Twin Moose 0.00 0.00 515 0.555 40.0 40.0 40.0
201 400 Muzzafarnagar Vishnuprayag 1 D/C 280 Twin Moose 45.35 -1 45.35 -1 515 0.555 155.4 64.7 64.7
202 400 Muzzafarnagar Vishnuprayag 2 D/C 280 Twin Moose 45.35 -1 45.35 -1 515 0.555 155.4 64.7 64.7
203 400 Obra Sultanpur 1 S/C 230 Twin Moose 45.35 -1 45.35 -1 515 0.555 127.9 37.2 37.2
204 400 Panki Muradnagar 1 S/C 397 Twin Moose 45.35 -1 45.35 -1 515 0.555 220.3 129.6 129.6
*Series
Compensated line
(40%)
205 400 Panki Obra 1 S/C 388 Twin Moose 45.35 -1 45.35 -1 515 0.555 215.1 124.4 124.4
206 400 Roorkee Muzzafarnagar 1 S/C 71 Twin Moose 0.00 0.00 515 0.555 39.4 39.4 39.4
207 400 Sarnath Azamgarh 1 S/C 97 Twin Moose 0.00 45.35 -1 515 0.555 53.7 8.3 8.3
208 400 Sultanpur Lucknow PG 1 S/C 209 Twin Moose 0.00 0.00 515 0.555 116.1 116.1 116.1
209 400 Unnao Lucknow UP 1 S/C 39 Twin Moose 0.00 0.00 515 0.555 21.8 21.8 21.8
210 400 Unnao Panki 1 S/C 49 Twin Moose 0.00 0.00 515 0.555 27.1 27.1 27.1
211 765 Anpara Unnao 1 S/C 409 Quad Bersimis 330.00 -1 330.00 -1 633 0.730 298.6 -361.4 -361.4
212 400 Baspa
Karcham
Wangtoo
1 D/C 18 Triple snowbird 0.00 0.00 605 0.656 11.8 11.8 11.8
213 400 Baspa
Karcham
Wangtoo
2 D/C 18 Triple snowbird 0.00 0.00 605 0.656 11.8 11.8 11.8
214 400
Karcham
Wangtoo
NJPC 1 D/C 17 Triple snowbird 0.00 0.00 605 0.656 11.2 11.2 11.2
215 400
Karcham
Wangtoo
NJPC 2 D/C 17 Triple snowbird 0.00 0.00 605 0.656 11.2 11.2 11.2
29335 2642.0 3460.8 16886.1 10783.3 12168.3
LILO portion is of
JKHCL (Jaypee
Karcham Hydro
Corporation Ltd)
TOTAL
J. UPPTCL
K. JHPL (Jaypee Hydro Power Limited)
*Series
Compensated line
(45%)
NLDC 2012 REACTIVE POWER MANAGEMENT-a resource handbook 9 OF 26
ANNEXURE 3
ESTIMATED MVAR RELIEF AVAILABLE WHEN LINE IS OPENED
WESTERN REGION
Sl.
No
Voltage
in kV
FROM TO
CKT
ID
Ckt. Type
(Tower)
Line
Length
(in km)
Type of
conductor
From End
Shunt
Reactor
rated for
400kV
From End
reactor used as
Bus Reactor
(Yes=1, No=-1)
To End
Shunt
Reactor
rated for
400kV
To End reactor
used as Bus
Reactor (Yes=1,
No=-1)
SIL
Line
charging
Mvar/km
Total
Line
Charging
Mvar of
the line
MVAR
relief
available
when line is
opened
MVAR relief
available when
line is opened
& Line Reactor
is used as Bus
Reactor
*
Remarks
CENTRAL SECTOR
1 765 SIPAT SEONI S/C 1 S/C 351 Quad Bersimis 0.00 240.00 2250 2.910 1021.4 781.41 1021.41
2 765 SIPAT SEONI S/C 1 S/C 351 Quad Bersimis 0.00 240.00 2250 2.910 1021.4 781.41 1021.41
3 765 BINA GWALIOR 1 S/C 235 Quad Bersimis 45.35 0.00 633 0.730 171.6 126.20 171.55
765kV Line Charged
at 400kV
4 765 BINA GWALIOR 1 S/C 235 Quad Bersimis 0.00 0.00 633 0.730 171.6 171.55 171.55
765kV Line Charged
at 400kV
5 765 SEONI BINA 1 S/C 293 Quad Bersimis 0.00 0.00 633 0.730 213.9 213.89 213.89
765kV Line Charged
at 400kV
6 765 Seoni Wardha 1 S/C 274 Quad Bersimis 0.00 0.00 633 0.730 200.0 200.02 200.02
765kV Line Charged
at 400kV
7 400 Korba(NTPC) Korba (W) 1 S/C 14 Twin Moose 0.00 0.00 515 0.555 7.8 7.77 7.77
8 400 Wardha Parli (PG) Quad 1 D/C 341 Quad Moose 0.00 0.00 687 0.74 252.3 252.34 252.34
9 400 Wardha Parli (PG) Quad 2 D/C 341 Quad Moose 0.00 0.00 687 0.74 252.3 252.34 252.34
10 400 Korba (NTPC) ACBIL 1 S/C 21 Twin Moose 0.00 0.00 515 0.555 11.7 11.66 11.66
11 400 ACBIL Bhatapara 1 S/C 107 Twin Moose 0.00 0.00 515 0.555 59.4 59.39 59.39
12 400 Mundra (TATA) Bachchau 1 D/C 282
Triple Snowbird
0.00 0.00 605 0.656 185.0 184.99 184.99
13 400 Mundra (TATA) Bachchau 2 D/C 282
Triple Snowbird
0.00 0.00 605 0.656 185.0 184.99 184.99
14 400 Bachchau
Ranchorpura
(Vadavi)
1 D/C 99 Triple Snowbird 0.00 45.35 -1 605 0.656 64.9 19.59 19.59
15 400 Bachchau
Ranchorpura
(Vadavi)
2 D/C 99 Triple Snowbird 0.00 45.35 -1 605 0.656 64.9 19.59 19.59
16 400 Korba (NTPC) Raipur 1 D/C 212 Twin Moose 0.00 45.35 515 0.555 117.7 72.31 117.66
17 400 Korba (NTPC) Raipur 2 D/C 212 Twin Moose 0.00 0.00 515 0.555 117.7 117.66 117.66
18 400 Bhadrawati Parli (PG) D/C 1 D/C 388 Twin Moose 0.00 0.00 515 0.555 215.3 215.34 215.34
19 400 Bhadrawati Parli (PG) D/C 2 D/C 388 Twin Moose 0.00 0.00 515 0.555 215.3 215.34 215.34
20 400 Raigarh Rourkela - I 1 S/C 212 Twin Moose 0.00 0.00 515 0.555 117.7 117.66 117.66
21 400 Raigarh Sterlite-II 1 S/C 127 Twin Moose 0.00 0.00 515 0.555 70.5 70.49 70.49
22 400 Raigarh Rourkela - III & IV 1 D/C 220 Twin Moose 0.00 0.00 515 0.555 122.1 122.10 122.10
23 400 Raigarh Rourkela - III & IV 2 D/C 220 Twin Moose 0.00 0.00 515 0.555 122.1 122.10 122.10
24 400 Dehgam Pirana I & II (PG) 1 D/C 46 Twin Moose 0.00 0.00 515 0.555 25.5 25.53 25.53
25 400 Dehgam Pirana I & II (PG) 2 D/C 46 Twin Moose 0.00 0.00 515 0.555 25.5 25.53 25.53
26 400 Birsinghpur Damoh D/C 1 D/C 227 Twin Moose 0.00 0.00 515 0.555 126.0 125.99 125.99
NLDC, 2012 REACTIVE POWER MANAGEMENT-a resource handbook 10 OF 26
ANNEXURE 3
ESTIMATED MVAR RELIEF AVAILABLE WHEN LINE IS OPENED
WESTERN REGION
Sl.
No
Voltage
in kV
FROM TO
CKT
ID
Ckt. Type
(Tower)
Line
Length
(in km)
Type of
conductor
From End
Shunt
Reactor
rated for
400kV
From End
reactor used as
Bus Reactor
(Yes=1, No=-1)
To End
Shunt
Reactor
rated for
400kV
To End reactor
used as Bus
Reactor (Yes=1,
No=-1)
SIL
Line
charging
Mvar/km
Total
Line
Charging
Mvar of
the line
MVAR
relief
available
when line is
opened
MVAR relief
available when
line is opened
& Line Reactor
is used as Bus
Reactor
*
Remarks
27 400 Birsinghpur Damoh D/C 2 D/C 227 Twin Moose 0.00 0.00 515 0.555 126.0 125.99 125.99
28 400 Parli (MSETCL) Parli (Powergrid) 1 D/C 7 Twin Moose 0.00 0.00 515 0.555 3.9 3.89 3.89
29 400 Parli (MSETCL) Parli (Powergrid) 2 D/C 7 Twin Moose 0.00 0.00 515 0.555 3.9 3.89 3.89
30 400 Bina Sujalpur D/C 1 D/C 198 Twin Moose 57.14 45.35 515 0.555 109.9 7.40 109.89
31 400 Bina Sujalpur D/C 2 D/C 198 Twin Moose 57.14 45.35 515 0.555 109.9 7.40 109.89
32 400 Sujalpur Nagda D/C 1 D/C 150 Twin Moose 0.00 57.14 515 0.555 83.3 26.11 83.25
33 400 Sujalpur Nagda D/C 2 D/C 150 Twin Moose 0.00 57.14 515 0.555 83.3 26.11 83.25
34 400 Korba(NTPC) Bhilai I 1 S/C 197 Twin Moose 0.00 45.35 515 0.555 109.3 63.98 109.34
35 400 Korba(NTPC) Bhilai II 1 S/C 192 Twin Moose 0.00 45.35 515 0.555 106.6 61.21 106.56
36 400 Korba(NTPC) Pathadi s/c 1 S/C 32 Twin Moose 0.00 0.00 515 0.555 17.8 17.76 17.76
37 400 Pathadi Raipur s/c 1 S/C 189 Twin Moose 0.00 0.00 515 0.555 104.9 104.90 104.90
38 400 Bhatapara Bhilai 1 S/C 93 Twin Moose 0.00 0.00 515 0.555 51.6 51.62 51.62
39 400 Vindhyachal Korba(NTPC) -I 1 S/C 215 Twin Moose 45.35 0.00 515 0.555 119.3 73.97 119.33
40 400 Vindhyachal- Korba(NTPC) -II 1 S/C 289 Twin Moose 0.00 0.00 515 0.555 160.4 160.40 160.40
41 400 Bhilai Koradi 1 S/C 272 Twin Moose 45.35 45.35 515 0.555 151.0 60.26 150.96
42 400 Bhilai Bhadravati 1 S/C 322 Twin Moose 72.56 45.35 515 0.555 178.7 60.80 178.71
43 400 Raipur Bhadravati I 1 S/C 333 Twin Moose 72.56 45.35 515 0.555 184.8 66.90 184.82
44 400 Raipur Bhadravati 1 D/C 345 Twin Moose 0.00 0.00 515 0.555 191.5 191.48 191.48
45 400 Raipur Bhadravati 2 D/C 345 Twin Moose 0.00 0.00 515 0.555 191.5 191.48 191.48
46 400 Koradi Satpura 1 S/C 149 Twin Moose 0.00 45.35 515 0.555 82.7 37.34 82.70
47 400 Satpura Itarsi 1 S/C 79 Twin Moose 0.00 0.00 515 0.555 43.8 43.85 43.85
48 400 Itarsi Indore I 1 S/C 214 Twin Moose 45.35 45.35 515 0.555 118.8 28.07 118.77
49 400 Itarsi Indore II 1 S/C 215 Twin Moose 45.35 45.35 515 0.555 119.3 28.62 119.33
50 400 Itarsi Khandwa I 1 S/C 197 Twin Moose 0.00 0.00 515 0.555 109.3 109.34 109.34
51 400 Itarsi Khandwa II 1 S/C 197 Twin Moose 0.00 0.00 515 0.555 109.3 109.34 109.34
52 400 Khandwa Dhule I 1 S/C 262 Twin Moose 45.35 45.35 515 0.555 145.4 54.71 145.41
53 400 Khandwa Dhule II 1 S/C 262 Twin Moose 45.35 45.35 515 0.555 145.4 54.71 145.41
54 400 Indore Asoj I 1 S/C 288 Twin Moose 45.35 -1 45.35 -1 515 0.555 159.8 69.14 69.14
55 400 Indore Asoj II 1 S/C 273 Twin Moose 45.35 -1 45.35 -1 515 0.555 151.5 60.81 60.81
56 400 Bhadravati Chandrapur I 1 D/C 20 Twin Moose 0.00 0.00 515 0.555 11.1 11.10 11.10
57 400 Bhadravati Chandrapur II 2 D/C 20 Twin Moose 0.00 0.00 515 0.555 11.1 11.10 11.10
58 400 Bhadravati Chandrapur III 1 D/C 22 Twin Moose 0.00 0.00 515 0.555 12.2 12.21 12.21
NLDC, 2012 REACTIVE POWER MANAGEMENT-a resource handbook 11 OF 26
ANNEXURE 3
ESTIMATED MVAR RELIEF AVAILABLE WHEN LINE IS OPENED
WESTERN REGION
Sl.
No
Voltage
in kV
FROM TO
CKT
ID
Ckt. Type
(Tower)
Line
Length
(in km)
Type of
conductor
From End
Shunt
Reactor
rated for
400kV
From End
reactor used as
Bus Reactor
(Yes=1, No=-1)
To End
Shunt
Reactor
rated for
400kV
To End reactor
used as Bus
Reactor (Yes=1,
No=-1)
SIL
Line
charging
Mvar/km
Total
Line
Charging
Mvar of
the line
MVAR
relief
available
when line is
opened
MVAR relief
available when
line is opened
& Line Reactor
is used as Bus
Reactor
*
Remarks
59 400 Bhadravati Chandrapur IV 2 D/C 22 Twin Moose 0.00 0.00 515 0.555 12.2 12.21 12.21
60 400 Vindhyachal Jabalpur I 1 D/C 360 Twin Moose 57.14 57.14 515 0.555 199.8 85.51 199.80
61 400 Vindhyachal Jabalpur II 2 D/C 360 Twin Moose 57.14 57.14 515 0.555 199.8 85.51 199.80
62 400 Vindhyachal Jabalpur III 3 D/C 387 Twin Moose 57.14 57.14 515 0.555 214.8 100.50 214.79
63 400 Vindhyachal Jabalpur IV 4 D/C 387 Twin Moose 57.14 57.14 515 0.555 214.8 100.50 214.79
64 400 Jabalpur Itarsi I 1 D/C 232 Twin Moose 45.35 45.35 515 0.555 128.8 38.06 128.76
65 400 Jabalpur Itarsi II 2 D/C 232 Twin Moose 45.35 45.35 515 0.555 128.8 38.06 128.76
66 400 Jabalpur Itarsi III 1 D/C 234 Twin Moose 45.35 45.35 515 0.555 129.9 39.17 129.87
67 400 Jabalpur Itarsi IV 2 D/C 234 Twin Moose 45.35 45.35 515 0.555 129.9 39.17 129.87
68 400 Jhanor Dehgam 1 D/C 156 Twin Moose 0.00 0.00 515 0.555 86.6 86.58 86.58
69 400 Jhanor Dehgam 2 D/C 156 Twin Moose 0.00 0.00 515 0.555 86.6 86.58 86.58
70 400 Jhanor Sugen 1 S/C 65 Twin Moose 0.00 0.00 515 0.555 36.1 36.08 36.08
71 400 Dehgam Sugen 1 D/C 156 Twin Moose 0.00 0.00 515 0.555 86.6 86.58 86.58
72 400 Dehgam Sugen 2 D/C 156 Twin Moose 0.00 0.00 515 0.555 86.6 86.58 86.58
73 400 Jhanor GPEC 1 S/C 16 Twin Moose 0.00 0.00 515 0.555 8.9 8.88 8.88
74 400 Vindhyachal Satna I 1 D/C 266 Twin Moose 45.35 45.35 515 0.555 147.6 56.93 147.63
75 400 Vindhyachal Satna II 2 D/C 266 Twin Moose 45.35 45.35 515 0.555 147.6 56.93 147.63
76 400 Vindhyachal Satna III 3 D/C 258 Twin Moose 0.00 45.35 515 0.555 143.2 97.84 143.19
77 400 Vindhyachal Satna IV 4 D/C 258 Twin Moose 0.00 45.35 515 0.555 143.2 97.84 143.19
78 400 Satna Bina I 1 D/C 276 Twin Moose 45.35 45.35 515 0.555 153.2 62.48 153.18
79 400 Satna Bina II 2 D/C 276 Twin Moose 45.35 45.35 515 0.555 153.2 62.48 153.18
80 400 Satna Bina III 1 D/C 273 Twin Moose 45.35 45.35 515 0.555 151.5 60.81 151.52
81 400 Satna Bina IV 2 D/C 273 Twin Moose 45.35 45.35 515 0.555 151.5 60.81 151.52
82 400 Bhilai Raipur I 1 S/C 13 Twin Moose 0.00 0.00 515 0.555 7.2 7.22 7.22
83 400 Bhilai Raipur II 1 S/C 17 Twin Moose 0.00 0.00 515 0.555 9.4 9.44 9.44
84 400 Kolhapur Mapusa I 1 D/C 150 Twin Moose 0.00 0.00 515 0.555 83.3 83.25 83.25
85 400 Kolhapur Mapusa II 2 D/C 150 Twin Moose 0.00 0.00 515 0.555 83.3 83.25 83.25
86 400 Raipur Raigarh I 1 D/C 217 Twin Moose 0.00 0.00 515 0.555 120.4 120.44 120.44
87 400 Raipur Raigarh II 2 D/C 217 Twin Moose 0.00 0.00 515 0.555 120.4 120.44 120.44
88 400 Raipur Raigarh III 3 D/C 220 Twin Moose 0.00 0.00 515 0.555 122.1 122.10 122.10
89 400 Raipur Raigarh IV 4 D/C 220 Twin Moose 0.00 0.00 515 0.555 122.1 122.10 122.10
90 400 Tarapur Padge I 1 D/C 91 Twin Moose 0.00 0.00 515 0.555 50.5 50.51 50.51
NLDC, 2012 REACTIVE POWER MANAGEMENT-a resource handbook 12 OF 26
ANNEXURE 3
ESTIMATED MVAR RELIEF AVAILABLE WHEN LINE IS OPENED
WESTERN REGION
Sl.
No
Voltage
in kV
FROM TO
CKT
ID
Ckt. Type
(Tower)
Line
Length
(in km)
Type of
conductor
From End
Shunt
Reactor
rated for
400kV
From End
reactor used as
Bus Reactor
(Yes=1, No=-1)
To End
Shunt
Reactor
rated for
400kV
To End reactor
used as Bus
Reactor (Yes=1,
No=-1)
SIL
Line
charging
Mvar/km
Total
Line
Charging
Mvar of
the line
MVAR
relief
available
when line is
opened
MVAR relief
available when
line is opened
& Line Reactor
is used as Bus
Reactor
*
Remarks
91 400 Tarapur Padge II 2 D/C 91 Twin Moose 0.00 0.00 515 0.555 50.5 50.51 50.51
92 400 Tarapur Boisar I 1 D/C 21 Twin Moose 0.00 0.00 515 0.555 11.7 11.66 11.66
93 400 Tarapur Boisar II 2 D/C 21 Twin Moose 0.00 0.00 515 0.555 11.7 11.66 11.66
94 400 Sugen Vapi 1 S/C 118 Twin Moose 0.00 0.00 515 0.555 65.5 65.49 65.49
95 400 Vapi Boisar 1 S/C 91 Twin Moose 0.00 0.00 515 0.555 50.5 50.51 50.51
96 400 Boisar Padge 1 S/C 101 Twin Moose 0.00 0.00 515 0.555 56.1 56.06 56.06
97 400 Bina(PGCIL) Bina(MPPTCL) 1 D/C 1 Twin Moose 0.00 0.00 515 0.555 0.6 0.56 0.56
98 400 Bina(PGCIL) Bina(MPPTCL) 2 D/C 1 Twin Moose 0.00 0.00 515 0.555 0.6 0.56 0.56
99 400 Nagda Dehgam I 1 D/C 332 Twin Moose 45.35 45.35 515 0.555 184.3 93.56 184.26
100 400 Nagda Dehgam II 2 D/C 332 Twin Moose 45.35 45.35 515 0.555 184.3 93.56 184.26
101 400 Seoni
Khandwa I
Quad
1 D/C 350 AAAC 72.56 72.56 515 0.555 194.3 49.13 194.25
102 400 Seoni
Khandwa II
Quad
2 D/C 350 AAAC 72.56 72.56 515 0.555 194.3 49.13 194.25
103 400 Khandwa Rajgarh-I 1 D/C 220 Twin Moose 0.00 0.00 515 0.555 122.1 122.10 122.10
104 400 Khandwa Rajgarh- II 2 D/C 220 Twin Moose 0.00 0.00 515 0.555 122.1 122.10 122.10
105 400 Sipat Raipur I 1 D/C 149 Twin Moose 0.00 0.00 515 0.555 82.7 82.70 82.70
106 400 Sipat Raipur II 2 D/C 149 Twin Moose 0.00 0.00 515 0.555 82.7 82.70 82.70
107 400 Wardha Akola-I 1 D/C 165 Twin Moose 0.00 0.00 515 0.555 91.6 91.58 91.58
108 400 Wardha Akola- II 2 D/C 165 Twin Moose 0.00 0.00 515 0.555 91.6 91.58 91.58
109 400 Damoh Bhopal 1 D/C 216 Twin Moose 0.00 0.00 515 0.555 119.9 119.88 119.88
110 400 Damoh Bhopal 2 D/C 216 Twin Moose 0.00 0.00 515 0.555 119.9 119.88 119.88
111 400 MUNDRA SAMI 1 D/C 282 Twin Moose 0.00 45.35 -1 515 0.555 156.5 111.16 111.16
112 400 MUNDRA SAMI 2 D/C 282 Twin Moose 0.00 45.35 -1 515 0.555 156.5 111.16 111.16
113 400 SAMI DEHGAM 1 D/C 152 Twin Moose 0.00 0.00 515 0.555 84.4 84.36 84.36
114 400 SAMI DEHGAM 2 D/C 152 Twin Moose 0.00 0.00 515 0.555 84.4 84.36 84.36
115 400 Sugen Pirana (T) 1 D/C 219 Twin Moose 0.00 40.82 -1 515 0.555 121.5 80.73 80.73
116 400 Sugen Pirana (T) 2 D/C 219 Twin Moose 0.00 40.82 -1 515 0.555 121.5 80.73 80.73
117 400 Raipur NSPCL 1 D/C 13.5 Twin Moose 0.00 0.00 515 0.555 7.5 7.49 7.49
118 400 Raipur NSPCL 2 D/C 13.5 Twin Moose 0.00 0.00 515 0.555 7.5 7.49 7.49
119 400 Hadala Vadinar (ESSAR) 1 D/C 113 Twin Moose 0.00 0.00 515 0.555 62.7 62.72 62.72
120 400 Hadala Vadinar (ESSAR) 2 D/C 113 Twin Moose 0.00 0.00 515 0.555 62.7 62.72 62.72
IPP
NLDC, 2012 REACTIVE POWER MANAGEMENT-a resource handbook 13 OF 26
ANNEXURE 3
ESTIMATED MVAR RELIEF AVAILABLE WHEN LINE IS OPENED
WESTERN REGION
Sl.
No
Voltage
in kV
FROM TO
CKT
ID
Ckt. Type
(Tower)
Line
Length
(in km)
Type of
conductor
From End
Shunt
Reactor
rated for
400kV
From End
reactor used as
Bus Reactor
(Yes=1, No=-1)
To End
Shunt
Reactor
rated for
400kV
To End reactor
used as Bus
Reactor (Yes=1,
No=-1)
SIL
Line
charging
Mvar/km
Total
Line
Charging
Mvar of
the line
MVAR
relief
available
when line is
opened
MVAR relief
available when
line is opened
& Line Reactor
is used as Bus
Reactor
*
Remarks
121 400 Pirana (PG) Pirana (T) 1 D/C 5 Twin Moose 0.00 0.00 515 0.555 2.8 2.78 2.78
122 400 Pirana (PG) Pirana (T) 2 D/C 5 Twin Moose 0.00 0.00 515 0.555 2.8 2.78 2.78
MATHYA PRADESH
123 400 Bhopal Bina I & II 1 D/C 135 Twin Moose 0.00 45.35 -1 515 0.555 74.9 29.57 29.57
124 400 Bhopal Bina I & II 2 D/C 135 Twin Moose 0.00 45.35 -1 515 0.555 74.9 29.57 29.57
125 400 Birsingpur Damoh 1 S/C 233 Twin Moose 0.00 45.35 -1 515 0.555 129.3 83.96 83.96
126 400 Damoh Katni 1 S/C 115 Twin Moose 0.00 0.00 515 0.555 63.8 63.83 63.83
127 400 Indirasagar Nagda 1 S/C 105 Twin Moose 0.00 0.00 515 0.555 58.3 58.28 58.28
128 400 Indirasagar Satpura 1 S/C 201 Twin Moose 0.00 0.00 515 0.555 111.6 111.56 111.56
129 400 Itarsi Indore -I 1 S/C 80 Twin Moose 0.00 45.35 -1 515 0.555 44.4 -0.95 -0.95
130 400 Itarsi Indore -II 1 S/C 81 Twin Moose 0.00 45.35 -1 515 0.555 45.0 -0.40 -0.40
131 400 Indore Nagda 1 S/C 105 Twin Moose 0.00 0.00 515 0.555 58.3 58.28 58.28
132 400 Itarsi Bhopal I & II 1 D/C 97 Twin Moose 0.00 0.00 515 0.555 53.8 53.84 53.84
133 400 Itarsi Bhopal I & II 2 D/C 97 Twin Moose 0.00 0.00 515 0.555 53.8 53.84 53.84
134 400 Katni Birsingpur 1 S/C 118 Twin Moose 0.00 0.00 515 0.555 65.5 65.49 65.49
135 400 Rajgarh Nagda D/C 1 D/C 103 Twin Moose 0.00 45.35 -1 515 0.555 57.2 11.81 11.81
136 400 Rajgarh Nagda D/C 2 D/C 103 Twin Moose 0.00 45.35 -1 515 0.555 57.2 11.81 11.81
137 400 Satpura Seoni 1 S/C 147 Twin Moose 0.00 45.35 -1 515 0.555 81.6 36.23 36.23
138 400 Seoni Bhilai 1 S/C 154 Twin Moose 0.00 0.00 515 0.555 85.5 85.47 85.47
139 400 SSP Rajgarh-D/C 1 D/C 81 Twin Moose 0.00 0.00 515 0.555 45.0 44.96 44.96
140 400 SSP Rajgarh-D/C 2 D/C 81 Twin Moose 0.00 0.00 515 0.555 45.0 44.96 44.96
MAHARASHTRA
141 400 Akola Bhusawal 1 S/C 182.000 Twin Moose 0.00 45.35 -1 515 0.555 101.0 55.66 55.66
142 400 Aurangabad Bhusawal 1 S/C 238.000 Twin Moose 0.00 0.00 515 0.555 132.1 132.09 132.09
143 400 Babhaleshwar Aurangabad 1 S/C 125.000 Twin Moose 0.00 0.00 515 0.555 69.4 69.38 69.38
144 400 Babhaleshwar Padghe 1 D/C 170.000 Twin Moose 0.00 0.00 515 0.555 94.4 94.35 94.35
145 400 Babhaleshwar Padghe 2 D/C 170.000 Twin Moose 0.00 0.00 515 0.555 94.4 94.35 94.35
146 400 Bhusawal Babhaleshwar 1 S/C 222.000 Twin Moose 0.00 0.00 515 0.555 123.2 123.21 123.21
147 400 Chakan Pune (PG) 1 S/C 19.000 Twin Moose 0.00 0.00 515 0.555 10.5 10.55 10.55
148 400 Chandrapur Khaperkheda 1 S/C 148.000 Twin Moose 0.00 0.00 515 0.555 82.1 82.14 82.14
149 400 Chandrapur Parli Ckt I 1 S/C 357.000 Twin Moose 45.35 -1 45.35 -1 515 0.555 198.1 107.43 107.43
150 400 Chandrapur Parli Ckt II 1 D/C 357.000 Twin Moose 45.35 -1 45.35 -1 515 0.555 198.1 107.43 107.43
NLDC, 2012 REACTIVE POWER MANAGEMENT-a resource handbook 14 OF 26
ANNEXURE 3
ESTIMATED MVAR RELIEF AVAILABLE WHEN LINE IS OPENED
WESTERN REGION
Sl.
No
Voltage
in kV
FROM TO
CKT
ID
Ckt. Type
(Tower)
Line
Length
(in km)
Type of
conductor
From End
Shunt
Reactor
rated for
400kV
From End
reactor used as
Bus Reactor
(Yes=1, No=-1)
To End
Shunt
Reactor
rated for
400kV
To End reactor
used as Bus
Reactor (Yes=1,
No=-1)
SIL
Line
charging
Mvar/km
Total
Line
Charging
Mvar of
the line
MVAR
relief
available
when line is
opened
MVAR relief
available when
line is opened
& Line Reactor
is used as Bus
Reactor
*
Remarks
151 400 Chandrapur Parli Ckt III 2 D/C 357.000 Twin Moose 45.35 -1 45.35 -1 515 0.555 198.1 107.43 107.43
152 400 Dabhol Nagothane 1 D/C 137.000 Twin Moose 0.00 0.00 515 0.555 76.0 76.04 76.04
153 400 Dabhol Nagothane 2 D/C 137.000 Twin Moose 0.00 0.00 515 0.555 76.0 76.04 76.04
154 400 Dabhol
New Koyna
(Quad)
1 D/C 48.000 Twin Moose 0.00 0.00 515 0.555 26.6 26.64 26.64
155 400 Dabhol
New Koyna
(Quad)
2 D/C 48.000 Twin Moose 0.00 0.00 515 0.555 26.6 26.64 26.64
156 400 Dhule Babhaleshwar 1 D/C 170.000 Twin Moose 0.00 0.00 515 0.555 94.4 94.35 94.35
157 400 Dhule Babhaleshwar 2 D/C 170.000 Twin Moose 0.00 0.00 515 0.555 94.4 94.35 94.35
158 400 Dhule Sardar Sarovar 1 D/C 264 Twin Moose 0.00 0.00 515 0.555 146.5 146.52 146.52
159 400 Dhule Sardar Sarovar 2 D/C 264 Twin Moose 0.00 0.00 515 0.555 146.5 146.52 146.52
160 400 Jaigadh New Koyna 1 D/C 55.000 Twin Moose 0.00 0.00 515 0.555 30.5 30.53 30.53
161 400 Jaigadh New Koyna 2 D/C 55.000 Twin Moose 0.00 0.00 515 0.555 30.5 30.53 30.53
162 400 Jaigadh Karad 1 D/C 111.000 Twin Moose 0.00 0.00 515 0.555 61.6 61.61 61.61
163 400 Jaigadh Karad 2 D/C 111.000 Twin Moose 0.00 0.00 515 0.555 61.6 61.61 61.61
164 400 Jejuri Koyna IV 1 S/C 140.000 Twin Moose 0.00 0.00 515 0.555 77.7 77.70 77.70
165 400 Kalwa Kharghar 1 S/C 28.000 Twin Moose 0.00 0.00 515 0.555 15.5 15.54 15.54
166 400 Kalwa Lonikand 1 S/C 98.000 Twin Moose 0.00 0.00 515 0.555 54.4 54.39 54.39
167 400 Kalwa Padghe 1 S/C 56.000 Twin Moose 0.00 0.00 515 0.555 31.1 31.08 31.08
168 400 Karad New Koyna 1 D/C 72.000 Quad Moose 0.00 0.00 687 0.74 53.3 53.28 53.28
169 400 Karad New Koyna 2 D/C 72.000 Quad Moose 0.00 0.00 687 0.74 53.3 53.28 53.28
170 400 Karad Kolhapur 1 D/C 105.000 Twin Moose 0.00 0.00 515 0.555 58.3 58.28 58.28
171 400 Karad Kolhapur 2 D/C 105.000 Twin Moose 0.00 0.00 515 0.555 58.3 58.28 58.28
172 400 Khaperkheda Koradi 1 S/C 4.000 Twin Moose 0.00 0.00 515 0.555 2.2 2.22 2.22
173 400 Kharghar Padghe 1 S/C 86.000 Twin Moose 0.00 0.00 515 0.555 47.7 47.73 47.73
174 400 Koradi Bhusawal 1 S/C 344.000 Twin Moose 45.35 -1 45.35 -1 515 0.555 190.9 100.22 100.22
175 400 Koradi Akola 1 S/C 243.000 Twin Moose 45.35 -1 0.00 515 0.555 134.9 89.51 89.51
176 400 Lonikand Karad 1 S/C 161.000 Twin Moose 0.00 0.00 515 0.555 89.4 89.36 89.36
177 400 Lonikand Jejuri 1 S/C 100.000 Twin Moose 0.00 0.00 515 0.555 55.5 55.50 55.50
178 400 Lonikand Koyna-IV 1 S/C 211.000 Twin Moose 0.00 0.00 515 0.555 117.1 117.11 117.11
179 400 Lonikhand Chakan 1 S/C 25.000 Twin Moose 0.00 0.00 515 0.555 13.9 13.88 13.88
180 400 New Koyna Koyna stage IV 1 D/C 2.000 Twin Moose 0.00 0.00 515 0.555 1.1 1.11 1.11
181 400 New Koyna Koyna stage IV 2 D/C 2.000 Twin Moose 0.00 0.00 515 0.555 1.1 1.11 1.11
NLDC, 2012 REACTIVE POWER MANAGEMENT-a resource handbook 15 OF 26
ANNEXURE 3
ESTIMATED MVAR RELIEF AVAILABLE WHEN LINE IS OPENED
WESTERN REGION
Sl.
No
Voltage
in kV
FROM TO
CKT
ID
Ckt. Type
(Tower)
Line
Length
(in km)
Type of
conductor
From End
Shunt
Reactor
rated for
400kV
From End
reactor used as
Bus Reactor
(Yes=1, No=-1)
To End
Shunt
Reactor
rated for
400kV
To End reactor
used as Bus
Reactor (Yes=1,
No=-1)
SIL
Line
charging
Mvar/km
Total
Line
Charging
Mvar of
the line
MVAR
relief
available
when line is
opened
MVAR relief
available when
line is opened
& Line Reactor
is used as Bus
Reactor
*
Remarks
182 400 Padghe Nagothane 1 D/C 117.000 Twin Moose 0.00 0.00 515 0.555 64.9 64.94 64.94
183 400 Padghe Nagothane 2 D/C 117.000 Twin Moose 0.00 0.00 515 0.555 64.9 64.94 64.94
184 400 Parli Sholapur 1 S/C 182.000 Twin Moose 45.35 -1 0.00 515 0.555 101.0 55.66 55.66
185 400 Parli Lonikhand 1 D/C 284.000 Twin Moose 45.35 -1 45.35 -1 515 0.555 157.6 66.92 66.92
186 400 Parli Lonikhand 2 D/C 284.000 Twin Moose 45.35 -1 45.35 -1 515 0.555 157.6 66.92 66.92
187 400 Pune (PG) Padghe 1 S/C 96.000 Twin Moose 0.00 0.00 515 0.555 53.3 53.28 53.28
188 400 Sholapur(Mah) Sholapur(PG) 1 S/C 178.000 Twin Moose 0.00 0.00 515 0.555 98.8 98.79 98.79
189 400 Sholapur(PG) Karad 1 S/C 300.000 Twin Moose 0.00 45.35 -1 515 0.555 166.5 121.15 121.15
190 400 Asoj Ukai 1 S/C 140 Twin Moose 0.00 0.00 515 0.555 77.7 77.70 77.70
191 400 Mundra (Adani) Varsana 1 S/C 166 Twin Moose 0.00 0.00 515 0.555 92.1 92.13 92.13
192 400 Varsana Hadala 1 S/C 155 Twin Moose 0.00 0.00 515 0.555 86.0 86.03 86.03
193 400 Mundra (Adani) Hadala 1 S/C 238 Twin Moose 0.00 57.14 -1 515 0.555 132.1 74.95 74.95
194 400 Zerda Vadavi(R'chpur) D/C * 1 D/C 155 Twin Moose 0.00 0.00 515 0.555 86.0 86.03 86.03
195 400 Zerda Vadavi(R'chpur) D/C * 2 D/C 155 Twin Moose 0.00 0.00 515 0.555 86.0 86.03 86.03
196 400 Limbdi(Chorania) Vadavi(R'chpur) D/C * 1 D/C 190 Twin Moose 0.00 0.00 515 0.555 105.5 105.45 105.45
197 400 Limbdi(Chorania) Vadavi(R'chpur) D/C * 2 D/C 190 Twin Moose 0.00 0.00 515 0.555 105.5 105.45 105.45
198 400 Asoj Wanakbori 1 S/C 76 Twin Moose 0.00 0.00 515 0.555 42.2 42.18 42.18
199 400 Chorania Amreli 1 S/C 164 Twin Moose 0.00 0.00 515 0.555 91.0 91.02 91.02
200 400 Asoj Chorania 1 S/C 166 Twin Moose 0.00 0.00 515 0.555 92.1 92.13 92.13
201 400 Asoj Chorania 1 S/C 177 Twin Moose 0.00 0.00 515 0.555 98.2 98.24 98.24
202 400 Asoj SSP 1 S/C 83 Twin Moose 0.00 0.00 515 0.555 46.1 46.07 46.07
203 400 Kasor SSP 1 S/C 146 Twin Moose 0.00 0.00 515 0.555 81.0 81.03 81.03
204 400 Kasor GPEC 1 S/C 98 Twin Moose 0.00 0.00 515 0.555 54.4 54.39 54.39
205 400 Kasor-Chorania Chorania 1 S/C 103 Twin Moose 0.00 0.00 515 0.555 57.2 57.17 57.17
206 400 Amreli Jetpur 1 S/C 96 Twin Moose 0.00 0.00 515 0.555 53.3 53.28 53.28
207 400 Chorania Hadala 1 S/C 166 Twin Moose 0.00 0.00 515 0.555 92.1 92.13 92.13
208 400 Hadala Jetpur 1 S/C 115 Twin Moose 0.00 0.00 515 0.555 63.8 63.83 63.83
209 400 Soja Kansari 1 S/C 135 Twin Moose 0.00 0.00 515 0.555 74.9 74.93 74.93
210 400 Vadavi(R'chpur) Dehgam 1 S/C 62 Twin Moose 0.00 0.00 515 0.555 34.4 34.41 34.41
211 400 Vadavi(R'chpur) Dehgam 1 S/C 62 Twin Moose 0.00 0.00 515 0.555 34.4 34.41 34.41
212 400 Soja Wanakbori 1 S/C 95 Twin Moose 0.00 0.00 515 0.555 52.7 52.73 52.73
GUJARAT
NLDC, 2012 REACTIVE POWER MANAGEMENT-a resource handbook 16 OF 26
ANNEXURE 3
ESTIMATED MVAR RELIEF AVAILABLE WHEN LINE IS OPENED
WESTERN REGION
Sl.
No
Voltage
in kV
FROM TO
CKT
ID
Ckt. Type
(Tower)
Line
Length
(in km)
Type of
conductor
From End
Shunt
Reactor
rated for
400kV
From End
reactor used as
Bus Reactor
(Yes=1, No=-1)
To End
Shunt
Reactor
rated for
400kV
To End reactor
used as Bus
Reactor (Yes=1,
No=-1)
SIL
Line
charging
Mvar/km
Total
Line
Charging
Mvar of
the line
MVAR
relief
available
when line is
opened
MVAR relief
available when
line is opened
& Line Reactor
is used as Bus
Reactor
*
Remarks
213 Soja Dehgam 1 S/C 40 Twin Moose 0.00 0.00 515 0.555 22.2 22.20 22.20
214 400 Dehgam Wanakbori 1 S/C 67 Twin Moose 0.00 0.00 515 0.555 37.2 37.19 37.19
CHATTISGARH
215 400 Bhilai Korba(W) 1 S/C 190 Twin Moose 45.35 -1 0.00 515 0.555 105.5 60.10 60.10
216 400 Bhilai Seoni upto border 1 S/C 78 Twin Moose 45.35 -1 0.00 515 0.555 43.3 -2.06 -2.06
36060 2039.0 3329.0 22077.8 16709.8 20397.0
*
TOTAL
Utilization of line reactor as bus reactor necessitates arrangements for bypassing Neutral Grounding reactor(NGR) of line reactor. Work is in progress at many substations & this
column is therefore incomplete as of now
NLDC, 2012 REACTIVE POWER MANAGEMENT-a resource handbook 17 OF 26
ANNEXURE 3
ESTIMATED MVAR RELIEF AVAILABLE WHEN LINE IS OPENED
SOUTHERN REGION
Sl.
No
Voltage
in kV
FROM TO
CKT
ID
Ckt. Type
(Tower)
Line
Length (in
km)
Type of
conductor
From End
Shunt
Reactor
rated for
400kV
From End
reactor used as
Bus Reactor
(Yes=1, No=-1)
To End
Shunt
Reactor
rated for
400kV
To End
reactor used
as Bus
Reactor
(Yes=1, No=-
1)
SIL
Line
charging
Mvar/km
Total Line
Charging
Mvar of the
line
MVAR relief
available
when line is
opened
MVAR relief
available when line
is opened & Line
Reactor is used as
Bus Reactor
Remarks
A. POWERGRID-SR1
1 400
ALMATHI VALLUR 1 D/C 40.000 TWIN MOOSE
0.00 0.00 515 0.555 22.2 22.20 22.20
2 400
ALMATHI VALLUR 2 D/C 40.000 TWIN MOOSE
0.00 0.00 515 0.555 22.2 22.20 22.20
3 400
GOOTY NELMANGALA 1 S/C 256.130 TWIN MOOSE
0.00 45.35 -1 515 0.555 142.2 96.80 96.80
4 400
HYDERABAD GAJWAL 1 S/C 72.800 TWIN MOOSE
45.35 -1 0.00 515 0.555 40.4 -4.95 -4.95
5 400
HYDERABAD KURNOOL 1 S/C 226.500 TWIN MOOSE
0.00 0.00 515 0.555 125.7 125.71 125.71
6 400
HYDERABAD NAGARJUNASAGAR 1 S/C 155.264 TWIN MOOSE
0.00 0.00 515 0.555 86.2 86.17 86.17
7 400
KHAMMAM NAGARJUNASAGAR 1 S/C 144.577 TWIN MOOSE
0.00 0.00 515 0.555 80.2 80.24 80.24
8 400
KHAMMAM VIJAYAWADA 1 S/C 114.775 TWIN MOOSE
0.00 0.00 515 0.555 63.7 63.70 63.70
9 400
KHAMMAM WARANGAL 1 S/C 117.500 TWIN MOOSE
45.35 -1 0.00 515 0.555 65.2 19.86 19.86
10 400
KURNOOL GOOTY 1 S/C 84.590 TWIN MOOSE
0.00 0.00 515 0.555 46.9 46.95 46.95
11 400
MALKARAM HYDERABAD 1 S/C 54.060 TWIN AAAC
0.00 45.35 -1 425 0.555 30.0 -15.35 -15.35
12 400
MEHBOOBNAGAR RAICHUR 1 S/C 73.680 TWIN MOOSE
0.00 0.00 515 0.555 40.9 40.89 40.89
13 400
NAGARJUNASAGAR CUDDAPAH 1 S/C 277.325 TWIN MOOSE
0.00 45.35 -1 515 0.555 153.9 108.56 108.56
14 400
NAGARJUNASAGAR CUDDAPAH 2 S/C 278.664 TWIN MOOSE
0.00 45.35 -1 515 0.555 154.7 109.31 109.31
15 400
NAGARJUNASAGAR GOOTY 1 S/C 308.437 TWIN MOOSE
45.35 1 45.35 -1 515 0.555 171.2 80.48 125.83
16 400
NAGARJUNASAGAR MEHBOOBNAGAR 1 S/C 184.350 TWIN MOOSE
57.14 -1 0.00 515 0.555 102.3 45.17 45.17
17
NELLORE ALMATHI 1 D/C 194.450 TWIN MOOSE
0.00 0.00 515 0.555 107.9 107.92 107.92
18 400
NELLORE ALMATHI 2 D/C 194.450 TWIN MOOSE
0.00 0.00 515 0.555 107.9 107.92 107.92
19 400
RAICHUR GOOTY 1 D/C 146.720 QUAD BERSIMIS
0.00 0.00 691 0.746 109.5 109.45 109.45
20 400
RAICHUR GOOTY 2 D/C 146.720 QUAD BERSIMIS
0.00 0.00 691 0.746 109.5 109.45 109.45
21 400
RAICHUR MUNIRABAD 1 S/C 172.445 TWIN MOOSE
0.00 57.14 -1 515 0.555 95.7 38.56 38.56
22 400
RAMAGUNDAM CHANDRAPUR 1 D/C 177.605 TWIN MOOSE
0.00 0.00 515 0.555 98.6 98.57 98.57
23 400
RAMAGUNDAM CHANDRAPUR 2 D/C 177.605 TWIN MOOSE
0.00 0.00 515 0.555 98.6 98.57 98.57
24 400
RAMAGUNDAM GAJWAL 1 S/C 135.000 TWIN MOOSE
0.00 0.00 515 0.555 74.9 74.93 74.93
25 400
RAMAGUNDAM HYDERABAD 3 D/C 201.236 TWIN MOOSE
0.00 0.00 515 0.555 111.7 111.69 111.69
26 400
RAMAGUNDAM HYDERABAD 4 D/C 201.236 TWIN MOOSE
0.00 0.00 515 0.555 111.7 111.69 111.69
27 400
RAMAGUNDAM MALKARAM 1 S/C 192.400 TWIN AAAC
0.00 0.00 425 0.555 106.8 106.78 106.78
28 400
RAMAGUNDAM NAGARJUNASAGAR 1 D/C 267.200 TWIN MOOSE
45.35 -1 45.35 -1 515 0.555 148.3 57.59 57.59
29 400
RAMAGUNDAM NAGARJUNASAGAR 2 D/C 267.200 TWIN MOOSE
45.35 -1 45.35 -1 515 0.555 148.3 57.59 57.59
30 400
RAMAGUNDAM WARANGAL 1 S/C 98.830 TWIN MOOSE
0.00 0.00 515 0.555 54.9 54.85 54.85
31 400
SIMHADRI GAJUWAKA 1 S/C 12.800 TWIN MOOSE
0.00 57.14 1 515 0.555 7.1 -50.04 7.10
NLDC 2012 REACTIVE POWER MANAGEMENT-a resource handbook 18 OF 26
ANNEXURE 3
ESTIMATED MVAR RELIEF AVAILABLE WHEN LINE IS OPENED
SOUTHERN REGION
Sl.
No
Voltage
in kV
FROM TO
CKT
ID
Ckt. Type
(Tower)
Line
Length (in
km)
Type of
conductor
From End
Shunt
Reactor
rated for
400kV
From End
reactor used as
Bus Reactor
(Yes=1, No=-1)
To End
Shunt
Reactor
rated for
400kV
To End
reactor used
as Bus
Reactor
(Yes=1, No=-
1)
SIL
Line
charging
Mvar/km
Total Line
Charging
Mvar of the
line
MVAR relief
available
when line is
opened
MVAR relief
available when line
is opened & Line
Reactor is used as
Bus Reactor
Remarks
32 400
SIMHADRI GAJUWAKA 2 S/C 12.800 TWIN MOOSE
0.00 57.14 1 515 0.555 7.1 -50.04 7.10
33 400
VALLUR SRIPURUMPUDUR 1 D/C 104.300 TWIN MOOSE
0.00 0.00 515 0.555 57.9 57.89 57.89
34 400
VALLUR SRIPURUMPUDUR 2 D/C 104.300 TWIN MOOSE
0.00 0.00 515 0.555 57.9 57.89 57.89
35 400
VEMAGIRI SIMHADRI 1 S/C 193.500 TWIN MOOSE
0.00 0.00 515 0.555 107.4 107.39 107.39
36 400
VEMAGIRI SIMHADRI 2 S/C 193.500 TWIN MOOSE
0.00 0.00 515 0.555 107.4 107.39 107.39
37 400
VIJAYAWADA GAJUWAKA 3 D/C 314.718 TWIN MOOSE
57.14 1 57.14 1 515 0.555 174.7 60.38 174.67
38 400
VIJAYAWADA NELLORE 1 D/C 340.000 TWIN MOOSE
45.35 1 45.35 -1 515 0.555 188.7 98.00 143.35
39 400
VIJAYAWADA NELLORE 2 D/C 340.000 TWIN MOOSE
45.35 1 45.35 -1 515 0.555 188.7 98.00 143.35
40 400
VIJAYAWADA VEMAGIRI 3 D/C 195.410 TWIN MOOSE
45.35 1 0.00 515 0.555 108.5 63.10 108.45
41 400
VIJAYAWADA VEMAGIRI 4 D/C 195.410 TWIN MOOSE
57.14 1 0.00 515 0.555 108.5 51.31 108.45
A. POWERGRID-SR2
42 400
BANGALORE SALEM SC1 S/C 181.357 TWIN MOOSE
0.00 45.35 1 515 0.555 100.7 55.30 100.65
43 400
CHITOOR SRIPERUMBUDUR SC1 S/C 95.140 TWIN MOOSE
0.00 45.35 1 515 0.555 52.8 7.45 52.80
44 400
CUDDAPAH CHITOOR SC1 S/C 147.140 TWIN MOOSE
0.00 0.00 515 0.555 81.7 81.66 81.66
45 400
CUDDAPAH KOLAR AC SC1 S/C 174.073 TWIN MOOSE
0.00 0.00 515 0.555 96.6 96.61 96.61
46 400
GOOTY HOODY SC1 S/C 253.690 TWIN MOOSE
57.14 -1 0.00 515 0.555 140.8 83.66 83.66
47 400
HOSUR SALEM SC1 S/C 126.339 TWIN MOOSE
0.00 0.00 515 0.555 70.1 70.12 70.12
48 400
HASSAN MYSORE DC1 D/C 96.000 TWIN MOOSE
0.00 0.00 515 0.555 53.3 53.28 53.28
49 400
HASSAN MYSORE DC2 D/C 96.000 TWIN MOOSE
0.00 0.00 515 0.555 53.3 53.28 53.28
50 400
KAIGA NARENDRA DC1 D/C 107.662 AAAC TWIN
0.00 0.00 425 0.555 59.8 59.75 59.75
51 400
KAIGA NARENDRA DC2 D/C 107.662 AAAC TWIN
0.00 0.00 425 0.555 59.8 59.75 59.75
52 400
KAIGA SIRSI DC1 D/C 61.432 TWIN MOOSE
0.00 0.00 515 0.555 34.1 34.09 34.09
53 400
KAIGA SIRSI DC2 D/C 61.432 TWIN MOOSE
0.00 0.00 515 0.555 34.1 34.09 34.09
54 400
KALIVANDAPATTU SRIPERUMBUDUR SC1 S/C 30.700 TWIN MOOSE
0.00 0.00 515 0.555 17.0 17.04 17.04
55 400
KOLAR AC BANGALORE SC1 S/C 97.391 TWIN MOOSE
0.00 45.35 1 515 0.555 54.1 8.70 54.05
56 400
KOLAR AC HOODY DC1 D/C 51.067 QUAD BERSIMIS
0.00 0.00 691 0.746 38.1 38.10 38.10
57 400
KOLAR AC HOODY DC2 D/C 51.067 QUAD BERSIMIS
0.00 0.00 691 0.746 38.1 38.10 38.10
58 400
KOLAR AC HOSUR DC1 D/C 69.000 TWIN MOOSE
0.00 0.00 515 0.555 38.3 38.30 38.30
59 400
KOLAR AC HOSUR DC2 D/C 69.000 TWIN MOOSE
0.00 0.00 515 0.555 38.3 38.30 38.30
60 400
KOLAR AC KALIVANDAPATTU SC1 S/C 241.200 TWIN MOOSE
0.00 45.35 -1 515 0.555 133.9 88.51 88.51
61 400
KUDAMKULAM TIRUNELVELI DC1 D/C 72.489 QUAD MOOSE
0.00 0.00 687 0.740 53.6 53.64 53.64
62 400
KUDAMKULAM TIRUNELVELI DC2 D/C 72.489 QUAD MOOSE
0.00 0.00 687 0.740 53.6 53.64 53.64
63 400
KUDAMKULAM TIRUNELVELI DC3 D/C 79.534 QUAD MOOSE
0.00 0.00 687 0.740 58.9 58.86 58.86
NLDC 2012 REACTIVE POWER MANAGEMENT-a resource handbook 19 OF 26
ANNEXURE 3
ESTIMATED MVAR RELIEF AVAILABLE WHEN LINE IS OPENED
SOUTHERN REGION
Sl.
No
Voltage
in kV
FROM TO
CKT
ID
Ckt. Type
(Tower)
Line
Length (in
km)
Type of
conductor
From End
Shunt
Reactor
rated for
400kV
From End
reactor used as
Bus Reactor
(Yes=1, No=-1)
To End
Shunt
Reactor
rated for
400kV
To End
reactor used
as Bus
Reactor
(Yes=1, No=-
1)
SIL
Line
charging
Mvar/km
Total Line
Charging
Mvar of the
line
MVAR relief
available
when line is
opened
MVAR relief
available when line
is opened & Line
Reactor is used as
Bus Reactor
Remarks
64 400
KUDAMKULAM TIRUNELVELI DC4 D/C 79.534 QUAD MOOSE
0.00 0.00 687 0.740 58.9 58.86 58.86
65 400
MADURAI KARAIKUDI SC1 S/C 129.761 TWIN MOOSE
57.14 -1 0.00 515 0.555 72.0 14.87 14.87
66 400
MADURAI THIRUNELVELI DC1 D/C 161.700 TWIN MOOSE
0.00 0.00 515 0.555 89.7 89.74 89.74
67 400
MADURAI THIRUNELVELI DC2 D/C 161.700 TWIN MOOSE
0.00 0.00 515 0.555 89.7 89.74 89.74
68 400
MADURAI UDUMALPET SC1 S/C 127.232 TWIN MOOSE
0.00 0.00 515 0.555 70.6 70.61 70.61
69 400
NARENDRA DAVANGERE DC1 D/C 156.500 TWIN MOOSE
0.00 0.00 515 0.555 86.9 86.86 86.86
70 400
NARENDRA DAVANGERE DC2 D/C 156.500 TWIN MOOSE
0.00 0.00 515 0.555 86.9 86.86 86.86
71 400
NELAMANGALA BANGALORE DC1 D/C 42.004 TWIN MOOSE
0.00 0.00 515 0.555 23.3 23.31 23.31
72 400
NELAMANGALA BANGALORE DC2 D/C 42.004 TWIN MOOSE
0.00 0.00 515 0.555 23.3 23.31 23.31
73 400
NELAMANGALA BANGALORE SC1 S/C 53.695 TWIN MOOSE
0.00 57.14 1 515 0.555 29.8 -27.34 29.80
74 400
NELAMANGALA MYSORE DC1 D/C 132.897 TWIN MOOSE
0.00 0.00 515 0.555 73.8 73.76 73.76
75 400
NELAMANGALA MYSORE DC2 D/C 132.897 TWIN MOOSE
0.00 0.00 515 0.555 73.8 73.76 73.76
76 400
NEYVELI_TS1 TRICHY DC2 D/C 171.950 TWIN MOOSE
0.00 45.35 1 515 0.555 95.4 50.08 95.43
77 400
NEYVELI_TS2 NEYVELI_TS1 SC1 S/C 13.939 TWIN MOOSE
0.00 0.00 515 0.555 7.7 7.74 7.74
78 400
NEYVELI_TS2 PUDUCHERY SC1 S/C 68.000 TWIN MOOSE
0.00 0.00 515 0.555 37.7 37.74 37.74
79 400
NEYVELI_TS2 PUGALUR DC1 D/C 198.047 TWIN MOOSE
0.00 45.35 -1 515 0.555 109.9 64.56 64.56
80 400
NEYVELI_TS2 EXP PUGALUR SC1 SC1 199.670 TWIN MOOSE
0.00 45.35 -1 515 0.555 110.8 65.47 65.47
81 400
NEYVELI_TS2 SALEM SC1 S/C 199.670 TWIN MOOSE
0.00 0.00 515 0.555 110.8 110.82 110.82
82 400
NEYVELI_TS2 SALEM SC2 S/C 178.720 TWIN MOOSE
0.00 45.35 1 515 0.555 99.2 53.84 99.19
83 400
NEYVELI_TS2 TRICHY DC1 D/C 164.175 TWIN MOOSE
0.00 57.14 -1 515 0.555 91.1 33.97 33.97
84 400
PUDUCHERRY
SUNGUVARCHATRA
M
SC1 S/C 136.410 TWIN MOOSE
0.00 0.00 515 0.555 75.7 75.71 75.71
85 400
PUGALUR MADURAI DC1 D/C 123.643 TWIN MOOSE
0.00 0.00 515 0.555 68.6 68.62 68.62
86 400
PUGALUR MADURAI DC2 D/C 123.643 TWIN MOOSE
0.00 0.00 515 0.555 68.6 68.62 68.62
87 400
SALEM UDUMALPET SC1 S/C 150.543 TWIN MOOSE
0.00 45.35 1 515 0.555 83.6 38.20 83.55
88 400
SALEM UDUMALPET SC2 S/C 137.910 TWIN MOOSE
0.00 57.14 1 515 0.555 76.5 19.40 76.54
89 400
SUNGUVARCHATRAM SRIPERUMBUDDUR SC1 S/C 17.900 TWIN MOOSE
0.00 45.35 1 515 0.555 9.9 -35.42 9.93
90 400
THIRUNELVELI TRIVANDRUM DC1 D/C 160.400 TWIN MOOSE
0.00 57.14 -1 515 0.555 89.0 31.88 31.88
91 400
THIRUNELVELI TRIVANDRUM DC2 D/C 160.400 TWIN MOOSE
0.00 0.00 515 0.555 89.0 89.02 89.02
92 400
THIRUNELVELI UDUMALPET DC1 D/C 264.987 TWIN MOOSE
57.14 1 57.14 1 515 0.555 147.1 32.78 147.07
93 400
THIRUNELVELI UDUMALPET DC2 D/C 264.987 TWIN MOOSE
57.14 1 57.14 1 515 0.555 147.1 32.78 147.07
94 400
TRICHY KARAIKUDI SC1 S/C 97.699 TWIN MOOSE
0.00 0.00 515 0.555 54.2 54.22 54.22
95 400
TRICHY MADURAI DC1 D/C 130.486 TWIN MOOSE
0.00 45.35 1 515 0.555 72.4 27.07 72.42
96 400
UDUMALPET ARASUR DC1 D/C 65.116 TWIN MOOSE
0.00 0.00 515 0.555 36.1 36.14 36.14
NLDC 2012 REACTIVE POWER MANAGEMENT-a resource handbook 20 OF 26
ANNEXURE 3
ESTIMATED MVAR RELIEF AVAILABLE WHEN LINE IS OPENED
SOUTHERN REGION
Sl.
No
Voltage
in kV
FROM TO
CKT
ID
Ckt. Type
(Tower)
Line
Length (in
km)
Type of
conductor
From End
Shunt
Reactor
rated for
400kV
From End
reactor used as
Bus Reactor
(Yes=1, No=-1)
To End
Shunt
Reactor
rated for
400kV
To End
reactor used
as Bus
Reactor
(Yes=1, No=-
1)
SIL
Line
charging
Mvar/km
Total Line
Charging
Mvar of the
line
MVAR relief
available
when line is
opened
MVAR relief
available when line
is opened & Line
Reactor is used as
Bus Reactor
Remarks
97 400
UDUMALPET ARASUR DC2 D/C 65.116 TWIN MOOSE
0.00 0.00 515 0.555 36.1 36.14 36.14
98 400
UDUMALPET TRICHUR DC1 D/C 129.793 TWIN MOOSE
0.00 45.35 1 515 0.555 72.0 26.68 72.04
99 400
UDUMALPET TRICHUR DC2 D/C 129.793 TWIN MOOSE
0.00 45.35 1 515 0.555 72.0 26.68 72.04
100 400
TRICHUR KOCHI DC1 # D/C 78.200 TWIN MOOSE
0.00 0.00 515 0.555 43.4 43.40 43.40
101 400
TRICHUR KOCHI DC2 # D/C 78.200 TWIN MOOSE
0.00 0.00 515 0.555 43.4 43.40 43.40
102 400
KALPAKKA GAZUWAKA 1 D/C 12.000 TWIN MOOSE
0.00 0.00 515 0.555 6.7 6.66 6.66
103 400
KALPAKKA GAZUWAKA 2 D/C 12.000 TWIN MOOSE
0.00 0.00 515 0.555 6.7 6.66 6.66
104 400
KALPAKKA VEMAGIRI 1 D/C 158.000 TWIN MOOSE
0.00 0.00 515 0.555 87.7 87.69 87.69
105 400
KALPAKKA VEMAGIRI 2 D/C 158.000 TWIN MOOSE
0.00 0.00 515 0.555 87.7 87.69 87.69
106 400
KHAMMAM KALPAKKA 1 D/C 364.000 TWIN MOOSE
57.14 1 57.14 -1 515 0.555 202.0 87.73 144.88
107 400
KHAMMAM KALPAKKA 2 D/C 364.000 TWIN MOOSE
57.14 1 57.14 -1 515 0.555 202.0 87.73 144.88
108 400
KHAMMAM MAMIDAPALLY 1 D/C 198.000 TWIN MOOSE
0.00 0.00 515 0.555 109.9 109.89 109.89
109 400
KHAMMAM MAMIDAPALLY 2 D/C 198.000 TWIN MOOSE
0.00 0.00 515 0.555 109.9 109.89 109.89
110 400
MAMIDIPALLY GHANAPUR S/C 45.000 TWIN MOOSE
0.00 0.00 515 0.555 25.0 24.98 24.98
111 400
RAMAGUNDAM DICHPALLY 1 D/C 149.000 TWIN MOOSE
0.00 0.00 515 0.555 82.7 82.70 82.70
112 400
SIMHADRI KALPAKKA 1 D/C 3.700 TWIN MOOSE
0.00 0.00 515 0.555 2.1 2.05 2.05
113 400
SIMHADRI KALPAKKA 2 D/C 3.700 TWIN MOOSE
0.00 0.00 515 0.555 2.1 2.05 2.05
114 400
SIMHADRI KALPAKKA 3 D/C 3.700 TWIN MOOSE
0.00 0.00 515 0.555 2.1 2.05 2.05
115 400
SIMHADRI KALPAKKA 4 D/C 3.700 TWIN MOOSE
0.00 0.00 515 0.555 2.1 2.05 2.05
116 400
SRISAILAM KURNOOL S/C 104.000 TWIN MOOSE
0.00 0.00 515 0.555 57.7 57.72 57.72
117 400
SRISAILAM MAMIDAPALLI 1 D/C 147.000 TWIN MOOSE
0.00 0.00 515 0.555 81.6 81.59 81.59
118 400
SRISAILAM MAMIDAPALLI 2 D/C 147.000 TWIN MOOSE
0.00 0.00 515 0.555 81.6 81.59 81.59
119 400
SRISAILAM VTPS IV 1 D/C 213.000 TWIN MOOSE
0.00 0.00 515 0.555 118.2 118.22 118.22
120 400
SRISAILAM VTPS IV 2 D/C 213.000 TWIN MOOSE
0.00 0.00 515 0.555 118.2 118.22 118.22
121 400
VTPS IV VIJAYAWADA 1 D/C 18.660 TWIN MOOSE
0.00 0.00 515 0.555 10.4 10.36 10.36
122 400
VTPS IV VIJAYAWADA 1 D/C 18.660 TWIN MOOSE
0.00 0.00 515 0.555 10.4 10.36 10.36
123 400
VEMAGIRI GMR 1 D/C 1.760 TWIN MOOSE
0.00 0.00 515 0.555 1.0 0.98 0.98
124 400
VEMAGIRI GMR 2 D/C 1.760 TWIN MOOSE
0.00 0.00 515 0.555 1.0 0.98 0.98
125 400
VEMAGIRI GOUTAMI CCPP 1 D/C 39.000 TWIN MOOSE
0.00 0.00 515 0.555 21.6 21.65 21.65
126 400
VEMAGIRI GOUTAMI CCPP 2 D/C 39.000 TWIN MOOSE
0.00 0.00 515 0.555 21.6 21.65 21.65
127 400
VEMAGIRI GVK(JPD) 1 D/C 6.840 TWIN MOOSE
0.00 0.00 515 0.555 3.8 3.80 3.80
128 400
VEMAGIRI GVK(JPD) 2 D/C 6.840 TWIN MOOSE
0.00 0.00 515 0.555 3.8 3.80 3.80
APTRANSCO
NLDC 2012 REACTIVE POWER MANAGEMENT-a resource handbook 21 OF 26
ANNEXURE 3
ESTIMATED MVAR RELIEF AVAILABLE WHEN LINE IS OPENED
SOUTHERN REGION
Sl.
No
Voltage
in kV
FROM TO
CKT
ID
Ckt. Type
(Tower)
Line
Length (in
km)
Type of
conductor
From End
Shunt
Reactor
rated for
400kV
From End
reactor used as
Bus Reactor
(Yes=1, No=-1)
To End
Shunt
Reactor
rated for
400kV
To End
reactor used
as Bus
Reactor
(Yes=1, No=-
1)
SIL
Line
charging
Mvar/km
Total Line
Charging
Mvar of the
line
MVAR relief
available
when line is
opened
MVAR relief
available when line
is opened & Line
Reactor is used as
Bus Reactor
Remarks
129 400
VEMAGIRI KONASEEMA 1 D/C 26.010 TWIN MOOSE
0.00 0.00 515 0.555 14.4 14.44 14.44
130 400
VEMAGIRI KONASEEMA 2 D/C 26.010 TWIN MOOSE
0.00 0.00 515 0.555 14.4 14.44 14.44
131 400
VIJAYAWADA VEMAGIRI 1 D/C 195.410 TWIN MOOSE
0.00 0.00 515 0.555 108.5 108.45 108.45
132 400
VIJAYAWADA VEMAGIRI 2 D/C 195.410 TWIN MOOSE
0.00 0.00 515 0.555 108.5 108.45 108.45
133 400
WARANGAL BOOPALAPPALLI 1 D/C 45.620 TWIN MOOSE
0.00 0.00 515 0.555 25.3 25.32 25.32
134 400
WARANGAL BOOPALAPPALLI 2 D/C 45.620 TWIN MOOSE
0.00 0.00 515 0.555 25.3 25.32 25.32
135 400
BTPS JSW TORANAGALLU 1 S/C 14.000 TWIN MOOSE
45.35 -1 0.00 515 0.555 7.8 -37.58 -37.58
136 400
JSW TORANAGALLU GUTTUR 1 S/C 146.000 TWIN MOOSE
0.00 45.35 1 515 0.555 81.0 35.68 81.03
137 400
GUTTUR HIRIYUR 1 D/C 100.000 DRAKE
45.35 1 0.00 515 0.555 55.5 10.15 55.50
138 400
GUTTUR HIRIYUR 2 D/C 100.000 DRAKE
45.35 1 0.00 515 0.555 55.5 10.15 55.50
139 400
HASSAN NELMANGALA 1 * D/C 213.000 TWIN MOOSE
0.00 45.35 1 515 0.555 118.2 72.86 118.22
140 400
HIRIYUR NELMANGALA 1 D/C 160.000 DRAKE
0.00 45.35 1 515 0.555 88.8 43.45 88.80
141 400
HIRIYUR NELMANGALA 2 D/C 160.000 DRAKE
0.00 45.35 1 515 0.555 88.8 43.45 88.80
142 400
HOODY NELMANGALA S/C 70.000 TWIN MOOSE
0.00 0.00 515 0.555 38.9 38.85 38.85
143 400
MUNIRABAD GUTTUR S/C 118.000 TWIN MOOSE
0.00 0.00 515 0.555 65.5 65.49 65.49
144 400
RAICHUR BTPS S/C 151.400 TWIN MOOSE
0.00 0.00 515 0.555 84.0 84.03 84.03
145 400
TALAGUPPA HASSAN 1 * D/C 284.000 TWIN MOOSE
45.35 1 0.00 515 0.555 157.6 112.27 157.62
146 400
TALAGUPPA NELMANGALA 2 D/C 350.000 TWIN MOOSE
45.35 1 45.35 1 515 0.555 194.3 103.55 194.25
147 400
NEYVELI_TS2 NEYVELI_TS2 EXP 1 S/C 1.400 TWIN MOOSE
0.00 0.00 515 0.555 0.8 0.78 0.78
19267 1103.9 1910.2 10825.2 7811.1 9597.1
NLC
TOTAL
KPTCL
NLDC 2012 REACTIVE POWER MANAGEMENT-a resource handbook 22 OF 26
ANNEXURE 3
ESTIMATED MVAR RELIEF AVAILABLE WHEN LINE IS OPENED
EASTERN REGION
Sl.
No
Voltage
in kV
FROM TO
CKT
ID
Ckt. Type
(Tower)
Line
Length
(in km)
Type of
conductor
From End
Shunt
Reactor
rated for
400kV
From End reactor
used as Bus
Reactor (Yes=1,
No=-1)
To End
Shunt
Reactor
rated for
400kV
To End reactor
used as Bus
Reactor
(Yes=1, No=-1)
SIL
Line
charging
Mvar/km
Total Line
Charging
Mvar of the
line
MVAR relief
available
when line is
opened
MVAR relief
available when
line is opened &
Line Reactor is
used as Bus
Reactor
*
Remarks
1 400 ARAMBAGH BIDHANNAGAR (WB) 1 80 Twin Moose 0.00 0.00 515 0.555 44.4 44.40 44.40
2 400 BAKRESWAR ARAMBAGH 1 130 Twin Moose 45.35 -1 0.00 515 0.555 72.2 26.80 26.80
3 400 BARIPADA PG KOLAGHAT (WB) 1 174 Twin Moose 0.00 0.00 515 0.555 96.6 96.57 96.57
4 400 DSTPS MEZIA 1 32 Twin Moose 0.00 0.00 515 0.555 17.8 17.76 17.76
5 400 INDRAVATI (PG) INDRAVATI (OHPC) 1 1 Twin Moose 0.00 0.00 515 0.555 0.6 0.56 0.56
6 400 JEERAT BAKRESWAR 1 162 Twin Moose 45.35 -1 0.00 515 0.555 89.9 44.56 44.56
7 400 KTPP JEERAT 1 130 Twin Moose 0.00 0.00 515 0.555 72.2 72.15 72.15
8 400 KTPS ARAMBAGH 1 75 Twin Moose 0.00 0.00 515 0.555 41.6 41.63 41.63
9 400 MERAMUNDALI MENDHASAL 1 90 Twin Moose 0.00 0.00 515 0.555 50.0 49.95 49.95 CHARGED AT 220KV
10 400 MERAMUNDALI MENDHASAL I 1 100 Twin Moose 0.00 0.00 515 0.555 55.5 55.50 55.50
11 400 PARULIA(PG) BIDHANNAGAR (WB) 1 11 Twin Moose 45.35 -1 0.00 515 0.555 6.1 -39.25 -39.25 CHARGED AT 220KV
12 400 PATRATU TENUGHAT 1 53 Twin Moose 0.00 0.00 515 0.555 29.4 29.42 29.42 CHARGED AT 220KV
13 400 PPSP ARAMBAGH 1 210 Twin Moose 0.00 0.00 515 0.555 116.6 116.55 116.55
14 400 PPSP ARAMBAGH 2 210 Twin Moose 0.00 0.00 515 0.555 116.6 116.55 116.55
15 400 PPSP BIDHANNAGAR (WB) 1 185 Twin Moose 0.00 0.00 515 0.555 102.7 102.68 102.68
16 400 RENGALI BARIPADA 1 240 Twin Moose 57.14 -1 0.00 515 0.555 133.2 76.06 76.06
17 400 BARIPADA MENDHASAL 1 273 Twin Moose 57.14 -1 0.00 515 0.555 151.5 94.37 94.37
18 400 BARIPADA MENDHASAL 2 273 Twin Moose 57.14 -1 0.00 515 0.555 151.5 94.37 94.37
CENTRAL SECTOR
19 400 BARH PATNA I 1 94 Quad Moose 0.00 45.35 -1 687
0.740
69.6 24.21 24.21
20 400 BARH PATNA II 1 94 Quad Moose 0.00 45.35 -1 687
0.740
69.6 24.21 24.21
21 400 BIHARSHARIFF MUZAFFARPUR 2 130 Twin Moose 0.00 0.00 515 0.555 72.2 72.15 72.15
22 400 BIHARSHARIFF SASARAM - I 1 195 Twin Moose 0.00 57.14 -1 515 0.555 108.2 51.08 51.08
23 400 BIHARSHARIFF SASARAM - II 2 195 Twin Moose 0.00 57.14 -1 515 0.555 108.2 51.08 51.08
24 400 BIHARSHARIFF (BSEB) TENUGHAT (JSEB) 1 182 Twin Moose 0.00 45.35 -1 515 0.555 101.0 55.66 55.66 CHARGED AT 220KV
25 400 FARAKKA KAHALGAON - I 1 95 Twin Moose 0.00 0.00 515 0.555 52.7 52.73 52.73
26 400 FARAKKA KAHALGAON - II 2 95 Twin Moose 0.00 0.00 515 0.555 52.7 52.73 52.73
27 400 FARAKKA KAHALGAON - III 1 95 Twin Moose 0.00 0.00 515 0.555 52.7 52.73 52.73
28 400 FARAKKA KAHALGAON - IV 2 95 Twin Moose 0.00 0.00 515 0.555 52.7 52.73 52.73
29 400 FARAKKA JEERAT 1 238 Twin Moose 0.00 45.35 -1 515 0.555 132.1 86.74 86.74
30 400 FARAKKA SAGARDIH 1 67 Twin Moose 0.00 0.00 515 0.555 37.2 37.19 37.19
31 400 FRAKKA MALDA 1 40 Twin Moose 0.00 0.00 515 0.555 22.2 22.20 22.20
STATE SECTOR
NLDC, 2012 REACTIVE POWER MANAGEMENT-a resource handbook 23OF 26
ANNEXURE 3
ESTIMATED MVAR RELIEF AVAILABLE WHEN LINE IS OPENED
EASTERN REGION
Sl.
No
Voltage
in kV
FROM TO
CKT
ID
Ckt. Type
(Tower)
Line
Length
(in km)
Type of
conductor
From End
Shunt
Reactor
rated for
400kV
From End reactor
used as Bus
Reactor (Yes=1,
No=-1)
To End
Shunt
Reactor
rated for
400kV
To End reactor
used as Bus
Reactor
(Yes=1, No=-1)
SIL
Line
charging
Mvar/km
Total Line
Charging
Mvar of the
line
MVAR relief
available
when line is
opened
MVAR relief
available when
line is opened &
Line Reactor is
used as Bus
Reactor
*
Remarks
32 400 FRAKKA MALDA 2 40 Twin Moose 0.00 0.00 515 0.555 22.2 22.20 22.20
33 400 FRAKKA PARULIA-I 1 150 Twin Moose 45.35 -1 0.00 515 0.555 83.3 37.90 37.90
34 400 FRAKKA PARULIA-II 1 146 Twin Moose 0.00 0.00 515 0.555 81.0 81.03 81.03
35 400 INDRAVATI RENGALI 1 356 Twin Moose 45.35 -1 45.35 -1 515 0.555 197.6 106.88 106.88
36 400 JAMSHEDPUR ROURKELA - I 1 174 Twin Moose 0.00 45.35 -1 515 0.555 96.6 51.22 51.22
37 400 JAMSHEDPUR ROURKELA - II 2 174 Twin Moose 0.00 45.35 -1 515 0.555 96.6 51.22 51.22
38 400 JEYPORE INDRAVATI 1 72 Twin Moose 0.00 0.00 515 0.555 40.0 39.96 39.96
39 400 JEYPORE MERAMUNDALI (OPTCL) 1 456 Twin Moose 72.56 -1 72.56 1 515 0.555 253.1 107.96 180.52
40 400 KAHALGAON BIHARSHARIFF - I 1 201 Twin Moose 0.00 45.35 -1 515 0.555 111.6 66.20 66.20
41 400 KAHALGAON BIHARSHARIFF - II 2 201 Twin Moose 0.00 45.35 -1 515 0.555 111.6 66.20 66.20
42 400 KAHALGAON BIHARSHARIFF - III 1 166 Twin Moose 0.00 0.00 515 0.746 123.8 123.84 123.84
43 400 KAHALGAON BIHARSHARIFF - IV 2 166 Twin Moose 0.00 0.00 515 0.746 123.8 123.84 123.84
44 400 KAHALGAON PATNA I 1 257 Quad Moose 0.00 45.35 -1 687
0.740
190.2 144.83 144.83
45 400 KhSTPP BARH 1 217 Quad Moose 0.00 0.00 687
0.740
160.6 160.58 160.58
46 400 MAITHON JAMSHEDPUR - II 1 153 Twin Moose 0.00 0.00 515 0.555 84.9 84.92 84.92
47 400 MAITHON KHALGAON - I 1 172 Twin Moose 45.35 -1 0.00 515 0.555 95.5 50.11 50.11
48 400 MAITHON KHALGAON - II 2 172 Twin Moose 45.35 -1 0.00 515 0.555 95.5 50.11 50.11
49 400 MAITHON RANCHI I 1 200 Twin Moose 45.35 -1 45.35 -1 515 0.555 111.0 20.30 20.30
50 400 MAITHON RANCHI II 2 200 Twin Moose 45.35 -1 45.35 -1 515 0.555 111.0 20.30 20.30
51 400 MAITHON MEZIA 1 84 Twin Moose 0.00 0.00 515 0.555 46.6 46.62 46.62
52 400 MAITHON MAITHON RB 2 31 Twin Moose 0.00 0.00 515 0.555 17.2 17.21 17.21
53 400 MALBASE BINAGURI 1 125.1 Twin Moose 0.00 0.00 515 0.555 69.4 69.43 69.43
54 400 MALDA PURNEA I 1 167 Twin Moose 57.14 -1 0.00 515 0.555 92.7 35.54 35.54
55 400 MALDA PURNEA II 2 167 Twin Moose 57.14 -1 0.00 515 0.555 92.7 35.54 35.54
56 400 MEJIA JAMSHEDPUR I 1 168 Twin Moose 0.00 0.00 515 0.555 93.2 93.24 93.24
57 400 PARULIA JAMSHEDPUR 1 177 Twin Moose 0.00 0.00 515 0.555 98.2 98.24 98.24
58 400 PURNEA BINAGURI - I 1 168 Twin Moose 57.14 -1 0.00 515 0.555 93.2 36.10 36.10
59 400 PURNEA BINAGURI - II 2 168 Twin Moose 57.14 -1 0.00 515 0.555 93.2 36.10 36.10
60 400 PURNEA BINAGURI - III 1 160 Quad Moose 0.00 0.00 687
0.740
118.4 118.40 118.40
61 400 PURNEA BINAGURI - IV 2 160 Quad Moose 0.00 0.00 687
0.740
118.4 118.40 118.40
62 400 PURNEA MUZAFFARPUR 1 240 Quad Moose 57.14 -1 57.14 -1 687
0.740
177.6 63.31 63.31
63 400 PURNEA MUZAFFARPUR 2 240 Quad Moose 57.14 -1 57.14 -1 687
0.740
177.6 63.31 63.31
64 400 RANCHI ROURKELA 2 145 Twin Moose 0.00 0.00 515 0.555 80.5 80.48 80.48
65 400 SUBHASGRAM(PG) JEERAT(WB) 1 70 Twin Moose 0.00 0.00 515 0.555 38.9 38.85 38.85
66 400 TALA BINAGURI I 1 115 Twin Moose 0.00 57.14 1 515 0.555 63.8 6.68 63.83
NLDC, 2012 REACTIVE POWER MANAGEMENT-a resource handbook 24OF 26
ANNEXURE 3
ESTIMATED MVAR RELIEF AVAILABLE WHEN LINE IS OPENED
EASTERN REGION
Sl.
No
Voltage
in kV
FROM TO
CKT
ID
Ckt. Type
(Tower)
Line
Length
(in km)
Type of
conductor
From End
Shunt
Reactor
rated for
400kV
From End reactor
used as Bus
Reactor (Yes=1,
No=-1)
To End
Shunt
Reactor
rated for
400kV
To End reactor
used as Bus
Reactor
(Yes=1, No=-1)
SIL
Line
charging
Mvar/km
Total Line
Charging
Mvar of the
line
MVAR relief
available
when line is
opened
MVAR relief
available when
line is opened &
Line Reactor is
used as Bus
Reactor
*
Remarks
67 400 TALA BINAGURI II 2 115 Twin Moose 0.00 57.14 1 515 0.555 63.8 6.68 63.83
68 400 TALA BINAGURI-IV 4 98 Twin Moose 0.00 57.14 1 515 0.555 54.4 -2.70 54.45
69 400 TEESTA-V BINAGURI 1 115 Twin Moose 0.00 0.00 515 0.555 63.8 63.83 63.83
70 400 TSTPP ROURKELA - I 1 171 Twin Moose 45.35 0.00 515 0.555 94.9 49.55 94.91
71 400 TSTPP ROURKELA - II 2 171 Twin Moose 45.35 0.00 515 0.555 94.9 49.55 94.91
72 400 TSTPP RENGALI - I 1 24 Twin Moose 0.00 0.00 515 0.555 13.3 13.32 13.32
73 400 TSTPP RENGALI - II 2 24 Twin Moose 0.00 0.00 515 0.555 13.3 13.32 13.32
74 400 TSTPP (NTPC) MERAMUNDALI (OPTCL) 1 51 Twin Moose 0.00 0.00 515 0.555 28.3 28.31 28.31
10871 1085.7 1016.8 6367.4 4264.9 4599.6
*
TOTAL
Utilization of line reactor as bus reactor necessitates arrangements for bypassing Neutral Grounding reactor(NGR) of line reactor. Work is in progress at many substations & this column is
therefore incomplete as of now
NLDC, 2012 REACTIVE POWER MANAGEMENT-a resource handbook 25OF 26
ANNEXURE 3
ESTIMATED MVAR RELIEF AVAILABLE WHEN LINE IS OPENED
NORTH EASTERN REGION
Sl.
No
Voltage
in kV
FROM TO
CKT
ID
Ckt. Type
(Towers)
Line
Length
(in km)
Type of
conductor
From End
Shunt Reactor
rated for
400kV
From End
reactor used as
Bus Reactor
(Yes=1, No=-1)
To End Shunt
Reactor rated
for 400kV
To End reactor
used as Bus
Reactor
(Yes=1, No=-1)
SIL
Line
charging
Mvar/km
Total Line
Charging
Mvar of
the line
MVAR relief
available
when line is
opened
MVAR relief
available when
line is opened &
Line Reactor is
used as Bus
Reactor
Remarks
A. POWERGRID
1 400 BALIPARA BONGAIGAON 1 D/C 289.72 Twin Moose 57.14 -1 45.35 -1 515 0.555 160.8 58.30 58.30
2 400 BALIPARA BONGAIGAON 2 D/C 289.72 Twin Moose 57.14 -1 45.35 -1 515 0.555 160.8 58.30 58.30
3 400 BALIPARA RANGANADI (NEEPCO) 1 D/C 166.34 Twin Moose 45.35 1 45.35 -1 515 0.555 92.3 1.62 46.97
4 400 BALIPARA RANGANADI (NEEPCO) 2 D/C 166.34 Twin Moose 45.35 1 45.35 -1 515 0.555 92.3 1.62 46.97
5 400 BALIPARA MISA 1 D/C 95.41 Twin Moose 45.35 -1 0.00 0 515 0.555 53.0 7.60 7.60
6 400 BALIPARA MISA 2 D/C 95.41 Twin Moose 0.00 0 0.00 0 515 0.555 53.0 52.95 52.95
1103 250.3 181.4 612.1 180.4 271.1

TOTAL
NLDC, 2012 REACTIVE POWER MANAGEMENT-a resource handbook 26 OF 26
ANNEXURE 4
400 and 765kV REACTORS INSTALLED CAPACITY-ALL INDIA LEVEL
NO. OF
REACTOR
TOTAL
MVAR
NO. OF
REACTOR
TOTAL
MVAR
NO. OF
REACTOR
TOTAL
MVAR
NO. OF
REACTOR
TOTAL
MVAR
NO. OF
REACTOR
TOTAL
MVAR
NO. OF
REACTOR
TOTAL
MVAR
NO. OF
REACTOR
TOTAL
MVAR
NO. OF
REACTOR
TOTAL
MVAR
NO. OF
REACTOR
TOTAL
MVAR
NO. OF
REACTOR
TOTAL
MVAR
1 240 0 0 0 0 1 240 2 480 0 0 0 0 0 0 0 0 0 0 0 0 720
2 100 0 0 1 110 0 0 0 0 0 0 0 0 0 0 0 0 2 200 0 0 310
3 125 5 625 0 0 2 250 0 0 0 0 0 0 1 125 0 0 0 0 0 0 1000
4 93 1 93 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 93
5 90 0 0 0 0 1 90 0 0 0 0 0 0 0 0 0 0 0 0 0 0 90
6 80 11 880 10 800 9 720 10 800 3 240 2 160 3 240 5 400 0 0 0 0 4240
7 72 0 0 1 72 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 72
8 63 6 378 20 1260 7 441 14 882 13 819 21 1323 3 189 24 1512 0 0 6 378 7182
9 50 26 1300 83 4150 20 1000 83 4150 9 450 43 2150 16 800 21 1050 5 250 8 400 15700
10 40 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
11 31.5 0 0 0 0 0 0 0 0 0 0 0 0 2 63 0 0 0 0 0 0 63
12 25 1 25 0 0 12 300 0 0 0 0 0 0 0 0 0 0 0 0 0 0 325
13 20 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2 40 0 0 40
14 12.5 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 4 50 0 0 50
15 16.67 0 0 0 0 0 0 0 0 3 50.01 0 0 0 0 0 0 0 0 0 0 50.01
16 2 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2 4 0 0 4
TOTAL 50 3301 115 6392 52 3041 109 6312 28 1559 66 3633 25 1417 50 2962 15 544 14 778 29939.01
TOTAL
MVAR
TOTAL
MVAR
TOTAL
MVAR
1 3301 6392 9693
2 3041 6312 9353
3 1559 3633 5192.01
4 1417 2962 4379
5 544 778 1322
6 9862 20077 29939 524 ALL INDIA
Sl.
No
Region
(A)
66
50
14
LINE REACTOR
165
161 109
50
170 354
75
29
SUMMARY OF REACTORS
94
BUS REACTOR LINE REACTOR
NO. OF REACTOR
TOTAL
TOTAL NO. OF
REACTOR
North Eastern
28
25
115 Northern
Western
Southern
Eastern
52
15
NO. OF REACTOR
NORTH EASTERN REGION EASTERN REGION
BUS REACTOR LINE REACTOR
WESTERN REGION SOUTHERN REGION
BUS REACTOR LINE REACTOR BUS REACTOR
400 & 765kV REACTORS INSTALLED CAPACITY
Sl.
No
REACTOR
CAAPCITY
IN MVAR
LINE REACTOR
NORTHERN REGION
BUS REACTOR LINE REACTOR
TOTAL
REACTOR
CAPACITY IN
MVAR
BUS REACTOR
NLDC, 2012 REACTIVE POWER MANAGEMENT-a resource handbook 1 OF 1
ANNEXURE 5
FAULT LEVEL OF SUBSTATIONS
MVA KA MVA KA MVA KA MVA KA
1 AKOLA 8357 12 8417 12 8326 12 8648 12
2 AMRELI 4596 7 4739 7 4371 6 4775 7
3 ASOJ 14532 21 15660 23 12771 18 16585 24
4 AURANGABAD 7636 11 7743 11 7531 11 7884 11
5 BABLESHWAR 12202 18 12610 18 11713 17 12935 19
6 BHADRAWATI 16698 24 16797 24 16785 24 17161 25
7 BHATAPARA 9412 14 9512 14 8935 13 8993 13
8 BHILAI 21664 31 22040 32 20999 30 21631 31
9 BHOPAL 12578 18 12841 19 11053 16 13928 20
10 BHUSAWAL 7828 11 7903 11 7905 11 8256 12
11 BINA 13082 19 13377 19 11631 17 14360 21
12 BINA-PG 13120 19 13415 19 11650 17 14401 21
13 BIRSINGPUR 6196 9 6325 9 5932 9 6518 9
14 BOISAR 13868 20 14531 21 14340 21 14862 21
15 CHANDRAPUR 18272 26 18394 27 18334 26 18795 27
16 CHORANIA 11270 16 11973 17 7660 11 10699 15
17 DABHOL 12963 19 14687 21 16392 24 17316 25
18 DAMOH 6368 9 6472 9 4969 7 5805 8
19 DEHGAM 14295 21 15760 23 12119 17 18848 27
20 DHULE 10680 15 11130 16 8262 12 11520 17
21 GANDHAR 12747 18 14363 21 9742 14 15181 22
22 GPEC 11320 16 12662 18 9131 13 13377 19
23 GWALIOR 10409 15 10547 15 10182 15 10856 16
24 HADALA 6420 9 6689 10 6227 9 6899 10
25 INDIRASAGAR 8448 12 8938 13 7321 11 11441 17
26 INDORE 11803 17 12190 18 10222 15 14172 20
27 ITARSI 14467 21 14792 21 14224 21 16717 24
28 JABALPUR 9700 14 9879 14 10184 15 10711 15
29 JAIGAD 6991 10 7581 11 10658 15 11309 16
30 JEJURI 8004 12 8593 12 8462 12 8812 13
31 JETPUR 4904 7 5069 7 4778 7 5216 8
32 JINDAL-B1 5780 8 5790 8 7286 11 7306 11
33 JINDAL-B2 2943 4 2958 4 6900 10 6917 10
34 KALWA 15019 22 16923 24 16716 24 17955 26
35 KARAD 10338 15 11900 17 11559 17 12299 18
36 KASOR 9903 14 10734 15 5885 8 11026 16
37 KATNI 4955 7 5043 7 5283 8 5512 8
38 KHANDWA 9975 14 10179 15 7933 11 12048 17
39 KHAPARKHEDA 13794 20 13914 20 12162 18 12701 18
40 KHARGHAR 11831 17 13097 19 13001 19 13820 20
41 KOLHAPUR 6731 10 7266 10 7148 10 7389 11
42 KORADI 14875 21 15021 22 13828 20 14587 21
43 KORBA NTPC 20980 30 21820 31 25119 36 25365 37
44 KORBA(W) 15920 23 16875 24 18061 26 18163 26
45 KOYNA 11649 17 14935 22 14504 21 16469 24
STATION NAME Sl.No
MONSOON OFF PEAK MONSOON PEAK WINTER OFF PEAK WINTER PEAK
WESTERN REGION
NLDC 2012 REACTIVE POWER MANAGEMENT-a resource handbook 1 of 7
ANNEXURE 5
FAULT LEVEL OF SUBSTATIONS
MVA KA MVA KA MVA KA MVA KA
46 LANCO PATHADI 10141 15 10276 15 10716 15 10760 16
47 LONIKHAND 12232 18 13478 19 13178 19 14028 20
48 MAPUSA 4150 6 4291 6 4266 6 4330 6
49 MUNDRA 7715 11 8441 12 8579 12 9196 13
50 NAGDA 9334 13 9359 14 7626 11 12726 18
51 NAGOTHANE 10459 15 11263 16 11492 17 11918 17
52 NEW KOYNA 12937 19 16231 23 16035 23 17859 26
53 NSPCL 18770 27 19000 27 19329 28 20049 29
54 PADGHE 18019 26 19935 29 19595 28 21049 30
55 PARLI 9286 13 9524 14 8928 13 9807 14
56 PIRANA(T) 4308 6 4376 6 -- -- 11698 17
57 PIRANA_PG 4240 6 4307 6 7735 11 12109 17
58 RAIGARH 15827 23 15951 23 17273 25 17645 25
59 RAIPUR 23634 34 24041 35 24458 35 25684 37
60 RAJGARH 7097 10 7208 10 3365 5 9401 14
61 RANCHODPURA 10386 15 11078 16 7922 11 10054 15
62 SAMI 5602 8 6563 9 6381 9 7212 10
63 SATNA 9470 14 9739 14 9673 14 10663 15
64 SATPURA 12843 19 13030 19 12925 19 13825 20
65 SEONI (400) 14106 20 14219 21 12883 19 14785 21
66 SEONI (765) 12392 9 12420 9 11409 9 12769 10
67 SHOLAPUR 5335 8 5478 8 5219 8 5569 8
68 SIPAT (400) 11866 17 11629 17 9501 14 11766 17
69 SIPAT (765) 12636 10 12522 9 11270 9 12723 10
70 SOJA 11322 16 12136 18 10543 15 13366 19
71 SSP 11815 17 13570 20 7551 11 14151 20
72 SUGEN 15869 23 16818 24 13172 19 17054 25
73 TARAPUR APS 14341 21 15037 22 14886 21 15426 22
74 UKAI 4629 7 4744 7 4518 7 4806 7
75 VAPI 8611 12 8821 13 8490 12 8852 13
76 VINDHYACHAL (W) 15800 23 16024 23 19299 28 19750 29
77 WANAKBORI 12672 18 13389 19 11504 17 14546 21
78 WARDHA 6640 10 6658 10 6530 9 6754 10
79 ZERDA 6572 9 6732 10 6497 9 6862 10
80 ARAMBAG 10903 16 12078 17 10816 16 11905 17
81 BAKRESHWAR 7674 11 7906 11 7484 11 7865 11
82 BARH 5880 8 5933 9 8233 12 8388 12
83 BARIPADA 6975 10 7064 10 6987 10 7103 10
84 BIDHAN NAGAR 13013 19 14433 21 12936 19 14227 21
85 BIHARSHARIFF 15663 23 15832 23 16457 24 16836 24
86 BINAGURI 11323 16 11381 16 9122 13 9760 14
87 DURGAPUR STPS 6620 10 6594 10 6564 9 6602 10
88 FARAKKA 21605 31 22057 32 21348 31 22070 32
89 INDRAVATI GRIDCO 3855 6 4527 7 3876 6 4918 7
Sl.No
MONSOON OFF PEAK WINTER PEAK MONSOON PEAK WINTER OFF PEAK
EASTERN REGION
STATION NAME
NLDC 2012 REACTIVE POWER MANAGEMENT-a resource handbook 2 of 7
ANNEXURE 5
FAULT LEVEL OF SUBSTATIONS
MVA KA MVA KA MVA KA MVA KA
90 INDRAVATI PG 3902 6 4582 7 3924 6 4974 7
91 JAMSHEDPUR 11432 17 11431 16 11544 17 11653 17
92 JEERAT 9246 13 9422 14 9169 13 9463 14
93 JEYPORE 3992 6 4785 7 4014 6 5177 7
94 JINDAL 9116 13 9323 13 9342 13 7679 11
95 KAHALGAON 21255 31 21347 31 21868 32 22381 32
96 KODERMA -- -- -- -- 7359 11 7451 11
97 KOLAGHAT 10629 15 11121 16 10562 15 11084 16
98 MAITHON 13543 20 13523 20 13320 19 13471 19
99 MALDA 14261 21 14430 21 13834 20 14216 21
100 MALBASE 7483 11 7492 11 5787 8 5992 9
101 MEJIA 6913 10 6884 10 6864 10 6897 10
102 MENDHASAL 7154 10 7267 10 7198 10 7367 11
103 MERAMUNDALI 13294 19 13775 20 13859 20 14955 22
104 MPL 8610 12 8585 12 6546 9 6587 10
105 MUZAFFARPUR 12864 19 13048 19 12084 17 12382 18
106 PARULIA 14645 21 15842 23 14547 21 15704 23
107 PATNA 8836 13 8938 13 8674 13 8844 13
108 PURNEA 12528 18 12653 18 10552 15 11015 16
109 PURULIA PS 6156 9 9177 13 6173 9 8392 12
110 PUSAULI_E 9602 14 9713 14 9721 14 9887 14
111 RANCHI 9833 14 9517 14 7841 11 7923 11
112 RENGALI 14850 21 15379 22 15787 23 16612 24
113 ROURKELA 15928 23 15915 23 17233 25 17398 25
114 SAGARDIGHI 10628 15 10820 16 10467 15 10738 15
115 STERLITE 10177 15 10172 15 10064 15 10039 14
116 SUBHAS GRAM 6116 9 6160 9 6090 9 6182 9
117 TALA 8563 12 8571 12 6247 9 6476 9
118 TALCHER STG 2 19014 27 19713 28 20833 30 22070 32
119 TISTA 4981 7 4983 7 3523 5 4822 7
120 BALIPARA 3460 5 3447 5 4617 7 3500 5
121 BONGAIGAON 5046 7 5049 7 5185 7 4887 7
122 MISA 3087 4 2850 4 3794 5 3144 5
123 RANGANADI 2400 3 2384 3 4083 6 2424 3
124 ALMATTY 7245 10 7433 11 6099 9 6173 9
125 ARASUR 4871 7 5134 7 4919 7 5185 7
126 BELLARY TPS 10373 15 10577 15 10553 15 10631 15
127 BHADRAWATI_S 4316 6 4304 6 4431 6 4435 6
128 BUPAL PALLY 8001 12 8079 12 7582 11 7634 11
129 CHITTOR 5956 9 6041 9 5776 8 5827 8
130 CUDDAPAH 8347 12 8581 12 8134 12 8266 12
NORTH EASTERN REGION
WINTER OFF PEAK WINTER PEAK
Sl.No STATION NAME
MONSOON OFF PEAK MONSOON PEAK
SOUTHERN REGION
NLDC 2012 REACTIVE POWER MANAGEMENT-a resource handbook 3 of 7
ANNEXURE 5
FAULT LEVEL OF SUBSTATIONS
MVA KA MVA KA MVA KA MVA KA
131 DICHPALLY 3453 5 3431 5 3475 5 3466 5
132 GAJWEL 6744 10 6799 10 6880 10 6936 10
133 GAZUWAKA EAST 1965 3 2945 4 1967 3 3072 4
134 GAZUWAKA SOUTH 11645 17 12536 18 12883 19 13114 19
135 GHANAPUR 13190 19 14064 20 14068 20 14831 21
136 GMR 11951 17 14026 20 15452 22 15807 23
137 GOOTY 12175 18 12816 18 11993 17 12374 18
138 GOTAMI 8625 12 9949 14 10631 15 10781 16
139 GUTTUR 9631 14 10504 15 10157 15 10456 15
140 GVK 11357 16 13167 19 14365 21 14670 21
141 HASSAN 3986 6 3994 6 5779 8 5789 8
142 HIRIYUR 7831 11 8177 12 7807 11 7848 11
143 HOODY 10576 15 11232 16 10307 15 10735 15
144 HOSUR 8730 13 9091 13 8477 12 8754 13
145 JINDAL 10587 15 10808 16 10865 16 10952 16
146 KAIGA 7106 10 8105 12 8168 12 8414 12
147 KALIVNTHAPATTU 7084 10 7274 10 6651 10 6758 10
148 KALPAKA 12001 17 12934 19 13306 19 13549 20
149 KARAIKUDI 5567 8 5873 8 5637 8 5924 9
150 KHAMMAM 14851 21 15717 23 14207 21 14696 21
151 KOLAR 10880 16 11590 17 10593 15 11078 16
152 KONASEEMA 9500 14 10946 16 12006 17 12202 18
153 KOTHAGUDEM TPS 10297 15 10551 15 8398 12 8509 12
154 KUDAMKULAM -- -- 46 6699 4514 7 4718 7
155 KURNOOL 8698 13 9131 13 8513 12 8921 13
156 LANCO 11901 17 12897 19 13722 20 14226 21
157 MADURAI 8071 12 8792 13 8025 12 8692 13
158 MAHBOOBNAGAR 6874 10 7176 10 6992 10 7030 10
159 MALKAPURAM 8402 12 8611 12 8593 12 8762 13
160 MAMIDIPALLY 11631 17 12559 18 11758 17 12649 18
161 MUNIRABAD 6571 9 6729 10 6584 10 6603 10
162 MYSORE 5619 8 5695 8 6418 9 6467 9
163 NARENDRA 6862 10 7479 11 7373 11 7559 11
164 NEELAMANGALA 11541 17 12497 18 11300 16 11941 17
165 NELLORE 5920 9 5954 9 5512 8 5526 8
166 NEYVELI 10629 15 12351 18 10598 15 12320 18
167 NEYVELI 2EX4 10055 15 11567 17 10034 14 11549 17
168 NEYVELI1 EX4 8778 13 10165 15 8782 13 10170 15
169 PONDCHERRY 6766 10 7120 10 6316 9 6674 10
170 PUGALURU 6702 10 7189 10 6700 10 7176 10
171 RAICHUR TPS 12940 19 13586 20 12589 18 12919 19
172 RAMAGUNDAM 17481 25 18274 26 23845 34 25233 36
173 SALEM 10392 15 11249 16 10206 15 11056 16
174 SIMHADRI 11870 17 12769 18 13127 19 13361 19
175 SIMHDRI 10948 16 11740 17 12030 17 12225 18
WINTER OFF PEAK WINTER PEAK
Sl.No STATION NAME
MONSOON OFF PEAK MONSOON PEAK
NLDC 2012 REACTIVE POWER MANAGEMENT-a resource handbook 4 of 7
ANNEXURE 5
FAULT LEVEL OF SUBSTATIONS
MVA KA MVA KA MVA KA MVA KA
176 SOMANAHALLI 10634 15 11373 16 10392 15 10887 16
177 SRI PERUMUBUDUR 8716 13 9045 13 7945 11 8136 12
178 SRI SALEM 9561 14 11643 17 9191 13 11721 17
179 SVCHTRAM 6424 9 6548 9
180 TALAPALLY 12845 19 13676 20 13195 19 13727 20
181 TALGUPPA 3637 5 3737 5 3736 5 3757 5
182 TIRUNELVELLI 6122 9 6551 9 6175 9 6571 9
183 TRICHI 6910 10 7438 11 6949 10 7464 11
184 TRICHUR 5056 7 5397 8 5283 8 5561 8
185 TRIVANDRUM 3869 6 4092 6 4009 6 4210 6
186 UDUMALPET 8600 12 9557 14 8690 13 9510 14
187 VALLUR 6075 9 6155 9
188 VEMAGIRI 12200 18 14343 21 15840 23 16216 23
189 VIJAYWADA 13980 20 15481 22 16482 24 17256 25
190 VTS 13160 19 14473 21 15349 22 16107 23
191 WARANGAL 9815 14 9988 14 9659 14 9781 14
192 ANPARA C 6080 5 6074 5 6115 5 6193 5
193 ABDULLAPUR 13212 19 13541 20 13493 19 14713 21
194 AGRA (UP) 15072 22 15180 22 14938 22 15439 22
195 AGRA PG 18848 27 18979 27 18515 27 19297 28
196 ALLAHABAD 15501 22 15573 22 15409 22 15684 23
197 AMRITSAR 6976 10 7113 10 6096 9 6834 10
198 ANPARA 20654 30 20590 30 21039 30 21374 31
199 AURYA 13317 19 13375 19 13390 19 13694 20
200 AZAMGARH 12260 18 12407 18 12265 18 12509 18
201 BAGHLIHAR 6948 10 6961 10 4739 7 6127 9
202 BAHADURGARH 14182 20 14289 21 13514 20 14173 20
203 BALIA 765 Kv 13825 20 13987 20 13781 20 14085 20
204 BALLABHGARH 28766 42 28901 42 26973 39 28554 41
205 BAMNAULI 23696 34 23869 34 22322 32 23660 34
206 BARELI 14451 21 14516 21 13597 20 14280 21
207 BARELI-PG 15452 22 15521 22 14542 21 15272 22
208 BARMER 6752 10 6752 10 6407 9 6447 9
209 BASPA 7452 11 8196 12 8294 12 10786 16
210 BASSI 12931 19 12991 19 12743 18 13039 19
211 BAWANA 29473 43 29779 43 26966 39 29362 42
212 BHILWARA 4019 6 3998 6 3987 6 3987 6
213 BHINMAL 4641 7 4678 7 4631 7 4685 7
214 BHIWADI 14716 21 14803 21 14024 20 14574 21
215 BHIWANI 13279 19 13373 19 12674 18 13315 19
216 BIKANER 4297 6 4298 6 4311 6 4328 6
217 CHABRA 4785 7 4751 7 4462 6 4478 6
Sl.No STATION NAME
MONSOON OFF PEAK MONSOON PEAK WINTER OFF PEAK WINTER PEAK
NORTHERN REGION
NLDC 2012 REACTIVE POWER MANAGEMENT-a resource handbook 5 of 7
ANNEXURE 5
FAULT LEVEL OF SUBSTATIONS
MVA KA MVA KA MVA KA MVA KA
218 CHAKAN 8783 13 9343 13 9212 13 9567 14
219 CHAMER-1 9447 14 9253 13 5262 8 8802 13
220 CHAMER-2 9189 13 8819 13 4744 7 7647 11
221 CHAMERA-POL 9088 13 8729 13 -- -- -- --
222 DADRI-HVDC 32652 47 32756 47 28876 42 30923 45
223 DADRI-NCR 33594 48 33704 49 29619 43 31763 46
224 DAULATABAD 5894 9 5904 9 7479 11 7626 11
225 DEHAR 6757 10 6900 10 4578 7 5432 8
226 DULHASTI 4332 6 4335 6 2575 4 3752 5
227 FATEHABAD 11923 17 11964 17 11331 16 11800 17
228 GORAKHPUR 12512 18 12700 18 12379 18 12666 18
229 GORAKPUR_UP 10068 15 10228 15 10065 15 10274 15
230 GREATER NOIDA 24617 36 24685 36 22772 33 23983 35
231 GURGAON 12842 19 12883 19 12677 18 13039 19
232 HERAPUR 11648 17 11691 17 11369 16 11583 17
233 HINDAUN 4026 6 4046 6 3112 4 3132 5
234 HISSAR 18880 27 19053 28 17567 25 18890 27
235 JALANDHAR 14194 20 14310 21 10347 15 13246 19
236 JHAJAR_N 7712 11 7873 11
237 JHAJJAR 11784 17 11825 17 11483 17 11831 17
238 JODHPUR 8909 13 8910 13 8827 13 8905 13
239 KAITHAL 12700 18 12807 18 12130 18 12891 19
240 KANKROLI 8397 12 8416 12 8353 12 8456 12
241 KANPUR 21935 32 21988 32 21580 31 22227 32
242 KANPUR-BALLABGARH-FSC22386 3 2377 3 2458 4 2425 4
243 KANPUR-BALLABGARH-FSC32386 3 2377 3 2458 4 2425 4
244 KARCHAM WANGTOO 8049 12 8976 13 9325 13 12490 18
245 KASHIPUR 5277 8 5290 8 5119 7 5266 8
246 KHEDAR 11671 17 11685 17 11142 16 11510 17
247 KIRORI 10972 16 10986 16 10509 15 10836 16
248 KISHENPUR 10721 15 10771 16 6568 9 9232 13
249 KOTA 7432 11 7409 11 6933 10 6986 10
250 KOTESHWAR 7676 11 7673 11 5659 8 8698 13
251 LUCKNOW_UP 13130 19 13243 19 12945 19 13281 19
252 LUCKNOW-PG 17289 25 17453 25 16902 24 17413 25
253 LUDHIANA 10823 16 11014 16 9682 14 10739 16
254 MAHARANI BAGH 17175 25 17205 25 16984 25 17574 25
255 MAINPURI 8144 12 8204 12 8218 12 8367 12
256 MALERKOTA 10955 16 11150 16 10196 15 11075 16
257 MANDOLA 31517 45 31733 46 27997 40 30701 44
258 MAU 13535 20 13692 20 13506 19 13799 20
259 MEERUT 20758 30 20763 30 17533 25 20277 29
260 MERTA 9907 14 9902 14 9648 14 9748 14
261 MOGA 15319 22 15469 22 12076 17 14495 21
WINTER OFF PEAK WINTER PEAK
Sl.No STATION NAME
MONSOON OFF PEAK MONSOON PEAK
NLDC 2012 REACTIVE POWER MANAGEMENT-a resource handbook 6 of 7
ANNEXURE 5
FAULT LEVEL OF SUBSTATIONS
MVA KA MVA KA MVA KA MVA KA
262 MUNDKA 25434 37 25642 37 23747 34 25370 37
263 MURADABAD 10916 16 10963 16 10353 15 10790 16
264 MURADNAGAR 19412 28 19446 28 18070 26 19031 27
265 MUZAFFARNAGAR 14815 21 14679 21 13151 19 14149 20
266 NALLAGARH 9989 14 10392 15 10005 14 11465 17
267 NATHPA 8738 13 9628 14 10125 15 14098 20
268 OBRA 12790 18 12756 18 12328 18 12513 18
269 PANIPAT 11358 16 11388 16 10859 16 11281 16
270 PANKI 21278 31 21334 31 20943 30 21561 31
271 PATIALA 10729 15 10952 16 10340 15 11192 16
272 PUSAULI_N 9602 14 9713 14 9721 14 9887 14
273 RAJWEST 7438 11 7437 11 6961 10 7007 10
274 RAPS_C 6963 10 6951 10 6767 10 6825 10
275 RATANGAR 7477 11 7485 11 7576 11 7631 11
276 RIHAND-G 17333 25 17302 25 16806 24 16977 25
277 RIHAN-HV 17109 25 17079 25 16593 24 16761 24
278 RISHIKESH 5792 8 5795 8 5480 8 5717 8
279 ROORKEE 7370 11 7364 11 6890 10 7227 10
280 SARNATH 12930 19 13021 19 12957 19 13180 19
281 SHOLAPUR pg 3010 4 3076 4 3026 4 3094 4
282 SHUJALPR -- -- 7374 11
283 SHREE CEMENT 5060 7 5054 7 5720 8 5762 8
284 SINGRAULI 23074 33 23010 33 22087 32 22365 32
285 SONEP-PG 9528 14 9617 14 10861 16 11337 16
286 SULTANPUR 7706 11 7814 11 7734 11 7866 11
287 SURATGARH 8009 12 8008 12 8533 12 8592 12
288 TEHRI 8518 12 8510 12 5149 7 8488 12
289 TEHRI-POL 7813 11 7809 11 5729 8 8875 13
290 UNNAO 18841 27 18950 27 18348 26 18937 27
291 URI G-1 4909 7 4941 7 3177 5 3962 6
292 VERSANA 4523 7 4746 7 5515 8 5809 8
293 VINDHYCHA BT 21214 31 21160 31 20379 29 20630 30
294 VISHNU PRAYAG 3562 5 3306 5 2998 4 3048 4
295 WAGOORA 6150 9 6210 9 4160 6 5242 8
WINTER OFF PEAK WINTER PEAK
Sl.No STATION NAME
MONSOON OFF PEAK MONSOON PEAK
NLDC 2012 REACTIVE POWER MANAGEMENT-a resource handbook 7 of 7
ANNEXURE 6
Surge Impedance Loading (SIL) of transmission lines.
NLDC, 2012 REACTIVE POWER MANAGEMENT-a resource handbook 1 of 1
ANNEXURE 7
LIST OF 765KV LINES TO BE COMMISSIONED DURING 2012
Sl.
No
REGION UTILITY NAME OF THE LINE
Ckt. Type
(Tower)
Line Length (in
km)
TARGET DATE Remarks
1
STATE SECTOR-
UPPCL
Anpara D - Unnao S/C 416 Jan-12
2 Balia-Lucknow S/C 320 Feb-12
3 Meerut - Bhiwani line S/C 175 May-12
4 Agra - Jhatikara S/C 245 Jun-12
5 Jhatikara - Bhiwadi - Moga S/C 358 Jun-12
6 Meerut - Agra S/C 260 Jun-12
7 Fatehpur- Agra line-II S/C 303 Aug-12
8 Fatehpur- Agra Line I S/C 325 Aug-12
9 Rihand - Vindhyachal Pooling Station line-I S/C 32 Nov-12
10 Rihand - Vindhyachal Pooling Station line-II S/C 31 Nov-12
11 Anta - Phagi (Jaipur South Ckt-1) S/C 210 Nov-12
12 Anta - Phagi (Jaipur South Ckt-2) S/C 220 Nov-12
13 2nd S/C Seoni (PG)Wardha (PG) line (initially to be operated at 400kV) S/C 261 Feb-12
14 LILO of Sipat - Seoni line at WR Pooling station Near Sipat S/C 8 Feb-12
15 LILO of Sipat - Seoni (2nd Ckt) at WR Pooling station Near Sipat S/C 8 Feb-12
16 Bina - Indore S/C 311 Mar-12
17 Satna - Bina line -I S/C 274 Mar-12
18 Gwalior - Jaipur (RVPN) line S/C 300 Nov-12
19 Sasan - Vindhyachal Pooling Station line S/C 6 Nov-12
20 Satna - Gwalior line (359 Km + 60 Km D/C Portion) Ckt-II D/C + S/C 331 Nov-12
21 Satna - Gwalior line (Ckt-I) S/C 392 Nov-12
22 Vindhyachal Pooling Station - Satna line (234 Km + 12 Km D/C S/C Portion) Ckt-II D/C + S/C 234 Nov-12
23 Vindhyachal Pooling Station Satna line (Ckt-I) S/C 265 Nov-12
24 Sasan - Satna line -I S/C 246 Dec-12
25 Sasan - Satna line -II S/C 243 Dec-12
26 Satna - Bina line -II S/C 276 Dec-12
27 Gaya - Balia S/C 358 Feb-12
28 Sasaram - Fatehpur Line I S/C 320 Mar-12
29 Gaya-Sasaram S/C 145 Mar-12
30 Ranchi-WR Pooling Station S/C 398 Aug-12
31 Sasaram - Fatehpur line-II S/C 260 Dec-12
EASTERN
REGION
CENTRAL
SECTOR
NORTHERN
REGION
WESTERN
REGION
STATE SECTOR-
RAJASTHAN
(RVPNL)
CENTRAL
SECTOR
CENTRAL
SECTOR
NLDC, 2012 REACTIVE POWER MANAGEMENT-a resource handbook 1 OF 1
ANNEXURE 8
Shunt capacitors installed capacity-All India level.
Sl.
No
Region
(A)
Total capacity in
MVAR
Remarks
1 Northern 27694
2 Western 19725
3 Southern 16109
4 Eastern *
ER Data not
available
5 North Eastern 175
TOTAL 63703
LIST OF SHUNT CAPACITORS
NLDC, 2012 REACTIVE POWER MANAGEMENT-a resource handbook 1 of 1
ANNEXURE 9
SERIES COMPENSATION AND SVC ALL INDIA LEVEL
SL.
NO
REGION LINE COMPENSATION END REMARKS
1 Panki-Muradnagar 40% Muradnagar Agency is UPPCL
2 Unnao-Bareilley(UP) - 1 45% Unnao Agency is UPPCL
3 Unnao-Bareilley(UP) - 2 45% Unnao Agency is UPPCL
4 Kanpur-Ballabhgarh 1 35% Ballabhgarh
5 Kanpur-Ballabhgarh 2 40% Ballabhgarh
6 Kanpur-Ballabhgarh 3 40% Ballabhgarh
7 Balia-Lucknow 1 40% Lucknow ( PG)
8 Balia-Lucknow 2 40% Lucknow ( PG)
9 Gorakhpur-Muzaffarpur 1
40% & 10-15%
(Dynamic)
Gorakhpur FSC + TCSC
10 Gorakhpur-Muzaffarpur 2
40% & 10-15%
(Dynamic)
Gorakhpur FSC + TCSC
11 Lucknow - Gorakhpur 1 30% Lucknow ( PG)
12 Lucknow - Gorakhpur 2 30% Lucknow ( PG)
13 Lucknow - Gorakhpur 3 40% Lucknow ( PG)
14 Lucknow - Gorakhpur 4 40% Lucknow ( PG)
15 Allahabad-Mainpuri 1 40% Mainpuri
16 Allahabad-Mainpuri 2 40% Mainpuri
17 Mandola-Bareilley - 1 30% Bareilley ( PG)
18 Mandola-Bareilley - 2 30% Bareilley ( PG)
19 Kishenpur-Pampore 1 (220 kV) 40% Kishenpur Not in service
20 Kishenpur-Pampore 2 (220 kV) 40% Kishenpur Not in service
21 Khandwa-Seoni 1 40% Khandwa
22 Khandwa-Seoni 2 40% Khandwa
23 Adani-Sami 1 38% Sami Agency is Adani
24 Adani-Sami 2 38% Sami Agency is Adani
25 Raigarh-Raipur 1
40% fixed, +15%/-5%
dynamic
Raipur FSC + TCSC
26 Raigarh-Raipur 2
40% fixed, +15%/-5%
dynamic
Raipur FSC + TCSC
SERIES COMPENSATION & SVC ALL INDIA LEVEL
NR
WR
NLDC, 2012 REACTIVE POWER MANAGEMENT-a resource handbook 1 of 2
ANNEXURE 9
SERIES COMPENSATION AND SVC ALL INDIA LEVEL
SL.
NO
REGION LINE COMPENSATION END REMARKS
27 Purnea-Muzaffarpur 1
40% fixed, +15%/-5%
dynamic
Purnea FSC + TCSC
28 Purnea-Muzaffarpur 2
40% fixed, +15%/-5%
dynamic
Purnea FSC + TCSC
29 Ranchi-Sipat 1 40% Ranchi
FSC of ckt.1 out since
04.5.09
30 Ranchi-Sipat 2 40% Ranchi
FSC of ckt.1 out since
04.5.09
31 Rengali-Indravati 40% Rengali Not in service
32 Meramundali-Jeypore 40% Jeypore
33 Jeypore-Gazuwaka 1 40% Jeypore
34 Jeypore-Gazuwaka 2 40% Jeypore
35 N'Sagar-Cudappa 1 40% Cudappa
36 N'Sagar-Cudappa 2 40% Cudappa
37 Gooty-Hoody 40% Gooty
38 Gooty-Neelamangala 40% Gooty
SVC (Static Sar Compensator)
S.No. Location
ID Rating MVAr Remarks
1 SVC-1 140
2 SVC-2 140
ER
SERIES COMPENSATION & SVC ALL INDIA LEVEL
400kV
KANPUR
SR
NLDC, 2012 REACTIVE POWER MANAGEMENT-a resource handbook 2 of 2
ANNEXURE10
ICT TAP POSITION DETAILS
Note:
% age kV
1 ABDULLAPUR PGCL-NR2 400/220/33 ICT 01 315 BHEL 17 9 1.25 5 11
2 ABDULLAPUR PGCL-NR2 400/220/33 ICT 02 315 BHEL 17 9 1.25 5 11
3 ABDULLAPUR PGCL-NR2 400/220/33 ICT 03 315 BHEL 17 9 1.25 5 11
4 ALLHABAD PGCL-NR1 400/220/33 ICT 01 315 BHEL 17 9 1.25 5 11
5 ALLHABAD PGCL-NR1 400/220/33 ICT 02 315 BHEL 17 9 1.25 5 11
6 AMRITSAR PGCL-NR2 400/220/33 ICT 01 315 CGL 17 9 1.25 5 11
7 AMRITSAR PGCL-NR2 400/220/33 ICT 02 315 CGL 17 9 1.25 5 11
8 BAHADURGARH PGCL-NR2 400/220/33 ICT 01 315 BHEL 17 9 1.25 5 11
9 BAHADURGARH PGCL-NR2 400/220/33 ICT 02 500 AREVA 17 9 1.25 5 11
10 BALLABGARH PGCL-NR1 400/220/33 ICT 01 315 BHEL 17 9 1.25 5 11
11 BALLABGARH PGCL-NR1 400/220/33 ICT 02 315 BHEL 17 9 1.25 5 11
12 BALLABGARH PGCL-NR1 400/220/33 ICT 03 315 BHEL 17 9 1.25 5 11
13 BALLABGARH PGCL-NR1 400/220/33 ICT 04 315 BHEL 17 9 1.25 5 11
14 BASSI PGCL-NR1 400/220/33 ICT 01 315 TELK 17 9 1.25 5 13
15 BASSI PGCL-NR1 400/220/33 ICT 02 315 TELK 17 9 1.25 5 13
16 BAWANA PGCL-NR1 400/220/33 ICT 03 315 BHEL 17 9 1.25 5 11
17 BHINMAL PGCL-NR1 400/220/33 ICT 01 315 CGL 17 9 1.25 5 9
18 BHINMAL PGCL-NR1 400/220/33 ICT 02 315 BHEL 17 9 1.25 5 9
19 BHIWADI PGCL-NR1 400/220/33 ICT 01 315 TELK 17 9 1.25 5 11
20 BHIWADI PGCL-NR1 400/220/33 ICT 02 315 TELK 17 9 1.25 5 11
21 FATEHABAD PGCL-NR2 400/220/33 ICT 01 315 BHEL 17 9 1.25 5 11
22 FATEHABAD PGCL-NR2 400/220/33 ICT 02 315 CGL 17 9 1.25 5 11
23 GORAKHPUR PGCL-NR1 400/220/33 ICT 01 315 TELK 17 9 1.25 5 11
24 GORAKHPUR PGCL-NR1 400/220/33 ICT 02 315 CGL 17 9 1.25 5 11
25 GURGAON PGCL-NR1 400/220/33 ICT 01 315 BHEL 17 9 1.25 5 9
26 HISAR PGCL-NR2 400/220/33 ICT 01 315 BHEL 17 9 1.25 5 11
27 HISAR PGCL-NR2 400/220/33 ICT 02 315 BHEL 17 9 1.25 5 11
28 HISAR PGCL-NR2 400/220/33 ICT 03 315 CGL 17 9 1.25 5 11
29 J ALLANDHAR PGCL-NR2 400/220/33 ICT 01 315 BHEL 17 9 1.25 5 11
30 J ALLANDHAR PGCL-NR2 400/220/33 ICT 02 315 BHEL 17 9 1.25 5 11
31 KAITHAL PGCL-NR2 400/220/33 ICT 01 315 BHEL 17 9 1.25 5 11
32 KAITHAL PGCL-NR2 400/220/33 ICT 02 315 BHEL 17 9 1.25 5 11
33 KANKROLI PGCL-NR2 400/220/33 ICT 01 315 BHEL 17 9 1.25 5 9
34 KANKROLI PGCL-NR2 400/220/33 ICT 02 315 CGL 17 9 1.25 5 9
35 KANKROLI PGCL-NR2 400/220/33 ICT 03 315 BHEL 17 9 1.25 5 9
36 KANPUR PGCL-NR1 400/220/33 ICT 01 315 BHEL 17 9 1.25 5 12
37 KANPUR PGCL-NR1 400/220/33 ICT 02 315 BHEL 17 9 1.25 5 12
38 KISHENPUR PGCL-NR2 400/220/33 ICT 01 315 BHEL 17 9 1.25 5 9
39 KISHENPUR PGCL-NR2 400/220/33 ICT 02 315 BHEL 17 9 1.25 5 9
40 KOTA PGCL-NR2 400/220/33 ICT 01 315 CGL 17 9 1.25 5 9
41 KOTA PGCL-NR2 400/220/33 ICT 02 315 BHEL 17 9 1.25 5 9
Sl
No.
STEP
Station Name TT
TT-Total No. of Taps, NT-Nominal Tap, PT- Present Tap
NT PT
NORTHERN REGION
Owner
Voltage Ratio
(kV)
Equpt.
Rating
(MVA)
Make
NLDC-2012 REACTIVE POWER MANAGEMENT-a resource handbook 1 OF 10
ANNEXURE10
ICT TAP POSITION DETAILS
Note:
% age kV
42 LUCKNOW PGCL-NR1 400/220/33 ICT 01 315 CGL 17 9 1.25 5 9
43 LUDHIANA PGCL-NR2 400/132/33 ICT 01 315 BHEL 17 9 1.25 5 11
44 LUDHIANA PGCL-NR2 400/132/33 ICT 02 315 BHEL 17 9 1.25 5 11
45 LUDHIANA PGCL-NR2 400/132/33 ICT 03 315 ABB 17 9 1.25 5 11
46 MAHARANI BAGH PGCL-NR1 400/220/33 ICT 01 315 ABB 17 9 1.25 5 11
47 MAHARANI BAGH PGCL-NR1 400/220/33 ICT 02 315 ABB 17 9 1.25 5 11
48 MAHARANI BAGH PGCL-NR1 400/220/33 ICT 03 500 CGL 17 9 1.25 5 11
49 MAHARANI BAGH PGCL-NR1 400/220/33 ICT 04 500 CGL 17 9 1.25 5 11
50 MAINPURI PGCL-NR1 400/220/33 ICT 01 315 BHEL 17 9 1.25 5 13
51 MAINPURI PGCL-NR1 400/220/33 ICT 02 315 CGL 17 9 1.25 5 13
52 MALERKOTLA PGCL-NR2 400/220/33 ICT 01 315 BHEL 17 9 1.25 5 11
53 MALERKOTLA PGCL-NR2 400/220/33 ICT 02 315 CGL 17 9 1.25 5 11
54 MALERKOTLA PGCL-NR2 400/220/33 ICT 03 500 AREVA 17 9 1.25 5 11
55 MANDOLA PGCL-NR1 400/220/33 ICT 01 315 BHEL 17 9 1.25 5 12
56 MANDOLA PGCL-NR1 400/220/33 ICT 02 315 CGL 17 9 1.25 5 12
57 MANDOLA PGCL-NR1 400/220/33 ICT 03 315 CGL 17 9 1.25 5 12
58 MANDOLA PGCL-NR1 400/220/33 ICT 04 315 CGL 17 9 1.25 5 12
59 MANDOLA(SPARE) PGCL-NR1 400/220/33 ICT 05 315 CGL 17 9 1.25 5 12
60 MEERUT PGCL-NR1 400/220/33 ICT 01 315 BHEL 17 9 1.25 5 11
61 MEERUT PGCL-NR1 400/220/33 ICT 02 315 BHEL 17 9 1.25 5 11
62 MEERUT PGCL-NR1 400/220/33 ICT 03 315 BHEL 17 9 1.25 5 11
63 MOGA PGCL-NR2 400/220/33 ICT 01 250 BHEL 17 9 1.25 5 14
64 MOGA PGCL-NR2 400/220/33 ICT 02 250 BHEL 17 9 1.25 5 14
65 MOGA PGCL-NR2 400/220/33 ICT 03 250 BHEL 17 9 1.25 5 14
66 MOGA PGCL-NR2 400/220/33 ICT 04 315 BHEL 17 9 1.25 5 14
67 MUZAFFARNAGAR PGCL-NR1 400/220/33 ICT 01 315 ALSTOM 17 9 1.25 5 9
68 NALLAGARH PGCL-NR2 400/220/33 ICT 01 315 BHEL 17 9 1.25 5 10
69 NALLAGARH PGCL-NR2 400/220/33 ICT 02 315 BHEL 17 9 1.25 5 10
70 PANIPAT(BB) PGCL-NR2 400/220/33 ICT 02 450 TELK 17 9 0.65 2.25 11
71 PATIALA PGCL-NR2 400/220/33 ICT 01 315 BHEL 17 9 1.25 5 11
72 PATIALA PGCL-NR2 400/220/33 ICT 02 315 BHEL 17 9 1.25 5 11
73 PATIALA PGCL-NR2 400/220/33 ICT 03 500 AREVA 17 9 1.25 5 11
74 ROORKEE PGCL-NR2 400/220/33 ICT 01 315 BHEL 17 9 1.25 5 9
75 ROORKEE PGCL-NR2 400/220/33 ICT 02 315 BHEL 17 9 1.25 5 9
76 SONEPAT PGCL-NR2 400/220/33 ICT 01 315 BHEL 17 9 1.25 5 11
77 SONEPAT PGCL-NR2 400/220/33 ICT 02 315 ABB 17 9 1.25 5 11
78 WAGOORA PGCL-NR2 400/220/33 ICT 01 315 BHEL 17 9 1.25 5 9
79 WAGOORA PGCL-NR2 400/220/33 ICT 02 315 BHEL 17 9 1.25 5 9
80 WAGOORA PGCL-NR2 400/220/33 ICT 03 315 BHEL 17 9 1.25 5 9
81 WAGOORA PGCL-NR2 400/220/33 ICT 04 315 ABB 17 9 1.25 5 9
82 AURIYA CCGPP NTPC 400/220/33 ICT 01 315 BHEL 17 9 1.25 5 09
83 AURIYA CCGPP NTPC 400/220/33 ICT 02 315 TELK 17 9 1.25 5 09
84 DADRI TPS NTPC 400/220/33 ICT 01 500 CGL 17 9 1.25 5 11
85 DADRI TPS NTPC 400/220/33 ICT 02 500 CGL 17 9 1.25 5 11
86 DADRI TPS NTPC 400/220/33 ICT 03 500 CGL 17 9 1.25 5 11
Equipment
Rating
(MVA)
NORTHERN REGION
Owner
Voltage Ratio
(kV)
TT NT
TT-Total No. of Taps, NT-Nominal Tap, PT- Present Tap
Make
STEP
PT
Sl
No.
Station Name
NLDC-2012 REACTIVE POWER MANAGEMENT-a resource handbook 2 OF 10
ANNEXURE10
ICT TAP POSITION DETAILS
Note:
% age kV
87 DADRI GAS NTPC 400/220/33 ICT 04 500 CGL 17 9 1.25 5 11
88 DADRI GAS NTPC 400/220/33 ICT 05 500 BHEL 17 9 1.25 5 11
89 SINGRAULI STPS NTPC 400/132 ICT 01 100 BHEL 17 9 1.25 5 12
90 SINGRAULI STPS NTPC 400/132 ICT 02 100 BHEL 17 9 1.25 5 12
91 RIHAND STPS NTPC 400/132 ICT 01 200 PEEBLE UK 17 9 1.25 5 08
92 RIHAND STPS NTPC 400/132 ICT 02 200 BHEL 17 9 1.25 5 08
93 AGRA(UP) UPPTCL 400/220/33 ICT 01 315 BHEL 17 9 1.25 5 10
94 AGRA(UP) UPPTCL 400/220/33 ICT 02 315 ALSTOM 17 9 1.25 5 10
95 AGRA(UP) UPPTCL 400/220/33 ICT 03 315 SIEMENS 17 9 1.25 5 10
96 AZAMGARH UPPTCL 400/220/33 ICT 01 315 BHEL 17 9 1.25 2.75 12
97 AZAMGARH UPPTCL 400/220/33 ICT 02 240 HITACHI 17 9 1.25 2.75 12
98 BAREILY(UP) UPPTCL 400/220/33 ICT 01 315 BHEL 17 9 1.25 5 11
99 BAREILY(UP) UPPTCL 400/220/33 ICT 02 315 BHEL 17 9 1.25 5 11
100 GRETER NOIDA UPPTCL 400/220/33 ICT 01 315 EMCO 17 9 1.25 5 9
101 GRETER NOIDA UPPTCL 400/220/33 ICT 02 315 BHEL 17 9 1.25 5 9
102 GRETER NOIDA UPPTCL 400/220/33 ICT 03 315 TELK 17 9 1.25 5 9
103 GORAKHPUR(UP) UPPTCL 400/220/33 ICT 01 240 TELK 17 9 1.25 5 11
104 LUCKNOW(UP) UPPTCL 400/220/33 ICT 01 240 ALSTOM 17 9 1.25 5 10
105 LUCKNOW(UP) UPPTCL 400/220/33 ICT 02 240 HITACHI 17 9 1.25 5 10
106 MORADABAD UPPTCL 400/220/33 ICT 01 240 MITSUBISHI 17 9 1.25 5 09
107 MORADABAD UPPTCL 400/220/33 ICT 02 315 BHEL 17 9 1.25 5 09
108 MURADNAGAR UPPTCL 400/220/33 ICT 01 240 BHEL 17 9 1.25 5 10
109 MURADNAGAR UPPTCL 400/220/33 ICT 02 240 BHEL 17 9 1.25 5 10
110 MURADNAGAR UPPTCL 400/220/33 ICT 03 315 BHEL 17 9 1.25 5 10
111 MUZAFFARNAGAR UPPTCL 400/220/33 ICT 02 315 ALSTOM 17 9 1.25 5 9
112 MUZAFFARNAGAR UPPTCL 400/220/33 ICT 03 315 TELK 17 9 1.25 5 9
113 OBRA-B TPS UPPTCL 400/220/33 ICT 01 240 ALSTHOM 17 9 1.25 5 13
114 OBRA-B TPS UPPTCL 400/220/33 ICT 02 240 ALSTHOM 17 9 1.25 5 13
115 PANKI 400 UPPTCL 400/220/33 ICT 01 240 BHEL 17 9 1.25 5 13
116 PANKI 400 UPPTCL 400/220/33 ICT 02 240 BHEL 17 9 1.25 5 13
117 SARNATH UPPTCL 400/220/33 ICT 01 240 BHEL 17 9 1.25 5 10
118 SARNATH UPPTCL 400/220/33 ICT 02 315 TELK 17 9 1.25 5 10
119 SULTANPUR UPPTCL 400/220/33 ICT 01 240 BHEL 17 5 1.25 2.75 11
120 SULTANPUR UPPTCL 400/220/33 ICT 02 240 HITACHI 17 5 1.25 2.75 11
121 UNNAO UPPTCL 400/220/33 ICT 01 315 BHEL 17 9 1.25 5 11
122 UNNAO UPPTCL 400/220/33 ICT 02 315 BHEL 17 9 1.25 5 11
123 ANPARA TPS UPUN 400/132 ICT 01 100 BHEL 17 9 1.25 5 1
124 ANPARA TPS UPUN 400/132 ICT 02 100 CGL 17 9 1.25 5 5
125 ANPARA TPS UPUN 400/132 ICT 03 100 CGL 17 9 1.25 5 9
126 MAU (KASARA)-400 UPPTCL 400/132 ICT 01 200 ABB 17 9 1.25 5 10
127 MAU (KASARA)-400 UPPTCL 400/132 ICT 02 200 ABB 17 9 1.25 5 11
128 BARMER RRVPNL 400/220/33 ICT 01 315 TELK 17 9 1.25 5 9
129 BHILWARA RRVPNL 400/220/33 ICT 01 315 AREVA 17 9 1.25 5 9
130 BIKANER RRVPNL 400/220/33 ICT 01 315 AREVA 17 9 1.25 5 9
TT-Total No. of Taps, NT-Nominal Tap, PT- Present Tap
TT NT PT
NORTHERN REGION
Sl
No.
Station Name Owner
Voltage Ratio
(kV)
Equipment
Rating
(MVA)
STEP
Make
NLDC-2012 REACTIVE POWER MANAGEMENT-a resource handbook 3 OF 10
ANNEXURE10
ICT TAP POSITION DETAILS
Note:
% age kV
131 CHHABRA RRVPNL 400/220/33 ICT 01 315 BHEL 17 9 1.25 5 9
132 HEERAPURA RRVPNL 400/220/33 ICT 01 250 TELK 17 9 1.25 5 09
133 HEERAPURA RRVPNL 400/220/33 ICT 02 250 TELK 17 9 1.25 5 09
134 HEERAPURA RRVPNL 400/220/33 ICT 03 250 TELK 17 9 1.25 5 09
135 HEERAPURA RRVPNL 400/220/33 ICT 04 315 TELK 17 9 1.25 5 09
136 HINDAUN RRVPNL 400/220/33 ICT 01 315 TELK 17 9 1.25 5 9
137 HINDAUN RRVPNL 400/220/33 ICT 02 315 CGL 17 9 1.25 5 9
138 J ODHPUR RRVPNL 400/220/33 ICT 01 315 BHEL 17 9 1.25 5 09
139 J ODHPUR RRVPNL 400/220/33 ICT 02 315 BHEL 17 9 1.25 5 09
140 MERTA RRVPNL 400/220/33 ICT 01 315 ALSTOM 17 9 1.25 5 11
141 RAJ WEST RRVPNL 400/220/33 ICT 01 315 ABB 17 9 1.25 5 9
142 RATANGARH RRVPNL 400/220/33 ICT 01 315 TELK 17 9 1.25 5 10
143 RATANGARH RRVPNL 400/220/33 ICT 02 315 TELK 17 9 1.25 5 10
144 RATANGARH RRVPNL 400/220/33 ICT 03 315 TELK 17 9 1.25 5 10
145 SURATGARH TPS RVUN 400/220/33 ICT 01 315 CGL 17 9 1.25 5 12
146 SURATGARH TPS RVUN 400/220/33 ICT 02 315 CGL 17 9 1.25 5 12
147 BAMNAULI DTL 400/220/33 ICT 01 315 EMCO 17 9 1.25 5 9
148 BAMNAULI DTL 400/220/33 ICT 02 315 BHEL 17 9 1.25 5 9
149 BAMNAULI DTL 400/220/33 ICT 03 315 BHEL 17 9 1.25 5 9
150 BAMNAULI DTL 400/220/33 ICT 04 315 TELK 17 9 1.25 5 9
151 BAWANA DTL 400/220/33 ICT 01 315 BHEL 17 9 1.25 5 11
152 BAWANA DTL 400/220/33 ICT 02 315 BHEL 17 9 1.25 5 11
153 BAWANA DTL 400/220/33 ICT 04 315 TELK 17 9 1.25 5 11
154 MUNDKA DTL 400/220/33 ICT 01 315 TELK 17 9 1.25 5 9
155 MUNDKA DTL 400/220/33 ICT 02 315 EMCO 17 9 1.25 5 9
156 KASHIPUR PTCUL 400/220/33 ICT 01 315 ABB 17 9 1.25 5 12
157 KASHIPUR PTCUL 400/220/33 ICT 02 315 ABB 17 9 1.25 5 12
158 RISHIKESH 400 PTCUL 400/220/33 ICT 01 240 BHEL 17 9 1.25 5 9
159 RISHIKESH 400 PTCUL 400/220/33 ICT 02 240 MITSUBISHI 17 9 1.25 5 9
160 BHIWANI(BB) BBMB 400/220/33 ICT 01 500 TELK 17 9 1.25 5 10
161 DEHAR HEP BBMB 400/220/33 ICT 01 250 TELK 9 5 1.25 5 02
162 PANIPAT(BB) BBMB 400/220/33 ICT 01 450 TELK 17 9 0.65 2.25 11
NORTHERN REGION
TT-Total No. of Taps, NT-Nominal Tap, PT- Present Tap
Equipment
Rating
(MVA)
Make TT NT
Sl
No.
Station Name Owner
Voltage Ratio
(kV)
STEP
PT
NLDC-2012 REACTIVE POWER MANAGEMENT-a resource handbook 4 OF 10
ANNEXURE 10
ICT TAP POSITION DETAILS
% age kV
1 Raigarh 2x315 17 9 1.25 5 11
2 Jabalpur 2x315 17 9 1.25 5 9B
3 Satna 2x315 17 9 1.25 5 9B
4 Raipur 3x315 17 9 1.25 5 11
5 Mapusa 2x315 17 9 1.25 5 10
6 Vapi 2x315 17 9 1.25 5 12
7 Boisar 2x315 17 9 1.25 5 9
8 Khandwa 2x315 17 9 1.25 5 11
9 Seoni (765/400KV) 3x1500 23 9 1.25 5 9B
10 Seoni 2x315 17 9 1.25 5 9B
11 Bhatapara 2x315 17 9 1.25 5 9B
12 Rajgarh 2x315 17 9 1.25 5 11
13 Gwalior 2x315 17 9 1.25 5 9B
14 Damoh 2x315 17 9 1.25 5 9B
15 Itarasi 1x315 17 9 1.25 5 11
16 Dehgam 2x315 17 9 1.25 5 12
17 Wardha
2x315 17 9 1.25 5 11
18 Bina 1x315 17 9 1.25 5 9
19 Solapur 2x315 17 9 1.25 5 9
20 Pune 2x315 17 9 1.25 5 9
21 ASOJ 2x500 17 9 1.25 5 12
22 WANAKBORI 1x500 17 9 1.25 5 9
23 SOJA(Nardipur) 2x500 17 9 1.25 5 11
24 Jetpur 3x315 17 9 1.25 5 9
25 Chorania (Limdi) 2x500 17 9 1.25 5 13
26 Hadala(Rajkot) 2X315 17 9 1.25 5 9
27 GPEC 1x500 17 9 1.25 5 11
28 Kasor 1x500 17 9 1.25 5 9B
29 Amreli 2x315 17 9 1.25 5 12
30 Kansari(Zerda) 3x315 17 9 1.25 5 12
31 APL, Mundra 2x315 17 9 1.25 5
7
32 Ranchodpura(VADAVI) 2x315 17 9 1.25 5
9B
33 Korba (W) 1x500 17 9 1.25 5 12
34 Bhilai 3x315 17 9 1.25 5 13,13,9
35 Satpura 1x500 17 9 1.25 5 10
36 Indore 4x315 17 9 1.25 5 13,13,9B,9
37 Bhopal 3x315 17 9 1.25 5 9
38 Nagda 3x315 17 9 1.25 5 11
39 Birsinghpur 1x500 17 9 1.25 5 11
40 Katni 1x315 17 9 1.25 5 7
41 Bina 3x315 17 9 1.25 5 9
TT NT
STEP
Sl.No Substation
CHATTISGARH
WESTERN REGION
TT-Total No. of Taps, NT-Nominal Tap, PT- Present Tap
MADHYA PRADESH
Trafo. Cap PT Remarks
POWERGRID
GUJARAT
NLDC 2012 REACTIVE POWER MANAGEMENT-a resource handbook 5 OF 10
ANNEXURE 10
ICT TAP POSITION DETAILS
% age kV
42 Kalwa 1x600+2x500 17 9 1.25 5 11
43 Bhusawal 2x200 17 9 1.25 5 12
44 Bhusawal 1x315+1x500 17 9 1.25 5 11
45 Jejuri 2x500 17 9 1.25 5 9
46 Solapur 2x500 17 9 1.25 5 11
47 Koradi 1x300+1X315 17 9 1.25 5 11
48 Nagothane 2X315+1x500 17 9 1.25 5 9B
49 Chandrapur 2x315 17 9 1.25 5 12
50 Parli 2x315 17 9 1.25 5 12
51 Karad 3X315 17 9 1.25 5 9
52 Lonikhand 3x315 17 9 1.25 5 13
53 Aurangabad 2x315+1x500 17 9 1.25 5 9
54 Padghe 3x315 17 9 1.25 5 8
55 New Koyna 2x315 17 9 1.25 5 11
56 Dhule 2x315 17 9 1.25 5 11
57 Bableshwar 2x315+1x500 17 9 1.25 5 11,11,9
58 Kolhapur 4x315 17 9 1.25 5 9
59 Akola 1x315 17 9 1.25 5 8
60 Kharghar 2x315 17 9 1.25 5 11
61 Chakan 2x315 17 9 1.25 5 11
62 Seoni (765/400KV) 2x1000 23 9 1.25 5 7
63 VINDHYACHAL 3x200 17 9 1.25 5 9B
64 GANDHAR
2X500 17 9 1.25 5 10
65 Sardar Sarovar 2x315 17 9 1.25 5 9
66 JPL, Tamnar 2x315 17 9 1.25 5 9B
67 NSPCL,Bhilai 2x315 17 9 1.25 5 8
`
CENTRAL SECTOR/SSP/IPP
WESTERN REGION
TT-Total No. of Taps, NT-Nominal Tap, PT- Present Tap
Sl.No
MAHARASHTRA
Remarks Substation Trafo. Cap TT NT
STEP
PT
NLDC 2012 REACTIVE POWER MANAGEMENT-a resource handbook 6 OF 10
ANNEXURE 10
ICT TAP POSITION DETAILS
Note:
% age kV
1 CUDDAPAH - 1 400/220 315 BHEL 17 9 1.25 5 9
2 CUDDAPAH - 2 400/220 315 BHEL 17 9 1.25 5 9
3 GAJ UWAKA - 1 400/220 315 CGL 17 9 1.25 5 11
4 GAJ UWAKA - 2 400/220 315 CGL 17 9 1.25 5 11
5 GOOTY - 1 400/220 315 CGL 17 9 1.25 5 12
6 GOOTY - 2 400/220 315 BHEL 17 9 1.25 5 12
7 HYDERABAD -1 400/220 315 CGL 17 9 1.25 5 9
8 HYDERABAD - 2 400/220 315 CGL 17 9 1.25 5 9
9 HYDERABAD - 3 400/220 315 CGL 17 9 1.25 5 9
10 KHAMMAM - 1 400/220 315 CGL 17 9 1.25 5 12
11 KHAMMAM - 2 400/220 315 BHEL 17 9 1.25 5 12
12 MUNIRABAD - 1 400/220 315 TELK 17 9 1.25 5 9
13 MUNIRABAD - 2 400/220 315 BHEL 17 9 1.25 5 9
14 NAGARJ UNSAGAR - 1 400/220 315 TELK 17 9 1.25 5 10
15 NAGARJ UNSAGAR - 2 400/220 315 TELK 17 9 1.25 5 10
16 NAGARJ UNSAGAR - 3 400/220 315 BHEL 17 9 1.25 5 10
17 VIJ AYAWADA - 1 400/220 315 CGL 17 9 1.25 5 14
18 VIJ AYAWADA - 2 400/220 315 CGL 17 9 1.25 5 14
19 WARRANGAL - 1 400/220 315 TELK 17 9 1.25 5 9
20 WARRANGAL - 2 400/220 315 TELK 17 9 1.25 5 9
1 ARASUR - 1 400/220 315 BHEL 17 9 1.25 5 9
2 ARASUR - 2 400/220 315 BHEL 17 9 1.25 5 9
3 BANGALORE - 1 400/220 501 BHEL 17 9 1.25 5 8
4 BANGALORE - 2 400/220 501 CGL 17 9 1.25 5 8
5 HASSAN - 1 400/220 315 CGL 17 9 1.25 5 9
6 HASSAN - 2 400/220 315 CGL 17 9 1.25 5 9
7 HIRIYUR - 1 400/220 315 BHEL 17 9 1.25 5 9
8 HIRIYUR - 2 400/220 315 BHEL 17 9 1.25 5 9
9 HOSUR - 1 400/230 315 CGL 17 9 1.25 5 10
10 HOSUR - 2 400/230 315 CGL 17 9 1.25 5 10
11 KALIVANDAPATTU - 1 400/220 315 BHEL 17 9 1.25 5 7
12 KALIVANDAPATTU - 2 400/220 315 BHEL 17 9 1.25 5 7
13 KARAIKUDI - 1 400/230 315 CGL 17 9 1.25 5 9
14 KARAIKUDI -2 400/230 315 CGL 17 9 1.25 5 9
15 KOLAR - 1 400/220 501 CGL 17 9 1.25 5 7
16 KOLAR - 2 400/220 501 BHEL 17 9 1.25 5 7
17 MADURAI - 1 400/230 315 CGL 17 9 1.25 5 11
18 MADURAI - 2 400/230 315 CGL 17 9 1.25 5 11
19 MYSORE - 1 400/220 315 CGL 17 9 1.25 5 9
20 MYSORE - 2 400/220 315 CGL 17 9 1.25 5 9
TT Station Name
Voltage Ratio
(kV)
Rating
(MVA)
Make
TT-Total No. of Taps, NT-Nominal Tap, PT- Present Tap
NT PT
SOUTHERN REGION
POWERGRID SRTS - I
POWERGRID SRTS - 2
Sl No.
STEP
NLDC-2012 REACTIVE POWER MANAGEMENT-a resource handbook 7 OF 10
ANNEXURE 10
ICT TAP POSITION DETAILS
Note:
% age kV
21 NARENDRA - 1 400/220 315 BHEL 17 9 1.25 5 9B
22 NARENDRA - 2 400/220 315 BHEL 17 9 1.25 5 9B
23 PUDUCHERY - 1 400/230 315 TELK 17 9 1.25 5 9
24 PUDUCHERY - 2 400/230 315 TELK 17 9 1.25 5 9
25 PUGALUR 400/230 315 AREVA 17 9 1.25 5 9
26 PUGALUR 400/230 315 AREVA 17 9 1.25 5 9
27 THIRUNELVELI - 1 400/220 315 TELK 17 9 1.25 5 9
28 THIRUNELVELI - 2 400/220 315 TELK 17 9 1.25 5 9
29 TRICHY - 1 400/230 315 TELK 17 9 1.25 5 9
30 TRICHY - 2 400/230 315 TELK 17 9 1.25 5 9
31 TRIVANDRUM - 1 400/220 315 BHEL 17 9 1.25 5 9
32 TRIVANDRUM - 2 400/220 315 BHEL 17 9 1.25 5 9
33 TRIVANDRUM - 3 400/220 315 BHEL 17 9 1.25 5 9
34 UDUMALPET - 1 400/230 315 BHEL 17 9 1.25 5 8
35 UDUMALPET - 2 400/230 315 BHEL 17 9 1.25 5 8
36 UDUMALPET - 3 400/230 315 AREVA 17 9 1.25 5 8
1 RAMAGUNDAM - 1 400/132 200 BHEL 17 9 1.25 5 12
2 RAMAGUNDAM - 2 400/132 200 BHEL 17 9 1.25 5 12
3 RAMAGUNDAM - 3 400/220 250 BHEL 17 9 1.25 5 12
4 RAMAGUNDAM - 4 400/220 250 BHEL 17 9 1.25 5 12
5 RAMAGUNDAM - 5 400/220 315 BHEL 17 9 1.25 5 12
1 NEYVELI II - 1 400/230 250 BHEL 17 9 1.25 5 10
2 NEYVELI II - 2 400/230 250 BHEL 17 9 1.25 5 10
1 KAIGA - 1 400/220 501 BHEL 17 9 1.25 5 11
2 KAIGA - 2 400/220 501 BHEL 17 9 1.25 5 11
Voltage Ratio
(kV)
SOUTHERN REGION
NTPC
NPCIL
NLC
TT-Total No. of Taps, NT-Nominal Tap, PT- Present Tap
Sl No.
STEP
PT Station Name
Rating
(MVA)
Make TT NT
NLDC-2012 REACTIVE POWER MANAGEMENT-a resource handbook 8 OF 10
ANNEXURE 10
ICT TAP POSITION DETAILS
Note:
% age kV
1
JEYPORE
400/220
P0WERGRID 2x315
17 9 1.25 5
16
2
JAMSHEDPUR
400/220
P0WERGRID 2x315
17 9 1.25 5
15
3
BIHARSHARIFF
400/220
P0WERGRID 3x315
17 9 1.25 5
12
4
BIDHANNAGAR
400/220
WBSETCL 2x315
17 9 1.25 5
14
5
MAITHON
400/220
P0WERGRID 2x315
17 9 1.25 5
13
6
ARAMBAGH
400/220
WBSETCL 3x315
17 9 1.25 5
13
7
JEERAT
400/220
WBSETCL 3x315
17 9 1.25 5
13
8
TALCHER
400/220
NTPC 2x315
17 9 1.25 5
13
9
MALDA
400/220
P0WERGRID 2x315
17 9 1.25 5
12
10
KOLAGHAT
400/220
WBSETCL 2x315
17 9 1.25 5
12
11
RENGALI
400/220
P0WERGRID 2x315
17 9 1.25 5
12
12
NEW PURNEA
400/220
P0WERGRID 2x315
17 9 1.25 5
11
13
SASARAM
400/220
P0WERGRID 2x315
17 9 1.25 5
11
14
PATNA
400/220
P0WERGRID 2x315
17 9 1.25 5
11
15
FARAKKA
400/220
NTPC 2x315
17 9 1.25 5
11
16
PARULIA
400/220
P0WERGRID 2x315
17 9 1.25 5
11
17
BAKRESHWAR
400/220
WBSETCL 2x315
17 9 1.25 5
11
18
SUBHASGRAM
400/220
P0WERGRID 2x315
17 9 1.25 5
11
19
BINAGURI
400/220
P0WERGRID 2x315
17 9 1.25 5
10
20
ROURKELA
400/220
P0WERGRID 2x315
17 9 1.25 5
10
21
MERAMUNDALI
400/220
OPTCL 2x315
17 9 1.25 5
10
22
BARIPADA
400/220
P0WERGRID 2x315
17 9 1.25 5
9
23
MENDASAL
400/220
OPTCL 2x315
17 9 1.25 5
9
24
MUZAFFARPUR
400/220
P0WERGRID 2x315
17 9 1.25 5
9B
25
RANCHI
400/220
P0WERGRID 2x315
17 9 1.25 5
9B
26
INDRAVATI
400/220
OPTCL 2x315
17 9 1.25 5
9B
POWERGRID ERTS - I
Make
Rating
(MVA)
Voltage Ratio
(kV)
Station Name
EASTERN REGION
TT-Total No. of Taps, NT-Nominal Tap, PT- Present Tap
Owner NT TT Sl No.
STEP
PT
NLDC-2012 REACTIVE POWER MANAGEMENT-a resource handbook 9 OF 10
ANNEXURE 10
ICT TAP POSITION DETAILS
Note:
% age kV
1
BONGAIGAON
400/220
P0WERGRID 1x315
TELK 17 9 1.25 5
12
2
BALIPARA
400/220
P0WERGRID 1x315
TELK 17 9 1.25 5
10
3
MISA
400/220
P0WERGRID 1x315
TELK 17 9 1.25 5
5
POWERGRID NERTS
Owner
Rating
(MVA)
Make TT
NORTH EASTERN REGION
TT-Total No. of Taps, NT-Nominal Tap, PT- Present Tap
Sl No. Station Name
Voltage Ratio
(kV)
NT
STEP
PT
NLDC-2012 REACTIVE POWER MANAGEMENT-a resource handbook 10 OF 10
ANNEXURE 11
Typical Transformer Tap Changer online/offline detail
Type1 On Load Tap Changer
Used in 400/220 kV, 3 Phase, 315 MVA, BHEL Make, ICT
Tap Position Tap Remarka
Numbar +/-5% % kV Location:
1 440 220 1.25 5 Maximum Turns Ratio Position
2 435 220 1.25 5
3 430 220 1.25 5
4 425 220 1.25 5
5 420 220 1.25 5
6 415 220 1.25 5
7 410 220 1.25 5
8 405 220 1.25 5
9 400 220 1.25 5 Nominal Tap
10 395 220 1.25 5
11 390 220 1.25 5
12 385 220 1.25 5
13 380 220 1.25 5
14 375 220 1.25 5
15 370 220 1.25 5
16 365 220 1.25 5
17 360 220 1.25 5 Minimum Turns Ratio Position
Type2 On Load Tap Changer
Used in 400/220 kV, 3 Phase, 450 MVA, Hitachi Make, ICT
Tap Position Tap Remarka
Numbar +15 %,-5 % % kV Location:Panipat(BBMB)
1 400 253 1.25 2.75 Maximum Turns Ratio Position
2 400 250.5 1.25 2.75
3 400 247.5 1.25 2.75
4 400 244.75 1.25 2.75
5 400 242 1.25 2.75
6 400 239.25 1.25 2.75
7 400 236.15 1.25 2.75
8 400 233.75 1.25 2.75
9 400 231 1.25 2.75
10 400 228.25 1.25 2.75
11 400 225.5 1.25 2.75
12 400 222.75 1.25 2.75
13 400 220 1.25 2.75 Nominal Tap
14 400 217.25 1.25 2.75
15 400 214.5 1.25 2.75
16 400 211.75 1.25 2.75
17 400 209 1.25 2.75 Minimum Turns Ratio Position
Type3 Off Load Tap Changer
Used in 11/240 kV,3 Phase,Generator Transformer
Tap Position Tap Remarka
Numbar +/- 10 % % kV Location:Kota
1 264 11 2.5 6 Maximum Turns Ratio Position
2 258 11 2.5 6
3 252 11 2.5 6
4 246 11 2.5 6
5 240 11 2.5 6 Nominal Tap
6 234 11 2.5 6
7 228 11 2.5 6
8 222 11 2.5 6
9 216 11 2.5 6 Minimum Turns Ratio Position
Type4 Off Load Tap Changer
Used in 21/235 kV,3 Phase,Generator Transformer
Tap Position Tap Remarka
Numbar +/- 10 % % kV Location:RAPSB
1 258.5 21 2.5 5.875 Maximum Turns Ratio Position
2 252.625 21 2.5 5.875
3 246.75 21 2.5 5.875
4 240.875 21 2.5 5.875
5 235 21 2.5 5.875 Nominal Tap
6 229.125 21 2.5 5.875
7 223.25 21 2.5 5.875
8 217.375 21 2.5 5.875
9 211.5 21 2.5 5.875 Minimum Turns Ratio Position
High
Voltage(kV)
Intermediate
Voltage (kV)
Step
H
i
g
h

V
o
l
t
a
g
e

S
i
d
e
Step
Step
Step High
Voltage(kV)
Intermediate
Voltage (kV)
High
Voltage(kV)
Intermediate
Voltage (kV)
H
i
g
h

V
o
l
t
a
g
e

S
i
d
e
L
o
w

V
o
l
t
a
g
e

S
i
d
e
H
i
g
h

V
o
l
t
a
g
e

S
i
d
e
Intermediate
Voltage (kV)
High
Voltage(kV)
NLDC, 2012 REACTIVE POWER MANAGEMENT-a resource handbook 1 OF 2
ANNEXURE 11
Typical Transformer Tap Changer online/offline detail
Type5 Off Load Tap Changer
Used in 11/220 kV, 1 Phase, 25 MVA, Crompton Greaves Make,Generator Transformer
Tap Position Tap Remarka
Numbar +7.5/-2.5 % % kV Location:Tanakpur,Bairasiul
1 236.5/

3 11/

3 2.5 5.5 Maximum Turns Ratio Position


2 231/

3 11/

3 2.5 5.5
3 225.5/

3 11/

3 2.5 5.5
4 220/

3 11/

3 2.5 5.5 Nominal Tap


5 214.5/

3 11/

3 2.5 5.5 Minimum Turns Ratio Position


Type6 Off Load Tap Changer
Used in 15.75/420 kV, 306 MVA,3 Phase,Generator Transformer
Tap Position Tap Remarka
Numbar +2.5/-7.5 % kV Location:Tehri
1 430 15.75 2.5 10.5 Maximum Turns Ratio Position
2 419.5 15.75 2.5 10.5 Nominal Tap
3 409 15.75 2.5 10.5
4 398.5 15.75 2.5 10.5
5 388 15.75 2.5 10.5 Minimum Turns Ratio Position
Type7 Off Load Tap Changer
Used in 1 Phase,Generator Transformer
Tap Position Tap Remarka
Numbar +/-5% % kV Location:Dulhasti, Uri,Chamera-I
1 420/

3 11/

3 2.5 10 Maximum Turns Ratio Position


2 410/

3 11/

3 2.5 10
3 400/

3 11/

3 2.5 10 Nominal Tap


4 390/

3 11/

3 2.5 10
5 380/

3 11/

3 2.5 10 Minimum Turns Ratio Position


H
i
g
h

V
o
l
t
a
g
e

S
i
d
e
High
Voltage(kV)
H
i
g
h

V
o
l
t
a
g
e

S
i
d
e
Intermediate
Voltage (kV)
Step
High
Voltage(kV)
Step
H
i
g
h

V
o
l
t
a
g
e

S
i
d
e
Step
Intermediate
Voltage (kV)
Intermediate
Voltage (kV)
High
Voltage(kV)
NLDC, 2012 REACTIVE POWER MANAGEMENT-a resource handbook 2 OF 2
ANNEXURE 12
SYNCHRONOUS CONDENSER AT ALL INDIA LEVEL
SL.
NO
REGION SUBSTATION UTILITY RATING MVAR INSTALLED ON MAKE
1 Heerapura 220 kV RVPNL 20 33KV BUS SIEMENS
2 Heerapura 220 kV RVPNL 20 33KV BUS SIEMENS
SL.
NO
REGION STATION UTILITY RATING MW
1 Pong BBMB 6 X 66 = 396
2 Larji HPSEB 3 X 42 = 126
3 Ranjit Sagar HEP (RSD) PSEB 4 X 150 = 600
4 Rana Pratap Sagar (RPS) RVUN 4 X 43 = 172
5 Jawahar Sagar (JS) RVUN 3 X 33 = 99
6
Tehri
THDC
2 X 250 = 500
7 RBPH NCA 6X200=1200
8 KOYNA IV MSEGCL 4X250=1000
9 GHATGHAR MSEGCL 2X125=250
10 Sagar Andhra Pradesh 7 X 100.8 = 705.6
11 Sagar Andhra Pradesh 1 X 110 = 110
12 Srisailam LB Andhra Pradesh 6 X 150 = 900
13 Varahi Karnataka 2 X 115 = 230
14 Idukki Kerala 3 X 130 = 390
15 Kuttiadi Kerala 3 X 25 = 75
16 Lower Periyar Kerala 3 X 60 = 180
17 Basin Bridge Tamil Nadu 4 X 30 =120
18 Aliyar Tamil Nadu 1 X 60 = 60
7113.6 TOTAL
WR
NR
LIST OF SYNCHRONOUS CONDENSER
NR
HYDRO STATIONS HAVING SYNCHRONOUS CONDENSER FACILITY
SR
NLDC, 2012
REACTIVE POWER MANAGEMENT-a resource handbook 1 of 1

Das könnte Ihnen auch gefallen