Beruflich Dokumente
Kultur Dokumente
RESIDENTIAL BUILDING).
Sl. No.
1
Total Quantity
Unit
Sqm
581.00
Rate in Taka
1,907.00
Amount in Taka
1,107,967.00
58.00
Sqm
624.00
36,192.00
drawing paper accepted by the Engineer. Providing minimum ten (10) copies coloured post-card size progress photograph of works under contract taken by professional photographer which record the progress of the Works Preparation & submission of implementation schedule to the Engineer for approval prior ground breaking showing the events (works) and successive sub-events of works including all the management & control parameters like Earliest Start Time (EST), Earliest Finish Time (EFT), float events on critical path, resource allocation etc. with description of general method of works, in orderly manner all in the form network diagram prepared in computer software like MS project and presenting in Displayable hard and soft copy minimum 3 (three) sets. (This is a time related item. Proportionate payment for this item shall be made istributing in each bill on the basis of percentage progress of the whole works under contract) Providing layout and carry over PWD Bench-Mark (BM) at site from nearby BM pillar, Property lines, existing ground level (EGL), formation ground level (FGL), highest flood levels (HFL), plinth levels (PL), mean sea level (MSL), setting and marking all pillars, reduced marker, levels pegs (RLs) etc. showing and maintaining including locating,
6.00 Month
737.00
4,422.00
1.00
L.S.
21,133.00
21,133.00
2,200.00
Sqm
21.00
46,200.00
establishing, protecting all public utilities within the premise 6 of work and finally all to be presented in black and white. Mobilization and cleaning site before commencing actual physical work and during contract period and demobilization after completion of the Works under contract accepted by Engineer. This work shall also covers clayey cleaning and clearing, cutting or filling, dressing the project area on and in the ground to an extent that all the events of works of the project can be executed smoothly in a working environment with a particular attention on safety and security in all 2,200.00 Sqm 149.00 327,800.00
Sl. No.
7
Total Quantity
Unit
Rate in Taka
Amount in Taka
22,00.00
Sqm.
9.00
19,800.00
8 9
1,000.00 400.00
Hour Sqm
271.00 534.00
271,000.00 213,600.00
trenches up to 1.5 m depth, to protect loss due to damage of property by Palisading accepted by the Engineer. [the rate 10 is including cost of vertical post] Sand filling in foundation trenches and plinth with sand having F.M. 0.5 to 0.8 in 150mm layers including leveling, watering and compaction to achieve minimum dry density of 90% with optimum moisture content (Modified proctor test) by ramming each layer up to finished level as per design supplied by the design office only etc. all complete and accepted by the Engineer. Clearing and disposing of excavated earth from the construction site by truck or any other means to a place within 30 km radius of the city or town area including loading, unloading at both ends, leveling and dressing the carried 12 earth etc. complete accepted by the Engineer. Site Development/Improvement by carted/dredged earth or sand (free from any organic, foreign, environmental hazard substances) carried by head or truck or any other meansl in/c cost of cutting/dredging of earth/sand, carrying, placing the earth/sand in the designated area, maintaining slopes, breaking lumps, levelling and dressing in layers up to finished level etc. all complete as per direction and accepted by the engineer in charge. Supplying and mixing specified type chemical admixture delivered from an authorized local agent or manufacturer, comply with the ASTM C-494 requirements, confirming the current compliance of the admixture to specification requirements like physical properties, uniformity and equivalence in composition etc., performance (water content, fresh concrete setting time and compressive strength) requirements, delivered in sealed water-tight containers having and confirming plainly marked the proprietary name of the admixture type under this specification, net weight and /or volume, manufacturing and expiry date, non aggressiveness to environment, aggregates and metals in concrete etc. and mixing the admixture in non pre-stressed cement concrete mixture in the field under the strict accordance with manufacturers recommendation and instruction, providing safety provisions in all respects etc. all complete as per instruction and approved by the Engineer. Dose (quantity in milliliters per 50 kg bag cement) and brand/origin/ manufacturer with respect to particular brand of cement and particular stock of aggregates and method of use to be determined by mix design / trial mix at the cost borne by the Contractor and approved by the Engineer. (Use of a) Supply and use of water reducing chemical admixture ASTM C-494 Type - A of approved brand/origin/manufacturer in concrete: The admixture to reduce quantity of mixing water required for normal workability and to maintain low watercement (W/C) ratio for improved concrete. 240.00 Cum 182.00 43,680.00 100.00 Cum 549.00 54,900.00
11
3,590.00
Cum
408.00
1,464,720.00
13
4,500.00
Liter
169.00
760,500.00
Sl. No.
14
Total Quantity
Unit
Rate in Taka
Amount in Taka
190.00
M.Ton
81,000.00
15,390,000.00
15
16
Providing bearing joints fixed or free with 300 x 300 x 05 mm M.S. (Grade - A36) shoe plate fitted in the truss angles with 16 mm diameter M.S. rod counter sunk rivets, welded and anchored to 300 x 300 x 05 mm .M.S shoe plate by two Nos. 19 mm dia M.S. U rod embedded in the bed of the lintel around the reinforcement, cleaning and greasing the joints for all floors etc. all complete and accepted by the Engineer. Providing and making point welding at contact point of the spiral binders at reasonable intervals with the main reinforcements by electric arc welding for construction of cast in situ bored pile carefully with highly oxidized electrodes making the points prominent and accepted by the Engineer (rate is inclusive of all materials labour, tools and plants, electricity and all equipment). Providing and making welded splice by welding of minimum 300 mm length at the lap of main reinforcement in re-bar cage to be placed in bore-hole where necessary by electric arc welding with highly oxidized electrodes making the joint prominent and accepted by the Engineer. (rate is inclusive of all materials labour, tools and plants, electricity and all equipment). Conducting static load test as per ASTM D1143 or equivalent standard for the cast-in-situ/pre-cast pile providing required scaffolding, bracing, jacks, pressure test gauge, loading unloading, Kentledge and other plants and equipment including staging, mobilization, demobilization, hire charge, gunny bags, sand and filling sacs/gunny bags for loading, record readings and preparation of results in standard forms and other incidental charges per standard practice and procedures including submission of load test report, furnishing all graph and chart etc. complete in all respects approved and accepted by the Engineer (Minimum two cyclic loading). Before commencing load test, Contractor shall submit method statement for conducting load test to the Engineer for approval. However, Engineers approval shall not relieve the Contractor of his responsibilities and obligations under Contract. a) For 280 tonne load for 1 No. test
789.00
Each
2,496.00
1,969,344.00
25,000.00
Point
3.61
90,250.00
17
38,000.00
Inch
7.81
296,780.00
18
1.00
P/Test
256,236.65
256,236.65
b) For intermediate loading from 280 tonne to 300 tonne for each additional tonne.
400.00
P/Ton
881.93
352,772.00
Sl. No.
19
Total Quantity
Unit
Rate in Taka
Amount in Taka
14,600.00 1.00
Rm set
1,277.00 117,704.00
18,644,200.00 117,704.00
20
21
14,600.00
Rm
1,200.00
17,520,000.00
22
789.00
each
2,191.00
1,728,699.00
23
789.00
each
3,211.00
2,533,479.00
TK. =
63,271,378.00
In words: (Taka Six Crore Thirty two lakh Seventy One Thousand three hundred seventy eight Taka ) only.