Beruflich Dokumente
Kultur Dokumente
Page 1 of 13
Huawei Technologies Co., Ltd. provides customers with comprehensive technical support and service. For assistance, please contact our local office or company headquarters.
Copyright Huawei Technologies Co., Ltd. 2012. All rights reserved. No part of this document may be reproduced or transmitted in any form or by any means without prior written consent of Huawei Technologies Co., Ltd. Trademarks and Permissions
and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd. All other trademarks and trade names mentioned in this document are the propert ies of their respective holders.
Notice Every effort has been made in the preparation of this document to ensure accuracy of the contents, but all statements, information, and recommendations in this document do not constitute the warranty of any kind, express or implied.
Page 2 of 13
1
For PTN910:
After powering up the PTN equipment, wait 3-5 minutes for the PTN to start up completely. Then the engineer should check the status of PTN indicators.
There are 9 indicators on the PTN CXPH board. The correct indicators status should be as shown below:
By default, the GE optical interfaces are enabled after the PTN is powered up. The UGL engineer needs to check the output power of the GE optical interfaces (OUT1 and OUT2). The GE optical interface is 1000BASE4
LX(10Km). Its mean launched optical power should be from -11 to -3 dBm. The figures below shows the GE output interfaces to be tested.
The NE IP and GE interface IP should be configured to enable the remote communication and control of the PTN. UGL engineer should be responsible for the IP address configuration.
Then the Ethernet interface of the laptop should be connect to the ETH/OAM interface of the PTN with cable.
In the Login dialog box, set the username and the password.
Check whether the U2000 LCT processes can be normally started. The processes whose startup mode is manual must be started manually. If all the processes can be normally started, the server runs normally
Select the row which has the 129.9.255.255 as the IP Address in the pop-out window and click next
The system will find out the directly connected PTN-910. Select the entry and click Create. Enter the username as root and password as password to integrate the PTN into the U2000.
If the operation succussed, a new entry will be created under NE information List as below.
Note: For most of time, if an action has been executed successfully, the following window will be pop-out to indicate the operation is succussed, click close to continue.
10
11
Right-click the new-created 910 entry and click configuration; In the new window, select the Upload radio button and click Next to upload the configuration.
The system will finish the uploading process after the progress reach 100%
12
13