S.K.Kaul
18th August 2009
Total
14393
7886
14393 MW 12004 MW
Foreign Suppliers
250 MW
11 MW
Summary of ordering status of TG Sets of HE Projects for likely benefits in 11th Plan
The Hydro capacity addition programme: Ordering Status of T.G. Sets: Indian Supplier BHEL VA Tech Alstom Foreign suppliers 6017 MW 366 MW 339 MW 8905 MW 15627 MW
Manufacturing Capabilities of main indigenous manufacturers for plants & equipment for Hydro Power Plants
Categorisation of capacity of Hydro Plants 12th Plan Type of Scheme ROR STO PSS TOTAL Capacity (MW) 16,116 2,448 1,770 20,334 No. of Stations 77 7 3 87
It is observed that there is an appreciable increase (almost 2 times) in the no. of proposed Hydro Power schemes in the 12th Plan. Thus, there is a need to revisit the Manufacturing capabilities for Plant & Equipment for Hydro Power Plants.
ESTIMATED REQUIREMENT OF EQUIPMENT FOR HYDRO POWER PLANTS FOR 12th & 13th PLANS
No. Equipment 12th Plan (20,000 MW) 13th Plan (24,500 MW) Total
Hydro-Mechanical 1 Gates & Hoist i. Radial Spillway Gates (set) ii. Vertical lift gates (set) Electro-Mechanical 2 3 Turbine (MW) Turbine (No.) 20,130 238 24,495 286 44,625 524 415 630 505 767 920 1397
4
5
48
198
58
241
106
439
ESTIMATED REQUIREMENT OF EQUIPMENT FOR HYDRO POWER PLANTS FOR 12th & 13th PLANS
No. Equipment 12th Plan (20,000 MW) 238 22,366 238 238 1596 13th Plan (24,500 MW) 286 27,216 286 286 1943 Total
6 7 8 9 10
Digital Governor (Set) Synchronous Generator (MVA) Synchronous Generator (No.) Unit Control Board (set) Motor & MCC (unit)
11
12 13
267
238 238
286
286 286
553
524 524
14
238
286
524
ESTIMATED REQUIREMENT OF EQUIPMENT FOR HYDRO POWER PLANTS FOR 12th & 13th PLANS
No. Equipment 12th Plan (20,000 MW) 28,500 13th Plan (24,500 MW) 29,938 Total
15
58,498
16
10,710
12,876
23,586
17 18 19
ESTIMATED REQUIREMENT OF EQUIPMENT FOR HYDRO POWER PLANTS FOR 12th & 13th PLANS
No.
20
Equipment
EHV Equipment Circuit breaker (No.)
12th Plan
(20,000 MW)
13th Plan
(24,500 MW)
Total
390
515
908
1125
522 1344 920 1318 650 167 49 22
1367
640 1627 1120 1604 791 203 60 25
2492
1162 2971 2040 2922 1441 370 109 47
EHV Voltage Transformer (No.) Lightning Arrestor (LA) (No.) Isolator (Set) EHV Current Transformer (Set) 21 22 23 24 415 V Switchgear Board (Unit) 220/400 kV GIS Bay (No.) EHV XLPE Cable (km) EHV Bus Duct (km)
Sl.No. 1 2 3 Cement
Material
Quantity (in million tonne) 12th Plan 19.244 0.684 1.872 13th Plan 23.422 0.833 2.278
New materials and alloys for turbines & other under water parts resistant to the silt damages
Action points
To meet additional capacity requirements for 12th plan & beyond, manufacturers/ suppliers need to take appropriate steps. Advance action shall be taken by Project Authorities to Award Contracts for projects identified for the benefits in the 12th Plan so that timely action can be taken by manufacturers/suppliers Qualifying requirements may be modified/ rationalized to enable financially sound new players to compete. The project promoters should streamline, wherever required, the payment system to have better response from the suppliers. Placement of orders, where in few cases, has taken longer time due to various technical & other intricacies creating uncertainty in the planning process of manufacturers, needs to be expedited.
Action points
Tail end bunching can not be avoided. It is observed that in 11th Plan around 40% of the capacity is programmed to be commissioned in the last half of the year 2011-12. The erection, testing & commissioning engineers/contractors have to plan & gear up accordingly. Better quality control at manufacturer works would reduce the erection as well as operational problems. Manufacturers need to review the quality assurance programme of the E&M and HM equipments. Demand for Gas Insulated supplier (GIS) & XLPE Cables is expected to increase Indigenous manufacturing of such equipments/items need to be pursued more vigorously.
Action points
Delivering of equipment needs to be critically verified right from shop to the site store. Non-receipt of even one item which is essential for commissioning may delay the whole process. Enhance the availability of O&M engineers as shortage of operation & maintenance engineers particularly in Power Stations located in remote/difficult areas may also become a bottle neck in near future