AL-MOHILEB GROUP Almohileb For Contracting PLANNING & CONTROL DEPT.

PRODUCTIVITY RATES
1- SITE WORK Excavation No.
1 2 3 4 5 6 Soft Soil (Hand Tools) Hard Soil (Hand Tools) Soft Soil Hard Soil Soft Soil Hard Soil

Activity

M. P ( Gangs) 1H 1H -

Equipments
Hand Tools Hand Tools Shovel Shovel JCB J.C.B.

Unite
M3/Day M3/Day M3/Hr M3/Hr M3/Hr M3/Hr

Rate 3 1 40 25 20 10

Backfilling
1 2 3 4 Filling in foundation, plinth Level, Compaction Spreading 250mm layer Compaction 250mm layer 1H 1H Shovel Roller Comp. Shovel Roller Compr. M3/Hr M2/Day M2/Hr M2/Day

30 100 100 200

Cement Tiles
1 2 Laying Tiles Tiles on curved lines 1 M +1 H 1 M +1 H M2/Day M2/Day

45 30

Interlock Paving
1 2 3 Compaction / Levelling Spreading Sand and Brushing Laying Tiles 2H 2H 1M+1H Roller Compr. M2/Day M2/Day M2/Day

200 200 60

Precast KerbStone
1 2 3 Excavation & Blinding for Kerbstone Laying Kerbs Karb stone on curved lines 1H 1M+1H 1M+1H R.M/Day R.M/Day R.M/Day

10 35 20

2 - CONCRETE CONCRETE FORMWORK " Shuttering "


1 2 Shutt. of Blinding Shutt. of Raft & Isolate Footing Shutt. of Column Necks 3 4 5 6 7 8 9 10 11 12 Shutt. of Wall Shutt. of Column Shutt. O Connectionf Beam Shutt. of Floor Slab Shutt. of Lintel Shutt. of Parapet Expansion Joints / Ground Slab Shutt. of Beam & Column for H Shutt. of Staircase De-shuttering Works (Cleaning & Arrangement ) 1C+1H 1C+1H 1C+1H 1C+1H 1C+1H 1C+1H 2C+1H 1C+1H 1C+1H 1C+1H M2/Day M2/Day M2/Day M2/Day M2/Day M2/Day M2/Day M2/Day M2/Day L.M/Day M2/Day M2/Day

20 15 6 14 10 12 20 8 12 70 8 12

4m

1C+1H 1C+1H

40% more than Shuttering Works

REINFORCEMENT " Cut & Bend & Fix "


1 2 3 Reinf. of Raft & Isolate Footing Reinf. of Wall Reinf. of Column 1 SF + 1 H 1 SF + 1 H 1 SF + 1 H KG/Day KG/Day KG/Day

500 400 350

4 5 6 7 8

Reinf. ofConnection Beam Reinf. of Floor Slab (Solid & Hollow Block ) Reinf. of Lintel Reinf. of Parapet Reinf. of Staircase

1 SF + 1 H 1 SF + 1 H 1 SF + 1 H 1 SF + 1 H 1 SF + 1 H

KG/Day KG/Day KG/Day KG/Day KG/Day

300 400 200 300 300

CASTING CONCRETE "Readymix"


1 2 3 4 Cast. Blinding 15cm, 10cm Cast. Of Col. & Wall & Staircase Cast. Of Slab and Beams Cast. of Lintel & Parapet 1C+3H 2C+3H 2C+4H 1C+2H Pump Pump Pump Pump FOR ALL CASTING DAY FOR ALL CASTING DAY FOR ALL CASTING DAY FOR ALL CASTING DAY

3 - MASONRY BLOCK WORK


1 2 Solid Block Hollow Block 2M+1H 2M+1H Nos./Day Nos./Day

200 250

4- PLASTER Internal Plaster


1 2 3 4 5 Ceiling Plaster Wall Plaster up to 3m Height Wall Plaster 3m to 6m Height Fixing of Plaster Mesh Fixing of Corner Beed 1M+1H 1M+1H 1M+2H 1C+1H 1M+1H M2/Day M2/Day M2/Day Rm/Day Rm/Day

10 20 17 90 30

External Plaster
1 2 3 Wall Plaster up to 3m Height Wall Plaster 3m to 6m Height Wall Plaster above 6m Height 1M+1H 1M+2H 1M+2H M2/Day M2/Day M2/Day

20 18 15

5- TILING Mosaic
1 2 Floor Mosaic Tiles Mosaic Skirting 1M+1H 1M+1H M2/Day Rm/Day

15 40

Ceramic
1 2 3 4 5 6 7 Fixing of Ceramic Wall Tiles (Glur Type) Grouting of Ceramic Wall Tiles Fixing of Ceramic Floor Tiles 20x20cm Fixing of Ceramic Floor Tiles 30x30cm Fixing of Ceramic Floor Tiles 50x50cm Grouting of Ceramic Floor Tiles Ceramic Skirting 1M+1H 1M+1H 1M+1H 1M+1H 1M+1H 1M+1H 1M+1H M2/Day M2/Day M2/Day M2/Day M2/Day M2/Day Rm/Day

10 30 12 15 20 40 30

Marble & Stone


1 2 3 4 Marble & Stone Wall (Mec. Fixing ) Marble & Stone Floor Marble Skirting Marble Steps (Riser & Treads) 1M+1H 1M+1H 1M+1H 1M+1H M2/Day M2/Day Rm/Day Rm/Day

8 15 30 10

5- False Ceiling
1 False Ceiling - Suspended Type (Tiles&Board&Alu.) 1 FM + 1 H M2/Day

30

6- Painting Normal Paint


1 Primer 1P M2/Day/C oat

150

2 3 4

Stucco (Putty) Emulsion Paint Oil Paint

1P 1P 1P

M2/Day/C oat M2/Day/C oat M2/Day/C oat

40 50 30

NOTS :
One Day is considered as 8 working hours C=Carpenter; M=Mason; P=Painter; SF=Steel Fixer

Prepared By : Eng/ Mohammed Farag

* * * *