Sie sind auf Seite 1von 33

Gorgon Project Barrow Island LNG Plant

SUPPLIERS FRONT SHEET


(FOR A4/A3 DOCUMENTS ONLY)

Purchase Order No. Package Description Suppliers Name Suppliers Reference No.

78500051 DESIGN AND CONSTRUCTION OF LNG JETTY & MARINE STRUCTURES SAIPEM - LEIGHTON CONSORTIUM F10178-KAR-000-PCT-REP / 0-IFL

SUPPLIERS DOCUMENT NO.

Suppliers Rev 91

Suppliers Rev Date 31-JUL-13

Suppliers Name and Signature Prepared Checked Approved SIKB F. BOSQUET T. RAVELET

REVIEW SHALL NOT BE ASSUMED TO INDICATE EITHER RESPONSIBILITY OR LIABILITY FOR ACCURACY AND COMPLETENESS OF THIS DOCUMENT OR TO ALTER ANY CONTRACTUAL TERMS AND CONDITIONS

GORGON PROJECT BARROW ISLAND LNG PLANT


Document Title:

1. AC - ACCEPTED. WORK MAY PROCEED 2. ACC ACCEPTED WITH COMMENTS. PROCEED WITH WORK. INCORPORATE COMMENTS AND RESUBMIT 3. NAC - NOT ACCEPTED. WORK MAY NOT PROCEED. REVISE AND RESUBMIT 4. NR NOT REVIEWED. FOR INFORMATION ONLY

SIKB YARD WEEKLY PROGRESS REPORT


Equipment/Tag Nos.

Name ............................................................................ This document supersede /is superseded by: G1-VE............ PROJECT DOCUMENT NO. Signature ...................................................................... ............ Date .............................................................................. ............
Disc Code Unit No. SDRL PO No. Sequence No. Rev

G1 VE-

- 7000 -

A03

00051

0011

91

GORGON PROJECT - BARROW ISLAND LNG PLANT DESIGN AND CONSTRUCTION OF LNG JETTY & MARINE STRUCTURES

SIKB YARD WEEKLY PROGRESS REPORT

Rev. :

91

Rf.

G1-VE

Z
Disc

7000
Unit No.

A03
SDR

00051
PO No.

0011
Sequential

Page : 2 of 2

REVISION RECORDING

Date 16-MAY-11 23-MAY-11 30-MAY-11 06-JUN-11 13-JUN-11 20-JUN-11 27-JUN-11 04-JUL-11 11-JUL-11 18-JUL-11 25-JUL-11 01-AUG-11 08-AUG-11 15-AUG-11 22-AUG-11 29-AUG-11 05-SEP-11 12-SEP-11

Rev. A B C D E F G H I J K L M N O P Q R

Status IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation

Description of Revision

PT. Saipem Indonesia (Karimun Branch) REPORT SIKB YARD WEEKLY PROGRESS REPORT

Doc. No. SIKB-REP-GOR-PCT-0001 Rev. 117 Date: 31/07/13

Page 3 of 33

19-SEP-11 26-SEP-11 03-OCT-11 10-OCT-11 17-OCT-11 24-OCT-11 31-OCT-11 07-NOV-11 14-NOV-11 21-NOV-11 28-NOV-11 01-DEC-11 08-DEC-11 15-DEC-11 22-DEC-11 29-DEC-11 05-JAN-12 12-JAN-12 19-JAN-12 26-JAN-12 02-FEB-12 09-FEB-12 17-FEB-12

S T U V W X Y Z 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15

IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL

Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation

Uncontrolled when Printed

PT. Saipem Indonesia (Karimun Branch) REPORT SIKB YARD WEEKLY PROGRESS REPORT

Doc. No. SIKB-REP-GOR-PCT-0001 Rev. 117 Date: 31/07/13

Page 4 of 33

23-FEB-12 01-MAR-12 08-MAR-12 15-MAR-12 22-MAR-12 29-MAR-12 05-APR-12 12-APR-12 19-APR-12 26-APR-12 03-MAY-12 10-MAY-12 17-MAY-12 24-MAY-12 31-MAY-12 07-JUN-12 14-JUN-12 21-JUN-12 28-JUN-12 05-JUL-12 12-JUL-12 19-JUL-12 26-JUL-12

16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38

IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL

Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation

Uncontrolled when Printed

PT. Saipem Indonesia (Karimun Branch) REPORT SIKB YARD WEEKLY PROGRESS REPORT

Doc. No. SIKB-REP-GOR-PCT-0001 Rev. 117 Date: 31/07/13

Page 5 of 33

02-AUG-12 09-AUG-12 16-AUG-12 23-AUG-12 30-AUG-12 06-SEP-12 13-SEP-12 20-SEP-12 27-SEP-12 04-OCT-12 11-OCT-12 18-OCT-12 25-OCT-12 01-NOV-12 08-NOV-12 15-NOV-12 22-NOV-12 29-NOV-12 06-DEC-12 13-DEC-12 20-DEC-12 27-DEC-12 03-JAN-13

39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61

IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL

Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation

Uncontrolled when Printed

PT. Saipem Indonesia (Karimun Branch) REPORT SIKB YARD WEEKLY PROGRESS REPORT

Doc. No. SIKB-REP-GOR-PCT-0001 Rev. 117 Date: 31/07/13

Page 6 of 33

10-JAN-13 17-JAN-13 24-JAN-13 31-JAN-13 07-FEB-13 14-FEB-13 21-FEB-13 28-FEB-13 07-MAR-13 14-MAR-13 20-MAR-13 27-MAR-13 03-APR-13 10-APR-13 17-APR-13 24-APR-13 01-MAY-13 08-MAY-13 15-MAY-13 22-MAY-13 29-MAY-13 05-JUN-13 12-JUN-13

62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84

IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL IFL

Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation

Uncontrolled when Printed

PT. Saipem Indonesia (Karimun Branch) REPORT SIKB YARD WEEKLY PROGRESS REPORT

Doc. No. SIKB-REP-GOR-PCT-0001 Rev. 117 Date: 31/07/13

Page 7 of 33

19-JUN-13 26-JUN-13 03-JUL-13 10-JUL-13 17-JUL-13 24-JUL-13 31-JUL-13

85 86 87 88 89 90 91

IFL IFL IFL IFL IFL IFL IFL

Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation Issued for Implementation

Uncontrolled when Printed

PT. Saipem Indonesia (Karimun Branch) REPORT SIKB YARD WEEKLY PROGRESS REPORT

Doc. No. SIKB-REP-GOR-PCT-0001 Rev. 117 Date: 31/07/13

Page 8 of 33

Uncontrolled when Printed

PT. Saipem Indonesia (Karimun Branch) REPORT SIKB YARD WEEKLY PROGRESS REPORT

Doc. No. SIKB-REP-GOR-PCT-0001 Rev. 117 Date: 31/07/13

Page 9 of 33

PT. Saipem Indonesia (Karimun Branch) REPORT

SIKB YARD WEEKLY PROGRESS REPORT

SIKB-REP-GOR-PCT-0001

31/07/13

117

Approved for Use

F.Listiyana PCT Prepared

J. Sarmiento PCT Checked

F. Bosquet PMT Verified

L. Romano OPER Approved

Date

Revision

Description of Revision

This document is the property of Saipem who will safeguard its rights according to the civil and penal provisions of the law. All printed copies are considered uncontrolled and the validity of this document shall be verified via the DMS SharePoint before use.

Uncontrolled when Printed

PT. Saipem Indonesia (Karimun Branch) REPORT SIKB YARD WEEKLY PROGRESS REPORT

Doc. No. SIKB-REP-GOR-PCT-0001 Rev. 117 Date: 31/07/13

Page 10 of 33

Revision Summary

Date

Revision

Description of Revision

Prepared G. Pinna PCT M.Rizal P PCT M.Rizal P PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT

Checked L. Iacoponi PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT

Verified

Approved D. Durelli PMT F.Thery PMT F.Thery PMT L. Romano PMT L. Romano PMT L. Romano PMT L. Romano PMT L. Romano PMT L. Romano PMT L. Romano PMT L. Romano PMT L. Romano PMT L. Romano PMT L. Romano PMT G.Gonzales OPER L. Romano PMT L. Romano PMT

16/05/11

01

Approved for Use

23/05/11

02

Approved for Use

30/05/11

03

Approved for Use

06/06/11

04

Approved for Use

13/06/11

05

Approved for Use

20/06/11

06

Approved for Use

27/06/11

07

Approved for Use

04/07/11

08

Approved for Use

11/07/11

09

Approved for Use

18/07/11

10

Approved for Use

25/07/11

11

Approved for Use

01/08/11

12

Approved for Use

08/08/11

13

Approved for Use

15/08/11

14

Approved for Use

22/08/11

15

Approved for Use

29/08/11

16

Approved for Use

01/09/11

17

Approved for Use

Uncontrolled when Printed

PT. Saipem Indonesia (Karimun Branch) REPORT SIKB YARD WEEKLY PROGRESS REPORT

Doc. No. SIKB-REP-GOR-PCT-0001 Rev. 117 Date: 31/07/13

Page 11 of 33

12/09/11

18

Approved for Use

M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT

G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT

L. Romano PMT L. Romano PMT L. Romano PMT L. Romano PMT L. Romano PMT G Gonzales OPER L. Romano PMT L. Romano PMT L. Romano PMT L. Romano PMT L. Romano PMT L. Romano PMT L. Romano PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT

19/09/11

19

Approved for Use

26/09/11

20

Approved for Use

03/10/11

21

Approved for Use

10/10/11

22

Approved for Use

17/10/11

23

Approved for Use

24/10/11

24

Approved for Use

31/10/11

25

Approved for Use

07/11/11

26

Approved for Use

14/11/11

27

Approved for Use

21/11/11

28

Approved for Use

28/11/11

29

Approved for Use

01/12/11

30

Approved for Use

08/12/11

31

Approved for Use

15/12/11

32

Approved for Use

22/12/11

33

Approved for Use

29/12/11

34

Approved for Use

05/01/12

35

Approved for Use

12/01/12

36

Approved for Use

19/01/12

37

Approved for Use

Uncontrolled when Printed

PT. Saipem Indonesia (Karimun Branch) REPORT SIKB YARD WEEKLY PROGRESS REPORT

Doc. No. SIKB-REP-GOR-PCT-0001 Rev. 117 Date: 31/07/13

Page 12 of 33

26/01/12

38

Approved for Use

M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT

G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT

F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT L. Romano OPER L. Romano OPER F. Bosquet PMT F. Bosquet PMT

02/02/12

39

Approved for Use

09/02/12

40

Approved for Use

17/02/12

41

Approved for Use

23/02/12

42

Approved for Use

01/03/12

43

Approved for Use

08/03/12

44

Approved for Use

15/03/12

45

Approved for Use

22/03/12

46

Approved for Use

29/03/12

47

Approved for Use

05/04/12

48

Approved for Use

12/04/12

49

Approved for Use

19/04/12

50

Approved for Use

26/04/12

51

Approved for Use

03/05/12

52

Approved for Use

10/05/12

53

Approved for Use

17/05/12

54

Approved for Use

24/05/12

55

Approved for Use

31/05/12

56

Approved for Use

07/06/12

57

Approved for Use

Uncontrolled when Printed

PT. Saipem Indonesia (Karimun Branch) REPORT SIKB YARD WEEKLY PROGRESS REPORT

Doc. No. SIKB-REP-GOR-PCT-0001 Rev. 117 Date: 31/07/13

Page 13 of 33

14/06/12

58

Approved for Use

M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT

G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT

F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT

F. Bosquet PMT L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER

21/06/12

59

Approved for Use

28/06/12

60

Approved for Use

05/07/12

61

Approved for Use

12/07/12

62

Approved for Use

19/07/12

63

Approved for Use

26/07/12

64

Approved for Use

02/08/12

65

Approved for Use

09/08/12

66

Approved for Use

16/08/12

67

Approved for Use

23/08/12

68

Approved for Use

30/08/12

69

Approved for Use

06/09/12

70

Approved for Use

13/09/12

71

Approved for Use

20/09/12

72

Approved for Use

27/09/12

73

Approved for Use

04/10/12

74

Approved for Use

11/10/12

75

Approved for Use

18/10/12

76

Approved for Use

25/10/12

77

Approved for Use

Uncontrolled when Printed

PT. Saipem Indonesia (Karimun Branch) REPORT SIKB YARD WEEKLY PROGRESS REPORT

Doc. No. SIKB-REP-GOR-PCT-0001 Rev. 117 Date: 31/07/13

Page 14 of 33

01/11/12

78

Approved for Use

M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT

G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT G. Pinna PCT L. Iacoponi PCT L. Iacoponi PCT L. Iacoponi PCT L. Iacoponi PCT L. Iacoponi PCT L. Iacoponi PCT G. Limblici PCT G. Limblici PCT G. Limblici PCT G. Limblici PCT G. Limblici PCT G. Limblici PCT G. Limblici PCT

F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT G. Andrighetto PMT G. Andrighetto PMT G. Andrighetto PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT

L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER

08/11/12

79

Approved for Use

15/11/12

80

Approved for Use

22/11/12

81

Approved for Use

29/11/12

82

Approved for Use

06/12/12

83

Approved for Use

13/12/12

84

Approved for Use

20/12/12

85

Approved for Use

27/12/12

86

Approved for Use

03/01/13

87

Approved for Use

10/01/13

88

Approved for Use

17/01/13

89

Approved for Use

24/01/13

90

Approved for Use

31/01/13

91

Approved for Use

07/02/13

92

Approved for Use

14/02/13

93

Approved for Use

21/02/13

94

Approved for Use

28/02/13

95

Approved for Use

07/03/13

96

Approved for Use

14/03/13

97

Approved for Use

Uncontrolled when Printed

PT. Saipem Indonesia (Karimun Branch) REPORT SIKB YARD WEEKLY PROGRESS REPORT

Doc. No. SIKB-REP-GOR-PCT-0001 Rev. 117 Date: 31/07/13

Page 15 of 33

20/03/13

98

Approved for Use

M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT M. Ekopramono PCT R. Yulita PCT R. Yulita PCT R. Yulita PCT R. Yulita PCT R. Yulita PCT R. Yulita PCT R. Yulita PCT R. Yulita PCT R. Yulita PCT R. Yulita PCT R. Yulita PCT R. Yulita PCT R. Yulita PCT F. Listiyana PCT F. Listiyana PCT F. Listiyana PCT

G. Limblici PCT G. Limblici PCT G. Limblici PCT G. Limblici PCT G. Limblici PCT G. Limblici PCT G. Limblici PCT G. Limblici PCT G. Limblici PCT L. Iacoponi PCT G. Limblici PCT G. Limblici PCT G. Limblici PCT G. Limblici PCT G. Limblici PCT G. Limblici PCT G. Limblici PCT J. Sarmiento PCT J. Sarmiento PCT J. Sarmiento PCT

F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT G. Andrighetto PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT F. Bosquet PMT

L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER L. Romano OPER

27/03/13

99

Approved for Use

03/04/13

100

Approved for Use

10/04/13

101

Approved for Use

17/04/13

102

Approved for Use

24/04/13

103

Approved for Use

01/05/13

104

Approved for Use

08/05/13

105

Approved for Use

15/05/13

106

Approved for Use

22/05/13

107

Approved for Use

29/05/13

108

Approved for Use

05/06/13

109

Approved for Use

12/06/13

110

Approved for Use

19/06/13

111

Approved for Use

26/06/13

112

Approved for Use

03/07/13

113

Approved for Use

10/07/13

114

Approved for Use

17/07/13

115

Approved for Use

24/07/13

116

Approved for Use

31/07/13

117

Approved for Use

Uncontrolled when Printed

PT. Saipem Indonesia (Karimun Branch) REPORT SIKB YARD WEEKLY PROGRESS REPORT

Doc. No. SIKB-REP-GOR-PCT-0001 Rev. 117 Date: 31/07/13

Page 16 of 33

Uncontrolled when Printed

PT. Saipem Indonesia (Karimun Branch) REPORT SIKB YARD WEEKLY PROGRESS REPORT

Doc. No. SIKB-REP-GOR-PCT-0001 Rev. 117 Date: 31/07/13

Page 17 of 33

TABLE OF CONTENTS
1. FOREWORD.................................................................................................................... 19 2. HSE STATUS................................................................................................................... 19
2.1 Activities Performed Last Week .........................................................................................19 2.2 Activities to be performed next Week ................................................................................21 2.3 Areas of Concern ............................................................................................................... 22

3. QUALITY ASSURANCE AND CONTROL......................................................................22


3.1 Activities Performed Last Week..........................................................................................22 3.1.1 Loading Platform (LP) Deck & Jackets.............................................................22 3.2 Activities to be performed next Week ................................................................................23 3.2.1 Loading Platform (LP) Deck & Jackets.............................................................23 3.3 Areas of Concern ............................................................................................................... 23

4. MANAGEMENT AND SERVICES....................................................................................23


4.1 Info...................................................................................................................................... 23 4.2 Activities Performed Last Month......................................................................................... 23 4.3 Activities to be performed next Month.................................................................................23 4.4 Areas of Concern ............................................................................................................... 23

5. ENGINEERING............................................................................................................... 24
5.1 Activities Performed Last Week .........................................................................................24 5.1.1 Loading Platform (LP) Deck & Jackets.............................................................24 5.1.2 Piles & Pontoon.................................................................................................... 24 5.2 Activities to be performed Next Week ................................................................................24 5.2.1 Loading Platform (LP) Deck & Jackets ............................................................24 5.2.2 Piles & Pontoon.................................................................................................... 25 5.3 Areas of Concern ............................................................................................................... 25

6. PROCUREMENT AND SUPPLY......................................................................................26


6.1 Activities Performed This Week .........................................................................................26 6.1.1 Loading Platform (LP) Deck & Jackets.............................................................26 6.1.2 Piles & Pontoon ................................................................................................... 26 6.2 Activities to be performed Next Week ................................................................................26 6.2.1 Loading Platform (LP) Deck & Jackets.............................................................26 6.2.2 Piles & Pontoon ................................................................................................... 26 6.3 Areas of Concern ............................................................................................................... 26

7. CONSTRUCTION............................................................................................................. 26
7.1 Activities performed Last Week..........................................................................................26 7.1.1 Loading Platform (LP) Deck & Jackets.............................................................26 7.1.2 Piles & Pontoon.................................................................................................... 27 7.2 Activities to be performed next Week ...............................................................................27 7.2.1 Loading Platform (LP) Deck & Jackets.............................................................27 7.2.2 Piles & Pontoon.................................................................................................... 27 7.3 Areas of Concern................................................................................................................ 27

8. QUARANTINE.................................................................................................................. 27 9. ATTACHMENT................................................................................................................. 32
9.1 Weight Report (SOW no. 1 & SOW no. 2)..........................................................................32 9.2 SIKB fabrication document register....................................................................................32 9.3 Concession Request (CR).................................................................................................. 32 9.4 Request For Information (RFI)............................................................................................ 32 9.5 Progress Picture................................................................................................................. 33 9.6 Overall Physical Progress Report Loading Platform & Jackets..........................................33 9.7 Overall Progress S Curve-Rev.5 Loading Platform & Jackets............................................33 9.8 Procurement Plan (SOW no. 1 & SOW no. 2)....................................................................33 9.9 List AFC Drawings.............................................................................................................. 33

Uncontrolled when Printed

PT. Saipem Indonesia (Karimun Branch) REPORT SIKB YARD WEEKLY PROGRESS REPORT

Doc. No. SIKB-REP-GOR-PCT-0001 Rev. 117 Date: 31/07/13

Page 18 of 33

9.10 Overall Physical Progress Report Pontoons, Piles, Access Ramps & Gangways............33 9.11 Overall Progress S Curve Pontoons, Piles, Access Ramps & Gangways .......................33

Uncontrolled when Printed

PT. Saipem Indonesia (Karimun Branch) REPORT SIKB YARD WEEKLY PROGRESS REPORT

Doc. No. SIKB-REP-GOR-PCT-0001 Rev. 117 Date: 31/07/13

Page 19 of 33

1. FOREWORD
SLC inform on barge arrival on 2nd august and Load out 12 august. SIKB alerted that this period of the year is extremely difficult due to the end of Ramadan and low attendance from personnel. SLC has confirmed those dates. Planning of load out issue to SLC and CPY. MDR Preparation for Jacket Scope under finalization (98% Completed). Documentation balance are: o Balance NCR27/29 for DC on Jacket and Deck legs superposition. Additional DC required on 4 legs. SIKB to implement o Submit RLMU issued to Perth SLC. o Final reports of IRC ( after quarantine) Piles design change: final clarification to be received. SLC to expedite final requirements for design of Pad eyes on Domgas piles. Pontoons and Piles Barge layout to be received from Project. SIKB request assistance from Project for the Pontoons water 2 valves impossible to source. SLC to expedite all SIKB Pending RFI ( test pressure of the pontoons, sequence, etc).

2. HSE STATUS 2.1 Activities Performed Last Week Weekly tool box meeting themes : - Work at height in confine space. - Lesson and learn from latest incident. - Safety work near water. - Work at height in confine space. - Use correct additional PPE. - Safe on mobile elevating work platforms - Sand Blasting safety. - Safe painting inside confine space. - Fire Prevention. - Burning inside confine space safety. - Safe work in hanging scaffolding. - Beware electrical hazard - Beware falling object. - Heat stress. - Noise hazard. - Use sharp hand tool safety. - Housekeeping and management. - Hazardous substances. - Quarantine awareness Blooming Insect Conduct in-house trainings : - Confine Space. - Work at height. - Hand and Power Tools Operation - Safe Welding, Grinding and Cutting. - Scaffolding safe access and egress. - Noise and Hearing protection. - Manual handling. - Energy and water conservation . - Waste management. - Quarantine awareness. Highlight the latest incident to all workers on TBT. Keep continue socialization and monitored implemented of JSA for working on jacket

Uncontrolled when Printed

PT. Saipem Indonesia (Karimun Branch) REPORT SIKB YARD WEEKLY PROGRESS REPORT

Doc. No. SIKB-REP-GOR-PCT-0001 Rev. 117 Date: 31/07/13

Page 20 of 33

legs to all workers involved. Ensure all equipments (blower, flexible hose, etc.) and additional PPE in place and acceptable. Ensure condition of man-basket has been check by competent person and filled the checklist. Ensure and keep monitored the blasting and painting activities in accordance with the procedure. Especially for blasting and painting inside confine space (pontoon). Ensure only fire proof light used for activities painting inside confine space. Socialization JSA and procedure Painting and Blasting for pontoon to every worker involved. Monitored PFP for deck activities comply with the SIKB procedure requirement. Ensure all hazardous waste and toxic waste from PFP activities send to hazardous waste building daily based. Keep monitoring and improve the housekeeping/management, coordinated with team leader for arrange cable and hoses properly. Ensure proper scaffold structures erected for deck and pontoons. Keep continue Incentive program for monthly and weekly. Keep continued equipment inspections by supervisor (Gas and connections, also pneumatic tool and connection) with HSE officer. Preparation for load out and tagging system. Prepare JSA for pontoon leak test (pneumatic test and hydraulic test). Quarantine Weekly Walk every Saturday morning. Keep continue discussion about quarantine delivered to all worker once a week when TBT, for information and to raise quarantine awareness. Keep remind all team leaders about quarantine and hygiene matter, especially for team working in jacket legs and installation of fence at Qwall.

Uncontrolled when Printed

PT. Saipem Indonesia (Karimun Branch) REPORT SIKB YARD WEEKLY PROGRESS REPORT

Doc. No. SIKB-REP-GOR-PCT-0001 Rev. 117 Date: 31/07/13

Page 21 of 33

NO
1 2 3 4 5 6 7 8 9

LEADING INDIC ATOR


Lost Tim e Injury ( LTI) Restricted Work Case (RWC) Medical treatm ent Case (MTC) First Aid Case (FAC) Lost Tim e Injury Frequency Rate(LTIFR) Total Recordable Injury Frequency Rate (TRIFR) Property Dam age (m ajor)

PROJEC T TARGET / MEAS URING FACTORS


Continuous and substantial reduction in order to finally reach our 0 accident 0 incident goal Continuous and substantial reduction in order to finally reach our 0 accident 0 incident goal Continuous and substantial reduction in order to finally reach our 0 accident 0 incident goal Continuous and substantial reduction in order to finally reach our 0 accident 0 incident goal 0.00 (per Million m an hours) 1.15 (per Million m an hours)

CURRENT WEEK
SAIPEM SUBCONTRACTOR

TOTAL SINCE BEGINNING PROJECT

0 0 0 0 0 0 0 0 1 6507 803,407 50 1 0 2 12

0 0 0 0 0 0 0 0 0 4878 581,368

0 1 4 10 0 3.61 0 0 5 11,385 1,384,775 6,027 128 5 49 5,409

Continuous and substantial reduction in order to finally reach our 0 accident 0 incident goal Continuous and substantial reduction in order to finally reach our 0 Environment Pollution Incident accident 0 incident goal Near m iss reports Not Set - Reported with no objective Not Set Record with no objective Not Set Record with no objective Safety Hazards Observation Cards (3 SHOC cards per 1000 MHW) 1 Per Week Not Set

10 Total Hours Worked Week 26 Total Hours Worked Since 11 Beginning of Project Num ber of Safety Hazards 12 Observation Cards 13 Site Managem ent Inspection 14 Num ber of Em ergency Drill 15

Num ber of Senior Managem ent Not Set HSE visits on site HSE Training (15 hours per 16 171 hours 1000 MHW)

LEADING INDICATORS
NO
1 2 3 4 5

MANHOURS
11385 11385 11385 11385 11385

MEAS URING FAC TORS


Toolbox Talks (2.5 Sheets per 1000 MHW) Job Safety Analysis (1.5 Item s per 1000 MHW) HSE Inspection (1.3 Items per 1000 MHW) HSE Meeting (0.18 hours per 1000 MHW) Safety Hazards Observation Cards (3 SHOC cards per 1000 MHW)

TARGET
29 18 15 3 35

ACTUAL
32 25 31 2 50

PRECENTAGE
110% 139% 207% 67% 143%

2.2 Activities to be performed next Week Weekly tool box meeting themes : - Lesson and learn from latest incident. - Use masker: unhealthy smoke and haze. - Safety work near water. - Sand Blasting safety. - Safe painting inside confine space. - Safe distance between gas cylinder and hot work. - Burning inside confine space safety. - Beware electrical hazard - Beware falling object. - Housekeeping and management.

Uncontrolled when Printed

PT. Saipem Indonesia (Karimun Branch) REPORT SIKB YARD WEEKLY PROGRESS REPORT

Doc. No. SIKB-REP-GOR-PCT-0001 Rev. 117 Date: 31/07/13

Page 22 of 33

- Waste management. - Quarantine awareness Common Sow thistle Conduct in-house trainings : - Confine Space. - Work at height. - SHO Card. - PPE - Hand and Power Tools Operation - Safe Welding, Grinding and Cutting. - Scaffolding safe access and egress. - Noise and Hearing protection. - Manual handling. - Environment aspect assessment. Highlight the latest incident to all workers on TBT. Keep remind all worker and team leaders for more attentions about fire hazard thru TBT. Coordinated with team leaders in painting shed for take attentions about Housekeeping in that area, placement of the sand bag, paint tins, thinner, unused paint tins, etc. Keep continue socialization and monitored implemented of JSA for painting inside confine space to all workers involved. Ensure only fire proof light used for activities painting inside confine space. Ensure proper scaffold structures erected for deck and pontoons. Keep continued equipment inspections by supervisor (Gas and connections, also pneumatic tool and connection) with HSE officer. Ensure pontoon transfer by SPMT accordance with procedure. Preparation for load out and tagging system. Prepare JSA for pontoon leak test (pneumatic test and hydraulic test). Keep continue Incentive program for weekly. Quarantine Weekly Walk every Saturday morning. Keep continue discussion about quarantine delivered to all worker once a week when TBT, for information and to raise quarantine awareness. Keep remind all team leaders about quarantine and hygiene matter, especially at Qwall.
.

2.3 Areas of Concern


Lay down area Prefabrication workshop Assembly Hall Blasting and Painting Shed Final quarantine/erection area/Quay wall area.

3.

QUALITY ASSURANCE AND CONTROL 3.1 Activities Performed Last Week 3.1.1 Loading Platform (LP) Deck & Jackets
Continued coordination on MDR compilation for Gorgon Project. Continue to monitor Yard Issue Register (YIR). Follow-up and closure of outstanding NCRs both internal and external. Updating painting & hydrostatic testing activities on fabrication ITP.

Uncontrolled when Printed

PT. Saipem Indonesia (Karimun Branch) REPORT SIKB YARD WEEKLY PROGRESS REPORT

Doc. No. SIKB-REP-GOR-PCT-0001 Rev. 117 Date: 31/07/13

Page 23 of 33

Continued in process of fit up visual inspection. Continued in process dimensional inspections Continued check of Material receiving for Gorgon project at warehouse. NDT for Fabrication Progress at prefab for piles and pontoon Continued monitoring and check material identification traceability in warehouse. On-going calibration of new testing instruments and validation at the laboratory and fabrication shop. .

3.2 Activities to be performed next Week 3.2.1 Loading Platform (LP) Deck & Jackets
Continue to monitor Yard Issue Register (YIR). Continue to coordinate the MDR compilation of DECK, PONTOON & PILES for Gorgon Project. Follow-up and closure of outstanding NCRs both internal and external. Continue in process dimensional inspections and visual inspection on-going fabrication at shop Assembly, Bay No.3 and Bay No.2 for Jacket and Deck Fabrication Gorgon Project in progress. Continue monitoring and check of material identification and traceability in the warehouse. Continue calibration/validation of new equipment at the laboratory and fabrication shop. Continue monitoring and inspection painting and blasting activities at painting shop and assembly shop.

3.3 Areas of Concern


SIKB 029(Jacket Leg) & 030(Deck) to be closed before jacket load-out. DC report of jacket leg already submitted to SLC ENG., for evaluation & acceptance. DC report of deck will soon be submitted to SLC Eng., for evaluation & acceptance.

4. MANAGEMENT AND SERVICES 4.1 Info


Close monitoring of the progress of the decks required.

4.2 Activities Performed Last Month


Weekly progress Meeting with KJV Representative held every Wednesday.

4.3 Activities to be performed next Month


. Weekly progress Meeting with KJV Representative held every Wednesday.

4.4 Areas of Concern


Finalization of all equipment in view of the preparation for load out of the Jacket. East and West deck fabrication progress to be followed with all attention from management from both SIKB and SLC Issue related to internal SIKB RFI to be included into the MDR to be expedited.

Uncontrolled when Printed

PT. Saipem Indonesia (Karimun Branch) REPORT SIKB YARD WEEKLY PROGRESS REPORT

Doc. No. SIKB-REP-GOR-PCT-0001 Rev. 117 Date: 31/07/13

Page 24 of 33

5.

ENGINEERING 5.1 Activities Performed Last Week 5.1.1 Loading Platform (LP) Deck & Jackets

Issued revision document SIKB Yard Hydrotest Procedure For Pontoon 1, 2 And 3 Issued revision document SIKB Fabrication Yard Positive Material Identification Procedure Issued revision drawing for SLP East & West Welding Map Issued revision method drawing for Gorgon Part Loadout Barge Manhole Quarantine
Issued RFI 322

Issued revision welding map for EAST & WEST Welding Map
Prepare Redline Mark-Up for Deck loading Platform. Issued revision Redline Mark-Up for Jacket Loading Platform Assist production and QC for technical clarification Continue method drawing preparation for : o East & West Deck Weighing General arrangement o East & West Deck North & South Part Stud Bolts General Arrangement o East Deck South Part Erection Breakdown Structure o East Deck North Part Erection Breakdown Structure o East Deck South Part Construction Sequence Preparation of new welder certificate and welder register (routine activity) WQT activities at PT. DUJ Batam

5.1.2 Piles & Pontoon Continue update revision shop drawing Pontoon (PT1, PT2 & PT3), 4 drawing Issued shop drawing for Piping Support Pontoon (PT1, PT2 & PT3), 3 drawing Issued welding map drawing for pontoon (PT1) Issued Method Statement for sequence of pontoon testing (Hydro Test and Leak Test) Issued RFI 324 Issued revision mark drawing for channel navigation aids Issued revision document SIKB YARD Pontoon Air Pressure Testing Procedure Prepare Red Lines Mark up for Pontoon and Piles.

5.2 Activities to be performed Next Week 5.2.1 Loading Platform (LP) Deck & Jackets Prepare Red-line Mark Up for deck Prepare DCR (design change record) for Jacket and Deck Continue update xml and WSL and uploaded into FDBT Review and respond documents and/or technical queries from subcontractor (if any) Review documents from PFP applicators, PMS and PTE (if any) Prepare design change record (if any) Issue RFI and ERR (if any) Issue PR (if any)

Uncontrolled when Printed

PT. Saipem Indonesia (Karimun Branch) REPORT SIKB YARD WEEKLY PROGRESS REPORT

Doc. No. SIKB-REP-GOR-PCT-0001 Rev. 117 Date: 31/07/13

Page 25 of 33

Continue method study for lifting, transportation, support, fabrication shop, assembly hall, erection arrangement, loadout, weighing, mooring, grillage, sea fastening. Continue preparation of new welder certificate and welder register Prepare PQR for SS 316L Finalize constructability of the project Renewal welder expiration date

5.2.2 Piles & Pontoon


Prepare DCR (design change record) for Pontoon and Piles Prepare Red-Lines Mark Up for Pontoon and Piles Revision of shop drawing (if any) Prepare design change record (if any) Issue RFI and ERR (if any) Issue PR (if any) Prepared PEP SOW 2 revision Review and respond documents and/or technical queries from subcontractor (if any) Formalize method statement for pontoon construction, fuel line, potable water and ventsuction line Method drawings issuance (if any) Prepare methode statement for E & I installation & test for Pontoon (if any)

5.3 Areas of Concern


Site Queries pending : o F10178-KAR-SLC-RFI-0184 - PILES Barge lay-out, Sea fastening, Grillage o F10178-KAR-SLC-RFI-0215 - SOW 1: Requirements for Material certificates o F10178-KAR-SLC-RFI-0231 - SOW 2 Clarification of SOW for Patron Power Pedestal o F10178-KAR-SLC-RFI0255 - SOW 2 - Clarification Of Details Drawing For Lifting Padeyes o F10178-KAR-SLC-RFI0256 - SOW 2 - Electrical Works on Pontoon scope o F10178-KAR-SLC-RFI-0272 SOW1 Weld cutback detail on LP for offshore installation o F10178-KAR-SLC-RFI-0284 - SOW 2 Pontoon Piping - Valves potable water system o F10178-KAR-SLC-RFI-0290 - SOW 2 - Proposal For Ladder Fixation o F10178-KAR-SLC-RFI-0291 - SOW 2 Pontoon piping cam coupling scope o F10178-KAR-SLC-RFI-0300 - SOW1 Proposal For Change Dimension Of Gangways Bracing o F10178-KAR-SLC-RFI-0304 - SOW 2 Clarification of Additional SOW for Piles o F10178-KAR-SLC-RFI-0306 - SOW1 Clarification on RFI/CR for SIKB RFI o F10178-KAR-SLC-RFI-0309 - SOW 2 Pontoon Leak testing o F10178-KAR-SLC-RFI-0310 - SOW 2 Pontoon Leak testing bulkheads temporary opening o F10178-KAR-SLC-RFI-0312 - SOW 2 The Piping Diesel Line o F10178-KAR-SLC-RFI-0313 - SOW 2 - Clarify for Vent & Suction Valves Name Tag o F10178-KAR-SLC-RFI-0314 - SOW 2 - Proposal For Change NDT Category o F10178-KAR-SLC-RFI-0316 - SOW 2 Clarification of Bolt on Channel Navigation Aids o F10178-KAR-SLC-RFI-317 SOW 2 Proposal To Move Portable Water Line Position o F10178-KAR-SLC-RFI-318 SOW1 Quarantine closure box girders of deck o F10178-KAR-SLC-RFI-0319 SOW 2 Need Documents Related To Comments Of Document Mechanical Completion Procedure o F10178-KAR-SLC-RFI-320 Excluding Lines for All Scope

Uncontrolled when Printed

PT. Saipem Indonesia (Karimun Branch) REPORT SIKB YARD WEEKLY PROGRESS REPORT

Doc. No. SIKB-REP-GOR-PCT-0001 Rev. 117 Date: 31/07/13

Page 26 of 33

o o o

F10178-KAR-SLC-RFI-321 SOW 1 Request Official Drawing for Jacket Red Line Mark-Up F10178-KAR-SLC-RFI-322 SOW 2 - Proposal To Change Design Pressure For Leak Test F10178-KAR-SLC-RFI-323 SOW 1 East and West Deck Flip Over Lifting General Arrangement F10178-KAR-SLC-RFI-324 SOW 2 Bollard Installation on Pontoon 1, 2 & 3

Design drawings pending: o Final Grillage and sea fastening drawing for K1 & K2 Deck

6. PROCUREMENT AND SUPPLY 6.1 Activities Performed This Week 6.1.1 Loading Platform (LP) Deck & Jackets
N/A.

6.1.2 Piles & Pontoon


PO 817544 Cable Penetration Fiilling has been received at yard PO 586490 Jetty template has been received at yard

6.2 Activities to be performed Next Week 6.2.1 Loading Platform (LP) Deck & Jackets
N/A

6.2.2 Piles & Pontoon


Prepare PR Cable Leader For Channel Navigation Aids

6.3 Areas of Concern


N/A

7. CONSTRUCTION 7.1 Activities performed Last Week 7.1.1 Loading Platform (LP) Deck & Jackets
Erection East Deck Gangway Tower finished Install Nelson Studs West Deck Section South continued

Uncontrolled when Printed

PT. Saipem Indonesia (Karimun Branch) REPORT SIKB YARD WEEKLY PROGRESS REPORT

Doc. No. SIKB-REP-GOR-PCT-0001 Rev. 117 Date: 31/07/13

Page 27 of 33

7.1.2

Piles & Pontoon


Painting Pontoon 1 finished Painting Pontoon 2 finished Pontoon 3 moved to painting shed, ready for painting Fabrication & Assembly Access Platform & Ladder continued

7.2 Activities to be performed next Week 7.2.1 Loading Platform (LP) Deck & Jackets
Erection East Deck Gangway Tower finish Install nelson studs on West Deck Section South continue

7.2.2

Piles & Pontoon


Painting Pontoon 1 finish Painting Pontoon 2 finish Painting Pontoon 3 Fabrication & Assembly Access Platform & Ladder continued

7.3 Areas of Concern


Specific attention required to Progress on the Deck refabrication. Readyness of the stainless steel workshop in the yard.

8. QUARANTINE 1.1

ACTIVITIES TO BE PERFORMED LAST WEEK


The documents o QMP rev. 08 (G1-VE-B-7000-A19-00051-0039_08) issue for construction Housekeeping, concern area: Prefabrication Shop o Regularly housekeeping around Gorgon project area. o Keeping rubbish in waste bins with a tight-fitting lid that are emptied regularly. o Regular inspection by Quarantine Officer. Assembly Hall o Daily cleaning/housekeeping around this area. o Keeping rubbish in waste bins with a tight-fitting lid that are emptied regularly. o Regular inspection by Quarantine Officer. Painting Sheds o Regularly housekeeping around this area. o Keeping rubbish in waste bins with a tight-fitting lid that are emptied regularly. o Regular inspection by Quarantine Officer. Final Storage & Erection Site o Regular housekeeping this area. o Close the opened piles with tarpaulin. o Regular inspection by Quarantine Officer.

Uncontrolled when Printed

PT. Saipem Indonesia (Karimun Branch) REPORT SIKB YARD WEEKLY PROGRESS REPORT

Doc. No. SIKB-REP-GOR-PCT-0001 Rev. 117 Date: 31/07/13

Page 28 of 33

Load Out Area o Regular housekeeping around fences and hydraulic winch. o Regular inspection by Quarantine Officer. Pest Control activities

o The pest control Contractor monitoring the rat box, trigonal glue traps, cat/dog traps and Mobe
Moat on daily basis, and reported to the Quarantine Officer if any quarantine risk material trapped on the trap, and they will be replace the bait every two weeks.

Number of traps implemented at Gorgon Project area (updated 03 July 2013)

o Maintain salt barrier surround quarantine fences at Jacket and Load Out area.

o Replace moat at Final Storage & Erection Site.

o Covering the opened holes at connector for quarantine fences with adhesive tape. This activity has been done at Final Storage & Erection Site.

Uncontrolled when Printed

PT. Saipem Indonesia (Karimun Branch) REPORT SIKB YARD WEEKLY PROGRESS REPORT

Doc. No. SIKB-REP-GOR-PCT-0001 Rev. 117 Date: 31/07/13

Page 29 of 33

Residual insecticide spraying Regular insecticide spraying has been performed at toilet facilities, waste bins, Raw Material Storage, Prefabrication Shop, Assembly Hall, Final Storage & Erection Site and Load out Area. These activities are done at early morning (05:00hrs - 06:30hrs) by Pest Control contractor.

Insecticides spraying inside Leg Jacket and top cover plates at CD East Row C2, C3, D1, D2, AB East Row A2, A3 and B3 have been done after shim plates removed and cleaning activities finish.

Note: Chemical used for insecticide spraying is Bifenthrin, product name is BISTAR 25 g/L EC INSECTICIDE / MITICIDE. o Weed killer Weeds eradicated by two treatments, the first is manually pull out the weeds; and the second is prevent weeds growing by perform herbicide spraying. The active ingredient of chemical used for herbicide spraying is Glyphosate isopropyl amine salt, name of product is Roundup 486 SL. This activity has been performed at Final Storage & Erection Site.

o Fumigation Thermal fumigation has been performed around Raw Material Storage, Prefabrication Shop,

Uncontrolled when Printed

PT. Saipem Indonesia (Karimun Branch) REPORT SIKB YARD WEEKLY PROGRESS REPORT

Doc. No. SIKB-REP-GOR-PCT-0001 Rev. 117 Date: 31/07/13

Page 30 of 33

Assembly Hall and Final Storage & Erection Site. These activities are done at early morning (05:00hrs-06:30hrs) by Pest control contractor.

Note: Chemical used for fumigation is Permethrin, product name is PERMANETTM 100 EC INSECTICIDE.

Implemented pest control activities since 27 June 2013 till 03 July 2013

Uncontrolled when Printed

PT. Saipem Indonesia (Karimun Branch) REPORT SIKB YARD WEEKLY PROGRESS REPORT

Doc. No. SIKB-REP-GOR-PCT-0001 Rev. 117 Date: 31/07/13

Page 31 of 33

Quarantine Risk Materials since 27 June 2013 till 03 July 2013

Quarantine Awareness and Communication o HSE-Quarantine information Display the HSE-Quarantine information at prominent area, especially for Quarantine info awareness. HSE Quarantine Officer in charge will be update the information and replace with new information. o Tool Box Talk (TBT) PT. SIKB and Sub Contractor employees involved in Gorgon Project have conducted Tool Box Talk every morning before they are start of working. For Quarantine topic we will conduct every Friday, weekly quarantine tool box meeting topic for this week is Blooming Insect.

Uncontrolled when Printed

PT. Saipem Indonesia (Karimun Branch) REPORT SIKB YARD WEEKLY PROGRESS REPORT

Doc. No. SIKB-REP-GOR-PCT-0001 Rev. 117 Date: 31/07/13

Page 32 of 33

8.2

ACTIVITIES TO BE PERFORMED NEXT WEEK


Document Status o QMP Rev 08 (G1-VE-B-7000-A19-00051-0039_08) issue for construction Pest control Activities Continue inspection rodent bait station, trigonal glue trap, Mobe Moat and adhesive copper barrier tape. Continue residual insecticide spraying on the wall, floor, structure supports and the pits around Gorgon project area. Continue Insecticides spraying inside leg jacket CD East row D3, AB East row B1 and B2. Continue herbicide spraying to kill vegetation around Final Storage & Erection Site. Continue Abate Treatment at stagnant water inside the pits around Load Out area. Maintain salt barrier surround quarantine fences at Final Storage & Erection Site and Load Out area. Regular inspection weed and pest control activity. Housekeeping activities o Regular housekeeping around Gorgon Project area. o Keeping rubbish in waste bins with a tight-fitting lid that are emptied regularly. Check and maintain Gorgons materials free from quarantine risk materials. o Regular inspection housekeeping activity. Quarantine awareness o Weekly quarantine tool box meeting. Topic quarantine awareness for Tool Box meeting next week is Common Sowthistle o Install/update banner/poster at quarantine compliant area. o Quarantine awareness training for new employees. Weekly management walkabout HSE & Quarantine that is conducted on weekly basis. The Quarantine and HSE walkabout is attended by PMT, HSE and Quarantine representatives and CPY representatives.

1.2
o o

AREAS OF CONCERN
Final Storage Area & Erection Site Load Out Area

9. ATTACHMENT 9.1 9.2 9.3 9.4 Weight Report (SOW no. 1 & SOW no. 2) SIKB fabrication document register Concession Request (CR) Request For Information (RFI)

Uncontrolled when Printed

PT. Saipem Indonesia (Karimun Branch) REPORT SIKB YARD WEEKLY PROGRESS REPORT

Doc. No. SIKB-REP-GOR-PCT-0001 Rev. 117 Date: 31/07/13

Page 33 of 33

9.5 9.6 9.7 9.8 9.9 9.10 9.11

Progress Picture Overall Physical Progress Report Loading Platform & Jackets Overall Progress S Curve-Rev.5 Loading Platform & Jackets Procurement Plan (SOW no. 1 & SOW no. 2) List AFC Drawings Overall Physical Progress Report Pontoons, Piles, Access Ramps & Gangways Overall Progress S Curve Pontoons, Piles, Access Ramps & Gangways

Uncontrolled when Printed

Das könnte Ihnen auch gefallen