Definition
The process batch is a batch that you create for the production order so that you can document the properties of a material during the production process (for example, after the individual process steps). It also establishes a connection between the input batch and goods receipt batch.
Use
In production, you can use the process batch not just to document the progress made in production on a quantity basis (confirmations) but also to record the current properties of the material that is to be produced.In addition, the process batch ensures end-to-end batch tracking, because with this function, the system can automatically record n:m relationships between input and goods receipt batches.As a rule, no stock exists for a process batch. However, the process batch may have stock for a short time if you want to remove the relevant material from stock temporarily during the production process (see Prerequisites for Process Batch Management in the Settings in the Material Master section).
Example
Two bales of green fabric are to be produced with production order 1000185. Production consists of three operations: weaving, dyeing, and cutting. After each operation, the current properties of the fabric are documented in process batches: 1. In operation 10, one bale of undyed fabric is produced. Its properties (length, width, and color) are recorded in process batch (PB) 185_01. 2. In operation 20, this bale of fabric is dyed green. The new properties of the bale are documented in process batch 185_02. (You can also record the new properties in process batch 185_01.) 3. In operation 30, the bale of fabric is split into two bales of 100 m. The process batch 185_02 is therefore split into two process batches: 185_03_1 and 185_03_2. The properties of the final product are recorded in these two process batches. The following graphic illustrates the production order with its operations and the process batches that were generated for the individual operations: Example: Operations in a production order with the related process batches
Before you can create a process batch with reference to an input batch, you must assign the relevant input batch to the component in question. Proceed as follows to create a process batch with reference to an input batch: 1. In the Goods Issue area, select the component of the input batch for which you want to create a process batch. 2. Choose the pushbutton PB.
The system takes you to the characteristic valuation screen. The system has copied the characteristics of the same name from the input batch to the process batch.
Configuration Required:
Activate the flag for 'Original Batch Reference Material'
Logistics - General -> Material Master -> Basic Settings -> Make Global Settings
If you include the Goods Issue and/or Goods Receipt detail areas in your confirmation profile, the system hides the Goods movements pushbutton in the confirmation transaction, ass you post the goods movements for the production order in the selected detail areas.
If you work with process batches, and still want to enter quantities or activities for the operation, you must include the relevant additional detail areas in your confirmation profile, for example,: Quantities: Yield/Scrap/Rework/Cause (0200) SAP recommends that you select Operation Quantity as the pushbutton text. Activities: Activity 1 Activity 6 (0300) SAP recommends that you select Act./ Oper. as the pushbutton text. If you work with process batches in the confirmation transaction, you should not allow automatic proposals for quantities and confirmations. You make this setting in your confirmation profile. If you do allow this in your confirmation profile, the system automatically suppresses these proposals if, in the confirmation transaction, you call an order that has a header material that allows process batch management.
So that the system can use this confirmation profile in the time ticket/confirmation transaction, you must either define this confirmation profile as the standard profile or assign it to the users with the help of user parameterCORUPROF.
You can make the settings for batch management and OB management on the General Plant Data/Storage andWork Scheduling views of the material master.
These settings can be relevant for the following materials: Header material of the production order Materials of the co-product item Original batch reference material of the header item Original batch reference material of the materials in the co-product items You can only create process batches for a production order if the settings described have been made for the header material of the production order or its original batch reference material.
Execution: