Beruflich Dokumente
Kultur Dokumente
Biomass no. 5
1 TWh
Technological development
Wave energy & CCS
Trading no. 5
Presence in the most important trading markets
Core markets
2 | Vattenfall Wind Power | Lars Engelmann | 2011-11-21
BD Renewables
Biomass
Wind generation
Business Division Sustainable Energy Projects continues development of Vattenfalls project portfolio.
3 | Vattenfall Wind Power | Lars Engelmann | 2011-11-21
Netherlands Egmond aan Zee (108 MW) operational since 2007 Beaufort (340 MW) in development
United Kingdom Kentish Flats (90 MW) operational since 2005 Thanet (300 MW) operational since 2010 Ormonde (150 MW) start of operations 2011 East Anglia (7.200 MW) in development
Germany alpha ventus (60 MW) fully operational since 2010 DanTysk (288 MW) major construction period 2013 Nordpassage (400 MW) in development
Key facts of JV
SWM is a financially very stable and therefore attractive partner
49 %
51 %
Vattenfall is in the lead of: All operational work (development and construction) Business and operational management contracts for construction and operation The JV management is controlled by Vattenfall
DanTysk staff
Key people in the DanTysk project team were responsible and / or involved in planning and building up in previous VF projects - Project management and administration - Foundation structure - Construction surveillance - Project communication - R&D - Installation logistics Leading role in developing and defining industrywide standards Diverse team with sound know-how in technology, management and marine operations.
Foundations
What 80 monopiles and transition pieces incl. installation Special focus on grouting issue Proven installation technology Load-out in Vlissingen Transport and installation by Seafox 5 When Contract signed in March 2011 Pre-installation works starts in autumn 2012 Installation starts end of 2012 Why Very experienced contractor
Fabrication of Monopiles
Offshore Substation
What Offshore sub-station with jacket-structure 33/155 kV Strukton/Hollandia to design, manufacture and install Installation planned with Oleg Strashnov from SHL When Contract signed December, 2010 Installation start spring 2013 Commissioning finished June 2013 Why Experienced consortium (Nordzee Wind) Proven concept Low risk installation process
Installation of WTGs
What Purpose build Jack-up DP2 vessel Pacific Osprey Operator Swire Blue Ocean subsidiary of Swire Pacific Offshore (Singapore) 6 legs, load capacity of up to 12 complete sets of WTG When Contract signed in Feb 2011 Delivery from ship yard SHI in Dec 2012 Installation starts July 2013 Why Well known contractor Reliable offshore organization Reduced risk profile through high weather limits Very fast loading, transport and installation
Why Decision on location, specification and equipment of offshore accommodation Comparison between accommodation platform and accommodation vessel (Focus: HSE relevant aspects)
Various challenges for planning and execution of Offshore Wind Logistics and Marine Operations during Construction and Operations
Evaluation and deployment of new vessels, technologies and methods Contract right partner and resources Availability of suitable base and service port facilities
Foundation structure
Tendering
Negotiation
Design/Manufacturing
Installation
Tendering
Negotiation
Design/Manufacturing
Installation
Tendering
Negotiation
Construction of vessel
Installation of WTG
Grid Access
www.dantysk.de
DanTysk, 80 turbines
under construction
Sandbank, 96 turbines in
development
Sandbank Extension, 40
turbines in development
Nordpassage, 80 turbines
in development
376 turbines in total
Cost of Energy
- 30%
Projects
2012
2015
2020
Year
Control and master the business Control and master the costs
25 | Vattenfall Wind Power | Lars Engelmann | 2011-11-21
Reducing loading, transport and installation times: development of new methods, tools and equipment for seafastening and lifting
Ports to be more receptive to offshore wind: - Large laydown areas - Easy quay access from shore and sea - Jack up next to quay side Installation methodology to allow higher operational limits
Industrialised use of foundations requires development of: - Specialized Vessels, Barges and Equipment - Improvement of Load-out methods and accessibility - Efficient onshore and offshore logistics
Novel installation methodologies: - Holistic design of lifting tools, and noise mitigation
Novel installation methodologies required - Integrated laying and burial without damaging the cable - Improved pull in procedures and tools
Installation methodologies to allow higher operational limits and faster installation and commissioning times
Thanet
Alpha Ventus
Ormonde
Vattenfall Offshore
External Partner Shell
Lillgrund
Egmond
Safety
Performance
Cooperation