Sie sind auf Seite 1von 5

Presented in the Thirteenth International Working Seminar on Production Economics, Igls/Innsbruck, February 16-20, 2004

A Solution for the Material Delivery Problems in Construction Projects


Timo Ala -Risku*, timo.ala -risku@hut.fi Mikko Krkkinen*, mikko.karkkainen@hut.fi

*Helsinki University of Technology TAI Research Centre P.O. Box 5500 FIN-02015 TKK FINLAND

Abstract: The new project management methods emerging for construction projects generate new kinds of challenges for the delivery process of the project materials. The basic philosophy of the emerging methods is to create short-term schedules for project tasks based on a constraint analysis of project resources. This approach places two requirements for the material deliveries: Transparency to material availability, and short response times in the supply chain. In this paper, we propose a potential solution for managing the material logistics of construction projects. The solution consists of a shipment tracking-based approach tested in pilot implementations to provide inventory transparency, and a pro-active delivery approach for efficient material deliveries validated in expert group discussions. Keywords : supply chain management, logistics, inventory transparency, construction

Introduction
New project management methods addressing the shortcomings of traditional methods by adding flexibility to the execution of construction projects create new challenges to material delivery processes (e.g. Ballard, 2000; Choo et al., 1999; Chua et al., 2001; Koskela and Howell, 2002). The new methods acknowledge the impossibility of creating an exact schedule beforehand for a large, complex project. Instead, the methods use continuous planning on single construction task level. The basic philosophy of the methods is to create short-term schedules for project tasks based on a constraint analysis of project resources. The approach places two requirements for the material deliveries: The analysis of material constraints requires transparency to material availability in site inventories and other parts of the supply chain, and the short time-span of planning demands for short response times in the supply chain. The aim of this paper is to present a potential solution for managing the material logistics of construction projects. The solution consists of a shipment tracking-based approach to provide inventory transparency, and a pro-active material delivery approach for timely material availability. In the first section of the article we will review literature related to the new project management methods and its implications for material replenishments of construction projects. In the second section, we present our research problem and discuss our research design. The proposed solution for material replenishments of construction projects is presented in the third section. And, in the final sections we make concluding remarks on the proposals and outline directions for further research.

Literature review
In this section we review literature dealing with shortcomings of traditional project management practices, proposed developments, and their implications for logistics. First, we make a short overview on the criticism calling for developments in the traditional project management approach, and present a framework developed by Ballard (2000) the Last Planner System that introduces a novel approach in line with the suggested

development directions. Then, we discuss the material delivery related capabilities that are needed for the Last Planner approach to be effectively utilised.

Challenges in prevalent project management practices


The prevalent project management methods have recently been stated as inadequate for controlling the progress of construction projects (e.g. Ballard, 2000; Choo et al., 1999; Chua et al., 2001; Koskela and Howell, 2002). Some of the strongest opinions have been presented by Koskela and Howell in their statements that the underlying theory of project management is obsolete and there in fact exists no explicitly stated theory on project management (Koskela and Howell, 2001; Koskela and Howell, 2002). Their main objection is that planning, execution, and control are not utilised in practice as suggested by PMBOK Guide of Project Management Institute. In similar vein, Johnston and Brennan (1996) have argued that the general interpretation of project management is mana gement-as-planning based on a strong causal connection between generating a plan and the resulting operational activity. They conclude that such a straightforward coupling is not feasible, since no plan can ever be detailed enough to enable mere execution with no feedback from the environment. Koskela and Howell (2002) note that reliance on a general plan leads to poor short-term planning. These observations are confirmed, for example, in a study of six construction projects in England and Brazil (Santos et al., 2002). Koskela and Howell (2002) recognise that maintaining a comprehensive up-to-date plan is difficult. Therefore, being based on an out-of-date plan, the tasks pushed to execution often cannot be performed, as they lack either predecessor tasks or other inputs. As Johnston and Brennan (1996) state, That this approach works at all is largely attributable to tacit knowledge and improvisation at the operational level. From the supply chain point of view however, this management approach including last-minute improvisation leads to inefficient practices to guard against material shortages. Materials are often ordered either very late leading to buffering at supplier to guarantee service level, or too early leading to buffering at the site (Vrijhoef and Koskela, 2000).

Therefore, there has been a clear need for a more interactive management method, where the next steps to take in a construction project are determined from the current status of the project, not from predefined and outdated schedules obsolete for controlling practical actions. More flexible project management practices have been developed to overcome the challenges of traditional project management approaches (e.g. Ballard, 2000; Chua et al; 2001). In the following, we give the Last Planner System of Ballard (2000) as an example of such approaches. Last Planner - a novel method for managing projects The Last Planner System has been developed by Ballard (2000) since 1992. It is a project execution system that uses the overall project plan as the general frame, but suggests that the day-to-day activities of the actual production should be managed by a more flexible approach accounting for the actual progress of the project. The main philosophy is to ensure that all the prerequisites needed for performing a distinct task are in place, before it is assigned to a work group. This is the task of the last planner in the chain of plans of increasing detail in a project. Therefore, Last Planner has been used to mean both the system and the person responsible for the final arrangement of tasks.
Project Objective

Information

PLANNING THE WORK

SHOULD

CAN

LAST PLANNER PLANNING PROCESS

WILL

Resources

Production

DID

Figure 1. The Last Planner System (Ballard, 2000)

The four main categories for any executable assignment are SHOULD, CAN, WILL, and DID (Figure 1). 4

SHOULD: assignments that need to be done in the near future according to the overall project plan

CAN: assignments that have all their prerequisites ready: e.g. previous project steps are completed, necessary materials are at hand, and work force is available

WILL: the tasks that are commenced before the next planning round DID: the assignments that are completed

The Last Planner System includes rules and procedures, and a set of tools that facilitate the implementation of those procedures. The two main procedures are Production Unit Control and Work Flow Control. Production Unit Control coordinates the execution of work within production units (e.g. construction crews) and includes processes for directing workers through continuous learning and corrective actions. Work Flow Control coordinates the flow of design, supply, and installation to proactively arrange work to flow in the best achievable sequence and rate. From the supply chain perspective, the most important feature of the Last Planner System is the way the work flow control utilises a lookahead process. The traditional use for a lookahead process is only to highlight what SHOULD be done in the near term. However, within the Last Planner System, the process serves several functions, e.g. work flow sequence shaping, decomposing master schedule activities into assignments and revising higher level schedules as needed, and maintaining a backlog of work ready to be performed. These are accomplished through specific processes, such as matching load and capacity and constraints analysis. The vehicle for the entire lookahead process is a schedule of potential assignments for the next 3 to 12 weeks (Figure 2), the extent depending on project characteristics, such as lead times for acquiring materials or labour force.

Das könnte Ihnen auch gefallen