Dan Curry, Michael Cooper, Tom Shouldice, Josh Rubenstein, and Michael Young
7th International Mineral Processing Seminar PROCEMIN 2010 Santiago, Chile December 2010
Presentation Outline
Background The De-Bottlenecking Challenge Where We Started
The Opportunities
Final Flow Sheet Does It Work?
Background on Cosmos
Started in 1999 by Jubilee Mines NL Concentrator built from used equipment with three year LOM High grade (7% Ni), coarse pentlandite, low impurities (exhausted)
A$ 3.4 M budget
Original Flowsheet
Opportunity - Comminution
Jaw crusher and CVs could easily cope with tonnage increase
Very high Pe and Gn liberation from SAG More like a cleaner feed than a rougher feed
Opportunity to increase SAG throughput and coarsen grind without reducing rougher /scavenger recovery
Jameson : 14 weeks, froth washing, fine particle collection Wemco : 20 weeks, coarse particle collection
Existing 24 m2 filter replaced with new 32 m2 Larox
Opportunity Regrinding
Coarser SAG grind increased composites in final concentrate
Opportunity Regrinding
M500 IsaMill installed using low wear inert ceramic media
Rougher/ Scavenger
MgO Rejection
Cleaners
Prim Clnr
IsaMill
Sec Clnr
Clnr Scav
Regrind
Arsenic Rejection
ReClnr
Re-Cleaners
Conc
Budget
Actual
95% of budgeted tonnes milled in 2009 87% of design t/h achieved Further improvement in t/h needed Priority challenge for 2010
35 30 25 20 15 10 5 0
2008 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09
Budget
Actual
Planned mined grades not achieved New circuit not pushed on Ni t/h Residence time seems adequate
Results Flotation
28 26 24 22 20 18 16 14 12 10 70
2009
2010
2010 Budget
75
80
85
90
95
100
Recovery (%Ni)
Concentrator availability in 2009 (despite major changes) = 96.8 %
Acknowledgments
For permission to publish For assistance with commissioning and optimisation For (almost) doing what was promised For managing and supervising the project (and living with the result)
Thank You