Beruflich Dokumente
Kultur Dokumente
SECTION CONTENTS
1.0 Introduction
2.0 Scope
3.0 Definitions
4.0 Plant Layout Philosophy
5.0 Layout of Blocks/Facilities
5.1 General Considerations
5.2 Inter-distances
6.0 Layout of Process Units
6.1 General Considerations
6.1.1 Process Equipment
6.1.2 Control Room and Sub-Station
6.2 Equipment Spacing within Process Units
7.0 Layout of Storage Tanks
7.1 General Considerations
7.2 Inter-distances between Tanks / Offsite Facilities
8.0 Layout of LPG Facilities
8.1 General Considerations
8.1.1 LPG Storage
8.1.2 LPG Bottling
8.1.3 LPG Bulk Handling
8.2 Inter-distances for LPG Facilities
9.0 Layout of Utility Stations
9.1 General Considerations
9.2 Inter-distances
10.0 References
TABLES
1. Inter-distances between Blocks/Facilities
2. Equipment Spacing within Process Units
3. Inter-distances between Storage Tanks/Offsite Facilities
(for Small Installations)
4. Inter-distances between Storage Tanks/Offsite Facilites
5. Inter-distances between Storage Tanks
6. Distances from Boundary Fencing
7. Inter-distances for LPG Facilities
8. Inter-distances between LPG Storage Vessels and Boundary/Property Line/
Group of Buildings not associated with LPG plant.
3.0 DEFINITIONS
"Flash point" of any petroleum liquid is the (ix) STABLING LINE
minimum temperature at which the liquid yields
vapour in sufficient concentration to form an It is an additional railway line/spur reserved for
ignit-able mixture with air and gives a additional rake/stabling.
momentary flash on application of a small pilot
flame under speci-fied conditions of test as per 4.0 PLANT LAYOUT PHILOSOPHY
IS:1448 (Part-I).
A petroleum installation may be broadly
(vii) GENERAL CLASSIFICATION OF considered as a group of one or more of the following
PETROLEUM PRODUCTS units/facilities:
- Crude oil storage
Petroleum products are classified according to
their closed cup FLASH POINTS as follows: - Intermediate and finished product storage
- LPG storage and handling facilities
— Class "A" Petroleum:
- Process units and control room
Liquids which have flash point below 23
o
C. - Product loading/unloading facilities (Rail,
Road and Pipelines)
— Class "B" Petroleum:
Liquids which have flash point of 23 oC - Utilities generation and distribution centres
and above but below 65 oC. - Blowdown and flare system
— Class "C" Petroleum: - Waste water treatment facilities
Liquids which have flash point of 65 oC - Administrative and service buildings
and above but below 93 oC. (ware-house, workshop, canteen, fire
— Excluded Petroleum: station, laboratory, first aid, parking lot
Liquids which have flash point of 93 oC etc.)
and above.
Following points shall be kept in mind while
developing overall plant layout of any
Liquefied gases including LPG, do not fall under
installation.
this classification but form separate category.
(i) BASIC INFORMATION
In the following cases, above classification does
not apply and special precautions should be
(a) Information on following items should be
taken as required:
collected before proceeding with the
(a) Where ambient temperatures or the development of overall plot plan:
handling temperatures are higher than the - Process units and their capacities
flash point of the product. - Process flow diagram indicating flow
(b) Where product handled is artificially sequence
heated to a temperature above its flash - Utility requirements
point.
- Storage tanks list
(viii) TANK HEIGHT - LPG storage vessels and their sizes
Tank height is the: - Product despatch and mode of transport
(rail, road and pipeline)
- Height from tank bottom to top kerb angle
for cone roof tanks - Warehouses, open storage areas
- Height from tank bottom to top of tank - Number of flares
shell for floating roof tanks
- Operating and maintenance philosophy for divided into blocks. Maximum size of a
grouping of utilities block should be established based on tank
farm layouts.
- Plant and non-plant buildings
- Environmental considerations (iii) ROADS
- Scrap yards and dumping ground (a) All process units and dyked enclosures of
storage tanks shall be planned in separate
- Fire station and fire training ground
blocks with roads all around for access and
- Chemical/Toxic Chemical storage safety. Primary traffic roads in the
installation should be clear of hazardous
- Storage areas for solid products such as
classified areas. Roads separating the blocks
petroleum coke, petroleum wax, coal,
shall provide fire breaks and have facilities
bitumen and asphalt
for fire fighting activities.
(b) Data on following infrastructural facilities (b) Alternative access should be provided for
should be collected before detailed layout each facility so that it can be approached for
activity is taken up and due consideration fire fighting/maintenance/construction in
should be given for the same while deciding the event of blockage on one route.
plant layout:
(c) Road widths and turning radii at road
- Site location map junctions shall be designed to facilitate
movement of the largest fire fighting vehicle
- Prevailing wind direction in the event of emergency.
- Area topography contour map
(d) Rail spur shall be located close to the
- High flood level in the area periphery of the plant to minimise road
crossings and blockage of roads during
- Source of water supply and likely entry
shunting.
point
(e) Layout of the facilities shall be made to
- Electric supply source and direction of entry
minimise truck traffic ingress in the plant.
point
- Crude oil entry point (f) Two road approaches from the highway
should be provided, one for employees and
- Storm water disposal point and effluent other for product movement. Both these
disposal point approaches should be available for receipt
- Railway entry point and marshalling yard of assistance in emergency. However, for
location smaller installations, this requirement may
be relaxed if not feasible.
- Approach roads to main plant areas
- Inward/outward product movement by (iv) LOCATION
rail/ road and pipelines. (a) Process unit(s) should be located on high
- Surrounding risks ground to avoid flooding.
(ii) BLOCKS
(b) Presence of ignition source shall always be
(a) In any process installation, it is recommen- contemplated beyond the boundary wall of
ded that plant layout arrangement should the installation.
follow the general route of raw material to
(c) Orientation of flares,furnaces/heaters, dusty
process unit (s) with tankages interposed as
operations (e.g. sulphur handling) and
required followed by despatch facilities.
cooling towers should be decided based on
(b) Block layout should be adopted as much as prevailing wind direction.
possible. The entire area should be sub-
(V) ERECTION AND MAINTENANCE (iii) Process units should be centrally located with
straight approach from main gate. Orientation of
(a) Erection methods shall be anticipated for all process units should follow process flow in
types of equipments. Towers, reactors and sequential order so that piping runs are also
fired equipments should be located away minimum.
from congested areas to facilitate erection at
any stage. Location of tall columns and furnaces should be
(b) Maintenance methods for each type of close to road side for ease of construction and
equipment shall be identified in advance maintenance.
since these affect the requirements for
layout. Equipment requiring frequent atten- (iv) Storage tanks should be grouped according to
tion shall have easy accessibility. For equip- product classification. In undulating areas,
ments having removable parts, wherever storage tanks should be located at lower
possible, arrangements shall be made to elevations.
facilitate their removal without dismantling
long lengths of piping. Free access shall be (v) Utility blocks should be located adjacent to unit
provided for hoisting the equipment. blocks.
(vi) FUTURE EXPANSION (vi) Main power receiving station should be close to
the fence line with minimum overhead power
Future expansion shall be assessed and space transmission lines passing through the installa-
provision for known and unforeseen needs shall tion.
be made. Orderly future expansion shall be
affected by providing space adjacent to similar Overhead power transmission lines shall not pass
type of facilities for expansion. Extension of pipe over process units, storage tanks, offsite and
sleepers and pipe way, road crossings for yard utility areas. Wherever these lines are passing
piping shall be given due consideration. Care through plant premises adequate safety distances
shall be taken to facilitate future expansion shall be kept.
without any interferene to plant on-stream.
(vii) H T sub-station should be located close to major
5.0. LAYOUT OF BLOCKS/FACILITIES load centres. One or more sub-stations could be
provided to limit distances.
An installation may consist of one or more of the
following basic blocks/facilities: (viii) L T sub-station should generally be located at
- Storage tanks/offsites load centres in such a way that the distance
between distribution transformer and farthest
- LPG storage and filling facilities
motor is minimum.
- Process units
- Utilities and effluent disposal facilities (ix) Gas/Oil based power plants should be located
close to process units/utility blocks and closer to
5.1 GENERAL CONSIDERATIONS Main Receiving Station, as far as possible. Coal
based power plants should be located away from
While locating the above blocks/facilities and criticalfacilities like air separation plants, electri-
further sub blocks/facilities within them, following cal installations etc. to avoid problems due to coal
items should be considered : dust and ash.
(i) Layout planning should be in sequential order of
process flow. (x) Flare should be located upwind of process units.
Height of flare and its distance from operating
(ii) Orientation should be to suit wind direction to
facilities shall be decided based on heat radiation
avoid travel of hydrocarbon vapour over sources
considerations and other considerations like
of ignition.
ground level concentration, cold venting etc.
5.2 INTERDISTANCES
Area around flare should be paved to avoid
growth of grass/vegetation which can otherwise Interdistances between various blocks/facilities
provide combustible material for fires. (Ref. described above shall be as per Table-1.
section 8.0 of OISD-STD-106 on "Process Design
and Operating Philosophies on Relief and
Disposal systems").
TABLE - 1 (NOTE1)
MINIMUM INTERDISTANCES BETWEEN BLOCKS/FACILITIES
S.No. From \ To 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
7. Flares-elevated 90 90 90 90 90 90 90 150 90 90 90 90 90 90 90 90
8. Flares-ground 150 150 150 150 150 150 150 150 150 150 150 150 150 150 150 150
Contd...
10
TABLE - 1 (Contd..)
S.No. From \ To 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
** Distance will be 30 meters in case Control Room is blast proof and 60 meters in case it is not blast proof.
Notes :
1. All distances are in metres.
2. All distances shall be measured between the nearest points on the perimeter of each facility except in case of tank vehicle loading/unloading area
where the distance shall be measured from the centre of each bay.
3. "T" indicates the table to be referred.
4. Where distances have not been specified, it shall be decided based on construction,operation & maintenance requirements.
5. API/CPI, open oil separators/oil collection sumps shall be categorised under the same risk and shall be located at 90m distance from
heaters/boilers. However, if these are covered from top and provided with adequate venting to safe location, the minimum safe distance can be
reduced from 90m to 30m.
OISD-STD-118 Revision - II 11
7. Definitions :
Process Unit - a unit having integrated sequence of operation , physical and chemical, and may involve preparation, separation, purification, or change
in state, energy content or composition.
Service building – a building housing facilities for inspection/maintenance/other supporting services which are directly required for operation of the
plant.
Fire station – a building housing facilities of parking fire tenders and keeping other ready to use fire fighting equipment for meeting plant emergencies,
fire control room with required communication facilities/mimic panel.
Fire pump house – a building housing main fire water pumps, jockey pumps, communication and alarm system, instrumentation and the required
operating & supporting personnel.
12 OISD-STD-118 Revision - II
-118 Revision - I
6.0 LAYOUT OF PROCESS UNITS (vii) Cold boxes should be located on grade or
on separate elevated structures. Adequate
6.1 GENERAL CONSIDERATIONS space should be provided around cold
boxes for ease of operation and
6.1.1 PROCESS EQUIPMENT maintenance.
(i) Process flow sequence and operating (viii) Vessels having large liquid hold-up should
procedures shall be thoroughly understood be installed at lower heights and preferably
so that equipment arrangement in the plot at grade. Adequate drainage should be
plan is functional. Equipment shall be provided around such vessels. Where
arranged in logistic process sequence for process requirement dictates their installa-
short piping runs and operational ease. tion above grade, these should be located
in open area.
(ii) It is recommended that the unit pipe rack
be kept in the centre, thereby splitting the (ix) Towers/columns should be located along
unit into two or more areas of the pipe rack towards open areas for
equipments.Pumps may be arranged in unobstructed erection as well as
two rows close to and on either side of the maintenance of internals at grade. Tall
central pipe rack. Heat Exchangers and towers require frequent operating attention
vessels should be grouped together at upper levels. Hence they may be located
forming outer rows on both sides of the at one place so that common connecting
rack. Fired heaters should be kept at open platform can be provided.
end of the unit upwind from the remaining
plant equipments. (x) Thermo-siphon reboilers should
preferably be placed close to their
(iii) Spacing between battery limits of associated towers. Reboiler should be
individual pieces of equipment shall be mounted on the tower so that vertical
adequate for undertaking maintenance expansion will be uniform, piping system
jobs. design is simplified and inlet/outlet piping
is minimised. Clearance shall be provided
(iv) Spacing between two process units in a for movement between reboiler and tower.
complex should be decided based on shut
down philosophy for maintenance of the (xi) Gas compressors should be located down
units. If the shut down of the units are wind from heaters so that leaked gases will
expected at different occasions, then inter not drift towards the heater. Gas
distances may be increased.This will compressors should have roofing and open
facilitate ease in maintenance and from sides to avoid accumulation of
minimise risk from/for operating units heavier vapours/gases on the floor of
due to hot jobs in the units under shut compressor house. Compressor house
down. should be located near the battery limits to
facilitate ease in maintenance and
(v) Heat exchangers should be located operation.
perpendicular to the pipe rack on the outer
row to facilitate pulling of tube bundles (xii) Heaters should be located up wind at one
with mobile crane or by other means. Shell corner of the unit. Space should be
and tube heat exchanger should have a provided for removal and cleaning of
longitudinal clearance of at least one metre heater tubes besides approach for crane.
plus the length of removable bundles. Areas around the heaters shall be graded
for guiding spills away from process
(vi) Air fin coolers should be installed above equipment. FD fans shall be located away
the pipe rack. Pumps handling hydro- from process equipment from where they
carbons and materials above the arelikely to suck hydrocarbon vapours.
temperature of 230 degree C should not be
installed underneath the air fin coolers. The local control panel for soot blower
control and flue gas analyser shall only be
OISD-STD-118 Revision - II 13
located on and near the process heater. The protection to instruments and personnel is
rest of controls shall be taken to central ensured and non-hazardous electrical area
control room. classification is permitted. It should have
alternate means of exit with doors opening
(xiii) No other tankage except day tanks shall be towards outside. Doors should be made of
provided within battery limits of any fire proof material.
process unit.
(ii) Control room should be designed to cater
(xiv) Flare knock out drum of the closed blow for minimum occupancy.
down system should be located at battery
limit of the unit.
(iii) Transformers should be located in open
(xv) Blow down facilities/burried drum shall be area on the rear side of sub-station.Each
located at one corner of the plant farthest transformer shall be isolated from the other
from furnace or any fired equipment and by a brick masonary wall. Approach road
on the lee-ward side of the unit. to sub-station and transformer bays should
be provided to facilitate crane movement
Vent from Blow down facility shall be for erection and maintenance.
minimum 6m clear off the air fin coolers. It
shall be minimum 6m above the highest (iv) Electrical sub-station should be located
platform if horizontal distance of 15m from adjacent to the control room building and
process equipment is not possible. should meet the requirements of electrical
area classification.
6.1.2 CONTROL ROOM AND SUB-STATION
6.2 EQUIPMENT SPACING WITHIN PROCESS
(i) Control room should be located distinctly UNITS
in the process block or in the adjoining
block. It should be at a safe distance where Interdistances betweenvarious equipments in
process units shall be as per Table-2.
14 OISD-STD-118 Revision - II
TABLE-2
MINIMUM INTERDISTANCES BETWEEN EQUIPMENTS WITHIN PROCESS UNIT
“This table could be used by the oil companies as a guideline for their projects. These could be suitably modified as required to suit space constraints and
relevant engineering practices.” NOTE 1
S.No. From \ To 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Contd....
TABLE - 2 (Contd...)
S.No. From \ To 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Notes:
1. All distances are face to face clear minimum distances in meters.
2. Distance between equipments not covered herein & equipments handling non-hydrocarbons shall be as per good engineering practices.
3. From control room to heater, safe distance shall be 16m if the control room is for one unit and shall be 30m, if it is for two units. For gas
processing plants, it shall be 30m irrespective of whether the control room is for one or more units.
4. Distances between the reactor and furnace when directly connected process-wise, can be relaxed to 5m.
5. Only distances indicated from fired heaters (1) Fuel oil day tank (7), Control room (12), Fired heater local control panel (14), Fire water
hydrant/monitor (16), Blow down facility (18) and water spray deluge valve (19) are by safety considerations. Other distances indicated are
recommended from erection, operation and maintenance safe guards.
6. The local control panel meant for soot blower control & fuel gas analyser shall only be located on and near the process firedheater. The rest of
controls shall be taken to central control room.
7. Safety distances as per preceeding Table-2 for blow down facilities are for open pit location. If the blow down drum is located underground, the
distance from fired heater shall be reduced from 30m to 15m.
8. Steam snuffing/purging valve shall be located minimum 15m from only those equipments which are served bythe steam valve.
16 OISD-STD-118 Revision - II
9. Fuel Oil day tanks shall be located at a safe distance of 15m from equipment except those facilities such as heat exchanger, pump connected directly
with the Fuel Oil system. (Refer Table-5 for interdistance between tanks).
10. Distance between fired heater and distillation column shall be increased to 22.5m in case of light ends such as Naphtha stabiliser.
11. Minimum distances between equipment shall not be applicable for package items and their related appertenances.
OISD-STD-118 Revision - II 17
(d) Interdistance between the nearest tanks In a dyked enclosure where more than one tank is
located in two dykes shall be equivalent to located, fire walls of 600mm should be provided
the largest tank diameter or 30m, which- as explained below:
ever is more.
(a) Any tank having a diameter more than
(e) The tank or tanks shall be supported on 30m should be separated with fire walls
well designed foundations and shall be from other tank.
18 OISD-STD-118 Revision - II
TABLE - 3 (NOTE1)
INTERDISTANCES BETWEEN TANKS/OFFSITE FACILITIES
(For small installations)
S.No. From \ To 1 2 3 4 5 6 7 8 9 10 11 12 13
Contd...
20 OISD-STD-118 Revision - II
TABLE - 3 (Contd...)
S.No. From \ To 1 2 3 4 5 6 7 8 9 10 11 12 13
Notes:
TABLE - 4
S.No. From \ To 1 2 3 4 5 6 7 8 9
Notes :
TABLE - 5
Notes :
1. This table is applicable for installations where aggregate storage capacity of class A and class B
petroleum stored above grade exceeds 5000 cu.m. or where the diameter of any such tank for the storage
of petroleum exceeds 9 m.
3. Notation:
4. If the interdistance (for class A & B) calculated as above are less than 15m,then minimum of 15m or 0.5 D
or d shall be followed.
5. Interdistance between class A/B storage tanks and classC storage tanks shall not be less than 6 metres.
TABLE - 6 (NOTE1)
Minimum Distance
from Boundary
S.No. Installation fencing around
Installation
Notes :
2. This table is applicable for facilities in an installation where total quantity of petroleum class A & B stored
above ground in bulk exceeds 5000 cu.m. or where the diameter of any such tank for the storage of
petroleum exceeds 9 m.
3. Notation:
4. Above table is based on the assumption that property beyond the boundary line is either protected or
adequate green belt is provided as a safety buffer where no structure exists. Property beyond property
line is deemed protected if it is within the jurisdiction of public Fire Brigade or plant's own Fire Brigade.
** (I) Distance from Floating roof tank to boundary fencing for stable and boil-over liquids, having
protection for exposure shall be D/2 (minimum 20m).
The above distance shall be D/2 (minimum 20m) for tanks having approved foam or inerting
system and the tank diameter not exceeding 50m.
8.0 LAYOUT OF LPG FACILITIES of one sphere, the sump size shall be equal
to layout of two spheres.
(b) Curb wall around the storage tank shall
8.1 GENERAL CONSIDERATIONS have a minimum height of 30cm. However
it shall not exceed 60cm at shallow sump
8.1.1 LPG STORAGE position, as otherwise evaporation of
spilled LPG may get affected.
(i) GROUPING
(c) There shall not be any depressions, large
Vessels shall be arranged into groups each having ditches and low lying areas around LPG
a maximum of six vessels. Capacity of each group storage as the leaked gas can accumulate,
shall be limited to 15000 cu.m. Each group shall being heavier than air. Top surface of the
be provided with a curb wall. vessels installed in a group should be on
the same plane so that safety blowout from
Any vessel in one group shall be separated from a one vessel does not affect the other vessel.
vessel in another group by a minimum distance This will also minimise the chances of
of 30m. overfilling of adjoining vessels due to
gravitation.
Spheres and bullets shall be treated as separate
groups with 30m safety distance between two (d) A typical layout plan of LPG sphere area
groups. Separate dedicated manifold shall be with major safety requirements of distan-
provided for each group. ces, drainage sump, pump station location
etc. is enclosed at Annexure-1 for general
ii) LOCATION guidance.
(c) LPG storage vessels shall not be located There shall not be any deep ditches in the
within the same dykes where other surrounding area to avoid LPG settling.
flammable liquid hydrocarbons are stored.
(ii) CONSTRUCTION
(d) Storage vessels shall be laid out in single
row both in case of the spheres and bullets. Bottling section shall be of single storey having
Storage vessels shall not be stacked one roofing and open from sides for adequate
above the other. ventilation so that leaked gas can drift away.
RCC roofing should not be used to the extent
(iii) SPILLS AND LEAKS possible.
S.No. From \ To 1 2 3 4 5 6 7
2. Boundary/property line/ T8 - 30 30 30 30 **
group of buildings, not
associated with LPG plant
5. Rail spurs 30 30 30 50 50 30 60
6. Pump house/Comp. 15 30 15 30 30 - 60
house(LPG)
Notes :
2. Notation:
T8 – Refer Table - 8
* 1/4 of sum of diameters of adjacent vessels or half the diameter of the larger of the two adjacent
vessels whichever is greater.
TABLE - 8 (NOTE1)
Capacity of
S.No. Each Vessel Distance
(Cum.M. of water)
1. 10 - 20 15
2. 21 - 40 20
3. 41. 350 30
4. 351 - 450 40
5. 451 - 750 60
6. 751 - 3800 90
Note :
The plant air compressors and drying units iv) SMOKING BOOTHS
should preferably be located in the boiler house unit
block. Fuel oil heating and pumping facilities may also Smoking booths should not be provided in
be located within the boiler house unit block. These may hydrocarbon industry. However if it is necessary
be located in the boiler house unit block to minimise the to provide smoking booths, these should be
spreading ofvarious utility blocks around the process located at a safe distance of :
unit, to facilitate ease of operation.
(i) 30m from hydrocarbon source in case of oil
( i) ELECTRICAL refinery/storage installation.
(ii) 60m from hydrocabon source in case of
Electrical generation facilities should be located
LPG/Gas Processing Plants.
near the process unit block because such electrical
generation units normally supply steam to the
9.2 INTERDISTANCES
process units e.g. Cogeneration. When external
power grid is interconnected with plant power
Interdistances between various utility stations
generation facilities, either the power plant shall
and other facilities shall be as given in Table-1.
be located at the side of boundary wall or the
external power transmission lines shall be taken
underground upto the interconnection grid 10.0 REFERENCES
inorder to minimise the length of overhead
transmission lines within the plant. 1. OISD-STD-106 on Process Design and
Operating Philosophies on Relief and
(ii) COOLING TOWERS Disposal Systems.
2. OISD-STD-144 on LPG Bottling and
Cooling towers should be located away from Distribution.
process unit area, preferably downstream
3. NFPA Standard No.30 "Flammable and
direction of wind to avoid corrosion of the
Combus-tible Liquids Code".
equipments in process areas.
4. Petroleum Rules - 1976.
(iii) WASTE DISPOSAL FACILITIES 5. OISD-STD-117on Fire Protection facilities
for Petroleum depots and terminals.
Separate collection system should be provided for
different types of waste generated in the process 6. OISD-STD-116 on Fire Protection facilities
plant such as oily water, cooling tower for Petroleum Refineries/process plants.
blowdown, caustic and acidic effluents, sludge, 7. SMPV Rules - 1981.
fecal etc.
OISD-STD-118 Revision - II 31
ANNEXURE - 1
Section - XX
NOTES :
1. ALL DIMENSIONS ARE IN METRES
2. TOP SURFACE OF ALL VESSELS INSTALLED SHALL BE IN THE SAME PLANE.
3. SIZING CRITERIA FOR SUMP—FULL CONTAINMENT OF LPG SPHERE WITHIN KERB AREA IS NOT ENVISAGED HOWEVER
THERE IS CHANCE OF SMALL SPILL OFLPG IN THE STORAGE AREA IT IS ASSUMED THAT THE LEAK WILL BE ARRESTED
WITHIN ABOUT AN HOUR THE CONTAINMENT VOLUME FOR ONE HOUR LEAK CORRESPONDING TO LARGEST NOZZLE
SIZE AND LIGHTEST MATERIAL IS 18 MT OR ABOUT 35 M3 WITH A MAXIMUM LIQUID COLLECTION RATE OF APPROX. 5
KG./SEC.
4. ALL LEVELS ARE WITH RESPECT TO HIGH POINT OF PAVEMENT LEVEL I.E. 100.00
5. PROTECTIVE WALLS TO BE PROVIDED IF THE VALVE IS WITHIN 30 M FROM SPHERE SHELL.
6. WATER SEAL SHALL BE PROVIDED AT OUTLET FROM SHALLOW SUMP.
LEGEND :