Sie sind auf Seite 1von 29

LAYOUTS FOR OIL AND GAS INSTALLATIONS

OISD – STD. 118


INDEX

SECTION CONTENTS

1.0 Introduction
2.0 Scope
3.0 Definitions
4.0 Plant Layout Philosophy
5.0 Layout of Blocks/Facilities
5.1 General Considerations
5.2 Inter-distances
6.0 Layout of Process Units
6.1 General Considerations
6.1.1 Process Equipment
6.1.2 Control Room and Sub-Station
6.2 Equipment Spacing within Process Units
7.0 Layout of Storage Tanks
7.1 General Considerations
7.2 Inter-distances between Tanks / Offsite Facilities
8.0 Layout of LPG Facilities
8.1 General Considerations
8.1.1 LPG Storage
8.1.2 LPG Bottling
8.1.3 LPG Bulk Handling
8.2 Inter-distances for LPG Facilities
9.0 Layout of Utility Stations
9.1 General Considerations
9.2 Inter-distances
10.0 References

TABLES
1. Inter-distances between Blocks/Facilities
2. Equipment Spacing within Process Units
3. Inter-distances between Storage Tanks/Offsite Facilities
(for Small Installations)
4. Inter-distances between Storage Tanks/Offsite Facilites
5. Inter-distances between Storage Tanks
6. Distances from Boundary Fencing
7. Inter-distances for LPG Facilities
8. Inter-distances between LPG Storage Vessels and Boundary/Property Line/
Group of Buildings not associated with LPG plant.

ANNEXURE 1: TYPICAL LAYOUT OF LPG STORAGE VESSELS

LAYOUTS FOR OIL AND GAS INSTALLATIONS

1.0 INTRODUCTION (i) PETROLEUM REFINERY

Petroleum Refinery is a plant where crude oil is


Hydrocarbon processing and handling plants are
received and processed into intermediates and
inherently hazardous. Today's trend of large and
finished products.
complex plants presents substantial risk potential. At
times plants are modified to operate at higher capacities (ii) OIL/GAS PRODUCTION PLANT
or efficiencies necessitating larger storage requirements
than contemplated earlier. For these reasons, initial site Oil/Gas production plant is a plant where oil
analysis for the proposed new construction or addition and/or gas is collected, stabilised and despatched
should be done carefully while considering the space for further processing. Drilling activities and
allocation to the various facilities. facilities upstream of the christmas tree of a well
are not covered under this definition.
The hydrocarbon industry over the years learnt
lessons from fires and explosions throughout the world (iii) GAS PROCESSING PLANT
and has been up-dating plant safety norms including
inter-distances between facilities and their relative Gas processing plant is a facility where natural
locations. The minimum distances recommended many gas is received and processed to make gas, LPG,
years ago need review in the context of today's condensate etc.
environment in the industry.
(iv) LPG FILLING PLANT
It is not intended that requirement of this
LPG filling plant is a plant where liquefied
standard should be applied rigidly to existing premises
petroleum gas (LPG) is received/despatched by
where for a variety of reasons, it may not be practicable
rail, road and pipeline and filled in cylinders.
to comply with. This standard will however create
awareness and help in selective implementation of the (v) OTHER PETROLEUM STORAGE INSTALLA-
recommen-dations at existing installations. TIONS

2.0 SCOPE Other petroleum storage installations include:


- Crude oil gathering stations
This document lays down minimum
requirements of layouts within the plant boundary for - Coastal storage installations for crude oil
petroleum refineries, Oil/Gas production and and petroleum products
processing plants, LPG filling plants and other - Marketing depots and terminals
petroleum storage installations. The requirement of
green belt/buffer zone beyond the plant boundary is - Aviation storage and fuelling stations
outside the scope of this standard. Such provision may - Pipeline installations/terminals.
be considered based on local environmental/ security
requirements. (vi) FLASH POINT

3.0 DEFINITIONS
"Flash point" of any petroleum liquid is the (ix) STABLING LINE
minimum temperature at which the liquid yields
vapour in sufficient concentration to form an It is an additional railway line/spur reserved for
ignit-able mixture with air and gives a additional rake/stabling.
momentary flash on application of a small pilot
flame under speci-fied conditions of test as per 4.0 PLANT LAYOUT PHILOSOPHY
IS:1448 (Part-I).
A petroleum installation may be broadly
(vii) GENERAL CLASSIFICATION OF considered as a group of one or more of the following
PETROLEUM PRODUCTS units/facilities:
- Crude oil storage
Petroleum products are classified according to
their closed cup FLASH POINTS as follows: - Intermediate and finished product storage
- LPG storage and handling facilities
— Class "A" Petroleum:
- Process units and control room
Liquids which have flash point below 23
o
C. - Product loading/unloading facilities (Rail,
Road and Pipelines)
— Class "B" Petroleum:
Liquids which have flash point of 23 oC - Utilities generation and distribution centres
and above but below 65 oC. - Blowdown and flare system
— Class "C" Petroleum: - Waste water treatment facilities
Liquids which have flash point of 65 oC - Administrative and service buildings
and above but below 93 oC. (ware-house, workshop, canteen, fire
— Excluded Petroleum: station, laboratory, first aid, parking lot
Liquids which have flash point of 93 oC etc.)
and above.
Following points shall be kept in mind while
developing overall plant layout of any
Liquefied gases including LPG, do not fall under
installation.
this classification but form separate category.
(i) BASIC INFORMATION
In the following cases, above classification does
not apply and special precautions should be
(a) Information on following items should be
taken as required:
collected before proceeding with the
(a) Where ambient temperatures or the development of overall plot plan:
handling temperatures are higher than the - Process units and their capacities
flash point of the product. - Process flow diagram indicating flow
(b) Where product handled is artificially sequence
heated to a temperature above its flash - Utility requirements
point.
- Storage tanks list
(viii) TANK HEIGHT - LPG storage vessels and their sizes
Tank height is the: - Product despatch and mode of transport
(rail, road and pipeline)
- Height from tank bottom to top kerb angle
for cone roof tanks - Warehouses, open storage areas
- Height from tank bottom to top of tank - Number of flares
shell for floating roof tanks
- Operating and maintenance philosophy for divided into blocks. Maximum size of a
grouping of utilities block should be established based on tank
farm layouts.
- Plant and non-plant buildings
- Environmental considerations (iii) ROADS
- Scrap yards and dumping ground (a) All process units and dyked enclosures of
storage tanks shall be planned in separate
- Fire station and fire training ground
blocks with roads all around for access and
- Chemical/Toxic Chemical storage safety. Primary traffic roads in the
installation should be clear of hazardous
- Storage areas for solid products such as
classified areas. Roads separating the blocks
petroleum coke, petroleum wax, coal,
shall provide fire breaks and have facilities
bitumen and asphalt
for fire fighting activities.
(b) Data on following infrastructural facilities (b) Alternative access should be provided for
should be collected before detailed layout each facility so that it can be approached for
activity is taken up and due consideration fire fighting/maintenance/construction in
should be given for the same while deciding the event of blockage on one route.
plant layout:
(c) Road widths and turning radii at road
- Site location map junctions shall be designed to facilitate
movement of the largest fire fighting vehicle
- Prevailing wind direction in the event of emergency.
- Area topography contour map
(d) Rail spur shall be located close to the
- High flood level in the area periphery of the plant to minimise road
crossings and blockage of roads during
- Source of water supply and likely entry
shunting.
point
(e) Layout of the facilities shall be made to
- Electric supply source and direction of entry
minimise truck traffic ingress in the plant.
point
- Crude oil entry point (f) Two road approaches from the highway
should be provided, one for employees and
- Storm water disposal point and effluent other for product movement. Both these
disposal point approaches should be available for receipt
- Railway entry point and marshalling yard of assistance in emergency. However, for
location smaller installations, this requirement may
be relaxed if not feasible.
- Approach roads to main plant areas
- Inward/outward product movement by (iv) LOCATION
rail/ road and pipelines. (a) Process unit(s) should be located on high
- Surrounding risks ground to avoid flooding.
(ii) BLOCKS
(b) Presence of ignition source shall always be
(a) In any process installation, it is recommen- contemplated beyond the boundary wall of
ded that plant layout arrangement should the installation.
follow the general route of raw material to
(c) Orientation of flares,furnaces/heaters, dusty
process unit (s) with tankages interposed as
operations (e.g. sulphur handling) and
required followed by despatch facilities.
cooling towers should be decided based on
(b) Block layout should be adopted as much as prevailing wind direction.
possible. The entire area should be sub-
(V) ERECTION AND MAINTENANCE (iii) Process units should be centrally located with
straight approach from main gate. Orientation of
(a) Erection methods shall be anticipated for all process units should follow process flow in
types of equipments. Towers, reactors and sequential order so that piping runs are also
fired equipments should be located away minimum.
from congested areas to facilitate erection at
any stage. Location of tall columns and furnaces should be
(b) Maintenance methods for each type of close to road side for ease of construction and
equipment shall be identified in advance maintenance.
since these affect the requirements for
layout. Equipment requiring frequent atten- (iv) Storage tanks should be grouped according to
tion shall have easy accessibility. For equip- product classification. In undulating areas,
ments having removable parts, wherever storage tanks should be located at lower
possible, arrangements shall be made to elevations.
facilitate their removal without dismantling
long lengths of piping. Free access shall be (v) Utility blocks should be located adjacent to unit
provided for hoisting the equipment. blocks.

(vi) FUTURE EXPANSION (vi) Main power receiving station should be close to
the fence line with minimum overhead power
Future expansion shall be assessed and space transmission lines passing through the installa-
provision for known and unforeseen needs shall tion.
be made. Orderly future expansion shall be
affected by providing space adjacent to similar Overhead power transmission lines shall not pass
type of facilities for expansion. Extension of pipe over process units, storage tanks, offsite and
sleepers and pipe way, road crossings for yard utility areas. Wherever these lines are passing
piping shall be given due consideration. Care through plant premises adequate safety distances
shall be taken to facilitate future expansion shall be kept.
without any interferene to plant on-stream.
(vii) H T sub-station should be located close to major
5.0. LAYOUT OF BLOCKS/FACILITIES load centres. One or more sub-stations could be
provided to limit distances.
An installation may consist of one or more of the
following basic blocks/facilities: (viii) L T sub-station should generally be located at
- Storage tanks/offsites load centres in such a way that the distance
between distribution transformer and farthest
- LPG storage and filling facilities
motor is minimum.
- Process units
- Utilities and effluent disposal facilities (ix) Gas/Oil based power plants should be located
close to process units/utility blocks and closer to
5.1 GENERAL CONSIDERATIONS Main Receiving Station, as far as possible. Coal
based power plants should be located away from
While locating the above blocks/facilities and criticalfacilities like air separation plants, electri-
further sub blocks/facilities within them, following cal installations etc. to avoid problems due to coal
items should be considered : dust and ash.
(i) Layout planning should be in sequential order of
process flow. (x) Flare should be located upwind of process units.
Height of flare and its distance from operating
(ii) Orientation should be to suit wind direction to
facilities shall be decided based on heat radiation
avoid travel of hydrocarbon vapour over sources
considerations and other considerations like
of ignition.
ground level concentration, cold venting etc.
5.2 INTERDISTANCES
Area around flare should be paved to avoid
growth of grass/vegetation which can otherwise Interdistances between various blocks/facilities
provide combustible material for fires. (Ref. described above shall be as per Table-1.
section 8.0 of OISD-STD-106 on "Process Design
and Operating Philosophies on Relief and
Disposal systems").

(xi) Truck loading facilities should be located close to


product movement gate. Rail loading facilities
should suit rail siding layout and preferably be
located along periphery of the installation.

(xii) Effluent Treatment Plants should be located


minimum one block away from unit area, down
wind of process units and important areas to
avoid odour problems. They should be closer to
disposal point and at lower grade to facilitate
gravity flow of effluent.

(xiii) Sulphur recovery unit and sulphur loading area


should be located close to product movement
gate and away from hazardous and populated
areas. A minimum distance of 50m is recommen-
ded between sulphur storage/handling and any
building or boundary wall.

(xiv) Petroleum coke/coal storage and handling


facilities should be located as far as possible away
from process units, air separation plants,
populated and hazardous areas.

(xv) Sufficient open areas should be left where


construction activities can be undertaken.
Requirements for erecting tall structures should
be studied before finalising the layout.

(xvi) Fire station should be located close to main entry


gate with straight approach to process
units/other critical areas. Fire station and fire
water pump house shall be located at a safe place
away from hazardous areas. Fire station includes
fire tenders, foam equipments and fire fighting
accessories.

(xvii) Fire water storage and pumps shall be located at


a minimum distance of 60 m from hydrocarbon
storage and process units. However for
petroleum depots and terminals, it shall be as per
clause 4.3.5(V) of OISD-STD-117.
OISD-STD-118 Revision - II 9

TABLE - 1 (NOTE1)
MINIMUM INTERDISTANCES BETWEEN BLOCKS/FACILITIES

S.No. From \ To 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

1. Process Units 36 *** 30 45 30 60 90 150 45 60 45 30 60 60 30 90

2. Process Control *** - ** 45 30 60 90 150 45 30 30 - 30 15 30 30


Room

3. Storage Tank 30 ** T3 & T3 & T3 & 30 90 150 30 60 90 30 T6 60 30 50


Class A T5 T5 T5

4. Storage Tank 45 45 T3 & T3 & T3 & 30 90 150 30 60 90 30 T6 30 30 50


Class B T5 T5 T5

5. Storage Tank 30 30 T3 & T3 & T3 & 30 90 150 30 60 90 30 T6 30 30 50


Class C T5 T5 T5

6. Storage Vessels 60 60 30 30 30 T7 90 150 30 90 90 30 T8 45 30 60


(Pressure) LPG/Other

7. Flares-elevated 90 90 90 90 90 90 90 150 90 90 90 90 90 90 90 90

8. Flares-ground 150 150 150 150 150 150 150 150 150 150 150 150 150 150 150 150

9. Bulk loading racks 45 45 30 30 30 30 90 150 T7 90/60 30 T7 T6/T760 30 50


(rail/road) LPG/POL

10. Fire stations/ 60 30 60 60 60 90 90 150 90/60 - 30 30 12 12 30 90


First aid centre

Contd...
10

TABLE - 1 (Contd..)

S.No. From \ To 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

11. Boiler House/ 45 30 90 90 90 90 90 150 30 30 - 15 50 30 30 90


heaters

12. Rail spur 30 - 30 30 30 30 90 150 T7 30 15 - 30 6 15 50

13. Boundary fence 60 30 T6 T6 T6 T8 90 150 T6/T7 12 50 30 - 6 30 50


around installation

14. Service buildings 60 15 60 30 30 45 90 150 60 12 30 6 6 - 30 50

15. Cooling towers, 30 30 30 30 30 30 90 150 30 30 30 15 30 30 - 15


water storage,
nitrogen plant

16. API Separators/ 90 30 50 50 50 60 90 150 50 90 90 50 50 50 15 -


oil sludge pit

** Distance will be 30 meters in case Control Room is blast proof and 60 meters in case it is not blast proof.

*** Refer OISD-STD-163 on Process Control Room Safety

Notes :
1. All distances are in metres.
2. All distances shall be measured between the nearest points on the perimeter of each facility except in case of tank vehicle loading/unloading area
where the distance shall be measured from the centre of each bay.
3. "T" indicates the table to be referred.
4. Where distances have not been specified, it shall be decided based on construction,operation & maintenance requirements.
5. API/CPI, open oil separators/oil collection sumps shall be categorised under the same risk and shall be located at 90m distance from
heaters/boilers. However, if these are covered from top and provided with adequate venting to safe location, the minimum safe distance can be
reduced from 90m to 30m.
OISD-STD-118 Revision - II 11

6. Distance between bulk loading racks and fire station shall be :


(i) For LPG Gantry - 90 m &
ii) For POL Gantry - 60 m.

7. Definitions :

Process Unit - a unit having integrated sequence of operation , physical and chemical, and may involve preparation, separation, purification, or change
in state, energy content or composition.

Service building – a building housing facilities for inspection/maintenance/other supporting services which are directly required for operation of the
plant.

Fire station – a building housing facilities of parking fire tenders and keeping other ready to use fire fighting equipment for meeting plant emergencies,
fire control room with required communication facilities/mimic panel.

Fire pump house – a building housing main fire water pumps, jockey pumps, communication and alarm system, instrumentation and the required
operating & supporting personnel.
12 OISD-STD-118 Revision - II
-118 Revision - I
6.0 LAYOUT OF PROCESS UNITS (vii) Cold boxes should be located on grade or
on separate elevated structures. Adequate
6.1 GENERAL CONSIDERATIONS space should be provided around cold
boxes for ease of operation and
6.1.1 PROCESS EQUIPMENT maintenance.

(i) Process flow sequence and operating (viii) Vessels having large liquid hold-up should
procedures shall be thoroughly understood be installed at lower heights and preferably
so that equipment arrangement in the plot at grade. Adequate drainage should be
plan is functional. Equipment shall be provided around such vessels. Where
arranged in logistic process sequence for process requirement dictates their installa-
short piping runs and operational ease. tion above grade, these should be located
in open area.
(ii) It is recommended that the unit pipe rack
be kept in the centre, thereby splitting the (ix) Towers/columns should be located along
unit into two or more areas of the pipe rack towards open areas for
equipments.Pumps may be arranged in unobstructed erection as well as
two rows close to and on either side of the maintenance of internals at grade. Tall
central pipe rack. Heat Exchangers and towers require frequent operating attention
vessels should be grouped together at upper levels. Hence they may be located
forming outer rows on both sides of the at one place so that common connecting
rack. Fired heaters should be kept at open platform can be provided.
end of the unit upwind from the remaining
plant equipments. (x) Thermo-siphon reboilers should
preferably be placed close to their
(iii) Spacing between battery limits of associated towers. Reboiler should be
individual pieces of equipment shall be mounted on the tower so that vertical
adequate for undertaking maintenance expansion will be uniform, piping system
jobs. design is simplified and inlet/outlet piping
is minimised. Clearance shall be provided
(iv) Spacing between two process units in a for movement between reboiler and tower.
complex should be decided based on shut
down philosophy for maintenance of the (xi) Gas compressors should be located down
units. If the shut down of the units are wind from heaters so that leaked gases will
expected at different occasions, then inter not drift towards the heater. Gas
distances may be increased.This will compressors should have roofing and open
facilitate ease in maintenance and from sides to avoid accumulation of
minimise risk from/for operating units heavier vapours/gases on the floor of
due to hot jobs in the units under shut compressor house. Compressor house
down. should be located near the battery limits to
facilitate ease in maintenance and
(v) Heat exchangers should be located operation.
perpendicular to the pipe rack on the outer
row to facilitate pulling of tube bundles (xii) Heaters should be located up wind at one
with mobile crane or by other means. Shell corner of the unit. Space should be
and tube heat exchanger should have a provided for removal and cleaning of
longitudinal clearance of at least one metre heater tubes besides approach for crane.
plus the length of removable bundles. Areas around the heaters shall be graded
for guiding spills away from process
(vi) Air fin coolers should be installed above equipment. FD fans shall be located away
the pipe rack. Pumps handling hydro- from process equipment from where they
carbons and materials above the arelikely to suck hydrocarbon vapours.
temperature of 230 degree C should not be
installed underneath the air fin coolers. The local control panel for soot blower
control and flue gas analyser shall only be
OISD-STD-118 Revision - II 13

located on and near the process heater. The protection to instruments and personnel is
rest of controls shall be taken to central ensured and non-hazardous electrical area
control room. classification is permitted. It should have
alternate means of exit with doors opening
(xiii) No other tankage except day tanks shall be towards outside. Doors should be made of
provided within battery limits of any fire proof material.
process unit.
(ii) Control room should be designed to cater
(xiv) Flare knock out drum of the closed blow for minimum occupancy.
down system should be located at battery
limit of the unit.
(iii) Transformers should be located in open
(xv) Blow down facilities/burried drum shall be area on the rear side of sub-station.Each
located at one corner of the plant farthest transformer shall be isolated from the other
from furnace or any fired equipment and by a brick masonary wall. Approach road
on the lee-ward side of the unit. to sub-station and transformer bays should
be provided to facilitate crane movement
Vent from Blow down facility shall be for erection and maintenance.
minimum 6m clear off the air fin coolers. It
shall be minimum 6m above the highest (iv) Electrical sub-station should be located
platform if horizontal distance of 15m from adjacent to the control room building and
process equipment is not possible. should meet the requirements of electrical
area classification.
6.1.2 CONTROL ROOM AND SUB-STATION
6.2 EQUIPMENT SPACING WITHIN PROCESS
(i) Control room should be located distinctly UNITS
in the process block or in the adjoining
block. It should be at a safe distance where Interdistances betweenvarious equipments in
process units shall be as per Table-2.
14 OISD-STD-118 Revision - II

TABLE-2
MINIMUM INTERDISTANCES BETWEEN EQUIPMENTS WITHIN PROCESS UNIT
“This table could be used by the oil companies as a guideline for their projects. These could be suitably modified as required to suit space constraints and
relevant engineering practices.” NOTE 1

S.No. From \ To 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

1. Fired heaters/ - 15 15 15 22.5 15 15 20 15 15 15 16/30 15 - 18 15 6 30 15 15


any fired equip.
2. Reactors 15 2 2 6 8 7 15 7 7 4 3 16 - 15 5 15 3 15 15 3
3. Distillation 15 2 3 4 7.5 5 15 5 5 2 3 20 - 15 3 15 3 15 15 3
columns
4. Accumulators 15 6 4 2 8 5 15 4 4 2 3 20 - 15 3 15 3 15 15 3
(Hydrocarbon)
5. Gas compressors 22.5 8 7.5 8 3 7.5 15 7.5 7.5 7.5 7.5 16 - 15 4 15 3 20 15 7.5
(Hydrocarbon)
6. Hot oil transfer 15 7 5 5 7.5 1 7.5 1 1 1 2 2 16 - 15 3 15 - 15 15-
pumps
7. Fuel Oil Day tank 15 15 15 15 15 7.5 2 15 15 15 15 16 - 15 15 15 - 15 15 15
8. Pump for Class A & 20 7 5 4 7.5 1 15 1 1 2 2 16 - 15 3 15 - 15 15 -
all products above
auto-ignition temp.
9. Pumps - other 15 7 5 4 7.5 1 15 1 1 2 2 16 - 15 3 15 - 15 15 -
Hydrocarbon
10. Heat Exchanger- 15 4 2 2 7.5 2 15 2 2 2 2 16 - 15 2 15 2 15 15 -
Hydrocarbon
11. Air Fin Coolers- 15 3 3 3 7.5 2 15 2 2 2 - 16 - 15 2 15 - 15 15 2
Hydrocarbon
12. Control room 16/30 16 20 20 16 16 16 16 16 16 16 - 16 20 16 - 16 16 5 16
13. Snuffing/purging 15 - - - - - - - - - - 16 - - 2 - - 15 5 -
steam isolation
valve
OISD-STD-118 Revision - II 15
14. Fired heaters - 15 15 15 15 15 15 15 15 15 15 20 - - 10 15 - 15 15 5
control panel (local)

Contd....

TABLE - 2 (Contd...)
S.No. From \ To 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

15. Pressure Vessel/ 18 5 3 3 4 3 15 3 3 2 2 16 2 10 2 15 3 15 15 2


Drums
(Hydrocarbon)
16. Fire water 15 15 15 15 15 15 15 15 15 15 15 - - 15 15 - 15 15 - -
hydrants/monitors
17. Pipe rack (main) 6 3 3 3 3 - - - - 2 - 16 - - 3 15 - 15 15 -
18. Blow down facility 30 15 15 15 20 15 15 15 15 15 15 16 15 15 15 15 15 - 15 15
(pumps, drums,
stacks)
19. Water spray 15 15 15 15 15 15 15 15 15 15 15 5 5 15 15 - 15 15 - -
Deluge valve
20. Structural main 15 3 3 3 7.5 - 15 - - - 2 16 - 5 2 - - 15 - -
(Technological
platforms)

Notes:
1. All distances are face to face clear minimum distances in meters.
2. Distance between equipments not covered herein & equipments handling non-hydrocarbons shall be as per good engineering practices.
3. From control room to heater, safe distance shall be 16m if the control room is for one unit and shall be 30m, if it is for two units. For gas
processing plants, it shall be 30m irrespective of whether the control room is for one or more units.
4. Distances between the reactor and furnace when directly connected process-wise, can be relaxed to 5m.
5. Only distances indicated from fired heaters (1) Fuel oil day tank (7), Control room (12), Fired heater local control panel (14), Fire water
hydrant/monitor (16), Blow down facility (18) and water spray deluge valve (19) are by safety considerations. Other distances indicated are
recommended from erection, operation and maintenance safe guards.
6. The local control panel meant for soot blower control & fuel gas analyser shall only be located on and near the process firedheater. The rest of
controls shall be taken to central control room.
7. Safety distances as per preceeding Table-2 for blow down facilities are for open pit location. If the blow down drum is located underground, the
distance from fired heater shall be reduced from 30m to 15m.
8. Steam snuffing/purging valve shall be located minimum 15m from only those equipments which are served bythe steam valve.
16 OISD-STD-118 Revision - II

9. Fuel Oil day tanks shall be located at a safe distance of 15m from equipment except those facilities such as heat exchanger, pump connected directly
with the Fuel Oil system. (Refer Table-5 for interdistance between tanks).
10. Distance between fired heater and distillation column shall be increased to 22.5m in case of light ends such as Naphtha stabiliser.
11. Minimum distances between equipment shall not be applicable for package items and their related appertenances.
OISD-STD-118 Revision - II 17

7.0 LAYOUT OF STORAGE TANKS either buried underground or installed in


the open and surrounded by wall or
7.1 GENERAL CONSIDERATIONS embankment not more than two meter
high and made of earth, concrete or solid
(i) DYKED ENCLOSURES masonry capable of withstanding fully
hydrostatic load. Earth wall of over 1 meter
(a) Petroleum storage tanks shall be located in high shall have not less than 0.6 meter wide
dyked enclosures with roads all around the flat section on top. Note 2
enclosure. Aggregate capacity of tanks
located in one dyked enclosure shall not (f) Pump stations should be located outside
exceed following values : dyke areas by the side of roads.

For a group of (g) Tanks located overhead for process


floating roof tanks : 120,000 cu.m. considerations shall meet safety distance
and shall also have dyked enclosure of
For a group of RCC construction and provided with drain
fixed roof tanks : 60,000 cu.m. valves at suitable height for easy operation.

If a group of tanks contains both fixed and (ii) GROUPING


floating roof tanks, thenit shall be treated
as a group of fixed roof tanks for the (a) Grouping of petoleum products for storage
purpose of above limits. shall be based on the product classifi-
cation. Class "A" and/or class "B" petro-
(b) Dyked enclosure should be able to contain leum can be stored in the same dyked
the complete contents of the largest tank in enclosure. Class "C" petroleum should
the tank farm in case of any emergency. preferably be stored in separate enclosure.
Enclosure capacity shall be calculated after However, where class "C" petroleum is
deducting the volume of tanks (other than stored in a common dyke along with class
the largest tank) upto the height of the "A" and/or class "B" petroleum, all safety
enclosure. A free board of 200 mm above stipulations applicable for class "A" and/
the calculated liquid level shall be or class "B" respectively shall apply.
considered for fixing the height of the
dyke. (b) Excluded petroleum shall be stored in a
separate dyked enclosure and shall not be
However, for excluded petroleum, the stored along with class A, B or C
capacity of the dyked enclosure should be petroleum.
based on spill containment but not for
containment on tank rupture. (c) Tanks shall be arranged in maximum two
rows so that each tank is approachable
(c) The height of tank enclosure dyke shall be from the road surrounding the enclosure.
at least one metre and shall not be more However, tanks having 50,000 cu.m
than 2.0 m above average grade level capacity and above shall be laid in single
inside. However, for excluded Petroleum, row.
the minimum height of dyke wall shall be
600 mm. (iii) FIRE WALLS

(d) Interdistance between the nearest tanks In a dyked enclosure where more than one tank is
located in two dykes shall be equivalent to located, fire walls of 600mm should be provided
the largest tank diameter or 30m, which- as explained below:
ever is more.
(a) Any tank having a diameter more than
(e) The tank or tanks shall be supported on 30m should be separated with fire walls
well designed foundations and shall be from other tank.
18 OISD-STD-118 Revision - II

The following stipulations shall apply for the


(b) Fire walls should be provided by limiting inter distances for above ground tanks storing
the aggregate capacity of each group of petroleum:
tanks within, to 20,000 cu.m.
(i) Inter distances shall be as given in Table-3
(iv) GENERAL for tanks storing class "C" petroleum; or
class "A" and "B" petroleum products with
(a) The tank height shall not exceed one and total storage capacity not exceeding 5000
half times the diameter of the tank or 20m cu.m at one installation.
whichever is less.
(ii) Inter distances shall be as given in Table-4
(b) Piping from/to any tank located in a single for tanks storing class "A" and class "B"
dyked enclosure should not pass through petroleum products with total storage
any other dyked enclosure. Piping capacity exceeding 5000 cu.m
connected to tanks should run directly to
outside of dyke to the extent possible to (iii) Interdistances between tanks and fencing
minimise piping within the enclosures. shall be as given in Table-6 for tanks
storing Class "A", Class "B" and Class "C"
(c) No fire water/foam ring main shall pass petroleum products with total storage
through dyked enclosure. capacity of class "A" and class "B"
petroleum stored exceeding 5000 cu.m
(d) The minimum distance between a tank
shell and the inside toe of the dyke wall (iv) Interdistances between tanks storing
shall not be less than one half the height of excluded petroleum will not be governed
the tank. by Table-3 and 4 and should be decided on
construction, operation and maintenance
7.2 INTERDISTANCES BETWEEN TANKS / OFF- requirements.
SITE FACILITIES
OISD-STD-118 Revision - II 19

TABLE - 3 (NOTE1)
INTERDISTANCES BETWEEN TANKS/OFFSITE FACILITIES
(For small installations)

S.No. From \ To 1 2 3 4 5 6 7 8 9 10 11 12 13

1. Storage tank for 0.5 D 0.5 D 0.5 D 9 9 9 15 15 15 3 15 15 15


petroleum class A or 6 or 6
2. Storage tank for 0.5 D 0.5 D 0.5 D 9 0.5 D 0.5 D 9 4.5 4.5 3 4.5 D D
petroleum class B or 6 or 6 min.4.5 min.4.5
3. Storage tank for 0.5 D 0.5 D - 9 0.5 D - 9 4.5 - - - 0.5 D 0.5 D
petroleum class C or 6 or 6 min.3 min.3
4. Storage / filling shed 9 9 9 - 4.5 6 9 9 9 3 9 9 9
for petroleum class A
5. Storage / filling shed 9 0.5 D 0.5 D 4.5 - 1.5 9 4.5 4.5 1.5 4.5 4.5 4.5
for petroleum class B
6. Storage / filling shed 9 0.5 D - 6 1.5 - 9 4.5 - - - 3 3
for petroleum class C
7. Tank vehicle loading / 15 9 9 9 9 9 - 9 9 3 9 9 9
unloading area for
petroleum class A
8. Tank vehicle loading/ 15 4.5 4.5 9 4.5 4.5 9 - 4.5 1.5 4.5 4.5 4.5
unloading area for
petroleum class B
9. Tank vehicle loading/ 15 4.5 - 9 4.5 - 9 4.5 - - - 3 3
unloading area for
petroleum class C
10. Flame-proof electric 3 3 - 3 1.5 - 3 1.5 - - 3 - -
motors

Contd...
20 OISD-STD-118 Revision - II

TABLE - 3 (Contd...)

S.No. From \ To 1 2 3 4 5 6 7 8 9 10 11 12 13

11. Non-flameproof 15 4.5 - 9 4.5 - 9 4.5 - 3 - - -


electric motors

12. Office building, stores, 15 D 0.5 D 9 4.5 3 9 4.5 3 - - - -


amenities etc. within min. 4.5 min. 3
installation

13. Boundary fencing 15 D 0.5 D 9 4.5 3 9 4.5 3 - - - -


around installation min. 4.5 min. 3

Notes:

1. All distances are in metres.


2. Above table is applicable for installations where
i) Only petroleum class C is stored.
ii) The total quantity of petroleum class A and class B stored above ground in bulk does not exceed 5000 cu.m.
iii) The diameter of any tank storing petroleum class A or petroleum class B does not exceed 9m.
3. Interdistances given for tanks are shell to shell in the same dyke.
4. All distances shall be measured between the nearest point on the perimeter of each facility except in the case of tank vehicle
loading/unloading area where the distance shall be measured from the centre of each bay.
5. Where alternate distances are stipulated, maximum thereof shall be observed.
6. Notation :
"D" – diameter of the tank
(-) – a distance suitable for constructional and operational convenience.
OISD-STD-118 Revision - II 21

TABLE - 4

INTERDISTANCES BETWEEN STORAGE TANKS/OFFSITE FACILITIES

S.No. From \ To 1 2 3 4 5 6 7 8 9

1. Storage tank for petroleum T5 T5 T5 15 15 15 15 8 15


class A
2. Storage tank for petroleum T5 T5 T5 15 15 15 15 8 15
class B
3. Storage tank for petroleum T5 T5 T5 15 - 8 - - -
class C
4. Storage / filling shed for 15 15 15 - 8 15 15 8 15
petroleum class A or
class B
5. Storage/filling shed for 15 15 - 8 - 8 - - -
petroleum class C
6. Tank vehicle loading/ 15 15 8 15 8 - - 8 15
unloading area for
petroleum class A or B
7. Tank vehicle loading/ 15 15 - 15 - - - - -
unloading area for
petroleum class C
8. Flame proof electric pump 8 8 - 8 - 8 - - 8
motor
9. Non-flame proof electric 15 15 - 15 - 15 - 8 -
pump motor

Notes :

1. All distances are in metres.


2. Above table is applicable for installations where total quantity of petroleum class A and class B stored above
ground in bulk exceeds 5000 cu.m or where the diameter of any such tank for the storage of petroleum exceeds 9
m.
3. All distances shall be measured between the nearest points on the perimeter of each facility except in the case of
tank vehicle loading/unloading area where the distance shall be measured from the centre of each bay.
4. Notation:
(-) – any distance suitable for constructional or operational convenience.
T5 – Table-5 shall be referred.
5. This table is applicable for class C petroleum storage also alongwith class A & B petroleum as per limits specified
under note-2 above.
OISD-STD-118 Revision - II 23

TABLE - 5

INTERDISTANCES BETWEEN STORAGE TANKS

Sl. Item Floating Roof Fixed Roof Class C


No. Tanks Tanks (Class Petroleum
A & B Petroleum

1. All tanks with diameters (D + D) / 4 (D + d) / 4 (D + d) / 6


upto 50 metres

2. All tanks with diameters (D + d) / 4 (D + d) / 3 (D + d) / 4


exceeding 50 metres

Notes :

1. This table is applicable for installations where aggregate storage capacity of class A and class B
petroleum stored above grade exceeds 5000 cu.m. or where the diameter of any such tank for the storage
of petroleum exceeds 9 m.

2. Distances given are shell to shell in the same dyke.

3. Notation:

D – diameter of larger tank in metres

d – diameter of smaller tank in metres

4. If the interdistance (for class A & B) calculated as above are less than 15m,then minimum of 15m or 0.5 D
or d shall be followed.

5. Interdistance between class A/B storage tanks and classC storage tanks shall not be less than 6 metres.
TABLE - 6 (NOTE1)

DISTANCES FROM BOUNDARY FENCING

Minimum Distance
from Boundary
S.No. Installation fencing around
Installation

1. Storage tank for Petroleum Class A **

2. Storage tank for Petroleum Class B **

3. Storage tank for Petroleum Class C **

4. Storage/filling shed for Petroleum 15


Class A or Class B

5. Storage/filling shed for Petroleum 10


Class C

6. Tank vehicle loading/unloading area 20


for class A & B petroleum

7. Tank vehicle loading/unloading area 10


for class C petroleum

Notes :

1. All distances are in metres.

2. This table is applicable for facilities in an installation where total quantity of petroleum class A & B stored
above ground in bulk exceeds 5000 cu.m. or where the diameter of any such tank for the storage of
petroleum exceeds 9 m.

3. Notation:

"D" – diameter of larger tank in metres.

4. Above table is based on the assumption that property beyond the boundary line is either protected or
adequate green belt is provided as a safety buffer where no structure exists. Property beyond property
line is deemed protected if it is within the jurisdiction of public Fire Brigade or plant's own Fire Brigade.

** (I) Distance from Floating roof tank to boundary fencing for stable and boil-over liquids, having
protection for exposure shall be D/2 (minimum 20m).

(ii) For tanks with weak roof-to-shell joint :


OISD-STD-118 Revision - II 25

The above distance shall be D/2 (minimum 20m) for tanks having approved foam or inerting
system and the tank diameter not exceeding 50m.
8.0 LAYOUT OF LPG FACILITIES of one sphere, the sump size shall be equal
to layout of two spheres.
(b) Curb wall around the storage tank shall
8.1 GENERAL CONSIDERATIONS have a minimum height of 30cm. However
it shall not exceed 60cm at shallow sump
8.1.1 LPG STORAGE position, as otherwise evaporation of
spilled LPG may get affected.
(i) GROUPING
(c) There shall not be any depressions, large
Vessels shall be arranged into groups each having ditches and low lying areas around LPG
a maximum of six vessels. Capacity of each group storage as the leaked gas can accumulate,
shall be limited to 15000 cu.m. Each group shall being heavier than air. Top surface of the
be provided with a curb wall. vessels installed in a group should be on
the same plane so that safety blowout from
Any vessel in one group shall be separated from a one vessel does not affect the other vessel.
vessel in another group by a minimum distance This will also minimise the chances of
of 30m. overfilling of adjoining vessels due to
gravitation.
Spheres and bullets shall be treated as separate
groups with 30m safety distance between two (d) A typical layout plan of LPG sphere area
groups. Separate dedicated manifold shall be with major safety requirements of distan-
provided for each group. ces, drainage sump, pump station location
etc. is enclosed at Annexure-1 for general
ii) LOCATION guidance.

(a) Longitudinal axes of horizontal vessels 8.1.2 LPG BOTTLING


(Bullets) should not point towards other
vessels, vital process equipments and (i) LOCATION
control room.
LPG bottling facilities should be located at a safe
(b) Storage vessels should be located down distance from other facilities with minimum
wind of process units, important buildings ingress to trucking traffic and downwind to
and facilities. storage as far as possible.

(c) LPG storage vessels shall not be located There shall not be any deep ditches in the
within the same dykes where other surrounding area to avoid LPG settling.
flammable liquid hydrocarbons are stored.
(ii) CONSTRUCTION
(d) Storage vessels shall be laid out in single
row both in case of the spheres and bullets. Bottling section shall be of single storey having
Storage vessels shall not be stacked one roofing and open from sides for adequate
above the other. ventilation so that leaked gas can drift away.
RCC roofing should not be used to the extent
(iii) SPILLS AND LEAKS possible.

(a) Spillage collection shallow sump shall be (iii) OPERATION


located at a distance where the flames from
sump fire will not impinge on the vessel. (a) Stacking areas for empty and filled
This distance shall not be less than the cylinders should be located separately.
diameter of the nearest vessel or 15m Cylinders shall be stacked vertically.
whichever is higher. The capacity of the Filling machines and testing facilities shall
collection sump shall be as per drawing be organised in sequential manner
enclosed at Annexure-1. However in case distinctly in a separate area.
OISD-STD-118 Revision - II 27

(b) Filled LPG cylinders shall not be stored in


the vicinity of cylinders containing other (b) LPG rail loading/unloading station shall
gases or hazardous substances. be located on a separate rail spur and shall
(c) Storage shall be kept on or above grade not be grouped with other products.
and never below grade in cellar or
basement. (c) LPG loading/unloading rail gantries shall
be separated from other rail shunting
(d) Trucking traffic shall be smooth to avoid facilities by a minimum distance of 50m,
blocking/ obstruction for loading and except relating to service for the same
unloading of cylinders. gantry.

8.1.3 LPG BULK HANDLING (ii) Rail loading/unloading of LPG should be


restricted to a maximum of half rake, presently
(i) LOCATION capacity of which is 500 MT. If full rake
loading/unloading is envisaged, this shall be
(a) LPG truck loading/unloading station shall done on two separate rail gantries having a
be located in a separate block and shall not minimum distance of 50m. In case of 8 wheeler
be grouped with other products. wagons half rake unloading/ loading capacity
shall be 600 MT.
Maximum number of LPG tank lorry bays
shall be restricted to 8 in one group. The 8.2 INTERDISTANCES FOR LPG FACILITIES
bay should be designed in such a way that
the driver's cabin will be facing the exit Interdistances for LPG facilities shall be as given
direction and shall have no obstruction. in Table-7.
TABLE - 7
INTERDISTANCES FOR LPG FACILITIES

S.No. From \ To 1 2 3 4 5 6 7

1. LPG Storage vessels * T8 30 30 30 15 60

2. Boundary/property line/ T8 - 30 30 30 30 **
group of buildings, not
associated with LPG plant

3. Shed-LPG/Cold repair shed/ 30 30 15 30 30 15 60


cylinder evacuation facilities

4. Tank Wagon Gantry 30 30 30 50 50 30 60


Tank Truck Gantry

5. Rail spurs 30 30 30 50 50 30 60

6. Pump house/Comp. 15 30 15 30 30 - 60
house(LPG)

7. Fire Pump house 60 ** 60 60 60 60 -

Notes :

1. All distances are in metres.

2. Notation:

T8 – Refer Table - 8

* 1/4 of sum of diameters of adjacent vessels or half the diameter of the larger of the two adjacent
vessels whichever is greater.

** Any distance for operational convenience.

3. Distance of stabling line shall be as per minimum Railway Standards.


OISD-STD-118 Revision - II 29

TABLE - 8 (NOTE1)

INTERDISTANCES BETWEEN LPG STORAGE VESSELS AND


BOUNDARY / PROPERTY LINE / GROUP OF BUILDINGS
NOT ASSOCIATED WITH LPG FACILITIES

Capacity of
S.No. Each Vessel Distance
(Cum.M. of water)

1. 10 - 20 15

2. 21 - 40 20

3. 41. 350 30

4. 351 - 450 40

5. 451 - 750 60

6. 751 - 3800 90

Note :

All distances are in metres.


9.0 LAYOUT OF UTILITY STATIONS The waste disposal facilities like effluent
channels, land fill areas for disposing off solid
9.1 GENERAL CONSIDERATIONS waste etc. should preferably be located by the
side of boundary wall, but down stream of wind
Boiler House, Air compressors, fuel oil facilities direction so that the foul odour that may be
(for generation of steam) shall be located in separate present at times does not affect the plant
block adjoining the process unit blocks. The steam personnel and neighbourhood areas. Locating the
generation facilities block should preferably include waste disposal facility near the boundary wall
boiler feed water pump, chemical block for boiler house also eliminates the vehicular movement in
etc., which form the integral part of the steam process areas in case solid wastes are to be taken
generation facilities. out of installation for disposal.

The plant air compressors and drying units iv) SMOKING BOOTHS
should preferably be located in the boiler house unit
block. Fuel oil heating and pumping facilities may also Smoking booths should not be provided in
be located within the boiler house unit block. These may hydrocarbon industry. However if it is necessary
be located in the boiler house unit block to minimise the to provide smoking booths, these should be
spreading ofvarious utility blocks around the process located at a safe distance of :
unit, to facilitate ease of operation.
(i) 30m from hydrocarbon source in case of oil
( i) ELECTRICAL refinery/storage installation.
(ii) 60m from hydrocabon source in case of
Electrical generation facilities should be located
LPG/Gas Processing Plants.
near the process unit block because such electrical
generation units normally supply steam to the
9.2 INTERDISTANCES
process units e.g. Cogeneration. When external
power grid is interconnected with plant power
Interdistances between various utility stations
generation facilities, either the power plant shall
and other facilities shall be as given in Table-1.
be located at the side of boundary wall or the
external power transmission lines shall be taken
underground upto the interconnection grid 10.0 REFERENCES
inorder to minimise the length of overhead
transmission lines within the plant. 1. OISD-STD-106 on Process Design and
Operating Philosophies on Relief and
(ii) COOLING TOWERS Disposal Systems.
2. OISD-STD-144 on LPG Bottling and
Cooling towers should be located away from Distribution.
process unit area, preferably downstream
3. NFPA Standard No.30 "Flammable and
direction of wind to avoid corrosion of the
Combus-tible Liquids Code".
equipments in process areas.
4. Petroleum Rules - 1976.
(iii) WASTE DISPOSAL FACILITIES 5. OISD-STD-117on Fire Protection facilities
for Petroleum depots and terminals.
Separate collection system should be provided for
different types of waste generated in the process 6. OISD-STD-116 on Fire Protection facilities
plant such as oily water, cooling tower for Petroleum Refineries/process plants.
blowdown, caustic and acidic effluents, sludge, 7. SMPV Rules - 1981.
fecal etc.
OISD-STD-118 Revision - II 31

ANNEXURE - 1

TYPICAL LAYOUT OF LPG STORAGE VESSELS

Section - XX
NOTES :
1. ALL DIMENSIONS ARE IN METRES
2. TOP SURFACE OF ALL VESSELS INSTALLED SHALL BE IN THE SAME PLANE.
3. SIZING CRITERIA FOR SUMP—FULL CONTAINMENT OF LPG SPHERE WITHIN KERB AREA IS NOT ENVISAGED HOWEVER
THERE IS CHANCE OF SMALL SPILL OFLPG IN THE STORAGE AREA IT IS ASSUMED THAT THE LEAK WILL BE ARRESTED
WITHIN ABOUT AN HOUR THE CONTAINMENT VOLUME FOR ONE HOUR LEAK CORRESPONDING TO LARGEST NOZZLE
SIZE AND LIGHTEST MATERIAL IS 18 MT OR ABOUT 35 M3 WITH A MAXIMUM LIQUID COLLECTION RATE OF APPROX. 5
KG./SEC.
4. ALL LEVELS ARE WITH RESPECT TO HIGH POINT OF PAVEMENT LEVEL I.E. 100.00
5. PROTECTIVE WALLS TO BE PROVIDED IF THE VALVE IS WITHIN 30 M FROM SPHERE SHELL.
6. WATER SEAL SHALL BE PROVIDED AT OUTLET FROM SHALLOW SUMP.

LEGEND :

DVA Deluge Valve Assembly


........ Fire Water Piping
(Not to Scale)

Das könnte Ihnen auch gefallen