Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control

(75 que stions)

[Fact Pattern #1] ProperPropeller,Inc.planstomanufactureanewlydesignedhigh-technologypropellerfor airplanes.ProperPropellerforecaststhatasworkersgainexperience,theywillneedlesstimeto completethejob.Basedonpriorexperience,ProperPropellerestimatesa70%cumulative learningcurveandhasprojectedthefollowingcosts. Cumulativenumber ofunitsproduced 1 2 ManufacturingProjections Averagecostperunit Totalcosts $20,000 $20,000 14,000 28,000

[1] Gleim #: 1.3.99 -- Source: CMA 0408 1-146 (ReferstoFactPattern#1) IfProperPropellerproduceseightunits,thetotalmanufacturingcostwillbe A. B. C. D. $62,643 $54,880 $112,000 $50,660 Answer(A)isincorrect.Theamountof$62,643resultsfromusinganincorrect learningcurve. Answer(B)iscorrect.Learningcurveanalysisisusedtoprojectproductivitygains resultingfromtheincreasedrateatwhichpeopleperformtasksastheygainexperience. Theunderlyingassumptionoflearningcurveanalysisisthatworkersgainproductivity atapredictablerateastheygainexperiencewithanewprocess.Inthissituation,the companyisassumingthatthetotalcostsrequiredforeachdoublingofoutputwillbe 70%ofthecostsrequiredforthepreviousdoubling.TheeffectsofProperPropellers projectedlearningcurvecanbecalculatedasfollows: Cumulative Units Produced 1 2 4 8 Cumulative Average Cost $20,000 $14,000($20,00070%) $9,800($14,00070%) $6,860($9,80070%) Cumulative Total Cost $20,000 28,000 39,200 54,880

Batch 1 2 3 4

Answer(C)isincorrect.Theamountof$112,000resultsfromignoringthelearning curveafterthesecondunit. Answer(D)isincorrect.Theamountof$50,660resultsfromimproperlysummingthe cumulativeaveragecostfigures.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 1

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

[2] Gleim #: 1.1.28 -- Source: CMA 0408 2-010 Whichoneofthefollowingstatementsconcerningapproachesforthebudgetdevelopment processiscorrect? A. Sincedepartmentmanagershavethemostdetailedknowledgeaboutorganizational operations,theyshouldusethisinformationasthebuildingblocksoftheoperating budget. B. Thetop-downapproachtobudgetingwillnotensureadherencetostrategic organizationalgoals. C. Withtheinformationtechnologyavailable,theroleofbudgetsasanorganizational communicationdevicehasdeclined. D. Topreventambiguity,oncedepartmentalbudgetedgoalshavebeendeveloped,they shouldremainfixedevenifthesalesforecastuponwhichtheyarebasedprovestobe wronginthemiddleofthefiscalyear. Answer(A)iscorrect.Sincedepartmentmanagershavethemostdetailedknowledge aboutorganizationaloperations,theyshouldusethisinformationasthebuildingblocks oftheoperatingbudget. Answer(B)isincorrect.,whileatop-downapproachcanhelpmakestrategicgoals moreconsistent,itcannotensureadherence. Answer(C)isincorrect.informationtechnologymakesbudgetingeasier,notless relevantasameansoforganizationalcommunication. Answer(D)isincorrect.anybudgetshouldbeadaptedtochangingcircumstances. [3] Gleim #: 1.5.145 -- Source: CMA 0408 1-176 JohnsonSoftwarehasdevelopedanewsoftwarepackage.Johnsonssalesmanagerhas preparedthefollowingprobabilitydistributiondescribingtherelativelikelihoodofmonthly saleslevelsandrelativeincome(loss)forthecompanysnewsoftwarepackage. MonthlySales InUnits 10,000 20,000 30,000 40,000

Probability .2 .3 .3 .2

Income(Loss) $(4,000) 10,000 30,000 60,000

IfJohnsondecidestomarketitsnewsoftwarepackage,theexpectedvalueofadditional monthlyincomewillbe A. B. C. D. $25,000 $24,000 $24,800 $23,200

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 2

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

Answer(A)isincorrect.Theamountof$25,000resultsfromimproperlyweightingthe monthlysalesunits,ratherthantheincomeandlossfigures,bytheprobabilities. Answer(B)isincorrect.Theamountof$24,000resultsfromfailingtoaccountforthe $4,000lossatthe10,000-unitsaleslevel. Answer(C)isincorrect.Theamountof$24,800resultsfromimproperlytreatingthe$4,000 fromthe10,000-unitlevelasincomeratherthanasaloss. Answer(D)iscorrect.Expectedvalueisameansofassociatingadollaramountwitheach ofthepossibleoutcomesofaprobabilitydistribution.Theoutcomeyieldingthehighest expectedvalue(whichmayormaynotbethemostlikelyone)istheoptimalalternative.The expectedvalueofeachoutcome,andoftheprojectasawhole,canbedeterminedthrough thepreparationofapayofftable,asfollows: Monthly Sales InUnits 10,000 20,000 30,000 40,000

Probability .2 .3 .3 .2

Income (Loss) $(4,000) 10,000 30,000 60,000

= = = =

Expected Value $(800) 3,000 9,000 12,000 $23,200

[4] Gleim #: 1.2.62 -- Source: CMA 1289 4-11 Allofthefollowingareassumptionsunderlyingthevalidityoflinearregressionoutputexcept A. B. C. D. Thestandarddeviationoftheerrorsisconstant. Certainty. Themeanoftheerrorsiszero. Theerrorsarenormallydistributed. Answer(A)isincorrect.Itisanassumptionoftheregressionmodel. Answer(B)iscorrect.Linearregressionisbasedonseveralassumptions;forexample, thatthereisnochangeintheenvironment,thaterrorsinthevaluesofthedependent variablesarenormallydistributedwithameanofzero,thatthestandarddeviationof theseerrorsisconstant,thatthevaluesofthedependentvariablesarestatistically independentofeachother,andthattheindependentvariablesarenotcorrelatedwith eachother.However,regressionisonlyameansofpredictingthefuture;itcannot providecertainty. Answer(C)isincorrect.Itisanassumptionoftheregressionmodel. Answer(D)isincorrect.Itisanassumptionoftheregressionmodel.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 3

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

[5] Gleim #: 1.2.65 -- Source: CMA 0408 1-137 Acompanyhasaccumulateddataforthelast24monthsinordertodetermineifthereisan independentvariablethatcouldbeusedtoestimateshippingcosts.Threepossible independentvariablesbeingconsideredarepackagesshipped,milesshipped,andpounds shipped.Thequantitativetechniquethatshouldbeusedtodeterminewhetheranyofthese independentvariablesmightprovideagoodestimateforshippingcostsis A. B. C. D. Linearprogramming. Linearregression. Flexiblebudgeting. Variablecosting. Answer(A)isincorrect.linearprogrammingisamathematicaltechniqueusedto optimizealinearfunctionsubjecttocertainconstraints. Answer(B)iscorrect.Regressionanalysis,alsocalledleast-squaresanalysis,isthe processofderivingthelinearequationthatdescribestherelationshipbetweentwo(or more)variableswithanonzerocoefficientofcorrelation. Answer(C)isincorrect.flexiblebudgetingisthecalculationofthequantityandcostof inputsthatshouldhavebeenconsumedgiventheachievedlevelofproduction. Answer(D)isincorrect.variablecostingisacostingtechniquethattreatsonlyvariable manufacturingcostsasproductcosts. [6] Gleim #: 1.1.27 -- Source: CMA 0408 2-008 Whichoneofthefollowingisnotanadvantageofaparticipatorybudgetingprocess? A. B. C. D. Communicationbetweendepartments. Coordinationbetweendepartments. Controlofuncertainties. Costcongruence. Answer(A)isincorrect.participatorybudgetinginvolvesextensivecommunication betweendepartments. Answer(B)isincorrect.participatorybudgetinginvolvesextensivecoordination betweendepartments. Answer(C)iscorrect.Uncertaintiescanbepreparedfor,buttheycannotbesubjected tohumancontrolthroughanybudgetprocess. Answer(D)isincorrect.goalcongruenceisoneoftheadvantagesofparticipatory budgeting.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 4

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

[Fact Pattern #2] TheCollegeHonorSocietysellshot pretzelsatthehomefootballgames. Thepretzelsaresoldfor$1.00each, andthecostperpretzelis$.30.Any unsoldpretzelsarediscardedbecause theywillbestalebeforethenexthome game. Thefrequencydistributionofthedemandfor pretzelspergameispresentedasfollows. UnitSalesVolume 2,000pretzels 3,000pretzels 4,000pretzels 5,000pretzels 6,000pretzels Probability .10 .15 .20 .35 .20

[7] Gleim #: 1.5.126 -- Source: CMA 1289 5-21 (ReferstoFactPattern#2) Theestimateddemandforpretzelsatthenexthomefootballgameusingadeterministic approachbasedonthemostlikelyoutcomeis A. B. C. D. 4,000pretzels. 4,400pretzels. 6,000pretzels. 5,000pretzels. Answer(A)isincorrect.Thefigureof4,000pretzelsassumeseachoutcomeisequally likely. Answer(B)isincorrect.Theestimateddemandusinganexpectedvalueapproachis 4,400pretzels. Answer(C)isincorrect.Thefigureof6,000pretzelsismerelythegreatestdemand. Answer(D)iscorrect.Adeterministicapproachassumesthatavalueisknownwith certainty.Ifthatvalueisdeemedtobethemostlikelyoutcome,assumeddemandwill be5,000pretzels,thevolumewiththehighestprobability(35%). [8] Gleim #: 1.6.159 -- Source: CMA 0408 1-141 Whichoneofthefollowingtechniqueswouldmostlikelybeusedtoanalyzereductionsin thetimerequiredtoperformataskasexperiencewiththattaskincreases? A. B. C. D. Regressionanalysis. Sensitivityanalysis. Learningcurveanalysis. Normalprobabilityanalysis.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 5

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

Answer(A)isincorrect.regressionanalysis,alsocalledleast-squaresanalysis,istheprocess ofderivingthelinearequationthatdescribestherelationshipbetweentwo(ormore) variableswithanonzerocoefficientofcorrelation. Answer(B)isincorrect.sensitivityanalysisisusedtorevealhowsensitiveexpectedvalue calculationsaretotheaccuracyoftheinitialestimates. Answer(C)iscorrect.Learningcurveanalysisisusedtoprojectproductivitygainsresulting fromtheincreasedrateatwhichpeopleperformtasksastheygainexperience. Answer(D)isincorrect.normalprobabilityanalysisisusedtodeterminatewhetherthe distributionofasetofdataisstatisticallynormal. [9] Gleim #: 1.2.67 -- Source: CMA 0408 1-139 Inordertoanalyzesalesasafunctionofadvertisingexpenses,thesalesmanagerofSmith Companydevelopedasimpleregressionmodel.Themodelincludedthefollowingequation, whichwasbasedon32monthlyobservationsofsalesandadvertisingexpenseswitharelated coefficientofdeterminationof.90. Sales=$10,000+(2.5Advertisingexpenses) IfSmithCompanysadvertisingexpensesinonemonthamountedto$1,000,therelated pointestimateofsaleswouldbe A. B. C. D. $12,500 $11,250 $2,500 $12,250 Answer(A)iscorrect.Thesimpleregressionequationcanbesolvedasfollows: Sales = = = = $10,000+(2.5Advertisingexpenses) $10,000+(2.5$1,000) $10,000+$2,500 $12,500

Answer(B)isincorrect.Theamountof$11,250resultsfromimproperlymultiplying theanswerbythecoefficientofdetermination. Answer(C)isincorrect.Theamountof$2,500includesonlytheadvertisingexpense. Answer(D)isincorrect.Theamountof$12,250resultsfromimproperlyapplyingthe coefficientofdeterminationtotheadvertisingexpense.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 6

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

[Fact Pattern #3] AcomputerstoresellsfourcomputermodelsdesignatedasP104,X104,A104,andS104.The storemanagerhasmaderandomnumberassignmentstorepresentcustomerchoicesbasedonpast salesdata.Theassignmentsareshownbelow. Model P104 X104 A104 S104 RandomNumbers 0-1 2-6 7-8 9

[10] Gleim #: 1.5.143 -- Source: CMA 688 5-26 (ReferstoFactPattern#3) Inrunningasimulationofthecomputerdemand,thefollowingnumbersaredrawnin sequence:2,8,and6.Thesimulationindicatesthatthethirdcustomerwillpurchase. A. B. C. D. ModelX104. ModelS104. ModelP104. ModelA104. Answer(A)iscorrect.Thethirdcustomerissimulatedbythethirdnumberdrawn. Therefore,thethirdcustomerspurchaseisrepresentedbythenumber6.Thenumbers 2through6correspondtomodelX104.Thus,thethirdcustomerisexpectedto purchasemodelX104. Answer(B)isincorrect.ModelS104correspondstonumber9. Answer(C)isincorrect.ModelP104correspondstonumbers0and1. Answer(D)isincorrect.ModelA104correspondstonumbers7and8.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 7

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

[11] Gleim #: 1.1.30 -- Source: CMA 0408 2-012 MariettaThomas,AmadorCorporationsvicepresidentofplanning,hasseenandheardit all.Shehastoldthecorporatecontrollerthatsheis....veryupsetwiththedegreeofslack thatveteranmanagersusewhenpreparingtheirbudgets.Thomashasconsidered implementingsomeofthefollowingactivitiesduringthebudgetingprocess. 1. Developthebudgetsbytopmanagementandissuethemtolower-leveloperatingunits. 2. Studytheactualrevenuesandexpensesofpreviousperiodsindetail. 3. Havethebudgetsdevelopedbyoperatingunitsandacceptthemassubmittedbya company-widebudgetcommittee. 4. Sharethebudgetswithallemployeesasameanstoreachcompanygoalsand objectives. 5. Useaniterativebudgetingprocessthathasseveralroundsofchangesinitiatedby operatingunitsand/orseniormanagers. WhichoneoftheseactivitiesshouldAmadorimplementinordertobestremedyThomas concerns,helpeliminatetheproblemsexperiencedbyAmador,andmotivatepersonnel? A. B. C. D. 2,4,and5. 2and3. 1only. 2and4. Answer(A)iscorrect.Steps2,4,and5areappropriateforalleviatingAmadors budgetproblems.Step1shouldnotbeperformedbecauseabudgetimposedfromthe topismorelikelytoencounterresistance.Step3shouldnotbeperformedbecause operatingunitswilltendtoconsideronlytheirowninterestswhenpreparingbudgets. Answer(B)isincorrect.operatingunitswilltendtoconsideronlytheirowninterests whenpreparingbudgets. Answer(C)isincorrect.abudgetimposedfromthetopismorelikelytoencounter resistance. Answer(D)isincorrect.,whilestudyingpreviousperiodsandsharingthebudgetwith allemployeesareimportantstepstocorrectingAmadorsproblems,incrementally improvingthebudgetthroughaniterativeprocessisalsocrucial.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 8

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

[Fact Pattern #4] StanBerryisconsideringsellingpeanutsattheKeeferHighSchoolfootballgames.Thepeanuts wouldcost$.50perbagandcouldbesoldfor$1.50perbag.Noothercostswouldbeincurredto sellthepeanuts.Allunsoldbagscanbereturnedtothesupplierfor$.30each.Berryestimatedthe demandforpeanutsateachfootballgameandconstructedthepayofftablethatfollows. Demand (Bags) 20 30 40 50 Probability ofDemand .2 .4 .3 .1 20 $20 $20 $20 $20 Action(BagstoStock) 30 $18 $30 $30 $30 40 $16 $28 $40 $40 50 $14 $26 $38 $50

[12] Gleim #: 1.5.140 -- Source: CMA 690 5-18 (ReferstoFactPattern#4) ThemaximumthatStanBerryshouldpayforperfectinformationsothathecouldalways stockthecorrectnumberofbagsofpeanutsis A. B. C. D. $30.00 $.80 $2.60 $10.40

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 9

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

Answer(A)isincorrect.ThemostStanwouldpayforperfectinformationisthedifference betweenexpectedprofitwithperfectinformationandexpectedprofitwithoutperfect information. Answer(B)isincorrect.ThemostStanwouldpayforperfectinformationisthedifference betweenexpectedprofitwithperfectinformationandexpectedprofitwithoutperfect information. Answer(C)iscorrect.Expectedvalueanalysisestimatesfuturemonetaryvaluebasedon forecastsandtheirrelatedprobabilitiesofoccurrence.Theexpectedvalueisfoundby multiplyingtheprobabilityofeachoutcomebyitspayoffandsummingtheproducts.The expectedvalueofperfectinformationisthedifferencebetweentheexpectedvalueunder certaintyandtheexpectedvalueoftheoptimaldecisionunderuncertainty.Theexpected valueundercertaintyequalsthesumoftheproductsoftheprofitmaximizingpayoffsof perfectforecastsandtherelatedprobabilities. 20%$20= 40%$30= 30%$40= 10%$50= Expectedpayoffwithperfectinfo. $4.00 12.00 12.00 5.00 $33.00

Thus,withperfectinformation,theproprietorcouldachieveanaverageprofitof$33per game.Withoutperfectinformation,theexpectedvalueisonly$30.40.Accordingly,upto $2.60couldbepaidforperfectinformation($33-$30.40). Answer(D)isincorrect.ThemostStanwouldpayforperfectinformationisthedifference betweenexpectedprofitwithperfectinformationandexpectedprofitwithoutperfect information. [13] Gleim #: 1.2.50 -- Source: CIA 595 II-46 Theinternalauditorofabankhasdevelopedamultipleregressionmodelwhichhasbeen usedforanumberofyearstoestimatetheamountofinterestincomefromcommercialloans. Duringthecurrentyear,theauditorappliesthemodelanddiscoversthatther2valuehas decreaseddramatically,butthemodelotherwiseseemstobeworkingokay.Whichofthe followingconclusionsarejustifiedbythechange? A. B. C. D. Changingtoacross-sectionalregressionanalysisshouldcauser 2toincrease. Regressionanalysisisnolongeranappropriatetechniquetoestimateinterestincome. Somenewfactors,notincludedinthemodel,arecausinginterestincometochange. Alinearregressionanalysiswouldincreasethemodelsreliability.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 10

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

Answer(A)isincorrect.Cross-sectionalregressionanalysisisinappropriate.Theauditoris tryingtoestimatechangesinasingleaccountbalanceovertime. Answer(B)isincorrect.Regressionanalysismaystillbethemostappropriatemethodology toestimateinterestincome,buttheauditorshouldfirstunderstandthefactorsthatmaybe causingr2todecrease.Thereasonmaybeasystematicerrorintheaccountbalance. Answer(C)iscorrect.Thecoefficientofdetermination(r2)istheamountofvariationin thedependentvariable(interestincome)thatisexplainedbytheindependentvariables.In thiscase,lessofthechangeininterestincomeisexplainedbythemodel.Thus,someother factormustbecausinginterestincometochange.Thischangemeritsauditinvestigation. Answer(D)isincorrect.Linearregressionmodelsaresimplermodels,buttheauditor shouldbesearchingforasystematicerrorintheaccountbalanceorapplyingamore complexmodel. [14] Gleim #: 1.2.64 -- Source: CMA 0408 1-136 Forcostestimation,simpleregressiondiffersfrommultipleregressioninthatsimple regressionusesonly A. Oneindependentvariable,whilemultipleregressionusesmorethanoneindependent variable. B. Onedependentvariable,whilemultipleregressionusesallavailabledatatoestimatethe costfunction. C. Dependentvariables,whilemultipleregressioncanusebothdependentandindependent variables. D. Onedependentvariable,whilemultipleregressionusesmorethanonedependent variable.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 11

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

Answer(A)iscorrect.Simpleregressionusesthealgebraicformulaforastraightline,y=a +bx,wherexistheindependentvariable.Multipleregressionisusedwhenthereismore thanoneindependentvariable.Multipleregressionallowsafirmtoidentifymanyfactors (independentvariables)andtoweighteachoneaccordingtoitsinfluencesontheoverall outcome(y=a+b1x1+b2x2+b3x3+etc.). Answer(B)isincorrect.simpleregressionusesthealgebraicformulaforastraightline,y= a+bx,wherexistheindependentvariable.Multipleregressionisusedwhenthereismore thanoneindependentvariable.Multipleregressionallowsafirmtoidentifymanyfactors (independentvariables)andtoweighteachoneaccordingtoitsinfluencesontheoverall outcome(y=a+b1x1+b2x2+b3x3+etc.). Answer(C)isincorrect.simpleregressionusesthealgebraicformulaforastraightline,y= a+bx,wherexistheindependentvariable.Multipleregressionisusedwhenthereismore thanoneindependentvariable.Multipleregressionallowsafirmtoidentifymanyfactors (independentvariables)andtoweighteachoneaccordingtoitsinfluencesontheoverall outcome(y=a+b1x1+b2x2+b3x3+etc.). Answer(D)isincorrect.simpleregressionusesthealgebraicformulaforastraightline,y= a+bx,wherexistheindependentvariable.Multipleregressionisusedwhenthereismore thanoneindependentvariable.Multipleregressionallowsafirmtoidentifymanyfactors (independentvariables)andtoweighteachoneaccordingtoitsinfluencesontheoverall outcome(y=a+b1x1+b2x2+b3x3+etc.).Bothmethodsuseonlyonedependentvariable. [15] Gleim #: 1.1.22 -- Source: CMA 0408 2-001 Allofthefollowingareadvantagesoftheuseofbudgetsinamanagementcontrolsystem exceptthatbudgets A. B. C. D. Limitunauthorizedexpenditures. Forcemanagementplanning. Promotecommunicationandcoordinationwithintheorganization. Provideperformancecriteria. Answer(A)iscorrect.Budgetsservemanyroles.Theyforcemanagementtoplan ahead,communicateorganizationalgoalsthroughouttheorganization,andprovide criteriaforfutureperformanceevaluations. Answer(B)isincorrect.forcingmanagementplanningisanadvantageofusing budgets. Answer(C)isincorrect.promotingcommunicationandcoordinationwithinthe organizationisanadvantageofusingbudgets. Answer(D)isincorrect.providingperformancecriteriaisanadvantageofusing budgets.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 12

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

[16] Gleim #: 1.1.25 -- Source: CMA 0408 2-006 Allofthefollowingareadvantagesoftop-downbudgetingasopposedtoparticipatory budgeting,exceptthatit A. B. C. D. Increasescoordinationofdivisionalobjectives. Reducesthetimerequiredforbudgeting. Facilitatesimplementationofstrategicplans. Maylimittheacceptanceofproposedgoalsandobjectives. Answer(A)isincorrect.,sinceatop-downbudgetisimposedbyuppermanagement, coordinatingtheobjectivesofseparatedivisionsissimplified. Answer(B)isincorrect.,sinceatop-downbudgetiscoordinatedfromabove,itisless time-consumingthanobtaininglower-levelinput. Answer(C)isincorrect.,sinceatop-downbudgetiscoordinatedfromabove,the implementationofstrategicplansiscentralizedandthussimplified. Answer(D)iscorrect.Sinceatop-downbudgetisimposedbyuppermanagement,it haslesschanceofacceptance(alsocalledbuy-in)bythoseonwhomthebudgetis imposed. [17] Gleim #: 1.3.97 -- Source: CMA 0408 1-144 Amanufacturingcompanyhastheopportunitytosubmitabidfor20unitsofaproducton whichithasalreadyproducedtwo10-unitlots.Theproductionmanagerbelievesthatthe learningexperienceobservedonthefirsttwolotswillcontinueforatleastthenexttwolots. Thedirectlaborrequiredonthefirsttwolotswasasfollows: 5,000directlaborhoursforthefirstlotof10units 3,000additionaldirectlaborhoursforthesecondlotof10units Thelearningrateexperiencedbythecompanyonthefirsttwolotsofthisproductis A. B. C. D. 62.5% 60.0% 80.0% 40.0%

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 13

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

Answer(A)isincorrect.Thispercentageresultsfromimproperlydividingthe5,000hours spentonthefirstlotbythe8,000totalhoursspentonbothlots. Answer(B)isincorrect.Thispercentageresultsfromimproperlydividingthe3,000hours spentonthesecondlotbythe5,000hoursspentonthefirstlot. Answer(C)iscorrect.Learningcurveanalysisisusedtoprojectproductivitygainsresulting fromtheincreasedrateatwhichpeopleperformtasksastheygainexperience.The underlyingassumptionoflearningcurveanalysisisthatworkersgainproductivityata predictablerateastheygainexperiencewithanewprocess.Forthiscompany,atotalof 8,000hourswasspenttocompletetwolotsofproduct.Thecumulativeaveragespenton thetwolotswastherefore4,000hoursperlot(8,0002).Thiscumulativeaverageof4,000 is80%ofthe5,000hoursthatwerespentonthefirstlot.Thelearningcurveistherefore 80%. Answer(D)isincorrect.Thispercentageresultsfromimproperlydividingthe3,000hours spentonthesecondlotbythe5,000hoursspentonthefirstlotandtakingthecomplement. [Fact Pattern #5] Aerosub,Inc.hasdevelopedanewproductforspacecraftthatincludestheproductionofa complexpart.Themanufactureofthispartrequiresahighdegreeoftechnicalskill.Management believesthereisagoodopportunityforitstechnicalforcetolearnandimproveastheybecome accustomedtotheproductionprocess.Theproductionofthefirstunitrequires10,000direct laborhours.Managementprojectsan80%learningcurveandwantstoproduceatotalofeight units. [18] Gleim #: 1.3.94 -- Source: CMA 0408 1-142 (ReferstoFactPattern#5) Uponcompletionoftheeighthunit,Aerosubscumulativeaveragedirectlaborhours requiredperunitoftheproductwillbe A. B. C. D. 5,120hours. 10,000hours. 8,000hours. 6,400hours.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 14

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

Answer(A)iscorrect.Theunderlyingassumptionoflearningcurveanalysisisthatworkers gainproductivityatapredictablerateastheygainexperiencewithanewprocess.A commonassumptionisthatthenumberofhoursrequiredforeachdoublingofoutputwillbe 80%ofthehoursrequiredforthepreviousdoubling.TheeffectsofAerosubsprojected learningcurveonthisproductcanbecalculatedasfollows: Cumulative Units Produced 1 2 4 8 Cumulative Average LaborHours 10,000 8,000(10,00080%) 6,400(8,00080%) 5,120(6,40080%)

Batch 1 2 3 4

Answer(B)isincorrect.Thenumber10,000resultsfromfailingtotakethelearningcurve effectintoaccountatall. Answer(C)isincorrect.Theprojectednumberofhoursaftertwounitsis8,000. Answer(D)isincorrect.Theprojectednumberofhoursafterfourunitsis6,400. [19] Gleim #: 1.5.152 -- Source: CMA 0408 1-183 Whichoneofthefollowingfourprobabilitydistributionsprovidesthehighestexpected monetaryvalue? Alternative#1 Cash Prob Inflows 10% $50,000 20% 75,000 40% 100,000 30% 150,000 Alternative#3 Cash Prob Inflows 10% $50,000 20% 75,000 40% 100,000 30% 125,000 Alternative#2 Cash Prob Inflows 10% $50,000 20% 75,000 45% 100,000 25% 150,000 Alternative#4 Cash Prob Inflows 10% $150,000 20% 100,000 40% 75,000 30% 50,000

A. B. C. D.

Alternative#4. Alternative#1. Alternative#3. Alternative#2.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 15

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

Answer(A)isincorrect.theexpectedvalueofAlternative#4isonly$80,000. Answer(B)iscorrect.Whenmonetaryoutcomesandprobabilitiescanbereasonably estimated,apayofftablecanbeconstructedtodeterminethebestcourseofaction: Alternative#1 Probability Payoffs 10% $50,000 20% 75,000 40% 100,000 30% 150,000 Total Alternative#3 Probability Payoffs 10% $50,000 20% 75,000 40% 100,000 30% 125,000 Total Alternative#2 Expected Value Probability Payoffs $5,000 10% $50,000 15,000 20% 75,000 40,000 45% 100,000 45,000 25% 150,000 $105,000 Total Alternative#4 Expected Value Probability Payoffs $5,000 10% $150,000 75,000 20% 100,000 40,000 40% 75,000 37,500 30% 50,000 $97,500 Total Expected Value $15,000 20,000 30,000 15,000 $80,000 Expected Value $5,000 15,000 45,000 37,500 $102,500

Answer(C)isincorrect.theexpectedvalueofAlternative#3isonly$97,500. Answer(D)isincorrect.theexpectedvalueofAlternative#2isonly$102,500. [20] Gleim #: 1.1.33 -- Source: CMA 0408 2-016 Allofthefollowingaredisadvantagesoftop-downbudgetingasopposedtoparticipatory budgeting,exceptthatit A. B. C. D. Maylimittheacceptanceofproposedgoalsandobjectives. Reducesthetimerequiredforbudgeting. Mayresultinabudgetthatisnotpossibletoachieve. Reducesthecommunicationbetweenemployeesandmanagement. Answer(A)isincorrect.,sinceatop-downbudgetisimposedbyuppermanagement,it haslesschanceofacceptance(alsocalledbuy-in)bythoseonwhomthebudgetis imposed. Answer(B)iscorrect.Sinceatop-downbudgetiscoordinatedfromabove,itisless time-consumingthanobtaininglower-levelinput. Answer(C)isincorrect.abudgetestablishedwithoutlower-levelinputmaycontain unrealisticgoals. Answer(D)isincorrect.reducedcommunicationbetweenemployeesandmanagement isadisadvantageoftop-downbudgeting.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 16

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

[21] Gleim #: 1.5.128 -- Source: CMA 1289 5-23 (ReferstoFactPattern#2) Theconditionalprofitpergameofhaving4,000pretzelsavailableandsellingall4,000 pretzelsis A. B. C. D. $800 $1,200 $2,800 $2,100 Answer(A)isincorrect.Theamountof$800assumes2,000aresold. Answer(B)isincorrect.Thecostof4,000pretzelsis$1,200. Answer(C)iscorrect.Eachpretzelcosts$.30.Thus,thecostof4,000pretzelsis $1,200(4,000$.30).Selling4,000pretzelsat$1eachproducesrevenueof$4,000. Subtractingthe$1,200ofcostsfromthe$4,000ofrevenueresultsinaconditional profitof$2,800. Answer(D)isincorrect.Theamountof$2,100assumes3,000areavailableand3,000 aresold. [22] Gleim #: 1.1.38 -- Source: CMA 0408 2-021 DianaStinson,CherryValley,Inc.sfactorymanager,hadlostherpatience.Sixmonthsago, sheappointedateamfromtheproductionandservicedepartmentstofinalizetheallocation ofcostsandsettingofstandardcosts.Theywerestillfeuding,soshehiredBrennanand Rose,alargeconsultingfirm,toresolvethematter. AllofthefollowingarepotentialconsequencesofhavingthestandardssetbyBrennanand Roseexceptthat A. BrennanandRosemaynotfullyunderstandCherryValleysmanufacturingprocess, resultinginsuboptimalperformance. B. Therecouldbedissatisfactionifthestandardscontaincoststhatarenotcontrollableby theunitheldresponsible. C. Employeescouldreactnegativelysincetheydidnotparticipateinsettingthestandards. D. Thestandardsmayappeartolackmanagementsupport. Answer(A)isincorrect.BrennanandRosemaynotfullyunderstandCherryValleys manufacturingprocess,resultinginsuboptimalperformance. Answer(B)isincorrect.therecouldbedissatisfactionifthestandardscontaincosts thatarenotcontrollablebytheunitheldresponsible. Answer(C)isincorrect.employeescouldreactnegativelysincetheydidnotparticipate insettingthestandards. Answer(D)iscorrect.Standardsconcoctedbyanoutsidefirm,lackingtheintimate knowledgethatemployeeswouldhave,mayappeartolackmanagementsupport.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 17

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

[23] Gleim #: 1.5.132 -- Source: CMA 688 5-20 Thefollowingtablecontainstheprofitoutcomesforeachstateofnatureanddecision combinationforafirm StatesofNature S1 S2 S3 $24 $14 $(6) $20 $10 $5 $(20) $8 $15 0.10 0.50 0.40

Decision1 Decision2 Decision3 Probabilities

Theexpectedvalueofperfectinformationforthisfirminthiscaseis A. B. C. D. $6.40 $9.00 $8.60 $8.40 Answer(A)iscorrect.Thefirststepistodeterminetheexpectedvaluewithoutperfect informationbyformulatingapayoffmatrix.Forexample,theexpectedpayoffforthe combinationofStateofNatureS1andDecision1is$2.40(10%probability$24 outcome).Theentirepayoffmatrixis S1 $2.40 2.00 (2.00) S2 $7.00 5.00 4.00 S3 $(2.40) 2.00 6.00 Total $7.00 9.00 8.00

Decision1 Decision2 Decision3

Thus,thebestdecisionunderconditionsofuncertaintyisDecision2(expectedvalue= $9).Ifthedecisionmakerknewexactlywheneachstateofnaturewouldoccur,the decisionwouldcorrespondtothemaximumprofitopportunityforthatstateofnature. Forinstance,ifS1iscertain,themostprofitabledecisionisDecision1($24).Thus,the expectedpayoffgivenperfectinformationis$15.40. StateofNature 1 2 3 Profit $24 14 15 Probability 10% 50 40 Payoff $2.40 7.00 6.00

Theexpectedvalueofperfectinformationistherefore$6.40($15.40$9.00). Answer(B)isincorrect.Thebestdecisionunderconditionsofuncertaintyis$9.00. Answer(C)isincorrect.Theexpectedvalueofperfectinformationisthedifference betweentheexpectedpayoffwithperfectinformationandtheexpectedpayoffwithout perfectinformation. Answer(D)isincorrect.ThepayoffsfromDecisions1and3equal$8.40($2.40+ $6.00).

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 18

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

[24] Gleim #: 1.6.158 -- Source: CMA 0408 1-187 SusanHineshasdevelopedanestimateoftheearningspershareforherfirmforthenext yearusingthefollowingparameters. Sales Costofgoodssold General&administrativeexpenses Sellingexpense Debtoutstanding Effectivetaxrate Commonsharesoutstanding $20million 70%ofsales $300,000 $100,000plus10%ofsales $5million@8%interestrate 35% 2million

Sheisnowinterestedinthesensitivityofearningspersharetosalesforecastchanges.A10% salesincreasewouldincreaseearningspershareby A. B. C. D. 7.0centspershare. 13.0centspershare. 10.4centspershare. 20.0centspershare.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 19

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

Answer(A)isincorrect.Theamountof7.0centspershareresultsfromassumingan increaseinfixedsellingcosts. Answer(B)iscorrect.Sensitivityanalysisrevealshowsensitiveexpectedvaluecalculations aretotheaccuracyoftheinitialestimates.Sensitivityanalysisisthususefulindetermining whetherexpendingadditionalresourcestoobtainbetterforecastsisjustified. Original Projection $20,000,000 (14,000,000) $6,000,000 (300,000) (2,100,000) $3,600,000 (400,000) $3,200,000 (1,120,000) $2,080,000 $1.04 10% Increase $22,000,000 (15,400,000) $6,600,000 (300,000) (2,300,000) $4,000,000 (400,000) $3,600,000 (1,260,000) $2,340,000 $1.17

Sales Costofgoodssold Grossprofit Sellingexpenses G&Aexpenses Operatingincome Interestexpense Earningsbeforetaxes Incometaxes Netincome Earningspershare

Answer(C)isincorrect.Theamountof10.4centspershareresultsfromincorrectly assuminganincreaseininterestexpense. Answer(D)isincorrect.Theamountof20.0centspershareresultsfromfailingtotakethe variableportionofsellingexpensesintoaccountorfailingtodeducttheextraincometaxes.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 20

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

[Fact Pattern #6] DonehartCorporationproducesagriculturalvehicles.Mostofthecomponentpartsforthese vehiclesaresubcontractedtoreliablevendors.Thefinalassemblyofallvehiclesisaccomplished atDonehartsplant.DonehartsEngineeringDepartmenthasdevelopedanewfuelinjection systemthatcanbeproducedin-housebecauseoftheavailabilityofproductioncapacity.Thefirst productionrunofthenewfuelinjectionsystemhasalreadybeencompletedin-house.This80-unit productionruntook60directlaborhoursperunittoproducebasedonthecumulativeaverage laborhoursperfuelinjectionunit.Doneharthasexperiencedan80%learningcurvewithsimilar products,andthisexperienceindicatesthatlearningtendstoceasebythetime640systemsare produced.Donehartsdirectlaborcost(includingemployeebenefits)is$18perdirectlaborhour. Donehartsmanagementmustdecidewhethertocontinueproducingthefuelinjectionsystemor tosubcontractthework.DonehartspurchasingagenthasreceivedaproposalfromMidland, Inc.,acompanyspecializinginfuelinjectionsystems.Frompastcontracts,Midlandhasprovento beefficientandreliable.ThetermsofMidlandsproposalareoutlinedbelow. - Donehartmustsupplyallmaterialsrequiredforthefuelinjectionsystemunits. - Thefirst80unitsproducedbyMidlandwillrequiredirectlaborinputattherateof56hours perunit.Currentdirectlaborcostis$20perhour. - ThedirectlaborcostchargedtoDonehartwillbethehourlyrateineffectatthetimethework isperformed.Midlandiscurrentlynegotiatingitslaborcontract,whichincludesa4%increase indirectlaborcostandshouldbeapplicablewhenDonehartsignsthecontract. - Alearningcurvefactorof75%willbeappliedthroughthefirst640unitsproduced,andall benefitsderivedfromthelearningfactorwillaccruetoDonehart. - Donehartmustpaytheactuallaborcostincurredplusa5%margin. [25] Gleim #: 1.3.87 -- Source: Publisher (ReferstoFactPattern#6) IfDonehartmanufacturestheunitsin-house,howmanytotalhourswillittaketocomplete 1,000units? A. B. C. D. 24,330hours. 8,294.4hours. 27,955.2hours. 19,660.8hours.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 21

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

Answer(A)isincorrect.Thetimerequiredtocomplete1,000unitsifsubcontractedto Midland,Inc.is24,330hours. Answer(B)isincorrect.Thetimerequiredtocompletetheremaining360unitsafterthe learningcurveis8,294.4hours. Answer(C)iscorrect.Thetotalhoursrequiredtocompleteaprojectwithalearningcurve isfoundbyaddingthetotallaborhoursrequiredtoproducethelastsetofunitsonthe learningcurvewiththeremainingnumberofunitstimesthefinalhoursperincrementalunit. Thefollowingchartshowsthefinalhoursperincrementalunit: Cumulative Average Batch Units LaborHours Cumulative Number Produced perUnit TotalHours 1 80 60 4,800 2 160 48 7,680 3 320 38.4 12,288 4 640 30.72 19,660.8 Hours Numberof Spent Unitsin onBatch Batch 4,800 80 2,880 80 4,608 160 7,372.8 320 HoursSpent onEachUnit inBatch 60 36 28.8 23.04

Afterthefourthbatch,itisassumedthatthelearningcurvewillhavepeaked.Thus,allunits producedthereafterwillrequire23.04hours.Tocomplete1,000units,360mustbe producedafterthefourthbatch.Thisfifthbatchwillrequire8,294.4hours(360units 23.04hoursperunit).Thisnumberaddedtothe19,660.8hoursrequiredtocompletethe 640hoursonthelearningcurveequals27,955.2hours. Answer(D)isincorrect.Thetimerequiredtocompletethe640unitsonthelearningcurve is19,660.8hours.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 22

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

[26] Gleim #: 1.5.150 -- Source: CMA 0408 1-181 ThesalesmanagerofSeritoDollCompanyhassuggestedthatanexpandedadvertising campaigncosting$40,000wouldincreasethesalesandprofitsofthecompany.Hehas developedthefollowingprobabilitydistributionfortheeffectoftheadvertisingcampaignon companysales: Salesincrease (units) 15,000 30,000 45,000 60,000 75,000

Probability .10 .35 .10 .25 .20

Thecompanysellsthedollsat$5.20each.Thecostofeachdollis$3.20.Seritosexpected incrementalprofit,iftheadvertisingcampaignisadopted,is A. B. C. D. $93,000 $6,500 $46,500 $53,000 Answer(A)isincorrect.Theamountof$93,000resultsfromfailingtotakethecostof advertisingintoaccount. Answer(B)isincorrect.Theamountof$6,500resultsfromtreatingtheexpectedunit increasesasexpectedprofitamounts. Answer(C)isincorrect.Theamountof$46,500resultsfromtreatingtheexpectedunit increasesasexpectedprofitamountsandfailingtotakethecostofadvertisinginto account. Answer(D)iscorrect.Whenmonetaryoutcomesandprobabilitiescanbereasonably estimated,apayofftablecanbeconstructedtodeterminethebestcourseofaction [Seritosincrementalprofitoneachdollsoldis$2.00($5.20$3.20)]: Unit Sales Increase 15,000 30,000 45,000 60,000 75,000 Expected Unit Increase 1,500 10,500 4,500 15,000 15,000

Probability 0.10 0.35 0.10 0.25 0.20

= = = = =

Incr. Profit $2 = $2 = $2 = $2 = $2 = Expectedgrossprofit Costofadvertising Expectednetprofit

Expected Profit $3,000 21,000 9,000 30,000 30,000 $93,000 (40,000) $53,000

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 23

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

[27] Gleim #: 1.1.32 -- Source: CMA 0408 2-015 Whichoneofthefollowingitemswouldmostlikelycausetheplanningandbudgetingsystem tofail?Thelackof A. B. C. D. Topmanagementsupport. Inputfromseverallevelsofmanagement. Historicalfinancialdata. Adherencetorigidbudgetsduringtheyear. Answer(A)iscorrect.Topmanagementsbeliefinandsupportoftheplanningand budgetingprocessisthesinglemostimportantelementinitssuccess. Answer(B)isincorrect.inputfromseverallevelsofmanagementishelpful,butnotthe mostessentialelementofsuccessfulbudgeting. Answer(C)isincorrect.thelackofhistoricaldataisnotfataltoanadequateplanning andbudgetingprocess. Answer(D)isincorrect.willingnesstoadapttochangingcircumstancesiscrucialtothe successofanyplanningandbudgetsystem. [28] Gleim #: 1.3.98 -- Source: CMA 0408 1-148 (ReferstoFactPattern#1) IfProperPropellerproduceseightunits,theaveragemanufacturingcostperunitwillbe A. B. C. D. $9,800 $1,647 $14,000 $6,860

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 24

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

Answer(A)isincorrect.Theamountof$9,800isthecumulativeaveragecostafterfour units. Answer(B)isincorrect.Theamountof$1,647isthecumulativeaverageaftereight batches,noteightunits. Answer(C)isincorrect.Theamountof$14,000isthecumulativeaveragecostaftertwo units. Answer(D)iscorrect.Learningcurveanalysisisusedtoprojectproductivitygains resultingfromtheincreasedrateatwhichpeopleperformtasksastheygainexperience.The underlyingassumptionoflearningcurveanalysisisthatworkersgainproductivityata predictablerateastheygainexperiencewithanewprocess.Inthissituation,thecompanyis assumingthatthetotalcostsrequiredforeachdoublingofoutputwillbe70%ofthecosts requiredforthepreviousdoubling.TheeffectsofProperPropellersprojectedlearning curvecanbecalculatedasfollows: Cumulative Units Produced 1 2 4 8 Cumulative Average Cost $20,000 $14,000($20,00070%) $9,800($14,00070%) $6,860($9,80070%)

Batch 1 2 3 4

[29] Gleim #: 1.1.40 -- Source: CMA 0408 2-023 Whichoneofthefollowingwillallowabetteruseofstandardcostsandvarianceanalysisto helpimprovemanagerialdecision-making? A. CompanyBusestheprioryearsaverageactualcostasthecurrentyearsstandard. B. CompanyCinvestigatesonlynegativevariances. C. CompanyAdoesnotdifferentiatebetweenvariableandfixedoverheadincalculatingits overheadvariances. D. CompanyDconstantlyrevisesstandardstoreflectlearningcurves. Answer(A)isincorrect.simplyusingfiguresfromapreviousperiodisan unsatisfactorymeansofestablishingabudget. Answer(B)isincorrect.positivevariancescanbeasignofreducedqualityorother concerns. Answer(C)isincorrect.notdistinguishingvariablefromfixedoverheadwillleadto poordecisionmaking. Answer(D)iscorrect.Learningcurvesareanestablishedphenomenon.Workerslearn anewtaskatapredictablerateandtheresultingimprovementsinproductivityshould befactoredintostandardsettingandvarianceanalysis.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 25

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

[30] Gleim #: 1.3.100 -- Source: CMA 0408 1-151 (ReferstoFactPattern#1) Aftercompletingproductionofthefirstpropeller,theestimatedcostforProperPropellerto fillanorderforsevenadditionalpropellersis A. B. C. D. $98,000 $34,880 $92,000 $54,880 Answer(A)isincorrect.Theamountof$98,000resultsfromignoringtheeffectofthe learningcurve. Answer(B)iscorrect.TheeffectsofProperPropellersprojectedlearningcurvecan becalculatedasfollows: Cumulative Units Produced 1 2 4 8 Cumulative Average Cost $20,000 $14,000($20,00070%) $9,800($14,00070%) $6,860($9,80070%) Cumulative Total Cost $20,000 28,000 39,200 54,880

Batch 1 2 3 4

Sinceeightpropellersrequire$54,880andthefirstoneofftheassemblylinecost $20,000,thecostofunits2through8willbe$34,880($54,880$20,000). Answer(C)isincorrect.Theamountof$92,000resultsfromassumingnolearning curveafterthesecondunit. Answer(D)isincorrect.Theamountof$54,880isthecostofalleightpropellers. [31] Gleim #: 1.1.37 -- Source: CMA 0408 2-020 Whencomparedwithidealstandards,practicalstandards A. B. C. D. Resultinalessdesirablebasisforthedevelopmentofbudgets. Incorporateverygenerousallowanceforspoilageandworkerinefficiencies. Producelowerper-unitproductcosts. Serveasabettermotivatingtargetformanufacturingpersonnel.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 26

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

Answer(A)isincorrect.practicalstandardsaremoreappropriateinmostcasesthanideal standardsinthedevelopmentofbudgets. Answer(B)isincorrect.anacceptanceofhighlevelsofspoilageandworkerinefficiencies cannotbeovercomethroughtheuseofstandards. Answer(C)isincorrect.theeffectofonetypeofstandardoveranothercannotguarantee lowercosts. Answer(D)iscorrect.Practicalstandards,alsocalledattainablestandards,aremorelikely tomeetwithworkeracceptancethanstandardsbasedonanunachievableideal. [32] Gleim #: 1.5.127 -- Source: CMA 1289 5-22 (ReferstoFactPattern#2) Theconditionalprofitpergameofhaving4,000pretzelsavailablebutonlyselling3,000 pretzelsis A. B. C. D. $2,800 $1,800 Someamountotherthanthosegiven. $2,100 Answer(A)isincorrect.Theconditionalprofitgiventhat4,800aresoldis$2,800. Answer(B)iscorrect.Eachpretzelcosts$.30.Thus,thecostof4,000pretzelsis $1,200(4,000$.30).Selling3,000pretzelsat$1eachproducesrevenueof$3,000. Subtractingthe$1,200ofcostsfromthe$3,000ofrevenueresultsinaconditional profitof$1,800. Answer(C)isincorrect.Theamountof$1,800isamongtheresponsesgiven. Answer(D)isincorrect.Theamountof$2,100assumes3,000areavailableand3,000 aresold. [33] Gleim #: 1.3.88 -- Source: Publisher (ReferstoFactPattern#6) IfDonehartmanufacturestheunitsin-house,howmuchadditionalcostwillthecompany incurafterthefirstbatchinordertoproduceatotalof1,000units? A. B. C. D. $559,104 $503,193.60 $463,104 $416,793.60

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 27

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

Answer(A)isincorrect.UsingthedirectlaborcostrelatedtooutsourcingtoMidland resultsin$559,104. Answer(B)isincorrect.Theamountof$503,193.60isfoundbynotsubtractingthecostof theinitial80units. Answer(C)isincorrect.UsingthedirectlaborcostrelatedtooutsourcingtoMidland resultsin$463,104. Answer(D)iscorrect.Thebestmethodtodeterminethetotalout-of-pocketcoststo completeaprojectistofirstmultiplythetotalhoursrequiredbythecostperhour.After this,subtracttheinitialcostsofproducingthefirstbatch.Thiswillresultinthetotalout-ofpocketcoststocompleteaproject. Costfor1,000units (27,955.2hours$18perhour) Costforfirstbatch (80units60hours$18perhour) Costfor920units [34] Gleim #: 1.1.24 -- Source: CMA 0408 2-005 Thefollowingsequenceofstepsisemployedbyacompanytodevelopitsannualprofitplan: Planningguidelinesaredisseminateddownwardbytopmanagementafterreceiving inputfromalllevelsofmanagement. Asalesbudgetispreparedbyindividualsalesunitsreflectingthesalestargetsofthe varioussegments.Thisprovidesthebasisfordepartmentalproductionbudgetsand otherrelatedcomponentsbythevariousoperatingunits.Communicationisprimarily lateralwithsomeupwardcommunicationpossible. Aprofitplanissubmittedtotopmanagementforcoordinationandreview.Top managementsrecommendationsandrevisionsareacteduponbymiddlemanagement. Arevisedprofitplanisresubmittedforfurtherreviewtotopmanagement. Topmanagementgrantsfinalapprovalanddistributestheformalplandownwardtothe variousoperatingunits. Thisoutlineofstepsbestdescribeswhichoneofthefollowingapproachestobudget development? A. B. C. D. Top-downapproach. Totaljustificationofallactivitiesbyoperatingunits. Imposedbudgetingbytopmanagement. Bottom-upapproach. $503,193.60 (86,400.00) $416,793.60

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 28

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

Answer(A)isincorrect.thesestepsdescribetheoppositeofatop-downapproach. Answer(B)isincorrect.topmanagementisnotdemandingjustificationofallactivitiesin thestepsdescribed;suchademandwouldbeconsistentwithasystemknownaszero-based budgeting. Answer(C)isincorrect.topmanagementhasreceivedextensiveinputandcooperationfrom lowerlevelsthroughperformingthesesteps. Answer(D)iscorrect.Abottom-upapproachischaracterizedbygeneralguidancefromthe highestlevelsofmanagement,followedbyextensiveinputfrommiddleandlower management.Thissequenceofstepsaptlydescribesthisprocess. [35] Gleim #: 1.5.123 -- Source: Publisher Underfavorableweatherconditions,themanagementofFlesherFarmsexpectsitsraspberry croptohavea$120,000marketvalue.Anunprotectedcropsubjecttofrosthasanexpected marketvalueof$80,000.IfFlesherprotectstheraspberriesagainstfrost,themarketvalueof thecropisstillexpectedtobe$120,000underfrost-freeconditionsand$180,000ifafrost occurs.WhatmustbetheprobabilityofafrostforFleshertobeindifferenttospending $20,000fortentstoprovidefrostprotection? A. B. C. D. .333 .250 .167 .200

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 29

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

Answer(A)isincorrect.Iftheprobabilityoffrostisgreaterthan.200,anexpectedvalue analysisindicatesthecompanyshouldprovideprotection. Answer(B)isincorrect.Iftheprobabilityoffrostisgreaterthan.200,anexpectedvalue analysisindicatesthecompanyshouldprovideprotection. Answer(C)isincorrect.Iffrosthasaprobabilityof.167,theexpectedvalueofnot providingprotectionexceedsthatofprovidingprotection. Answer(D)iscorrect.Withoutprotection,thecompanywillhavesalesofeither$80,000or $120,000.Withprotection,thecompanywillhavesalesofeither$120,000or$180,000.The $20,000costoftentsmustbesubtractedfromtheseamountstocomputethenet contribution.Thus,thecontributioniftheberriesareprotectedwillbeeither$100,000or $160,000.Theproblemcanbesolvedalgebraicallywiththefollowingformula(X=the probabilityoffrost):

X($80,000)+(1X)($120,000) = X($160,000)+(1X)($100,000) $80,000X+$120,000$120,000X = $160,000X +$100,000$100,000X $120,000$40,000X = $100,000+$60,000X $120,000 = $100,000+$100,000X $20,000 = $100,000X X = .200
Inotherwords,iftheprobabilityoffrostis20%,managementwillbeindifferentbetween providingandnotprovidingprotection.Atafrostexpectancyofgreaterthan20%, managementshouldprovideprotection. [36] Gleim #: 1.4.109 -- Source: Publisher Violationofwhichassumptionunderlyingregressionanalysisisprevalentintimeseries analysis? A. B. C. D. Expectedvalueoferrortermequalszero. Errortermsareindependent. Varianceoferrortermisconstant. Distributionoferrortermsisusuallynormal. Answer(A)isincorrect.Intimeseriesanalysis,theexpectedvalueoftheerrorterm usuallyequalszero. Answer(B)iscorrect.Timeseriesanalysisisaregressionmodelinwhichthe independentvariableistime.Intimeseriesanalysis,thevalueofthenexttimeperiodis frequentlydependentonthevalueofthetimeperiodbeforethat.Hence,theerrorterms areusuallycorrelatedordependentonthepriorperiod;i.e.,theyarecharacterizedby autocorrelation(serialcorrelation). Answer(C)isincorrect.Intimeseriesanalysis,varianceoftheerrortermisusually constant. Answer(D)isincorrect.Intimeseriesanalysis,distributionoftheerrortermsisusually normal.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 30

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

[37] Gleim #: 1.3.90 -- Source: Publisher (ReferstoFactPattern#6) IfDonehartsubcontractstheordertoMidland,howmanyhourswillittaketocompletea unitaftertheinitial640unitsonthelearningcurvearefinished? A. B. C. D. 21.50hours. 11.81hours. 23.625hours. 15.75hours. Answer(A)isincorrect.Thetimeneededtofinishadditionalassumingan80%learning curveis21.50hours. Answer(B)isincorrect.Thetimeneededtofinishadditionalunitsafter1,280units, assumingthelearningcurvedidnotendat640units,is11.81hours. Answer(C)isincorrect.Theaveragelaborhoursperunittofinish640unitsis23.625 hours. Answer(D)iscorrect.Thehoursperunitrequiredtofinishadditionalunitsaftera pointonthelearningcurveisfoundbysubtractingthetotalhoursrequiredtofinishthe previouspointonthelearningcurvefromthecurrentone.Then,thisnumberisdivided bytheincreaseinunitsproduced.InMidlandscase,thecalculationis Hoursneededtoproduce640units Hoursneededtoproducefirsthalf Hoursneededtoproducesecondhalf 15,120 (10,080) 5,040

Thus,eachindividualunitinthesecondgroupof320unitswilltake15.75hoursa piece(5,040320). [38] Gleim #: 1.1.39 -- Source: CMA 0408 2-022 JuraCorporationisdevelopingstandardsforthenextyear.CurrentlyXZ-26,oneofthe materialcomponents,isbeingpurchasedfor$36.45perunit.Itisexpectedthatthe componentscostwillincreasebyapproximately10%nextyearandthepricecouldrange from$38.75to$44.18perunit,dependingonthequantitypurchased.Theappropriate standardforXZ-26fornextyearshouldbesetatthe A. Highestpriceintheanticipatedrangetoensurethatthereareonlyfavorablepurchase pricevariances. B. Priceagreeduponbythepurchasingmanagerandtheappropriatelevelofcompany management. C. Currentactualcostplustheforecasted10%priceincrease. D. Lowestpurchasepriceintheanticipatedrangetokeeppressureonpurchasingto alwaysbuyinthelowestpricerange.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 31

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

Answer(A)isincorrect.standardsshouldbesettightlyenoughtoprovidemotivationto purchasingmanagement. Answer(B)iscorrect.Standardpricesaredesignedforinternalperformancemeasurement. Standardsshouldbeattainable,butnotsoeasilyastonotprovidemotivation.Management shoulddecideitsobjectivesandsetastandardthatwillachievethatobjectivewhenthe standardismet.Forexample,thelowestpricemightnotbeselectedifthecompanyisusing aJITsystem,forwhichtheprimaryobjectiveistheminimizationofinventories. Answer(C)isincorrect.theactualcostcouldbemoreorlessdependinginthequantity purchased. Answer(D)isincorrect.thelowestpricemaynotalwaysbeinthecompany'sbestinterests ifthequantityrequiredtoobtainthelowestpricewouldleadtomuchhighercarryingcosts. [39] Gleim #: 1.3.91 -- Source: Publisher (ReferstoFactPattern#6) IfDonehartsubcontractstheordertoMidland,howmuchadditionalcostwillDonehartincur afterthefirstbatchinordertoobtainatotalof1,000units? A. B. C. D. $426,535.20 $330,220.80 $390,600 $302,400 Answer(A)iscorrect.Thetotalout-of-pocketcostforoutsourcingisfoundbyadding thetotallaborhoursrequiredtofinishtheunitsonthelearningcurvetotheproductof additionalunitsandhoursperadditionalunit.Thisnumberisthenmultipliedbythe directlaborcost.SinceDoneharthasalreadyproducedabatchof80units,only920are neededfromMidland.Thefirst640ofthis920areonthelearningcurveandwill requireatotalof15,120hourstoproduce.Thisleaves280unitsat15.75hoursapiece, foratotalhoursneededof19,530[15,120+(28015.75)].Thedirectlaborrateis $21.84[$20.00(1+.04laborincrease)(1+.05costmargin)].Donehartscostfor the920unitsoutsourcedtoMidlandistherefore$426,535.20(19,530$21.84). Answer(B)isincorrect.Theamountof$330,220.80ignoresthehoursrequiredforthe additionalunits. Answer(C)isincorrect.Theamountof$390,600ignorestheincreasesinthedirect laborrate. Answer(D)isincorrect.Theamountof$302,400ignoresthehoursrequiredforthe additionalunitsanditignorestheincreasesinthedirectlaborrate.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 32

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

[40] Gleim #: 1.5.139 -- Source: CMA 690 5-17 (ReferstoFactPattern#4) TheoptimumnumberofbagsofpeanutsforStanBerrytostockis A. B. C. D. 20 30 40 50 Answer(A)isincorrect.Thefigureof20unitsdoesnothavethegreatestexpected value. Answer(B)isincorrect.Thefigureof30unitsdoesnothavethegreatestexpected value. Answer(C)iscorrect.Expectedvalueanalysisisameansofselectingthebestoption whendecisionsinvolverisk.Theexpectedvalueequalsthesumoftheproductsofthe variouspayoffsandtheirrespectiveprobabilities.StanBerrycancalculatetheexpected valueofeachofhisfourpossibleactionsasfollows: Bags Stocked 20 30 40 50 Expected Value $20.00 27.60 30.40 29.60

.2($20)+.4($20)+.3($20)+.1($20) .2($18)+.4($30)+.3($30)+.1($30) .2($16)+.4($28)+.3($40)+.1($40) .2($14)+.4($26)+.3($38)+.1($50)

= = = =

Theactionwiththehighestexpectedpayoffistostock40bags. Answer(D)isincorrect.Thefigureof50unitsdoesnothavethegreatestexpected value. [41] Gleim #: 1.3.89 -- Source: Publisher (ReferstoFactPattern#6) IfDonehartsubcontractstheordertoMidland,whatisthetotalnumberoflaborhours requiredtoproducethe640unitsonthelearningcurve? A. B. C. D. 19,530hours. 18,350hours. 15,120hours. 35,840hours.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 33

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

Answer(A)isincorrect.Thetotalhoursrequiredtocompletetheprojectis19,530hours. Answer(B)isincorrect.Thefigureof18,350hoursisfoundbyusingan80%learning curve. Answer(C)iscorrect.Learningcurvesreflecttheincreasedrateatwhichpeopleperform tasksastheygainexperience.Forthisexample,thelearningcurvehasthefollowingeffect: Batch Number 1 2 3 4 Cumulative Units Produced 80 160 320 640 AverageLabor HoursperUnit 56 42 31.5 23.625 (5675%) (4275%) (31.575%) Cumulative Hours 4,480 6,720 10,080 15,120

Answer(D)isincorrect.Theamountoftimenecessaryassumingnolearningcurveis 35,840hours. [42] Gleim #: 1.5.142 -- Source: CMA 688 5-25 (ReferstoFactPattern#3) TheprobabilitythatacustomerwillselectmodelP104is A. B. C. D. Somepercentageotherthanthosegiven. 10% 50% 20% Answer(A)isincorrect.Thecorrectpercentageisamongtheresponsesgiven. Answer(B)isincorrect.ThispercentageistheprobabilityofselectingS104. Answer(C)isincorrect.TheprobabilityofselectingX104is50%. Answer(D)iscorrect.Tenrandomnumbershavebeenassigned.Ofthese,two(0and 1)havebeenassignedtomodelP104.Thus,therearetwochancesoutoften,or20%, thatacustomerwillselectthatmodel. [43] Gleim #: 1.5.134 -- Source: CMA 691 4-3 Theexpectedvalueofperfectinformationisthe A. Differencebetweentheexpectedprofitundercertaintyandtheexpectedmonetary valueofthebestactunderuncertainty. B. Differencebetweentheexpectedprofitunderuncertaintyandconditionalprofitforthe bestactundercertainty. C. Sameastheexpectedprofitundercertainty. D. Sumoftheconditionalprofit(loss)forthebesteventofeachacttimestheprobability ofeacheventsoccurring.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 34

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

Answer(A)iscorrect.Theexpectedvalueunderuncertaintyisfoundbymultiplyingthe probabilityofeachoutcome(event)byitspayoff(conditionalprofitorloss)andsumming theproducts.Perfectinformationistheknowledgethatafuturestateofnaturewilloccur withcertainty.Theexpectedvalueofperfectinformationisthedifferencebetweenthe expectedvalueundercertaintyandtheexpectedvalueoftheoptimaldecisionunder uncertainty.Theexpectedvalueundercertaintyequalsthesumoftheproductsoftheprofit maximizingpayoffsofperfectforecastsandtherelatedprobabilities. Answer(B)isincorrect.Itmaynotbethebestactundercertaintythatisconsidered;the valueofperfectinformationisbasedontheeventthatisknownwillhappen,whetherthat eventisthebestortheworst. Answer(C)isincorrect.Thevalueofperfectinformationislimitedtotheexcessofthe profitundercertaintyoverthebestreturnwithoutperfectinformation. Answer(D)isincorrect.Thevalueofperfectinformationislimitedtotheexcessofthe profitundercertaintyoverthebestreturnwithoutperfectinformation. [44] Gleim #: 1.4.110 -- Source: CMA 0408 1-152 Salesofbig-screentelevisionshavegrownsteadilyduringthepastfiveyears.Adealer predictedthatthedemandforFebruarywouldbe148televisions.ActualdemandinFebruary was158televisions.Ifthesmoothingconstantis=0.3,thedemandforecastforMarch, usingtheexponentialsmoothingmodel,willbe A. B. C. D. 148televisions. 151televisions. 155televisions. 158televisions. Answer(A)isincorrect.Exponentialsmoothinginvolvesmorethansimplyusingone monthsforecastastheforecastforthefollowingmonth. Answer(B)iscorrect.Exponentialsmoothingisawidespreadtechniqueformaking projectionsbecauseitrequireslessdatabekeptonhandthanthemovingaverage methods.Mathematically,aforecastisarrivedatwithexponentialsmoothingaccording tothefollowingformula: Forecast = (SmoothingfactorPreviousmonthresult)+ (SmoothingfactorcomplementPreviousmonthforecast) = (0.3158)+(0.7148) = 47.4+103.6 = 151 Answer(C)isincorrect.Thisnumberresultsfromreversingthesmoothingfactorand smoothingfactorcomplement. Answer(D)isincorrect.Exponentialsmoothinginvolvesmorethansimplyusingone monthsactualdemandastheforecastforthefollowingmonth.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 35

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

[45] Gleim #: 1.1.17 -- Source: Publisher Animproperlyexecutedbudgetprocessmighthavetheeffect(s)of A. B. C. D. Alloftheanswersarecorrect. Inflatedbudgetrequests. Disregardofoverallcompanygoals. Meetingshort-termbutnotlong-termgoals. Answer(A)iscorrect.Lackofgoalcongruencecanresultwhenattainingasubunits budgetarygoalresultsindisregardofoverallcompanygoals.Subunitmanagersmay inflatetheirbudgetrequeststoprovideoperatingleewayandthenengagein unnecessaryspendingtoavoidfuturebudgetcuts.Abudgetmayencourageexclusive concentrationonmeetingshort-termstandardsattheexpenseoflong-term considerations.Amanagerfearfulofnotmeetingthebudgettargetsmayimproperly manipulateallocationofexpenses.Themanagerseekingtostaywithinthebudgetmay disregardemployeemoraleandpoorworkingconditions.Interunitresentmentmay developasaresultofcompetitionforscarcefunds. Answer(B)isincorrect.Allofthelistedeffectsmightoccurbecauseofanimproperly executedbudgetprocess. Answer(C)isincorrect.Allofthelistedeffectsmightoccurbecauseofanimproperly executedbudgetprocess. Answer(D)isincorrect.Allofthelistedeffectsmightoccurbecauseofanimproperly executedbudgetprocess. [46] Gleim #: 1.1.20 -- Source: Publisher Ineffectivebudgetcontrolsystemsarecharacterizedby A. B. C. D. Alloftheanswersarecorrect. Lackoftimelyfeedbackintheuseofthebudget. Useofbudgetsasaplanningbutnotacontroltool. Useofbudgetsforharassmentofindividualsratherthanmotivation.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 36

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

Answer(A)iscorrect.Ineffectivebudgetcontrolsystemsarecharacterizedbyeachofthe itemsnoted.Theuseofbudgetsforplanningonlyisaproblemthatmustberesolved throughtheeducationprocess.Managementmustbeeducatedtousethebudgetdocuments forcontrol,notjustplanning.Managementmustlearnthatbudgetscanmotivateandhelp individualsachieveprofessionalgrowthaswellasthegoalsofthefirm.Ignoringbudgets obviouslycontributestotheineffectivenessofthebudgetsystem.Finally,feedbackmustbe timelyorlowermanagementandemployeeswillsoonrecognizethatbudgetfeedbackisso lateitprovidesnoinformation,makingthebudgetaworthlessdevice. Answer(B)isincorrect.Thisisnottheonlyitemlistedthatcharacterizesineffectivebudget controlsystems. Answer(C)isincorrect.Thisisnottheonlyitemlistedthatcharacterizesineffectivebudget controlsystems. Answer(D)isincorrect.Thisisnottheonlyitemlistedthatcharacterizesineffectivebudget controlsystems. [47] Gleim #: 1.5.146 -- Source: CMA 0408 1-177 Accordingtorecentfocussessions,NortonCorporationhasacantmissconsumer productonitshands.Salesforecastsindicateeitherexcellentorgoodresults,withNortons salesmanagerassigningaprobabilityof.6toagoodresultsoutcome.Thecompanyisnow studyingvarioussalescompensationplansfortheproductandhasdeterminedthefollowing contributionmargindata: Contribution Margin Ifsalesareexcellentand Plan1isadopted Plan2isadopted Ifsalesaregoodand Plan1isadopted Plan2isadopted $300,000 370,000 240,000 180,000

Onthebasisofthisinformation,whichofthefollowingstatementsiscorrect? A. Plan1shouldbeadoptedbecauseofthesalesmanagershigherconfidenceingood results. B. EitherPlanshouldbeadopted,thedecisionbeingdependentontheprobabilityof excellentsalesresults. C. Plan2shouldbeadoptedbecauseitis$10,000moreattractivethanPlan1. D. Plan1shouldbeadoptedbecauseitis$8,000moreattractivethanPlan2.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 37

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

Answer(A)isincorrect.thepurposeofexpectedvaluecomputationistotakeallpossible outcomesintoaccount,notjustthemostlikely. Answer(B)isincorrect.theplanmustbeadoptedbeforetheactualoutcomeisknown. Answer(C)isincorrect.theexpectedvalueofPlan2exceedsthatofPlan1by$10,000only aftermerelysummingtheunweightedcontributionmargins. Answer(D)iscorrect.Whenmonetaryoutcomesandprobabilitiescanbereasonably estimated,apayofftablecanbeconstructedtodeterminethebestcourseofaction: Decision Alternative Plan1 Stateof Nature Excellent Good Contribution Margin $300,000 240,000 Expected Value $120,000 144,000 $264,000 $148,000 108,000 $256,000

Probability 0.4 0.6

= =

Plan2

Excellent Good

$370,000 180,000

0.4 0.6

= =

Afterweightingthepossiblemonetaryoutcomesbytheirrespectiveprobabilities,the expectedvalueofPlan1is$8,000higherthantheexpectedvalueofPlan2. [48] Gleim #: 1.3.86 -- Source: Publisher (ReferstoFactPattern#6) IfDonehartmanufacturestheunitsin-house,whatistheaveragelaborhoursperunitafter manufacturing640units? A. B. C. D. 60 23.63 23.04 30.72

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 38

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

Answer(A)isincorrect.Theaveragelaborhoursperunitonthefirstproductionrunis60. Answer(B)isincorrect.TheaveragelaborhoursperunitforMidland,Inc.is23.63. Answer(C)isincorrect.Incrementalhoursperunitafter320unitshavebeenproducedis 23.04. Answer(D)iscorrect.Learningcurvesreflecttheincreasedrateatwhichpeopleperform tasksastheygainexperience.Forthisexample,thelearningcurvehasthefollowingeffect: Batch Number 1 2 3 4 Cumulative Units Produced 80 160 320 640 Average AverageLabor perUnit 60 48 38.4 30.72 (6080%) (4880%) (38.480%)

Therefore,theaveragelaborhoursperunitis30.72hours. [49] Gleim #: 1.1.36 -- Source: CMA 0408 2-019 Oneapproachfordevelopingstandardcostsincorporatescommunication,bargaining,and interactionamongproductlinemanagers;theimmediatesupervisorsforwhomthestandards arebeingdeveloped;andtheaccountantsandengineersbeforethestandardsareacceptedby topmanagement.Thisapproachwouldbestbecharacterizedasa(n) A. B. C. D. Engineeringapproach. Centralizedtop-downapproach. Teamdevelopmentapproach. Imposedapproach. Answer(A)isincorrect.anengineeringapproachinvolvesonlyengineers. Answer(B)isincorrect.acentralizedtop-downapproachinvolvesstandardsbeing dictatedbyuppermanagement. Answer(C)iscorrect.Ateamdevelopmentapproachtostandardsettinginvolves interactionamongvariousgroupsorindividuals,includingproductlinemanagers,the departmentsforwhichthestandardsarebeingdeveloped,accountants,andindustrial engineers. Answer(D)isincorrect.theapproachdescribedistheoppositeofanimposed approach.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 39

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

[Fact Pattern #7] Acompanyisconsideringthreealternativemachinestoproduceanewproduct.Thecost structures(unitvariablecostsplusavoidablefixedcosts)forthethreemachinesareshownas follows.Thesellingpriceisunaffectedbythemachineused. Singlepurposemachine Semiautomaticmachine Automaticmachine $.60x+$20,000 $.40x+$50,000 $.20x+$120,000

Thedemandforunitsofthenewproductisdescribedbythefollowingprobabilitydistribution. Demand 200,000 300,000 400,000 500,000 Probability 0.4 0.3 0.2 0.1

[50] Gleim #: 1.5.137 -- Source: CMA 689 5-26 (ReferstoFactPattern#7) Ignoringthetimevalueofmoney,theexpectedcostofusingthesemiautomaticmachineis A. B. C. D. $210,000 $250,000 $130,000 $170,000 Answer(A)isincorrect.Theamountof$210,000iscalculatedbyusingdemandof 400,000units. Answer(B)isincorrect.Theamountof$250,000iscalculatedbyusingdemandof 500,000units. Answer(C)isincorrect.Theamountof$130,000iscalculatedbyusingdemandof 200,000units. Answer(D)iscorrect.Theexpecteddemandis300,000units[(.4200,000)+(.3 300,000)+(.2400,000)+(.1500,000)].Totalexpectedcostistherefore$170,000 [$50,000fixedcost+($.40300,000)variablecost]. [51] Gleim #: 1.3.95 -- Source: CMA 0408 1-145 (ReferstoFactPattern#5) Uponcompletionoftheeighthunit,Aerosubscumulativedirectlaborhourswillbe A. B. C. D. 64,000hours. 80,000hours. 40,960hours. 29,520hours.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 40

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

Answer(A)isincorrect.Thefigureof64,000resultsfromimproperlymultiplyingthe cumulativenumberofunitsproducedbythe10,000hoursspentonthefirstbatch,then multiplyingbythelearningcurvepercentage. Answer(B)isincorrect.Thefigureof80,000resultsfromimproperlymultiplyingthe cumulativenumberofunitsproducedbythe10,000hoursspentonthefirstbatch. Answer(C)iscorrect.Theunderlyingassumptionoflearningcurveanalysisisthatworkers gainproductivityatapredictablerateastheygainexperiencewithanewprocess.A commonassumptionisthatthenumberofhoursrequiredforeachdoublingofoutputwillbe 80%ofthehoursrequiredforthepreviousdoubling.TheeffectsofAerosubsprojected learningcurveonthisproductcanbecalculatedasfollows: Cumulative Units Produced 1 2 4 8 Cumulative Average LaborHours 10,000 8,000(10,00080%) 6,400(8,00080%) 5,120(6,40080%) Cumulative Total LaborHours 10,000 16,000 25,600 40,960

Batch 1 2 3 4

Answer(D)isincorrect.Thefigureof29,520resultsfromimproperlysummingthe cumulativeaveragelaborhourfigures. [52] Gleim #: 1.1.41 -- Source: CMA 0408 2-024 AfterperformingathoroughstudyofMichiganCompanysoperations,anindependent consultantdeterminedthatthefirmslaborstandardswereprobablytootight.Whichoneof thefollowingfactswouldbeinconsistentwiththeconsultantsconclusion? A. Managementnotedthatminimalincentivebonuseshavebeenpaidinrecentperiods. B. Productionsupervisorsfoundseveralsignificantfluctuationsinmanufacturingvolume, withshort-termincreasesonoutputbeingfollowedbyrapid,sustaineddeclines. C. Michigansbudgetingprocesswaswell-definedandbasedonabottom-upphilosophy. D. Areviewofperformancereportsrevealedthepresenceofmanyunfavorableefficiency variances. Answer(A)isincorrect.thewidespreadfailureforexpectedbonusestobeearned wouldbeanindicatoroftoo-tightstandards. Answer(B)isincorrect.thesituationdescribedisindicativeofrushjobsbeingtoo common,whichisaresultofpoorproductionplanning,nottightlaborstandards. Answer(C)iscorrect.Itishighlyunlikelythatworkersfamiliarwiththeirown processeswouldsettoo-tightstandards. Answer(D)isincorrect.manyunfavorableefficiencyvarianceswouldbeanindicator oftoo-tightstandards.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 41

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

[53] Gleim #: 1.1.23 -- Source: CMA 0408 2-003 Allofthefollowingarecriticismsofthetraditionalbudgetingprocessexceptthatit A. Incorporatesnon-financialmeasuresaswellasfinancialmeasuresintoitsoutput. B. Isnotuseduntiltheendofthebudgetperiodtoevaluateperformance. C. Makesacross-the-boardcutswhenearlybudgetiterationsshowthatplannedexpenses aretoohigh. D. Overemphasizesafixedtimehorizon,suchasoneyear. Answer(A)iscorrect.Traditionalbudgetingfocusesstrictlyonfinancialmeasures. Answer(B)isincorrect.traditionalbudgetingisdifficulttousethroughoutthebudget periodforperformancemeasurement. Answer(C)isincorrect.across-the-boardcutsareaneasilyavailablesolutionwhen traditionalbudgetingisused. Answer(D)isincorrect.traditionalbudgetingisheavilyfocusedonafixedtime horizon. [54] Gleim #: 1.5.135 -- Source: CIA 1188 III-44 Indecisiontheory,thoseuncontrollablefutureeventsthatcanaffecttheoutcomeofa decisionare A. B. C. D. Nodes. Probabilities. Statesofnature. Payoffs. Answer(A)isincorrect.Nodes(junctionpoints)aredecisionpoints. Answer(B)isincorrect.Probabilitiesarethelikelihoodofoccurrenceofthestatesof nature. Answer(C)iscorrect.Applyingdecisiontheoryrequiresthedecisionmakerto developanexhaustivelistofpossiblefutureevents.Allpossiblefutureeventsthat mightoccurmustbeincluded,eventhoughthedecisionmakerwilllikelybevery unsureastowhichspecificeventswilloccur.Thesefutureuncontrollableeventsare referredtoasstatesofnature. Answer(D)isincorrect.Payoffsareoutcomemeasuressuchasprofitorloss.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 42

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

[55] Gleim #: 1.5.148 -- Source: CMA 0408 1-179 ScarfCorporationscontrollerhasdecidedtouseadecisionmodeltocopewithuncertainty. Withaparticularproposal,currentlyunderconsideration,Scarfhastwopossibleactions, investornotinvestinajointventurewithaninternationalfirm.Thecontrollerhas determinedthefollowing. Action: InvestintheJointVenture

EventsandProbabilities: Probabilityofsuccess Costofinvestment Cashflowifinvestmentissuccessful Cashflowifinvestmentisunsuccessful Additionalcoststobepaid Costsincurreduptothispoint

= = = = = =

60% $9.5million $15.0million $2.0million $0 $650,000

Action: DoNotInvestintheJointVenture

Events: Costsincurreduptothispoint Additionalcoststobepaid

= $650,000 = $100,000

Whichoneofthefollowingalternativescorrectlyreflectstherespectiveexpectedvaluesof investingversusnotinvesting? A. B. C. D. $(350,000)and$(100,000). $(350,000)and$(750,000). $300,000and$(100,000). $300,000and$(750,000).

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 43

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

Answer(A)isincorrect.Theamountof$(350,000)resultsfromimproperlytreatingsunk costsasrelevantwhencalculatingtheexpectedvalueofinvesting. Answer(B)isincorrect.Theamountsof$(350,000)and$(750,000)resultfromimproperly treatingsunkcostsasrelevant. Answer(C)iscorrect.Whenmonetaryoutcomesandprobabilitiescanbereasonably estimated,apayofftablecanbeconstructedtodeterminethebestcourseofaction: Decision Alternative Invest Stateof Nature Success Nosuccess Expected Value $9,000,000 800,000 (9,500,000) 0 $300,000 $0 0 0 (100,000) $(100,000)

CashInflow $15,000,000 2,000,000

Probability 0.6 = 0.4 = Costofinvestment Additionalcosts Netexpectedvalue 0.6 = 0.4 = Costofinvestment Additionalcosts Netexpectedvalue

DoNot Invest

Success Nosuccess

$0 0

Answer(D)isincorrect.Theamountof$(750,000)resultsfromimproperlytreatingsunk costsasrelevantwhencalculatingtheexpectedvalueofnotinvesting. [56] Gleim #: 1.1.34 -- Source: CMA 0408 2-017 Suboptimaldecisionmakingisnotlikelytooccurwhen A. Thereislittlecongruenceamongtheoverallorganizationgoals,thesubunitgoals,and theindividualgoalsofdecisionmakers. B. Thesubunitsintheorganizationcompetewitheachotherforthesameinputfactorsor forthesamecustomers. C. Goalsandstandardsofperformancearesetbythetopmanagement. D. Guidanceisgiventosubunitmanagersabouthowstandardsandgoalsaffectthem. Answer(A)isincorrect.lowcongruenceamongtheoverallorganizationgoals,the subunitgoals,andtheindividualgoalsofdecisionmakersincreasesthechancesof suboptimaldecisionmaking. Answer(B)isincorrect.,whenthesubunitsintheorganizationcompetewitheach otherforthesameinputfactorsorforthesamecustomers,thechancesofsuboptimal decisionmakingareincreased. Answer(C)isincorrect.,whengoalsandstandardsaredictatedbythetop management,thechancesofsuboptimaldecisionmakingareincreased. Answer(D)iscorrect.Suboptimaldecisionmakingisnotlikelytooccurwhen guidanceisgiventosubunitmanagersabouthowstandardsandgoalsaffectthem.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 44

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

[57] Gleim #: 1.1.26 -- Source: CMA 0408 2-007 Indevelopingthebudgetforthenextyear,whichoneofthefollowingapproacheswould producethegreatestamountofpositivemotivationandgoalcongruence? A. Havethedivisionalandseniormanagementjointlydevelopgoalsandobjectiveswhile constructingthecorporationsoverallplanofoperation. B. Permitthedivisionalmanagertodevelopthegoalforthedivisionthatinthemanagers viewwillgeneratethegreatestamountofprofits. C. Havethedivisionalandseniormanagementjointlydevelopgoalsandthedivisional managerdeveloptheimplementationplan. D. Haveseniormanagementdeveloptheoverallgoalsandpermitthedivisionalmanager todeterminehowthesegoalswillbemet. Answer(A)isincorrect.seniormanagementmaynotbeinapositiontodevelopan implementationplan. Answer(B)isincorrect.usingdivisionmanagerstodeveloptheirgoalsdoesnothing forgoalcongruence. Answer(C)iscorrect.Jointdevelopmentofgoalsismoreconducivetomotivation,as isallowingdivisionalmanagerstodeveloptheimplementationplan.Goalcongruenceis enhancedwhenseniormanagementisinvolvedinthebudgetingprocessalongwith divisionmanagers. Answer(D)isincorrect.havingseniormanagementsetgoalswouldnotbeas conducivetomotivationaswouldhavinginputfromdivisions. [58] Gleim #: 1.2.68 -- Source: CMA 0408 1-140 TheresultsofregressingYagainstXareasfollows: Coefficient 5.23 1.54

Intercept Slope

WhenthevalueofXis10,theestimatedvalueofYis A. B. C. D. 53.84 6.78 8.05 20.63

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 45

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

Answer(A)isincorrect.Thefigure53.84resultsfromtransposingtheinterceptandslope. Answer(B)isincorrect.Thefigure6.78resultsfromsimplyaddingtheinterceptandslope. Answer(C)isincorrect.Thefigure8.05resultsfromsimplymultiplyingtheinterceptand slope. Answer(D)iscorrect.Asimpleregressioncanbecalculatedusingtheformulafora straightline: y=a+bx Where:y a b x = = = = thedependentvariable theY-axisintercept theslopeoftheregressionline theindependentvariable

Solvingwiththeinformationgivenyieldsthefollowingresults: y= = = = a+bx 5.23+(1.5410) 5.23+15.4 20.63

[59] Gleim #: 1.5.138 -- Source: CMA 689 5-27 (ReferstoFactPattern#7) Usingtheexpectedvaluecriterion, A. B. C. D. Theautomaticmachineshouldbeusedbecauseofthehighexpecteddemand. Thesemiautomaticmachineshouldbeusedbecauseithasthelowestexpectedcost. Thesinglepurposemachineshouldbeusedbecauseofthelowexpecteddemand. Theautomaticmachinehasthelowestexpectedcost. Answer(A)isincorrect.Theautomaticmachineisnotthebestchoicebasedonthe expecteddemandlevel. Answer(B)iscorrect.Thesemiautomaticmachinehasanexpectedcostof$170,000 basedonanexpecteddemandof300,000units[(.4200,000)+(.3300,000)+(.2 400,000)+(.1500,000)].Thesinglepurposemachinehasanexpectedcostof $200,000[($.60300,000)+$20,000].Theautomaticmachinehasanexpectedcost of$180,000[($.20300,000)+$120,000)].Hence,thesemiautomaticmachinehas thelowestexpectedcostattheexpectedlevelofdemand. Answer(C)isincorrect.Thesinglepurposemachineisnotthebestchoicebasedonthe expecteddemandlevel. Answer(D)isincorrect.Theautomaticmachinehasthesecondlowestexpectedcost.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 46

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

[60] Gleim #: 1.6.160 -- Source: CMA 0408 1-143 Amanufacturingfirmplanstobidonaspecialorderof80unitsthatwillbemanufacturedin lotsof10unitseach.Theproductionmanagerestimatesthatthedirectlaborhoursperunit willdeclinebyaconstantpercentageeachtimethecumulativequantityofunitsproduced doubles.Thequantitativetechniqueusedtocapturethisphenomenonandestimatethedirect laborhoursrequiredforthespecialorderis A. B. C. D. Linearprogramminganalysis. TheMarkovprocess. Cost-profit-volumeanalysis. Learningcurveanalysis. Answer(A)isincorrect.linearprogrammingisamathematicaltechniqueusedto optimizealinearfunctionsubjecttocertainconstraints. Answer(B)isincorrect.theMarkovprocessisusedindecisionproblemsinwhichthe probabilityoftheoccurrenceofafuturestatedependsonlyonthecurrentstate. Answer(C)isincorrect.cost-volume-profitanalysisisatoolforunderstandingthe interactionofrevenueswithfixedandvariablecosts. Answer(D)iscorrect.Learningcurveanalysisisusedtoprojectproductivitygains resultingfromtheincreasedrateatwhichpeopleperformtasksastheygainexperience. [61] Gleim #: 1.1.35 -- Source: CMA 0408 2-018 Allofthefollowingstatementsconcerningstandardcostsarecorrectexceptthat A. Timeandmotionstudiesareoftenusedtodeterminestandardcosts. B. Standardcostsareusuallysetforoneyear. C. Standardcostsareusuallystatedintotal,whilebudgetedcostsareusuallystatedona per-unitbasis. D. Standardcostscanbeusedincostinginventoryaccounts. Answer(A)isincorrect.timeandmotionstudiesareoftenusedtodeterminestandard costs. Answer(B)isincorrect.standardcostsareusuallysetforoneyear. Answer(C)iscorrect.Standardcostscanbeusedattheper-unitlevelandanylevelof aggregationabove. Answer(D)isincorrect.standardcostscanbeusedincostinginventoryaccounts.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 47

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

[62] Gleim #: 1.1.31 -- Source: CMA 0408 2-013 Budgetingproblemswheredepartmentalmanagersarerepeatedlyachievingeasygoalsor failingtoachievedemandinggoalscanbebestminimizedbyestablishing A. Preventivecontrols. B. Bettercommunicationwherebymanagersdiscussbudgetmattersdailywiththeir superiors. C. Apolicythatallowsmanagerstobuildslackintothebudget. D. Participativebudgetingwheremanagerspursueobjectivesconsistentwiththosesetby topmanagement. Answer(A)isincorrect.preventivecontrolsismuchtoovagueaterminthis circumstance. Answer(B)isincorrect.simplydiscussingbudgetmattersmoreoftendoesnotinject disciplineintotheprocess. Answer(C)isincorrect.apolicyallowingbudgetaryslackwouldmaketheproblem worse. Answer(D)iscorrect.Participativebudgetingisapracticalmeansofsettingrealistic, achievablebudgetgoals. [63] Gleim #: 1.5.147 -- Source: CMA 0408 1-178 Denton,Inc.manufacturesindustrialmachineryandrequires100,000switchesperyearinits assemblyprocess.Whenswitchesarereceivedfromavendortheyareinstalledinthespecific machineandtested.Iftheswitchesfail,theyarescrappedandtheassociatedlaborcostof $25isconsideredlostproductivity.Dentonpurchasesofftheshelfswitchesasopposedto custom-madeswitchesandexperiencesqualityproblemswithsomevendorsproducts.A decisionmustbemadeastowhichvendortobuyfromduringthenextyearbasedonthe followinginformation. Percentageexpected topassthetest 90% 94% 97% 99%

Vendor P Q R S

Priceperswitch $35 37 39 40

WhichvendorshouldDentonscontrollerrecommendtomanagement? A. B. C. D. VendorR. VendorQ. VendorP. VendorS.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 48

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

Answer(A)isincorrect.thetotalcostofusingVendorRisgreaterthanthatofVendorP. Answer(B)isincorrect.thetotalcostofusingVendorQisgreaterthanthatofVendorP. Answer(C)iscorrect.Thetotalcostofbuyingfromeachvendorcanbecalculatedas follows: Annual Total Unit Quantity Purchase % Vendor Price Purchased Price Unusable P $35 100,000 $3,500,000 10% Q 37 100,000 3,700,000 6% R 39 100,000 3,900,000 3% S 40 100,000 4,000,000 1%

Quantity Costof Unusable Scrapping TotalCost 10,000 $250,000 $3,750,000 6,000 150,000 3,850,000 3,000 75,000 3,975,000 1,000 25,000 4,025,000

Answer(D)isincorrect.thetotalcostofusingVendorSisgreaterthanthatofVendorP. [64] Gleim #: 1.2.66 -- Source: CMA 0408 1-138 SlawfordManufacturingdevelopedthefollowingmultipleregressionequation,utilizing manyyearsofdata,andusesittomodel,orestimate,thecostofitsproduct. Cost=FC+(aL)+(bM)

Where:FC = fixedcosts L = laborrateperhour M = materialcostperpound

Whichoneofthefollowingchangeswouldhavethegreatestimpactoninvalidatingthe resultsofthismodel? A. Renegotiationoftheunioncontractcallingformuchhigherwagerates. B. Asignificantchangeinlaborproductivity. C. Alargedropinmaterialcosts,asaresultofpurchasingthematerialfromaforeign source. D. Asignificantreductioninfactoryoverheads,whichareacomponentoffixedcosts.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 49

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

Answer(A)isincorrect.thewagerateisoneofthevariables,andadifferencebetween expectedandactualvalueforthevariablesisanintegralpartofmultipleregression. Answer(B)iscorrect.Inmultipleregression,alargedifferencebetweentheexpectedvalue andtheactualvalueofoneofthecoefficientshasthemostimpactinrenderingthemodel invalid.Achangeincostswouldbeincorporatedintotheequationautomatically,buta changeinproductivityperhourwouldnot. Answer(C)isincorrect.materialscostisoneofthevariables,andadifferencebetween expectedandactualvalueforthevariablesisanintegralpartofmultipleregression. Answer(D)isincorrect.fixedcostisoneofthevariables,andadifferencebetween expectedandactualvalueforthevariablesisanintegralpartofmultipleregression. [65] Gleim #: 1.5.149 -- Source: CMA 0408 1-180 AllbeeCompanyhasthreepossibleinvestmentopportunities.Thecontrollercalculatedthe payoffsandprobabilitiesasfollows: Probabilities InvestmentB .2 .2 .2 .2 .2

Payoffs InvestmentA $(20,000) .3 (10,000) .1 30,000 .3 70,000 .2 100,000 .1

InvestmentC .3 .1 .2 .3 .1

ThecostofinvestmentsA,B,andCarethesame.Usingtheexpected-valuecriterion,which oneofthefollowingrankingsoftheseinvestments,fromhighestpayofftolowestpayoff,is correct? A. B. C. D. B,A,C. A,B,C. C,A,B. B,C,A.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 50

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

Answer(A)isincorrect.InvestmentChasahigherexpectedvaluethanInvestmentA. Answer(B)isincorrect.InvestmentBhasahigherexpectedvaluethanInvestmentA. Answer(C)isincorrect.InvestmentBhasahigherexpectedvaluethanbothInvestmentC andInvestmentA. Answer(D)iscorrect.Whenmonetaryoutcomesandprobabilitiescanbereasonably estimated,apayofftablecanbeconstructedtodeterminethebestcourseofaction: InvestmentA Payoffs Probability $(20,000) 0.3 (10,000) 0.1 30,000 0.3 70,000 0.2 100,000 0.1 Total InvestmentC Payoffs Probability $(20,000) 0.3 (10,000) 0.1 30,000 0.2 70,000 0.3 100,000 0.1 Total Expected Value $(6,000) (1,000) 6,000 21,000 27,000 $47,000 Expected Value $(6,000) (1,000) 9,000 14,000 23,000 $39,000 InvestmentB Payoffs Probability $(20,000) 0.2 (10,000) 0.2 30,000 0.2 70,000 0.2 100,000 0.2 Total Expected Value $(4,000) (2,000) 6,000 14,000 20,000 $34,000

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 51

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

[66] Gleim #: 1.5.151 -- Source: CMA 0408 1-182 StockXhasthefollowingprobabilitydistributionofexpectedfuturereturns: Expected Return 20% 5% 15% 20% 30%

Probability .1 .2 .4 .2 .1

TheexpectedrateofreturnonStockXis A. B. C. D. 16% 10% 12% 19% Answer(A)isincorrect.Thispercentageresultsfromfailingtotreatthe20%return figureasareduction. Answer(B)isincorrect.Thispercentageresultsfromimproperlysummingthe expectedratesofreturnanddividingbythenumberofoccurrences. Answer(C)iscorrect.Expectedvaluecomputationcanbeappliedtoratesofreturnas wellastodollaramounts. Weighted Expected Return 2% 1% 6% 4% 3% 12%

Probability 0.1 0.2 0.4 0.2 0.1

Expected Return 20% 5% 15% 20% 30%

Answer(D)isincorrect.Thispercentageresultsfromoverstatingthereturnsatthe higherexpectedreturns.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 52

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

[67] Gleim #: 1.3.101 -- Source: CMA 0408 1-147 MartinFabricatingusesacumulativeaverage-timelearningcurvemodeltomonitorlabor costs.Dataregardingtworecentlycompletedbatchesofapartthatisusedintractor-trailer rigsisasfollows: Batch Number 1 2 Number ofUnits 50 50 CumulativeAverage HoursPerUnit 20 16

Ifthesamerateoflearningcontinuesforthenextseveralbatchesproduced,whichofthe followingbestdescribes(1)thetype(i.e.,degree)oflearningcurvethatthefirmis experiencingand(2)theaveragehoursperunitforunitsincludedinthe201-400rangeof unitsproduced(i.e.,thelast200units)? Type(Degree)of LearningCurve A. B. C. D. 80% 20% 20% 80% AverageHoursPer UnitforUnits201-400 10.24 3.84 10.24 7.68

Answer(A)isincorrect.Thenumber10.24isthecumulativeaveragenumberofhours afterthe4thbatch,nottheaveragespentontheunitsinthebatch. Answer(B)isincorrect.Twentypercentisthecomplementofthelearningcurve,and improperlyhalvingthetimespentontheunitsinthe4thbatch. Answer(C)isincorrect.Twentypercentisthecomplementofthelearningcurve,and 10.24isthecumulativeaveragenumberofhoursforallunitsafterthe4thbatch,not thetimespentontheunitsinthe4thbatch. Answer(D)iscorrect.Thelearningcurvepercentageisdeterminedbynotingthe hoursusedinproducingthefirstdoublingofoutputasapercentageofthehoursused intheoriginalbatch.Since16is80%of20,Martinisexperiencingan80%learning curve.Theaveragehoursusedtoproducethe4thbatchofoutput(units201400)can becalculatedasfollows: Units Cumulative Cumulative in Units Average Batch Batch Produced LaborHours 1 50 50 20 2 50 100 16 3 100 200 12.8 4 200 400 10.24 Cumulative Total Time 1,000 1,600 2,560 4,096 TimeSpent on Batch 1,000 600 960 1,536 TimeSpent onUnits inBatch 20 12 9.6 7.68

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 53

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

[68] Gleim #: 1.5.144 -- Source: CMA 683 5-8 Acompanyissimulatingtheactionsofagovernmentagencyinwhich50%ofthetimea recallofaproductisrequired,40%ofthetimeonlynotificationofthebuyerabouta potentialdefectisrequired,and10%ofthetimenoactiononitspartisrequired.Random numbersof1to100arebeingused.Anappropriateassignmentofrandomnumbersforthe recallcategorywouldbe A. B. C. D. 11-60 40-90 1-40 61-100 Answer(A)iscorrect.Givena50%chanceofarecall,50differentnumbersshouldbe assignedtothatalternative.Theanswer(11-60)istheonlyalternativewith50 numbers. Answer(B)isincorrect.Theassignmentof40-90includes51numbers. Answer(C)isincorrect.Theassignmentof1-40isanappropriateassignmentof randomnumbersforthenotificationcategory. Answer(D)isincorrect.Theassignmentof61-100isanappropriateassignmentof randomnumbersforthenotificationcategory. [69] Gleim #: 1.1.29 -- Source: CMA 0408 2-011 RockIndustrieshasfourdivisions.Inthequesttodevelopamoreachievablebudgetforthe comingyear,thechiefexecutiveofficerhaselectedtodevelopthecompanysbudgetby usingadecentralizedbottom-upbudgetapproach.ChipJonesisproductionmanagerinone ofthedivisions.Jonesinvolvementinthebudgetprocessthisyearwillprobably A. Benegligible. B. Requiredevelopmentofaproductionbudgetafterreceivingthedivisionsprojected salesforecast. C. Requiredevelopmentofaproductionbudgetbasedontheprioryearsmanufacturing activity. D. RequiredevelopmentofaproductionbudgetthatisforwardedtotheBudget Department. Answer(A)isincorrect.theproductionmanagermustbeinvolvedinthebudget process. Answer(B)iscorrect.Managementofthedivisionisresponsibleforsettingthesales forecast.Asproductionmanager,Joneshastheresponsibilityofensuringtheproducts arereadyonscheduleandintherightquantities. Answer(C)isincorrect.currentyearprojectionsarerelevanttoabudget,notprior yearactivity. Answer(D)isincorrect.aproductionmanagercannotdevelopabudgetforproduction until(s)hehasbeentoldwhatthesalesforecastis.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 54

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

[70] Gleim #: 1.1.21 -- Source: Publisher Whichofthefollowingstatementsregardingbudgetsisfalse? A. B. C. D. Abudgetisaplanthatcontainsaquantitativestatementofexpectedresults. Budgetsmaybedevelopedforcashflowsorlaborusage. Budgetsareusedonlyasaplanningfunction. Budgetspresentorganizationalplansinaformal,logical,andintegratedmanner. Answer(A)isincorrect.Itisatruestatementregardingbudgeting. Answer(B)isincorrect.Itisatruestatementregardingbudgeting. Answer(C)iscorrect.Budgetformulationisaplanningfunction;however,budgets arealsousefulcontroldevices.Budgetsprovideabasisforcontrolofperformance throughcomparisonsofactualwithbudgeteddata.Theypermitanalysisofvariations fromplansandsignaltheneedforcorrectivemanagerialaction. Answer(D)isincorrect.Itisatruestatementregardingbudgeting. [Fact Pattern #8] TheBoosterClubatBlairCollegesellshotdogsathomebasketballgames.Thegrouphasa frequencydistributionofthedemandforhotdogspergameandplanstoapplytheexpectedvalue decisionruletodeterminethenumberofhotdogstostock. [71] Gleim #: 1.5.136 -- Source: CMA 691 4-2 (ReferstoFactPattern#8) TheBoosterClubshouldselectthedemandlevelthat A. B. C. D. Isclosesttotheexpecteddemand. Hasthegreatestprobabilityofoccurring. Hasthegreatestexpectedmonetaryvalue. Hasthegreatestexpectedopportunitycost. Answer(A)isincorrect.Stockinganamountequaltoexpecteddemand(thesumofthe productsofthepossibleamountsdemandedandtheirrespectiveprobabilities)doesnot necessarilymaximizeexpectedprofits. Answer(B)isincorrect.Thenumberofbagstostockisnotnecessarilythesameasthe amountdemandedwiththehighestprobability.Theinventorydecisionshouldbebased ontherelationoftheprobabilitydistributiontothemonetaryoutcomes. Answer(C)iscorrect.TheBoosterClubshouldselectthedemandlevelthat maximizesprofits,thatis,thelevelwiththegreatestexpectedmonetaryvalue.This levelmaynotincludetheeventwiththehighestconditionalprofitbecausethisprofit maybeaccompaniedbyalowprobabilityofoccurrence.Alternatively,theeventwith thehighestprobabilityofoccurrencemaynotbeselectedbecauseitdoesnotoffera highconditionalprofit. Answer(D)isincorrect.Thegreatestopportunitycostisnotfactoredintotheexpected valueanalysis.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 55

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

[72] Gleim #: 1.3.102 -- Source: CMA 0408 1-150 Amanufacturingcompanyrequired800directlaborhourstoproducethefirstlotoffour unitsofanewmotor.Managementbelievesthata90%learningcurvewillbeexperienced overfourlotsofproduction.Howmanydirectlaborhourswillberequiredtomanufacture thenext12units? A. B. C. D. 2,016 1,792 1,944 2,160 Answer(A)isincorrect.a90%learningcurveproducesanincrementalproductiontime of1,792. Answer(B)iscorrect.Witha90%learningcurve,thecumulativeproductiontimes wouldbeasfollows: Cumulative Time 800 1,440 2,592

Batch 1 2 4

AverageTime 800 720(80090%) 648(72090%)

Subtractingthe800hoursspentonthefirstbatchfromthecumulativetimeforfour batchesleaves1,792hoursforthelastthreebatches(12units). Answer(C)isincorrect.a90%learningcurveproducesanincrementalproductiontime of1,792. Answer(D)isincorrect.a90%learningcurveproducesanincrementalproductiontime of1,792.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 56

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

[73] Gleim #: 1.5.141 -- Source: CMA 0205 CarsonProductssellsweatshirtsandispreparingforaWorldCupSoccermatch.Thecost persweatshirtvarieswiththequantitypurchasedasfollows. Quantity 4,000 5,000 6,000 7,000 Unitcost $14.00 13.50 13.00 12.50

Carsonmustpurchasethesweatshirtsonemonthbeforethegameandhasanalyzedthe marketandestimatedsaleslevelsasfollows. Unitsales Probability 4,000 15% 5,000 20% 6,000 35% 7,000 30%

Theestimatedsellingpriceis$25forsalesmadebeforeandduringgameday.Any sweatshirtsremainingaftergamedaycanbesoldatwholesaletoalocaldiscountstorefor $10. TheexpectedprofitifCarsonpurchased6,000shirtsis A. B. C. D. $64,500 $72,000 $66,000 $69,000

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 57

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

Answer(A)iscorrect.Anexpectedvalueforeachlevelofdemandisderivedbyweighting theprofitforthatlevelbytheprobabilityofitsoccurrence.Thecostofgoodsisthesamein everycasebecause6,000sweatshirtsarebeingpurchasedwithoutcertainknowledgeof whatdemandwillbe.Also,thegamedayrevenueforthe7,000demandlevelisthesameas for6,000sinceCarsononlyhas6,000sweatshirtsavailableforsale. DemandLevel 5,000 6,000 $125,000 $150,000 (78,000) (78,000)

Gamedayrevenue@$25ea. Costofgoods(6,000@$13 ea.) Remainder (2,000@$10 revenue ea.) (1,000@$10 ea.) (0@$10ea.) Totalprofit Probability Expectedvalue

4,000 $100,000 (78,000) 20,000

7,000 Total $150,000 (78,000)

10,000 0 $72,000 35% $25,200 0 $72,000 30% $21,600 $64,500

$42,000 15% $6,300

$57,000 20% $11,400

Answer(B)isincorrect.Improperlyusing7,000unitsalesatthe7,000demandlevel(only 6,000shirtsareavailableforsale)resultsin$72,000. Answer(C)isincorrect.Improperlyusingaunitcostof$14.00forallunitsandfailingto weightthetotalprofitsresultsin$66,000. Answer(D)isincorrect.Improperlyusingaunitcostof$13.50forallunitsandfailingto weightthetotalprofitsresultsin$69,000.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 58

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

[74] Gleim #: 1.3.92 -- Source: CIA 1193 III-69 Managementofabookkeepingcompanyobservedthattheaveragetimespenttoperform identicaltasksusinganewsoftwarepackagedecreasesasthenumberoftasksperformed increases.Thefollowinginformationontheuseofthenewsoftwarewascollected. Numberof Tasks Performed 1 2 4 TotalTimeto PerformAll Tasks 10minutes 18minutes 32.4minutes AverageTime toPerform EachTask 10minutes 9minutes 8.1minutes

Ifthislearningeffectcontinues,whatistheaveragetimetoperformeachofthefirsteight tasks? A. B. C. D. 6.56minutes. 5.90minutes. 8.1minutes. 7.29minutes. Answer(A)isincorrect.Thecumulativeaveragetimefor16tasksis6.56minutes. Answer(B)isincorrect.Thecumulativeaveragetimefor32tasksis5.90minutes. Answer(C)isincorrect.Thecumulativetimeforfourtasksis8.1minutes. Answer(D)iscorrect.Learningcurvesreflecttheincreasedrateatwhichpeople performtasksastheygainexperience.Thetimerequiredtoperformagiventask becomesprogressivelyshorter.Thistechniqueisapplicableonlytotheearlystagesof productionortoanynewtask.Onecommonassumptionisthatthecumulativeaverage timeperunitisreducedbyafixedpercentageeachtimecumulativeproductionis doubled.Basedonthegivendata,thiscompanyhasa90%learningcurve(90%10 minutes=9minutes,and90%9minutes=8.1minutes).Accordingly,thecumulative averagetimetoperformeighttasksis7.29minutes(90%8.1minutes). [75] Gleim #: 1.3.96 -- Source: CMA 0408 1-149 (ReferstoFactPattern#5) Aftercompletingthefirstunit,theestimatedtotaldirectlaborhoursAerosubwillrequireto producethesevenadditionalunitswillbe A. B. C. D. 30,960hours. 40,960hours. 70,000hours. 56,000hours.

Copyright 2010 Gleim Publications Inc. Printed for mohamed mahmoud

Page 59

Gleim CMA Test Prep: Part 1: Financial Planning, Performance, and Control
(75 que stions)

Answer(A)iscorrect.Thecumulativetotalhoursspentontheunitscanbecalculatedas follows: Cumulative Units Produced 1 2 4 8 Cumulative Average LaborHours 10,000 8,000(10,00080%) 6,400(8,00080%) 5,120(6,40080%) Cumulative Total LaborHours 10,000 16,000 25,600 40,960

Batch 1 2 3 4

Sinceittookatotalof40,960hourstocompletealleightunitsand10,000tocompletethe firstone,units2through8took30,960hours(40,96010,000). Answer(B)isincorrect.Thefigure40,960isthenumberofhourstocompletealleight units. Answer(C)isincorrect.Thefigure70,000resultsfromimproperlymultiplyingtheseven unitsbythe10,000averagelaborhoursconsumedinproducingthefirstunit. Answer(D)isincorrect.Thefigure56,000resultsfromimproperlymultiplyingtheseven unitsbythe8,000averagelaborhoursconsumedinproducingthesecondbatch.