HUAWEI GSM SSV GUIDE BOOK REGION: EAST JAVA PROJECT: HCPT ROLLOUT PREPARED BY: FACHRURRASYID DOCUMENT VERSION: 1.0 RELEASED DATE: 26 AUGUST 2013
Version V1.0
Author Fachrurrasyid
Remark
Table of Content 1. 2. 3. 4. 5. 6. 7. Overview .. 3 Work Flow 3 Team Requirements . 5 Test Methodology and sequence . 6 Equipment List and configuration 7 Test Item for output KPI .. 8 SSV Report . 9 7.1. Basic Information ... 9 7.2. OSS Part . 9 7.3. DT Part .. 10 7.3.1. 7.3.2. 7.3.3. Mobile Test (for Plot) . 12 Mobile Test (For Function) . 13 Stationary Test .. 13
7.4. Remarks/Justification Examples . 15 7.5. From others (Simulation) . 18 8. 9. Attention Items . 18 Reference .. 18
Commercial in confidence
Page 2 of 19
1. Overview
Single Site Verification (SSV) Test is a test performed on newly integrated sites, it is done by performing Drive test (Moving) and also stationery test around one particular target site. The purpose of this test is to ensure all the basic functions of the site cell are normal. Below are the items needed to verify with SSV: - Coverage (CI, RX Level & RX Quality) - BCCH frequency (No Interference) - No installation faults (No Crossfeeder, wrong antenna direction etc.) - Make service test calls (Functionality test of CS and PS access)
2. Work Flow
Below is the flowchart of whole SSV Process for HCPT-RO-EJ:
A. Preparation
Commercial in confidence
Page 3 of 19
C. Perform SSV
SSV Flowchart.docx
Commercial in confidence
Page 4 of 19
3. Team Requirements
Sr.RNO/TL
.
Jr.RNO/DT Coordinator
OSS Engineer
DT Engineer
DT Analyst
DT Engineer
1) Senior RNO (Team Leader) - Responsible of Team Lead and Progress of Project as a whole - Responsible of L0 KPI monitoring & optimization after SSV Pass 2) Junior RNO (DT Coordinator) - Check & Analyze Sites before team go SSV (Neighbor relation & Initial Parameter) - Make optimization as needed based on pre-SSV Analyze result - Coordinate team for SSV (Make schedule, SSV monitoring and update progress) - Review SSV Reports compiled by DT analyst and send to Huawei - Make Justification and schedule Re SSV for reject SSV Reports - Reports for sites problem or need troubleshoot for SSV (Crossfeeder, site down, etc.) 3) OSS Engineer - Provide daily data KPI Performance for all sites - Provide Alarm and monitoring data for all sites - Execute PCR optimization requested by RNO - Provide other data as requested by Huawei and/or RNO whenever needed 4) DT Analyst - Compile SSV Reports - Make Coverage plot prediction and Route and send to team before SSV - Make justification as needed for SSV Reports 5) DT Engineer - Perform Drive Test for Site SSV - Close coordinate with DT Coordinator - Report directly to Coordinator if found sites problem during SSV
Commercial in confidence
Page 5 of 19
A. Mobile/Moving Test :
- MS1 Idle Mode : 1. Lock on GSM 2. Lock on All sector BCCH - MS2 Dedicated Mode : 1. Lock on GSM 2. Use Command Sequence of Long Call to 212
B. Stationary Test :
For stationary test all test done with lock on BCCH of each cell 1. Voice Call : a. Short Call to 212, Duration : 120 seconds, Wait : 10 seconds, Repeat : 10 times b. MOC to MTC, MS2 make voice call to MS1, functionality test 2. Packet Data : a. Download (DL) EDGE ; MS2 Use Command Sequence FTP DL; filesize : 1 Mb b. Upload (UL) EDGE; MS2 Use Command Sequence FTP UL; filesize : 300 Kb 3. SMS : a. Send SMS from MS2 to MS1, functionality test 4. Handover : a. Handover intra site : Lock to sector A BCCH, MS2 dedicated mode make long call to 212 During call, force HO to sector B, using set target HO in GSM dedicated mode tab in TEMS MS option, and do the same from sector B to sector C Consecutively force HO with this order A B C B A C b. Reselection Inter Technology (2G to 3G) : Set RAT Control to lock GSM, lock to BCCH each cell When serving by Cell, change RAT Control to 3G
Commercial in confidence Page 6 of 19
Command sequence
Test Type 1. Moving Test Test Item Moving Dedicated mode Moving Idle Mode a. Voice Short Call b. Voice MOC to MTC c. PS Download d. PS Upload Command sequence use Long Call to 212 Not needed Short Call to 212; Duration : 120 s; Wait : 10 s; Repeat : 10 times Short Call from MS2 to MS1; Duration : 20 s; Wait : 10 s; Repeat : 2 times EDGE Download 1 MB data from FTP server EDGE Upload 300 kB data to FTP server Send SMS from MS2 to MS1; Repeat : 2 times Long Call to 212, change target HO during call Apply to MS2 MS1 MS2
HCPT DT_Static Voice_212.xml
XML file
HCPT DT_longCall_Idle_212_9999.xml
2. Stationary test
MS2
HCPT MOC-MTC.xml
MS2
MS2
MS2
HCPT DT_sms.xml
MS2
HCPT DT_longCall_Idle_212_LOOP.xml
Notebook
Recommended: Notebook with minimum dual core processor, RAM 1 GB, Hard disk 350 GB Sony Ericsson K800 (+ USB connector cable) Sony Ericsson K790 (+ USB connector cable) BU-353 or similar type
2 3 4
GSM Handset (MS1) GSM Handset (MS2) GPS with USB interface
1 1 1
Windows XP Based, Pre-Installed TEMS Investigation 8.0.3 (patched) Pre-Installed drivers for MS and GPS Pre Installed TEMS Pocket Pre-Installed TEMS Pocket
Commercial in confidence
Page 7 of 19
Number of item(s) 1
Specification Additional Software for support : - Mapinfo 8.5 - Image Capture (e.g: Snagit etc.) - Actix Analyzer - Google Earth - Atoll 500 Watt Any Any
2 3 4
1 1 1
Commercial in confidence
Page 8 of 19
Site Verification (Database data from BSC Dump & Measured data verified by DT result) SECTOR 1 SECTOR 2 SECTOR 3 Database Measured Database Measured Database Measured Cell ID 13852 13849 13849 13851 13851 13852 LAC 13750 13750 13750 13750 13750 13750 MCC 510 510 510 510 510 510 MNC 89 89 89 89 89 89 BSIC 0-4 0-4 0-4 0-4 0-4 0-4 BCCH 841 841 848 848 850 850 - Plot BCCH (Plot using Nastar from BCCH actual) BCCH Plot Sector 1 BCCH Plot Sector 2
Commercial in confidence
Page 9 of 19
Verify All Cell working normally, serving in Dedicated Mode Verify no Drop Call, no Interference and no Blocking or Fading of coverage Take Photo Justification for end of route or Blocking by surrounding Verify Handover success to all surrounding neighbor sites : Cell A to NCell Cell B to NCell Cell C to NCell OK OK OK NOK NOK NOK NCell to Cell A NCell to Cell B NCell to Cell C OK OK OK NOK NOK NOK
Commercial in confidence
Page 10 of 19
Verify All Cell working normally, serving in Idle Mode Verify no Crossfeeder Verify no Co-Channel BCCH with neighbor sites C. Predicted Over lay for Site 132879 (IDLE RX LEVEL PLOT)
Verify Rx Level Plot must Match with Coverage Plot Verify for any justification if Rx Level actual doesnt match CovPlot (Blocking, Hilly Terrain etc.)
Commercial in confidence
Page 11 of 19
Verify Rx Level Plot in Dedicated is normal Power Control should be put in consideration for Dedicated Plot (Rx Level tend to decrease along with Power Contro enabled)
Commercial in confidence
7.3.2.
-
Verify Handover success to each cell of that site (can be done by moving around site or take static handover test by applying Force Handover via TEMS) : OK OK OK NOK NOK NOK Cell B to A Cell C to A Cell C to B OK OK OK NOK NOK NOK
Verify Handover success to all surrounding neighbor sites : NCell to Cell Cell A to NCell OK NOK A NCell to Cell Cell B to NCell OK NOK B NCell to Cell Cell C to NCell OK NOK C
OK OK OK
7.3.3.
Voice Call SMS Test FTP DL FTP UL -
Stationary Test
SECTOR 1 Pass Pass Pass Pass Pass SECTOR 2 Pass Pass Pass Pass Pass SECTOR 3 Pass Pass Pass Pass Pass
PASS Test Functionality for : 1) Voice Call (to:212 and MOC-MTC) = All call success (CSSR=100%) 2) SMS Test (MS2 to MS1) = All SMS Sent & Received Successfully 3) FTP DL 100 Kbps 4) FTP UL 50 Kbps SECTOR 1 sec. 2.206 Kbps: 90.54 Kbps: 111.36 SECTOR 2 sec. Kbps: Kbps: SECTOR 3 sec. Kbps: Kbps:
Commercial in confidence
Page 13 of 19
- Take Capture for FTP DL and FTP UL (Replay from TEMS Investigation) DL throughput Chart Sector 1 UL throughput Chart Sector 1
Commercial in confidence
Page 14 of 19
Site 133174 ISAT BABAT (CI:12051, 12052, 12053) was not serving during SSV causing no HO event to that site.
Commercial in confidence Page 15 of 19
Based on performance during that time, possibly site 133174 ISAT BABAT was not active:
Route of sector 2 cover by site 130078 SIMOKATRUNGANS (CI 5234), because suspect blocking by trees and fading by building
Commercial in confidence
Page 16 of 19
Poor Rx Level in circled area caused by obstruction by a hill, blocking the coverage to that area E. Poor Rx Qual
Commercial in confidence
Page 17 of 19
8. Attention Items
Ensure before go SSV, Sites is up and running normally. Checking Sites for Alarm and Status is essential. Sites that is ready for SSV is clear from abnormal conditions. Report immediately to Project team if found following conditions : 1) Locked BTS/Cell/TRX 2) Service Impact Alarms such as : Equipment Alarms, e.g.: VSWR, DULNA, COBA Quality Alarms, e.g.: BTS with no transactions, No Call within predefined period 3) TCH Availability cell hourly data for more than one day period is <100% continuously Check and optimize Neighbors & Site Parameter setting as necessary to ensure SSV and KPI have good results. This include retune BCCH frequency and modify neighbors if needed For site rectification of issues like crossfeeder, make sure plan join visit with project team to avoid repeated failed SSV