Sie sind auf Seite 1von 26

2/24/2013

BARAKAH NUCLEAR POWER PLANT PROJECT

Pl Please Turn T off ff your mobile! Or Switch to vibration mode!

Check! Right Now!


BARAKAH NUCLEAR POWER PLANT PROJECT

2/24/2013

SCREEN

1 2 3 4 5

Dont Panic Switch Off All Electrical Equipment Dont Run, Walk Fast! Go to the Assembly Point Wait for the Final Instruction

BARAKAH NUCLEAR POWER PLANT PROJECT

BARAKAH NUCLEAR POWER PLANT PROJECT

2/24/2013

1. Previous Meeting 2. HSE Programs 3. HSE Statistics Performance per Area and Total 4. HSE Findings Summary Findings analysis- cause wise, Company, and Area HSE Findings by Company Reported Near Miss Evaluation by Findings Score

5. Weekly Inspection 6. Environmental Issues 7. Action Plans

BARAKAH NUCLEAR POWER PLANT PROJECT

BARAKAH NUCLEAR POWER PLANT PROJECT

2/24/2013

NO.

ITEMS

ACTION PLANS
Everyone is invited on activity today, all staff are join and support pp the 2013 HSE Objectives j advised to j by affixing their signature on the banner, and demonstrating their commitment in HSE objectives.

ACTION BY

DUE DATE

STATUS

Banner Signing S

____

Information I f ti

Hwachon although on initial phase with their Low Submission construction will promote submission of HSE of HSE Findings findings and aim to exceed from the total findings reported by HSJV and KEPCO. Seobon once again tops HSE findings after ratings are applied on all raised issues. The organization will revert back on next meeting on their planned countermeasures. Copy of the emergency evacuation for identified non-permit required confined space at Power Block will be forwarded to ENEC HSE Mr. Chris. The entry access is located through a hole in dense set of vertical rebars.

Hwachon

Next Meeting

High HSE Fi di Findings

Seobon

Next Meeting M ti

Emergency Evacuation Procedure

HSJV

Done

BARAKAH NUCLEAR POWER PLANT PROJECT

Description : Banner signing day last 18 Feb. 2013, 11:30 to 1:30 PM. Staff and Management participated in the campaign for 2013 HSE Objective. Senior Management personnel show their commitment for a safe construction.
BARAKAH NUCLEAR POWER PLANT PROJECT

2/24/2013

BARAKAH NUCLEAR POWER PLANT PROJECT

Company Seo Yong ADVAN D&I Total

Installed 0 1 0 1

Stand by 5 3 NA 8

No. of winch (for emergency rescue) : 9 winch is available when emergency situation.

Description : Non - permit required confined space, retrieval system. Available number of Nonwinch at site that can be used as retrieval of personnel during emergency at limited entry vertical access confined space.
BARAKAH NUCLEAR POWER PLANT PROJECT

2/24/2013

Thi slide This lid is i to t be b presented and discussed by HSJV Electrical Team.
BARAKAH NUCLEAR POWER PLANT PROJECT

BARAKAH NUCLEAR POWER PLANT PROJECT

2/24/2013

Methods of Communication :
1. Safety Alerts 2 Tool box meetings 2. 3. Notice boards 4. MeetingsMeetings daily, weekly, monthly 5. Incident reports 6. Others

Description : The manner HSE issues are communicated from site. Site Manager of Subcontractor should lead in the transfer of information. All HSE issues and instructions should reach workers and understands the message correctly.
BARAKAH NUCLEAR POWER PLANT PROJECT

BARAKAH NUCLEAR POWER PLANT PROJECT

2/24/2013

(This Week From Feb 16 Feb 22, 2013)

Item
Near Misses
Over speeding
First Aid Cases (FA) Medical Treatment Cases (MTC) Restricted Work Cases (RWC) LTIs Property/Vehicle Accidents Environmental R l Release

Ancillary Area For the Cum Week

Camp Area For the Cum Week

Office Area For the Cum Week

Power Block For the Cum Week

Village 1 For the Cum Week

Village 2 For the Cum Week

HSJV Total For the Cum Week

NMDC Total For the Cum Week

0 0 0 0 1 0 0 0

0 0 1 0 1 0 1 0

0 0 0 0 0 0 0 0

0 0 0 0 1 0 1 0

0 0 0 0 0 0 0 0

2 0 0 2 0 0 1 0

0 0 2 1 0 0 2 0

5 0 4 3 1 0 3 0

0 0 0 0 0 0 0 0

0 1 2 0 0 0 1 0

0 0 0 0 0 0 1 0

0 0 2 0 0 0 2 0

0 0 2 1 1 0 3 0

7 1 9 5 3 0 9 0

0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0

Forthisweek OneStrike Policy 0

Cumulative 109*

Legend : Ancillary Rebar Shop, Batch Plant, Paint Shop, Heavy Equipment Shop Power Block Cut Off Wall, Wharf Area, Concrete Block Area * : 41 cases (Oct- Dec. 2011), 64 cases (2012), 4 (2013)

BARAKAH NUCLEAR POWER PLANT PROJECT

(This Week From Feb 16 Feb 22 , 2013)


Source: CAR, Near Miss, Observation Cards and Walkthrough

Area

No. of No. of Inspections Findings

KEPCO & HSJV

SUBCON
350

KEPCO&HSJV

SUBCON

Ancillary Area Camp Area Office Area Power Block Village 1 Village 2

5 4 5 5 5 5

52 20 74 318 77 16

8 16 5 51 6 0

44 4 69

300

267

250

200

150

267 71 16

100 44 8 0 Ancillary Area Camp Area 16 4 5

69 51 6 Power Block

71

50

16 0 Village2

Total Findings

557

Office Area

Village1

BARAKAH NUCLEAR POWER PLANT PROJECT

2/24/2013

BARAKAH NUCLEAR POWER PLANT PROJECT

(This Week From Feb 16 Feb 22 , 2013)

Issued Findings
K E P C O H S J V
S U B C O N

Status
Total

Open
KEPCO HSJV Subcon KEPCO

Closed
HSJV Subcon

NearMiss CAR OC&WF TOTAL

0 3 0 3

0 3 0 3

0 0 0 0

0 0 0 0

0 0 0 0

0 43 40 83

0 177 294 471

43 177 223 40 294 334 83 471 557

BARAKAH NUCLEAR POWER PLANT PROJECT

2/24/2013

for the Period


Feb16 Feb22,2013 Company CCAP
Geumhwa HSJV Seoyong 1 1 1

CAR/NM
0 0 0

Total

BARAKAH NUCLEAR POWER PLANT PROJECT

(This Week From Feb 16 Feb 22, 2013)

Signs,Barriers&barricades Access&Egress MaterialManagement PPE FirePrevention ElectricalSafety Plant&Equipment WorkingatHeight Scaffolding Lifting ColorCoding WasteManagement Health&Welfare Environmental Documents Hand&PowerTools Training FallProtection HotWorks PoorIllumination PTW ConfinedSpace

59 52 45 39 34 32 29 25 24 22 21 20 13 11 11 9 9 8 8 6 5 1
0 10 20

Source: CAR, Near Miss, Walkthrough and Observation Card


30 40 50 60 70

BARAKAH NUCLEAR POWER PLANT PROJECT

10

2/24/2013

1
Install barricade on open excavation ( RCB, Al Raeel) Provide details, warning signs on electrical distribution panel (Power Block, Gusan) Provide warning signage, and barricade on pipelines under hydro test (TGB, Younchang PB) Lifting works should be enclosed by barricade (Village 1, Hyundai C&I) Erect access way for personnel working at height (RCB, Advan) Removal of obstruction on access to substation (STC, Jonghap) Ensure ladder is secured as per industry practices (RCB, Seoyong PB) Clearing entrance of building from portable tools (Village 1, Eunmin)

2
Surplus electrical cable should be kept at designated place (ADB, Seobon) Water proofing materials must not be left in the working area. (TGB1, Isam Kabbani) Initiate arrangement of storage area at steel fabrication ex. A place for plywood (Ancillary, Yooa) Perform material arrangement in the area. (TGB, D&I)

Signs, & Barricades

Access and Egress


BARAKAH NUCLEAR POWER PLANT PROJECT

Material Management

BARAKAH NUCLEAR POWER PLANT PROJECT

11

80 70 60 50 40 30 20 10 0
Seoyong Seoyong(PB) TowersTech Gusan Gusan(PB) Eunmin Jonghap Jonghap(PB) YounChang YounChang(PB) Hwachon WBG Hilalco Advan Hanlim Uwell YooA HyundaiC&I Samjin Eugene Daemyung Seobon D&I AlRaeel DOW Samho
BARAKAH NUCLEAR POWER PLANT PROJECT

(This Week From Feb 16 Feb 22, 2013)

BARAKAH NUCLEAR POWER PLANT PROJECT

KEPCO/HSJV SUBCON Manpower

800 700 600 500 400 300 200 100 0

2/24/2013

12

2/24/2013

FindingsScore=NumberofCausalxRisk(FactorScore) 10.0 9.0 80 8.0 7.0 6.0 5.0 4.0 3.0 2.0 1.0 0.0
Source: CAR, Near Miss, Walkthrough and Observation Card reported by KEPCO & HSJV

70 7.0 6.0 3.8 3.6 4.1 2.1 2.2 0.2 0.9 2.9 1.5 1.5 0.2 3.6 1.0

Legend : (I) Infra, (PB) Power Block

ActionPlan forCompanyrequiringassistanceandsupportfromthesystem 1.JointInspection willbecarriedoutbyAreaManagementTeam. 2.SpotTrainingwillbegiven toworkersaboutmajorfindings 3.Actionplanwillbe submittedtoHSJVHSETeamdevelopbyADVAN


BARAKAH NUCLEAR POWER PLANT PROJECT

BARAKAH NUCLEAR POWER PLANT PROJECT

13

2/24/2013

Health& Welfare,1

Environmental,1 Material Management,1

HotWorks,1

Signs,Barriers& Barricades,1

ColorCoding,1

Total No. of Findings: 55


Top Hazards

Hand&Power Tools,1

El t i lSafety, S f t 1 Electrical

Access& Egress,11

Cause Access&Egress Housekeeping


Control Measure

Nos 11 9
Due Date

Waste Management,2 PPE,2 FallProtection,2

Laddershouldbefixedby suitable part,accessmust beclearedofobstruction Improvearrangement cables lyingontheground. Observehousekeepingatall times

Always
g 4 Scaffolding,

Always

Workingat Height,5 Lifting,6

FirePrevention,6 Housekeeping,9

Source: CAR, Near Miss, Walkthrough and Observation Card


BARAKAH NUCLEAR POWER PLANT PROJECT

Supervision,1 Scaffolding,1

ColorCoding,1 ElectricalSafety,1 Housekeeping,9

Total No. of Findings: 41


Top Hazards Cause Housekeeping Signs,Barriers&Barricades
PPE,2

Nos 9 5

Training,2

Health& Welfare,2

Control Measure Removalofexcessconcrete intimelymanner. Arrangementofcables awayfromwetsurfaces surfaces. Install barricadeonopen excavation.Scaffolding surplusmaterialsshouldbe boundedbybarricade.

Due Date

Hand&Power Tools,2

Always
Plant& Equipment,2 Material Management,3 Access& Egress,3 FirePrevention,3 Signs,Barriers& Barricades,5 Workingat Height,4

Always

Source: CAR, Near Miss, Walkthrough and Observation Card


BARAKAH NUCLEAR POWER PLANT PROJECT

14

2/24/2013

Total No. of Findings : 37


Top Hazards Cause Housekeeping Signs, Barriers,&Barricades Nos 6 6

Material Management,3 Waste Management,1 supervision 2 supervision,

Access&Egress,1 Training,1

ColorCoding,1 ElectricalSafety,2 FirePrevention,1 Health& Welfare,3

Control Measure Management of housekeepingat constructionsite,and insidecamp p barricadeof Complete excavation,construction materialandstationary equipment.

Due Date
Signs,Barriers& Barricades,6

Always

PPE, PPE 4

Housekeeping,6

Always
Plant& Equipment,4 Lifting,2

Source: CAR, Near Miss, Walkthrough and Observation Card


BARAKAH NUCLEAR POWER PLANT PROJECT

BARAKAH NUCLEAR POWER PLANT PROJECT

15

2/24/2013

AREA : Power Block (Advan (Advan) )

February 19,2013

CORRECTIVE ACTION:

PLANNED SUPERVISOR PREVENTIVE ACTION

BARAKAH NUCLEAR POWER PLANT PROJECT

AREA : Village 2 (Al Raeel Raeel) )

February 19,2013

CORRECTIVE ACTION:

PLANNED SUPERVISOR PREVENTIVE ACTION

BARAKAH NUCLEAR POWER PLANT PROJECT

16

2/24/2013

AREA : Power Block (RCB/AB) (Seoyong (Seoyong) )

Feb. 21, 2013

CORRECTIVE ACTION:

PLANNED SUPERVISOR PREVENTIVE ACTION

BARAKAH NUCLEAR POWER PLANT PROJECT

BARAKAH NUCLEAR POWER PLANT PROJECT

17

2/24/2013

Inspection Committee Inspection Weekly Inspection

Date 2013-02-19 2013-02-20

Attendees HSJV, KEPCO, HSE Management Team HSJV HSE Team

Remark 8 Findings 16 Findings

BARAKAH NUCLEAR POWER PLANT PROJECT

FindingsperCompany
5 4 3 2 1 0
Advan Geumhwa Hanlim Samjin Seobon Seoyong(PB) Uwell

Total

4 2 1 1 2 2 1 1
YounChang YounChang(PB)

FindingsperCausal
NoPPE LacksFirePreventionEquipment LacksTraining ImproperEquipment PoorGrounding LacksSafetyControl NoWorkPermit 0 1 1 1 1 2 2 2 3 6

Key item : Welding & Hot Works


3 4 5 6 7

BARAKAH NUCLEAR POWER PLANT PROJECT

18

2/24/2013

BARAKAH NUCLEAR POWER PLANT PROJECT

No.

Source of Injury

Area

Description

Immediate Action

Planned Supervisor Preventive Action

Theabovementioned employeewashelpingto unloadsteelembeddedplate fromtheloadingbodyofpick Consult SteelFixer up.Duringthetime,oneplate Oral wasstackedwiththeother Backpain analgesic Powerblock platethenheappliedmore givenfor (laydown pressureandhisbackgot pain area) suspected t dli ligament tsprain. i Th The plateweightwasaround25kg 16022013 andhandledbytwopersons

Hilal Co.

11:20

BARAKAH NUCLEAR POWER PLANT PROJECT

19

2/24/2013

No.

Source of Injury

Area

Description

Immediate Action

Planned Supervisor Preventive Action

HSJV Workshop
TowerCrane Operator PowerBlock 17022013 17:00 Workersrightknee washitbyaslow movingcrane trolley.

Pain,Right knee

Analgesicspray applied Elasticbandage applied Icecompress done Oralanalgesic given Mefenamic Acid

BARAKAH NUCLEAR POWER PLANT PROJECT

No.

Source of Injury

Area

Description

Immediate Action

Planned Supervisor Preventive Action

Hewasdoinghis surveyactivitieson Surveyor thegroundlevel DoctorReferral Hitting his A&Bareawhen rightlower tooutsidefor PowerBlock suddenlyahand back further RCB/ABArea cutterfellfromthe portionof treatmentina groundhittinghis hisear Hospital. 17022013 rightlowerback portionofear. 10:00

Seoyong

BARAKAH NUCLEAR POWER PLANT PROJECT

20

2/24/2013

No.

Source of Injury

Area

Description

Immediate Action

Planned Supervisor Preventive Action

YooA
Whilehesteppedonthe Elastic cabinsstair,hislegslipped Bandageapply andhelosthisbalance Ancillary, Pain,Rt withsplint and fell down with Steel Ring& Referralto 4 Fabrication weldingmachine.Hisright Smallfinger Hospitalfor handring&smallfingers Shop Swelling further trappedinbetween evaluation weldingmachineand 18022013 CheckXray. ground. 15:40 Welder

BARAKAH NUCLEAR POWER PLANT PROJECT

BARAKAH NUCLEAR POWER PLANT PROJECT

21

2/24/2013

Location Description Actiontaken Status

PetrolStation Fuelleakagehappened atconnection partduringfillingafueltank Imperviousdriptrayplacedonthechargingpointofthepetrolstation CLOSED

BARAKAH NUCLEAR POWER PLANT PROJECT

Location Description Actiontaken Status

Intersectionbetween rebarshopandwarehouseinancillaryarea Allcontrolvalvesareexposed topotentialaccident/incidents without fenceandsignagearoundthe STPFacility Installthefenceandpropersignage topreventaccessofunauthorized personnel OPEN
BARAKAH NUCLEAR POWER PLANT PROJECT

22

2/24/2013

Location Description Actiontaken Status

AroundRCB Unit2inpowerblock ObservedminorhydraulicoilleakagefromADVANconcretepumptruck#BNPP1987 Theconnectinghosewasdamagedandtemporarywrappedbyglovesandtapes. Theconnectinghosewasrepairedandreplacedwithaproperjointvolt CLOSED

BARAKAH NUCLEAR POWER PLANT PROJECT

Location Description Actiontaken Status

GIBareainpowerblock Observedminorhydraulicoilleakagefromstationary dieselgeneratorequipmentACM84 Cleanedupcontaminated soilandprovideddriptraytocontainoilleakage

CLOSED
BARAKAH NUCLEAR POWER PLANT PROJECT

23

2/24/2013

No.0

Date

Action by Company

Description

Status

Closing Date

Expiration Date

Ref. No.

Main Area

Sub-Area

Issued By

Issuer Company

UA/UC

20Feb13

Hilalco

Stationarydieseloperatedgenerator equipmentACM84observedminor hydraulicoilleakagebeneaththe equipment

Closed 24Feb13 25Feb13 20130518

Power Block

GIBArea

HSJV

Renato Ponce

UC

20Feb13

Advan

Advanconcretepumptrucki.d.# BNPP1987parkatRCBUnit2observed minorhydraulicoilleakageonthe concretegroundandthesourceof leakageistemporarywrapbyknetted glo e gloves.

Closed 23Feb13 25Feb13 20130524

Power Block

RCBU nit2

HSJV

Renato Ponce

UC

24Feb13

HSJV O&M

Allcontrol valvesareexposedto potentialaccident/incidentwithoutfence Open andsignagearoundSTPfacilityin Ancillaryarea.

Intersectio nbetween 06Mar13 000000160 Ancillary rebarshop and warehouse

KEPCO

Yang,Ji Young

UC

BARAKAH NUCLEAR POWER PLANT PROJECT

WASTETYPE
Paper Metal Construction Concrete Wood(Good) Wood(Bad) Plastic Municipal Hazardous TotalSolidWaste

WASTEMANAGEMENTUPDATE Week=14/02/2013 20/02/2013 Thisweek


Collected(m3) Disposal(m3) Recycled(m3) Recycle(%)

Lastweek
Recycle(%)

Collected(m3) Disposal(m3) Recycled(m3)

72 32 120 0 0 192 72 0 16 504

0 0 495 0 0 180 0 288 16 979

0 90 0 0 0 0 0 0 0 90 9.19%

24 88 96 0 0 280 104 0 0 592

0 0 675 0 0 225 0 264 0 1164

0 0 0 45 0 0 0 0 0 45 3.86%

Legend: Collected WastefromSitetoTemporaryStorageArea Disposal WastefromTemporaryStorageAreatoLandfillArea Recycle Treatedwaste(GMET)toRecyclingPlants BARAKAH NUCLEAR POWER PLANT PROJECT

24

2/24/2013

BARAKAH NUCLEAR POWER PLANT PROJECT

BARAKAH NUCLEAR POWER PLANT PROJECT

25

2/24/2013

BARAKAH NUCLEAR POWER PLANT PROJECT

BARAKAH NUCLEAR POWER PLANT PROJECT

26

Das könnte Ihnen auch gefallen