2) Screen material at spoil area. 3) Mix material. - Load screened material into pugmill hopper - Load cement into Pugmill silo - Load water into pugmill. The conveyor belt on the pugmill shall be calibrated by timing the belt and weighting the amount of material on the belt in the given time. The gate on the cement hopper shall be set and the flow calculated by weighing the amount of cement on the belt in a given time The gate of the cement hopper shall be adjusted to be coordinated with the flow of material to 60kg +/- 10kg cement per meter cube of material. The water flow rate shall be adjusted to allow the addition of water to OMC +/- 5% 4) Transport The material shall be transported from the pugmill to the placing area by ADT/Tipper Trucks at the placing area. 5) Placing and compaction The material shall tipped and spread by loader and or grader. Once the material has been spread it shall be compacted by 10T vibrating roller and pedestrian roller. 6) Cure With Water From Water Tanker( within 2 hrs from placement) Notes The slopes shall be overbuilt to allow for compaction on the edges. The slope shall be trimmed to correct line and level by excavator Proposed placing rate is 200m3 per day. 1
Cement to be PPC 32.5N Plant and method statement shall be finalized after completion of trial section Cure with bitumen once reaching final level
7) Plant List Water Tanker Generator 250KVA Pugmill Komatsu 420 Loader (Or Similar) Vibrating Screen 2no ADT/Tipper Komatsu 420 Loader ( Or Similar) Grader BW 212 Vibration Roller Or Similar 1Tonne Pedestrian Roller Or Similar Excavator Supply Water To Pugmill Power Pugmill Mix Material Load Pugmill Screen Material Transport Csg Spread Material Spread Material Compaction Compaction Trim Slopes
PLANT Komatsu 420 Loader Vibrating Screen Re Claimer Grader Excavator 2 X ADT/ Tipper Load Screen Screen Material Mix Material Spread Material Trim Slopes Transport Material Spoil Bank To Placing Area 3