© 2008, Interactive Saudi Arabia Limited. All rights reserved. This document or any part thereof may not, without the
written consent of Interactive Saudi Arabia Limited (ISA), be copied, reprinted, or reproduced in any material from,
including but not limited to photocopying, tanscribing, transmitting, or sorting it in any medium or translationg it into
any language, in any form or by any means, be it electronic, mechanical, xerographic, optical, magnatic or
otherwise.The information contained in this document is proprietry and confidential; all copyrights, trademarks, trade
names, patents and other intellectual property rights in the documentation are the exclusive propery of ISA unless
otherwise specified. The information (including but not limited to data, drawings, specification and documentation)
shall not at any time, be disclosed directly or indirectly to any third party without the prior written consent of ISA. The
information contained herein is believed to be accurate and reliable. ISA accepts no repsonsibility for its use by any
means or in any way whatsoever.The indormation contained herein is subject to change without notice.
<Document Name>
<Project Name & Project Code>
1.2 Background
<Project Background Descriptions>
1.3 Scope
<Project Scope Descriptions>
Author
Document Created or Received or or
Notes
(and version / date) Available Reviewed Resourc
e
Requirements Yes
Yes No
Specification No
Functional Yes
Yes No
Specification No
Yes
Use-Case Reports Yes No
No
Yes
Project Plan Yes No
No
Yes
Design Specifications Yes No
No
3.1 Approach
Test cases developed during the construct phase will be updated by the Project
Team during test execution and test logs will be created. Any deviations in
expected results will be documented in the comments section of the log. All the
defects found during the testing will be tracked to closure. Decisions on test
case updates will be reserved for the daily or weekly Project review meeting as
applicable during the test period.
The project teams plan to complete all test cases. Every failed test case will be
recorded. When a single coding error appears in multiple parts of the application, it
is recorded as multiple fails. Application development rework will be done as soon
as a test case fails. The application cannot move to production with level one, two
and three errors but may work with level four errors with customer approval.
What is a Defect?
Testing is performed to ensure the application satisfies all requirements. When
the application does not perform as expected, the tester first confirms that both
Variance from product specifications - The product built varies from the product
specified.
Hardware (TBD)
Software (TBD)
7.2 QC Desktop
Hardware (TBD)
Software (TBD)
0 0
Resources
Productive Hours Per Workday 0
Resources 0
Human Resources
Worker Resources Specific Responsibilities/Comments
Recommended
Test Team Lead () Full-time Responsibilities:
Problem Domain Specialist
External Components Acquirer
End-User Educator
Technical Lead
Product Delivery Specialist
Test Analyst/Architect () Full-time Responsibilities:
Testing Methodology
Automatic Testing Tools
Technical basics of particular
application
System & Integration Tests
Performance tests
User Acceptance Tests
Delivery & Planning –
Estimate
Test Dependencies:
Availability of required Real System Data
Unit and System testing must be stable to begin Integration and Regression testing
Integration and Regression testing must be stable to begin Performance and Load
testing
Performance and Load Test must be stable to begin UAT testing
*Note: An Issue is something that has happened. A Risk is something that could happen
16.1 Signoffs