Sie sind auf Seite 1von 23

INTERACTIVE SAUID ARABIA LTD.

Test Plan Template


Test Plan
Ahmed Abdulhamid
12/2/2008

© 2008, Interactive Saudi Arabia Limited. All rights reserved. This document or any part thereof may not, without the
written consent of Interactive Saudi Arabia Limited (ISA), be copied, reprinted, or reproduced in any material from,
including but not limited to photocopying, tanscribing, transmitting, or sorting it in any medium or translationg it into
any language, in any form or by any means, be it electronic, mechanical, xerographic, optical, magnatic or
otherwise.The information contained in this document is proprietry and confidential; all copyrights, trademarks, trade
names, patents and other intellectual property rights in the documentation are the exclusive propery of ISA unless
otherwise specified. The information (including but not limited to data, drawings, specification and documentation)
shall not at any time, be disclosed directly or indirectly to any third party without the prior written consent of ISA. The
information contained herein is believed to be accurate and reliable. ISA accepts no repsonsibility for its use by any
means or in any way whatsoever.The indormation contained herein is subject to change without notice.
<Document Name>
<Project Name & Project Code>

< Test Plan>


<Company Name>
<Project Name>

Project Code: <Client Name – 3 Letters>-<Project Short Name>

Document Name: <Document Name>


Prepared for: <Company Name>
Author: Ahmed Abdulhamid
Pages: 23
Last Updated: 6/1/2009
TABLE OF CONTENTS
1 Introduction ................................................................................................................ 5
1.1 Purpose .............................................................................................................. 5
1.2 Background ........................................................................................................ 5
1.3 Scope ................................................................................................................. 5
1.4 Project Team ...................................................................................................... 5
1.5 Project Identification ........................................................................................... 5
2 Requirements for Test ............................................................................................... 7
2.1 Use Cases Phase 1............................................................................................ 7
2.2 Use Cases Phase 2............................................................................................ 7
2.3 Use Case Diagram Phase 1 & 2 ........................................................................ 8
3 Approach ................................................................................................................... 9
3.1 Approach ............................................................................................................ 9
Flow Chart Phase1 ........................................................................................................ 9
Flow Chart Phase 2 ....................................................................................................... 9
3.2 Testing Tools ...................................................................................................... 9
3.3 Measurement and Metrics .................................................................................. 9
3.4 Deliverables ........................................................................................................ 9
4 Item Pass/Fail Criteria ............................................................................................. 10
The following chart defines the Interactive agreed-upon severity levels: ....................... 10
5 Test Strategy ........................................................................................................... 11
6 Test Procedures ...................................................................................................... 12
6.1 Configuration Management .............................................................................. 12
6.2 Change Control Process .................................................................................. 12
6.3 Defect Reporting .............................................................................................. 12
6.4 File Locations ................................................................................................... 13
7 Environmental Needs .............................................................................................. 14
7.1 QC Test Lab ..................................................................................................... 14
7.2 QC Desktop ...................................................................................................... 14
7.3 Staffing and Training Needs............................................................................. 14
8 Tools ........................................................................................................................ 15
9 Resources................................................................................................................ 16
10 Test Case Creation/Execution Estimates (Schedule) ......................................... 17
11 Roles & Responsibilities ...................................................................................... 18
12 Issues/Risks and Mitigating Factors .................................................................... 19
13 Project Milestones and Target Dates................................................................... 20
14 Reports................................................................................................................. 21
15 Approvals ............................................................................................................. 22
16 Appendix A: Release Signoff Form...................................................................... 23
16.1 Signoffs............................................................................................................. 23

ISA Test_Plan_Template.doc (Version 1.0.0


Page 3 of 23
CHANGE HISTORY
Section Date Change Made

ISA Test_Plan_Template.doc (Version 1.0.0


Page 4 of 23
1 INTRODUCTION
1.1 Purpose
<Project Purpose Descriptions>

1.2 Background
<Project Background Descriptions>

1.3 Scope
<Project Scope Descriptions>

1.4 Project Team


Name: Title: Role: Phone #:

1.5 Project Identification


The table below identifies the documentation and availability used for
developing the test plan:

Author
Document Created or Received or or
Notes
(and version / date) Available Reviewed Resourc
e
Requirements  Yes 
 Yes  No
Specification No
Functional  Yes 
 Yes  No
Specification No
 Yes 
Use-Case Reports  Yes  No
No
 Yes 
Project Plan  Yes  No
No
 Yes 
Design Specifications  Yes  No
No

ISA Test_Plan_Template.doc (Version 1.0.0


Page 5 of 23
 Yes 
Prototype  Yes  No
No
 Yes 
User’s Manuals  Yes  No
No
Business Model or  Yes 
 Yes  No
Flow No
 Yes 
Data Model or Flow  Yes  No
No
Business Functions  Yes 
 Yes  No
and Rules No
Project or Business  Yes 
 Yes  No
Risk Assessment No
Architecture Diagram  Yes  No  Yes  No

ISA Test_Plan_Template.doc (Version 1.0.0


Page 6 of 23
2 REQUIREMENTS FOR TEST
The information below identifies those items (Use Cases, Functional Requirements, Non-
Functional Requirements) that have been identified as targets for testing. From a high
level this represents what will be tested.

2.1 Use Cases Phase 1


1 login (UC6)
<Use Case, Functional Specifications details etc>

2.2 Use Cases Phase 2


1 <Use Case, Functional Specifications details etc>

ISA Test_Plan_Template.doc (Version 1.0.0


Page 7 of 23
2.3 Use Case Diagram Phase 1 & 2
<Image Use Case Diagram>

ISA Test_Plan_Template.doc (Version 1.0.0


Page 8 of 23
3 APPROACH

3.1 Approach

Flow Chart Phase1


<Visio Image>

Flow Chart Phase 2


<Visio Image>
3.2 Testing Tools
 Test Coverage documents for Requirements Traceability management
 Automated Defect Tracking Tool for defect management-BTT
 Visual Source Safe for all test artifacts (e.g. test cases, execution log etc)
 QTP for test automation.
 <>

3.3 Measurement and Metrics


 UAT, System and Integration Test Cases.
 Final Test Execution Report.
 Base lined correct test results for all future tests.
 Defect Log
 <>
3.4 Deliverables
Deliverable elements from test team are.
o Test Plan
o Test Scenarios
o Test Data
o Test Cases
o Weekly Defect Report
o Test Execution Report
o <>

ISA Test_Plan_Template.doc (Version 1.0.0


Page 9 of 23
4 ITEM PASS/FAIL CRITERIA

THE FOLLOWING CHART DEFINES THE ZEON AGREED-UPON SEVERITY LEVELS:

Severity Level Description


1 – Crash Major functionality defect or loss with no workaround, causing
loss of data or application crash.
2 – Block Any functionality defect or loss with no workaround, causing a
failure to meet a specific system requirement
3 – Major Any functionality defect or loss causing a failure to meet a
specific system requirement, but which has a workaround that
is acceptable to the customer for a finite agreed period of time.
4 – Minor Inconvenience or annoyance issues

Defect Levels Permitted for Release Promotion from Validation to UAT


Priority one: zero maximum.
Priority two: five maximum.
Priority three: ten maximum.

Defect Levels Permitted for Release Promotion from UAT to Production


Priority one: zero maximum.
Priority two: zero maximum (unless an approved Change Request is in place).
Priority three: eight maximum

Test cases developed during the construct phase will be updated by the Project
Team during test execution and test logs will be created. Any deviations in
expected results will be documented in the comments section of the log. All the
defects found during the testing will be tracked to closure. Decisions on test
case updates will be reserved for the daily or weekly Project review meeting as
applicable during the test period.

The project teams plan to complete all test cases. Every failed test case will be
recorded. When a single coding error appears in multiple parts of the application, it
is recorded as multiple fails. Application development rework will be done as soon
as a test case fails. The application cannot move to production with level one, two
and three errors but may work with level four errors with customer approval.

Interactive Saudi Arabia Page 10 of 23


5 TEST STRATEGY
The testing strategy should define the objectives of all test stages and the
techniques that apply. The testing strategy also forms the basis for the
creation of a standardized documentation set, and facilitates communication
of the test process and its implications outside of the test discipline. Any test
support tools introduced should be aligned with, and in support of, the test
strategy
(Separate Document Available)

Interactive Saudi Arabia Page 11 of 23


6 TEST PROCEDURES

6.1 Configuration Management


The goal of configuration management is to control and document the physical and functional of a system to ensure the
integrity of the system is maintained. This is accomplished by implementing version control and change control
procedures of all physical and functional configurations of the system.

6.2 Change Control Process


The main objective of change control is to control the changes made to
project artifacts (technical documents, code and databases). If change
control processes are not followed, projects have a risk of scope creep or
moving the target that everyone is aiming at. In order for developers to
build software, they need a clear definition of how the software is
supposed to function.

6.3 Defect Reporting


The primary objective of a defect tracking system is to define
responsibilities and activities necessary to ensure that defects are
identified, prioritized and fixed. The key benefits of a good tracking
system are the improvements in communication and accountability.

The system must ensure:


 Anyone who needs to know about a defect should learn of it soon after it is
reported (Timeliness).
 No error will go unfixed merely because someone forgot about it
(Accountability).
 No errors will go unfixed merely because of poor communication
(Communication).

The tracking system will be used to document defect


information from initial finding through
resolution. During the course of software development, the
status of each defect will be
updated to keep the information current with the development-
test-repair cycle.

What is a Defect?
Testing is performed to ensure the application satisfies all requirements. When
the application does not perform as expected, the tester first confirms that both

Interactive Saudi Arabia Page 12 of 23


the test conditions and errant result are repeatable. Underlying conditions and
test results are then documented as a defect in the defect tracking system. A
defect is a variance from a desired product attribute. There are two categories
of defect:

 Variance from product specifications - The product built varies from the product
specified.

Wrong - the specifications have been implemented incorrectly. The


defect is a variance from customer/user specification.

Missing - a specified requirement is not in the built product. This can


be a variance from specification, an indication that the specification
was not implemented, or a requirement that the customer identified
was not in the specification. If a requirement is missing the new
requirement must flow through the change control process.

 Variance from customer/user expectation - This variance is something


that the user wanted that is not in the built product. The missing piece
may be a specification or requirement, or unsatisfactory implementation
of the requirement. If a requirement is missing or the requirement is
changed the new/changed requirement must flow through the change
control process.
6.4 File Locations
All files should be located where everyone on the project team can access them. The following chart will be used to
track the locations of the files.

File Name File Location in VSS Phases Test Case Type

Interactive Saudi Arabia Page 13 of 23


7 ENVIRONMENTAL NEEDS
This section specifies the necessary and desired properties of the test
environment including:
(TBD)
Each component developed is required to perform sufficient unit testing. The
unit test cases, test data, and test results will be created before the project
migrate to the pre-production environment. Testing tool will be used for
functional and load testing of the application. Scripts created for testing the
application will be also used in the pre-production environment.

7.1 QC Test Lab

Hardware (TBD)

Operating Systems (TBD)

Software (TBD)

7.2 QC Desktop

Hardware (TBD)

Operating Systems (TBD)

Software (TBD)

7.3 Staffing and Training Needs


N/A

Interactive Saudi Arabia Page 14 of 23


8 TOOLS

The following tools will be employed for this project:

Type Tool Vendor/In-house Version


Manage Documents Visual Source Safe 6.0
Bug snapshot Snagit 8.0
Automated Defect Bug Tracker 3.0
Tracking Tool for
defect management
Flow Charts Visio 10.0
Unit test MbUnit or NUnit
Browsers testing IETester , Firefox , Google
Chrome , Opera
Code Documentation NDoc V1.3.1
<> <> <> <>

Interactive Saudi Arabia Page 15 of 23


9 RESOURCES
This section presents the recommended resources for the test effort, their main
responsibilities, and their knowledge or skill set.

Name: Title: Role: Phone #:


QA Testing
QA Testing
QA Testing
QA Testing
QA Testing
<> <> <> <>

Interactive Saudi Arabia Page 16 of 23


10 TEST CASE CREATION/EXECUTION ESTIMATES
(SCHEDULE)

Test Case Creation / Execution Time Estimate


TestCases- TestCases-
UseCase# Use Case Title Phases Needed(est) Rework
<>

0 0

Test Case Creation


Total TestCases To Be Created 0
Total TestCases To Be Reworked 0
Hours To Rework Existing TestCase 0 0
Hours To Create New TestCase and Approval 0 0.0
Total HoursTo Completion (1 Person) 0.0
Total Days To Completion (1 Person) 0.0
Total Days To Completion (Test Team) #DIV/0!

Test Case Execution


Total TestCases To Be Executed 0
Average Hours to Execute Each Test Case 0
Total HoursTo Completion 0.0
Total Days To Completion (1 Person) #DIV/0!
Total Days To Completion (Test Team) #DIV/0!

Resources
Productive Hours Per Workday 0
Resources 0

Interactive Saudi Arabia Page 17 of 23


11 ROLES & RESPONSIBILITIES
This table shows the staffing assumptions for the project.

Human Resources
Worker Resources Specific Responsibilities/Comments
Recommended
Test Team Lead () Full-time Responsibilities:
 Problem Domain Specialist
 External Components Acquirer
 End-User Educator
 Technical Lead
 Product Delivery Specialist
Test Analyst/Architect () Full-time Responsibilities:

 Testing Methodology
 Automatic Testing Tools
 Technical basics of particular
application
 System & Integration Tests
 Performance tests
 User Acceptance Tests
 Delivery & Planning –
Estimate

Test Automation () Full-time Responsibilities:


Architect
 Design and develop manual scenarios from
system requirements.
 Design and develop automation scripts.
These may be developed from manual
scenarios.
 Design and configure test environment.
Update automated software.
<> <> <>

Interactive Saudi Arabia Page 18 of 23


12 ISSUES/RISKS AND MITIGATING FACTORS
All project Issues/Risks and Mitigating Factors have been documented within a separate Issue
and Risk log. All issues are document, prioritized, tracked and managed through the Issue &
Risk Management Process Flow.

Test Dependencies:
 Availability of required Real System Data
 Unit and System testing must be stable to begin Integration and Regression testing
 Integration and Regression testing must be stable to begin Performance and Load
testing
 Performance and Load Test must be stable to begin UAT testing

Issue / Risk Assigned Proposed Resolution Proposed


To Resolution
Date
Equipment failure of
Testing Environment
Communications/net
work failure
Fire or other natural
disasters

*Note: An Issue is something that has happened. A Risk is something that could happen

Interactive Saudi Arabia Page 19 of 23


13 PROJECT MILESTONES AND TARGET DATES
This section contains information about the project schedule, test milestones and
item delivery events.
(Refer to Project Plan)

Task # Task Name Duration Start Finish Predecessors

1 Test Scenario Matrix Phase1


2 System Test Cases Phase1
3 UAT Test Cases Phase1
4 Integration Test Cases Phase1
5 Test Scenario Matrix Phase2
6 System Test Cases Phase2
7 UAT Test Cases Phase2
8 Integration Test Cases Phase2
10 Test Data Phase1
11 Test Data Phase2

Interactive Saudi Arabia Page 20 of 23


14 REPORTS
Requirement coverage report – The requirement coverage report will be
used to track the development of test cases. This report will contain the total
requirements that have test cases developed.
Test case completion report – The test case completion report will be used
to track the development of testing test cases. This report will contain the
total test cases developed and the number of test cases remaining to be
developed.
Defect Summary report – The defect summary report will be used to track
the status of all defects. This report will contain the total number of open
defects (by status and priority).
Weekly status report – The weekly status report will be used to track the
progress of testing. It will contain detailed information about the
development of requirements, test cases, test data, test cases executed and
any problems or issues uncovered during testing.

Interactive Saudi Arabia Page 21 of 23


15 APPROVALS
We, the undersigned, certify that this Test Plan is complete, accurate, and can be
used to guide the testing activities.

Name Signature Date


<> <> <>

Interactive Saudi Arabia Page 22 of 23


16 APPENDIX A: RELEASE SIGNOFF FORM

16.1 Signoffs

Project Manager <>

System Architect <>

Development Team Lead <>

Test Team Lead <>

Interactive Saudi Arabia Page 23 of 23