Beruflich Dokumente
Kultur Dokumente
The Speaker:
Mr. T. Y. Leung - Principal Surveyor, Area Quality Manager for Area Asian/South Asia and Area Australia/ New Zealand
CV of the Speaker:
Mr. TY Leung has been working for GL as a Surveyor since 1988. He is also an ISM/ISPS/ISO9001/ISO14001 Auditor. He finished his Shipbuilding Apprenticeship in Hong Kong United Dockyards in 1978; graduated from the University of Glasgow in Naval Architecture and Ocean Engineering in 1985 and obtained his Master in Environmental Management from the National University of Singapore in 2004.
No. 2
No. 4
Precautionary Principle When an activity raises threats of harm to human health or the environment, precautionary measures should be taken even if some cause and effect relationships are not fully established scientifically."
No. 5
70 % thereof aquatic organisms Ballast water has been identified as a major threat
No. 6
No. 7
Sustainability
In 1987, the World Commission on Environment and Development developed a definition of sustainability that was included in its findings, which became known as the Brundtland Report. It stated that:
Sustainable development meets the needs of the present without compromising the ability of future generations to meet their own needs.
No. 8
The introduction of invasive marine species into new habitats can cause the collapse of existing ecosystems.
No. 10
Possible dangers by unwanted species They might: competing with existing species; fast
spreading; carrying toxic substances.
No. 11
No. 12
Tanks
Habitats for invasive species Where can such small creatures survive in a shipboard environment?
Ballast Water
Hull Fouling
Sediments
No. 13
Now, it has to be managed not only for the safety of the ship, but our environment.
No. 14
Facts & Figures Germanischer Lloyd (GL) employs more than 6,700 engineers, surveyors, experts and administrative staff in 80 countries. The global network consists of more than 208 stations and site offices.
No. 16
2003 Draft International Convention for the Control and Management of Ships Ballast Water and Sediments (with 10 Guidelines)
2004 - International Convention for the Control and Management of Ships Ballast Water and Sediments (with 14 Guidelines, G1 to G14)
No. 17
Separately, with 14
Guidelines
No. 18
No. 19
No. 20
No. 21
Articles
Art. 1 - Definitions
No. 23
Articles
Art. 3 Application
Notes - Application for all vessels that carry ballast water - This Ballast Water Management Convention shall not apply to: Ships not designed or constructed to carry ballast water Ships which only operate in waters of one Party, unless the Party determines that BW discharge would damage the environment, human health Ships which only operate in waters of one Party and the high seas Warships, naval auxiliary and others used only in governmental noncommercial service Ships with permanent BW in sealed tanks, not subject to discharge
No. 24
Articles
Art. 4 Control of the Transfer of harmful Aquatic Organisms and Pathogens
Through Ships Ballast Water and Sediments
No. 25
detailed inspection
No. 26
Articles
Art. 10 - Detection of Violations and Control of Ships Art. 11 - Notification of Control of Actions Art. 12 - Undue Delay to Ships Art. 13 - Technical Assistance, Co-operation and regional Co-operation Art. 14 - Communication of information Art. 15 - Dispute Settlement Art. 16 Relationship to International Law and other Agreements Art. 17 Signature, Rectification, Acceptance, Approval and Accession Art. 18 Entry into Force Art. 19 - Amendments; Art. 20 Denunciation Art. 21 Depositary Art 2 2 - Languages
No. 27
Regulations Section A General Provisions Section B Management and Control Requirement for Ships Section C Special Requirements in Certain Areas Section D Standard for Ballast Water Management Section E Survey and Certification Requirements for Ballast
Water Management
No. 29
No. 30
Section B Management and Control Requirements for ships Reg. B1 Ballast Water management Plan
Note: - every vessel should be equipped with a BMW Plan - plan is to be approved by Class or Flag State
No. 31
Ship particulars Tank arrangement Piping & pumping arrangement Officer and crew
Sampling points
Responsibilities Training
Operational procedures
General requirements Usage of the BWM Plan Ballast management Sediment management
Pumps/Piping arrangement
No. 32
100 A5 BWM
Ballast Water Management No. 33
No. 34
Reg. B-3 Ballast Water Management for Ships today Application Dates
const. date date BW [m] 1500 voluntarily (national Reg.) 5000 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014
2015
2016
< 2009
D1 or D2
D2
< 1500 < 2009 or voluntarily (national Reg.) > 5000 2009 < 5000 2009 and 5000 < 2012 2012 5000
D1 or D2
allowance period (recommended by IMO *)
D2
D2
D1 or D2
D2 D2
* refer to IMO.Res.A1005(25)
BW exchange BW treatment
Ballast Water Management No. 35
Reg. B-4 Ballast Water Exchange Note: 200 NM from land with 200M water depth
- Sequential Method
- Flow-through Method
No. 36
No. 37
No. 38
Section D Standard for Ballast Water Management Reg. D1 - Ballast Water Exchange Standard
Note: at least 95% volumetric exchange of ballast water; for flow through, at least 3 times the volume
No. 39
Reg. D4 Prototype ballast Water Treatment Technology Reg. D5 Review of Standards by the Organization
No. 40
BWM Convention Content - Regulations Section E Survey and Certification requirement for BWM
Reg. E1 Surveys
Note:- for 400GT and above - Initial, annual, intermediate and renewal
Reg. E4 - Form and the Certificate Reg. E5 Duration and Validity of the Certificate
No. 41
Exchange
Treatment
Isolation
Sequential
Flow-through
Mechanical
Physical
Chemical
Reception facilities
Return to origin
Dilution
Retention on board
No. 43
No. 44
Weather conditions
Ballast Water Management No. 45
Sequential method
Advantages Applicable for new &
existing ships necessary
Disadvantages
Changed loading condition for each step Limitations regarding stability, steel structure, Check of feasibility prior to exchange necessary Extensive pre-planning by crew required (safety reasons)
No. 46
Flow-through method
No. 47
No. 48
Constant overflow through airpipes with bypass Special airpipe head / Alternative airpipe design Constant overflow by overflow systems Ring ballast systems (dilution)
No. 49
Flow-through method
Additional pressure on structure Flow-through method can cause
additional pressure on the tank structure In case overflow point is at a high position,
then a combination of different pressures values occur
No. 50
No. 51
No. 52
No. 53
Flow-through method
Advantages No change in loading
condition
Disadvantages
Usually conversion work necessary (piping system, airpipes, overflow point, ) Not all tanks designed for constant high pressure
More time consuming than sequential method (approx. 1.5 times) Overflow to open deck not suitable in cold environment
No. 54
Exchange
Treatment
Isolation
Sequential
Flow-through
Mechanical
Physical
Chemical
Reception facilities
Return to origin
Dilution
Retention on board
No. 56
dirty water
Treatment System
clean water
No. 57
Filtration
Working method Technical constraints
Self-cleaning procedures
reduce the nominal flow rate (e.g. due to high sediment load)
Technical constraints
gravity different to that of water can be separated
No. 59
Coagulation, Flocculation
Working method Technical constraints Addition of coagulants to the Storage tank for additives needed
BW that create starting Sludge tank for out-flocked cells for flocculation of solid particles needed particles to bigger bodies Time consuming process Removal of the bigger cells (voyage length to be considered) by siffing out (e.g. filters)
Additionally magnetic/
electrical forces can be applied to improve the separation of flocs
No. 60
UV radiation
Working method
by quartz sleeves produce UV radiation
Technical constraints
turbidity of BW (i.e. sediments could limit the transmission of UV radiation)
membrane of organisms and UV lamps need to be maintained that a clear pathogens light is produced
No. 61
UV lights need to be
maintained that a clear light is produced
No. 62
Cavitation / Ultrasound
Working method Slit plates or venturi pipes
generate cavitation bubbles
External creation of
Ultrasound which is induced to the BW
Ballast Water Management
No. 63
Chemical additives
Working method Direct adding of chemical Technical constraints Dosing to be exactly adjusted additives to the BW that have Holding time in tank disinfectory actions
required Ozone (O3) Hydrogen peroxide (H2O2) Peracetic acid (Peraclean ) Chlorine / Chlorine dioxide Seakleen (Vitamin K)
No. 64
Electrolysis / Electro-chlorination
Working method Electric current will be
applied to the BW within an electrolytic chamber in sea water, will be split to active Chlorine, which disinfects the water
No. 65
Technical constraints
(voyage length to be considered)
Controlled atmosphere in
tanks is needed to avoid reoxygenation (pressure vales instead of common airpipe heads for BW tanks)
No. 66
BW Treatment systems shall Systems that make use of an Certification by Flag State (or
authorized Classification Society)
Res.MEPC.125(53)
GUIDELINES FOR APPROVAL OF BALLAST WATER MANAGEMENT SYSTEMS (G8)
Approval by IMO
Res.MEPC.126(53)
PROCEDURE FOR APPROVAL OF BALLAST WATER MANAGEMENT SYSTEMS THAT MAKE USE OF ACTIVE SUBSTANCES (G9)
No. 67
Certificate
Ballast Water Management No. 68
No. 69
Based on a sample vessel with 5000 m BW capacity and flow rate of 300 m/hr
No. 70
Every Ballast Water Treatment Systems is to be type approved by the Flag State Administration Systems that make use of an active substance are subject to an additional certification which includes Basic Approval and Final Approval by IMO
No. 71
this corresponds
to 0.3% of total CO2 from ships
No. 72
No. 74
Operational cost
No. 75
Arrangement in the engine room alternatively separate module on weather deck or in hold Second treatment interferes with discharge by gravity (e.g. for bulk carriers) IN-LINE treatment shall not interfere with cargo operations in harbour IN-TANK treatment shall not interfere with voyage schedule/routing
No. 76
No. 77
Problems to be solved
Proof of compliance with D-2 standard during the type
approval process
Definition of size and power supply for a system Application for all types/sizes of vessels Arrangement on existing vessels Storage of consumables/additives Is a re-design of the piping system necessary? Costs (installation/maintenance)
Ballast Water Management No. 78
Ballast Water Management Part 9 Ballast Water Isolation and Risk Assessment
Exchange
Treatment
Isolation
Sequential
Flow-through
Mechanical
Physical
Chemical
Reception facilities
Return to origin
Dilution
Retention on board
No. 80
Unlikely that ports will provide such facilities Extended time span at designated discharge point
No. 81
Shifting of BW from one tank to another is possible Thorough planning necessary Not applicable for tank vessels, bulk carriers
Ballast Water Management No. 82
No. 83
Exchange
Treatment
Isolation
Sequential
Flow-through
Mechanical
Physical
Chemical
Reception facilities
Return to origin
Dilution
Retention on board
No. 84
No. 85
Risk assessment
Risk assessment as first step for any country
contemplating a formal watch-system
No. 86
No. 87
United Kingdom
Israel
USA
mandatory from 2004-09-27
Australia
Victoria, mandatory from 2004-07-01
New Zealand
No. 89
2006-05
State of Victoria 2004-07-01 Argentina (Buenos Aires) 1990 Brazil 2005-10-15 Canada 2006-06-08 Chile 1995-08-10 Egypt Israel 1996-07-19 New Zealand 2004-04-01 Norway (2009-01-01) NW Europe ( 2007-09)
No. 90
No. 91
No. 92
http://canadagazette.gc.ca/partII/2006/20060628/html/sor129-e.html https://www.tc.gc.ca
No. 93
http://www.daffa.gov.au/fisheries/inva
sive/national-system
No. 94
No. 95
of a certain size of a certain size factor 100 Less than 1 living organism per Less than 10 viable organisms per
1 m greater than 50m factor 100 Less than 10 viable organisms per 1 ml smaller than 50m and greater than 10m Limited number of indicator microbes
1 CFU Vibrio cholera per 100 ml 250 CFU eschericia coli per 100 ml 100 CFU enterocci per 100 ml
factor 2 factor 3
10 m greater than 50m Less than 1 viable organisms per 10 ml smaller than 50m and greater than 10m Limited number of indicator microbes
1 CFU Vibrio cholera per 100 ml 126 CFU eschericia coli per 100 ml 33 CFU enterocci per 100 ml
No. 96
Regional Regulation in EU
BWM strategies for North West Europe and for Baltic Sea under
development
Subdivision in geopolitical-regions and bio-regions Assumption that inside a bioregion aquatic organisms are
spread out already (or can spread out naturally)
No. 97
Application:
once entered into force: applicable to ships on international voyage, that carry
ballast water for existing ships (built before 01 January 2009) retrofitting of ballast water treatment system will be required
No. 99
No. 100
Repeat
Article 9 Inspection of ship by PSC
Verifying Certificates Checking of Water Ballast Record Book Sampling of ships water ballast
Note: Repeat, the time required to analyze the samples shall not be used as a basis for unduly delaying the operation movement or departure of the ship.
No. 101
Remember(1)
Documentation side: Reg. B1 Ballast Water Management Plan
AND
No. 102
Remember (2)
Operation side:
OR
No. 103
Remember (3)
Enforcement side:
Reg.E1 Survey
Initial, annual, intermediate and renewal AND
Reg.E2 Certification
Issuance and endorsement
No. 104
No. 105
Contact
Germanischer Lloyd GL Academy Singapore 83 Clemenceau Avenue #13-05 UE Square (S)239920 Phone: +65 835 9714 Fax.: +65 887 4526 gl-academy-singapore@gl-group.com http://www.gl-group.com/glacademy
No. 106
No. 107