Beruflich Dokumente
Kultur Dokumente
Prepared for
Millennium Challenge Corporation
875 15th Street, N.W.
Washington, DC 20005
Prepared by
ICF International
9300 Lee Highway
Fairfax, VA 22031
and
CORE International, Inc.
5101 Wisconsin Avenue, N.W., Suite 305
Washington, DC 20016
10-010
blank
page
Table of Contents
Annex 10: Costing Model, Project Packaging, and Cost Estimates ..................................... 1
Introduction .......................................................................................................................... 1
Costing Model and Methodology for Developing Costs ........................................................ 1
Project Packaging ................................................................................................................ 7
Annex 10.1: Technical/Engineering Project Cost Estimates for Individual Projects..........11
Annex 10.2: Cost Estimates for Project Packages ...............................................................55
Annex 10.3: Project-Level Cost Estimates for Weed Management, Sediment Control,
Environmental Mitigation, and Resettlement ........................................................57
Weed Management and Sediment Control Costs ............................................................... 57
Environmental Mitigation Costs .......................................................................................... 63
Resettlement Costs ............................................................................................................ 73
List of Exhibits
Exhibit 1: An Example for the Build Up of the Costs for the Upgrade and Rehabilitation
of the Bwengu 66/33-kV Substation.......................................................................................................... 3
Exhibit 2. Constant Cost Element Percentages.............................................................................................................. 4
Exhibit 3: Historic US$/ZAR Exchange Rate .................................................................................................................. 6
Exhibit 4: Composition of Project Packages ................................................................................................................... 9
Exhibit 5: Weed Management Project Costs ................................................................................................................ 57
Exhibit 6: Sediment Management Project Costs .......................................................................................................... 61
Exhibit 7: Nkula A Environmental Mitigation Costs....................................................................................................... 64
Exhibit 8: Environmental Mitigation Costs by Project ................................................................................................... 68
Exhibit 9: Resettlement Compensation Costs by Project ............................................................................................. 76
The Project Number and Project Description are shown at the top of the document.
Column A includes the Equipment Description of individual pieces of equipment included
in the project.
Columns B and C include the Quantity of assets and Unit applied, respectively.
Column D includes the price of the equipment, and is entitled Materials and Equipment
(Including Transport, Insurance, Storage, Handling, and Clearing Charges). This
column includes the delivered price of the assets and can be broken down as follows:
Ex-Works price of equipment
Transport, insurance, storage, handling, and clearing charges
Earthing and bonding
Civil component
Busbar system
Exhibit 1: An Example for the Build Up of the Costs for the Upgrade and Rehabilitation of the Bwengu 66/33-kV Substation
Project No: 6005 TSN Bwengu 66/33kV Substation (equipment removed to fit on 8 x 11 page – SAMPLE ONLY) Contingency: XX%
(Including Contingency)
Installation, Commissioning,
Equipment Description
(Including Contingency)
(Including Contingency)
(Including Contingency)
(Including Contingency)
and Site Establishment
(Without Contingency)
and Clearing Charges)
EPC Cost
EPC Cost
Unit
Qty
A B C D E F G H I J K L M
CB_33kV 1 ea $XXX $XXX $XXX $XXX $XXX $XXX $XXX $XXX $XXX $XXX
Isolator + e/s_33kV 3 ea $XXX $XXX $XXX $XXX $XXX $XXX $XXX $XXX $XXX $XXX
CT_1p_33kV 3 ea $XXX $XXX $XXX $XXX $XXX $XXX $XXX $XXX $XXX $XXX
SA_33kV_1p 3 ea $XXX $XXX $XXX $XXX $XXX $XXX $XXX $XXX $XXX $XXX
VT_1p_33kV 3 ea $XXX $XXX $XXX $XXX $XXX $XXX $XXX $XXX $XXX $XXX
Project Totals SAMPLE ONLY SAMPLE ONLY
Price Contingencies
In the power engineering industry, price contingencies vary from project to project based on the
level of uncertainty and risk associated with the project. For example, a project to replace an existing
transformer at a substation does not pose as much risk as a project to refurbish turbines at the
Nkula A power plant. The risk associated with the Nkula A turbine rehabilitation/refurbishment
project is clearly higher because one can develop accurate pricing only by shutting down the plant
and physically inspecting the turbine. The same consideration applies to other projects. The
discussion below provides our assumptions about contingencies for different types of rehabilitation
and upgrade projects based on standard industry practices.
Overhead Line Contingency—XXX Percent
Access to the line route
Soil conditions
Route length inaccuracy
Unforeseen deviations of the line route
Changes in conductor sizes or types
Contractor capacity
Equipment manufacturer capacity
Security enhancement
Occupied servitude
Availability of materials in Malawi
Underground services
Bush clearing.
Substation Contingency—XXX Percent
Access to site
Soil conditions
System configuration
Building material available in Malawi
Contractor capacity
Equipment manufacturer capacity
Security enhancement.
Underground Cables— XXX Percent
Soil and ground conditions
Excessive rock
Site access
Underground services
Unforeseen route deviation
Contractor capacity
Equipment manufacturer capacity
Security enhancement
Occupied servitude.
SCADA Contingency—XXX Percent
Substation building constraints
Final number of I/O (inputs and outputs required)
Contractor capacity
Equipment manufacturer capacity
Security enhancement
Final extent of system
Finalization of detailed design
Suitability of radio communications in certain instances.
Hydro Generation Contingency—XXX Percent
Condition of all components—extent of refurbishment
Condition of plant infrastructure
Contractor capacity
Parts and equipment refurbishment—factory capacity
Unforeseen commissioning issues.
Alternative options have been priced only for the overhead transmission line because of the
large scope of work and large capital cost.
The outline designs produced for the Malawi projects are proven and extensively used in many
southern African countries, including Malawi, Namibia, South Africa, Botswana, Mozambique, and
Zambia. The designs comply with local and international standards and internationally accepted
standards that have been utilized extensively in southern Africa over the past decades.
The costing model is based on an actual cost approach for all distribution and substation work.
All pricing was obtained in South African Rand (ZAR) and was converted to U.S. dollars at an
exchange rate of 7 to 1 taking into consideration the historic fluctuations in the US$/ZAR
exchange rate (see Exhibit 3). All prices are based on material and labor costs as of March
2010 and are subject to indices, including (but not limited to) labor, metal, zinc, aluminum,
cement, road freight, and fuel indices. Historic US$/ZAR exchange rate is shown in Exhibit 3.
One of the key drivers to developing the cost estimates for the recommended projects was that our
costing experts routinely bid such jobs all over Africa and internationally under the Engineer,
Procure, and Construct (EPC) approach for tendering. Accordingly, the cost estimates proposed by
the ICF/CORE team will withstand industry benchmarks and tests in terms of their reasonableness.
The percentages associated with the equipment related costs do not show a direct correlation to
the equipments’ Ex Works price due to the method in which the costing is calculated. A High Ex
Works price will usually result in a lower percentage.
The prices are expressed per kilometer of transmission line but include all overhead and site
establishment costs, and as such cannot be used out of context of the specific project. Because
of the specialized nature of transmission line construction, pricing can vary massively depending
on the level of interest from the international line construction companies, which is invariably
linked to their individual order books. Additional outline engineering is required to refine the
costs, and this engineering ideally should be completed once the system study has confirmed
the suitability of the assumed parameters.
The information and material used in this report with regard to transmission line
recommendations are sourced from the records and archives of Merz and McLellan, the lead
engineers in the ICF/CORE team combined with our experience in the transmission line sector
over the past few decades.
All pricing was obtained in ZAR and was converted to U.S. dollars at an exchange rate of 7 to 1.
All prices are based on material and labor costs as of March 2010 and are subject to indices,
including (but not limited to) labor, metal, zinc, aluminum, cement, road freight, and fuel indices.
Project Packaging
As the study evolved from the Interim Technical Assessment, to Draft and Final Feasibility
stages the project packaging was modified to best serve the objectives of the given stage as
described in Section 1 of the main report.
MCC’s overall Compact budget is fixed at $XXX including all capacity building, project-related
technical assistance, and program administration costs. Accordingly, MCC, MCA-M, ESCOM,
and the ICF/CORE Team representatives held discussions on July 22-23, 2010 to prioritize the
individual projects and develop a new set of technically sound and high priority projects based
on both the additional load flow studies and the constraints of the MCC budget. This exercise
resulted in the development of a total of 7 final project packages for further detailed costing and
economic and financial analysis. Exhibit 4 provides the composition of the final 7 packages that
were analyzed for the Final Feasibility Report.
Exhibit 4 provides a composition of each project package based on the project numbers
assigned by the ICF/CORE team based on its numbering convention (Annex 1 of this Final
Feasibility Study Report) to individual subprojects listed in Annex 1 of the MCC RFP.
10-010
Project Totals
Project Totals
Project No: 7096 DCN
Cable_185mm_3Core_Cu_XLPE_11kV
Qty Qty
Unit Unit
$0.00
500 m $0.00
Storage, Handling, and Clearing Storage, Handling, and Clearing
Charges) Charges)
$0.00
$0.00
Katoto - Existing OHL UGC
$0.00
$0.00
$0.00
$0.00
Contingency Contingency
11
Karonga S/S - Existing OHL (Ref. 7082 DSN) UGC
FINAL
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00 Contingency)
$0.00
$0.00
Contingency) Contingency)
Contingency)
$0.00
$0.00
Contingency)
$0.00
$0.00
Contingency:
Contingency:
$0.00
$0.00
10-010
Project Totals
Project Totals
Unit Unit
Materials and Equipment Materials and Equipment
(Including Transport, Insurance, (Including Transport, Insurance,
$0.00
640 m $0.00
$0.00
600 m $0.00
$0.00
$0.00
$0.00
$0.00
Sharpe road - ABS 249 UGC
$0.00
$0.00
$0.00
$0.00
Contingency Contingency
12
FINAL
$0.00
$0.00
$0.00
$0.00
Contingency:
Contingency:
10-010
Project Totals
Project Totals
$0.00
1000 m $0.00
(Including Transport, Insurance,
$0.00
200 m $0.00
Site Establishment
$0.00
$0.00
Site Establishment
$0.00
$0.00
Zomba 1L5 - ABS 804 UGC
$0.00
$0.00
$0.00
$0.00
Contingency
13
Contingency
FINAL
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
Contingency)
$0.00
$0.00
Contingency:
Contingency:
Contingency)
$0.00
$0.00
10-010
Project Totals
Project Totals
Unit Unit
Materials and Equipment Materials and Equipment
(Including Transport, Insurance, (Including Transport, Insurance,
$0.00
200 m $0.00
$0.00
200 m $0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
14
Contingency Contingency
FINAL
$0.00
$0.00
$0.00
$0.00
Contingency:
Contingency:
10-010
Project Totals
Project Totals
8
Qty
Qty
Unit
Materials and Equipment Unit
(Including Transport, Insurance,
$0.00
km $0.00
Materials and Equipment
2
Storage, Handling, and Clearing (Including Transport, Insurance,
$0.00
200 m $0.00
$0.00
$0.00
Installation, Commissioning, and
Site Establishment
$0.00
$0.00
Zomba 5L5 - ABS 804 UGC
$0.00
$0.00
$0.00
$0.00
Contingency
15
Contingency
FINAL
$0.00
$0.00
$0.00
$0.00
Contingency)
$0.00
$0.00
Contingency)
$0.00
$0.00
Contingency)
$0.00
$0.00
Contingency)
$0.00
Contingency:
Contingency:
Contingency)
$0.00
$0.00
10-010
Project Totals
Project Totals
8
4
Qty Qty
Unit Unit
Materials and Equipment Materials and Equipment
(Including Transport, Insurance,
$0.00
km $0.00
(Including Transport, Insurance,
$0.00
km $0.00
33 kV 175mm2 OHL
33 kV 175mm2 OHL
$0.00
$0.00
Site Establishment
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
Contingency Contingency
16
$0.00
$0.00
FINAL
$0.00
$0.00 EPC Cost (including EPC Cost (including
Contingency) Contingency)
$0.00
$0.00
$0.00
$0.00
Unit Cost Breakdown
Unit Cost Breakdown
Contingency)
$0.00
$0.00
Contingency)
$0.00
$0.00
$0.00
Contingency:
Contingency:
10-010
Project Totals
Project Totals
Project No: 7072 DLC
OHL_33kV_'T'-Wood_ACSR_Wolf_SC
7
6
Qty Qty
Unit Unit
$0.00
km $0.00
2
2
Storage, Handling, and Clearing Storage, Handling, and Clearing
Charges)
Charges)
33 kV 175mm OHL
33 kV 175mm OHL
Kauma - Chatata OHL
Site Establishment
$0.00
$0.00
Site Establishment
$0.00
$0.00
EPC Cost (without Contingency) EPC Cost (without Contingency)
$0.00
$0.00
$0.00
$0.00
Contingency Contingency
17
$0.00
$0.00
FINAL
$0.00
$0.00
$0.00
$0.00
Annex 10: Costing Model, Project Packaging, and Cost Estimates
Malawi Power System Project Studies: Final Feasibility Study Report
Contingency)
$0.00
$0.00
Contingency)
$0.00
$0.00
Contingency:
Contingency:
$0.00
$0.00
10-010
Project Totals
Project Totals
Project No: 7074 DLC
OHL_33kV_'T'-Wood_ACSR_Dog_SC
Qty
2
Qty
Unit
Unit
Materials and Equipment
Materials and Equipment (Including Transport, Insurance,
$0.00
10 km $0.00
2
$0.00
km $0.00
Storage, Handling, and Clearing
Storage, Handling, and Clearing Charges)
33 kV 175mm OHL
Charges)
Installation, Commissioning, and
Kanengo - Area 25 OHL
33 kV Up-Rating 100mm2
Site Establishment
$0.00
$0.00
Bwengu - Phwezi Turn off OHL
$0.00
$0.00
Contingency Contingency
18
FINAL
$0.00
$0.00
$0.00
$0.00
EPC Cost (including EPC Cost (including
Contingency) Contingency)
$0.00
$0.00
$0.00
$0.00
Unit Cost Breakdown
$0.00
$0.00
Contingency)
$0.00
$0.00
$0.00
Contingency:
Contingency:
Contingency)
$0.00
$0.00
10-010
Project Totals
Project Totals
Asset Description
OHL_33kV_'T'-Wood_ACSR_Wolf_SC
Unit Unit
Materials and Equipment Materials and Equipment
2
(Including Transport, Insurance, (Including Transport, Insurance,
$0.00
20.6 km $0.00
$0.00
3.5 km $0.00
33 kV 175mm OHL
Charges) Charges)
$0.00
$0.00
Karonga - Songwe Turn off OHL
$0.00
$0.00
Contingency Contingency
19
$0.00
$0.00
FINAL
$0.00
$0.00 EPC Cost (including EPC Cost (including
Contingency) Contingency)
$0.00
$0.00
$0.00
$0.00
Unit Cost Breakdown
$0.00
$0.00
Malawi Power System Project Studies: Final Feasibility Study Report
Contingency)
$0.00
$0.00
Contingency)
$0.00
Contingency:
Contingency:
$0.00
$0.00
10-010
Project Totals
Project No: 7035 DLS
Contingency
20
$0.00
$0.00
FINAL
EPC Cost (including
Contingency)
$0.00
$0.00
Unit Cost Breakdown
Surveys, Preliminary
Engineering, Tender Document,
$0.00
$0.00
Annex 10: Costing Model, Project Packaging, and Cost Estimates
Malawi Power System Project Studies: Final Feasibility Study Report
Surveys, Preliminary
EPC Cost (including
Site Establishment
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency
Charges)
Unit
Qty
TR_10MVA_33kV_11kV_OLTC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_ Panel_Trf_<66kV_&_TCCP 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_33kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_33kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_33kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_33kV_1p 9 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_33kV_Auto_Reclose 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TR_AUX_0.050MVA_33kV_0.4kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cable_240mm_1Core_Cu_XLPE_11kV 600 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cable_185mm_3Core_Cu_XLPE_11kV 300 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV_1250A_25kA_INC_I/D 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV_630A_25kA_FDR_I/D 4 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Fence_Concrete_Palisade 140 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
2
Control_Building 60 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
2
Earthing_Earth_Mat 400 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
2
Substation_Stoning 400 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Surveys, Preliminary
EPC Cost (including
Site Establishment
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency
Charges)
Unit
Qty
Isolator + e/s_33kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_33kV_Auto_Reclose 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_33kV_1p 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Surveys, Preliminary
EPC Cost (including
Site Establishment
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency
Charges)
Unit
Qty
Control_Protection_ Panel_Trf_<66kV_&_TCCP 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_66kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_66kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_66kV_1p 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_66kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV_1250A_25kA_INC_I/D 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV_630A_25kA_FDR_I/D 4 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Battery Charger _ 20A_110V DC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Batteries_110V DC_95Ah 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TR_AUX_0.050MVA_11kV_0.4kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cable_240mm_1Core_Cu_XLPE_11kV 600 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cable_185mm_3Core_Cu_XLPE_11kV 300 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
2
Control_Building 60 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Fence_Concrete_Palisade 140 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
2
Earthing_Earth_Mat 400 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
2
Substation_Stoning 400 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project No: 7066 DSC New Lilongwe City Centre 33/11kV Substation Contingency:
Unit Cost Breakdown
Surveys, Preliminary
EPC Cost (including
Site Establishment
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency
Charges)
Unit
Qty
TR_10MVA_33kV_11kV_OLTC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_ Panel_Trf_<66kV_&_TCCP 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_33kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_33kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_33kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_33kV_1p 9 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_33kV_Auto_Reclose 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TR_AUX_0.050MVA_33kV_0.4kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cable_240mm_1Core_Cu_XLPE_11kV 600 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cable_185mm_3Core_Cu_XLPE_11kV 300 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV_1250A_25kA_INC_I/D 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV_630A_25kA_FDR_I/D 4 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Fence_Concrete_Palisade 140 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Building 60 m2 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
2
Earthing_Earth_Mat 400 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Substation_Stoning 400 m2 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Surveys, Preliminary
EPC Cost (including
Site Establishment
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency
Charges)
Unit
Qty
CB_33kV_Auto_Reclose 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_33kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_33kV_1p 9 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TR_AUX_0.050MVA_33kV_0.4kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV_1250A_25kA_INC_I/D 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV_630A_25kA_FDR_I/D 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Batteries_110V DC_32Ah 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Battery Charger _ 10A_110V DC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Surveys, Preliminary
EPC Cost (including
Site Establishment
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency
Charges)
Unit
Qty
Isolator + e/s_33kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV_1250A_25kA_INC_I/D 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV_1250A_25kA_B-S_I/D 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV_630A_25kA_FDR_I/D 6 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Building 56 m2 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_33kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_33kV_1p 9 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_33kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_33kV_Auto_Reclose 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Surveys, Preliminary
EPC Cost (including
Site Establishment
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency
Charges)
Unit
Qty
CB_11kV_1250A_25kA_INC_I/D 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV_1250A_25kA_B-S_I/D 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV_630A_25kA_FDR_I/D 7 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Battery Charger _ 10A_110V DC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Batteries_110V DC_32Ah 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
2
Control_Building 100 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Fence_Concrete_Palisade 120 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Earthing_Earth_Mat 900 m2 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
2
Substation_Stoning 900 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Surveys, Preliminary
EPC Cost (including
Site Establishment
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency
Charges)
Unit
Qty
Isolator + e/s_33kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_33kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_33kV_1p 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_33kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TR_10MVA_66kV_33kV_OLTC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_ Panel_Trf_<66kV_&_TCCP 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV_1250A_25kA_INC_I/D 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV_630A_25kA_FDR_I/D 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cable_400mm_1Core_Cu_XLPE_11kV 30 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Battery Charger _ 10A_110V DC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Batteries_110V DC_32Ah 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Surveys, Preliminary
EPC Cost (including
Site Establishment
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency
Charges)
Unit
Qty
TR_10MVA_33kV_11kV_OLTC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_33kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_33kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_33kV 6 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_33kV_Auto_Reclose 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_33kV_1p 18 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_ Panel_Trf_<66kV_&_TCCP 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV_1250A_25kA_INC_I/D 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Building 25 m2 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Earthing_Earth_Mat 900 m2 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Fence_Concrete_Palisade 160 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
2
Substation_Stoning 900 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Surveys, Preliminary
EPC Cost (including
Site Establishment
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency
Charges)
Unit
Qty
TR_10MVA_33kV_11kV_OLTC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_33kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_33kV 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_33kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TR_AUX_0.050MVA_33kV_0.4kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Battery Charger _ 10A_110V DC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Batteries_110V DC_32Ah 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_33kV_1p 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_ Panel_Trf_<66kV_&_TCCP 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cable_400mm_1Core_Cu_XLPE_11kV 100 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Fence_Concrete_Palisade 160 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Surveys, Preliminary
EPC Cost (including
Site Establishment
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency
Charges)
Unit
Qty
TR_5MVA_33kV_11kV_OLTC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_33kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_33kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_33kV_1p 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_33kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV_1250A_25kA_INC_I/D 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV_630A_25kA_FDR_I/D 4 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_Panel_33kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_ Panel_Trf_<66kV_&_TCCP 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Battery Charger _ 10A_110V DC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Batteries_110V DC_32Ah 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TR_AUX_0.1MVA_33kV_0.4kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cable_185mm_3Core_Cu_XLPE_11kV 200 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Building 48 m2 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Earthing_Earth_Mat 100 m2 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Substation_Stoning 120 m2 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Surveys, Preliminary
EPC Cost (including
Site Establishment
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency
Charges)
Unit
Qty
TR_10MVA_33kV_11kV_OLTC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_ Panel_Trf_<66kV_&_TCCP 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_33kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_33kV 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_33kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_33kV_1p 6 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_33kV_Auto_Reclose 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TR_AUX_0.050MVA_33kV_0.4kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
OHL_33kV_'T'-Wood_ACSR_Dog_SC 0.5 km $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_11kV 4 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV_Auto_Reclose 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_11kV_1p 12 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_11kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Battery Charger _ 10A_110V DC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Batteries_110V DC_32Ah 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Building 25 m2 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Earthing_Earth_Mat 900 m2 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Fence_Concrete_Palisade 160 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
2
Substation_Stoning 900 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Surveys, Preliminary
EPC Cost (including
Site Establishment
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency
Charges)
Unit
Qty
CB_11kV_1250A_25kA_INC_I/D 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV_1250A_25kA_B-S_I/D 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV_630A_25kA_FDR_I/D 6 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Battery Charger _ 10A_110V DC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Batteries_110V DC_32Ah 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Surveys, Preliminary
EPC Cost (including
Site Establishment
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency
Charges)
Unit
Qty
TR_10MVA_33kV_11kV_OLTC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_33kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_33kV_Auto_Reclose 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_33kV 4 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_33kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TR_AUX_0.050MVA_33kV_0.4kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Battery Charger _ 10A_110V DC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Batteries_110V DC_32Ah 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_33kV_1p 12 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_ Panel_Trf_<66kV_&_TCCP 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_11kV 5 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV_Auto_Reclose 4 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_11kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_11kV_1p 15 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Fence_Concrete_Palisade 300 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Surveys, Preliminary
EPC Cost (including
Site Establishment
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency
Charges)
Unit
Qty
CB_33kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_33kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_33kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_11kV_1p 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_ Panel_Trf_<66kV_&_TCCP 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV_1250A_25kA_INC_I/D 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV_630A_25kA_FDR_I/D 4 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TR_AUX_0.050MVA_11kV_0.4kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Battery Charger _ 10A_110V DC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Batteries_110V DC_32Ah 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cable_185mm_3Core_Cu_XLPE_11kV 100 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Building 48 m2 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Earthing_Earth_Mat 40 m2 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Substation_Stoning 100 m2 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Surveys, Preliminary
EPC Cost (including
Site Establishment
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency
Charges)
Unit
Qty
TR_10MVA_33kV_11kV_OLTC 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_ Panel_Trf_<66kV_&_TCCP 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_33kV 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_33kV 5 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_33kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_33kV_1p 12 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_33kV_Auto_Reclose 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TR_AUX_0.050MVA_33kV_0.4kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cable_400mm_1Core_Cu_XLPE_11kV 900 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Surveys, Preliminary
EPC Cost (including
Site Establishment
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency
Charges)
Unit
Qty
Nkula_A_Uprate_and_Refurbishment 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Surveys, Preliminary
EPC Cost (including
Site Establishment
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency
Charges)
Unit
Qty
Comms_Fibre_Blantyre_Main_To_Chichiri_UGC 1 Lot $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Comms_Fibre_Blantyre_Main_To_Customs_UGC 1 Lot $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Comms_Fibre_Nkula_To_Headpond_ADSS 1 Lot $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Comms_Fibre_Tedzani_To_Headpond_ADSS 1 Lot $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Comms_Fibre_Old_Bwengu_To_New_Bwengu_ADSS 1 Lot $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Comms_Fibre_Turn_In_New_Lilongwe 1 Lot $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Comms_Fibre_Turn_In_New_Blantyre 1 Lot $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Comms_Fibre_Indoor_Terminal_Equipment_Type_1 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Comms_PLC_Line_Traps/CVT's/Matching Units 18 per link $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Comms_PLC_Indoor_Terminal_Equipment 18 per link $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Comms_Radio_End_To_End_Link_Complete 37 per link $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
RTU_Basic 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
RTU_Small 6 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
RTU_Medium 48 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
RTU_Large 6 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Batteries_50V DC_95Ah 18 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Battery Charger _ 20A_50V DC 18 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Master_Station_NCC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Master_Station_RCC_South 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Master_Station_RCC_Central 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Master_Station_RCC_North 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Master_Station_GCC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Voice_Exchange 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Voice_Remote_Unit_Type_1 61 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Voice_Remote_Unit_Type_2 28 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
10-010
Project Totals
Project Totals
OHL_66kV_Steel_Pole_ACSR_Lynx_SC
OHL_66kV_Steel_Lattice_ACSR_Lynx_SC
203
203
Unit
km
km
Unit
km
km
Materials and Equipment Materials and Equipment
Lilongwe 66kV OHL
$0.00
$0.00
$0.00
Storage, Handling, and Clearing Storage, Handling, and Clearing
Charges) Charges)
Nkula B-New Lilongwe OHL
66kV Steel Lattice Single Circuit
$0.00
$0.00
$0.00
EPC Cost (without Contingency) EPC Cost (without Contingency)
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
38
FINAL
Contingency Contingency
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
Contingency)
$0.00
$0.00
$0.00
Annex 10: Costing Model, Project Packaging, and Cost Estimates
Surveys, Preliminary
Malawi Power System Project Studies: Final Feasibility Study Report
Surveys, Preliminary
Engineering, Tender Document,
$0.00
$0.00
$0.00
Contingency)
$0.00
$0.00
$0.00
Contingency)
$0.00
$0.00
$0.00
Contingency)
$0.00
$0.00
Contingency:
Contingency:
10-010
Project Totals
Project Totals
Project No: 6001 TLN
OHL_132kV_Steel_Lattice_ACSR_Mulberry_S 60
Qty
Unit Unit
km
km
Materials and Equipment Materials and Equipment
(Including Transport, Insurance,
$0.00
$0.00
$0.00
$0.00
Luwinga-Bwengu OHL
Site Establishment
$0.00
$0.00
Site Establishment
$0.00
$0.00
EPC Cost (without Contingency) EPC Cost (without Contingency)
$0.00
$0.00
$0.00
$0.00
39
Contingency Contingency
FINAL
$0.00
$0.00
$0.00
$0.00
Contingency)
$0.00
$0.00
Unit Cost Breakdown
Surveys, Preliminary
Annex 10: Costing Model, Project Packaging, and Cost Estimates
Surveys, Preliminary
Malawi Power System Project Studies: Final Feasibility Study Report
$0.00
Contingency:
Contingency:
$0.00
$0.00
Project No: 6046 TLN Bwengu 66/33kV - New Bwengu 132/66KV 66 kV OHL Contingency:
66kV Steel Lattice Single Circuit
Unit Cost Breakdown
Surveys, Preliminary
EPC Cost (including
Site Establishment
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency
Charges)
Unit
OHL_66kV_Steel_Lattice_ACSR_Lynx_SC Qty
3 km $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Surveys, Preliminary
EPC Cost (including
Site Establishment
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency
Charges)
Unit
Qty
CB_11kV 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_11kV 8 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV_Auto_Reclose 6 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_11kV_1p 24 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_11kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TR_15MVA_66kV_11kV_OLTC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_ Panel_Trf_<66kV_&_TCCP 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_66kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_66kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_66kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_66kV_1p 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Battery Charger _ 20A_110V DC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Batteries_110V DC_95Ah 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Earthing_Earth_Mat 600 m2 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
2
Substation_Stoning 600 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project No: 6017 TSC New Lilongwe (Nkhoma) 220 /132kV Substation Contingency:
Unit Cost Breakdown
Surveys, Preliminary
EPC Cost (including
Site Establishment
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency
Charges)
Unit
Qty
CB_132kV 9 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_132kV_B/P 4 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_132kV 26 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CT_1p_132kV 21 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_132kV 24 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_132kV_1p 24 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_220kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_220kV_B/P 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_220kV 4 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CT_1p_220kV 9 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_CVT/LineTrap_1p_220kV 6 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_220kV_1p 9 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_ Panel_Trf_220kV_&_TCCP 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_Panel_220kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TR_100MVA_132kV_220KV_OLTC_AUTO 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_66kV 7 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_66kV 12 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CT_1p_66kV 12 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_66kV_1p 18 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_66kV 12 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_33kV_Auto_Reclose 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_33kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_33kV 7 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CT_1p_33kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_33kV 12 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_33kV_1p 15 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TR_15MVA_66kV_33kV_OLTC 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TR_40MVA_132kV_66kV_OLTC_AUTO 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TR_AUX_0.1MVA_33kV_0.4kV 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_Panel_132kV 4 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_Panel_66kV 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_ Panel_Trf_<66kV_&_TCCP 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_ Panel_Trf_132kV_&_TCCP 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Bus-Zone_Protection_Panel 4 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Bus-Section/Coupler_Protection_Panel 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Batteries_110V DC_95Ah 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Battery Charger _ 20A_110V DC 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
OHL_132kV_Steel_Lattice_ACSR_Parakeet_DC 2 km $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
OHL_66kV_Steel_Lattice_ACSR_Lynx_SC 21 km $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Fence_Concrete_Palisade 640 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
2
Substation_Stoning 2500 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Earthing_Earth_Mat 3000 m2 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
2
Control_Building 195 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project No: 6027 TSC Lilongwe A / Old Town 66/11kV Substation Contingency:
Unit Cost Breakdown
Surveys, Preliminary
EPC Cost (including
Site Establishment
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency
Charges)
Unit
Qty
CB_11kV_1250A_25kA_INC_I/D 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV_1250A_25kA_B-S_I/D 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV_630A_25kA_FDR_I/D 7 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Batteries_110V DC_32Ah 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Battery Charger _ 10A_110V DC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_ Panel_Trf_<66kV_&_TCCP 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Surveys, Preliminary
EPC Cost (including
Site Establishment
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency
Charges)
Unit
Qty
CB_66kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_66kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_66kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_66kV_1p 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TR_15MVA_66kV_33kV_OLTC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_ Panel_Trf_<66kV_&_TCCP 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Disturbance_Recorder 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_ Panel_Trf_132kV_&_TCCP 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_Panel_132kV 4 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Bus-Section/Coupler_Protection_Panel 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_33kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_33kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_33kV_Auto_Reclose 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_33kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_33kV_1p 9 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cable_185mm_3Core_Cu_XLPE_33kV 100 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Surveys, Preliminary
EPC Cost (including
Site Establishment
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency
Charges)
Unit
Qty
CB_66kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_66kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_66kV_1p 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_66kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TR_15MVA_66kV_33kV_OLTC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_ Panel_Trf_<66kV_&_TCCP 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Bus-Zone_Protection_Panel 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_33kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_33kV 4 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_33kV_1p 12 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_33kV_Auto_Reclose 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_33kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TR_AUX_0.050MVA_33kV_0.4kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Substation_Stoning 900 m2 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Surveys, Preliminary
EPC Cost (including
Site Establishment
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency
Charges)
Unit
Qty
TR_10MVA_66kV_11kV_OLTC 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_ Panel_Trf_<66kV_&_TCCP 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_11kV 4 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV_Auto_Reclose 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_11kV_1p 9 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_66kV 4 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_66kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_Panel_66kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_66kV 8 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_66kV_1p 12 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CT_1p_66kV 6 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
OHL_66kV_Steel_Lattice_ACSR_Lynx_SC 0.4 km $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Surveys, Preliminary
EPC Cost (including
Site Establishment
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency
Charges)
Unit
Qty
CB_132kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_132kV 4 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_132kV_B/P 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CT_1p_132kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_132kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_132kV_1p 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Capacitor_5MVAr 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV_2000A_31.5kA_INC_I/D 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cable_185mm_3Core_Cu_XLPE_11kV 100 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_Panel_132kV 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_Panel_66kV 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_66kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TR_5MVA_33kV_11kV_OLTC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cable_185mm_3Core_Cu_XLPE_33kV 1000 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_33kV_Auto_Reclose 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV_Auto_Reclose 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_ Panel_Trf_<66kV_&_TCCP 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Surveys, Preliminary
EPC Cost (including
Site Establishment
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency
Charges)
Unit
Qty
CB_33kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_33kV 4 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_33kV_1p 12 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_33kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_33kV_Auto_Reclose 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV_1250A_25kA_INC_I/D 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV_1250A_25kA_B-S_I/D 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_11kV_630A_25kA_FDR_I/D 4 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cable_185mm_3Core_Cu_XLPE_11kV 300 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_132kV 4 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_132kV 12 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_132kV_B/P 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CT_1p_132kV 9 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_132kV 12 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_132kV_1p 9 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TR_25MVA_132kV_33KV_OLTC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Batteries_110V DC_95Ah 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Battery Charger _ 20A_110V DC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
2
Substation_Stoning 1800 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Building 12 m2 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_Panel_132kV 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Bus-Section/Coupler_Protection_Panel 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_ Panel_Trf_132kV_&_TCCP 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Surveys, Preliminary
EPC Cost (including
Site Establishment
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency
Charges)
Unit
CB_33kV Qty
1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_33kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CT_1p_33kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_33kV_1p 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_33kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_Panel_33kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cable_185mm_3Core_Cu_XLPE_11kV 600 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
2
Substation_Stoning 625 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Surveys, Preliminary
EPC Cost (including
Site Establishment
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency
Charges)
Unit
Qty
CB_132kV 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_132kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_132kV_B/P 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CT_1p_132kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_132kV 6 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_132kV_1p 6 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TR_25MVA_132kV_66KV_OLTC_AUTO 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TR_AUX_0.050MVA_132kV_0.4kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_ Panel_Trf_132kV_&_TCCP 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_Panel_132kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_Panel_66kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Batteries_110V DC_95Ah 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Battery Charger _ 20A_110V DC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Fence_Concrete_Palisade 200 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Substation_Stoning 625 m2 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Building 66 m2 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_66kV 6 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_66kV_1p 6 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CT_1p_66kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_66kV 4 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_66kV 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Surveys, Preliminary
EPC Cost (including
Site Establishment
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency
Charges)
Unit
Qty
CB_66kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_66kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_66kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_66kV_1p 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TR_15MVA_66kV_33kV_OLTC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_ Panel_Trf_<66kV_&_TCCP 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_33kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_33kV 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_33kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_33kV_1p 6 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_33kV_Auto_Reclose 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Surveys, Preliminary
EPC Cost (including
Site Establishment
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency
Charges)
Unit
Qty
CB_132kV 5 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_132kV 14 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_132kV_B/P 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CT_1p_132kV 9 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_132kV 12 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_132kV_1p 12 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_66kV 11 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_66kV 24 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CT_1p_66kV 24 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_66kV_1p 30 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_66kV 24 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_33kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_33kV_Auto_Reclose 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_33kV 7 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CT_1p_33kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_33kV 12 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_33kV_1p 15 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TR_40MVA_132kV_66kV_OLTC_AUTO 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TR_15MVA_66kV_33kV_OLTC 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TR_AUX_0.1MVA_33kV_0.4kV 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_Panel_132kV 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_Panel_66kV 6 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_ Panel_Trf_132kV_&_TCCP 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_ Panel_Trf_<66kV_&_TCCP 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Bus-Zone_Protection_Panel 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Bus-Section/Coupler_Protection_Panel 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Batteries_110V DC_95Ah 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Battery Charger _ 20A_110V DC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Battery Charger _ 20A_50V DC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Batteries_50V DC_95Ah 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
OHL_132kV_Steel_Lattice_ACSR_Parakeet_SC 20 km $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
OHL_66kV_Steel_Lattice_ACSR_Lynx_SC 20 km $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Fence_Concrete_Palisade 400 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Substation_Stoning 1600 m2 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
2
Earthing_Earth_Mat 1700 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Building 130 m2 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Surveys, Preliminary
EPC Cost (including
Site Establishment
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency
Charges)
Unit
Qty
CB_66kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_66kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_66kV_1p 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TR_10MVA_66kV_33kV_OLTC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_ Panel_Trf_<66kV_&_TCCP 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_33kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_33kV 6 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_33kV_Auto_Reclose 5 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_33kV_1p 18 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Battery Charger _ 10A_110V DC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Batteries_110V DC_32Ah 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_33kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
2
Control_Building 25 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Fence_Concrete_Palisade 200 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
OHL_33kV_'T'-Wood_ACSR_Dog_SC 0.2 km $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Surveys, Preliminary
EPC Cost (including
Site Establishment
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency
Charges)
Unit
Qty
CB_33kV_Auto_Reclose 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_33kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_33kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TR_15MVA_66kV_33kV_OLTC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Battery Charger _ 10A_110V DC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Batteries_110V DC_32Ah 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_33kV_1p 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
2
Substation_Stoning 1600 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
OHL_33kV_'T'-Wood_ACSR_Dog_SC 0.8 km $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_ Panel_Trf_<66kV_&_TCCP 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Surveys, Preliminary
EPC Cost (including
Site Establishment
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency
Charges)
Unit
Qty
CB_132kV 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_132kV 4 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CT_1p_132kV 6 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_1p_132kV 6 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_132kV_1p 6 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CB_220kV 3 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_220kV_B/P 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Isolator + e/s_220kV 4 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
CT_1p_220kV 9 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
VT_CVT/LineTrap_1p_220kV 6 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
SA_220kV_1p 9 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_ Panel_Trf_220kV_&_TCCP 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Control_Protection_Panel_220kV 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Bus-Zone_Protection_Panel 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TR_AUX_0.1MVA_132kV_0.4kV 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
2
Control_Building 65 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Fence_Concrete_Palisade 240 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Substation_Stoning 900 m2 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
2
Earthing_Earth_Mat 3000 m $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Battery Charger _ 20A_110V DC 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Batteries_110V DC_95Ah 1 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
TR_100MVA_132kV_220KV_OLTC_AUTO 2 ea $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Project Totals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
ROW Compensation
Surveys, Preliminary
Project Management
Document, Contract
Environmental Cost
Capacity Building
Compact Budget
Escalation (MCC)
Package Number
Supervision, and
Cost (including
Administration
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
and Program
Contingency
Total Cost
(including
(including
(MCC)
$0 Mil
Costs
Nkula A
1 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
5001 Nkula A Power Plant $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
2 Weed and Sediment Management $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
3001 Additional harvester for Liwonde Barrage $0.00 $0.00 $0.00 $0.00
3002 Trash Diversion Barrier for Nkula Headpond $0.00 $0.00 $0.00 $0.00
3003 Trash Diversion Barrier Tedzani Headpond $0.00 $0.00 $0.00 $0.00
3004 Trash Diversion Barrier for Kapichira Headpond $0.00 $0.00 $0.00 $0.00
4001 Dredger for Kapichira $0.00 $0.00 $0.00 $0.00
4002 Dredger for Tedzani $0.00 $0.00 $0.00 $0.00
4003 Rehabilitation of Dredger for Nkula $0.00 $0.00 $0.00 $0.00
3 South and Central Transmission Backbone $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
6012 Lilongwe 66kV OHL $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
6017 New Lilongwe (Nkhoma) 220 /132kV Substation $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
6018 New Blantyre Substation $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
6048 Nkula B 132/220kV Substation $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
6050 Nkula B-New Lilongwe 220kV OHL $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
4 North Transmission Backbone $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
6001 Chintheche-Mzuzu (Luwinga) OHL $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
6003 Luwinga 132/33/11kV Substation $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
6004 Luwinga-Bwengu OHL $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
6045 New Bwengu 132/66kV Substation $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
6046 Bwengu 66/33kV - Bwengu New 66 kV Line $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
5 South and Central Local Transmission and Distribution $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
6014 Area 48 66/11kV Substation $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
6027 Lilongwe A/Old Town 66/11kV Substation $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
6028 LilongweB/Kanengo 132/66/33/11kV Substation $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
6042 Lilongwe C 66/11kV (Barracks) Substation $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
6043 Bunda T/off 66/11kV Substation $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7055 Area 33 33/11kV Substation $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7054 Area 25 33/11kV Substation $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7064 Kang'oma 66/11kV Substation $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7066 New Lilongwe City Centre 33/11kV Substation $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7069 Area 33 - Lilongwe City Centre OHL $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7070 Lilongwe City Centre - Barracks OHL $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7071 Barracks - Kauma OHL $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7072 Kauma - Chatata OHL $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7073 Chatata - Kanengo OHL $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7074 Kanengo - Area 25 OHL $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
6015 Chigumula 66/33k/11V Substation $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
6036 Liwonde 66/33kV Substation $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
6038 Monkey Bay 66/33kV Substation $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7003 Blantyre Main 11kV Substation $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7004 David Whitehead33/11kV Substation $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7005 Limbe A 33/11kV Substation $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7006 Limbe B 33/11kV Substation $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7008 Maldeco 33 /11kV Substation $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7012 Ntonda 33/11kV Substation $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7013 Queens 11kV Substation $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7014 Thyolo A 33/11kV Substation $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7015 Thyolo B 33/11kV Substation $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7017 Zomba 33/11kV Substation $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7035 Chigumula 105 - Bangwe 105 OHL $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7045 Sharpe road - ABS 249 UGC $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7048 Limbe 'B' - Unilever UGC $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7049 Zomba 1L5 - ABS 804 UGC $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7050 Zomba 2L5 - ABS 785 UGC $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7051 Zomba 3L5 - ABS 704 UGC $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7052 Zomba 4L5 - ABS 794 UGC $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7053 Zomba 5L5 - ABS 804 UGC $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
6 North Local Transmission and Distribution $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
6002 Chinteche 66/33/11kV Substation (also 7079) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
6005 Bwengu 66/33kV Substation (also 7077) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7082 Karonga 66/33/11kV Substation $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7084 Mzuzu 33/11kV Substation $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7088 Bwengu - Phwezi Turn off OHL $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7089 Karonga - Songwe Turn off OHL $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7100 Karonga S/S - Existing OHL (Ref. 7082 DSN) UGC $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7096 Katoto - Existing OHL UGC $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7118 Mzuzu-Katoto-Luwinga OHL (New) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7 SCADA $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
1000 SCADA - Escom Malawi $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
ROW IMPLEMENTATION AND PLANNING $0.00 $0.00 $0.00 $0.00 $0.00
GRAND TOTAL $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
ROW Compensation
EPC Cost (including Contingency)
Surveys, Preliminary
Project Management
Document, Contract
Environmental Cost
Capacity Building
Compact Budget
Escalation (MCC)
CE Classification
Package Number
Supervision, and
Cost (including
Administration
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
Contingency)
and Program
Contingency
Total Cost
(including
(including
$72 Mil
Year 1
Year 2
Year 3
Year 4
Year 5
Year 1
Year 2
Year 3
Year 4
Year 5
(MCC)
Costs
Nkula A
1 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00
2
Weed and Sediment Management $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 7 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00
3
South and Central Transmission Backbone $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00
4
North Transmission Backbone $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00
5
South and Central Local Transmission and Distribution $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00
6
North Local Transmission and Distribution $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00
7
SCADA $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00
ROW IMPLEMENTATION AND PLANNING $0.00 $0.00 $0.00 $0.00 $0.00 8 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00
GRAND TOTAL $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Surveys, Preliminary Engineering, Tender Document, Contract Supervision, and Project Institutional Capacity Building and Program Administration Costs Environmental Cost (including Contingency) Social and ROW Cost (including Contingency)
Project Description
Package Number
Project Number
Year 1
Year 2
Year 3
Year 4
Year 5
Year 1
Year 2
Year 3
Year 4
Year 5
Year 1
Year 2
Year 3
Year 4
Year 5
Year 1
Year 2
Year 3
Year 4
Year 5
Year 1
Year 2
Year 3
Year 4
Year 5
Year 1
Year 2
Year 3
Year 4
Year 5
Year 1
Year 2
Year 3
Year 4
Year 5
Year 1
Year 2
Year 3
Year 4
Year 5
1 Nkula A 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00
2 Weed and Sediment Management 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00
3 South and Central Transmission Backbone 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00
4 North Transmission Backbone 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00
5 South and Central Local Transmission and Distribution 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00
6 North Local Transmission and Distribution 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00
7 SCADA 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00
ROW IMPLEMENTATION AND PLANNING 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00
GRAND TOTAL $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total (Without MCC Adjustments) MCC Adjustments Total (with MCC Adjustments)
Project Description
Compact Budget
Package Number
Project Number
Year 1
Year 2
Year 3
Year 4
Year 5
Year 1
Year 2
Year 3
Year 4
Year 5
Year 1
Year 2
Year 3
Year 4
Year 5
Year 1
Year 2
Year 3
Year 4
Year 5
$0 Mil
Nkula A
1 $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
2
Weed and Sediment Management $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
3
South and Central Transmission Backbone $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
4
North Transmission Backbone $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
5
South and Central Local Transmission and Distribution $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
6
North Local Transmission and Distribution $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
7
SCADA $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
ROW IMPLEMENTATION AND PLANNING $0.00 $0.00 $0.00 $0.00 $0.00 0% 0% 0% 0% 0% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
GRAND TOTAL $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Annex 10.3: Project-Level Cost Estimates for Weed Management, Sediment Control,
Environmental Mitigation, and Resettlement
Weed Management and Sediment Control Costs
The cost of the weed management and sediment control projects includes preliminary studies, trainings, equipment purchases,
expendable supplies, and additional staff salary (Exhibit 5). The environmental mitigation costs associated with the projects are
included in the estimates for project implementation and operation. All of the recommended projects have been included in the cost.
The total 5-year cost includes the one-time studies or purchases, along with salaries applied starting in year three or four. The
rationale for the weed control projects is provided in Annex 6 and summarized in Section 3. Annex 7 and Section 4 describe the
rationale for the sediment control projects. In some cases, the recommendation in Annex 7 is one or two dredgers based on studies
to be completed. The cost estimate includes two dredgers because this is the more costly option.
Trash Diversion and New Tipper Trucks at Power Stations (Project No. 3002, 3003, and 3004)
Purchase and installation of a 300-meter standard floating trash Nkula, Tedzani,
Trash diversion O $XXX
diversion boom or fixed trash diversion plate; three at $XXX each Kapichira
Nkula, Tedzani,
New tipper truck One for each generation site to improve disposal efficiency O $XXX
Kapichira
Nkula, Tedzani,
Conveyor One for each generation site to improve disposal efficiency O $XXX
Kapichira
Fuel Fuel for the three tipper trucks $XXX
Maintenance Maintenance for the three tipper trucks $XXX
Subtotal $XXX $XXX
Salaries
1 full-time equivalent (FTE) cutter operator, 1 FTE harvester
Liwonde harvesting operations Liwonde Barrage A $XXX
operator, 1 FTE tipper truck operator, 1 FTE maintenance/support
1 full-time equivalent (FTE) cutter operator, 1 FTE harvester
Nkula harvesting operations Nkula A $XXX
operator, 1 FTE tipper truck operator, 1 FTE maintenance/support
1 FTE to work at rearing facility and provide support to application
Biological agent rearing Rearing facility A $XXX
and monitoring team
Tedzani, Kapichira,
Application and monitoring team Team of 4 FTEs to work at all sites A $XXX
Nkula, Liwonde Barrage
Subtotal $XXX $XXX
Tedzani (4002)
Dredge Purchase 300-mm dredge equipment O $XXX
Equipment Piping, flotation, cables, etc. O $XXX
Small dredge Purchase small dredge for use in the "inner" pond O $XXX
Construction Construction of additional disposal area $XXX
Labor 2 FTE A $XXX
Subtotal $XXX $XXX
Kapichira (4001)
Dredge Purchase 300-mm dredge equipment (two dredges) O $XXX
Equipment Piping, flotation, cables, etc. O $XXX
Construction Construction of additional disposal area O $XXX
Labor 2 FTE A $XXX
Subtotal $XXX $XXX
blank
page
rating of the replaced transformer from which the oil would be drained. The unit cost
represents the cost per MVA of transformer capacity.
Transport and disposition of PCB oil-filled small transformers—The costs in this
category reflect the estimated costs to transport PCB-contaminated oil drained from small
transformers to Thermopower Process Technology Ltd in Johannesburg, South Africa for
thermal destruction by incineration. The cost of disposal varies based on the level of PCB
contamination in the oil, so the unit cost is based on oils with five levels of contamination
ranging from less than 50 ppm to greater than 2,000 ppm. Unlike the large transformer cost
above, the small transformer cost does include costs for shipping, dismantling, and
destroying the replaced transformers. The quantities in Exhibit 8 indicate the number of
transformers to be managed at each project site, with the oil quantity based on the amount
of oil in a 200 kVA transformer. The unit cost represents the cost per 200 kVA transformer.
Transport and disposition of PCB oil-filled switchgear—The costs in this category are
estimates for the transport of oil-filled switchgear and its contents to Thermopower Process
Technology Ltd in Johannesburg, South Africa for thermal destruction by incineration. The cost
of disposal varies based on the level of PCB contamination in the oil, so the unit cost is based
on oils with five levels of contamination ranging from less than 50 ppm to greater than 2,000
ppm. The cost includes shipping, dismantling, and destroying the components. The quantities in
Exhibit 8 indicate the number of PCB oil-filled components managed at each project site. The
unit cost was estimated to be 25 percent of the unit cost of managing a 200 kVA transformer.
Erosion control—The primary costs for erosion control are the procurement and installation
of silt fencing or comparable materials to intercept surface runoff, reduce the transport of
exposed soil, and minimize the offsite flow of turbid water. The length of silt fence required
would depend on the type of project. The estimate considers that each transmission line with a
new right-of-way (ROW), including an access road along the entire ROW would require silt
fencing along some percentage of its length plus at the location of every steel lattice tower
foundation. Distribution lines would require less erosion control along the line because a full
access road would not be required, but have more closely spaced support points where
ground disturbance would occur. Because of the shorter span lengths, distribution poles could
also be closer to streams and wetlands. New substations would generally require erosion
protection along one or two sides. Exhibit 8 shows the unit cost for the material and installation
per meter of silt fence and the length of silt fencing required for each project.
Revegetation—Revegetation costs include the costs for labor and materials to plant vetiver
grass at a density of four slips per square meter. Exhibit 8 indicates the area estimated for
revegetation for each project.
Transport and disposition of metal waste—Substations undergoing rehabilitation and
upgrades could have a variety of obsolete equipment removed such as old switchgear,
insulators, cables, gantry components, control panels. PCB oil-filled equipment has been
discussed previously. The rest of the removed equipment will consist primarily of steel,
copper, and aluminum components, with smaller quantities of glass, ceramics, and plastics.
The unit costs for the transport and disposition of metal waste are calculated solely on
transporting the waste materials an average of 400 km. No disposal costs are included
because the scrap metal can be sold at a profit. Any receipts from the sale of the metal
components are assumed to offset the costs of disposal of the materials with no scrap value.
In Exhibit 8, the total environmental mitigation cost for each project is computed by multiplying
the quantity for each mitigation measure by the unit cost for that mitigation measure, summing
the costs for all the mitigation measures, and adding a 10 percent for contingency. This
contingency reflects the uncertainty in actual quantities to be addressed with environmental
mitigation measures, which cannot be specified more precisely until after designs are complete.
The contingency also reflects the uncertainty in actual prices that will be paid for the elements of
the environmental mitigation measures, as these will depend upon final arrangements for
procurement of materials and disposition of waste. The costs in Exhibit 8 do not include
associated costs for engineering design, planning, site supervision or management.
blank
page
Resettlement Costs
The resettlement cost estimates use average values; exact values would be developed during
resettlement planning following design for individual projects. Estimates are based on the
following assumptions.
All land for substations will be acquired outright. Easement agreements will be used where
possible for wayleaves for transmission lines and distribution lines; these easements would
allow cultivation of low annual crops under the lines but no tree crops or residential or business
structures. Up-rating lines will require construction of new support structures. Where
rehabilitation or up-rating cannot be done without additional ROWs to permit safe construction
next to live lines, a strip of ROW will be acquired parallel to existing ROW where possible; for
220kV lines, 30 m; for 132-kV lines, 20 m; for 66-kV lines, 15 m; and for 33-kV and 11kV lines,
7.5 m. Where structures occur next to the current ROW, full new ROW will be acquired.
transmission lines and 80 percent of land along distribution lines is arable; non-arable land
will not require easement agreements or compensation.
Residential or business structures—Residential or business structures that must be
relocated will be replaced in kind or compensated at full replacement value. An average value
of U.S. $XXX per structure is used based on an average between estimates obtained in 2010
for an 8m x 6 m house to be built in the Northern Region and a 13m x 9 m house to be built in
the Central Region. There are no structures at the proposed new substation sites. Where
specific counts were not available, the cost estimates assume 1 residential or business
structure per 10 hectares of transmission line right-of-way, and 1 residential or business
structure per 4 hectares of distribution line right-of-way. These density estimates are based on
compensation data from four ESCOM distribution lines built in 2007 and 2008 and two
transmission lines built in 2000 and 2001; plus observations of the resettlement specialists
along projects 6001, 6004, 6006, 6008, 6010, 6011, 6012.06, 6046, 7035, and 7036.
Moving costs—Moving costs will be provided for each residential or business structure that
must be relocated. An average value of $XXX is used.
Loss of profit—Loss of profit will be compensated for businesses that must be relocated.
An average value of $XXX is used. The cost estimates assume that 1 in every 5 affected
structures along a transmission line and 1 in every 4 affected structures along a distribution
line is a business.
Outlying structures—Outlying structures associated with residential or business structures
such as detached kitchens, granaries, and walls will be compensated at full replacement
value if they must be relocated or if the residential or business structure will be moved so far
that the outlying structures can no longer serve the intended function. An average value of
$XXX per structure is used. The cost estimate assumes 1 outlying structure per residential
or business structure and 1 outlying structure per kilometer of cable.
Perennial crops, crop trees and timber trees—Perennial crops, crop trees, and timber
trees that must be cut will be compensated based on net present value of income over the
period required for newly planted trees and crops to reach production. An average value of
$XXX per tree is used, based on a 2010 government schedule for the Central Region,
consideration of maturation periods for typical crops, and the mix of high value and low
value crops on compensation schedules from four ESCOM distribution lines built in 2007
and 2008 and two transmission lines built in 2000 and 2001. The estimate assumes 24 trees
per hectare of distribution line and transmission line, also based on these ESCOM data.
A 10 percent contingency has been included in the total costs for each project in Exhibit 9. This
contingency reflects the uncertainty in amount and location of land and specific assets that
would be affected, which cannot be specified precisely until after designs are complete. The
contingency also reflects the uncertainty in market values for trees and crops and replacement
values for structures that vary across districts and over time.
In addition to compensation costs, resettlement costs would include approximately $XXX million
for resettlement planning and implementation (developing resettlement action plans as designs
are finalized; implementing relocations and compensation; monitoring). A total resettlement cost
of approximately $XXX million includes the individual project estimates with XXX percent
contingency, plus the $XXX million planning and implementation cost.
blank
page