Beruflich Dokumente
Kultur Dokumente
IMN:BTSE BS-240/240XL
The same text in German: Wichtiger Hinweis zur Produktsicherheit In elektrischen Anlagen stehen zwangslufig bestimmte Teile der Gerte unter Spannung. Einige Teile knnen auch eine hohe Betriebstemperatur aufweisen. Eine Nichtbeachtung dieser Situation und der Warnungshinweise kann zu Krperverletzungen und Sachschden fhren. Deshalb wird vorausgesetzt, dass nur geschultes und qualifiziertes Personal die Anlagen installiert und wartet. Das System entspricht den Anforderungen der EN 60950 / IEC 60950. Angeschlossene Gerte mssen die zutreffenden Sicherheitsbestimmungen erfllen.
Trademarks: All designations used in this document can be trademarks, the use of which by third parties for their own purposes could violate the rights of their owners.
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
Issue History
Issue Number 1 2 3 4 5 6 7 Date of issue Reason for Update
New release BR5.0 added description of TMA mounting revised version of earlier issues additional graphics and specials for BS240U New issue for BR5.5 modified description of installation steps Installation of BS-240XL included
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
Contents
1 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 2 2.1 2.2 2.3 2.4 2.4.1 2.4.2 2.5 2.5.1 2.5.2 2.5.3 2.5.4 2.6 2.6.1 2.6.2 2.6.2.1 2.6.2.2 2.6.2.3 2.6.3 2.6.4 2.6.5 2.6.6 2.7 2.7.1 2.7.2 2.7.3 2.7.4 2.7.5 2.7.6 2.7.7 2.7.8 2.7.9 2.7.10 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Purpose of the Manual . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Tasks of the Base Transceiver Stations . . . . . . . . . . . . . . . . . . . . . . . . . . . Feature Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Types of Base Transceiver Stations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Installation Prerequisites. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Handling of the Modules . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Installation Tools . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Ancillary Material. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Technical Data of BS-240/240XL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . BS-240/240XL Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Position in the System . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Site Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Site Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Construction View of BS-240/240XL. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rack Configurations for BS-240 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rack Configurations for BS-240XL . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Equipment Delivery. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Preliminary Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rack Unpacking . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Devices Unpacking . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rack Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Rack Completion. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Preparation of the Top Cover . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Installation of Backup Batteries. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Installation of Backup Batteries Type Sonnenschein . . . . . . . . . . . . . . . . Installation of Backup Batteries Type Oerlicon. . . . . . . . . . . . . . . . . . . . . Battery Cabling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . DC-Cabling between the Racks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . CAN-Bus Connections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SELIC-Cabling between the Racks. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Installation of Link Equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Setup of System Cabling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . BS-240, 1 Cell with DUAMCO 2:2 (Proposal) . . . . . . . . . . . . . . . . . . . . . . . BS-240, 1 Cell with DUAMCO 4:2 (Proposal) . . . . . . . . . . . . . . . . . . . . . . . BS-240, 2 Cells with DUAMCO 2:2 (Proposal) . . . . . . . . . . . . . . . . . . . . . BS-240, 2 Cells with DUAMCO 4:2 (Proposal) . . . . . . . . . . . . . . . . . . . . . . BS-240, 2 Cells with DUAMCO 2:2/4:2 (Proposal) . . . . . . . . . . . . . . . . . . . BS-240, 3 Cells with DUAMCO 2:2 (Proposal) . . . . . . . . . . . . . . . . . . . . . . BS-240, 3 Cells with DUAMCO 2x2:2, 4:2 (Proposal) . . . . . . . . . . . . . . . . BS-240, 1 Cell with FICOM (Proposal) . . . . . . . . . . . . . . . . . . . . . . . . . . . . BS-240, 2 Cells with FICOM, max 4,4,0 (Proposal) . . . . . . . . . . . . . . . . . . BS-240, 2 Cells with FICOM, max. 2,6,0 (Proposal). . . . . . . . . . . . . . . . . . 11 11 11 11 12 12 12 13 13 14 15 15 15 16 16 18 20 22 22 23 23 23 28 30 31 31 34 35 37 38 39 40 44 49 50 51 52 53 54 55 56 57 58
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
2.7.11 2.7.12 2.7.13 2.7.14 2.7.15 2.8 2.8.1 2.8.2 2.8.3 2.8.4 2.8.5 2.8.5.1 2.8.5.2 2.8.5.3 2.8.6 2.8.7 2.8.8 2.8.9 2.9 3
BS-240XL, 4 Cells with DUAMCO 4:2 (Proposal) . . . . . . . . . . . . . . . . . . . . 59 BS-240XL, 2 Cells with DUAMCO 4:2 (Proposal) . . . . . . . . . . . . . . . . . . . . 60 BS-240XL, 2 Cell with DUAMCO 8:2 (Proposal) . . . . . . . . . . . . . . . . . . . . . 61 BS-240XL, 2 Cell with DUAMCO 8:2 and 4:2 (Proposal). . . . . . . . . . . . . . . 62 Cabling for HPDU Connection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 63 External Cabling Activities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 64 Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 64 Ground and Power Supply Connections 3 x 230 V AC . . . . . . . . . . . . . . . . 67 Ground and Power Supply Connections -48 V DC . . . . . . . . . . . . . . . . . . . 69 Ground and Power Supply Connections BS240U . . . . . . . . . . . . . . . . . . . . 70 Abis-Interface - PCM Link Terminal . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 73 Abis-Interface for 100/120 Ohm Cable Impedance . . . . . . . . . . . . . . . . . . . 73 Abis-Interface for 75 Ohm Cable Impedance. . . . . . . . . . . . . . . . . . . . . . . . 76 Monitoring Interfaces on OVPT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 77 Alarm Collection Terminal - external Signal Sensors. . . . . . . . . . . . . . . . . . 79 Local Maintenance Terminal (LMT) Interface . . . . . . . . . . . . . . . . . . . . . . . 84 Antenna Connections. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85 Installation of the Tower Mounted Amplifier . . . . . . . . . . . . . . . . . . . . . . . . . 87 Post Installation Notes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 90 Abbreviations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 91
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
Illustrations
Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. 1.1 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 2.9 2.10 2.11 2.12 2.13 2.14 2.15 2.16 2.17 2.18 2.19 2.20 2.21 2.22 2.23 2.24 2.25 2.26 2.27 2.28 2.29 2.30 2.31 2.32 2.33 2.34 2.35 2.36 2.37 2.38 2.39 2.40 2.41 2.42 ESD Symbol. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Position of the BS-240/240XL within the SBS . . . . . . . . . . . . . . . . . . . . Site configuration BS-240/240XL. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Types of BS-240 racks. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Configuration of a Service1 rack . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Configuration of Service2 rack . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Types of BS-240XL racks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ShockwatchTM-lable and TiltwatchTM-lable . . . . . . . . . . . . . . . . . . . . . Removal of top cover for crane eye access. . . . . . . . . . . . . . . . . . . . . . Guideline for crane transport . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Space necessary for installation of BS-240/240XL . . . . . . . . . . . . . . . . Removal of fastening claws . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Adjusting of rack feeds. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Fixing variants of BS-240/240XL Rack . . . . . . . . . . . . . . . . . . . . . . . . . Earthquake mounting kit . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Drilling sketch for eartquake mounting kit (2 racks) . . . . . . . . . . . . . . . . Contents of the connection kit . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Setup of EMC sealing stripes. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Connection of the racks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Top cover . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Paint coat retouche of the top cover . . . . . . . . . . . . . . . . . . . . . . . . . . . Battery tray with backup batteries type Sonnenschein . . . . . . . . . . . . Connection of backup batteries . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Contents of the air vent kit . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Connection of backup batteries (Co. Oerlicon) . . . . . . . . . . . . . . . . . . . Air vent system for Oerlicon battery set . . . . . . . . . . . . . . . . . . . . . . . . . Overview of Battery Cabling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Routing of DC cabling between the racks . . . . . . . . . . . . . . . . . . . . . . . Access to the DC terminal block . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Location of CAN-Bus interfaces. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Example for CAN-Bus cable connections . . . . . . . . . . . . . . . . . . . . . . . Location of SELIC interfaces . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SELIC-Cabling between the racks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Overview of microwave cabling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Cabling for link equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Interfaces on frame F:NT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Overview of NTPM cabling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Slot numbering of the BS240 Racks . . . . . . . . . . . . . . . . . . . . . . . . . . . Overview of BS-240XL TX/RX cabling . . . . . . . . . . . . . . . . . . . . . . . . . Example for Configuration Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . Example for Cabling Configuration List . . . . . . . . . . . . . . . . . . . . . . . . . System Cabling DUAMCO 2:2, 1 cell . . . . . . . . . . . . . . . . . . . . . . . . . . System Cabling DUAMCO 4:2, 1 cell . . . . . . . . . . . . . . . . . . . . . . . . . . 13 15 16 18 19 19 20 22 24 24 25 25 26 26 27 27 28 29 29 30 30 32 32 33 34 35 36 37 37 38 38 39 39 40 41 41 42 45 46 47 48 49 50
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig. Fig.
2.43 2.44 2.45 2.46 2.47 2.48 2.49 2.50 2.51 2.52 2.53 2.54 2.55 2.56 2.57 2.58 2.59 2.60 2.61 2.62 2.63 2.64 2.65 2.66 2.67 2.68 2.69 2.70 2.71 2.72 2.73 2.74 2.75 2.76 2.77 2.78 2.79 2.80 2.81 2.82 2.83
System Cabling DUAMCO 2:2, 2 cell . . . . . . . . . . . . . . . . . . . . . . . . . . . 51 System Cabling DUAMCO 4:2, 2 cells . . . . . . . . . . . . . . . . . . . . . . . . . . 52 System Cabling DUAMCO 2:2/4:2, 2 cells . . . . . . . . . . . . . . . . . . . . . . . 53 System Cabling DUAMCO 2:2, 3 cells . . . . . . . . . . . . . . . . . . . . . . . . . . 54 System Cabling DUAMCO 2x2:2, 4:2, 3 cells . . . . . . . . . . . . . . . . . . . . . 55 System Cabling FICOM , 1 cell . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 56 System Cabling FICOM, 2 cells . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 57 System Cabling FICOM, 2cells . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 58 System Cabling DUAMCO 4:2, 4 cell . . . . . . . . . . . . . . . . . . . . . . . . . . . 59 System Cabling DUAMCO 4:2, 3 cells . . . . . . . . . . . . . . . . . . . . . . . . . . 60 System Cabling DUAMCO 8:2, 2 cell . . . . . . . . . . . . . . . . . . . . . . . . . . 61 System Cabling DUAMCO 8:2 and 4:2, 2 cell . . . . . . . . . . . . . . . . . . . . 62 Overview for HPDU cabling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 63 Interfaces on top of the BS240E/240XL service1 rack . . . . . . . . . . . . . . 64 Interfaces on top of the BS-240/240XL base rack . . . . . . . . . . . . . . . . . 65 Interfaces on top BS-240/240XL extension rack. . . . . . . . . . . . . . . . . . . 65 Locations of connection points for external cables . . . . . . . . . . . . . . . . . 66 Ground and AC mains connections of the BS-240/240XL (example) . . . 67 Pinning of 230 V AC terminal block (Service1 Rack) . . . . . . . . . . . . . . . 68 Ground-and power supply connections with -48V DC . . . . . . . . . . . . . . 69 Terminal block for -48 V DC input of MSU . . . . . . . . . . . . . . . . . . . . . . . 70 Ground and AC/DC connections of the BS240U . . . . . . . . . . . . . . . . . . 71 Preparation of the PCM-cable, 120 impedance . . . . . . . . . . . . . . . . . 73 Fixing of PCM cables at OVPT . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 74 Pinning Abis interface PCM0 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 74 Pinning Abis interface PCM1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 75 OVPT with terminal block (120 ) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 75 OVPT with 1,0/2,3 connectors (75 ) . . . . . . . . . . . . . . . . . . . . . . . . . . . 76 Monitoring interfaces for PCM lines of OVPT . . . . . . . . . . . . . . . . . . . . . 77 Terminal numbering of the ACTM. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79 Connector arrangement at ACTC . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82 Cell numbering (top view from the antenna pole) . . . . . . . . . . . . . . . . . . 85 Max. dimensions of antenna connectors . . . . . . . . . . . . . . . . . . . . . . . . 86 Antenna jumpers at cable feeding module . . . . . . . . . . . . . . . . . . . . . . . 86 Routing of antenna jumpers above the EMI-panel . . . . . . . . . . . . . . . . . 87 Position of TMA (DUAMCO combiner used). . . . . . . . . . . . . . . . . . . . . . 87 Position of TMA (FICOM combiner used) . . . . . . . . . . . . . . . . . . . . . . . . 88 Configuration with HPDU, DUBIAS and TMA . . . . . . . . . . . . . . . . . . . . . 88 Installation of TMA and DUBIAS. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 88 Bottom view of the Tower Mounted Amplifier . . . . . . . . . . . . . . . . . . . . . 89 TMA with mounting brackets. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 90
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
Tables
Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. Tab. 1.1 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 2.9 2.10 2.11 2.12 2.13 2.14 2.15 2.16 2.17 2.18 2.19 2.20 2.21 2.22 2.23 2.24 2.25 2.26 2.27 2.28 Technical Data of BS-240/240XL. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Equipping variants of frames, BS-240XL Base and Extension Racks . . Equipping variants, BS-240XL Service1 Rack. . . . . . . . . . . . . . . . . . . . Equipping variants, BS-240XL Service2 Rack. . . . . . . . . . . . . . . . . . . . Capacity of backup battery sets. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Selection of Slot ID . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . List of battery cables between the racks . . . . . . . . . . . . . . . . . . . . . . . . List of tempresistor cables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . List of DC cable connections between the racks . . . . . . . . . . . . . . . . . . Example for CAN-Bus cabeling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . List of SELIC-Cabling. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Pinning of -48 V interface of frame F:NT . . . . . . . . . . . . . . . . . . . . . . . . Pinning of PCM-Input connector of frame F:NT. . . . . . . . . . . . . . . . . . . Pinning of PCM-Output connector of frame F:NT . . . . . . . . . . . . . . . . . Functionality of system cables BS-240 . . . . . . . . . . . . . . . . . . . . . . . . . Functionality of system cables BS-240XL . . . . . . . . . . . . . . . . . . . . . . . Pinning of the AC input terminal block . . . . . . . . . . . . . . . . . . . . . . . . . . Pinning of Abis interface PCM0, 75 . . . . . . . . . . . . . . . . . . . . . . . . . . Pinning of Abis interface PCM1, 75 . . . . . . . . . . . . . . . . . . . . . . . . . . Pinning of the monitoring interfaces PCM0 . . . . . . . . . . . . . . . . . . . . . . Pinning of the monitoring interfaces PCM1 . . . . . . . . . . . . . . . . . . . . . . Pinning ACTM Connector X5 Site Inputs. . . . . . . . . . . . . . . . . . . . . . . . Pinning ACTM Connector X6, X7 Site Inputs . . . . . . . . . . . . . . . . . . . . Pinning ACTM Connector X8, X4 Site Inputs . . . . . . . . . . . . . . . . . . . . Pinning ACTA Connector X3, X2 Site Inputs . . . . . . . . . . . . . . . . . . . . . Pinning ACTA Connector X1 Site Inputs . . . . . . . . . . . . . . . . . . . . . . . . Environmental Alarms at ACTM and ACTC. . . . . . . . . . . . . . . . . . . . . . Pinning of the LMT interface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Pinning of the LMT RJ45 interface. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14 21 21 21 31 31 35 36 37 38 39 42 43 43 44 45 71 76 77 77 78 79 80 80 81 81 82 84 84
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
10
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
1 Introduction
!
The CE and UL declaration of conformity for the product will be fulfilled if the setup and cabling is undertaken in accordance with the specification in the manual and the documentation listed there, such as mounting instructions, cable lists etc. Where necessary, project-specific documentation should be taken into account. Deviations from the specifications or independent changes during setup, such as use of cable types with lower screening values, for example, can lead to the CE requirements being violatad. In such cases the CE declaration of conformity is invalidated and the responsibility passes to the person who has caused the deviations.
1.1
1.2
1.3
Feature Overview
Rack design BS-240 with up to 8 carriers per rack Rack design BS-240XL with up to 12 carriers per rack Rack extension up to 24 carriers per site (max. 12 carriers per cell) and up to 12 cells per site Easy rack extension with up to 2 extension racks for BS-240 and max. 1 extension rack for BS-240XL without interruption Duplex Combiners, Filter Combiners Full-rate and half-rate channels are supported
A30808-X3247-F380-7-7631
11
IMN:BTSE BS-240/240XL
Integrated Abis cross connect LMT-operation with full O&M functionality at a transmission rate of 64 kBit Integrated NTPM (will be used in Germany only) and Wave-equipment, battery backup in service rack
1.4
1.5
Installation Prerequisites
It is required that the installer pays attention to the valid EMC instructions. All other equipment on site must be CE designated and must provide interfaces for connecting of external cables conformable to EMC instructions.
1.6
12
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
Fig. 1.1
ESD Symbol
These are sensitive to static discharge. Notice: Avoid handling the modules in a high-static environment When handling the modules, do not touch connector contacts An earthed high-impedance wrist strap must be worn when handling modules. Use the socket at the racks for wrist strap connection. The modules must be transported in appropriate packaging
1.7
Installation Tools
The correct installation is carried out with the aid of the following tools: Standard toolkit for BSS-installation Spirit-level Plumb bob Torque spanner for SMA connectors (35 N/cm) Torque spanner for SMC connectors (100 N/cm) Screw driver for torx screws T8, T10, T20, T25, T30, T40, T50 (length 200 mm) Long screw driver for torx screws T30 (length 400 mm) Engineers wrenches for M12, M42 (SW 19, 65 mm) Ratchet with insets for nuts M4, M5, M6, M8, M10 (SW 7, 8, 10, 13, 17 mm) Security torx bit IPR25 (Knrr part no. 4000031 98) Screw drivers for hexagonal socket screw or hexagonal socket screw key SW 4 mm Screw driver for slotted screw M3, M4, M5 Screw driver for pozi drive screws M3,M4, M5 A pair of scissors Stripping knife for RF cables 90 offset screw driver for torx screws T20 knee pads (recommended) Adjuster feed wrench M42 (SW65) (Knrr part no. 01.139.965.7) For installation of power supply, transmission equipment, antennas, cableways and other infrastructure equipment, additional tools may be necessary.
1.8
Ancillary Material
The following ancilliary materials are needed : plumb line colophony adhesive tape (yellow/green, green, blue, red, orange, white) cable fasteners wire end sleeves for 16 mm copper wires cable lugs M8 wire end sleeves paint retouch kit (Siemens Serial No. A500-C101-B261)
A30808-X3247-F380-7-7631
13
IMN:BTSE BS-240/240XL
1.9
-48 V DC -48 V DC 400 V AC/50Hz 400 V AC/50Hz (3 x 230 Vac single phase) (3x 230 Vac single phase) 208 V AC 60 Hz (2 x 120 Vac single phase) 9W 25 W 12 W 135 W 17 W 17 W 10 W 60 W 80 W 43 W 20 W indoor wire, fibre optic, microwave max. 8 max. 12 1 - 12 7-16, female terminal block (120 Ohm) or 1.0/2.3 coaxial connectors female (75 Ohm) WAGO terminal block (max. AWG 8) WAGO terminal block (max. AWG 6) bolt M8 spring terminal blocks SubD 15, female max. 12 9W 25 W 12 W 135 W 17 W 17 W 10 W 60 W 80 W 43 W 20 W
power consumption: TMA DUAMCO DIAMCO CU (GSM) COBA COSA DC panel frame AC/DC converter ACOM battery set location condition: Abis link media: CU per single rack: multiple cell per BTSE no. of CU per Cell external interfaces: TX/RX antenna Abis interface mains input AC mains input DC ground connection external alarms LMT Tab. 1.1
14
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
2 BS-240/240XL Installation
2.1 Position in the System
Like all other base stations the BS-240/240XL interconnects the MS via the Um interface with the trunk network via the Abis interface.
Um interface
TRAU A interface
MSC
SBS
Position of the BS-240/240XL within the SBS
Fig. 2.1
2.2
Site Requirements
Prior to the commencement of installation, the construction of the room in which the base transceiver station is to be housed must be complete and the room in good condition and dry heaters, if necessary, should be put up in the room. The BS-240/240XL is intended to be installed in a restricted access area. Doors and windows must already have been installed and must be lockable. Openings in wall or ceiling of oor - if required - must be complete. The oor coverings must have been laid. Room lighting and wall sockets must have been installed. Heating or air-conditioning systems should be ready for operation. Walls and ceilings should have been painted.The room must be clean. A minimum oor space of 1,70 m x 1,50 m must be provided (later extension not possible). optional cable runways must be installed rst The oor load of the construction room must be not less than 7500 N/m2. All installation works off 3 phase 230 V AC (BS-240E/240XL) or 2 phase 208/110 V AC (BS-240U) power supply, including a false current protection switch (BS-240E/240XL) or a ground fault indicator in each phase (BS-240U) which must be nished in each phase. To prevent subsequent accumulation of dust and dirt, the parts and equipment units to be installed must be unpacked outside the room (if possible). After that it is advantageous to install the BTS, after all other installation works to create the required infrastructure (power supply, antenna cabling, PCM line...) are complete.
A30808-X3247-F380-7-7631
15
IMN:BTSE BS-240/240XL
2.3
Site Conguration
Operation of the BS240/240XL requires additional equipment on site: TX/RX antennas microwave outdoor unit *
external alarms**
ground connection
*dependent on type of network integration **optional
Fig. 2.2
2.4
16
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
Overvoltage Protection and Tracer (OVPT): Protect the PMC30 ports of core boards from overvoltage and provide a monitoring interface for connected Abis-lines. Carrier related Modules: Carrier Unit (CU): Consists of a receiving and transmitting part with syntheziser and power amplifier, a signal processing unit as well as a power supply unit. Antenna System Modules: Antenna Combiners (ACOM): Can be Duplexer Amplifier Multicoupler-DUAMCO or Filter Combiner-FICOM in conjunction with an High Power Duplexer HPDU. Antenna Multicoupler (MUCO): Multicoupling will be done with a DI-Amplifier Multicoupler (DIAMCO) or a DUAMCO. The types and numbers of modules are subject to modification, it depends on the cell configuration and the type of antenna combining. AC/DC Converter (ACDC): Converts the mains voltage of 230 V AC into the -48 V DC supply voltage. Link Equipment (LE): Can be NTPM (BS-240/240XL), CSU (BS-240U) if terrestrial line is used for connection to BSC or microwave. Backup Batteries: guarantees continuous operation for a certain time in case of mains breakdown or AC/DC failure.
Note: All empty slots in a partial equipped subrack must be closed with cover plates, so that the air flow inside the rack will not be affected. Plates are not necessary for link equipment and empty battery trays.
A30808-X3247-F380-7-7631
17
IMN:BTSE BS-240/240XL
2.4.1
SIEMENS
SIEMENS
LMT ETHERNET
SIEMENS
DC-PANEL ACT-C
DC-PANEL ACT-C
DC-PANEL ACT-C
LE 0 LE 1 LE 2 LE 3 LE 4 LE 5
MUCO #0
MUCO #1
MUCO #0
CU CU #2 #3
CU #6
CU #7
CU CU #2 #3
MUCO #1
CU #6
CU #7
CU CU #0 #1
CU #4
CU #5
CU CU #0 #1
CU #4
CU #5
Service1 Rack
Base Rack
Extension Rack
Fig. 2.3
18
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
00 01 02 03 04 05
00 01 02 03 04 05
00 01 02 03 04 05
AC + DC Distribution
AC + DC Distribution
AC + DC Distribution
LE 0 LE 1 LE 2 LE 3 LE 4 LE 5
11 12 13 14 15
11 12 13 14 15
AC + DC Distribution
AC + DC Distribution
LE 0 LE 1 LE 2 LE 3 LE 4 LE 5
LE 0 LE 1 LE 2 LE 3 LE 4 LE 5 LE 6 LE 7 LE 8 LE 9 LE 10 LE 11
Fig. 2.4
LE 0 LE 1 LE 2 LE 3 LE 4 LE 5
LE 0 LE 1 LE 2 LE 3 LE 4 LE 5 LE 6 LE 7 LE 8 LE 9 LE 10 LE 11
LE 0 LE 1 LE 2 LE 3 LE 4 LE 5
LE 0 LE 1 LE 2 LE 3 LE 4 LE 5 LE 6 LE 7 LE 8 LE 9 LE 10 LE 11
Fig. 2.5
A30808-X3247-F380-7-7631
19
IMN:BTSE BS-240/240XL
2.4.2
SIEMENS
DC-PANEL ACT-C
SIEMENS
DC-PANEL ACT-C
SIEMENS
ETHERNET DC-PANEL ACT-C LMT
SIEMENS
DC-PANEL ACT-C
FAN #0 LE #0 LE #1 LE #2 LE #3 LE #4 LE #5 LE #6
LE #7
FAN #1
FAN #0
FAN #1
FAN #0
FAN #1
AC/
CTRL
DC AC/ AC/ AC/ AC/ AC/ AC/ DC DC DC DC DC DC #00 #00 #01 #02 #03 #04 #05 AC + DC DISTRIBUTION
LE #8 LE #9 LE #10 LE #11
FAN #2
FAN #3
FAN #2
FAN #3
FAN #2
FAN #3
AC/
MUCO #2
MUCO #2
AC + DC DISTRIBUTION
MUCO #3
#4
#10
#11
#4
#5
MUCO #3
CTRL
DC AC/ AC/ AC/ AC/ AC/ AC/ DC DC DC DC DC DC #01 #10 #11 #12 #13 #14 #15
CU
CU #5
CU
CU
CU
CU
CU #10
CU #11
FAN #5 CU #8 CU #9
FAN #5 CU #8 CU #9
1/4 Battery
1/4 Battery
1/4 Battery
1/4 Battery
FAN #6 CU #0 CU #1
FAN #7 CU #6 CU #7
FAN #6 CU #0 CU #1
FAN #7 CU #6 CU #7
1/4 Battery
1/4 Battery
1/4 Battery
1/4 Battery
Service2 Rack
Service1 Rack
Base Rack
Extension Rack
Fig. 2.6
20
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
installed modules Base Rack 4 x DUAMCO 2:2 or 4 x DUAMCO 4:2 or 2 x DUAMCO 8:2 or 4 x FICOM modules (Base/Expansion modules in site specific configuration) 4 x CU; 2 x DIAMCO 4 x CU; 2 x DIAMCO 4 x CU; 2 x COBA; 2 x COSA
installed modules Extension rack 4 x DUAMCO 2:2 or 4 x DUAMCO 4:2 or 2 x DUAMCO 8:2 or 4 x FICOM modules (Base/Expansion modules in site specific configuration) 4 x CU; 2 x DIAMCO 4 x CU; 2 x DIAMCO 4 x CU
3 2 1 (down)
Tab. 2.1
Service1 rack frame no. 4 (top) 3 2 type 1 F:AC/DC1/1 2 F:LE (6 x LE) type 2 F:AC/DC1/1 2 F:LE F:BATTERY F:BATTERY type 3 F:AC/DC1/1 2 F:AC/DC2 F:LE (6 x LE) up to 8000 W type 4 F:AC/DC1/1 2 F:AC/DC2 F:LE F:BATTERY type 5 F:AC/DC1/1 2 F:AC/DC2 F:BATTERY F:BATTERY
Service2 rack frame no. 4 (top) 3 2 1 (down) Tab. 2.3 F:LE (6 x LE) F:BATTERY F:BATTERY type 1 (R:BS120) F:LE F:BATTERY F:BATTERY F:BATTERY type 2 R:BS120)
A30808-X3247-F380-7-7631
21
IMN:BTSE BS-240/240XL
2.5
Equipment Delivery
The BS-240/240XL racks are shipped vertically in wooden crates (or horizontally in case of transportation by airplane).The crates dimensions for the BS-240 are 1800 mm x 800 mm x 650 mm (HxWxD). Depending on the pre-installed modules inside the racks, the crate can weigh up to approx. 150 kg. The crates dimensions for the BS-240XL are 2225 mm x 800 mm x 650 mm (HxWxD). The Service racks will be delivered without backup batteries (weight aspects). Additional crates will be used for transportion of the batteries. All crates have the following information printed on them for identification of delivery: customer order number serial number of rack or other supplied equipment destination gross and net weight overall dimensions (cm) symbol or inprint to identify the "Top" and the "Bottom" delivery papers For transportation of the crates from the unloading area into the construction room use handling aids (for example: fork-lift truck, goods elevator), a second person is needed for help. The 4 fastening clamps which fixing the rack-feets to the bottom of the crate should be used for later floor-fixing.
2.5.1
Preliminary Checks
The transportation crate of the BS-240/240XL is equipped with a ShockwatchTM-lable and a TiltwatchTM-lable. These lables are fixed at the crate for indication of fallover or strong shocks during the transport from factory to the site. Check that the crate and lable are not damaged. In case of evident damage due to transport, unpack the equipment in presence of an insurance company representative and promptly claim any damage and inform the shipper for specifying the damage. Check whether the package is actually addressed to the site and complete.
shockwatch lable
tiltwatch lable
Fig. 2.7
22
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
2.5.2
Rack Unpacking
During the unpacking steps great care must be taken to ensure that the rack is not scratched or damaged in any way. Proceed as follows: Cut the straps and remove the top of the crate. Take out the proles protecting the rack edges. Remove the protection to the head and to the base of the rack. Take out the rack from the crate. Use the straps around the rack. Lift the rack in vertical position (if necessary). Open and remove the tubular PE shrink-wrap protecting the rack . Immediadately after unpacking the rack, inspect it for damage and report the extent of any damage to the transport company.
2.5.3
Devices Unpacking
Proceed as follows: Open the PVC wrap protecting the carton and withdraw it. Remove the dehydrating material bag from the box. Cut with a suitable knife the adhesive tape sealing the box. Take the device out. Open the PVC wrap protecting the device/board and withdraw it. The packing material should be preserved for possible future re-packing. For this purpose, reverse the procedure described above, taking into account the warnings specified for the packing. If the packing material is supplied by the customer, special care should be taken to avoid damage during the transport and storage of the devices.
2.5.4
Rack Installation
Prior to the commencement of rack installation, consult the site documentation to locate the installation point of the BS-240/240XL, the PCM24/30 network termination, AC mains or power supply unit (if -48V will be provided from external equipment) and the access of the antenna cables into the construction room. After that check the proper installation of the earthing bar and the necessary cable runways. If the rack must be moved to the final installation position by crane and for later connection works, it is necessary to remove the topcover of the rack. Proceed as follows: Open the rack-door and unscrew both screws in the upper part of the front of rack. (see Fig. 2.8 ) Lift up the top cover and slide it back. Disconnect the green/yellow ground wire from the pin inside the top cover.
Before opening the rack-door take measures to prevent the rack falling over! Note the accident prevention regulations, when working with a fork lift truck or crane ! Dont remove the crane eyes after the crane transport is finished to guarantee the later EMI-closeness of the rack! If the racks stand side by side, they must be screwed together to one common unit with one nut and screw M8x20. For this purpose the top cover has to be removed as shown in the figure Fig. 2.8.
A30808-X3247-F380-7-7631
23
IMN:BTSE BS-240/240XL
unscrew
ground wire
Fig. 2.8
60
Fig. 2.9
The total weight rack must not exeed 380 kg when being lifted (unequipped weight: 90kg). For determination the weight refer to section 1.9 Technical Data Under no circumstances must the sets of batteries be inserted into the Service Racks during transportation on site. The doors must be kept closed during transportation.
24
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
1500 mm
1100 mm BS-240 2200 mm min. dimensions for 3-rack solution 1600 mm 2025 mm
1500 mm
1700 mm 450 mm Fig. 2.10 min. dimensions for double rack solution
Space necessary for installation of BS-240/240XL Four fastening claws fixing the adjustable rack-feets to the base of the crate. The claws can be later used for floor fixing of the BS-240/240XL rack.
Fig. 2.11
450 mm
2350 mm
A30808-X3247-F380-7-7631
25
IMN:BTSE BS-240/240XL
4 3 1
Fig. 2.12
Proceed as described in the list below: Unscrew the 4 fastening claws from the crates base as shown in Fig. 2.11 and move the rack carefully to the nal installation position. Check the correct vertical rack position, using the spirit-level. In case, the position is incorrect, equalize differences in the oor height by adjusting the rack feets. (see Fig. 2.12). Loose the lock nut (1) and screw down or up the rack feed (2) for proper oor contact by using adjuster feed wrench M42 (SW65, Knrr part no. 01.139.965.7). Tighten the lock nut as fast as possible to avoid a gap between the bottom section (3) and the rack frame (4)
The electrical contact between lock nut and bottom section is absolute required for EMIcloseness of the BS-240/240XL Rack. Push a claw on each of the 4 rack feets and mark the drilling point on the oor. Remove the clamps and drill the 4 holes and insert the 4 wallplugs (e.g. Fischer S8GK) into the holes. Push the claws on the rack feets and x them. Use a ratchet with a 10 nut. (see Fig. 2.13, left side)
The BS-240/240XL rack can alternatively fixed to wall. The rack has two right angle brackets on its top rear for fixing to wall (Fig. 2.13, right side).
Fig. 2.13
In areas with the possibility of earthquake, the fixation to wall is prohibited. Use the earthquake mounting kit for floor fixation Siemens Serial No. S30861-K2086-X.
26
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
For setup the earthquake mounting kit proceed in steps as follows: Mark the positions of the drilling holes in accordance with Fig. 2.15. Drill the holes with 18 mm in diameter and a depth of 90 mm.Dont pre-drill the holes! Produce an undercut of the drilling holes: drill the hole to stop and swivel the jack hammer 3-5 times keeping stop to concrete. Clean out the drilling holes by blowing or sucking. Put steel plug (e.g. Fischer FZA 18x80 M10 I) into the inserting tool (e.g. Fischer FZE 18) and hammer into each hole until the sleeve is ush with surface. Fit bolts M10 (1) with washer (2) through both holes of claw (3) and distance plate (4). Screw down the bolts into the steel plugs as fast as possible. Fix in this way all claws for the rearside rackfeeds rst. Shift the racks to the correct position, so that each of the rear adjuster feeds is placed in the cutout of a claw. Push a claw on each of the frontside feeds and x them with bolts and washers. The distance plates are not needed for the frontside row.
1 2
1085 1135
485 535
600 650
22,5 0 50
0 rear
Service1 Rack
Base Rack
front
463
Fig. 2.15
If the earthquake mounting kit will be used for rack fixing, it is not allowed to mount the rack addtional to the wall !
A30808-X3247-F380-7-7631
27
IMN:BTSE BS-240/240XL
2.6
Rack Completion
The BS-240/240XL racks are shipped including equipment components, pre-installed by the manufacturer in accordance with customer configuration: sub-rack, which holds several boards and modules DC panel backplanes (multilayer PC-boards, which are mounted at the rear side of the subrack) the rack internal cabling heaters and fan unit core modules carrier related modules (Carrier Units, Antenna Combiners) AC/DC converters semi-rigid cables for setup of the system cabling The following items are planned for installation after setup of the racks on site: backup batteries cabling between the racks (battery cabling, DC-cabling, CAN-BUS) link equipment For cable routing from one rack into another one (eg. DC power supply, CAN-Bus, battery cables) two ways can be used. Without leaving the EMC-protected area, an interconnection hole in upper area of the side walls of each rack is provided. The holes are covered by plates for single racks and the endracks of a row. The connectionkit MK:EMCRV1 as shown in the figure below contains all parts, which are needed for connection of two racks
28
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
Fig. 2.16
Mount the parts of the connection kit in the following order: Removed by unscrewing the security screws M3. Setup the sealing stripes (1) at the edges of the holes. Move the racks in position closed together. Screw the racks to one common unit with nut and screw M8x20 (2). Connect the ground bolts of both rack with the ground wire (3).
Fig. 2.17
A30808-X3247-F380-7-7631
29
IMN:BTSE BS-240/240XL
Fig. 2.18
For connections outside the EMC-protected area (e.g. CAN-bus, antenna jumpers, site inputs...), the routing of these cables directly below the roof section is possible.
2.6.1
30
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
removable pieces
Fig. 2.19
Top cover
Fig. 2.20
A30808-X3247-F380-7-7631
31
IMN:BTSE BS-240/240XL
2.6.2
As up to 2 AC/DC frames can be installed in the Service1 rack, an identification of the AC/DC controllers is needed. The first AC/DC frame is installed in the upper position. Dip switches at the front of the AC/DC controller are used for selecting the Slot ID.
Slot ID bit 0 upper frame (AC/DC 0) lower frame (AC/DC 1) Tab. 2.5 ON OFF OFF ON
Slot ID bit 1
Selection of Slot ID
i
2.6.2.1
The capacity of the installed battery systems has to be selected at the Dip switch rows of the AC/DC controller. For detailed information refer to ITMN:BTSE BS-240/240XL.
Only use insulated tools for connecting the cables to the battery terminals in order to avoid accidental short circuits.
32
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
battery2
battery3
battery4 battery1
fixing straps
Fig. 2.21
tempresistor cable
(color as shown not relevant)
- 48 V (blue)
+ 0 V (black)
+ 2
+ 3
1 +
4 +
air vent tube (routed via RF cable entry outsite the rack)
Fig. 2.22
A30808-X3247-F380-7-7631
33
IMN:BTSE BS-240/240XL
The figure below shows the premanufactured parts of the battery air vent system. For setup proceed in accordance with the figure in steps as follows: Setup a plastic angle (1) at the air outlet of each battery. Fix one of the 4 clear plastic tubes (2) at each angle. Connect the tubes of battery 2 and 3 with the T-connector (3). Connect the tubes of battery 1 and 4 with cross-connector (4). Setup the connection between the T-connector and the cross-connector. Use the short plastic tube (5). Connect the long clear plastic tube (6) at the cross-connector. Equip the other end of the tube with the outlet nipple (7). Route the tube along the right side rack frame upwards to the cable feeding module. The outlet part will be placed inside the cable feeding module. The tube must be xed at the rack frame by cable straps. The second T-connector (8) will be used for connecting the air vent system of a second battery tray.
2 4
1 7 3 5 8
Fig. 2.23
34
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
2.6.2.2
Tighten the battery nuts with 20 Nm. Turn up the protection cap to the end position, during tighten the cables to the battery poles (avoid contact of metall) The battery capacity must be adjusted at the AC/DC controller. Only use insulated tools for connecting the cables to the battery terminals in order to avoid accidental short circuits. After all electrical connections are complete, setup the air vent system: Fix the short clear plastic tubes (1) at the air vent nipples of battery 2 and 3. Fix the longer plastic tubes (2) at the air vent nipples of battery 1 and 4. Connect the 4 tubes at the collector part (3). Connect the long clear plastic tube (4) at the collector part. Route the tube along the right side rack frame upwards through the cable feeding module. The tube must be xed at the rack frame by cable straps. - 48 V (blue) 0 V (black)
temperatur sensor cable
to MK: Battery
to F:ACDC
GCSTM
GCSTM
GCSTM
GCSTM
Fig. 2.24
A30808-X3247-F380-7-7631
35
IMN:BTSE BS-240/240XL
Fig. 2.25
2.6.2.3
Battery Cabling
A overview of battery cabling is shown in the picture below. battery system BAT 0 battery cable no. 110/1 111/1 BAT 1 110/2 111/2 BAT 2 110/3 111/3 BAT 3 110/4 111/4 Tab. 2.6 from to length 1500 mm 1500 mm 2500 mm 2500 mm 3700 mm 3700 mm 4200 mm 4200 mm colour blue black blue black blue black blue black
S1-AC/DC1-26b S1/BAT0/- (-48V) S1-AC/DC1-25b S1/BAT0/+ (+0V) S1-AC/DC1-28b S2/1 BAT1 -2a S1-AC/DC1-27b S2/1 BAT1 -1a S1-AC/DC2-15b S2/2 BAT2 -2a S1-AC/DC2-14b S2/2 BAT3 -1a S1-AC/DC2-17b S2/3 BAT3 -2a S1-AC/DC2-16b S2/3 BAT3 -1a
36
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
from S1/BAT0 (+) S2/1 BAT1 (+) S2/2 BAT2 (+) S2/3 BAT3 (+)
Service 2/3
top cover air vent
Service 2/2
air vent
Service2/1
air vent
Service1
air vent
tempresistor cable
frame AC/DC 1
110/1 111/1
T1 T0
112/4
t
frame AC/DC 2
112/1
110/4 111/4
T1
T0
t
BAT3
t
BAT2
t
BAT1
t
BAT0
A30808-X3247-F380-7-7631
37
IMN:BTSE BS-240/240XL
2.6.3
DC-Panel
DC-Panel 34
DC-Panel
35
DC-Panel
33
Service2 Rack Service1 Rack Base Rack
36
Extension1 Rack Extension2 Rack (for BS-240 only)
Fig. 2.27
unscrew
cable no. 33 34 35 36
Tab. 2.8
38
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
2.6.4
CAN-Bus Connections
The CAN-Bus will be routed in loop configuration through the racks to collect external and internal alarms and lead them to ACT of the Base rack. The CAN-Bus must be terminated at the end with the terminating resistor S30861-K2047-K. cable no. 229 230 231 232 233 Tab. 2.9 from CAN OUT Base Service 1 Extension 1 Service 2/1 Extension 2 toCAN IN Service 1 Extension1 Service 2/1 Extension 2 Service 2/2 Code no. S30864-X210-A1 S30864-X210-A1 S30864-X210-A1 S30864-X210-A1 S30864-X210-A1 length 1200 mm 1900 mm 2600 mm 3300 mm 4000 mm
CAN IN
Fig. 2.29
CAN OUT
- 48 V SERIAL IF
CAN TEST
A30808-X3247-F380-7-7631
39
IMN:BTSE BS-240/240XL
2.6.5
Fig. 2.31
CU 4...7 CU 0...3
277 278
Extension 1 Rack
Extension 2 Rack
(for BS-240 only)
to interface Extension Rack Extension 1 CU 0...3 Extension 1 CU 4...7 Extension 2 CU 0...3 Extension 2 CU 4...7
278
Tab. 2.10
List of SELIC-Cabling
40
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
2.6.6
rack front
SubD 9 female SubD 9 male PCM1 PCM0
F:CORE
LE1-4 LE5-8
Fig. 2.33
Connect the microwave antenna cables to the indoor units as follows: Unscrew the front part of cable feeding module. Feed the microwave cable through the cable feeding module forward to the front connectors of microwave indoor units. Fix the microwave cables at the connectors. Bend the microwave cables into the correct position for easy closing of cable feeding module. Screw the front part of feeding module in its original position. Fix each cable at the strain reliefs of the feeding module.
A30808-X3247-F380-7-7631
41
IMN:BTSE BS-240/240XL
Connect the microwave power supply/alarm cables (S30864-K2045-X-*-7483) at the front connectors of ACTC. Route the cable bundle forward to the link equipment devices. Cut the cables for the matching length and equip the end with device-specic connectors.
service rack
Fig. 2.34
In case of transmission via terrestrial lines, the NTPMs are placed inside the Service rack, which is equipped with a mounting kit for NTPM, called frame F:NT. Each frame F:NT includes the equivalent space of 3 HU, allowing the installation of up to 2 NTPM. The frame F:NT provides 3 interface as shown in the figure below.
Pin 9
-48 V
Pin 1
Fig. 2.35
42
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
The interfaces are: subD 9, male with M3 xings for -48 V output subD 25, female with M3 xings for PCM input subD 25, male with M3 xings for PCM output
PCM lines
Base Rack
EMI panel
ACTC -48 V
F:CORE
PCM1 PCM0
rack front
F:NT F:NT
EMI panel
Fig. 2.36
The power supply cable from the frame F:NT to the ACTC is part of the F:NT. The PCM cabling is site specific and depends on customer requirements. Name 0V -48 V Tab. 2.11 1,2,6 4,5,9 Pinning of -48 V interface of frame F:NT F:NT -48 V , subD 9 female pin
A30808-X3247-F380-7-7631
43
IMN:BTSE BS-240/240XL
Signal name PCM 1 - ULA PCM 1 - ULB GND/G PCM 1 - DLA PCM 1 - DLB GND/G PCM 2 - ULA PCM 2 - ULB GND/G PCM 2 - DLA PCM 2 - DLB GND/G Tab. 2.12 1 14 3 2 15 16 4 17 6 5 18 19
Signal name PCM 1 - ULA PCM 1 - ULB GND/G PCM 1 - DLA PCM 1 - DLB GND/G PCM 2 - ULA PCM 2 - ULB GND/G PCM 2 - DLA PCM 2 - DLB GND/G Tab. 2.13 1 14 3 2 15 16 4 17 6 5 18 19
44
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
2.7
1250 mm SMA,90,male/ semi-rigid N-Con,90,male .141 Al 400 mm 7/16,90,male 7/16,90,male 1/2 jumper cable Coax flexible
A30808-X3247-F380-7-7631
45
IMN:BTSE BS-240/240XL
connection DUAMCO 0/3CU 0/1/6/7 DUAMCO 0/1/2/3CU 2/3/8/9 DUAMCO 0/1/2/3CU 4/5/10/11 DUAMCO 0/3CU 0/1/6/7 DUAMCO 0/1/2/3CU 2/3/8/9 DUAMCO 0/1/2/3CU 4/5/10/11 Tab. 2.15 HPDU #0
length
connector
cable type semi-rigid .086 Al semi-rigid .086 Al semi-rigid .086 Al semi-rigid .141 Al semi-rigid .141 Al semi-rigid .141 Al
1800 mm SMC,90,male/ SMC,90,male 1600 mm SMC,90,male/ SMC,90,male 1350 mm SMC,90,male/ SMC,90,male 1650 mm SMA,90,male/ SMA,90,male 1250 mm SMA,90,male/ SMA,90,male 1050 mm SMA,90,male/ SMA,90,male
FAN
#0
#1
FAN
#0
#1
FAN
#2 MUCO # 0 CU #3
FAN
#3 CU #6 CU
#7
FAN
#2 CU #3 MUCO # 0
FAN
#3 CU #6 CU
#7
MUCO # 1
FAN
#4 CU #1
FAN
#5 CU #4 CU #5
FAN
#4 CU #1
MUCO # 1
CU #2
CU #2
FAN
#5 CU #4 CU #5
CU #0
CU #0
Extension Rack
46
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
FAN
#0
#1
FAN
#0
#1
FAN
#2 CU #5 MUCO # 0
FAN
#3 CU #10 CU
# 11
FAN
#2 CU #5 MUCO # 0
FAN
#3 CU #10
#11
MUCO # 1
-C114
-C114
-C118
MUCO # 1
CU #4
CU #4
CU -C118
-C160
FAN
#2 CU #3 MUCO # 0
FAN
#3 CU #8
#9
-C160
-C113
FAN
#2 CU #3 MUCO # 0
FAN
#3 CU #8 CU
#9
-C113
MUCO # 1
-C204
FAN
-C204 #4 CU #1
CORE # 0 CORE # 1 CORE # 2 CORE # 3
FAN
-C206
FAN
MUCO # 1
CU #2
CU
CU #2
-C206 #4 CU #1
CORE # 0 CORE # 1 CORE # 2 CORE # 3
FAN
#5 CU #6 CU #7
#5 CU #6 CU #7
CU #0
CU #0
TX-Cabling
The following sections are intended to give an overview about the most interesting configurations with different combining modulesThe configurations of system cabling as described in the following sections are standard proposals. For information about the actual configuration refer to the Configuration Overview and the Cabling Configuration List, which will be delivered with each BS240 and should be used for checking the correct configuration. An example of the Configuration Overview and Cabling Configuration List is shown in the following figures.
A30808-X3247-F380-7-7631
47
IMN:BTSE BS-240/240XL
PULL: IDXxxx004097 Rack: Baserack BTS EQUIPMENT PLUS 23. March 2000 BS-240 BASE Rack SIEMENS
FAN 0 F: ACOM
FAN 1
ACOM 0
ACOM 1
ACOM 2
ACOM 3
FAN 2 F: CU
FAN 3
CU 2
CU 3
DIAMCO 0 DIAMCO 1 CU 6
CU 7
FAN 5
CORE 2
CORE 3
CORE 1
CU 0
CU 1
CU 4
CU 5
Fig. 2.39
48
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
BTS Cabling 23. March 2000 PULL: IDXxxx004097 Rack: Baserack AD400S2268D (Sales Unique Name)
SIEMENS
Type of ACOM 0
from RX/TX
Modul 0 RX 0 Modul 1 RX 0 Modul 0 RX 1 Modul 1 RX 1 Modul 0 RX 2 Modul 1 RX 2 Modul 0 RX 3 Modul 1 RX 3 Modul 0 RX 4 Modul 1 RX 4 Modul 0 RX 5 Modul 1 RX 5 Modul 0 RX 6 Modul 1 RX 6 Modul 0 RX 7 Modul 1 RX 7 Modul 0 TX 0 Modul 1 TX 0 Modul 0 TX 1 Modul 1 TX 1 Modul 0 TX 2 Modul 1 TX 2 Modul 0 TX 3 Modul 1 TX 3
to CU
0 0 1 1 2 2 3 3
Type of Cable C39195-Z80Cxxx Cxxx Cxxx Cxxx Cxxx Cxxx Cxxx Cxxx Cxxx Cxxx Cxxx Cxxx Cxxx Cxxx Cxxx Cxxx Cxxx Cxxx Cxxx Cxxx Cxxx Cxxx Cxxx Cxxx
DUAMCO4G
0 1 2 3
Type of ACOM 1
from RX/TX
to CU
A30808-X3247-F380-7-7631
49
IMN:BTSE BS-240/240XL
2.7.1
DUAMCO 0 2:2 Module 0
RX0 RX1
Module 0
RX
CU 0
TX0
Module 1
RX RXdiv
CU 1
TX0
SLOT 1
SLOT 1
Module 1
RX RXdiv
CU 3
TX0
SLOT 2
SLOT 2
Module 1
RX RXdiv
CU 7
TX0
Module 1
RX0 RX1
SLOT 3
SLOT 3
Module 1
RX RXdiv
CU 5
TX0
Fig. 2.41
50
A30808-X3247-F380-7-7631
Module 1
RX0 RX1
Carrier 8
Carrier 7
Carrier 6
Carrier 5
CU 6
Module 1
RX0 RX1
Carrier 4
Carrier 3
CU 2
Module 1
RX0 RX1
SLOT 0
SLOT 0
Carrier 2
Carrier 1
IMN:BTSE BS-240/240XL
2.7.2
DUAMCO 0 4:2 Module 0
RX0 RX1 RX2 RX3 RX0
TX0 TX1
SLOT 1
SLOT2
SLOT 2
SLOT 1
SLOT3
TX0 TX1
Module 1
Fig. 2.42
Module 1
SLOT 0
Module 1
A30808-X3247-F380-7-7631
Module 1
SLOT 0
IMN:BTSE BS-240/240XL
2.7.3
DUAMCO 0 2:2 Module 0
RX0 RX1
Module 0
RX
CU 0
TX0
Module 1
RX RXdiv
CU 1
TX0
SLOT 1
SLOT 1
Module 1
RX RXdiv
CU 3
TX0
SLOT 2
SLOT 2
Module 1
RX RXdiv
CU 7
TX0
Module 1
RX0 RX1
Carrier 3
Carrier 4
CU 6
Module 1
RX0 RX1
Carrier 4
Carrier 3
CU 2
Module 1
RX0 RX1
Module 1
RX RXdiv
CU 5
TX0
Fig. 2.43
52
A30808-X3247-F380-7-7631
Module 1
RX0 RX1
SLOT 3
SLOT 3
Carrier 1
Carrier 2
SLOT 0
SLOT 0
Carrier 2
Carrier 1
IMN:BTSE BS-240/240XL
2.7.4
DUAMCO 0 4:2 Module 0
RX0 RX1 RX2 RX3 RX0
TX0 TX1
SLOT 1
SLOT 2
SLOT2
SLOT 1
SLOT 0
Module 1
Module 1
SLOT 0 SLOT 3
SLOT 3
TX0 TX1
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
2.7.5
DUAMCO 0 2:2 Module 0
RX0 RX1
Module 0
RX
CU 0
TX0
Module 1
RX RXdiv
CU 1
TX0
SLOT 1
SLOT 1
Module 1
RX RXdiv
CU 3
TX1
Module 1
RX0 RX1
SLOT 2
SLOT 2
Carrier 4
Carrier 3
CU 2
Module 1
RX0 RX1
TX0 TX1
Fig. 2.45
54
A30808-X3247-F380-7-7631
SLOT 3
Module 1
Module 1
SLOT3
SLOT 0
SLOT 0
Carrier 2
Carrier 1
IMN:BTSE BS-240/240XL
2.7.6
DUAMCO 0 2:2 Module 0
RX0 RX1
Module 0
RX
CU 0
TX0
SLOT 0
Module 1
RX RXdiv
CU 1
TX0
SLOT 1
Module 1
RX RXdiv
CU 3
TX0
SLOT 2
Module 1
RX0 RX1
SLOT 3
Module 1
RX RXdiv
CU 5
TX0
Fig. 2.46
A30808-X3247-F380-7-7631
Module 1
RX0 RX1
Carrier 1
Carrier 2
Carrier 2
Carrier 1
CU 2
Module 1
RX0 RX1
Carrier 2
Carrier 1
IMN:BTSE BS-240/240XL
2.7.7
DUAMCO 0 2:2 Module 0
RX0 RX1
Module 0
RX
CU 0
TX0
SLOT 0
Module 1
RX RXdiv
CU 1
TX0
SLOT 1
Module 1
RX RXdiv
CU 3
TX0
SLOT2
Module 1
RX0 RX1
TX0 TX1
Fig. 2.47
56
A30808-X3247-F380-7-7631
SLOT 3
Module 1
Module 1
Carrier 2
Carrier 1
CU 2
Module 1
RX0 RX1
Carrier 2
Carrier 1
IMN:BTSE BS-240/240XL
2.7.8
RX RXdiv
CU 0
TX0
SLOT 0
Carrier 3 Carrier 2
TX1 RX RXdiv
CU 1
DIAMCO 0
RX0 RX1 RX2 RX RXdiv
RX3 RX4 RX5 RX6 RX7 RX0 RX2 RX RXdiv RX RXdiv TX1
CU 3
CU 6
Module 1
Expansion
SLOT 2
RX RXdiv
CU 7
TX1
RX RXdiv
Expansion
RX RXdiv
CU 5
Fig. 2.48
Carrier 8
TX1
SLOT3
Carrier 7
CU 4
TX0
Carrier 6
Carrier 5
RX1
TX0
CU 2
TX0
Expansion
Base
Module 0
SLOT 1
A30808-X3247-F380-7-7631
Carrier 4
Carrier 1
IMN:BTSE BS-240/240XL
2.7.9
RX RXdiv
CU 0 TX 0
CU 1 TX 1
RX1 RX2
TX 0 Expansion
Module 1
SLOT 1
RX3
CU 3 TX 1
RX RXdiv
TX 0 Expansion
Module 0
SLOT 2
Carrier 4
DIAMCO 1
CU 6
Carrier 4
Carrier 3 Base
RX0
CU 2
CU 7
TX 1
RX1 RX2
TX 0
Module 1
SLOT3
CU 5 TX 1
Fig. 2.49
58
A30808-X3247-F380-7-7631
Carrier 1
Carrier 2
RX0
CU 4
Carrier 3
Module 0
SLOT 0
Base
Carrier 2
Carrier 1
DIAMCO 0
IMN:BTSE BS-240/240XL
2.7.10
BS-240, 2 Cells with FICOM, max. 2,6,0 (Proposal) Logical numbering of carrier (cell 0) Logical numbering of carrier (cell 1)
59
RX RXdiv
CU 0 TX 0
Module 0
Base
CU 1 TX 1
RX1 RX2
TX 0 Expansion
Module 1
CU 3 TX 1
RX RXdiv
TX 0 Expansion
Module 0
CU 7
TX 1
RX1 RX2
TX 0
Module 1
Base
CU 5 TX 1
Fig. 2.50
A30808-X3247-F380-7-7631
Carrier 1
Carrier 2
RX0
CU 4
Carrier 3
Carrier 4
DIAMCO 1
CU 6
Carrier 5
Carrier 6
RX0
CU 2
Carrier 2
Carrier 1
DIAMCO 0
IMN:BTSE BS-240/240XL
2.7.11
DUAMCO 0 4:2 Module 0
RX0 RX1 RX2 RX3 RX0
TX0 TX1
Module 0
SLOT 1
Module 1
TX1
Module 1
SLOT 2
SLOT2
TX1
Module 1
RX0
RX CU 9 RXdiv
TX0
TX0 TX1
Module 1
SLOT3
Module 0
TX1
Fig. 2.51
60
A30808-X3247-F380-7-7631
Module 0
RX CU 8 RXdiv
TX0
SLOT3
RX CU 7 RXdiv
TX1
Module 1
RX0
RX CU 6 RXdiv
TX0
DUAMCO 3 4:2
DUAMCO 3 4:2
DUAMCO 2 4:2
DUAMCO 2 4:2
Module 0
Module 0
Module 1
RX CU 5 RXdiv
TX0
SLOT 1
RX CU 4 RXdiv
TX1
Module 0
RX0
RX CU 3 RXdiv
TX0
DUAMCO 1 4:2
DUAMCO 1 4:2
SLOT 0
Module 1
Module 1
SLOT 0
IMN:BTSE BS-240/240XL
2.7.12
DUAMCO 0 4:2 Module 0
RX0 RX1 RX2 RX3 RX0
TX0 TX1
Module 0
SLOT 1
Module 1
RX CU11 RXdiv
TX1
Module 1
RX CU10 RXdiv
TX0
SLOT 2
Module 1
Module 1
RX0
TX0 TX1
TX0 TX1
Fig. 2.52
A30808-X3247-F380-7-7631
DUAMCO 3 4:2
DUAMCO 3 4:2
SLOT 3
Module 0
Module 0
SLOT 3
SLOT2
SLOT 1
RX CU 5 RXdiv
TX1
Module 0
RX0
RX CU 4 RXdiv
TX0
DUAMCO 1 4:2
DUAMCO 1 4:2
SLOT 0
Module 1
Module 1
SLOT 0
IMN:BTSE BS-240/240XL
2.7.13
DUAMCO 0 8:2
RX0 RX1 RX2
CU 0
TX0
Carrier 1
Module 0
RX RXdiv
CU 1
TX2
Module 0
TX1
Carrier 2
Carrier 3
RX RXdiv
CU 2
TX3
RX RXdiv
CU 3
TX0
Module 1
CU 5
RX RXdiv
CU 6
TX0
Carrier 2
Module 1
CU 7
Carrier 3
CU 9
TX0
Module 0
RX RXdiv
CU11
Fig. 2.53
62
A30808-X3247-F380-7-7631
SLOT2
RX3
CU10
TX1
DUAMCO 1 8:2
DUAMCO 1 8:2
SLOT 1
RX3
RX
CU 4
TX1
SLOT 0
IMN:BTSE BS-240/240XL
2.7.14
DUAMCO 0
RX0 RX1 RX2
8:2 CU 0 CU 1
RXdiv RX
8:2 Carrier 1
TX0
Module 0
Module 0
RX
CU 2
SLOT 0
RX3
RXdiv
TX1
Carrier 2
RXdiv RX
TX2
Carrier 3
CU 3
TX3
Carrier 4
RXdiv RX
CU 4
TX0
Carrier 5
Module 1
RXdiv
Module 1
RX
CU 5
RXdiv RX
CU10
SLOT 1
TX1
Carrier 6
RXdiv RX
TX2
Carrier 7
CU11
RXdiv
TX3
Carrier 8
SLOT2
DUAMCO 1 Module 1
RX0 RX1 RX2 RX3 RX0
4:2
RX
DUAMCO 1 4:2 CU 6
RXdiv RX
CU 7
RXdiv RX
TX1
Module 1
TX0
Carrier 1
Carrier 2
Module 0
Module 0
RXdiv RX
TX0
SLOT 3
CU 8
Carrier 3 Carrier 4
CU 9
TX1
RXdiv
Fig. 2.54
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
2.7.15
RXOUT
SMA
TXIN
FICOM BASE#0
HPDU #1
DIAMCO#1
RXOUT
SMA
TXIN
FICOM BASE#1
Fig. 2.55
64
A30808-X3247-F380-7-7631
Cell 1
Cell 0
IMN:BTSE BS-240/240XL
2.8
2.8.1
2 3
2 4 5
64
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
3 11 PCM 0 1 2 PCM 1 13
1 Abis interface on OVPT 0 2 Abis interface (OVPT 1) 3 ground bolts 4 DC terminal 5 CAN bus OUT Fig. 2.57
6 CAN bus IN 7 CAN bus TEST 8 lightning protection alarms 9 serial interface 10 site inputs on ACK
3 3 1 2 9 4 5
A30808-X3247-F380-7-7631
65
IMN:BTSE BS-240/240XL
Some additional hints for the installation of external cabling: The rst cable that has to be installed is the ground cable between the main ground stud on top of the rack and the nearest ground bar on site. The second installation step is to connect the ground stud of the different racks in series. After that all other cables like AC mains, RF cabling or alarm wires can be installed. The screen of the RF jumpers has to be grounded before entering the BTSE via the cable feeding module, see Fig. 2.76. If cables are fed through coaxial cable access located at the top of the rack at the front, the screen has to be grounded like all other coaxial cables. The following figure shows the location of the external interfaces for the BS-240/240XL (example of BS-240 with Service1-, Base- and Extension rack). serial interface cable external alarms / commands Abis lines (OVPT PCM0, PCM1) antenna cables 3 x 230 V AC or 3 x 208 /120 V AC ground cable microwave
SIEMENS
LMT ETHERNET
-48 V DC*
DC-PANEL ACT-C
LE 0 LE 1 LE 2 LE 3 LE 4 LE 5
MUCO #0
MUCO #1
MUCO #0
CU CU #2 #3
CU #6
CU #7
CU CU #2 #3
MUCO #1
CU #6
CU #7
CU CU #0 #1
CU #4
CU #5
CU CU #0 #1
CU #4
CU #5
*) only in case of external power supply Service1 rack Base rack Extension rack
Fig. 2.59
66
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
2.8.2
3 x 230 V AC mains
connection to ground
Fig. 2.60
Ground and AC mains connections of the BS-240/240XL (example) Note, that the connection by screws at the top of racks standing side by side is a mechanical connection only. These connection is not a ground connection ! The figure above shows the recommended cabling for the power supply and ground connections. The recommended cable types guarantees the proper function of the BS240E/240XL, equipped with up to 24 carriers. An easily accessible disconnect device is incorporated into the AC mains supply wiring. To isolate the mains supply 3 x 25 A circuit breakers are connected (one per phase), and are installed in the AC distribution box close to the BS240/240XL. The disconnect device shall simultaneously interrupt all phase conductors.
A30808-X3247-F380-7-7631
67
IMN:BTSE BS-240/240XL
A 5-pole terminal block of the MSU, located in the top of Service1 rack, is the connection point for the AC mains cable. The BS240/240XL will be powered by 3 x 230 V, 50 Hz, 20 A per phase.
PE L3 L2
L1
Fig. 2.61
This warning must appear in the original German text: Vor Anschlu des 3 x 230 V Einspeisungskabels ist sicherzustellen, da das Kabel spannungsfrei ist. Die Hauptsicherungen sind zu unterbrechen. Es sind geeignete Manahmen gegen unbefugtes Einschalten der Netzspannung zu treffen. An imprint, located on the front panel of the AC frame gives instruction how to deenergize the BS240U: To deenergize entire unit : 1) Switch OFF BATT 0 + BATT 1(BR14 + BR15) to deenergize DC circuit 2) Switch OFF breakers (BR11 + BR12 + BR13) to deenergize AC circuit To connect the BS240/240XL with the AC mains connection point proceed with the following steps: Unscrew the bolts in the top extrusions for opening the roof. Remove the roof sections carefully, avoid damages to the paint work. Refer to the site documentation for the required information about type and location of the AC distribution. Check the actual distance between terminal block of the MSU and AC distribution. Remove the insulation of the cable and cut back the wire insulation at the end; that is to be connected to the terminal block. Fix the cable at the strain relief by straps. Insert the wires into the terminals. Use a screwdriver for opening the terminal springs.Check that all wires are in xed position.
68
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
2.8.3
alternative solution for rack grounding DC main wires 2 2 x H 07 V-R 16 mm (BS-240) 2 2 x H 07 V-R 25 mm (BS-240XL) 80 A main breaker (BS-240) 100 A main breaker (BS-240XL) UE -48 V DC power supply unit
+
H 07 V-R 35 mm
50 mm
Fig. 2.62
Ground-and power supply connections with -48V DC Installation of the DC wires is as follows: Ascertain the real distance between rack and the power supply unit or power distribution panel. Cut the wires to the required length. Remove the cable covering (length approx. 12 mm) and x wire end sleeves at the ends to be connected to the terminal block of the MSU (the location is shown in Fig. 2.63). Insert the prepared ends into the terminal block. Check the correct polarity of the connection from BTS to the DC output of the power supply unit.
A30808-X3247-F380-7-7631
69
IMN:BTSE BS-240/240XL
-48 V +0 V
Fig. 2.63
For installation of the ground connection proceed as described in section 2.6.2 of this manual.
2.8.4
70
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
To deenergize entire unit : 1) Switch OFF BATT 0 + BATT 1(BR13 + BR14) to deenergize DC circuit 2) Switch OFF both breaker (BR11 + BR12) to deenergize AC circuit The terminal block for the AC mains input is located at the top of the Service1 rack, accessible after removing the roof.
Make sure that the AC mains cable is deenergized before connection with the BS240. Take measures against unauthorized switch on at the power distribution ! The BS240U rack requires a 2 phase, 3 wire plus ground (PE) connection with the AC mains (208 / 120 V AC, 60Hz), each phase must be protected by branch circuit breaker 70A, UL489, long delay. Install the connection in the following stages: Check the actual distance between terminal block and the connection point. Cut the cable to the required length. Remove the insulation of the cable and cut back the wire insulation at the end; that is to be connected to the terminal block. Lead the prepared cable to the terminal block of the MSU at the top of the rack. Insert the wires into the terminals. Lead the main cable to the connection point for 120 V AC. conductor 208/120 VAC phase 1 208/120 VAC phase 2 neutral conductor protection earth Tab. 2.16 L1 L2 N PE label terminal 1 3 2 4 black brown or black blue yellow/green colour
ground wire #8 AWG ground wire bridges 4x #4 AWG AC distribution AC counter 2 x 70 A main breakers 208 / 120 V 60 Hz AC mains main ground wire #2 AWG or larger ground bar
Fig. 2.64
A30808-X3247-F380-7-7631
71
IMN:BTSE BS-240/240XL
i i
Note: Use only copper conductors for power supply and ground connections ! Note : Before starting installation of Data Circuits and External Interconnection Cables pay attention to the NEC, section 725-54 c). Transient voltage surge suppression and primary protectors are not required at the entry of the wiring to the BS240U if the exposed wiring is limited to less or equal 140 feet. Refer to NEC Article 725 c) and 800-30 for proper clearence of data wiring from power and lightning conductors. The corresponding Canadian Electric Codes (CEC) sections to NEC 800-30 are CEC 600-20 and 60-202. The corresponding CEC sections to NEC 725 c) are CEC 16-200 thru 16-256.Refer before starting the installation of the antenna connections to NEC Article 810.The corresponding CEC Articles to NEC 810 is Section 54. Further pay attention before the cabling works to NEC 770, 810, 800, 810-57, 400-4, 410-57, and CEC Rules 16-224, 54-802, 4-010, 26-708, and sections 56, 54, 60 .
72
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
2.8.5
Use only twisted pair or coaxial copper cables with braided shielding ! The outer diameter of the PCM cable must not exeed 8 mm. The maximum cable length depends on the attenuation of the cable, in order to fulfill the requirements of minimum voltage levels to be provided at Abis interface according to PCM standards. The cable shielding must be connected to the relevant ground pins as close as possible (in order to avoid EMC/RF interfering effects).
2.8.5.1
Fig. 2.65
Cut the cable to the required length (1). Cut back the outer insulation approx.13 cm (2). Remove approx. 11 cm of the braided shield (3).
A30808-X3247-F380-7-7631
73
IMN:BTSE BS-240/240XL
Cut around the outer insulation and shift the insulation ring to the end of the braided shield (4).Remove the foil shields and the additional plastic wires. Remove 6 mm of the wires insulation. Wrap the exposed cable screen, which will be xed at the stress relieving.
Fig. 2.66
Fix the cable at the stress-relieving by straps or screw down the screen clamps (not part of the OVPT, WAGO part-no. 790-108 for outer diameter up to 8 mm or 790-116 for outer diameter up to 16 mm). Insert the wires into the terminals of the OVPT. Insert the additional wire (shielding potential) into one of the ground terminals (e.g. no. 24). Lead the additional wire and the uplink and downlink wires on the shortest route (that means without sleeves) between the stress relieving and the screw terminals. All unconnected PCM lines (4 wires per line) must be connected to one of the ground terminals. EXT SYNC B EXT SYNC A
Down Link = RX
B 1
A 3 5
B 7
B 19
9 11 13 15 17
21 23 25 27
8 10 12 14 16 18
20
22 24 26 28
A PCM 4
PCM 3
PCM 2
PCM 1 Up Link = TX
Fig. 2.67
74
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
Down Link = RX
B 1
A 3 5
B 7
B 19
A 21 23 25 27
9 11 13 15 17
8 10 12 14 16 18
20
22 24 26 28
A PCM 8
PCM 7
PCM 6
PCM 5 Up Link = TX
Fig. 2.68
monitoring interfaces
screen clamps (not part of OVPT) terminals for external PCM cables down link lines up link lines
Fig. 2.69
A30808-X3247-F380-7-7631
75
IMN:BTSE BS-240/240XL
2.8.5.2
Fig. 2.70
For Abis cabling with 75 impedance use coaxial cable e.g. 2YCCY 0.4/2.5. The coaxial cables will be prepared as follows: Fix a 1,0/2,3-female connector for each PCM-up and down line at the end to be connected to the OVPT. Connect the prepared cable to the matching connectors. Use a torque spanner for 1,0/2,3 connector (35 N/cm). Fix the screening at the holes for stress-relieving by straps. signal PCM1-ULA PCM1-DLA PCM2-ULA PCM2-DLA PCM3-ULA Tab. 2.17 1 2 3 4 5 coax connector signal PCM3-DLA PCM4-ULA PCM4-DLA EXTSYNCA --6 7 8 9 --coax connector
76
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
coax connector
coax connector
2.8.5.3
Signal name PCM 1 - ULA GND/G PCM 1 - DLA PCM 1 - DLB PCM 2 - ULA GND/G PCM 2 - DLA PCM 2 - DLB
Function PCM Line 1 Up Link A shield pair 1 PCM Line 1 Down Link A PCM Line 1 Down Link B PCM Line 2 Up Link A shield pair 2 PCM Line 2 Down Link A PCM Line 2 Down Link B
A30808-X3247-F380-7-7631
77
IMN:BTSE BS-240/240XL
Signal name PCM 3 - ULA GND/G PCM 3 - DLA PCM 3 - DLB PCM 4 - ULA GND/G PCM 4- DLA PCM 4- DLB EXTSYNCA EXTSYNCB
Function PCM Line 3 Up Link A shield pair 3 PCM Line 3 Down Link A PCM Line 3 Down Link B PCM Line 4 Up Link A shield pair 4 PCM Line 4 Down Link A PCM Line 4 Down Link B
Signal name PCM 5 - ULA GND/G PCM 5 - DLA PCM 5 - DLB PCM 6 - ULA GND/G PCM 6 - DLA PCM 6 - DLB PCM 7 - ULA GND/G PCM 7 - DLA PCM 7 - DLB PCM 8 - ULA GND/G PCM 8 - DLA PCM 4 - DLB -----
Function PCM Line 1 Up Link A shield pair 1 PCM Line 1 Down Link A PCM Line 1 Down Link B PCM Line 2 Up Link A shield pair 2 PCM Line 2 Down Link A PCM Line 2 Down Link B PCM Line 3 Up Link A shield pair 3 PCM Line 3 Down Link A PCM Line 3 Down Link B PCM Line 4 Up Link A shield pair 4 PCM Line 4 Down Link A PCM Line 4 Down Link B
78
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
2.8.6
X4
X3
X2
X1
X9 X10
X8
X7
X6
X5
Fig. 2.72
Signal name AL0P AL0M (GND) AL1P AL1M (GND) AL2P AL2M (GND) 7 8 9 10 11 12
Signal name
A30808-X3247-F380-7-7631
79
IMN:BTSE BS-240/240XL
Signal name AL6P AL6M (GND) AL7P AL7M (GND) AL8P AL8M (GND) AL9P AL9M (GND) AL10P AL10M AL11P AL11M 1 2 3 4 5 6 7 8 9
Pin no. X7
Signal name AL12P AL12M (GND) AL13P AL13M (GND) AL14P AL14M (GND) AL15P AL15M (GND) AL16P AL16M (GND) AL17P AL17M (GND)
10 11 12
Signal name AL18P AL18M (GND) AL19P AL19M (GND) AL20P AL20M (GND) AL21P AL21M (GND) AL22P AL22M (GND) AL23P AL23M (GND) 1 2 3 4 5 6 7 8 9
Pin no. X4
Signal name AL24P AL24M (GND) AL25P AL25M (GND) AL26P AL26M (GND) AL27P AL27M (GND) AL28P AL28M (GND) AL29P AL29M (GND)
10 11 12
80
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
Signal name AL30P AL30M (GND) AL31P AL31M (GND) AL32P AL32M (GND) AL33P AL33M (GND) AL34P AL34M (GND) AL35P AL35M (GND) 1 2 3 4 5 6 7 8 9 10 11 12
Pin no. X2
Signal name AL36P AL36M (GND) AL37P AL37M (GND) AL38P AL38M (GND) AL39P AL39M (GND) AL40P AL40M (GND) AL41P AL41M (GND)
Signal name AL42P AL42M (GND) AL43P AL43M (GND) AL44P AL44M (GND) 7 8 9 10 11 12
Pin no. X1
Signal name AL45P AL45M (GND) AL46P AL46M (GND) AL47P AL47M (GND)
Additionally to the site inputs at ACTM, there exists the ACTC board, used as a connection board to support single connectors for the internal alarms (FAN, heatexchanger, temperatur sensor, rack in service...) and the DC supply for the FANs, heatexchangers, microwave equipment, smoke sensor and ACT. The ACTC is located in the DC panel of each rack (see Fig. 2.73)
A30808-X3247-F380-7-7631
81
IMN:BTSE BS-240/240XL
HX0 HX1
HX3
SMOKE RDO
ALARM
BB0 BB1
BB2
24
meaning of abbrevations: RDO: rack door open LE0...8: microwave 1...9 SMOKE: smoke sensor BB0...2: battery fuse 0...2
Fig. 2.73
The following table gives information on the connecting of enviromental alarms at ACTM and ACTC. ENVA Alarms at WAGO- block PIN 11, 12 9, 10 7, 8 Indication at LMT Alarm Alarm-Board Connector PIN
0 1 2 3 4 5 6 7 8 9 10 11 12
5, 6
3, 4 1, 2 Microwave AL-0 AL-1 AL-2 AL-3 Environmental Alarms at ACTM and ACTC
Tab. 2.26
82
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
ENVA
Indication at LMT
Alarm
Alarm-Board
Connector
PIN
13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 Tab. 2.26
AL-4 AL-5 AL-6 AL-7 AL-8 AL-9 AL-10 AL-11 AL-12 AL-13 AL-14 AL-15 AL-16 AL-17 AL-18 AL-19 AL-20 AL-21 AL-22 AL-23 AL-24 AL-25 AL-26 AL-27 AL-28 AL-29 AL-30 AL-31 AL-32 AL-33 AL-34 AL-35 AL-36 Environmental Alarms at ACTM and ACTC
ACTM ACTM ACTM ACTM ACTM ACTM ACTM ACTM ACTM ACTM ACTM ACTM ACTM ACTM ACTM ACTM ACTM ACTM ACTM ACTM ACTM ACTM ACTM ACTM ACTM ACTM ACTM ACTM ACTM ACTM ACTM ACTM ACTM
X5 X5 X6 X6 X6 X6 X6 X6 X7 X7 X7 X7 X7 X7 X8 X8 X8 X8 X8 X8 X4 X4 X4 X4 X4 X4 X3 X3 X3 X3 X3 X3 X2
9,10 11,12 1,2 3,4 5,6 7,8 9,10 11,12 1,2 3,4 5,6 7,8 9,10 11,12 1,2 3,4 5,6 7,8 9,10 11,12 1,2 3,4 5,6 7,8 9,10 11,12 1,2 3,4 5,6 7,8 9,10 11,12 1,2
A30808-X3247-F380-7-7631
83
IMN:BTSE BS-240/240XL
ENVA
Indication at LMT
Alarm
Alarm-Board
Connector
PIN
46 47 48 49 50 51 52 53 54 55 56 Note:
AL-37 AL-38 AL-39 AL-40 AL-41 AL-42 AL-43 AL-44 AL-45 AL-46 AL-47
ACTM ACTM ACTM ACTM ACTM ACTM ACTM ACTM ACTM ACTM ACTM
X2 X2 X2 X2 X2 X1 X1 X1 X1 X1 X1
3,4 5,6 7,8 9,10 11,12 1,2 3,4 5,6 7,8 9,10 11,12
1.The Indication at LMT has to be defined by Customer. It will be recommended to use the proposed indication. 2.Connector X9 and X10 are not used Environmental Alarms at ACTM and ACTC
Tab. 2.26
2.8.7
84
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
2.8.8
Antenna Connections
The BTSE has to be connected to the transmit and receive antennas. The antenna configuration and the required cabling are dependent on the site and the type of combining. For detailed information refer to the site-specific documentation or use the corresponding customer documents. For installation and service purposes it is useful to know, which hardware is connected to which cell. The numbering, seen from the top of the antenna pole, starts at an azimuth angle of 0 (north) and rotates clockwise. The first existing cell whose beam centre line lies at 0 or more is defined as cell 0 or sector 0. The next one following in the same direction cell is cell 1 etc. In case of omni cell the cell no. is 0. 0
sector 2
sector angle
directional antenna
N sector 1
sector 0
Fig. 2.74
Jumper cable with a max. diameter 1/2 have to be used because the thick cables from the antenna are not able to enter the racks. With regard to overvoltage protection it is recommended to ground the outer conductor of antenna feeder cables where they are connected with the jumper cables outside the BS240. The antenna cables must be routed through the EMI panel forward to the 7/16 front connectors of DUAMCO/FICOM and to N-type male connector of DIAMCO.
Note that being able to close the doors means that the depth of the right angle connector is not allowed to exeed 45 mm.
A30808-X3247-F380-7-7631
85
IMN:BTSE BS-240/240XL
max. 45 mm
Fig. 2.75
Connect the antenna cables to the combining equipment as follows: Unscrew the front part of the cable feeding module. Route the antenna jumpers to the rack, which has to be connected. For grounding remove outer insulation approx. 60 mm for proper contact with the metal lids of the cable feeding module (see Fig. 2.76). Feed the jumpers through the cable feeding module forward to the front connectors of antenna combiners. Fix the jumpers at the connectors TX/RX of combiners. Bend the jumpers into the correct position for easy closing of cable feeding module. Screw the front part of the cable feeding module in its original position.
Fig. 2.76
86
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
Fig. 2.77
2.8.9
TMA
DUAMCO
CU
Fig. 2.78
A30808-X3247-F380-7-7631
87
IMN:BTSE BS-240/240XL
If a FICOM as antenna combiner inside the rack, the TMA is used in conjunction with a DIAMCO and it only amplifies the overall BTS uplink signal.
TMA
FICOM
Fig. 2.79
If a TMA used together with HPDU, a DUBIAS is required for powering and signalling of the TMA.The configuration is shown in figure below and the installation in Fig. 2.81
TMA
TMA DIAMCO
Fig. 2.80
From FICOM
RXOUT
DIAMCO
Fig. 2.81
88
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
ANT
(input/output towards TX/RX antenna)
BTS
(input/output towards BTS)
ground screw
Fig. 2.82 Bottom view of the Tower Mounted Amplifier
Two 7/16 female connectors, located at the bottom of the TMA (lettered ANT and BTS) are the interfaces for connections to the antenna jumper 1/2 and the feeder cable towards to the BTS. The TMA can be pole-or wall mounted in vertical position only. The following figure shows the location of the external interfaces. For mounting of the TMA may be done as follows in accordance with Fig. 2.83. While still on ground, join each of the 2 brackets with one screw M8, but leave the brackets open. Be sure not to loose the remaining 2 screws. First connect the TMA to the main feeder, then with the jumper cable to the antenna. Do not forget to consider thermal dimensional changes of the main feeder. Position the TMA on the mast/pole and tighten the remaining 2 screws. Connect the grounding cable on the ground screw and the nearest grounding facility at the mast or pole. The grounding cables eyes must have the right size for the TMAs M8 ground screw and the cable should be have an area of at least of 16 mm2. The other end should be safely connected to a well grounded point on the mast. Then the mounting of the TMA is completed.
Note, that the max. diameter of the mast do not exeed 140 mm, if the fixing material will be used as shown in the following figure.
A30808-X3247-F380-7-7631
89
IMN:BTSE BS-240/240XL
Fig. 2.83
The TMA may be also mounted on a wall by means of suitable screws (not supplied with the TMA) The corresponding holes in the mounting plate have a diameter of 9 mm. The proper way of mounting the TMA on a wall varies from case to case. The best method can only be decided by the installer. Please note, however, that the wall itself does probably not provide adequate grounding, it may be insulated.
It is absolutely necessary to prepare and connect an adequate grounding cable to the TMAs grounding point. Pay attention to the thermals dimensional changes of the antenna feeder cable.
2.9
90
A30808-X3247-F380-7-7631
IMN:BTSE BS-240/240XL
3
AC ACOM ACTC ACTM AWG BS BSC BSS BTS BTSE CAN COBA COSA CU DC
Abbreviations
Alternating Current Antenna Combiner Alarm Collection Terminal Connection Board Alarm Collection Terminal for Base/Shelter American Wire Gauge Base Station Base Station Controller Base Station System Base Transceiver Station Base Station Transceiver Equipment Controller Area Network Core Basis Core Satellite Carrier Unit Direct Current Dual Inline Amplifier Multicoupler Duplexer Amplifier Multiplexer Duplexer Bias Path Electro Magnetic Interference Electrostatically Sensitive Device Filter Combiner Global System for Mobile Communication High Power Duplexer Heat Exchanger Link Equipment Local Maintenance Terminal Mobile Station Antenna Multicoupler Network Termination for PCM30 Operation and Maintenance over voltage protection Pulse Code Modulation Radio Frequency Siemens Base Station System
DIAMCO DUAMCO DUBIAS EMI ESD FICOM GSM HPDU HX LE LMT MS MUCO NTPM O&M OVPT PCM RF SBS
A30808-X3247-F380-7-7631
91
IMN:BTSE BS-240/240XL
92
A30808-X3247-F380-7-7631