Beruflich Dokumente
Kultur Dokumente
GROUP - 9
SARFRAZ AHMED BHATTI MALIK MUHAMMAD ASHRAF HAFIZ ADNAN HAMEED MUHAMMAD USMAN MUHAMMAD UMAIR SIBTAIN RAZA
APPROVAL OF PROJECT
PROJECT LOCATION
KALMA CHOWK
Background
1. In March 2010, a presentation was made by NESPAK to Honorable Chief Minister Punjab with recommendations:
Construct 6-lane flyover along Ferozepur road (Cost = 2300 Million Rs.) 6-lane underpass along Main Boulevard (Cost = 950 Million Rs.) In addition to above, four grade separations Costing Rs. 1,800 Millions were also recommended to be taken up in phases at following locations:
0.6 Km
CENTRE POINT
KALMA CHOWK
Walton Airstrip
GULZAR UNDERPASS
LAHORE BRIDGE
KALMA CHOWK
Average Daily Traffic (ADT)
122,940
LIBERTY
74,892
Total Traffic = 396,044 VPD Along Ferozepur Road = 61% Along Main Boulevard = 39%
118,595
KALMA CHOWK
111,283
45,327
78,889
BARKAT MARKET
1.0 Million Road Users per day, (70% along Ferozepur Road)
ITTIFAQ HOSPITAL
QADDAFI STADIUM
HAFIZ ADNAN
Phase 1
Phase 2
6 Lane Underpass along Main Boulevard - Rs. 1.7 Billion Signal Cycle Time reduces to 90 sec (55% reduction). Centre Point underpass to be taken up simultaneously.
Grade separation at adjoining three number intersections to be taken up in near future Costing roughly 1.5 Billion
Phase 3
ALLOTMENT OF WORK
ALLOTEMEN OF WORK
Work alloted through negotiation with transparent processsing and international procedures
Communucation & Works Deptt (C&W) M/S NESPAK. M/S NLC ( National Logestic cell )
ALLOTEMEN OF WORK
Approval: Client: Consultant: Contractor: Agreement Amount: Date of Start: Date of Completion: Rs. 2.30 Billion (Dated 21.03.2011) Communication & Works Department M/s NESPAK (Prv) Ltd. M/s NLC (Pvt) Ltd. Rs.1527.854 Million 02.04.2011 14.08.2011
Time Period:
135 Days
Work schedule from contractor M/S NLC Establishment of site office Traffic Diversion implemented. Design of flyover completed by M/S NESPAK. Site cordoned off with corrugated sheets.
CENTRE POINT
DIVERSION ROUTE
GADDAFI STADIUM
Grid Station
Qasar-eNoor
Lahore Bridge
Ahad Tower
PTCL
Mabarak Centre
KALMA CHOWK
BARKAT MARKET
CENTRE POINT
DIVERSION ROUTE
GADDAFI STADIUM
Grid Station
Qasar-eNoor
Lahore Bridge
Ahad Tower
PTCL
Mabarak Centre
KALMA CHOWK
BARKAT MARKET
MUHAMMAD UMAIR
SALIENT FEATURES
SALIENT FEATURES
60 Km / h 675 m
4 % Max in a length of 120 m 375 m 150 m each side 3+3 11.9 m 10m Wide (3 lanes) 2ft x 3ft on either side of Bridge 135 Days Rs 2.3 Billion (Flyover)
Barkat Market
Center Point
ROW ~ 70 m 18.6 m 11.4 m 3-Lane Flyover 10.0 m Reserved for BRTS 11.4 m 3-Lane Flyover 18.6 m
2.0 m Utility
9.0 m 3-Lanes
9.0 m 3-Lanes
2.0 m
WALTON AIRSTRIP
Mabarak Center
BRTS CORRIDOR
STRUCTURAL MEMBERS
(FLYOVER NO.1+2)
Sr. No.
Pier Stage 2
Total 100 22 4 22
1 2
Pier Stage 1
3
4 5 6 7 8
Piles 4 No
2nd Stage
Transoms Transom Walls End Girders Main Girders
22
22 22 48 168 216
Stressing of Girders
Deck slabs
24
SABTAIN RAZA
Series of coordination meetings with all concerned agencies convened and time schedules have been finalized to relocate the services
BARKAT MARKET
PTCL Lines
CANAL
LEGEND
FLYOVER UNDERPASS
Relocation Schedule
Payment made on March 26, 2011 Start date March 28, 2011 Completion date June 27, 2011
PTCL LINE NTC LINE OFC LINE SEWERAGE LINE WATER SUPPLY LINE GAS PIPE LINE RELOCATED 132 KVA POLE
BARKAT MARKET
NTC Lines
CANAL
LEGEND
FLYOVER UNDERPASS PTCL LINE
Relocation Schedule
Payment made on March 26, 2011 Start date March 28, 2011 Completion date April 27, 2011
NTC LINE OFC LINE SEWERAGE LINE WATER SUPPLY LINE GAS PIPE LINE RELOCATED 132 KVA POLE
BARKAT MARKET
OFC Lines
CANAL
LEGEND
FLYOVER UNDERPASS PTCL LINE NTC LINE OFC LINE SEWERAGE LINE WATER SUPPLY LINE GAS PIPE LINE RELOCATED 132 KVA POLE
GULBERG
18 Pipe Line
27 Pipe Line
BARKAT MARKET
12 Pipe Line
LEGEND
FLYOVER UNDERPASS PTCL LINE NTC LINE OFC LINE SEWERAGE LINE WATER SUPPLY LINE GAS PIPE LINE RELOCATED 132 KVA POLE
GULBERG
12 Pipe Line
16 Pipe Line
BARKAT MARKET
6 Pipe Line
LEGEND
FLYOVER UNDERPASS PTCL LINE
Relocation Schedule
Payment made on March 26, 2011 4 Days required for disconnecting existing lines Start date March 28, 2011 Completion date June 27, 2011
NTC LINE OFC LINE SEWERAGE LINE WATER SUPPLY LINE GAS PIPE LINE RELOCATED 132 KVA POLE
8 Pipe Line
BARKAT MARKET
1 Pipe Line
CANAL
4 Pipe Line
LEGEND
FLYOVER UNDERPASS PTCL LINE
Relocation Schedule
Payment made on March 26, 2011 Start date March 28, 2011 Completion date May 13, 2011
1 Pipe Line
NTC LINE OFC LINE SEWERAGE LINE WATER SUPPLY LINE GAS PIPE LINE RELOCATED 132 KVA POLE
BARKAT MARKET
CANAL
LEGEND
FLYOVER UNDERPASS
Relocation Schedule
Payment made on March 26, 2011 Start date March 28, 2011 Completion date June 27, 2011 Space for relocation has been finalized
PTCL LINE NTC LINE OFC LINE SEWERAGE LINE WATER SUPPLY LINE GAS PIPE LINE RELOCATED 132 KVA POLE
11 KVA Poles
LEGEND
FLYOVER UNDERPASS
Relocation Schedule
Payment made on March 26, 2011 Start date March 28, 2011 Completion date June 27, 2011 Space for relocation has been finalized
PTCL LINE NTC LINE OFC LINE SEWERAGE LINE WATER SUPPLY LINE GAS PIPE LINE RELOCATED 132 KVA POLE
NAME OF AGENCY
LESCO 132 KVA
AMOUNT PAID
36.000
2.
LESCO 11 KVA
50.000
46.159
41.543
3.
WASA (Water &Sewerage PTCL i. Flyover Side ii. Under-Pass Side NTC/ OFC Sui Gas i. Flyover Side ii. Under-Pass Side
Supply
132.392
102.981
92.682
3 Months
4. 5.
108.094 23.894
97.285 21.504
3 Month 1 Month
6.
4.499
4.049
3 Months
TOTAL
716.217 SAVINGS
325.627 390.590
293.063
USMAN AHMAD
Tansom
SUPER STRUCTURE. Girders Deck Slabs New Jerssie Barries and Planters
Barkat Market
Center Point
ROW ~ 70 m 18.6 m 11.4 m 3-Lane Flyover 10.0 m Reserved for BRTS 11.4 m 3-Lane Flyover 18.6 m
2.0 m Utility
9.0 m 3-Lanes
9.0 m 3-Lanes
2.0 m
DECK SLAB
MONITORING
%AGE
2010-11
1094
986
90%
2011-12
1600
245
16%
Sub Base
Base Course (WBM)
913 CM
9030 CM
Bitumen
1062 Ton
86
CONCLUSION
Uninterrupted flow of traffic during execution. Introduction of sleek design in Pakistan. Observation of environmental rules & regulation. Public safety measures. Fast track execution by better engineering management techniques through hour to hour monitoring. Proper coordination among the departments. Project will recoup its original cost within 18 months due to operational cost of vehicles & fuel saving as per economic analysis.
MOC PRESENTATION
THANK YOU