WORKING SEQUENCE

STEP 1

Completion of Bottom shuttering.

WORKING SEQUENCE

STEP 2

Completion of Bottom Nominal reinforcements

WORKING SEQUENCE

STEP 3

GI Ducts Laying

WORKING SEQUENCE

STEP 4

Fixing of ducts at End Anchorages.

WORKING SEQUENCE

STEP 5

Threading of HT strands into Ducts .

WORKING SEQUENCE

STEP 6

Fixing of bar chair to form tendon profile.

WORKING SEQUENCE

STEP 7

Stressing anchorages.

Stressing end Anchorage

WORKING SEQUENCE

STEP 8

Fixing of Dead ends and Fixing of grout vent.

WORKING SEQUENCE

STEP 9

Laying of Tendons on completion

WORKING SEQUENCE

STEP 10

View of PT Tendon after Laying.

WORKING SEQUENCE

STEP 11

Recess Formers at Stressing anchorages

Fixing of anchor Blocks.

WORKING SEQUENCE

STEP 12

25 % of initial stressing.

Stressing of Strands to 100 % force

WORKING SEQUENCE

STEP 13

Mono Jack Stressing Of Slab Tendons.

Paint Mark shows Elongation

WORKING SEQUENCE

STEP 14

ANCHORAGES AFTER STRESSING

WORKING SEQUENCE

STEP 15 A N C H O R A G E S A F T E R S T R E S S I N G

WORKING SEQUENCE

STEP 16

Patching up live end anchorages.

WORKING SEQUENCE

STEP 17

PT Flat slab after Deshuttering.