Beruflich Dokumente
Kultur Dokumente
This Document is currently in its provisional status and is available for public review and comment. As its provisional status denotes, however, it will continue to serve as the basis for further development, pilot validation, and professional editing. While BCA tries to highlight the major points of submission requirements, BCA cannot take into account all the special cases in other regulatory agencies as well as the changing technology. Updated versions will continue to be issued to address and incorporate on-going feedback in an open, collaborative process. All readers of this provisional guide are encouraged to submit feedback to BCA CORENET. No part of these materials should be copied, reproduced or published in any form by any means whatsoever electronic or mechanical including photocopy or by way pf any information storage or retrieval system nor should the material be disclosed to other parties without the express written autorisation of Building and Construction Authority. Information and contents set forth in this document are subject to changes and will be release as updates in subsequent version.
Building and Construction Authority 5 Maxwell Road #16-00 Tower Block MND Complex Singapore 069110 www.bca.gov.sg
Version 2.0 January 2008 Version 1.5 November 2007 Version 1.0 September 2007
CORENET e-Plan Check Team Building and Construction Authority 5 Maxwell Road #16-00 Tower Block MND Complex Singapore 069110
CONTENTS
CONTENTS ................................................................................................................................. i TABLES ...................................................................................................................................... ii FIGURES .................................................................................................................................... ii 1. Introduction ..................................................................................................................... 3 1.1. 1.2. 2. Purpose of Document .............................................................................................. 3 Scope ....................................................................................................................... 3
General Requirements.................................................................................................... 4 2.1. 2.2. 2.3. 2.4. 2.5. 2.6. 2.7. Deliverable Format ................................................................................................... 4 Model Scale.............................................................................................................. 4 Model Orientation and Site Configuration ................................................................ 5 Standard Naming of File and Drawing Views .......................................................... 5 Last Saved Model or Last Saved View .................................................................... 6 Model for Re-submission ......................................................................................... 7 Model for Addition and Alteration Works.................................................................. 7
3.
High-Level Modelling Requirements (Optional) .......................................................... 9 3.1. 3.2. BIM Objects and Properties ..................................................................................... 9 Spaces and Zones ................................................................................................. 11
Appendix A Specific Submission Requirements ............................................................... 12 A-1 A-2 A-3 A-4 BCA-BPD Submission Requirements .................................................................... 12 URA Submission Requirements............................................................................. 16 NEA-CBPU and PUB Submission Requirements .................................................. 22 FSSD Submission Requirements........................................................................... 40
Appendix B Standard Certifications for Building Works................................................... 43 B-1 B-2 B-3 BCA: Qualified Persons Endorsements ................................................................ 43 URA: Qualified Persons Endorsements ................................................................ 46 FSSD: Qualified Persons Endorsements .............................................................. 48
Appendix C Step-by-step Guideline in Preparing 3D Model for Submission.................. 51 C-1 C-2 Users of Autodesk Revit......................................................................................... 51 Users of Other 3D Modelling Tools (eg. Graphisoft ArchiCAD) ............................. 54
Appendix D Naming Conventions of BIM Objects ............................................................. 61 D-1 Building Element (IfcSlab, IfcDoor, IfcOpening)..................................................... 61
TABLES
Table 1 Naming convention for each 3D model or BIM file submitted...................................... 5 Table 2 Naming convention for each drawing view .................................................................. 6 Table 3 Colours used for A&A project....................................................................................... 7 Table 4 Table format of Gross Floor Area Summary.............................................................. 19 Table 5 Table format for number of persons provided with means of escape at each nonresidential storey ....................................................................................................... 42
FIGURES
Figure 1 Schematic diagram showing the steps in preparing the 3D CAD model for submission ................................................................................................................. 4 Figure 2 Sample of A&A project (2D and 3D views)................................................................. 8 Figure 3 BIM containment hierarchy......................................................................................... 9 Figure 4 Sample of site plan view in 3D CAD or BIM model .................................................. 12 Figure 5 Sample floor plan with indication of platform levels and room tags ......................... 13 Figure 6 Sample of floor plan with elevation and section line or marker (highlighted in BLUE) ................................................................................................................................. 14 Figure 7 Sample of elevation or sectional view ...................................................................... 14 Figure 8 Sample of layout view with QPs declaration and companys profile ....................... 15 Figure 9 Sample floor plan view (a close-up) with space boundary (in BLUE) for GFA calculation ................................................................................................................ 18
ii
1. Introduction
1.1. Purpose of Document
The objective of this Document is to assist qualified persons (QPs) in developing 3D CAD models to meet new requirements of Building Information Model (BIM) submission. It describes the requirements and guidance for creating BIM with specific object types, associated properties and presentation format to the following regulatory agencies for visual processing: a. Building and Construction Authority (BCA), Building Plan Department; b. Urban Redevelopment Authority (URA); c. National Environment Agency (NEA), Central Building Plan Unit; d. Public Utility Board (PUB); and e. Fire Safety and Shelter Department (FSSD). The respective regulatory agency reserves the right to reject and request for necessary correction of any required deliverables or formats that do not meet the requirements.
1.2.
Scope
This submission guideline contains a list of requirements written in a concise form to guide QPs in preparing 3D CAD models for submission to the above mentioned regulatory agencies. It is by no means an exhaustive list of requirements of the building works which must be complied with when making a building plan or planning submission. The items in this Standard Guideline may also be amended or revoked when new written laws come into force. For more information or enquiries on the specific submission requirements, please consult the appropriate regulatory agency above. CAD vendors and retailers have developed their own application dependent user manuals. These user manuals should be read carefully as this Document cannot take into account all the special features of individual 3D CAD or BIM application. For any submission requirements mentioned in the Appendices that require customizations to a certain extent, QPs are also advised to make reference to the training model distributed or to consult the respective software vendor for any enquiries on the application. If there are contradictions between this submission guideline and vendors instructions, BCA CORENET e-Plan Check team shall be contacted for clarification.
2. General Requirements
2.1. Deliverable Format
QPs are required to submit 3D CAD model or BIM saved in the following file format upon submission to each of the above mentioned regulatory agencies: a. A single DWF (Design Web Format) file; and b. A single BIM in the native format of 3D CAD tools that are IFC 2x3 certified, including all the standard properties and approved space names in Appendix D. c. For Major project (e.g. phase condominium development), separate BIM files can be submitted for each building. However, a SITE BIM file linking all the buildings should be submitted.
All drawing views below should be compiled in a single DWF file. Refer to Appendix C for detailed steps in publishing to DWF. a. Plans, elevations, sections, layout views or sheets (refer to Appendix A for specific requirements from each regulatory agency); and b. A 3D DWF model, to be included with other drawing views in a single DWF file.
BIM Environment
a. Autodesk Revit; or b. Graphisoft ArchiCAD
STEP 1:
Designing and Modelling Agency
STEP 2:
Customise each drawing view (plan, elevation and section) according to the presentation format as specified in the 3D submission guideline of each regulatory agency
STEP 4:
Submit both DWF and native files (RVT or PLA)
2.2.
Model Scale
All 3D CAD models or BIM submitted for approval have to be drawn in real size as built (1:1) in metric scale.
2.3.
2.4.
M L P 1 _ A
- 0 1 _ A -
Table 1 Naming convention for each 3D model or BIM file submitted Name of Field Project Identification Author Indicators ACELMNSTVXNN Description User defined field for the project Architect Civil engineer Electrical engineer Land surveyor Mechanical engineer Equipment supplier Structural engineer Telecommunication/ Signal engineer Other disciplines Contractor where, N: zone or block number e.g.: 01 for Block 1 A1 for Zone A1 For all blocks st 1 submission nd 2 submission rd 3 submission User defined code for in-house applications (optional field)
-ABC-
Within each DWF or BIM model (either RVT or PLA) submitted to the regulatory agencies, all its related drawing views (plans, elevations, sections and 3D views) and layouts (contain only data information such as qualified persons declarations and schedules) should follow the naming convention below:
Sample:
B C A - _
Name of Field Agency BCA URA CBPU PUB FSSD Type of View SP FP FE FX 3D LV
P
Indicators
ST
S T O R E Y
Description Building and Construction Authority Urban Redevelopment Authority Central Building Plan Unit Public Utility Board Fire Safety and Shelter Department Site Plan Floor Plan Elevation Section 3D View Layout View (should contain only data information, e.g.: QPs declarations and schedules)
View Name
1 STOREY; or ND 2 STOREY; or RD 3 STOREY; or TH N STOREY; or LOWER ROOF; or ROOF MEZZANINE N BASEMENT N X ELEVATION
ST
where, N: Mezzanines number where, N: Basements number where, X: Directions (e.g.: East, West, North, South) where, N: Sections number
2.5.
2.6.
2.7.
Any building works which are to be deleted, removed or demolished must be shown in dotted lines on the plans and presented in a manner that can be easily identified or distinguished, as shown in Figure 2.
IFCProject
Project
IFCSite
Site
Building IFCBuilding
IFCBuildingStorey
IFCBuildingElement IFCWall IFCDoor IFCWindow IFCOpening IFCSlab IFCColumn IFCBeam IFCStair IFCRamp
Building Elements: Walls Doors Windows Openings Slabs Columns Beams Stairs Ramps
IFCSpace
Spaces
Zones
Figure 3 BIM containment hierarchy This section is not intended to prescribe a step-by-step method to create 3D BIM, but to highlight best practices in creating 3D BIM enriched with information of objects or building elements.
3.1.
10
3.2.
11
1.1.4. Dimensions
There shall be indication of building setback and distance between the new building to be erected or the building works to be carried out and its adjacent lot boundary.
12
ventilated; c. the toilet or parking lots for disabled people; and room. d. the location of equipment, plant room and water tank
Figure 5 Sample floor plan with indication of platform levels and room tags
2.
13
Figure 6 Sample of floor plan with elevation and section line or marker (highlighted in BLUE)
14
3.
Figure 8 Sample of layout view with QPs declaration and companys profile
15
A-2
16
17
(http://www.ura.gov.sg/circulars/text/dcdgfahb_d0e4.htm).
Figure 9 Sample floor plan view (a close-up) with space boundary (in BLUE) for GFA calculation b. Service Ducts without floor slabs and voids shall be indicated clearly with crosses; c. If applicable, details calculations on quantum use and secondary use shall be incorporated (please refer to latest Handbook on Gross Floor Area
18
for details of these areas).; e. If applicable, detailed calculations on GFA exemption items shall be incorporated (please refer to latest Handbook on Gross Floor Area (http://www.ura.gov.sg/circulars/text/dcdgfahb_d0e4.htm) for details of these areas).; f. Detailed calculations on Building Coverage and Communal Open Space shall be incorporated.
Blk No. 1
Storey Basement st 1 Storey nd 2 Storey rd 3 Storey Roof Subtotal: st 1 Storey nd 2 Storey rd 3 Storey Roof Subtotal:
Total: Quantum (%): Summary of Incentive GFA Breakdown of Incentive* GFA Thru Carpark Communal Covered Block / Residual Landscaped Walkways Upp Level Areas Areas Linkages
Blk No.
Storey
GFA 2 (m )
Sky Terrace
19
20
21
A-3
22
23
maintenance access to the refuse chute; and e. Roof gutter or scupper drains (if any), parapet walls and railings.
2. Pollution Control
24
g. Locations of air pollution control equipment; h. Containment facility for storage tanks; i. System for treatment and discharge of rainwater collected within the secondary containment facility; j. k. l. Locations of toxic industrial water treatment and disposal facilities; Containment facilities for generator; Air intake/exhaust points for mechanical ventilation system; and m. Car washing bays, garage gully or oil interceptor at basement, if any.
25
d. Refuse chute chambers and sanitary facilities or toilets; e. Restaurant, foodshop and its kitchen/food preparation area, outdoor refreshment area (if any) and washing area, sanitary pipes, drip tray, double floor slab, hood and flue system and grease trap; and f. Common drain.
26
4. Detailed Plan for Sewerage Works (Proposed Sewer/ Sewer Diversion Works) 4.1. Site and First Storey Floor Plan View
In specific, the site and 1 storey floor plan for sewage works shall show the following: a. Boundary of development site shall be edged in RED; b. Outline of neighbouring development plots or buildings or structure within 1km radius; c. Proposed or existing sewer or pumping main or diversion, and their setback distance from building or structures or Drainage Reserve or neighbouring lot; d. Reinforced concrete trench with removable slabs (annotated on the plan) for existing or proposed sewer under building or structures or with insufficient setback from building or structures; e. Invert or top and pipe size levels of the connecting manhole(s); and f. Provision of pump sump or holding tank or sewage treatment plant.
st
27
5. Detailed Plan for Sanitary Works (for Sanitary Plumbing & Drainage System/ Sewer Connection) 5.1. Site Plan View
In specific, the site plan for sanitary works shall show the following: a. Boundary of development site shall be edged in RED; b. Outline of neighbouring development plots or buildings or structure within 1km radius; c. Sewer connection and its pipe size, the invert and top levels of last inspection chamber and the connecting manhole;
28
29
6. Detailed Plan on Sewerage M&E Works 6.1. Electrical Floor Plan View
In specific, the electrical drawings must be endorsed by LEW/ Electrical QP and shall include the following: a. Electrical Single Line Diagram; b. Electrical Control Schematic Diagram; c. Electrical Panel Diagram; and
d. Float Switches or Electrodes Level Arrangement Diagram and the description of their operations.
d. Make and model of pump; e. Centre line of RSJ; f. Ventilation system; g. Indicate the end point of vent pipe connection; and h. Location of control panel.
7. Detailed Plan on Drainage Works Main Development Submission 7.1. Site Plan View
In specific, the site plan for drainage works shall show the following:
30
31
8. Detailed Plan on Drainage Works Proposed Roadside Drain/ Culvert 8.1. Site Plan View
In specific, the site plan for drainage works shall show the following: a. Boundary of development site shall be edged in RED; b. Outline of neighbouring development plots or buildings and MRT tracks, if any, within 100m radius; c. Alignment and extent of proposed drain; d. Highlight the proposed drain; e. Summit point and direction of flow of proposed drain; f. Width and type of proposed drain;
g. Road reserve or widening line or boundary line; h. Drainage reserve lines with dimensions (if applicable); i. j. k. Invert levels, top levels and road or ground levels; Size and spacing of grating covers for closed drain; and Drop inlet chambers and scupper drains.
32
d. Width and type of proposed drain; e. Road reserve or widening line or boundary line; f. Drainage reserve lines with dimensions (if applicable);
g. Invert levels, top levels and road or ground levels; h. Size and spacing of grating covers for closed drain; and i. Drop inlet chambers and scupper drains.
For slab crossing over the existing drain, the floor plan shall show: a. Dimension clearance between cope of drain and soffit of slab; b. Dimension clearance between pile cap or footing and drainwall; c. Endorsement on maintenance and removal of slab by owner as and when required by PUB; d. Safety railings, if applicable; e. Boundary line or road widening line; f. Concrete paving on ground below the slab;
st
g. Cross fall of concrete paving; and h. Show location of slab crossing on site or 1 storey plan.
33
d. Gradient and direction of flow of proposed drain or culvert; e. Clear depth and chainages; and f. Size and type of existing drain at both ends of the proposed drain or culvert.
9. As-built Plan for TOP/CSC Proposed Sewer/ Pumping Mains/ Sewer/ Pumping Main Diversion Works 9.1. Site and First Storey Floor Plan View
In specific, the site and 1 storey floor plan for TOP/ CSC shall show the following: a. Boundary of development site shall be edged in RED; b. Outline of neighbouring development plots or buildings or structure within 1km radius; c. Proposed or existing sewer or pumping main or diversion, gradient, and their setback distance from building or structures or Drainage Reserve or neighbouring lot; d. Reinforced concrete trench with removable slabs (annotated on the plan) for existing or proposed sewer under building or structures or with insufficient setback from building or structures; e. Invert and top levels of the connecting manhole(s); and f. Provision of pump sump or holding tank or sewage treatment plant; and g. Party maintaining.
st
34
10. As-built Plan for TOP/CSC Sanitary Works (Sanitary Plumbing & Drainage System/ Sewer Connection) 10.1. Site Plan View
In specific, the site plan for TOP/ CSC sanitary works shall show the following: a. Boundary of development site shall be edged in RED; b. Outline of neighbouring development plots or buildings or structure within 1km radius; c. Sewer connection and its pipe size, the invert and top levels of last inspection chamber and the connecting manhole; d. Existing sewer or pumping main and their setback distance from building or structures;
35
36
11. As-built Plan for CSC Proposed Roadside Drain/ Culvert 11.1. Site Plan and First Storey Floor Plan View
In specific, the site plan and 1 storey floor plan for CSC drain or culvert shall show the following: a. Alignment and extent of proposed drain; b. Highlight the proposed drain; c. Summit point and direction of flow of proposed drain; d. Width and type of proposed drain; e. Road reserve or widening line or boundary line;
st
37
g. Invert levels, top levels and road or ground levels; h. Size and spacing of grating covers for closed drain; and i. Drop inlet chambers and scupper drains.
d. Type of safety railings, if applicable; e. Thickness of walls, top and base slab; f. Reinforced details and grade of concrete;
g. 300mm thick false bottom; h. Weepholes, hardcore backing and geotextile; i. j. k. l. Lean concrete and hardcore sub base; Aluminium rungs, if applicable; Cross fall of benching; Cross section of ramp within maintenance access, if applicable; m. Steel posts and chains across maintenance access, if applicable; and n. Details of box drain connections within drainage reserve, if applicable.
d. Gradient and direction of flow of proposed drain or culvert; e. Clear depth and chainages; and f. Size and type of existing drain at both ends of the proposed drain or culvert.
38
14. Certified Survey Plan for CSC Development in the Vicinity of/ Affected by Drainage Reserve
In specific, the site plan and cross section view for CSC Survey Plan shall show the proposed structure or foundation which is less than 300mm away from the Drainage Reserve, as well as lots numbers of the drainage reserve, if affected.
15. URA Approved Sub-division Plan for CSC for Site Affected by Drainage Reserve
In specific, the Sub-division Plan or Certified Survey Plan shall indicate the lot number.
39
A-4
40
2. Building Plan (BP) and Fire Protection Plan (FP) 2.1. Site Plan View
In specific, the site plan submitted for FSSD BP and/or FP approval shall include the following: a. Provision of fire engine accessibility in accordance with current Fire Code; b. Designated driveways/ access roads to withstand the operating load of fire engine appliances (to be filled with GREY); and c. Position of external hydrant(s) along public roads in the vicinity of the subject site and additional provision of internal hydrant(s), if any, within the subject site.
2.3. Schedule
Calculations on the designed occupancy load and exit requirement per storey should be summarised according to the format below. These calculations are required even though the submission is for a small part of the storey.
41
Exit doors
Total:
42
43
5. Structural Works and Design Calculations Complying with Acceptable Solutions in Approved Document
Certification by Qualified Person In accordance with Regulation 9 of the Building Control Regulations, I (Name of qualified person for structural works), hereby submit the detailed structural plans and design calculations prepared by me and certify that they have been prepared in accordance with the provisions of the Building Control Regulations, the Building Control Act and any other written law pertaining to buildings and construction for the time being in force. 2. I further certify that these detailed plans and design calculations are in reference to Project Ref. No.: ______________________. 3. Total number of structural plans submitted: ____________ and total number of pages of design calculations in this book: ______________. Certification by Accredited Checker I, (Name of accredited checker), hereby certify that I have carried out an evaluation, analysis and review of the detailed structural plans and design calculations presented herein and am satisfied that there are no inadequacies in the key structural elements. 2. I further certify that these detailed structural plans and design calculations are in reference to Project Ref. No.: ___________________and the key structural elements are consistent with the layout shown in the building plans. 3. Total number of structural plans checked: ____________ and total number of pages of design calculations in this book: ______________. 4. I hereby declare that I have no professional or financial interest in the building works shown in the plans as defined in section 18 of the Building Control Act (Cap 29).
Design
Calculations
with
In accordance with Regulation 9 of the Building Control Regulations, I, (Name of qualified person for structural works), hereby submit the detailed structural plans and design calculations prepared by me and certify that they have been prepared in accordance with the provisions of the Building Control Regulations, the Building
44
with
I, (Name of qualified person), hereby submit the detailed civil defence shelter plans *(and design calculations) prepared by me and certify that (a) the preparation of these civil defence shelter plans are in accordance with the Building Control Regulations; and (b) the civil defence shelter works shown on these plans are designed in accordance with shelter technical requirements. 2. Total number of civil defence shelter plans submitted: _____________ and total number of pages of design calculations: ______________.
*include whichever is applicable
45
B-2
ROAD LINE I, (Name of architect/ professional engineer), confirm that the road reserve lines, the category of the proposed and existing roads and other related road information as shown in the layout plan is in accordance with the current information provided by the LTA.
3. Subdivision Application
I, (Name of surveyor) declare that the building layout tallies with the development approved plans registered as plan ( ) in DC/AP_ES______________ dated __________. I also declare that the setbacks shown on this plan do not deviate more than 3% of the setback as approved under the said development plans.
46
1. I, (Name of surveyor) certify that the strata unit layout is in accordance with the Building Plan approved on date: __________ under BP number: ____________. 2. I, (Name of surveyor) declare that the strata unit excludes all common properties indicated and referred to in the planning permission granted by the Competent Authority under the Planning Act (Cap 232).
47
B-3
FSSD: Qualified Persons Endorsements 1. Fire Safety Works Complying Provisions in Fire Code
BUILDING PLAN (BP) I, (Name of qualified person) NRIC No./Passport No._________________, being a qualified person under the Fire Safety Act, hereby certify that the fire safety works as shown on these plans have been designed in accordance with the provisions of the Fire Code, the Fire Safety Act and any regulations made thereunder, the relevant codes of practice and design guidelines, subject to modifications or waivers under section 27 of the Fire Safety Act.
with
Prescriptive
(FP)
AND
AIR-CONDITIONING/MECHANICAL
I, (Name of qualified person) NRIC No./Passport No._________________, being a qualified person under the Fire Safety Act, hereby certify that the fire safety works as shown on these plans have been designed in accordance with the provisions of the Fire Code, the Fire Safety Act and any regulations made thereunder, the relevant codes of practice and design guidelines, subject to modifications or waivers under section 27 of the Fire Safety Act. I, (Name of qualified person) hereby certify that the proposed ______________ system has been designed in accordance with the provisions of (State the code used).
2. Fire Safety Works with Alternative Solution (Performance-based Fire Safety Engineering)
BUILDING PLAN (BP) OPTION 1 To be completed by the qualified person who is a fire safety engineer and who prepares the plans of fire safety works which include any alternative solution, and the fire safety engineering report. I, (Name of qualified person), NRIC No./Passport No._________________ being a qualified person and a fire safety engineer under the Fire Safety Act, hereby certify that (a) the fire safety works as shown on these plans have been designed in accordance with the provisions of the Fire Code, the Fire Safety Act and any regulations made thereunder, the relevant codes of practice and design guidelines, subject to modifications or waivers under section 27 of the Fire Safety Act; and (b) the alternative solution in the plans, and the fire safety engineering report, satisfy the fire performance requirements in the Fire Code, and comply with the Fire Safety Act and any regulations made thereunder, the relevant codes of practice and design guidelines, subject to any deviation or modification approved by the Commissioner.
48
BUILDING PLAN (BP) OPTION 2 To be completed by a qualified person who is NOT a fire safety engineer and who prepares the plans of fire safety works, and prepares the alternative solution in the plans under the supervision of a fire safety engineer. I, (Name of qualified person), NRIC No./Passport No. _________________ being a qualified person under the Fire Safety Act, hereby certify that (a) the fire safety works as shown on these plans have been designed in accordance with the provisions of the Fire Code, the Fire Safety Act and any regulations made thereunder, the relevant codes of practice and design guidelines, subject to modifications or waivers under section 27 of the Fire Safety Act; and (b) the alternative solution in the plans adheres to the fire safety engineering report. To be completed by the fire safety engineer who is not a qualified person and who supervises the preparation of the alternative solution in the plans of fire safety works, and prepares the fire safety engineering report. I, (Name of fire safety engineer), NRIC No./Passport No.______________ being a fire safety engineer under the Fire Safety Act, hereby certify that the alternative solution shown on these plans, and the fire safety engineering report, satisfy the fire performance requirements in the Fire Code, and comply with the provisions of the Fire Safety Act and any regulations made thereunder, the relevant codes of practice and design guidelines, subject to any deviation or modification approved by the Commissioner.
FIRE PROTECTION (FP) AND AIR-CONDITIONING/MECHANICAL VENTILATION PLAN OPTION 1 To be completed by the qualified person who is a fire safety engineer and who prepares the plans of fire safety works which include any alternative solution, and the fire safety engineering report. I, (Name of qualified person), NRIC No./Passport No._________________ being a qualified person and a fire safety engineer under the Fire Safety Act, hereby certify that (a) the fire safety works as shown on these plans have been designed in accordance with the provisions of the Fire Code, the Fire Safety Act and any regulations made thereunder, the relevant codes of practice and design guidelines, subject to modifications or waivers under section 27 of the Fire Safety Act; and (b) the alternative solution in the plans, and the fire safety engineering report, satisfy the fire performance requirements in the Fire Code, and comply with the Fire Safety Act and any regulations made thereunder, the relevant codes of practice and design guidelines, subject to any deviation or modification approved by the Commissioner. I, (Name of qualified person) hereby certify that the proposed ______________ system has been designed in accordance with the provisions of (State the code used).
49
FIRE PROTECTION (FP) AND AIR-CONDITIONING/MECHANICAL VENTILATION PLAN OPTION 2 To be completed by a qualified person who is NOT a fire safety engineer and who prepares the plans of fire safety works, and prepares the alternative solution in the plans under the supervision of a fire safety engineer. I, (Name of qualified person), NRIC No./Passport No. _________________ being a qualified person under the Fire Safety Act, hereby certify that (a) the fire safety works as shown on these plans have been designed in accordance with the provisions of the Fire Code, the Fire Safety Act and any regulations made thereunder, the relevant codes of practice and design guidelines, subject to modifications or waivers under section 27 of the Fire Safety Act; and (b) the alternative solution in the plans adheres to the fire safety engineering report. I, (Name of qualified person) hereby certify that the proposed ______________ system has been designed in accordance with the provisions of (State the code used). To be completed by the fire safety engineer who is not a qualified person and who supervises the preparation of the alternative solution in the plans of fire safety works, and prepares the fire safety engineering report. I, (Name of fire safety engineer), NRIC No./Passport No.______________ being a fire safety engineer under the Fire Safety Act, hereby certify that the alternative solution shown on these plans, and the fire safety engineering report, satisfy the fire performance requirements in the Fire Code, and comply with the provisions of the Fire Safety Act and any regulations made thereunder, the relevant codes of practice and design guidelines, subject to any deviation or modification approved by the Commissioner.
50
b. In the Publish dialog, navigate to the directory where you want to save the DWF file. c. Enter a file name. Rooms, and click OK. d. Click the Options button, select Export Object Data for Revit Elements and
51
e. Click Print Setup and choose Sheet Size, Paper Placement, Zoom, and other settings. However, it is advisable to keep as the default settings.
f.
Back to the Publish dialog, click on the Selected views/sheets option and select the relevant drawing views prepared for submissions.
52
g. Click Save to publish the 2D DWF file or files. Note: For 2D DWF, ensure that all drawing views are published in Hidden Line mode.
c.
In the Export dialog, navigate to the directory where you want to save the DWF file.
53
b. Drag and drop the 3D DWF file (of the same project) into the Contents of the opened 2D DWF, or vice versa.
c.
54
http://usa.autodesk.com/adsk/servlet/index?id=8683923&siteID=123112
b. Click Publishing Properties and navigate to the directory where you want to save the DWF file, then click OK.
c.
Back to the Publish dialog and select the relevant drawing views prepared for submission. Hold on to Ctrl button for multiple selections. Make sure that DWF is chosen as the Format.
55
d. Choose the option Selected Items at the bottom right of the dialog and click Publish once confirmed. A processing dialog will be shown as follows.
56
Note: DWF Writer for 3D can create 3D DWF files from programs that use OpenGL to display 3D models. Programs that use other methods to display 3D models, such as Microsoft DirectX, cannot use DWF Writer for 3D to create 3D DWF files. b. Click Start -> Autodesk DWF Writer 3.5 -> DWF Writer for 3D. The DWF Writer dialog opens. Do not open a 3D model yet. If you have opened any files, close them.
Note: If you started the DWF Writer for 3D before you started the 3D program, the 3D program will not be shown in the drop-down list. In DWF Writer for 3D, click the Refresh List button.
57
d. Click Browse to open the Save As dialog box and navigate to the directory where you want to save the DWF file, then click Save.
e. Click the Options tab and enable the publishing options as follows. Change the unit of measurement to millimeter (mm).
58
f.
Click OK and on the Status tab, a Waiting message is shown. Go back to the 3D program and open the 3D model view. Autodesk Design Review will open and the published 3D view will be displayed.
IMPORTANT: Do not open more than one model at a time, or the wrong model may be captured. Do not move the mouse pointer over the 3D program while it is capturing the 3D model.
59
b. Drag and drop all the relevant 2D and 3D DWF file (of the same project) into the Contents of the opened 2D DWF.
c.
60
IfcOpening
VENTILATION DOOR_WAY
61
62
CIRCULATION SPACE
63
TOILET
M&E INSTALLATION
REFUSE
CAR PARKING
64
TENANCY_UNIT
FIRE_COMPARTMENT
PARKING_GROUP
REFUSE_CHUTE
65
Acknowledgements
The development of this provisional version of the 3D CAD Submission Guideline has been a collaborative effort among a cadre of very knowledgeable consultants, vendors and processing officers from different regulatory agencies. Significant contributors are listed below:
66
16.
67