Beruflich Dokumente
Kultur Dokumente
Contents
1 2 3 4 5 6 7 8 9 10 11 12 Introduction Site and Surroundings Description of Development Works Description and Methods Site Logistics and Setup Infrastructure Works Safety, Health and Environmental Considerations during Construction Community Liaison and Public Relations Work Force Appendix 1: Logistics Plan Appendix 2: Site Vehicle Access Appendix 3: Site Traffic Study 3 6 8 10 13 21 23 33 35 36 37 38
1 Introduction
This Construction Environmental Management Plan (CEMP) has been prepared and submitted by Lend Lease to satisfy condition number 3 of planning permission reference 12/AP/2797 for the Trafalgar Place project, the Site (previously known as Phase One) which is bounded by Victory Place to the north, Balfour Street to the east and Rodney Road to the south and west. This CEMP contains the construction programme for the Trafalgar Place project which describes the nature of the activities to be undertaken. It identifies the environmental considerations associated with these activities and outlines appropriate measures that will be implemented for their mitigation. This plan identifies implementation of effective management controls, for example the employment of dust suppression methods and use of effectively maintained plant. This plan will set out the management; monitoring, auditing and training procedures that will be put in place to ensure compliance with the relevant legislation and which ensures that any impacts on the surrounding environment are mitigated as far as possible. The issues that have been considered within this document are as follows: Enabling Works Site Logistics Construction Traffic Management Infrastructure Works Works Description and Methods Safety, health and environmental mitigation provisions Community liaison and public relations Work force This document contains the following information to satisfy planning condition number 3: Item A detailed specification of construction works including consideration of environmental impacts and the required remedial measures. The specification shall include details of the method of piling. Engineering measures, acoustic screening and the provision of sound insulation required mitigating or eliminating specific environmental impacts. Arrangements for publicity and promotion of the scheme during construction A commitment to adopt and implementation of the Considerate Contractor Scheme registration. Section 4 - Works Description and Methods 5 - Site Logistics 6 - Infrastructure Works 7 - Safety, Health and Environmental Considerations during Construction N/A piling will not be used on the project.
1.1
A flexible approach to planning, logistics and programming of the Development has been applied to incorporate both the best practice currently available and to allow for future trade contractor input. The Trafalgar Place Project is split into the below construction phases which are further explained in section 6: Pre-implementation works Enabling works Substructure Superstructure Envelope, Roof, Shell & Core Fit Out & External Works The programme for the overall works is set out in the table below. Due to the number of buildings that will be constructed, works will be implemented working across several buildings at once and elements of the works will overlap. The site has been split into two phased handovers as follows: Phase 1 Buildings R1A, R2A, R2B, R2C, R2D, R2E1 March 20152 Phase 2 Buildings R1B and R1C May 20152 Activity Start Date Finish Date
Pre-Implementation Works June 2013 Enabling Works and Substructure i.e. implementation of the works
July 2013
July 2013
January 2014
Superstructure
September 2013
June 2014
November 2013
January 2015
November 2013
May 2015
1 2
See below for site planning and building references Dates are subject to change and are provided to give guidance on the period of works
November 2013
May 2015
The Pre-Implementation works will include: installation of site hoarding excavation and levelling of the site Installation of temporary accommodation Installation of temporary service connections Works to trees including tree felling, pruning and protection The Enabling and Substructure works will include: installation of drainage, crane bases, raft foundations and erection of the substation housing further works will include completion of pre-implementation works installation of temporary crossovers for site access The Superstructure works will include: erection of the building cores, concrete frame, Cross Laminated Timber (CLT) frame to the upper floors of buildings R2B and R2C installation of insitu and pre-cast stairs The Envelope, Roof, Shell and Core works will include: initial Mechanical, Electrical and Plant (MEP) fixings brickwork, glazing, internal structural frame system skin, timber cladding and rainscreen cladding works all roofing works and installation of external doors The Fit Out and External works will include: internal installation for MEP, drylining, decoration, furniture, fixtures and fittings, floor finishes, concierge desk all public realm and courtyard landscaping including that externally to the red line (Section 278 works) Provision of offsite trees outside of the planning red line
The consented Heygate Masterplan to the west and northwest of the Site, which will provide for the redevelopment of a 9.71 hectare site for a maximum of 330,741 sq m (GEA) mixed use floor space comprising of residential, retail, business, community and leisure, and sui generis uses; The consented Stead Street development to the south of the Site, which will provide 140 residential units, a new church hall, and a retail unit. It is understood that construction will commence on this site at a similar time to that of Trafalgar Place. The Larcom Street Conservation Area is located to the west of the Site.
3 Description of Development
This chapter outlines the detailed planning permission.
Building Heights: Plot R1: R1A 10 storeys with a 7 storey element to the south of the building R1B 7 storeys, stepping up to 8 storeys to the west of the building R1C 4 storeys at Balfour Street end, stepping to 6 storeys to the west Plot R2: R2A 9 Storeys R2B 4 Storeys R2C 5 Storeys R2D 5 Storeys R2E 4 Storeys
Figure 3.1
4.2
The following pre-implementation works will be carried out; elements of this work will continue into the enabling works period: Statutory notifications and consents if required, for example HSE asbestos notices, hoarding and scaffold licences, road closures and alterations etc Submission and approval of method statements and risk assessments, scaffolding and temporary works designs Installation of perimeter 2.4m high hoarding and both vehicular and pedestrian gates to Rodney Road and Balfour Street to facilitate a haul road between Rodney Road and Victory Place (please refer to Appendix 1: Site Logistics Plan for further information) Connections to temporary utilities for site accommodation Installation of site accommodation and welfare facilities Facilitation of tree pruning, tree removal and installation of tree protection measures as per the Tree Protection Plan submitted to satisfy planning condition number 26 Establishment of fire escape routes / systems & emergency plans Installation of temporary power, lighting and water services
4.4
The following works occur at the same time as the enabling works detailed in section 4 and include: A reduced level dig for the raft foundations, the storm water attenuation tank, the tower crane bases, deep drainage and service ducts for the CHP distribution etc. will be undertaken. New foundations will be concrete raft construction of varying thickness. Three tower cranes will be erected in due time to assist with the erection of the frame formwork and concrete placing. The tower cranes will also be utilised for the superstructure, the SFS frame, the scaffold erection/scaffold strike, the brick work and rain screen cladding faades, the bulk loading out and the balcony install. Static or mobile concrete pumps will be employed in placing concrete.
10
Larger mechanical plant may be placed as ground level construction proceeds for ease of access. Excavate, lay and test underground drainage, coordinate and install incoming services to plot, backfill including concrete surround and drainage suspension system Trim and prepare ground floor slab formation including concrete blinding and waterproofing system; Install ground floor slabs where ground bearing/raft Fix rebar, shutter and pour ground floor slabs
4.5
The superstructure works include: All buildings will utilise traditional reinforced concrete formwork methods, however buildings R2B and R2C have two and three floors respectively of CLT (Cross Laminated Timber) above two floors of RC Concrete framing. CLT is a modern means of construction utilising mechanically dried Spruce timber boards from sustainable sources, glued at right angles between 3 and 7 layers thick, dependant on the structural requirements and fabricated off site. As a whole, CLT is a more efficient and sustainable building material than traditional resources, being prefabricated off site it can be constructed faster whilst reducing the buildings carbon footprint. Set up safety exclusion zone around the foundations, fix core wall steel and assembly core wall shutters Core shutters will be installed as the frame rises, operative access to the working decks will be via Haki staircases, rebar lifted by tower crane, concrete pumped using concrete placing boom supplemented by tower crane Pre-Cast concrete Core stairs will be installed as soon as the deck and core is completed and shutters removed they will be progressively installed as the frame rises. The floor slabs will be constructed using traditional formwork methods Pre cast Stairs will be installed in the cores as early as possible to provide operative vertical access to reduce reliance on external Haki staircases.
4.6
The raised courtyard structure will comprise of suspended reinforced concrete slabs with vertical concrete elements constructed using traditional formwork methods, it is planned to be completed as early as possible to give an additional material logistics area, and also once waterproofed it will provide the roof to the Lend Lease Welfare and Office area based in the Car Park.
4.7
Cladding to the buildings will predominantly be single skin masonry with a steel frame system or similar panellised backing wall. Materials will be handled by tower cranes, tele-handlers and goods/ passenger hoists operating externally to the facade. Access for operatives will be from inside the floor plates of the new building and from Haki stairs attached to the external scaffolds. At completion of the lift installation, beneficial use will be allocated for distribution of materials only. Balconies will be prefabricated structures erected by tower crane with operatives accessing bolted connections from the adapted scaffolding surrounding the building. Balconies are installed as the scaffold is struck. Where required, mechanical plant and roof materials will be placed by tower crane. Once this is complete the cranes will be used to install the balconies.
4.8
Fit Out and Finishes and external works (from circa November 2013)
11
The fit out, finishes and external works include: The roof waterproofing system will be installed as soon as the roof concrete slab has cured to achieve the earliest watertight date for all buildings; Fit out of residential units including bathroom construction will use traditional techniques and trade sequences, serviced by tower cranes, loading bays, external hoists and beneficial use of lifts in the buildings. Residential units will be completed from roof downwards and handed over following hoist removal and mechanical and electrical services commissioning. As the envelope completes the tower cranes and electric hoists will be removed. Operative movements and materials for the fitting out of apartments will continue with the beneficial use of the internal lifts. Throughout the fit out, prefabricated components will be utilised where practical to limit the extent of site works. The carpark will provide residential car and motorcycle parking, cycle storage and include associated access/egress. Public realm landscaping to Paragon Row, Balfour Street, Rodney Road and Victory Place Completion and installation of Section 278 works these works outside the site will be phased in such a way to minimise disruption to users of the surrounding streets, some temporary footpath and road closures will be required to complete these works which include: o Victory Place o Rodney Road works to the end of Paragon Row, Victory Place, the cycle crossover and layby o Balfour street formation of new carpark entrance and works to the end of Victory Place and Paragon Row, installation of new street trees and service diversions, Landscaping of the raised courtyard Landscaping to front and rear gardens for ground level homes
12
5.1.1 Pre-Implementation Works and Enabling Works (including drainage and foundations)
During the first 6 weeks of the works, the site will be fully enclosed by a 2.4m high hoarding system. Vehicular and pedestrian security gates will be installed on Rodney Road (access) and Balfour Street (egress). During the earliest elements of the works, access and egress will be via Balfour Street as a temporary crossover needs to be formed across the pavement on Rodney Road to form the main site vehicular access point. Formation of the temporary crossover will take place during the school summer holiday period in July 2013 to maintain the safety of the schoolchildren and minimise the impact on local residents. A temporary footpath will be installed during the crossover construction as discussed with LBS Highways within the boundary of the site Formation of this temporary cross over will ensure that disruption to residents is minimised as far as possible as it will eventually provide one way access through the site during the main works phase which will reduce the traffic impact to both Balfour St and Rodney Road. This also provides the ability to manage traffic flow safely; negating the need for vehicles to travel in and out of Balfour St to access the site. The tree protection zones will be established as described in the details submitted for planning condition 26, fenced and signage placed. Temporary site cabins and welfare cabins will be delivered and placed in an area not affected by the enabling works. Suspension of some of the parking bays on Balfour Street will be agreed with the Local Authority to provide a pit lane for lifting of materials and waste management for the site. This will be in place for approximately 12 months from August 2013 and will operate during the hours of 7.30am to 5.30pm. The pit lane will be formed of Water filled Jersey barriers and managed by a traffic marshall at all times. The pit lane will still allow good cyclist and vehicular access down Balfour Street. Pedestrian access will not be available during operation of the pit lane down this side of Balfour Street, however the other footpath will remain open. Utilising a vehicular pit lane, avoids double handling by the tower cranes (jockey lifts), the pit lane is deconstructed outside of the site working hours and weekends. See Appendix 1: Logistics Plan.
13
Following construction of the temporary crossover for the first 3-4 months of the works, the vehicle count will be high due to the volume of excavated material, steel reinforcement and concrete deliveries which will be required, please refer to Appendix 3 for Vehicle flows. HGVs at this stage of the works will mostly be shorter wheelbase rigid vehicles (muck away and concrete) and will enter the site from Rodney Road and exit onto Balfour Street. Wheel cleaning facilities will be provided at the site exits using large collection gullies and water hose as the site is not large enough to warrant a fully automated drive-on wheel wash. Concrete will be delivered directly to the point of pouring by concrete wagon or poured into a concrete pump for access to all areas of the site. Sheet materials (hoardings and accommodation) would generally be offloaded by a suitable vehicle i.e. vehicle with crane attachment, forklift or rough terrain tele-handler. Temporary footpath closures and diversions will be installed as required whilst the hoardings are erected and there will be a major temporary footpath diversion whilst the temporary vehicle crossover is formed for the site entrance on Rodney Road
5.1.2 Crane Bases, Service Ducts, Tower Crane Erection, RC Frames and CLT Frames
The crane bases will be constructed as reinforced concrete raft foundations with a tower crane mast section cast within, they will be set low enough to be sacrificial, the level will also allow for the service ducts and drainage to pass above them if required. Erection of the tower cranes will commence upon proof of Cube test results reaching required strength. The reinforced concrete frames will commence on buildings R1A followed by R2A and R2E following the erection of the tower cranes and continue across the site. These are identified on the logistics plan. Generally, the construction of the Development is concrete frame, however, the upper levels of buildings R2B and R2C will be constructed from cross laminated timber (CLT) frames once the lower two floors have been constructed. This means that the apartment levels of these buildings will be constructed from CLT and this will commence during Q1 2014. Use of CLT on Site is a modern method of construction and will provide a number of benefits both during the construction process and following completion. CLT is a material which is comes in sections ready to assemble on site and requires only a small skilled team to erect the structure. The installation process itself will be a much quieter and quicker process than concrete frame and will also provide a safer environment both for operatives and the community whilst it is assembled. Following practical completion, it will provide benefits to residents as it has good insulator qualities and air tightness which will require less heating. As the material is timber, it is also much easier to undertake DIY. CLT sequesters carbon and does not create as much carbon emissions as concrete construction.
14
Bulk roofing materials and stair case pop-ups will be delivered by tower crane to roof level. Platform hoists will be taken to roof level for on-going sundry materials and final roof materials.
5.1.4
Fit Out
All materials for the fit out will be delivered using a Just In Time (JIT) approach and will be distributed to working floors by the methods described above including tower cranes, hoist and beneficial use of the passenger lifts.
5.2
All statutory consents & licences required to commence an onsite activity will be obtained ahead of elements of works commencing and allowing for the appropriate statutory notice period. These will include: Notices for works on the Highway in accordance with the Highways Act 1980 (Ref 5-5) and Road Traffic Act 1998 (ref. 5-6) Hoarding and scaffold licences for works on the perimeter boundary Construction Notices Section 61 of the Control of Pollution Act: 1974 Connections to existing utilities and main sewers Licence to discharge water from the Site into the public sewer Approval of the CEMP Consents will be obtained from the relevant authority where tower cranes oversail the public highway The construction programme and precise requirements for aeronautical obstacle lighting to the mast of the tower cranes will be discussed with the appropriate airport and the Civil Aviation Authority when the construction programme and crane methodology is finalised and prior to work starting on the tallest building on the Site
5.3
Upon taking possession of the Site, the first stage of the construction programme will be to establish the area as a construction site The working areas will be secure and the general public will be separated from the works by the use of solid timber hoarding, vehicular gates and pedestrian gated entrances. Where required, temporary hoardings will be provided on short term boundaries All site facilities will be contained within the site area All gates will be maintained by security officers during working hours Flood-lighting in areas adjacent to sensitive receptors (i.e. nearby residential properties) will generally be limited to the working hours identified in this document Site lighting will be kept to a minimum taking into account the needs of site health, safety and security
5.4
Asbestos Removal
It has been assumed that there will be no asbestos on site due to all the previous structures having been removed. In the eventuality of asbestos discovery, its removal will be undertaken in line with industry best practice and statutory requirements and the relevant notices will be served.
15
5.5
Demolition
Demolition of the buildings has already been undertaken on site to ground level. Demolition and removal of the existing substation and housing and the previous building foundations forms the basis of a works package managed by Lend Lease on behalf of the London Borough of Southwark, which upon completion will leave the site clear for the pre-implementation and enabling works.
5.6 Hoarding
The current fencing around the site will be replaced with 2.4m high hoarding. Security gates will be installed at the Rodney Road/Paragon Row, Balfour Street/New Carpark Entry and Balfour Street/Paragon Row junctions. Please refer to Appendix 1: Site Logistics Plan. Additional pedestrian gates with turnstile security will be installed off Victory Place. When specific works within the highway are required these will be secured by temporary hoarding
16
5.9
Contractors and their subcontractors will maintain a tidy site and operate a Just in Time policy for the delivery and supply of materials for the works in order to minimise disruption to the local community. This is particularly important during the final phase of the works when on site storage will be at a minimum; Any materials that are required to be stored on Site will be sufficiently protected to minimise damage by vehicles, vandals, weather or theft; Tanks and drums of liquid chemicals and fuels are not encouraged but where unavoidable they will be stored in bunded compounds. Packaging will be returned, wherever possible, and minimised by design Deliveries of potentially hazardous materials will be supervised and a Just-In-Time delivery system will be implemented to minimise storage times and reduce the risk of environmental incidents on the Site; Tower cranes will be used for general unloading and hoisting during the structural and envelope works. Where unloading in the pit lane (see 5.1.1) is required, provisions will be agreed and licensed with Southwark Council. Passenger/goods materials hoists will be used to hoist materials to the floors, and fork lift trucks used to distribute and transport faade materials to loading bays and hoist positions along Paragon Row.
17
Dedicated circulation routes for site spoil movement will be set up and segregated where possible from the material delivery route. For large pre-planned loads, or abnormal loads, Southwark Council, Metropolitan Police guidelines and designated routes will be complied with. Site routes within the Development will not change during the construction sequence and are designed to provide the safest, most economical traffic circulation and the minimum environmental impact through noise and dust. Site personnel access to the site will be via security-manned posts/gates and will be segregated from on-site construction traffic by means of vehicular barriers/fencing/hoardings etc. A Traffic Management Plan will be developed for the project (in accordance with the HSE Guide The Safe use of Vehicles on Construction Sites) prior to works commencing. This will take into account current legislation, Police, Fire Authority and HSE Guidance, Local Authority Transport Schemes and neighbourhood Lorry Restrictions. The Traffic Management Plan will be reviewed and updated in line with the construction programme and will typically include details of the following:
Temporary traffic control measures; Temporary and permanent access to the works for personnel/vehicles; Off-loading and storage areas; Traffic management procedures for waste disposal vehicles; Personnel and vehicle segregation; Equipment, e.g. road cones, temporary fencing and signage etc; Ensuring all work is planned and method statements prepared detailing safe systems of work; Ensuring that all sub/trade contractors make adequate provision for vehicle selection and supervision of drivers; i.e. their own Banks men/Traffic Marshall Making vehicle safety an integral part of the Development health and safety plan; Defining standards for driver competence, vehicle safety and maintenance; as per the Southwark Council and TfL guidelines and initiatives. Ensuring co-ordination and co-operation between contractors; Ensuring all workers receive site induction training covering safe traffic routes and site rules for operating vehicles; Establishing safety monitoring procedures for the use of vehicles on site e.g. permit to work etc. ; and HGV drivers working on or delivering to the site will be required to undertake the Southwark Council cyclists awareness course.
18
would use Blackfriars Road, Farringdon Road to Euston Road to the north. Please see Appendix 2: Site Vehicle Access The construction programme commences in Q3 2013, there will be a peak in HGV trips coinciding with the busiest periods of construction please refer to Appendix 3: Site Traffic Study On the basis of 5 working days per week and a 10-hour working day, five to six hourly HGV construction trips may be expected within the peak period as outlined in Appendix 3. For most of the construction programme, vehicle numbers will approximately be half compared to the peak periods as outlined in Appendix 3: Site Traffic Study. Movements of large or unusual loads will be addressed in advance with the relevant highway authorities and the police in order to ensure compliance with regulations and to provide advance notification for local residents. The Site is located close to the Elephant and Castle rail and underground stations and a number of bus stops. Given this proximity to public transport services, it is envisaged that the majority of construction personnel would travel to Site by public transport, there is no provision for onsite parking and this will be advised in placement of Contractors Orders and further reinforced during the site inductions. In addition, the passage of vehicular traffic to and from the Site would adhere to the environmental procedures contained within the Environmental Management Plans and enforced on all contractors involved within the Development.
19
20
6 Infrastructure Works
6.1 Utility Infrastructure Works
Separate soil / waste and rainwater drainage has been designed to connect to the existing below ground drainage infrastructure
6.2
The development includes amendments to Victory Place. This involves removing the turning head and rationalising the kerb to the north of building R1A as contained within the Planning permission. The works also include installation of bollards and raising of the roadway to create a shared surface. A new layby and cycle turning point is being installed on Rodney Road and new car park entry from Balfour Street which amend the footpath slightly in line with the planning permission. No further permanent or long-term footpath or road diversions or closures outside of the Site are envisaged, should this situation change consent would be obtained from Southwark Council. Furthermore, prior notices regarding planned closures and diversions of roads would be given to the Metropolitan Police, the London Fire and Emergency Planning Authority (LFEP) and other emergency services.
6.3
Utilities Diversions
Utilities disconnections have been undertaken as part of the demolition completed by LBS process to provide a clear site. There will be limited utility diversions required for installations of trees on Balfour Street and potentially on Rodney Road for works to the lay by and carpark entry. Disruption to existing services and highways will be minimised where possible, however, this will be dependent upon discussions with the statutory providers. Lend Lease will manage the installation of the utility infrastructure within the site to the point of connection on the site boundary. Lend Lease will coordinate the routes for on-site distribution of new utility services thus avoiding any tree root zones and soft landscaping.
6.4
Public realm
21
22
23
That adequate multi-lingual supervision is provided so as to ensure that employees continue to be adequately and effectively informed and supervised on all matters affecting their health and safety That suitable bi-lingual arrangements are in place to ensure that statutory related matters are complied with All contractors will be required to adopt the Construction Skills Certification Scheme (CSCS) or equivalent skills certification. This will be combined with the Lend Lease in house Incident and Injury Free (IIF) health and safety training scheme for 100% of personnel involved with the project including all sub-contractor personnel who will be involved in the project for over a day. General operatives will be required to complete the health and safety training element of the CSCS scheme and may be given the opportunity to pursue a relevant NVQ qualification. All contractor supervisors will receive additional Lend Lease training, this is a pre requisite to any orders being placed. A formal Health & Safety Policy Statement will be adopted, in accordance with the requirements of the Health & Safety Executive and other statutory and local authority guidelines. Compliance with the following mandatory provisions will be carefully monitored and where required enforced: COSHH, 1999 Provision and Use of Work Equipment Regulations, 1998 Highly flammable Liquids & Petroleum Gases Regulations, 1972 Health & Safety at Work Act, 1974 Mandatory attendance at Lend Leases Incident & Injury Free (IIF) training programme
7.2
All substances coming onto site and all work activities which may involve or generate hazardous substances will be managed and controlled in accordance with the Control of Substances Hazardous to Health regulations (COSHH), 1999 and best practice guidance, such as that published by the Environment Agency. Examples of the control measures to be employed are as follows: All fuels and chemicals will be stored in designated areas, with deliveries of all hazardous materials supervised Storage tank or container facilities will be appropriately bunded with designated areas as far as possible from any watercourses or surface drains In case of spills or discharges, immediate remedial action will be undertaken in line with Lend Leases Health and Safety Plan. A logistics plan will be developed to take into account the management and control of hazardous substances on site. Personal protective equipment (PPE) suitable to prevailing conditions will be used by all construction workers.
7.3
24
Spills or discharges to the atmosphere, water supplies, sewerage systems, rivers and other watercourses, or to the ground of:
Any chemical product or formulation Oils and fuels Effluents/fumes and gases Waste or contaminated materials
Damage to existing:
25
7.4
Where trees are identified for retention construction work will be undertaken in accordance with relevant guidelines in BS 5837 : 2005 Trees in relation to Construction recommendations to ensure that any construction within close proximity of these trees is undertaken without significantly impacting on them. An arboricultural method statement will be produced detailing step by step mitigation procedures required when working close Retained trees will be adequately protected from damage throughout the demolition and construction works, tree protection measures will include some or all of the following: Assessment of location of roots The Root Protection Areas (RPA) will be designated as a construction exclusion zone (CEZ) within which trees will be protected from activities that have a potential to cause damage. CEZs will be appropriately protected, e.g. fencing. Any works within a CEZ will need to be undertaken by hand. generated in accordance with BS5837:2012provides a sufficient precautionary zone where rooting conditions are more or less open, unobstructed and level Where root conditions are such that it is not possible to confidently accept the RPA as providing a more or less accurate illustration of the location of roots then it will be necessary to carry out soil investigation to ascertain location of roots Prepare detailed Arboricultural Method Statements for specific operations near trees Training (e.g. tool box talks) in how to avoid tree damage Facilitation Pruning Supervision of sensitive operations and regular monitoring by an Arboricultural Consultant Appropriate Tree Protection Fencing and Barriers Appropriate Ground Protection measures Contingency planning. Works close to TfL Highway Routes: Works shall be carried out in accordance with Southwark Council and TfL approval procedures for all activities in close proximity to existing assets.
7.5
Air Quality
26
7.5.5 Dust
Control measures would be implemented to prevent the release of potentially contaminated dust entering the atmosphere and / or being deposited on nearby receptors. These would include the use of water sprayers and hoarding, dust covers, the restriction of drop heights onto lorries and appropriate storage locations of dusty materials. Dust control will be best achieved at sources, and if possible activities will be carried out in a manner so as to preclude dust generation. Dust levels will be controlled and, if required, consent sought from the Southwark Council under the Control of Pollution Act 1974, Environmental Protection Act 1990 and local policy guidelines, to ensure that the Development is operated in a way which is not detrimental to the amenity of local residents. If dust is generated, steps will initially be taken to protect workers in the vicinity who shall, as a minimum, be issued with dust masks. Dust will, if possible, be contained in the location in which it is generated, and be controlled and managed therein. Dust suppression measures will be carried out to ensure that dust nuisance affecting neighbouring properties is minimised.
27
Dust emissions from construction will be controlled through careful pre-project planning and effective site management. The following control measures and good management practices, will be employed:
Site operations will be planned to take into account local topography, prevailing wind patterns and local sensitive receptors e.g. schools, residences and ecological designated sites; Burning and materials on site will be prohibited; Loading and unloading will only be permitted in designated areas; Provision of water sprays and wind/dust fences where possible, particularly in dust sensitive locations, for example, during demolition works. Water spraying and/or screening will be undertaken prior to and during demolition; Stockpiles of soil, arising or other granular material will be sheeted and/or treated using Dust Buster or similar to prevent dust raising that may cause risk to health or nuisance to the public; An appointed person will oversee/control activities and handle complaints; and Dust on tree foliage will be minimised where practical.
7.6
Ecology
All construction works will be carefully planned and managed to minimise and mitigate their potential environmental impact through implementation of this plan as agreed with all relevant statutory bodies (Southwark Council, the Environment Agency (EA) and Natural England). Procedures to minimise risk of pollution incidents relating to machinery or building materials will be as agreed with the EA and facilities installed for rapid appropriate response to any accidental spillages. During ecology surveys carried out at the Site in 2011, no suitable roosting habitat for bats was found to be present, so it is highly unlikely that disturbance of bat roosts during tree removal works will occur. Notwithstanding this, should roosting bats be discovered during tree removal, works will cease and an appropriate mitigation strategy will be agreed with and approved by Natural England. The removal of trees on the Site will be undertaken outside the bird breeding season, wherever possible. However, where works are required to be undertaken during the bird breeding season an ecologist will inspect any trees to be felled, scrub and/or tall vegetation to be cleared within 24 hours prior to clearance. A strategy of eradication or control of noxious weeds will be developed before works commence. Monitoring, control and eradication will take place on a continual basis. Japanese Knotweed (Reynutria japonica) has not been identified to date.
7.7
28
by contractors to minimise the disturbance to local residents and other potentially sensitive receptors. These measures would include: appropriate and well maintained hoardings constructed on the boundaries of adjacent noisesensitive premises; careful selection of construction methods and plant, including its location, to be used; switching off plant when not in use; regular maintenance and servicing of vehicles, equipment and plant; operational hours (to be agreed with Southwark Council); the use of temporary acoustic barriers where appropriate and the use of enclosures and screens around noisy fixed plant where practicable; appropriate handling and storage of materials; damping down surfaces during dry weather; the use of dust screens; adherence to relevant British Standards; and An appropriate choice of plant that would ensure compliance with the vibration targets agreed with Southwark Council.
7.8
29
7.9
Waste
Minimising raw material waste through analysing design and construction techniques where possible A commitment to develop waste minimisation opportunities by maintaining a role in the management of the supply chain during construction. Measures such as bulk buying will be utilised to facilitate this. Liaison with suppliers to enable packaging material is to be sent back for reuse, the use of off-cuts where possible and the recycling of off-cut material by the supplier Engaging contractors in the process of maximising the use of recycled aggregates for hardcore and alternative cements according to application
To ensure compliance with legislative requirements, only Environment Agency licensed waste hauliers, waste management contractors and landfill sites will be used Suitable protection measures will be incorporated in the design of the waste management area to prevent pollution, and regular inspections carried out to ensure that stored waste is covered by present accidental spillage and from being blown away Movement of waste by haul road and public highways will avoid, where possible, the use of access routes through residential areas. When leaving site, vehicles will be sheeted/covered to prevent any escape of materials onto the public highway Waste transfer notes will be retained and will fully describe the waste in terms of type, quantity and containment in accordance with relevant regulations. Information regarding the type and quantity of material returned to the supplier and the contractor or contractors will also hold copies of all waste documentation
30
Materials stored on Site for disposal (e.g. spoil arising) will be subject to the provisions of the duty of care, and may require a waste management permit. Where this is identified the permit or any exemption will be managed by Lend Lease
Discharge to public sewers after prior agreement with Thames Water The existing storm water drainage system will be retained where possible during construction, with modifications made as necessary to prevent ingress of debris utilising silt traps etc. Discharge via sediment traps/settlement tanks or ponds Installation of interceptors Control of spoil and other materials to prevent spillage, particularly during period of high local surface flood risk (September to March), and through appropriate handling and selection of spoil/material storage locations Issues relating to contaminated land affected by the construction, together with proposals for protection of surface and groundwater All drainage arrangements will be determined in consultation with the Environment Agency and Southwark Council Careful siting and bunding of fuel storage facilities and any areas used for the storage of potentially hazardous materials
Appropriate construction techniques will seek to ensure that groundwater seepage into excavated areas does not take place Subject to appropriate discharge consents, water arising during excavation works will be discharged to the surface water drainage network after attenuation in oil/water separators and settlement ponds/tanks. The discharge would be monitored to meet any requirements set by the EA. Any water not meeting the criteria set by the EA would be discharged to sewer and in accordance with Thames Waters requirements Consents to discharge from the Environment Agency or Thames Water may be subject to specified conditions. Monitoring will be undertaken as appropriate and records kept to demonstrate compliance with any specified conditions
31
Packages will be bought on the basis of trades disposing of their own major packaging waste in a sustainable fashion as far as possible. For example materials should be packed in re-usable crates which are returned with the delivery transport or recyclable packaging which also leaves site in the same way Shared skips will be provided as necessary for fitting out trades where use will be controlled and segregated at site as far as possible, although space limitations are likely to dictate that segregation will be undertaken away from site by the skip provider
32
8.2
The site will be registered with the Considerate Constructors Scheme which is administered by the Construction Industry Board. This is a voluntary code of practice that seeks to:
Minimise any disturbance or negative impact (in terms of noise, dirt and inconvenience) sometimes caused by construction sites to the immediate neighbourhood; Eradicate offensive behaviour and language from construction sites; and Recognise and reward the constructors commitment to raise standards of site management, safety and environmental awareness beyond statutory duties.
The scheme requires constructors to adhere to a Code of Practice that includes the following principles:
Be environmentally aware in the selection of resources. Pay particular attention to pollution avoidance and waste management. Use local resources wherever possible and keep to a minimum at all times noise from construction site activity; Be considerate to the needs of all those affected by the construction process and of its impact on the environment. Special attention to be given to the needs of those with sight, hearing or mobility difficulties;
33
Keep the Site clean and in good order and ensure that the surrounding area is kept free from mud, spillage and any unnecessary construction debris; Be a good neighbour by undertaking full and regular consultation with neighbours regarding site activity from pre-start to final handover. Provide site information and viewing facilities where practical; Promote respectable and safe standards of behaviours and dress. Derogatory behaviours shall not be tolerated under threat of the strongest possible disciplinary action; Be safe. All construction operations and vehicle movements to be carried out with care of the safety of passers-by, neighbours and site personnel; Be accountable to the public by providing site contact details and be available to deal with their concerns and develop good local relations; All contractors will be required to adhere to the requirements of the code of practice. Information about the scheme will be provided to all personnel at induction and through on going awareness raising such as posters and tool box talks as appropriate; and The scheme will also be publicised to local residents by the use of appropriate banners and posters with contact details posted at the boundary of the Site.
34
9 Work Force
9.1 Employment and Management Workforce
Catering and other essential welfare facilities will be provided on site. An employment strategy will be delivered in line with the employment and training strategy submitted to LBS. This will be delivered by Lend Lease, BeOnsite, Southwark Council, local agencies, training providers and Contractors. The Contractors will engage with the workplace training coordinator service to encourage local residents to apply to meet the employment requirements of construction.
9.2
Working Hours
Prescribed hours of work will be agreed with Southwark Council. Due to the proximity of residential dwellings and commercial activities to the Site, it is likely that the standard hours of work would be prescribed as follows:
08:00 to 18:00 hours Monday to Friday 08:00 to 13:00 hours Saturday No undertaking of noisy works on Sundays, Bank Holidays or Public Holidays
In order to maintain the above working hours, the Principal Contractor may require at certain times a period of up to one hour before and after normal working hours to start and close down activities (this will not include works that are likely to exceed agreed maximum construction noise levels). Specialist construction operations and deliveries may also be required to be carried out side these core hours in agreement with Southwark Council. Although night-time, out-of-hours or weekend working would not normally be permitted, it is conceivable that certain specialist construction operations and deliveries may have to be undertaken during these periods. In such cases prior agreement with Southwark Council will be sought. Works will take place outside these hours but will mostly be within noise limits set by Southwark Council. Consultation with Southwark Council will be required prior to noisy activities taking place outside normal hours of operation, with the exception of emergency work which may need to take place as required.
35
36
37
38