Materials System Specification

32-SAMSS-021 Manufacture of Industrial Boilers Heat Transfer Equipment Standards Committee Members
Anizi, Salamah Salem, Chairman Bagawi, Jamil Jarallah, Vice Chairman Anezi, Mohammed Ali Dossary, Musfir Abdullah Fernandez, Gabriel Thomas Gahtani, Moraya Saif Guthami, Mohammed Mohsen Hamam, Ibrahim Hassan Harbi, Abdullah Mohammed Saeed Mansour, Khalid Mohammad Naffaa, Mahmoud Youniss Rumaih, Abdullah Mohammad

18 January 2010

Saudi Aramco DeskTop Standards


Table of Contents 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Scope............................................................. 2 Conflicts and Deviations................................. 2 References..................................................... 2 Definitions and Abbreviations......................... 5 Responsibilities............................................... 6 Proposals........................................................ 6 Design............................................................ 8 Sootblowers.................................................. 18 Air Preheaters............................................... 21 Economizers................................................. 21 Firing System Equipment............................. 22 Forced Draft Fans........................................ 26 Ductwork...................................................... 28 Stacks........................................................... 29 Insulation and Refractories.......................... 29

Previous Issue: 6 September 2008

Next Planned Update: 18 January 2015 Page 1 of 41

Primary contact: Anizi, Salamah Salem on 966-3-8760203


CopyrightSaudi Aramco 2010. All rights reserved.

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

Table of Contents (cont'd) 16 17 18 19 20 21 22 23 24 25 26 27 Noise Attenuation......................................... 30 Connections, Boiler Trim and Instruments... 30 Burner Management Systems...................... 34 Painting........................................................ 34 Fabrication.................................................... 34 Nondestructive Testing................................. 35 Postweld Heat Treatment............................. 36 Inspection and Equipment Testing............... 36 Nameplates and Stampings......................... 38 Preparation for Shipment............................. 38 Drawings, Calculations and Data................. 40 Life Cycle Cost Evaluation........................... 40

Scope 1.1 This specification covers the minimum mandatory requirements for the manufacture of industrial type watertube fire, (herein referred to as boilers), that are fueled by either oil, or gas. This specification includes requirements for the thermal sizing, mechanical design, shop fabrication, field fabrication, installation, and testing of boilers. The requirements in this specification are in addition to and supplement the requirements of the Boiler and Pressure Vessel Code, ASME SEC I, (herein referred to as the Code).

1.2 1.3

Conflicts and Deviations 2.1 Any conflicts between this specification and other applicable Saudi Aramco Materials Systems Specifications (SAMSSs), Saudi Aramco Engineering Standards (SAESs), Standard Drawings (SASDs), or industry standards, codes, and forms shall be resolved in writing by the Company or Buyer Representative through the Manager, Consulting Services Department of Saudi Aramco, Dhahran. Direct all requests to deviate from this specification in writing to the Company or Buyer Representative, who shall follow internal company procedure SAEP-302 and forward such requests to the Manager, Consulting Services Department of Saudi Aramco, Dhahran.

2.2

Page 2 of 2

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

References Materials or equipment supplied to this specification shall comply with the latest edition of the references listed below, unless otherwise noted. 3.1 Saudi Aramco References Saudi Aramco Engineering Procedures SAEP-302 Instructions for Obtaining a Waiver of a Mandatory Saudi Aramco Engineering Requirement Equipment Life Cycle Cost Procedure

SAEP-341

Saudi Aramco Engineering Standards SAES-A-004 SAES-A-005 SAES-A-102 SAES-A-112 SAES-B-054 SAES-H-001 SAES-H-100 SAES-H-101 SAES-J-602 SAES-N-001 SAES-N-100 SAES-N-110 SAES-N-130 SAES-N-140 Pressure Testing Safety Instruction Sheet Air Pollutant Emission Source Control Meteorological and Seismic Design Data Access, Egress, and Material Handling for Plant Facilities Selection Requirements for Industrial Coatings Painting Requirements for Industrial Facilities Approved Protective Coating Systems Burner Management, Combustion, and Waterside Control Systems for Watertube Boilers Basic Criteria, External Insulation Refractory Systems Installation Requirements - Castable Refractory Installation Requirements - Fireclay Bricks Installation Requirements - Refractory Ceramic Fiber

Saudi Aramco Materials System Specifications 17-SAMSS-503 32-SAMSS-009 NEMA Frame Motors General Purpose Steam Turbines

Page 3 of 3

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

34-SAMSS-611 34-SAMSS-617 34-SAMSS-619 34-SAMSS-830

Safety Relief Valves, Conventional and Balanced Types Fire Monitoring Systems Flame Monitoring and Burner Management Systems Programmable Logic Controllers

Saudi Aramco Inspection Requirements Form 175-321300 Boiler: Power; Water Tube

Saudi Aramco Forms and Data Sheets Form 7305-ENG Form 9570-ENG Form SDS-ME 9550 Form SA-F-002 Form NMR-7913 3.2 Industry Codes and Standards American Institute of Steel Construction AISC 325 AISC 326 Steel Construction Manual Detailing for Steel Construction Equipment Noise Data Sheet Safety Instruction Sheet Watertube Boiler Smart Data Sheets Pre-commissioning Boilers Non-material Requirements for Industrial Watertube Boilers

Air Movement and Control Association, Inc. AMCA 210 Laboratory Methods of Testing Fans for Rating

American Society of Civil Engineers ASCE 7 Minimum Design Loads for Buildings and Other Structures

American Society of Mechanical Engineers ASME PTC 4 ASME SEC I ASME SEC II ASME SEC V ASME SEC VIII Steam Generating Units Power Boilers Material, Part D Nondestructive Examination Rules for Construction of Pressure Vessels
Page 4 of 4

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

ASME SEC IX

Welding and Brazing Qualifications

American Society for Testing and Materials ASTM A20 ASTM A435 ASTM D1066 General Requirement for Steel Plates for Pressure Vessels Straight-Beam Ultrasonic Examination of Steel Plate Standard Practice for Sampling Steam

National Fire Protection Association NFPA 85 4 Definitions and Abbreviations Definitions Boiler: Within the scope of ASME SEC I, Power Boilers, and this specification. Boiler Power Piping: Within the scope of ASME SEC I, Power Boilers, Figures PG58.3.1 and PG-58.3.2, and this specification. Boiler Supplier: The Company responsible for manufacturing boilers in accordance with the requirements of this specification. Engineering Company: The company responsible for specifying the design requirements for boilers on the data sheet EPRS: Effective projected radiant surface, is the projected area of the walls, roof, and floor of the furnace enclosure, including the furnace exit area. Furnace Volume: The cubic contents of space provided for the combustion of fuels. Heating Surface: The flat projected area, excluding refractory covered surfaces. Saudi Aramco Engineer: The Supervisor of the Heat Transfer Systems Unit, Consulting Services Department, Dhahran. Saudi Aramco Inspector: The person or company authorized by the Saudi Aramco Inspection Department to inspect boilers to the requirements of this specification. Flame Impingement: Direct contact between a flame and a tube. ADCT: Acid Dew point Calculated Temperature. It shall be calculated on the basis of 5% conversion of sulfur dioxide to sulfur trioxide. Boiler and Combustion System Hazard Code

Page 5 of 5

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

Abbreviations (Levels and Rating) HHWL: High-High Water Level ESD HWL: High Water Level Alarm LLWL: Low-Low Water Level ESD LWL: Low Water Level Alarm MCR: Maximum Continuous Rating NLL: Normal Water Level 5 Responsibilities 5.1 The Boiler Supplier is responsible for the thermal design, mechanical design, (Code and structural calculations), supply of all materials, fabrication, inspection, testing, and preparation for shipment, in accordance with the Code, the completed data sheet and this specification. The Engineering Company is responsible for specifying the design requirements for boilers, as noted on the data sheet. The balance of boiler instrumentation in accordance with SAES-J-602, for both field and control room instruments including the following shall be supplied by the Boiler Supplier: 1) 2) 3) 4) 5) 6) 7) 8) 9) 10) Combustion and feedwater regulatory controls Burner management systems Steam drum level indication and shutdown instruments Sootblower controls Combustion and waterside analyzers Desuperheater controls Flue gas analyzers (CO, NOx, O2) All instrument connections Combustion air flow elements Connections for flame monitors, including: scanners, receivers and mountings for junction boxes

5.2

11) Soot Blower hardware 12) Thermowells 6 Proposals 6.1 General


Page 6 of 6

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

6.1.1 6.1.2 6.1.3

The Boiler Supplier proposal shall be based on details for individual boilers as outlined on the data sheet. The Boiler Supplier may offer an alternative design, but must quote on the base inquiry documents. The Boiler Supplier proposal shall include a detailed description of any exception to the requirements of this specification and referenced industry standards herein. The Boiler Supplier shall advise the Saudi Aramco Engineer when Boiler Supplier has any part of a stress analysis executed by a third party. No proof testing shall be permitted unless specifically approved by the Saudi Aramco Engineer. Application of Code Cases to the Supplier of boilers requires approval of the Saudi Aramco Engineer.

6.1.4 6.1.5 6.1.6 6.2

Detailed Requirements The Boiler Supplier is to supply the following information with the proposal. This information is necessary and will be used to complete the technical evaluation of the quotation. The quotation will be technically unacceptable if any of the information required is not included. 1) 2) 3) 4) 5) 6) 7) A completed data sheet. A complete boiler supplier performance sheet including heat libration calculation for furnace sizing at 25%, 50%, 75%, and 100% MCR. Minimum and average Circulation ratios for all circuit diagrams. A list of users operating boilers of the same design and under similar operating conditions. Sizes of observation ports. The pressure and flowrate required for desuperheater spraywater. Dimensional drawing(s) showing typical internals of drums, materials of drums and headers, inside diameters, drum and header thicknesses, water and steam circuit arrangements, furnace configuration, burner locations, flue gas and air duct arrangements. Typical cross-sectional sketch of steam drums showing the location of internals, all water levels, and the highest downcomer. The sketch shall

8)

Page 7 of 7

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

also show the useful water volume in the steam drum below the NWL, LWL, and LLWL ESD. 9) Locations of access doors, observation ports, platforms, stairways, and ladders on a general arrangement type drawing.

10) Acid dewpoint temperature against acid dew point corrosion. 11) Maximum Flame profile dimensions for all specified fuels or combination of fuels 12) Typical Burner general arrangement drawings with a turn down ratio. 13) Maximum Atomizing steam flow and steam/oil pressure differential requirements. 14) A completed noise data sheet (Form 7305-ENG) with a detailed description of acoustical design. 6.3 Performance Guarantees The following shall be guaranteed for the length of the warranty period specified in the purchase order or contract documents: 1) 2) 3) Superheater outlet pressure and temperature downstream of the non-return valve as specified on the data sheet operating between 25% and 100% MCR. Efficiency at 25%, 50%, 75% and 100% MCR with steam conditions and fuels fired as specified. Unless otherwise specified on the data sheet, a maximum concentration of 100 ppb (parts per billion) total dissolved solids (TDS) and 20 ppb each of sodium and silica in saturated steam at any load within a boiler's controlled range when firing any fuel or combination of fuels specified on the data sheet, provided that ASME BFW quality is met. A controlled flame at all loads to comply with definition of flame impingement. Stable flame within operation of the boiler from start-up to 100% MCR. when firing any of the fuels specified on the data sheet. Maximum % load achievable with stable flame- when firing any fuel or combination of fuels specified and with one burner out of service. Smooth operation in either direction with a stable flame over the complete operating range with a rate of change in steam demand of 10% MCR per minute, and without actuating of the LLWL ESD or HHWL ESD.

4) 5) 6) 7)

Page 8 of 8

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

8) 9) 7 Design 7.1

Flue gas emission levels at operating range of 25% to 100% MCR. Sound levels at normal operating conditions.

General 7.1.1 7.1.2 The design of boilers, boiler piping, and associated equipment shall conform to the Code, and the completed data sheet. Equipment and components of standard manufacture shall be provided to ensure the availability of spare parts. Components need not be products of the Boiler Supplier, however, the Boiler Supplier shall assume full responsibility for all components supplied regardless of their source. The design of boilers auxiliary components located outdoors shall be suitable for continuous operation at the summer design temperature for the site, as specified in SAES-A-112. Regardless of climatic conditions, all external surfaces shall be selfdraining and protected against corrosion. Open covers (roof and sides only) shall be provided over firing aisles. Boilers shall be designed to operate continuously in the automatic control mode, but with manual control override capabilities, under all conditions specified on the data sheets. Boilers and auxiliaries, including control instrumentation, shall be designed for continuous operation during electrical power outages through an uninterrupted power supply system (to be provided by others). The Boiler Manufacturer shall submit an estimate of the electrical power required. Boiler auxiliaries shall be capable of sustained operation in automatic control mode between 25% and 100% MCR for a minimum period of two years between shutdowns required for the complete testing and inspection (T&I) of a boiler. Boilers and auxiliaries shall be capable of accommodating a rate of change of 10% MCR per minute over the control range of the boiler, for both an increasing and decreasing steam demand, without causing a level shutdown or water carryover during the transient condition.

7.1.3

7.1.4

7.1.5

7.1.6

7.1.7

7.1.8

Page 9 of 9

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

7.1.9 7.1.10

Circulation calculations at100% MCR shall be prepared and submitted by the Boiler Supplier for review. For shipping shop-assembled units (packaged boilers), the boiler, burners, all necessary appurtenances, and auxiliary equipment (except fans, drivers, air preheater, economizer, panels for local controls and burner management systems) shall be mounted on an integral steel base to provide a complete, self-contained steam generating unit. All vibration-sensitive equipment shall be shock-mounted. Furnaces and gas passes shall be designed to prevent dead-ended or poorly ventilated pockets where combustibles might accumulate and cause an explosion upon ignition. Gas passes through furnaces, superheaters and convective heat transfer surfaces, as well as air and flue gas ducts, shall be designed and arranged to prevent vibrations from vortex shedding, sootblower impact loadings, and turbulence. Boiler Supplier shall submit vibration calculations including flow induced and acoustical vibration. All outside water walls and furnace division walls shall be of the membrane wall design. Gaps between tubes shall be proportional to the tube OD, and shall not exceed 25 mm in the firebox. Fins (strips) shall be at least 6 mm thick. Tangent tube welded walls are not acceptable. Any deviation in fin dimensions shall be identified in the proposal and shall be supported by fin temperature gradient and stress calculations in the design phase. All water, steam and fuel piping shall extend 1.0 m beyond the battery limits of the boiler, exact locations shall be specified by the Engineering Company. Space and access shall be provided for the inspection, cleaning, removal, and maintenance of tube bundles, headers, retractable burner parts, valves, pumps, fans, turbines, and motor drivers. The boiler floor casing shall be a minimum of 1 m above grade. Guards or personal protection type insulation shall be provided around operating areas where exposed surfaces are hotter than 65C. Facilities shall be provided for the complete draining of all water from the fire side of boiler units after washing. Drains openings shall be a minimum of 75 mm diameter and be sealed against overheating and escape of flue gases.
Page 10 of 10

7.1.11

7.1.12

7.1.13 7.1.14

7.1.15

7.1.16

7.1.17 7.1.18

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

7.1.19 7.2

Enclosures for instrumentation and electrical equipment shall be selected for the area classification specified on the data sheet.

Corrosion Allowances Pressure components other than tubes shall have a minimum corrosion allowance of 1.0 mm.

7.3

Furnaces 7.3.1 The dimensions and design of furnaces shall be such that complete combustion of fuels take place within the furnace limits without flame impingement on sidewalls, roofs, and front walls. Based on the highest heating values of the fuels, the maximum heat release at 100% MCR in a furnace of watertube boiler type shall be designed within the following parameters: 1) The net heat liberation within a furnace volume shall not exceed 620-kW/ m (60,000 Btu/hr-ft) for liquid fuels, 15 API gravity and heavier, or 820-kW/m (80,000 Btu/hr-ft) for gaseous fuels and liquid fuels, lighter than 15 API gravity. The net heat absorption rate shall not exceed 470 kW/m (150,000 Btu/hr-ft) of the effective projected radiant surface (EPRS) for all fuels. Credit for tile-covered floor tubes shall not exceed 10% of the projected floor area.

7.3.2

2)

3) 7.3.3

Self-closing observation ports having minimum dimensions of 50 x 100 mm or a 100 mm in diameter shall be provided. Ports shall be of the guillotine design and shall be air-purged for self-cleaning and cooling. The number, size, and location of ports shall ensure the visibility of all burner tips, furnace rear walls, side walls, furnace exit areas, and furnace roofs.

7.3.4

7.4

Superheaters 7.4.1 7.4.2 Superheaters shall be located such that inlet tubes are not located in regions of highest flue gas temperatures. Superheaters may be an all-welded convection or radiant-convection, located outside furnaces. When located within direct view of burners a

Page 11 of 11

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

minimum of two rows of staggered screen tubes shall be provided between the superheater and furnace. 7.4.3 Flow equalization through superheater tubes shall be achieved by the sizing of tubes, inlet header, and outlet headers. Tube inlet restrictions, including swaging, is not permitted. Desuperheater water flow should not exceed 5% of steam flow. In case where more percentage is required the steam temperature down stream the attemperator shall be higher by 10C above saturation temperature. Superheater elements shall be located and supported to prevent vibration, sagging, and misalignment. Superheater headers shall be located outside gas spaces. Superheater interconnecting piping shall be provided with, thermowell,and temperature transmitter. Superheater outlet piping shall be provided with connections for safety valves and startup vent, test gage, pressure transmitter, thermowell, temperature transmitter and pressure gage connections. All superheater outlet piping connections shall be located upstream ofthe start up vent. 7.4.7 The startup vent and its discharge stack shall be sized for not less than 25% MCR steam flow, and shall be provided with a silencer. Silencers shall be provided with suitable drains for condensate removal, and piped to sewer. Superheater tubes shall be arranged so that sootblowers can effectively remove soot from the outside surfaces of tubes. Superheater tubes shall be arranged to prevent soot bridging and plugging gas passages.

7.4.4

7.4.5 7.4.6

7.4.8

7.5

Desuperheaters 7.5.1 7.5.2 Desuperheaters shall be of the water-spray design. A spray-type desuperheater mixing chamber with an alloy steel liner shall be provided.

7.6

Steam Generating and Superheater Tubes 7.6.1 7.6.2 All tubes shall be seamless steel or electric resistance welded (ERW) steel. ERW tubes shall not be used in superheaters. All tubes shall have a minimum outside diameter of 38 mm.
Page 12 of 12

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

7.6.3 7.6.4

Tube material shall be selected based on the highest anticipated metal temperatures and flue gas composition. Tube configurations shall allow the free natural circulation of water and steam, in the proper direction, at all loads, and installed to allow complete draining of each tube. Tubes to boiler drums shall be attached by rolling for drums. All vertical tubes shall be supported or guided, or both, to prevent bowing and vibration, and to permit expansion. The minimum wall thicknesses of tubes shall be: 4 mm for 3" OD tubes and 3 mm for 2"OD tubes and below. Exposed portions of drums and headers shall be covered with firebricks or castable refractory. Horizontal (less than 3 degrees) tubes located in furnace floors shall be covered by firebricks, 50 mm minimum thickness.

7.6.5 7.6.6 7.6.7 7.6.8 7.6.9 7.7 Baffles 7.7.1 7.7.2

The use of baffles shall be minimized and refractory baffles are prohibited. Baffles shall be manufactured of heat-resistant alloy steel and capable of withstanding gas temperatures and sulfur content under maximum load conditions. Baffle walls shall be designed with gas-tight design to prevent gas bypassing. All baffles shall be accessible for inspection and repair without dismantling of casings.

7.7.3 7.7.4 7.8

Drums and Headers 7.8.1 7.8.2 7.8.3 Design pressure shall be at least 5% or 100 kPa (15 psig), above maximum operating drum pressure, whichever is the greater. Downcomers and internals shall be designed to ensure positive circulation under all loads. Steam drum sizing shall satisfy the following criteria:

Page 13 of 13

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

1)

The steam space shall be adequately sized to contain steam separation equipment necessary to attain the guaranteed steam purity specified throughout the control range. The water holding capacity between the LWL and LLWL shall be sufficient to sustain one minute evaporation at MCR with no feedwater flow. The LLWL shall be located not less than 50 mm above the top of the highest downcomer. A rise in water level (swell) above the NWL resulting from the requirements specified in paragraph 7.1.9 shall not cause a carryover or actuation of the HWL alarm. A fall in water level (shrinkage) below the NWL resulting from the requirements specified in paragraph 7.1.9 shall not cause the actuation of the LWL alarm.

2)

3) 4)

5)

7.8.4

When intermediate headers are required within a circulating circuit, restrictions to boiler circulation caused by headers shall be considered. Headers shall be protected from direct heat or radiant heat from flue gases. Drum connections shall be a minimum of inch NPS. The wall thickness of connections up to and including 2 inch NPS shall be schedule 160 minimum. Pipe sizes of 1 inch, 5 inch, and 7 inch NPS shall not be used. A manway shall be provided at both ends of steam and water drums and provided with hinged covers. Header handholes shall be provided. Drum connections shall be in accordance with Table 1. Table 1 Drum Connections

7.8.5 7.8.6 7.8.7 7.8.8 7.8.9 7.8.10

Service Description Steam outlets Safety valves Chemical feed with thermal sleeve All All All

Design Pressure

Type of End-Connection Welded Flanged Flanged

Page 14 of 14

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015 Service Description Feedwater inlet with thermal sleeve Water columns, lower connection with thermal sleeve Steam pressure gages Vents Sampling connections Continuous and intermittent blowdown All Design Pressure

32-SAMSS-021 Manufacture of Industrial Boilers Type of End-Connection Welded Welded Flanged Welded Flanged Welded Flanged Welded Welded

Under 4.48 MPa (650 psig) 4.48 MPa (650 psi) and above Under 4.48 MPa (650 psig) 4.48 MPa (650 psi) and above Under 4.48 MPa (650 psig) 4.48 MPa (650 psi) and above Under 4.48 MPa (650 psig) 4.48 MPa (650 psi) and above Under 4.48 MPa (650 psig) 4.48 MPa (650 psi) and above

7.8.11 7.8.12 7.8.13 7.8.14

The facings of flanged connections shall be raised face type. Steam and water drums shall be welded, postweld heat treated, and 100% radiographically tested in accordance with the Code. Headers shall be constructed of seamless steel pipe. Drums with wall thicknesses 50 mm and thicker shall have nozzle connections as follows: 1) Connections 6 inch NPS and larger per Figures PW-16.1 (q-1), (q-2), (q-3), or (q-4 ). [100% radiography test to be guaranteed for (a,) (b), (c), (g), or (h)] Connections 4 inch and less as per (1) above or Figure PW-16.1 (a), (b), (c), (g), or (h)

2) 7.9

Steam Drum Internals 7.9.1 7.9.2 Steam drum internals shall consist of equipment for steam separation, feedwater distribution, chemical feed distribution, and blowdown. Steam separation equipment shall consist of centrifugal separators for boilers above 20 bar operating pressure followed by dryers section designed to meet the purity of steam specified on the data sheet. Proposals for other types of steam separation equipment must be included in the Boiler Manufacturer's proposal and must be substantiated with test results from commercial units that the steam purity entering the superheater will not exceed those specified on the data sheet.

7.9.3

Page 15 of 15

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

7.9.4 7.9.5

All internals shall be designed such that they can be removed without cutting. The design of chemical feed distribution piping shall comply with the following: 1) 2) 3) 4) 5) Be extended through steam drums and be of sufficient length to ensure proper mixing of chemicals Be perforated Closed at the far end with a threaded cap Provided with a thermal sleeve Located in the steam drum to avoid short-circuiting of chemicals into the continuous blowdown collection system.

7.9.6

Boiler feedwater distribution piping shall be provided with a thermal sleeve and be extended through the steam drum to assure proper mixing of the feedwater with the saturated recirculated water so that thermal shock is avoided. The design of continuous blowdown internal piping shall comply with the following: 1) 2) 3) Located in the area with the highest concentration of boiler water impurities Be extended as far as possible Be perforated with holes not smaller than 10 mm or V-notched on the top.

7.9.7

7.10

Water Drum Intermittent Blowdown 7.10.1 Intermittent blowdown nozzles shall be located on the lowest point of water drums. The size shall be based on water quality and operation, but shall not be less than 1 inch nor greater than 2 inch NPS. Separate drain valves shall be provided at the lowest point of water drums as a means for the draining of boilers.

7.10.2 7.11

Settings and Casings 7.11.1 Drains shall be provided at the low-points of furnaces and bank areas in order to remove flue gas deposits by water washing.

Page 16 of 16

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

7.11.2

Boiler enclosures, including air and gas ducting, shall be weatherproof and shall be pressure tight without buckling or bowing when subjected to an internal pressure transient of 1.5 times the furnace operating pressure. Bolted access doors shall be provided as required for ready access to all parts of the equipment for cleaning, inspecting, repairing, and replacing the tubes and headers. Access to the furnace through burner openings is not acceptable. Access doors shall be easy to enter from floor levels or platforms, and shall be clear of all obstructions.

7.11.3

7.12

Structural Steel 7.12.1 The Boiler Supplier shall supply the structural steel necessary to support the entire operating weight of all parts of a boiler, including future sootblowers and platforming. Wind speeds, and seismic forces shall be in accordance with SAES-A-112. Boilers shall be designed for wind and earthquake loads in accordance with ASCE 7. With reference to ASCE 7, the wind Category Classification to be used in the calculations of wind loads shall be Category III, and the Seismic Hazard Exposure Group to be used in calculations of earthquake loads shall be Group III. Wind pressures shall be assumed to act on the projected surface area and shall include due allowances for platforms, ladders, piping, insulation, and supported equipment. 7.12.4 The design metal temperatures of structures shall be the maximum calculated metal temperature expected for all operating modes with an average ambient temperature specified in accordance with SAES-A-112. Structural steel shall be designed and detailed in accordance with AISC 325 and AISC 326. Refractory shall not be used to support structural loads. Platforms with stairways or ladders shall be in accordance with the requirements of SAES-B-054, and this specification. As a minimum platforms with stairways or ladders that are not accessible from ground level shall be provided for the following:
Page 17 of 17

7.12.2 7.12.3

7.12.5 7.12.6 7.12.7 7.12.8

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

1) 2) 3) 4) 5) 6) 7) 8) 9)

All stop and non-return valves Superheater, and economizer safety valves Vent, blowdown, drain, and shutoff valves Flue gas draft control and guillotine dampers Access doors, handholes, and manways Burners, sootblowers, and observation ports Fans and fan drivers Instrument and control valves Electrical equipment

10) Stack sampling or monitoring 11) Draft gages 12) Steam Drum instrumentation 7.12.9 Burner platforms shall be provided with at least one stairway and have access to all other platforms.

7.12.10 Burner platforms shall be arranged to provide easy removal of burner guns. 7.12.11 Where several levels of burners are installed, each level shall be provided with a separate platform, with minimum headroom of 2.1 m. 7.13 Materials 7.13.1 7.13.2 7.13.3 All materials shall be in accordance with the ASME SEC II part D and the selection criteria in this specification for individual components. Cast iron, or cast steel fittings are not permitted. When tube support design temperatures exceed 600C and fuels contain a vanadium/sodium ratio between 3:1 and 18:1, tube supports shall be fabricated from high alloy materials: 60% Chromium-40% Nickel or 50% Chromium-50% Nickel materials. High alloy components shall not be welded to carbon steel components.

7.14

Valves Boiler Valves 7.14.1 The selection of gate, globe and check valves shall be in accordance with the Code.
Page 18 of 18

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

Fuel System Valves 7.14.2 7.14.3 7.14.4 All fuel shutoff valves shall be slow-opening, quick-closing, tight shutoff valves, and shall be certified fire-safe. Fuel gas and fuel oil shut-off valves shall be either ball or nonlubricated plug types. Position indicator handles shall be supplied for all ball and plug type valves.

Sootblowers 8.1 General 8.1.1 When boiler fuels are specified on the data sheet as oil or a combination of oil and gas, sootblowers shall be provided. When the fuel is specified as gas only, spaces for the future addition of sootblowers shall be provided in boiler convection sections. Rotary sootblowers shall be used in flue gas passes when flue gas temperature is below 650C. Retractable sootblowers shall be used in flue gas passes when flue gas temperature is above 650C. The Boiler Supplier is responsible for providing a complete and effective sootblowing system designed to remove soot and other unfused deposits from all convective heat transfer surfaces. Sootblowers shall be fully automatic with selected sequential control and manual override capabilities for individual sootblowers. Each sootblower shall be easily maintainable, with accessible lubrication fittings at all required lubrication points. Sootblower entrance ports shall be protected with 3 mm Type 304 stainless steel sleeves. The sootblower manufacturer's design shall be substantiated by at least two years of satisfactory experience in comparable service. A steam flow measuring device as designed by the Design Engineer shall be installed in sootblower steam supply lines to each boiler.

8.1.2 8.1.3 8.1.4

8.1.5 8.1.6 8.1.7 8.1.8 8.1.9

Page 19 of 19

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

8.1.10 8.2 Piping 8.2.1 8.2.2

Sootblowers shall be provided with connections for water washing of boilers.

The design of sootblower piping shall be arranged so that condensate buildup drains away from sootblower heads. Drain valves shall be interlocked with the control valve to ensure that upstream condensate is drained during warm-up and prior to the operation of sootblowers.

8.3

Instrumentation and Controls 8.3.1 8.3.2 Each sootblower shall be provided with individual controls to allow the selection of either manual or automatic operation. Automatic control shall be obtained via a programmable logic controller designed and specified by the Design Engineer in accordance with 34-SAMSS-830. Initiation of operating modes shall be prevented until steam supply systems have warmed-up, all condensate has been drained, and steam pressure has been established upstream of the sootblower control valves. The system shall be provided to prevent the start of a sootblower cycle until any other operating sootblower has completed its cycle. Automatic mode of operation shall incorporate the following functions: 1) 2) Enable the lockout of any sootblower from normal operating sequence. Enable the sequence to be "held" at any point in the sequence by operator intervention, and allow sootblowers to operate in the manual or local mode during that "hold" period. On re-selection of the automatic mode, the sootblower sequence shall continue from where it was interrupted. After two minutes from the initiation of any emergency stop signal, automatically retracts any operating retractable sootblower and shuts down the system to a safe condition.

8.3.3

8.3.4 8.3.5

3)

8.3.6

The following are the minimum indications of system status that shall be provided:

Page 20 of 20

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

1) 2) 3) 4) 5) 6) 7) 8) 9) 8.3.7

The mode of operation selected When the system is running under automatic sequential control Individual sootblower in operation The direction of travel for individual retractable sootblower during operation Steam system warm-up period is in progress Steam system warm-up period is completed Any sootblower(s) locked out of the normal operating sequence Open/closed positions of main supply valve Open/closed positions of individual boiler steam supply shutoff valves

The following are the minimum indications of alarm status: 1) 2) 3) 4) Elapsed time Motor overload Steam pressure Out of sequence

8.3.8

The following shall be provided in control rooms: 1) 2) 3) Alarms and status indications Automatic and manual mode pushbuttons Sootblower selector switches

Air Preheaters 9.1 9.2 9.3 Air preheaters, if cost effective, shall be of the fixed tubesheet recuperative design. Air preheaters shall be shop-prefabricated to minimize field assembly. The materials of construction of tubes and tubesheets shall be selected based on the acid dewpoint corrosion temperature (ADCT) plus 28C. (The value of the ADCT shall be calculated on the basis of a 5% conversion of sulfur dioxide to sulfur trioxide). The selection of all other air preheater materials shall be based on flue gas composition and metal temperatures developed during minimum load operation at minimum ambient air temperature.
Page 21 of 21

9.4

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

9.5 10

All pipe and pipe fittings shall be of steel construction.

Economizers 10.1 General 10.1.1 10.1.3 10.1.4 Economizers shall be provided and designed to avoid steaming at all loads. Economizers shall be made of Carbon Steel. Water bypass with double block valves shall be provided for the economizer to allow emergency operation of the boiler in cases where the economizer is out of service. Economizer shall be provided with a block valve and a safety valve.

10.2

Economizer Tubes and Tubesheets 10.2.1 10.2.2 Tubes shall be arranged in either staggered or in-line rows to allow for higher boiler performance. Finned tubes, with a maximum of six fins per 25 mm, shall be used. The fins shall be attached by high-frequency continuous resistance welding. The fin thickness shall be a minimum of 1.25 mm and the fin height shall not exceed 25 mm. Finned tubes with a maximum of 4 fins per 25 mm shall be used when firing liquid fuels. Serrated fins shall not be used when firing liquid fuel. The minimum design metal temperature of tubes and tubesheets shall be 15C above the calculated ADCT.

10.2.3 10.2.4 10.2.5 10.3

Enclosures 10.3.1 Where size and shipping facilities permit, economizers and enclosures shall be prefabricated to allow for field installation with minimum assembly and welding. Coil supports may be manufactured from carbon steel when the design metal temperature is less than 425C and flue gas is sulfur-free.

10.3.2

11

Firing System Equipment 11.1 General


Page 22 of 22

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

11.1.1 11.1.2

Burners shall be of the forced draft type designed to operate continuously over the specified turndown range. Flame profiles of all burners shall be contained within the confines of the furnace without flame impingement on walls, roof, floor, or exit screen, and without flame penetration through the exit screen to the superheater space. Take ABMA's definition and put it instead and we will add it in the definitions section. The Boiler Supplier shall provide optical flame scanners to each of the burner assemblies as detailed by the Design Engineer in accordance with SAES-J-602 and 34-SAMSS-617. Burners shall be capable of covering all boiler loads from start up to 100% MCR with stable flame. Turndown shall be achieved automatically, without changing burner tips or impairing flame stability. Burners controls shall be designed to facilitate rapid changeover between fuel types. Flue gas shall satisfy emission requirements as specified in the data sheet at operating conditions between 25% to 100% MCR. Burner and fuel system design shall permit safe fuel switching during operation and sudden trip of a burner. Burners shall be designed to minimize exposure to furnace radiation. Burner components exposed to furnace radiation shall be fabricated from heat-resistant alloys. All burner hardware (including piping, tubing, hoses, valves, and cocks) shall be of steel construction. Cast iron, copper alloys, and aluminum alloys, are not permitted.

11.1.3

11.1.4

11.1.5 11.1.6 11.1.7 11.1.8

11.1.9

11.1.10 The proposed burner design shall be compatible with the burner management system in accordance with this specification. 11.1.11 Burners shall be designed to meet sound level limitations as specified in this specification. 11.1.12 Connections shall be provided to verify combustion air and fuel balances between burners. 11.1.13 Burner curves shall be submitted and shall show the fuel consumption over the burner turndown range against fuel pressure required at the
Page 23 of 23

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

burner, and burner draft loss (Register Draft Loss) requirement excess air vs. load, and pressure vs. load, burner pressure vs. MMbtu's. 11.1.14 The air leakage through a closed air register at the rated load shall be a maximum of 10% 11.1.15 All safety shutoff and vent valves on burner/pilots shall be as specified by the Design Engineer in accordance with NFPA 85. 11.2 Oil Burner Assembly 11.2.1 Oil burners shall be the high efficiency, with maximum ratio of steam to fuel oil flow of 1 to 3, atomizing type, and provide uniform atomization throughout the burner turndown range with an excess air not more than 15% at MCR Burners shall not require more than 1034 kPag (150 psig) oil pressure at the burner. If the fuel oils specified on the data sheet will require different burner tips, the burner design shall be such that the only operator action required to change a burner tip is the withdrawal of a gun after isolation of the fuel supply. Positioning and removal of oil gun assemblies shall prevent flashback when exchanging burner guns. Oil gun assemblies shall be provided with flexible stainless steel hoses for fuel oil and atomizing steam. Air diffusers (swirler) located at the ends of burner positioning pipes shall be fabricated from heat-resistant alloy.

11.2.2 11.2.3

11.2.4 11.2.5 11.2.6 11.3

Gas Burner Assembly 11.3.1 Gas burners shall be capable of efficiently burning the specified fuels within the specified range of heating values throughout the burner turndown range. Gas burners shall be the high efficiency throughout the burner turndown range with an excess air not more than 10% at MCR Gas burners shall be of the multiport design.

11.3.2 11.3.3 11.4

Air Registers 11.4.1 Air register "open" setting shall provide equal distribution of
Page 24 of 24

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

combustion air to each burner to assure optimum flame conditions for the fuel(s) being fired over the turndown range of the burner. 11.4.2 11.5 Pilots 11.5.1 11.5.2 Class 2 or Class 3 gas igniters, as defined in NFPA 85 shall be supplied. Pilots shall be the automatic air and gas type, complete with an electric spark igniter and designed to utilize combustion air supplied by the main forced draft fan, as specified in NFPA 85. Pilots shall be blowout proof and capable of attaining ignition while maximum combustion air flows through the burner. Pilots shall be designed to resist furnace radiation with the air registers closed and main burners in operation without cooling air. All parts of air registers shall be shielded from furnace radiation and protected against conducted heat as covered in NFPA 85.

11.5.3 11.5.4 11.6

Burner Windboxes 11.6.1 11.6.2 11.6.3 Burner shall be furnished with windboxes, with bolted access doors, and acoustic insulation where required. Windboxes shall be provided to assure equal distribution of combustion air to air registers for each burner. Where a windbox supplies combustion air to more than two burners, the Boiler Supplier shall demonstrate the effectiveness of the air distribution. A minimum thickness of 5mm is required for the wind box. All stiffners to the the wind box shall be continuously welded.

11.6.4 11.6.5 11.7

Burner Piping 11.7.1 11.7.2 11.7.3 11.7.4 Burner piping required for oil, gas, and steam including shut-off valves shall be supplied by the Boiler Supplier. Tie-ins shall be from the tops of headers. Fuel headers shall be supplied with blow-down connections. All piping and valving shall be located, from a single-point entry, for
Page 25 of 25

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

each fuel to the fuel rack. 11.7.5 11.7.6 Fuel oil shut-off valves shall be located as close as possible to headers with no dead legs. Unless otherwise specified, a strainer with block and bypass valves shall be supplied for liquid fuels, located in the supply lines to each boiler. The size of mesh shall be not larger than half of the smallest orifice diameter in the burner guns. Hoses shall only be used for atomizing steam and liquid fuels heavier than 68 API, (0.709 relative density). The design and materials of hoses shall be as follows: 1) Three ply construction comprising of the following: a) b) c) 2) 3) An inner hose of close pitch corrugated tubing A middle layer of type 321 stainless steel braid An outer layer of interlocked stainless steel armor

11.7.7

Either weld-end or flanged connections Hoses are to be installed such that the hose manufacturer's minimum bend radius is not exceeded, or any moment is applied while in service.

11.7.8

Piping shall be arranged to ensure that all manually operated valves are in easy access. Supervisory manually operated valves for each fuel shall be the last valve before burners and located so that the valve operator can view the burner flame through the burner observation ports while operating the valve as per NFPA 85.

11.8

Burner Testing For non standard burner design a production model of each burner shall be tested for capacity, flame profile, stability within the turndown range with a reference list of users. Witness of the test firing is at the discretion of the Saudi Aramco Inspector.

12

Forced Draft Fans 12.1 General 12.1.1 Fans shall be, low speed type connected to drivers by flexible couplings with coupling guards.

Page 26 of 26

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

12.1.2

Forced draft fans shall be located at ground level and located to permit easy access to the interior of fan casings and to allow easy removal of rotors.

12.2

Fan Design 12.2.1 Fans shall be designed for not less than the following conditions: 1) Air flow rated capacity shall be 105% of air flow required for maximum continuous rating with 15% excess air for fuel oil and 10% excess air for fuel gas. Maximum ambient design temperature and humidity as per SAES-A-112. Static head shall be 110% of the head required at MCR with 15% excess air firing for fuel oil and 10% excess air for fuel gas. Operating horsepower, as determined from items (1), (2), and (3) corrected for density at the minimum ambient design temperature.

2) 3) 4)

12.2.2 12.2.3 12.2.4 12.2.5

Fans shall be furnished with inlet guide vanes and with a vane drive arm for connection to the operating source. Vanes shall be provided with a mechanical stop to prevent airflow from falling below 25% MCR. Fans shall be furnished with a double extended shaft, unless specified otherwise on the data sheet. Fan housings shall be a minimum of 5 mm thick. The housing shall be of all-welded construction and shall be equipped with a cleanout door and a 2 inch NPS drain. Housings shall be constructed to allow for rotor removal. Fans shall be provided with split-sleeve bearings and be self-aligning, oil lubricated, with independent pedestals and soleplates, or antifriction bearings may be offered as an alternative. Air intakes of fans located outdoors shall be provided with bird screens and with means to avoid pickup of rain and wind-driven sand. The inlet shall also be designed to avoid wind effects on combustion airflow measuring devices. If required, air intake and discharge ducts shall be provided with silencers in order to meet the noise level limitations specified.
Page 27 of 27

12.2.6

12.2.7

12.2.8

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

12.3

Fan Drivers 12.3.1 Drivers shall be as specified on the data sheet and shall be in accordance with the specified electric power supply and steam conditions. Turbine drivers shall conform with the requirements of 32-SAMSS-009. Motor drivers shall conform with the requirements of 17-SAMSS-503. Geared drives shall be separately coupled units with a minimum service factor of 1.5. Gear shafts shall be equipped with split-sleeve bearings. A torsional analysis shall be prepared for geared units.

12.3.2 12.3.3 12.3.4

13

Ductwork 13.1 General 13.1.1 13.1.2 The Boiler supplier shall furnish a complete ductwork system for combustion air travel from air intake fans to burner windboxes. The system shall include supports, expansion joints, hangers, access doors, dampers, isolation plates, and connections for the measurement of airflow, temperature, and pressure. Flue gas ducting from the outlet to the stack, with all the necessary appurtenances, shall be furnished by the Boiler supplier when specified on the data sheet.

13.1.3

13.2

Design 13.2.1 13.2.2 13.2.3 13.2.4 13.2.5 Ducts for air and flue gas shall be designed, arranged, and installed in a manner to prevent vibration, distortion, and undue noise. Ducts shall be airtight and gastight. The maximum velocity of air and flue gas shall not exceed 20.0 m/s. Ducts shall be capable of withstanding an internal transient pressure of 14 kPa (2 psi). The minimum thickness of flue gas ducts shall be 5 mm and air ducts shall be 5 mm minimum thickness. Where more than one boiler exhausts to a common stack, an isolating plate, complete with davits, and flange spreaders, shall be provided in

Page 28 of 28

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

the discharge ducting of each boiler. Isolation plates shall be designed for tight shut-off and maximum fan discharge pressure. 13.2.6 13.2.7 Flanged connections shall be complete with flanges, erection bolts, and nuts. Flanges shall be sealwelded in the field. Ductwork shall be shop-fabricated for field assembly, including the installation of supports required for external insulation or internal refractory lining. An expansion joint shall be provided between force draft fans and the discharge ducting to boiler. Internal lining shall be provided where the metal temperature is less than the calculated value for ADCT. Alternately, external insulation shall be used where applicable.

13.2.8 13.2.9

14

Stacks 14.1 14.2 14.3 Stacks shall be furnished by the Boiler Supplier. Boilers shall be provided with a common self-supported stack. Unless otherwise specified on the data sheet, the minimum stack height above grade shall be 45 m. The Boiler Supplier shall calculate and guarantee emission rates of nitrogen oxides and sulfur oxides. The emission rates shall be expressed in Lb/MM BTU's when the boiler is operated at its design rate firing the fuels specified. Flue gas emissions (NOx, CO, particulates, hydrocarbons, etc.) shall not exceed the specified levels as per SAES-A-102. Where the stack metal temperature at any operating load can be less than the calculated value for ADCT a 50 mm castable refractory lining shall be provided. All external attachments to the shell shall be continuously welded. The design of refractory systems shall be in accordance with SAES-N-100.

14.4 14.5 14.6 15

Insulation and Refractories 15.1 General 15.1.1 Headers, drums, air heaters, economizer casings, windboxes, external superheater headers, exposed tubes, hot gas ducts, hot air ducts, steam turbines, and other heated and exposed surfaces shall be insulated in accordance with SAES-N-001.

Page 29 of 29

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

15.1.2 15.1.3 15.2

The design of refractory systems shall be in accordance with SAES-N-100. Refractory shall be installed in accordance with SAES-N-110, SAES-N-130, and SAES-N-140.

Ductwork 15.2.1 Corners of insulation on ductwork shall be protected with metal corner beading. Insulation on ducts shall be properly supported and securely fastened. Clips or welding studs for holding wires and bands shall be spaced a maximum of 450 mm on center. Exposed supports, duct doors, and other parts that project through the insulated surfaces shall be insulated for protection of personnel. Where the metal temperature of flue gas duct, at any operating load, is less than the calculated value of the ADCT, a 50 mm castable refractory lining shall be provided. Alternately, external insulation shall be used where applicable.

15.2.2

15.2.3

16

Noise Attenuation 16.1 The Engineering company shall specify limits for the sound pressure levels (SPL) and sound power levels (PWL) at the designated locations, on Form 7305-ENG. The boiler supplier shall ensure that the required limits as specified for SPL and PWL can be achieved by supplying test results of a representative boiler. Boilers shall be designed and provided with the acoustical treatment necessary to meet the specified noise levels. This shall include burner mufflers and acoustical lining for plenums, ducts, and stacks, vent silencer as required.

16.2 16.3

17

Connections, Boiler Trim and Instruments 17.1 General 17.1.1 17.1.2 The Boiler supplier shall supply all connections and equipment in accordance with this specification. All instrument connections, except thermowells, shall be provided with separate block valves to permit removal of devices without affecting other active devices.

Page 30 of 30

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

17.1.3 17.1.4 17.1.5

Steam drum connections shall be provided for level instrumentation in accordance with SAES-J-602. Connections shall be provided for the chemical cleaning of boilers, superheaters, and economizers. Drain connections shall be provided for draining all water after shutdown or boilout. Valves shall be 2 inch NPS minimum and located at the lowest point on the water drum to allow complete drainage of boilers in one hour or less at a pressure of 35 kPa g (5 psig). Connections shall be provided for the quick draining of all accumulated water in areas of furnaces, superheaters, boiler banks, and economizers following water washing of external tube surfaces. A sealing air system shall be provided from forced draft fan discharge ducts for all burner removal openings, sootblower wall boxes, and observation ports. Flexible connections between the sealing system and air supply lines may be used to compensate for differential expansion.

17.1.6

17.1.7

17.2

Boiler Trim The minimum boiler trim requirements to be provided by the Boiler supplier, shall be as follows: 1) Safety valves for drums, superheater outlets, and economizers in accordance with the requirements of the Code and 34-SAMSS-611. Valves shall be complete with discharge piping to a point 3 m above the nearest platform. Safety valves shall be equipped with lifting levers. A steam outlet stop valve and a screw-down non-return valve, each with a pressure-sealed bonnet and of approved boiler quality. A pressureequalizing warm-up line of not less than 2 inch NPS shall be provided around stop valve. Intermittent blowdown valves, using two valves in series at each blowdown nozzle. The outside valve shall be quick-opening, except at water wall headers. Boiler feedwater shutoff and check valves. Boiler vent valves, using two valves in series at each location. Valves for obtaining representative saturated steam samples, using two valves in series (double block) at least one down stream of SD and one superheated steam sample downstream of the SH. If the boiler design
Page 31 of 31

2)

3)

4) 5) 6)

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

includes a series of small-diameter tubes between the steam drum and superheater header, the sample points shall be spaced no more than 1.5 m apart. Sample connections shall be in accordance with ASTM D1066. 7) Continuous blowdown valves, using two valves in series. The downstream control valve shall be a hand-operated, V-port valve with a micrometer indicator or a V-port valve with TDS/conductivity control. Chemical feed valves, using two block valves in series and a check valve. Superheater drain and vent valves, using two valves in series at each location.

8) 9)

10) Lower header drain valves, using two valves in series for each connection. 11) A sample connection with two valves in series for obtaining representative water samples. The sample connection shall be located upstream of the continuous blowdown control valve. 12) Lower drum drain valves, using two valves in series at each location. 13) Three sample coolers (in accordance with ASTM D1066), valving and drainage trough. The sample piping and valving shall be arranged such that boiler water, saturated steam, and final steam each have a dedicated cooler. 14) Desuperheater water shutoff and check valves. 15) Sootblower steam valves, using two valves in series at each location. 16) Economizer outlet stop valve and screwdown non-return valve, where a water bypass is included. 17) Economizer safety valve (in accordance with the Code) if a bypass is included. 17.3 Pipework The minimum piping to be supplied by the Boiler supplier shall be as follows: 1) 2) 3) 4) 5) Steam piping from the superheater outlet header to the main stop valve Interconnecting steam piping between superheater stages and the desuperheater Saturated steam piping from the steam drum to the superheater inlet header Interconnecting piping from the economizer to the steam drum Boiler feedwater piping from the check valve to the economizer inlet header
Page 32 of 32

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

6) 7) 8) 17.4

Complete piping for the sealing air system, from the FD fan to all users Complete piping for the air system from a single point supply connection to all users All drain piping from the source to 1 m above grade

Instrumentation and Safety Relief 17.4.1 The minimum instrument requirements shall be in accordance with the Code and the following: 1) A combination airflow metering element shall be provided in the forced draft fan inlet or discharge duct. The flowmeter element shall be located upstream of any air-heater and be either a multipoint thermal mass flowmeter or a different head venturi or airfoil section. Differential head elements shall be capable of generating a differential head pressure up to 250 mm water gage at maximum flow. 2) 3) 4) 5) Sample connections for oxygen and combustible analyzers at the furnace exit, boiler, economizer, and air preheater outlets. Connections for flame monitoring and scanning. Connections for the measurement of opacity, particulate matter, sulfur dioxide, nitrogen oxides, oxygen, and carbon monoxide Connections for draft gages at fan inlet and discharge, air outlet of the air preheater, windbox, furnace, boiler outlet, economizer outlet, flue gas outlet of the air preheater, and stack entry. Thermocouple wells for measuring the steam temperature after each stage of superheaters, including the steam temperature before and after the desuperheater. Thermowells shall also be provided for measuring the temperature of the feedwater out of the economizer. Thermocouple wells for measuring flue gas temperatures leaving the furnace, air preheater, boiler, and economizer thermowells for measuring air temperatures before and after the air preheater and in the windbox, with provision for purging. The thermocouple hot junction shall be located to measure the average flue gas temperature, and shall be shielded to minimize the cooling effects of the surrounding surfaces.

6)

7)

Page 33 of 33

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

17.4.2 17.4.3 18

All instrumentation shall be in accordance with the Code, NFPA 85, and SAES-J-602. Safety relief devices shall be designed in accordance with the Code.

Burner Management Systems 18.1 Unless otherwise specified in the purchase order, boiler supplier shall supply a burner management system in accordance with NFPA 85, SAES-J-602 and 34-SAMSS-619. All nozzles, instrument connections, and thermowells for the burner management system shall be supplied by the Boiler Supplier.

18.2

19

Painting 19.1 19.2 All exposed surfaces shall be prepared and painted in accordance with SAES-H-001, SAES-H-100, and SAES-H-101. Gasket contact surfaces shall not be painted.

20

Fabrication 20.1 Forming and Assembly 20.1.1 The layout of shell plates, heads, and head plates shall be made in such a manner that manways, nozzles and their reinforcement are not located within any weld seams. Manways, nozzles and their reinforcement shall not be located within 20 mm of any weld seam. All nozzles and manways shall be ground flush to the inside curvature of the drums and headers, and inside diameters shall be radiused smooth. Where a split-reinforcing pad is required, the weld joining the pad sections shall be oriented with the circumferential direction of the shell. Tapped tell-tale holes inch NPT shall be provided as follows: 1) 2) 20.1.4 One hole in all single piece reinforcing pads. Where a pad is split, each segment shall have at least one tapped hole.

20.1.2

20.1.3

All internal and external nonpressure-welded attachments shall be fully seal welded and shall have their radiused corners.

Page 34 of 34

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

20.2

Welding All welding shall be in accordance with the requirements of ASME SEC I.

21

Nondestructive Testing 21.1 General 21.1.1 All Nondestructive Testing (NDT) shall be performed in accordance with the Boiler supplier written procedure prepared in accordance with ASME SEC V with the scope of NDT and acceptance/rejection criteria as defined by the Code and this specification. All NDT on boiler drums which are to be postweld heat-treated shall be made after postweld heat treatment. All pressure and nonpressure welds shall be visually inspected.

21.1.2 21.1.3 21.2

Radiographic Testing 21.2.1 Radiographic testing of tube support castings shall be conducted on any cracks or other indications exposed by liquid penetrant inspection that exceeds the quality requirements of ASME SEC I, PG-25. Areas of stress concentration in corners of castings, especially at support lugs, shall be radiographically inspected. At least two spot radiographs shall be taken of the lower flanges of each cast tube support section. One random spot radiograph shall be made for circumferential weld and one random radiograph for longitudinal welds of each stack shell section. In addition, each longitudinal and circumferential welds intersection shall be radiographed in the circumferential direction. All personnel performing field radiography at Saudi Aramco facilities, sites, and concessionary areas shall be in possession of valid permit to handle and use radioactive ionization materials and equipment.

21.2.2

21.2.3

21.2.4

21.3

Ultrasonic Testing 21.3.1 All butt-welds on boiler piping, 32 mm wall thickness and thicker shall be ultrasonically tested. Ultrasonic examination and interpretation shall be in accordance with ASME SEC VIII. Tubesheets and forgings 50 mm and thicker shall be ultrasonically tested in accordance with ASTM A435.
Page 35 of 35

21.3.2

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

21.4

Magnetic Particle Testing 21.4.1 Beveled edges of carbon steel plates with thicknesses 25 mm and thicker and all ferrous alloy plates shall be magnetic particle examined for linear discontinuities. Defects shall not exceed limits as per ASTM A20. All internal and external welds for all services made using the SMAW welding process when the nominal thickness of pressured components is 25 mm and thicker shall be magnetic particle tested.

21.4.2

21.5

Hardness Testing Weld hardness testing shall be in accordance with the requirements of ASME SEC I.

22

Postweld Heat Treatment 22.1 22.2 Code exemptions for postweld heat treatment of ferritic materials based on the use of austenitic or nickel-based electrodes are not permitted. The maximum postweld heat treating soaking temperature for carbon steel and C- Mo materials shall not exceed the temperature at which the test pieces were heat treated, as shown on the Mill Test Certificates or 650C for carbon steel and 690C for C- Mo. The maximum postweld heat treating soaking temperature for low-chrome alloy steels shall not exceed the tempering temperature at which test pieces and components were heat treated as shown on Mill Test Certificates, but shall be not less than 700C. Postweld heat treatment shall follow all welding and repairs but shall be performed prior to any hydrotest or other load test. Postweld heat treating shall be in accordance with the requirements of ASME SEC I and ASME SEC IX.

22.3

22.4 22.5

23

Inspection and Equipment Testing 23.1 Inspection 23.1.1 All materials and fabrication shall be subject to inspection by the Saudi Aramco Inspector in accordance with Saudi Aramco Inspection Requirements Form 175-321300. Written reports and evaluations of all inspections performed by the Boiler Supplier shall be made and submitted to the Saudi Aramco
Page 36 of 36

23.1.2

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

Inspector, at a frequency to be determined by the Saudi Aramco Inspector. 23.1.3 Written reports and evaluations of all inspections performed by the Boiler Supplier shall be made and submitted to the Saudi Aramco Inspector, at a frequency to be determined by the Saudi Aramco Inspector. Prior to final inspection and pressure testing, the inside and outside of boilers shall be thoroughly cleaned of all slag, scale, dirt, grit, weld spatter, paint, oil, etc. The Saudi Aramco Inspector shall have free access to the work at all times. Refractory linings and materials shall be inspected in accordance with SAES-N-110, SAES-N-130, and SAES-N-140.

23.1.4

23.1.5 23.1.6 23.2

FD Fan Testing Fans shall be tested by the Boiler Supplier in accordance with AMCA 210 and the following: 1) 2) No load, full speed run test One Aerodynamic performance test per FD fan type.

23.3

Boiler Performance Testing 23.3.1 A performance test, shall demonstrate complete and smokeless combustion without flame impingement on the furnace heating surface or flame penetration through the furnace exit screen, at all loads within the turndown range, and with any fuel or combination of fuels available at the time of the test on each boiler. Boiler efficiency shall be based on the higher heating value of the fuel, and the tests shall be made in accordance with ASME PTC 4, Performance Test Code (Abbreviated Method). If the results of a performance test do not conform in with the guaranteed values, the Boiler Supplier shall immediately correct deficiencies. Unless otherwise specified, the acceptance test shall be performed by the Boiler Supplier representative after commissioning. In addition to the Code, the following represent the minimum shop leak tests:

23.3.2

23.3.3 23.3.4

Page 37 of 37

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

Hydrostatic test of all pre-assembled pressure-containing sections, in accordance with the Code and SAES-A-004. 23.3.5 In addition to the Code, the following represent the minimum field leak tests: A hydrostatic test of all pressure parts in accordance with the Code, prior to installation of the casing. 23.3.6 23.3.7 Field pressure testing shall be in accordance with the Code. After inspection and testing, boilers shall be completely drained of all liquids.

24

Nameplates and Stampings 24.1 24.2 Boilers shall be Code stamped. Nameplates and nameplate mounting bracket shall be located such that they will not be covered by insulation and is easily readable from grade or a platform.

25

Preparation for Shipment 25.1 General 25.1.1 25.1.2 25.1.3 The Boiler Supplier is responsible for preparing materials for shipment and assuring their arrival on-site in good condition. All components shall be packed, securely anchored and satisfactorily protected for their respective shipment methods. One complete set of installation, operating, and maintenance instructions necessary for installation shall be packaged and shipped with the equipment. Bracing, supports, and rigging connections shall be provided to prevent damage during shipment, lifting and unloading. All instruments and valves, including auxiliary systems, shall be securely mounted, supported, and/or boxed to avoid damage during shipment. All exposed finished and machined surfaces, including bolts, shall be coated with a rust-inhibiting compound.

25.1.4 25.1.5

25.1.6

Page 38 of 38

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

25.1.7 25.1.8

Bearings and seal assemblies shall be fully protected against the entry of moisture and dirt. Flanged connections and all other machined surfaces shall be protected by a coating, which is easily removed in the field. Flanges shall be fitted with a steel or wood cover, 3 mm thick and neoprene gaskets. Covers shall be securely attached by a minimum of four bolts equally spaced. For ocean shipment, flanged connections shall also be covered with heavy duty plastic bags securely taped to the nozzles.

25.1.9

25.1.10 Markings shall be done with water soluble materials that contain no harmful substances that would attack or harmfully affect coils at both ambient and operating temperature. 25.1.11 Marking materials shall be free of lead, sulfur, zinc, cadmium, mercury, chlorine, or any other halogens. 25.1.12 Threaded connections, shall be protected with threaded plugs. 25.2 Internal Protection 25.2.1 The internals of drums and headers shall be protected from corrosion by use of a nontoxic vapor phase corrosion inhibitor applied at a rate of 1 kg/m. Desiccants may only be used with approval of the Saudi Aramco Engineer. Drums and headers must be sealed vapor tight using metallic covers, for inhibitors to be effective. Alternatively, nitrogen blanketing, temporary coatings or a vapor proof bag with moisture control may be used.

25.2.2 25.2.3 25.3

External Protection The protection of external surfaces shall be obtained by using one of the following: 1) A hard temporary preservative which can be removed at site prior to surface preparation and application of the Saudi Aramco coating and painting system. Prepare the surface and apply the complete (primer and final coatings) Saudi Aramco surface preparation, and coating and painting system in the shop.

2)

Page 39 of 39

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

26

Drawings, Calculations and Data 26.1 26.2 The Boiler Supplier shall prepare and submit for approval and review the preliminary and certified drawings and data detailed on Form NMR-7913. Drawings and calculations which are approved by the Design Engineer shall not relieve the Boiler Supplier of responsibilities to comply with the Code, and this specification. The Engineering Company is responsible for the completion of the Safety Instruction Sheet Saudi Aramco Form 9570-ENG in accordance with SAES-A-005 and the data on the Boiler Supplier drawings.

26.3

27

Life Cycle Cost Evaluation Unless otherwise approved by the Coordinator, Mechanical Engineering Division, Consulting Services Department, Quotations for boilers shall be evaluated on the basis of Life Cycle Cost (LCC) as explained in SAEP-341. This cost is composed of the initial purchase cost of the Boilers(s) plus the present worth of the fuel consumption over an assumed operating period of 15 years. The Life Cycle Cost of the Boiler(s) shall be determined using the following Life Cycle Cost spreadsheets: LCC-024, Single Fuel Boilers LCC-024A, Dual Fuel Boilers The efficiency of the boiler at 100% of the design heat releases shall be guaranteed. If the actual efficiency during performance tests is found to be less than the guaranteed efficiency. If not corrected, then the cost of the boiler(s) shall be reduced by an amount equal to the difference in fuel consumption (MMBTU/hr) for not meeting the guaranteed efficiency, multiplied by the Evaluation Factor $-hr/MMBTU as given in the Provided Life Cycle Cost spreadsheets included with boiler data sheet. The maximum reduction shall not exceed 15% of the initial cost of the boiler(s). Mathematically: Single Fuel: Efficiency Penalty = [actual efficiency - (guaranteed efficiency-0.01)] * L * EF
Commentary Note: Efficiency values are in decimal representation. 0.01 in the equation is a 1% test tolerance allowed.

EF = PV * EC * AH

Page 40 of 40

Document Responsibility: Heat Transfer Equipment Issue Date: 18 January 2010 Next Planned Update: 18 January 2015

32-SAMSS-021 Manufacture of Industrial Boilers

Dual Fuel: Efficiency Penalty = Sum of Efficiency Penalty of all fuels For each type of fuel the evaluation factor is defined by EF = PV * EC * T Where; L EF = = Boiler Load (Duty) @ normal condition (MMBTU/hr) will be show on the data sheet. Evaluation Factor ($-hr/MMBTU) will be shown on the data sheet that goes with the quotation request Energy cost in $/MMBTU for each fuel Annual operating hours OF * 8760 Operating Factor, equal 1 Present value factor = 5.85 based on 15% discount rate expressed as a decimal number and operating period of 15 years. Operating time for each fuel type, in hours

EC = AH = = OF = PV = T =

18 January 2010

Revision Summary Major revision.

Page 41 of 41