MRP Type P1 which firms our schedule agreement schedule lines at the end of the planning time fence

Firming type 1: An order proposal that lies within the planning time fence is firmed automatically as soon as its date lies at least one day before the finish date of the planning time fence. The date of new order proposals that are actually created in the planning time fence are rescheduled out to the end of the planning time fence. Therefore, these new order proposals are not firmed. Firming type 2: An order proposal that lies within the planning time fence is automatically firmed as soon as its date lies at least one day before the end of the planning time fence. The system does not create any new order proposals within the planning time fence. That is, the shortage situation is not adjusted within the planning time fence. Firming type 3: Order proposals that lie within the planning time fence are not firmed automatically. The order proposals required to cover the requirements are moved to the end of the planning time fence. Firming type 4: Within the planning time fence, the system creates no order proposals automatically. That is, the shortage situation is not adjusted within the planning time fence. Indicator: Planning time fence Using the planning time fence, you can exclude a certain period from the automatic planning run. In this period, only manual changes are made - depending on the firming type

MRP Type: PD : Mrp planning. explote the BOM upto last level and create the planned oder from finish product level to raw material level MO : Master schedling planning : the BOM upto next level of the final product.so create the planned order for the final product and create depended reqmt for the next level material MRp Type P1 or M1: Ans: THe order proposal that lies within the planning time fence is firmed automatically as soon as its date lies at least one day before the finish date of the planning time fence. The date of new order proposals that are actually created in the planning time fence are rescheduled out to the end of the planning time fence. Therefore, these new order proposals are not firmed MRP type P2 or M2: Ans: An order proposal that lies within the planning time fence is automatically firmed as soon as its date lies at least one day before the end of the planning time fence. The system does not create any new order proposals within the planning time fence. That is, the shortage situation is not adjusted within the planning time fence. MRP type P3 or M3: Ans: Order proposals that lie within the planning time fence are not firmed automatically. The order proposals required to cover the requirements are moved to the end of the planning time fence MRP type P4 or M4: Within the planning time fence, the system creates no order proposals automatically. That is, the shortage situation is not adjusted within the planning time fence. M4 is to classify the MS parts and P4 is for normal MRP items. BOm will be exploded in both cases to lower levels if procurement proposals created within or outside the time fence. VB/VM - here , the system do not consider the reqmt (pir or sales order ) , it check the reorder level in the material master and create the planned orde / pr once the stock reach the level.

ND : no planning . so the material will not be consider for planning XO : If you are going to do MRP planning the external . say APO or other you can use this type of mrp

Firming type 0 1 2 3 4

Description Planning results not firmed Automatic firming and order proposals rescheduled out Automatic firming without order proposal Manual firming and order proposals rescheduled out Manual firming without order proposal

firming type 0 The system does not firm procurement proposals automatically.

firming type 1 Procurement proposals that move into the planning time fence are firmed automatically, as soon as their date lies at least one day before the end date of the planning time fence. The date of new procurement proposals that are created in the planning time fence is displaced to the end of the planning time fence. These new procurement proposals are not firmed.

firming type 2 Procurement proposals that move into the planning time fence are firmed automatically, as soon as their date lies at least one day before the end date of the planning time fence. The system does not create any new procurement proposals within the planning time fence; that means, the system does not balance the shortage situation in the planning time fence.

firming type 3 Procurement proposals that move into the planning time fence are not firmed automatically by the system. All procurement proposals that are necessary for requirements coverage are displaced to the end of the planning time fence.

firming type 4 Procurement proposals that move into the planning time fence are not firmed automatically by the system. The system does not create any new procurement proposals within the planning time fence; that means, the system does not balance the shortage situation in the planning time fence.