Beruflich Dokumente
Kultur Dokumente
V100R002C00
Installation Guide
Contents
Installation Tools 2 Installation Options 3 Dimensions and Installation Clearance 4 Installation Procedure 6 Preparing the Installation 6 Installing the RRU on a Metal Pole 7 Installing the RRU on a U-Steel 12 Installing the RRU on an Angle Steel 12 Installing the RRU on a Wall 13 Installing the RRU Cables 16 RRU Hardware Installation Checklist 26 Powering On the RRU 26 Appendix 27 Change History ... 32
Installation Tools
ESD gloves
Vacuum cleaner
Claw hammer
Crimping pliers
Wire stripper
Adjustable wrench Knife Wire cutter (with the diameter of at least 32 mm)
Torque wrench
Combination wrench
(21mm~21mm) for pole installation
Level
Torque screwdriver
Marking pen Multimeter (with the diameter of no more than 10 mm) Measuring tape
Installation Options
On a metal pole
On a U-steel
On an angle steel
On a wall
The following figure describes the specifications for the metal pole, angle steel, and U-steel where the RRU is installed. 63 mm to 80 mm 60 mm to 114 mm
m 0 8
m 3 6
50 mm to 100 mm U-steel
RRU
The angle between the vertical and the angle steel or U10 steel or angle steel where the RRU is installed must be less than or equal to 10 degree.
The brackets cannot be combined when the RRUs are installed on the wall. WARNING z A maximum of two RRUs can be installed on a metal pole with the diameter of 60 mm to 76 mm, and the RRUs must be installed on the back. z Only one RRU can be installed on a U-steel or an angle steel at the back. z When installed on a tower, only one RRU can be installed in standard mode or reverse mode, and two RRUs cannot be installed in back-to-back mode, or the brackets cannot be combined when the RRUs are installed on the tower. z A single RRU can be bound and lifted to a tower. For details, see page 27 "Binding the RRU and Installation Components."
30 mm to 50 mm
400 mm
The recommended installation clearance meets the requirements of the equipment for normal running and OM. When the installation space is sufficient, the recommended installation clearance can be adopted.
The minimum installation clearance meets the requirements of the equipment for normal running and heat dissipation, but does not meet the requirements for Operation and Maintenance (OM) such as checking the status of the LEDs and opening the maintenance cavity. When the installation space is restricted, the minimum installation clearance can be adopted.
300 mm
200 mm
30 0m
10 0m m
m 00 8
m
6 00 mm
m 0m 60
40 0m
500 mm
300 mm
mm 00 5
80 0m m
m 300
60 0m m
500 mm
300 mm
300 mm
600 mm
600 mm
100 mm
400 mm
400 mm
500 mm
300 mm
500 mm
300 mm
Installation Procedure
Install the RRU cables Checking the RRU Hardware Installation Power on the RRU End
Cover plate
Main bracket
RRU
Back
Installing the RRU on a Metal Pole a Installing a Single RRU on a Metal Pole (Recommended )
1. Install the main bracket.
When installing the main bracket, ensure that the contact piece on the bracket is fixed.
1200mm1600mm
You may fit one end of the auxiliary bracket on one dual-nut bolt assembly and then the other end on the other dual-nut bolt assembly during the installation.
2. Use an adjustable wrench to tighten the nut until the fastening torque is 40 Nm. In this way, the main and auxiliary brackets are secured on the pole.
21 mm
40Nm
Fasten the two dual-nut bolt assemblies alternatively. After the brackets are secure, use a tape to measure the spacing between the main bracket and the auxiliary bracket at the two sides and ensure that the spacing is the same.
3. Install the RRU on the main bracket. When you hear click sound, you can infer that the RRU is in position.
Click
z The weight-bearing capacity of the RF ports at the bottom of the RRU is low. Do not place the RRU at its bottom. z During the operation, place the foam pad or cardboard under the RRU to prevent any damage to the housing of the RRU.
Installing the RRU on a Metal Pole b Installing Multiple RRUs in Centralized Mode (Recommended )
1. Install an RRU. For details, see page 7 Installing a Single RRU on a Metal Pole (Recommended) . 2. Install the second main fixture. 3. Fit the tabs on the attachment plate of the second RRU into the anchor slots on the second main fixture.
Installing the RRU on a Metal Pole b Installing Multiple RRUs in Centralized Mode (Recommended )
6. Fit the tabs on the attachment plate of the fourth RRU into the anchor slots on the fourth main fixture. 7. Four RRUs installed in centralized mode.
Installing the RRU on a Metal Pole c Installing a Single RRU on a Metal Pole
When the installation clearance for the RRU is limited, the RRUs can be installed in standard and reverse modes or in back-to-back mode.
1. Install the main fixture and the auxiliary fixture. For details, see page 7 Installing a Single RRU on a Metal Pole (Recommended) . 2. Reinstall the attachment plate and cover plate on the RRU by interchanging their positions.
M6X16
5Nm
3. Install the RRU on the main bracket. When you hear click sound, you can infer that the RRU is in position.
Click
10
Installing the RRU on a Metal Pole d Installing Two RRUs Back-To-Back on a Metal Pole
1. Install an RRU. For details, see page10 Installing a Single RRU on a Metal Pole. 2. Install the main fixture for another RRU.
3. Reinstall the attachment plate and cover plate on the second RRU by interchanging their positions.
M6X16
5Nm
In reverse mode
Ensure that the cabling cavities of the two RRUs face the same direction when installing the RRUs.
Cabling cavity
11
U-steel
z z The procedure for installing the RRU on a U-steel is the same as that for installing the RRU on a metal pole. z It is recommended that only one RRU be installed on a U-steel. z RRU
zThe procedure for installing the RRU on an angle steel is the same as that for installing the RRU on a metal pole. z It is recommended that only one RRU be installed on an angle steel.
12
56 mm
56 mm
RRU
1200 mm1600 mm
z It is recommended that the auxiliary bracket be 1,200 mm to 1,600 mm above the ground. z The RRUs cannot installed on a wall in centralized mode. Therefore, expansion bolt assemblies should be prepared for each RRU.
2. Drill holes at the anchor points and then install the expansion bolt assemblies.
M10x65 bolt Spring washer 10 14 Plastic tube Flat washer 10 Expansion tube 90 55 mm to 60 mm
Do not hammer the bolt entirely into the wall. Instead, leave 20 mm to 30 mm of the bolt outside the wall.
20 mm to 30 mm
When the RRU is installed on a wall, the requirements are as follows: z For one RRU, the wall has a weight-bearing capacity of 60 kg. z The fastening torque of the expansion bolt reaches 30 Nm, the expansion bolt works properly, and no damages such as cracks are on the wall.
13
M10
30Nm
14
Recommended Clearance :
760 mm 760 mm
128 mm
Minimum Clearance:
510 mm 510 mm
128 mm
70 mm
70 mm
128 mm
15
Antenna
Install the DC RRU alarm cable(optional) Install the AISG multi-wire cable between the RRU and the RCU (optional) Install the AISG multi-wire cable between the RRU and the RCU (optional)
CPRI optical cable DC RRU power cable RRU RF jumper PGND cable SFP high-speed cable for cascading DC RRU alarm cable
Antenna
16
Antenna
Installing the RRU Cables c Cable Connections between the RRU and the dual-BT (optional)
z The external BT couples the 12 V DC signals or OOK signals and RF signals into the RF jumpers and enables the 12 V DC signals and OOK signals to be transmitted to the Antenna Line Device (ALD) through the RF jumpers. The ALD includes the Tower Mounted Amplifier (TMA) and Remote Control Unit (RCU). z This figure shows only the cable connections between the RRU and the dual-BT. For details on the connections of other cables, see the cable connections for a single RRU. BT_A
BT_B RF jumper B AISG multi-wire cable between the RRU and the RCU RRU RF jumper PGND cable
Antenna Antenna
BT_A
BT_B
ANT_TX/RXB
ANT_TX/RXA
17
Cable
PGND cable (16 mm)
Connected to
Grounding bolt on the RRU Nearest grounding bar
RRU RF jumper
North American standard: The OT terminal on the blue wire is connected to the NEG(-) port on the cabling cavity of the RRU. The OT terminal on the black wire is connected to the RTN(+) port on the cabling cavity of the RRU European standard: The OT terminal on the blue wire is connected to the NEG(-) port on the cabling cavity of the RRU. The OT terminal on the brown wire is connected to the RTN(+) port on the cabling cavity of the RRU
Bare wire
DLC connector
Connect the fiber tails labeled 1A and 1B to the CPRI0 port on the RRU Connect the fiber tails labeled 2A and 2B to one of the CPRI0 to CPRI5 ports on the LBBP When the optical cable is used for RRU interconnection, the 1A and 1B ends are connected to the CPRI0 port in the cabling cavity of the RRU1, and the 2A and 2B ends are connected to the CPRI1 port in the cabling cavity of the RRU0.
18
Cable
AISG multi-wire cable between the RRU and the RCU
Connected to
Port labeled RET on the RRU Standard AISG male connector of the AISG extension cable or RCU
Standard AISG female connector of the AISG multi-wire cable Standard AISG male connector of the RCU
Port labeled EXT_ALM in the RRU cabling cavity External alarm devices
19
Installing the RRU Cables e Opening the Cover Plate of the RRU Cabling Cavity
1. Use a Phillips screwdriver to unfasten the screw for protecting the cabling cavity. 2. Open the cover for the cabling cavity by lifting the handle on the cover.
M4
Cabling cavity
Reference for making the power cable Cable trough for the optical cable Cable trough for the power cable Cable trough for the optical cable
cable clip
Waterproof filler
20
First wrap the joint with the waterproof tape, and then wrap it with the PVC insulating tape.
z For details about how to add easy power receptacle (pressfit type) connectors to the power cable, see "Adding Easy Power Receptacle (Pressfit Type) Connector to the Power Cable" in page 28. z For details on how to add OT terminals to the DC RRU power cable of the RRU, see page 29 " Add an OT terminal to the power cable on the DCDU side." z When wrapping the waterproof tape, apply even force to extend the tape until the width of the tape is 1/2 of the original width. z Wrap the joint spirally upward, downward, and then upward again. In other words, the joint is wrapped by three layers of the tape. Ensure that the two immediate layers overlap with each other about half the width of the tape. For details, see page 30 Waterproofing Outdoor Cables. z Install the optical module before installing the optical cables. For details, see page 30 Installing the Optical Module.
z Press the strap on the exposed shielding layer of the power cable tightly. Ensure that the lower edge of the exposed shield layer does not exceed the position shown in the figure. z Ground the shielding layer at the other end of the power cable. z Do not remove the dustproof cap from the feeder connectors that are not in use. If the RRU is installed outdoors, you also need to wrap the joint with waterproof tape. z Waterproof fillers should be installed in the unused cable trough.
21
1.4Nm
z The DC RRU power cable is connected to one of the LOAD4 to LOAD9 terminals of the PDU. z Strip the jacket of the DC RRU power cable for a small part, press the exposed shielding layer on the strap, and then connect the PGND cable on the strap to the nearest grounding bolt on the side in the APM30. z Three power cables can be led through each ground clip.
22
2. RRU+19-Inch Stand.
DC RRU power cable CPRI optical cable
BBU DCDU-03B
LOAD0
z The DC RRU power cable is connected to one of the LOAD0 to LOAD5 terminals of the DCDU-03B. z When connecting the DC RRU power cable to the DCDU-03B, you must add an OT terminal to the shielding layer. Then, fix the OT terminal to the corresponding PGND terminal of the DCDU-03B. For details on how to add an OT terminal, see page 29.
23
3. RRU+Wall-Mounted BBU.
DC RRU power cable CPRI optical cable LOAD0
The DCDU panel must face right side and the BBU panel must face downwards.
z The DC RRU power cable is connected to one of the LOAD0 to LOAD5 terminals of the DCDU-03B. z When connecting the DC RRU power cable to the DCDU-03B, you must add an OT terminal to the shielding layer. Then, fix the OT terminal to the corresponding PGND terminal of the DCDU-03B. For details on how to add an OT terminal, see page 29.
24
4. RRU+TMC11H.
PGND cable
z The DC RRU power cable is connected to one of the LOAD0 to LOAD5 terminals of the DCDU-03B. z Strip the jacket of the DC RRU power cable for a small part, press the exposed shielding layer on the strap. z Three power cables can be led through each ground clip.
25
Items
All self-made PGND cables are copper-based with the proper wire diameters. No breaking device such as switch and fuse is allowed for the electric connection of the grounding system. No short circuit is allowed. Each terminal on the grounding bar can be connected with only one wiring terminal of the PGND cable. The RRU and the installation parts are securely installed. The cover plate is securely installed on the cabling cavity of the RRU. Waterproof fillers are installed in the idle cable troughs of the cabling cavity of the RRU, and the cover plate of the cabling cavity is securely installed. In addition, the idle RF ports are covered with waterproof caps and waterproofed. There are no connectors or joints on the power cable or PGND cable. The terminals at both ends of the power cable or PGND cable are securely soldered or crimped. The flat washer and the spring washer are well mounted on all OT terminals. All the power cables and PGND cables are not short-circuited or reversely connected. In addition, no damaged or broken parts exist. The power cable, PGND cable, feeder, optical cable and the E1/T1/FE signal cable are bound separately with a spacing of larger than 30 mm. The connector of the signal cable is intact, and no damaged or broken parts exist on the cable. Labels are correct, legible, and complete on both ends of each cable.
2 3 4
5 6 7 8
10 11
Yes
Power on the RRU b Check whether the status of the LEDs on the RRU is normal? Yes End Rectify the fault b
No
26
Steering rope
z When lifting the RRU and installation components to the tower, prevent the RRU from colliding with the tower. z Lift the RRU to the tower before it is installed on the metal pole, angle steel, or U-steel.
Do not bind the lifting rope only on the handle when lifting the RRU.
Pulley
Lifting rope
Steering rope
z Installer A climbs onto the tower. Then, installer A fixes the pulley to the support of the tower platform and leads the lifting rope through the pulley. z Installer C uses a lifting rope to bind the RRU and installation components as shown in the preceding figure and then ties a knot in the steering rope at the handle of the RRU. z Installer B pulls the lifting rope, and at the same time, installer C pulls the steering rope away from the tower to prevent the RRU and installation components from colliding with the tower. z Installer A holds the RRU and installation components and untie the ropes.
27
Appendix b
Adding Easy Power Receptacle (Pressfit Type) Connector to the Power Cable
Determine lengths of power cables for different operations according to the scales on the inner side of the cover plate of the cabling cavity.
1. Measure each wire and strip the jacket off the wire for 7.5 mm to 8 mm. Ensure that the length of each revealed bare wire equals the depth of the holes in the easy power receptacle (pressfit type) connector.
Based on the determined length, remove the jacket and shielding layer off the power cable.
Add an easy power receptacle (pressfit type) connector to the two wires of the power cable.
Strip a 18 mm jacket off the power cable by cutting the jacket around the cable to reveal the shielding layer of the power cable.
3. By taking the American standard cables as an example, insert the blue NEG(-)0 wire into the 2 or - end and black RTN(+)0 wire into the 1 or + end of the easy power receptacle (pressfit type) connector. In this case, the sliding blocks return to the original positions. NEG(-)0
RTN(+)0
If the wire connections are faulty, the equipment cannot be powered on.
28
Lead the wires made of the shielding layers through heatshrinkable tubes.
Wrap the PVC insulating tape at the joint where the three wires meet.
WARNING Do not damage the shielding layer of the power cable when cutting around the jacket.
29
Waterproof tape
Insulating tape
tie
30
Appendix f
Pin Assignment for the Wires of the RRU Alarm Cable ( DC )
DB15 connector
X1.2 X1.3 X1.6 X1.7 X1.10 X1.11 X1.13 X1.14
Wire Color
Wire Type
Twisted pair
Label
White/blue Blue White/orange Orange White/ green Green White/ brown Brown
SWITCH_INPUT0+ GND
Twisted pair
SWITCH_INPUT1+ GND
Twisted pair
Twisted pair
31
Change History
This describes the changes in the RRU3220 Installation Guide.
z01 (2010-05-20) This is the draft release.
32