Project name Project number Contract Client Standard Manufacturer AS:3000

COMMISSIONING CHECKSHEET

DOCUMENT NUMBER

DC SWITCHBOARD

Drawing number Function Operation number Location Fed From Serial number

NOTE: Where automated relay test equipment is used, the test results obtained may take priority over or supplement the information recorded on this check sheet. In this case a reference will be made to an attached result sheet.

ABIDE BY SAFETY AND ISOLATION PROCEDURES IN SWMS7


1

VERIFY INSTALLATION
Tests Required (Minimum) Verify board installation method Verify board design and labelling as per schematic notes Verify clearances, terminal shrouding/pole blanks are installed and labelled Verify operation of all handles/locks Verify door seals Ensure all penetrations are filled/blanked N/A N/A N/A Schematics Greenlined/Updated Operation (Pass/Fail)

Accepted By (signature)

VERIFY CIRCUIT BREAKER/FUSE/LINK/RELAY TYPES AND RATINGS


Tests Required (Minimum) Verify circuit breaker/fuse and link type and ratings Verify relay types and ratings Schematics Greenlined/Updated Operation (Pass/Fail)

Accepted By (signature)

3 Tests Required (Minimum)

VERIFY EARTHING
Schematics Greenlined/Updated Operation (Pass/Fail)

Accepted By (signature)

Verify earthing to each cubicle section/gland plate/escutcheon plate/door Verify cable screen earthing Verify spare cores are earthed Switchboard Earth bar to grid/stake

Test earth resistance to earth grid/stake

Acceptance 0.5

Document1

Page 1 of 3

Revision: A

18/10/10

COMMISSIONING CHECKSHEET

DOCUMENT NUMBER

DC SWITCHBOARD

VERIFY CABLE INSTALLATION


Tests Required (Minimum) Verify cable types as per schematics Verify cable glanding Verify cable bending radius (12x diameter for multi-core, 15x diameter for single-core) Verify segregation Verify ducting/cable ties Verify internal and external labelling Verify ferruling as per schematics Verify termination lugs for correct size/type Verify terminal tightness N/A N/A N/A N/A N/A Schematics Greenlined/Updated Operation (Pass/Fail)

Accepted By (signature)

TEST INSULATION RESISTANCE


Tests Required (Minimum) Verify switchboard insulation resistance POS E M NEG E M Schematics Greenlined/Updated N/A POS - NEG M Acceptance 100M (New), 1M (Aged) Operation (Pass/Fail)

Accepted By (signature)

Test at 1kV for 1 Minute

TEST INCOMMING SUPPLIES


Tests Required (Minimum) Verify incoming supply polarity and phasing Schematics Greenlined/Updated N/A Operation (Pass/Fail)

Accepted By (signature)

RECORD VOLTAGES
Tests Required (Minimum) Record switchboard voltages POS-E NEG-E POS-NEG Schematics Greenlined/Updated N/A Operation (Pass/Fail)

Accepted By (signature)

Document1

Page 2 of 3

Revision: A

18/10/10

COMMISSIONING CHECKSHEET

DOCUMENT NUMBER

DC SWITCHBOARD

Remarks:

The associated system has been tested and proved to operate successfully as per the design information provided. Please refer to the Defect Report list and Testing Equipment Details. Commissioning Officer: Signed: Date: The test results have been reviewed, are within tolerance and are consistent with the design information provided. Client Commissioning Engineer: Signed: Date:

Defect Report 1 2 3 4 5 6 7 8 9 10

Date

Subject

Recommendation

Resolved

Test equipment Description

Serial Number

Document1

Page 3 of 3

Revision: A

18/10/10