Beruflich Dokumente
Kultur Dokumente
Pretender
Precontract
Contract
Cost
Time
Quality
BSc (Hons) BUILDING CONSTRUCTION MANAGEMENT
Determine Action
Measure Performance
Assess Deviation
Ahead/Behind
Denyer, 1972
project | control |
Control of Progress Control is comparing, at regular intervals, the actual work achieved with that planned Necessary corrective action can be taken to bring work back on schedule Use of monthly and weekly meetings are invaluable in helping control progress work not proceeding as planned can be considered in detail explanations can be assessed best solutions can be discussed and implemented Communications on progress can be made with other parts of the organisation BSc (Hons) BUILDING CONSTRUCTION MANAGEMENT
project | control |
project | control |
Progressing activities on a precedence diagram Progressing work and updating information directly on a network
project | control |
project | control |
project | control |
Cost control should enable the cost of each stage, activity or unit to be determined and compared with target costs to ascertain any deviations
The timing of cost information is all important and ideally should be done as work is being carried out
Problems can be identified early and remedial action taken as appropriate Most project management systems provide for this and enable resources and resources representing sections of work to be assessed in terms of cost and income The collection of cost information may be carried out via time sheets, weekly summary sheets and the measurement of work completed Cost control information is also be useful for the estimation of costs on future projects
Time/Cost optimisation A technique used to find the most economical way of carrying out a project in terms of time and cost The cost of a project can be considered a combination of direct and indirect costs The variation in duration of critical activities will affect these cost and the total cost of the project To accelerate activities is more expensive in terms of direct costs As a project duration increases so will the indirect costs Time/Cost optimisation is concerned with establishing project duration at minimum cost BSc (Hons) BUILDING CONSTRUCTION MANAGEMENT
acceleration | summary
Time/Cost optimisation The reduction in duration of an activity can be achieved through increased resources, working overtime or additional shifts The reduction in time is termed crashing for which there will be an associated crash cost Cost slope for activities can be determined by as follows cost slope = (crash cost - normal cost) / (normal duration crash duration) Critical activities can be accelerated in the order of least cost slope Direct and indirect costs can be calculated for each project duration to obtain the optimum cost BSc (Hons) BUILDING CONSTRUCTION MANAGEMENT
acceleration | summary
acceleration | summary
Discrete time and cost relationship for an activity Non-linear relationship between time and cost for an activity
acceleration | summary
Cost curves to establish the least cost for optimum project duration
acceleration | summary
acceleration | summary
Normal Cost () 4,700 5,485 Cost Slope ) 20 -
A B
11
6,536
15
3,400
E F
10 10 3
acceleration | summary
Normal Cost () 4,700 Cost Slope ) 20
acceleration | summary
Normal Cost () 6,536 Cost Slope ) First 3 days 35 per day 85 per day thereafter 55
26
10
3,950
Second Compression Compress activity C by 3 days = 3 x 35 = 105 Compress activity E by 3 days =3 x 55 = 165 Total 270
acceleration | summary
Third Compression Compress activity D by 2 days 2 x 40 = 80 Compress activity E by 2 days 2 x 55 = 110 Total 190 Fourth Compression Compress activity E by 1 day 1 x 55 = 55 Compress activity C by 1 day 1 x 85 = 85 Total 140
Fifth Compression Compress activity E by 3 days 3 x 55 = 165 Compress activity D by 3 days 3 x 95 = 285 Total 450 Sixth Compression Method (2) selected Compress activity F by 3 days 3 x 150 = 450
acceleration | summary
Indirect Cost () 7,080 6,480 6,120 5,880 5,760 5,400 5,040 Total Cost () 32,551 32,051 31,961 31,911 31,931 32,021 32,111 Duration (Days) 59 54 51 49 48 45 42
In-direct cost are 120 per day. The optimum cost is 31,911 with a duration of 49 days
summary
Summary Progress recording is an essential part of controlling work in order to identify problems and initiate remedial action Recording progress can be carried out in connection with bar charts and networks Cost optimisation is a technique used to find the most economic way of carrying out a project in terms of time and cost
summary
Activity
The construction of part of a commercial development is represented by the activities shown in Table 1.
Activity Reference A-B* A-C A-D B-C* B-F C-E* D-H E-H* F-G G-H Duration (weeks) 14 6 25 17 12 14 8 8 11 13 Crash Duration (weeks) 11 6 17 15 11 12 7 7 10 10 Cost () 7300 9100 15100 9100 4100 5600 11100 2000 7600 2300 Crash Cost () 7600 9100 19100 11100 4600 6300 12100 2300 8300 2300
* critical activities
summary
Activity
The indirect costs associated with the development are 1700 per week.
1. Using cost optimisation techniques, determine the optimum duration and cost for the work. 2. Describe three situations where cost optimisation techniques may be used in practice.