PMP® Exam Self-Assessment Test


75 Free Sample Questions

"If money is your hope for independence you will never have it. The only real security that a
man will have in this world is a reserve of knowledge, experience, and ability.“
Sponsors:
Henry Ford, Entrepreneur

Explanations (skip)
Feedback (since 2003)
The free preparation test below covers the current PMP®
exam version (per 31 August 2011). Mailed January 23, 2013 by Ramesh Ch. (India): "Respected Oliver Sir,
I'm glad to announce that I achieved the most coveted PMP credential on
Each question in this self assessment test has one best 21st Jan 2013. I'm even more glad and thankful to your free resources in
answer. www.oliverlehmann.com which had enriched my PM knowledge and bridged
the gaps in infinite number of ways."

Time to finish the test: 90 Minutes. Mailed July 24, 2012 by Christina W. (Canada): "Hello Oliver;
Thanks for your links to the many practice tests.
I took the PMP exam on July 19th and did well.
There is a timer in the title bar (top of most browsers). Best Regards, Christina"
Mailed July 09, 2012 by ChandraShekhar B. (India): "This test is very helpful
FREE Download for learning and Click the dark blue button (below) to reset the timer to in evaluating weak areas."
instruction. 00:00:00.
Mailed January 26 2012 by Sandie Q. (USA): "Hi there Oliver - your PMP
sample exam is really great; it's given me a good sense of the remaining
Insight tree supports project Click here for links to 3,000+ more PMP prep questions from work I need to do. Vielen Dank und Grusse aus Washington DC."
selection and helps you become a decision various providers (4,000+ for PMI members).
Mailed November 04 2011 by Satish S. C. (India, via Google+): "Hi Oliver
tree expert. I've cleared the PMP in first attempt
Life training classes: Thanks for all your valuable guidance and help. Really much appreciated. "
www.oliverlehmann.com/seminar-dates.html
Mailed October 27 2011 by Daniel C. (Australia, via LinkedIn): "Oliver,
on a side note I wish to say thank you for all the work you have put into to
PMI® has not participated in the development of this self assessment test and PMP training.
has not reviewed the content. I think it is safe to say that without your 175 free questions and the iPAD
app that is also based on your questions I would not have passed the PMP
exam as easily as I did. You really made a difference for me and I appreciate
it.

143 Tweet 84 Like 149 Send XING Follow Share

Ready? Click here to reset the timer and start the test

See references Marked for review

1. ________ is typically not referred to as a buffer type in critical chain project management.

Resource buffer

Free buffer

Feeding buffer

Project buffer

See references
Marked for review

2. A company has to make a choice between two projects, because the available resources in money and kind are
not sufficient to run both at the same time. Each project would take 9 months and would cost $250,000.

1. The first project is a process optimization which would result in a cost reduction of $120,000 per year. This benefit would
be achieved immediately after the end of the project.

2. The second project would be the development of a new product which could produce the following net profits after the
end of the project:

1. year: $ 15,000
2. year: $ 125,000
3. year: $ 220,000

Assumed is a discount rate of 5% per year. Looking at the present values of the benefits of these projects in the
first 3 years, what is true?

Both projects are equally attractive.

The first project is more attractive by app. 7%.

The second project is more attractive by app. 5%.

1 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

The first project is more attractive by app. 3%.

2 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

3. A production process has been defined as part of an industrial equipment manufacturing project. The process is
intended to produce steel bolts with a length of 20 cm. The control limits are 19.955cm and 20.045cm.

The measurements made at the end of the process yielded the following results:

20.033cm, 19.982cm, 19,995cm, 20.006cm, 19.970cm, 19.968cm,


19.963cm, 19.958cm, 19.962cm, 19.979cm, 19.959cm.

What should be done?

The process is under control. It should not be adjusted.

A special cause should be investigated, the process should be adjusted.

The control limits should be adjusted.

The measuring equipment should be recalibrated.

See references Marked for review

4. Your project management team includes two external consultants each from a different company. You found that
repeated conflicts between the two consultants already slow down project progress and jeopardize achievement of
objectives.

Which stage of team development can be difficult to overcome in such a situation?

Storming from Forming, Storming, Norming, Performing

Panic from Enthusiasm, Panic, Hope, Solution

Kickoff from Assignment, Kickoff, Training, Communicating

Frustration from Direction, Frustration, Cooperation, Collaboration

3 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

5. During a project, earned value analysis is performed, resulting in the following numbers:

EV: 523,000; PV: 623,000; AC: 643,000.

Which results are correct?

CV: +120,000; SV: +100,000

CV: +100,000; SV: +120,000

CV: -100,000; SV: -120,000

CV: -120,000; SV: -100,000

See references
Marked for review

6. A project manager spent some days to create a multi-page document, which he called project charter. The
document should have been issued by the project sponsor. The sponsor found the document outsized and asked
for a condensed document.

Which of the following is usually not an element of the project charter?


The authority level of the project manager

Detailed control account and work package descriptions

The business need that the project was undertaken to address

High-level risks

4 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

7. A document called ____________ is created by decomposing the project scope into smaller, more manageable
elements.

Scope Statement

Network Logic Diagram

Work Breakdown Structure

Requested Change

See references Marked for review

8. Which of the following tools is used to create a risk management plan?

Risk planning meetings

Documentation reviews

Data precision rankings

Diagramming techniques

5 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

9. In order to speed up a project, you made a decision to fast-track a phase currently performed with five team
members, and another one which was planned to begin in four weeks time with another five team members.

Which of the following activities should you do first?

Make sure that all exit criteria of the consecutive phase have been met to ensure the flow of
communications in a team situation which is more complex by a factor of 2.
Make sure that all entry criteria of the previous phase have been met by planning and performing a phase
gate meeting to assess technical aptness.
Make sure that all exit criteria of the previous phase have been met by planning and performing a phase
gate meeting to assess technical performance.
Restructure your team and delegate tasks in order to ensure the flow of communications in a team with the
number of communication channels increased by a factor of 4.5.

See references Marked for review

10. A project manager has been asked to support an internal project request by developing a business case.

What kind of information is the person expected to provide in the document?

The detailed information from a business standpoint to determine whether bidding for the customer project
will be successful.
The detailed information from a project management standpoint to determine whether the project will be
successful.
The detailed information from a technical standpoint to determine whether the project will be successful.

The necessary information from a business standpoint to determine whether the project is worth the
investment.

6 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

11. You found the following earned value analysis information for a project that was recently closed-out:

SPI = 0.7, CPI = 1.0

The project has been cancelled while it was executed. At that time the project was behind schedule and on
budget.
The project's deliverables have all been finished. The project came in behind schedule but on budget.

The project's deliverables have all been finished. The project came in ahead of schedule but on budget.

The project's deliverables have all been finished. The project came in on schedule but over budget.

See references Marked for review

12. Which should be included in a requirements management plan?

The document should trace requirements to project scope / WBS deliverables.

It should describe how requirements activities will be planned, tracked, and reported.

It should trace high-level requirements to more detailed requirements.

It should trace requirements to business needs, opportunities, goals, and objectives.

7 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

13. In a traditionally drawn decision tree, a circle represents ___________.


a chance to which no expected monetary value can be assigned so that a likely pay-off can not be shown.

a decision to which no expected monetary value can be assigned so that a likely pay-off can not be shown.

a chance to which an expected monetary value may be assigned to calculate the most likely pay-off.

a decision to which an expected monetary value may be assigned to calculate the most likely pay-off.

See references
Marked for review

14. A project management team has subcontracted work to a service company. Which of the following tools is the
best choice to assure that this company will be able to meet the quality requirements of the project?

Quality audit

Deliverable inspection

Fixed price contract

Service level agreement

8 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

15. With your team you are using judgment from subject matter experts to identify and analyze project risks. There is
a small number of experts available, but some of them have long been in a teacher-student or manager-assistant
relationship.

Which of the following techniques can ensure best that there is no dominating opinion during an expert review?

Peer review

SWOT analysis

Delphi technique

Monetary value calculation

See references Marked for review

16. You are running a project for a customer based on a cost-reimbursable contract with the following terms:

Target costs: $ 1,000,000


Fixed fee: $ 100,000
Benefit/cost sharing: 80% / 20%
Price ceiling: $ 1,200,000

Which is the PTA (= point of total assumption, break point) of the project?

$1,300,000

$1,500,000

$80,000

$1,125,000

9 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

17. During execution of a project which is performed for a customer on a T&M (time and material) contract base, a
new project manager is taking over the assignment.

He discovers that two members assigned to the project have charged time without performing any work for the
project customer. Upon further investigation, he determines that this occurred because there have been no other
project assignments open for these employees. The customer is unaware of these facts.

What should the project manager do?

Try to find some productive work for these staff members in the project and leave them on the team.

The best thing is to do nothing. The customer will not realize the problem anyway.

Try to find a responsible person for the over-assignment who can be made accountable.

Take the two people off the team immediately and arrange for the refund of the excess charges to the
customer.

See references Marked for review

18. Start dates in the following network logic diagram are defined as early morning, finish dates are evening.

If tasks are scheduled to begin at early start date, what is true?

Activity B has a free float of 10 d.

Activity B has a total float of 10 d.

Activity A has a free float of 10 d.

Activity A has a total float of 10 d.

10 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

19. Your project is executed with a globally spread virtual team. The project progress has been found to be too slow.
Which measure is most likely to immediately speed up the project?

Technical training for all team members

Daily phone conferences and detailed reporting

A team meeting at a location convenient to all team members

Collocation of team members at a suitable place

See references Marked for review

20. A project management team wants to procure some customized products which are available in identical grade
and quality from many vendors. What should be included in the procurement package to ensure that their offers
will be comparable?

A statement of work describing the needs of the project in sufficient detail to enable vendors to make
suitable proposals
A statement of work specifying attributes and metrics of the requested deliverables in detail to allow
vendors submission of bids
The approved project scope statement, the WBS which should be broken down to work package level and
the WBS dictionary
The risk management plan and the reports from those risk management reviews which have been made so
far

11 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

21. Which of the following becomes increasingly important in a virtual team environment?
Requirements engineering

Communication planning

Formal procurements closure

Network diagramming

See references
Marked for review

22. You are assigned as the project manager to a project which is executed for a customer under FP contract. Your
customer informed you this morning that they insist on certain "refinements" of the project scope.

You agree that the requested actions make really sense to the project, but believe that they constitute a major
change increasing the project scope. What should you do next?

Accept the request of the customer. Diligently document the additional costs and working hours spent by
yourself and the team on the implementation of the change and invoice these to the customer at
appropriate rates.
Perform earned value analysis to assess the current status of the project and get all the numbers you need
to communicate the case to the change control board which then will have to make the best decision
regarding the customer request.
Check the contract, the project charter, the scope statement and other documents related to the project and
the contract. Implement ADR (alternative dispute resolution) procedures if the conflict cannot be resolved
otherwise.
Talk to the project sales department and find a joint solution with them how to best reject the request
considering the commercial and strategic value of the customer to the organization you are working for.

12 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

23. A prime contractor in a customer project under CPFF contract has run into unexpected technical problems. Fixing
them will require a lot of additional work to be done.

The company made a decision to book more staff and equipment from their subcontractors in order to adhere to
the agreed timeline. The customer agreed to this decision.

What will most likely happen?

The contractor‘s indirect costs will increase and the customer‘s payment for them will increase, too.

The contractor‘s indirect costs will increase, but the customer‘s payment for them will not increase.

The contractor‘s indirect costs will not increase, but the customer‘s payment for them will.

Both the contractor's indirect costs and the customer‘s payment for them will not increase.

See references
Marked for review

24. A project management team is evaluating the causes that might contribute to unsatisfactory performance and
quality. Which of the following statements is not true?

Normal process variation is attributable to random causes and sometimes also called "white noise".

Special causes are easier to predict and handle than random causes (also called common causes).

Special causes are unusual events which are difficult to foresee and often produce outliers.

A process can be optimized to limit the bandwidth of variations due to random causes.

13 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

25. You are performing a project management audit in your company and find that most of the project plans are
neither consistent nor up-to-date.

Which of the following statements is not true?

Projects should never be executed without a valid, updated and working project management plan.

The consistency of the project management plan is secondary because it is only the results that matter.

A great deal of effort is required to develop and update a project plan, but the benefits include less pressure
on all stakeholders and a resulting product that will satisfy the requirements.
Poor planning and insufficient updating of project management plans are common reasons for cost and
time overruns.

See references
Marked for review

26. You want to perform active risk acceptance. What should you do?

Create contingency reserves in resources, money and time.

Develop a plan to minimize impact in case that an identified risk occurs.

Develop a plan to minimize the probability of occurrence for identified risks.

Make additional resources available to speed up the project.

14 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

27. A project manager made 3-point estimates on a critical path and found the following results:

Assuming ±3 sigma precision level for each estimate, what is the standard deviation of the allover path?

App. 4.2 days

App. 5.2 days

App. 6.2 days

You can not derive the path standard deviation from the information given.

See references
Marked for review

28. When do bidder conferences normally take place?

After the contract has been awarded to keep alternatives open.

After submission of bid or proposal, but before contract award.

Prior to the submission of a bid or proposal by the bidder.

After technical meetings with bidders to discuss contract requirements.

15 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

29. What is defined by control limits?

A measuring instrument solely used to describe process capability. The process is found capable if the ±3
sigma range is exceeded by not more than 0.3% of a tested sample lot.
The limits of the six sigma area on either side of a control chart to plot measured values; data found outside
the area are out of specification and can lead to rejection of an entire batch.
The area consisting of typically three standard deviations on either side of a mean value of a control chart
to plot measured values found in statistical quality control
The area consisting of typically three standard deviations on either side of a mean value of a control chart
to plot measured values found in quality assurance

See references
Marked for review

30. The scope baseline consists of what?


Scope statement, WBS, and WBS dictionary

Cost baseline, quality baseline and schedule baseline

Configuration management plan and configuration identification document

Procurement statement of work and project scope statement

16 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

31. Activity 1 has a duration of 20 days, activity 2 of 10 days, activity 3 of 5 days and activity 4 of 6 days.

What is the minimum total duration between the milestones A and B?

36 days

37 days

39 days

42 days

See references Marked for review

32. Which tool and technique is used in the processes Create WBS and Define activities?

Nominal group technique

Human resource assignment

Brainstorming

Decomposition

17 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

33. Which of the following statement(s) on whistleblowing is/are not true?

a. It is a term used to define an employee’s decision to disclose information on unethical, immoral or illegal actions at work
to an authority figure.
b. An employee should always discuss the matter with people external to the company before following the "chain of
command" and discuss it with the immediate superior.
c. The consequences of whistleblowing are often extreme and might include being branded as an owner of bad judgment,
layoff, civil action and imprisonment.
d. Carefully performed whistleblowing can lead to the end of unethical business practices.

b, c

c, d

See references Marked for review

34. Which of the following statements is not true?

Attribute sampling is the process of assessing whether results conform to specifications or not.

Prevention means keeping errors out of the process by applying actions before the process starts changing
its input.
Variables sampling means that the result is classified into one of the 3 categories:
"acceptable" - "acceptable after rework" - "rejected".
Inspection is often mainly done to keep errors out of the hands of the customer instead of as a means of
process control.

18 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

35. Which statement describes best why you should document assumptions?

Assumptions might prove to be wrong. Knowing which assumptions were incorrect allows baseline
adjustments in case of project crisis.
Assumption analysis is a valuable tool and technique to explore the validity of assumptions during risk
identification.
Assumptions limit the project management team's options for decision making because they can not be
controlled by the team.
In case of schedule or budget overruns, the documentation of assumptions supports a clear assignment of
responsibility.

See references Marked for review

36. Which is normally not regarded as an element of cost of quality?

Prevention costs

Maintenance cost

Appraisal costs

Failure costs

19 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

37. You have recently been assigned as a project manager to a new B-O-T (build, operate, transfer) capital project.
Reviewing the initial documentation you found out that it has been calculated with a very small margin during
operations of its product for the shareholders. What should you do?

As you are not responsible for lifecycle costing, you don't have to worry about operation profits. Focus on
project costs from initiation through handover.
Ensure maximum profits by buying the best and cheapest items, components and modules―potentially
from a big number of different suppliers―and integrating them.
Create a realistic plan broken down to a sufficient level of detail. Perform all risk management processes.
Ensure real-time communications with all stakeholders.
Try to get a second project manager assigned to share decision making and accountability to shareholders
with the person.

See references
Marked for review

38. A project is handled by departments of an organization and expedited by a project coordinator. Which of the
following statements is most likely to be true?

The performing organization is a weak matrix.

The performing organization is doing "management by projects".

The performing organization is a strong matrix.

The performing organization is projectized.

20 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

39. You are project manager in a global project with a team consisting of people from various countries. What can you
try to prevent misunderstandings due to cross-cultural differences?

Use all communication methods available that are suitable for the team and follow up in writing when
communicating verbally. Remember that cultural and individual diversity may help project teams solving
unforeseen problems during the course of the project.
When you are about to form a team for your project, keep in mind that some cultures are developed, others
are more primitive. Some have values, some not. You should consequently avoid choosing members from
countries with cultures that are not similar to your own.
Cultural dilemmas can prevent any project from being successful. They should therefore be smoothed or
suppressed so as to make sure that they cannot disrupt project work. Your effort should concentrate on
communication that can help reach that goal.
As norms regarding communication habits differ significantly across various cultures, communicating
between people from different countries should only be done using language. The nonverbal dimension
simply bears too many risks.

See references
Marked for review

40. Which statement on conflicts is true?


Conflict resolution should focus on people, not issues.

Conflict is natural and forces a search for alternatives.

Conflict should always be handled in private and not in the team.

Too much openness is a common cause of conflict.

21 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

41. A change request in a project has been rejected some weeks ago. Yesterday, the project manager found out that
it nevertheless has been implemented by the team members, who knew of the change request, but not of the
rejection.

In order to avoid such a situation, rejected change requests should be consistently communicated to stakeholders
through which process?

Report performance

Verify scope

Perform integrated change control

Monitor and control risks

See references
Marked for review

42. What is a trigger in project risk management?

An expected situation causing an unidentified risk to occur

A warning sign that a previously identified risk might be occurring or has occurred

An unexpected situation causing an identified risk to occur

An unexpected situation causing an unidentified risk to occur

22 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

43. According to the project plan, a contractor is scheduled to deliver some software components today afternoon. A
regular payment is due to be made to this contractor tomorrow.

You and your project team received a note this morning informing you that the software delivery will be delayed by
2 weeks.

What should you do right now?

You should delay the payment also for 2 weeks.

You must immediately find a different contractor.

You should conduct a meeting with the contractor to resolve the delivery issues before making the payment.

You should make the payment and reschedule the project plan.

See references Marked for review

44. In a software company a large number of simultaneously performed projects utilize the same groups of human
and other resources.

What is the term commonly used for this situation?

Concurrent engineering

Resource over-allocation

Resource pooling

Program management

23 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

45. What does the acronym RACI commonly stand for in project management?

Responsible, Accountable, to be Consulted, to be Informed

Remote, Attached, Connected, Integrated

Risk Analysis and Caution Initiative

Randomly Accessible Cashflow Information

See references Marked for review

46. You have used estimates made by your team members and applied the critical path method to compute a network
logic diagram for your project. Then you found out that it cannot be sufficiently optimized for scarce resources and
fast progress towards a given deadline. What should you do next?

Apply resource leveling heuristics to uncritical activities only.

Reduce estimates on duration and work efforts by an adequate percentage.

Apply Three-point estimation and critical chain project management.

Remove physical constraints and replace hard logic with soft logic.

24 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

47. Liquidated damages (LDs) are contractually agreed payments in order to...
...give the contractor an incentive to meet an aggressive schedule or challenging quality objectives.

...penalize the contractor for late completion of a project or failure to meet specifications.

...cover the customer's costs caused by late completion or failure to meet specifications by the contractor.

...make a bid or proposal binding for the offerer while the customer has time to select among various
bidders.

See references Marked for review

48. What should not be covered by a risk management plan?


Roles and responsibilities for handling project risks

Timing of project risk management activities

The methodological approach used for risk management

Individual risks and potential responses to them

25 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

49. You are assigned as the project manager to a project which had a one-time cost variance in the past caused by
unexpected rework which has meanwhile been finished.

You perform earned value analysis and get the following results:

EV: 250,000; PV: 200,000; AC 275,000

BAC is 500,000.

What is right?

EAC = 550,000

EAC = 525,000

EAC = 500,000

EAC = 425,000

See references Marked for review

50. An estimation has been made that the construction of a residential home will cost a certain amount per square
foot of living area. This is an example of what type of estimating?

Analogous estimating

Bottom-up estimating

Top-down estimating

Parametric estimating

26 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

51. What is true for prototypes?


Prototyping causes significant costs and should be avoided wherever possible.

They are tangible and allow for early feedback on requirements by stakeholders.

Prototypes are mostly developed toward the end of a design or build phase.

Prototypes increase the risk of misunderstandings between developers and users.

See references
Marked for review

52. What is a constructive change?

A change request that helps improving the project and its product, service or result and is discussed
generally in a friendly style.
A direction by the buyer or an action taken by the seller that the other party considers an undocumented
change to the contract.
A field change or ad-hoc change mandated by the project customer in a public construction project.

A change request which will lead to the re-construction of an older version of the project performance
baseline by the contractor.

27 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

53. Which of the following is generally not regarded to be a motivator according to Frederick Herzberg?

Working conditions and interpersonal relations

Responsibility for enlarged task

Interest in the task

Recognition for achievement

See references Marked for review

54. What is true for modern project management? Project managers need...

... to have a strict standing in negotiating

... to show experience in tricking business partners

... to be team players and facilitators instead of "bosses"

... to be strongly linked to local traditions

28 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

55. You are the project manager in an engineering project and have recently signed a contract with a software vendor
for the development of a complicated control solution. The software will be used to control machinery equipment
which your project team is currently developing. The contract is a lump-sum contract. The contractor has target
cost estimated which seem rather low to you. Which of the following statements is not true for this situation?
It is the contractor's risk in this type of contract that their profit may vanish if costs have been
underestimated.
This form of contract should only be chosen when all the requirements for the building of the product are
well-known by all parties involved.
In a fixed-price contract, change requests can cause issues regarding additional time and extra costs for
the changes to be applied.
It is likely that your organization may have to assume any unexpected additional costs for the software
development.

See references
Marked for review

56. A review to determine whether of project activities comply with organizational and project policies, processes, and
procedures is commonly called

Quality auditing

Inspection

Quality testing

Reject screening

29 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

57. Which of the following is true regarding the code of accounts?

It allows one to easily identify the breakdown level of the item in the resource structure.

It describes the coding structure used by the performing organization to report financial information in its
general ledger.
It is the collection of unique identifiers generally assigned to WBS items.

It defines ethical behavior in the project and the responsibilities to the customer and the profession.

See references
Marked for review

58. You are the manager of your company's project management office. The company is running many concurrent
projects; most of them share a resource pool of technical staff. Understanding how resources are utilized across
projects has been found essential to overall project performance, including cost effectiveness and profitability.

This morning you received a message that the resource pool members will be unable to perform as planned for
the next months because the overall work load has grown too high and while delays are adding up, the morale of
the staff is going down.

What should you do next?

Ensure that quantitative information for all projects is being made available in a uniform and reliable fashion
and verify that the project management methodology is adhered to. Then consolidate the information to get
an understanding of the problems related with the use of shared resources.
Implement an enterprise project management software solution which is able to level the human resources
across the various projects and which has the capability to model resource assignment on a percentage
level thus optimizing resource utilization for the overall organization.
Do nothing related to the described problem unless you are explicitly requested by the organizations upper
management. Supporting decision making on the level on which project portfolio management is done, is
not the project management office's business.
Evaluate project management software which supports planning and scheduling across enterprise-wide
project portfolios. Avoid managing the availability of shared enterprise resources for the projects run by an
organization because this is not the business of a project management office.

30 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

59. You have been criticized that certain specifications in your scope statement do not pass the test for SMART
objectives. What are SMART objectives?

Objectives specified in far more detail than necessary for a execution of a successful project.

Easily achievable objectives which help you reducing the pressure on yourself and the team.

Objectives that should be achieved in order to attain formal recognition by both the customer and the
project sponsor.
Objectives that are described using specific, measurable, assignable, realistic and time-related
specifications.

See references
Marked for review

60. You have been assigned as a project manager to a software project. While you and your team are working on a
WBS (work breakdown structure), estimations for activity durations based on the activity list vary significantly.
Which additional documents may help you clarify this situation?

Milestone list and scope baseline.

Project schedule network diagrams and human resource plan.

Activity cost estimates and scope baseline.

Activity attributes and project scope statement.

31 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

61. You are performing earned value technique on your project.

After budget approval, an additional and unexpected cost item has been identified, which made the project more
expensive some weeks ago. The item has meanwhile been paid by the project team, and it is expected that for the
remaining duration of the project, costs will be as budgeted.

In this case, which is the best formula to calculate EaC (Estimate at Completion)?

EaC = BaC - CV

EaC = BaC / CPI

EaC = AC + BtC / CV

You can not compute the EaC.

See references Marked for review

62. During a company event, you had the opportunity to talk to a colleague project manager. He told you that in his
current project actual costs are 15% under cumulated costs budgeted for today.

What do you think?

The information given to you by the colleague is not sufficient to assess project performance.

The project will probably be completed with total costs remaining under budget until the end.

A significant cost increase during the further course of the project will probably bring the costs back to
baseline level.
Original cost forecasting and budgeting for the project must have been poor to allow this variance.

32 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

63. What is the meaning of a concept called the "Journey to Abilene"?

Project managers should visit their customers far more often than what is usual in order to avoid
misunderstandings and bad emotions.
International projects may have an increased need for traveling which can lead to additional costs and
troubles with time zones.
Committee decisions can have the paradox outcome, that a jointly made or approved decision is not
desired by any individual group member.
A project is a temporary endeavor undertaken to create a unique product, service or result. Repeating it
would be similar to making the same journey twice.

See references Marked for review

64. Which of the following statements describes best the relationship between project phases and the project life
cycle?

The project life cycle includes the time when the project is performed and the expected product lifespan
after that.
In project management, the sequence of project phases and phase gates is often referred to as project life
cycle.
The project life cycle is regarded as a sequence of project activities while phases are defined to control
overlapping activities.
The project life cycle describes how iterations of project management processes are used when a project
schedule is developed.

33 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

65. Which is an appropriate order in most project situations for the development of scope-related documents?

1. Project SOW (statement of work),


2. Project charter,
3. Project scope management plan,
4. Project scope statement,
5. WBS (work breakdown structure) and WBS dictionary.
1. Work breakdown structure,
2. Scope statement,
3. Project charter,
4. CSOW (contractual statement of work),
5. Contractual work breakdown structure
1. Feasibility study
3. Contract,
4. CWBS (contractual work breakdown structure),
5. Scope of work descriptions,
6. PID (project initiation document).
1. BOM (Bill of materials),
2. CAP (control account plan),
3. Project charter
4. Change management plan,
5. Scope baseline.

See references
Marked for review

66. What is the S-curve in project management?

A graph that is generated if a normal curve is integrated.

A graph that is to be integrated to generate a normal curve.

A metaphoric description of the short term uncertainties that are present in every project.

The graph that describes the typical growth of earned value during the course of the project.

34 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

67. An output of the process Estimate activity resources is a document called "activity resource requirements". It
identifies the types and quantities of resources...

...while the term resources is limited to equipment and materials.

...required for each activity in a work package.

...while the term resources is limited to human resources.

...to be obtained solely from the performing organization.

See references Marked for review

68. What is not the purpose of configuration control when configuration management is applied in a project?

Verification that the configuration identification for a configuration item is accurate, complete, and will meet
specified program needs.
Ensuring that proposed and approved changes to configuration items are fully analyzed.

Ensuring that proposed and approved changes to configuration items are fully documented.

Managing and controlling the frequently requested changes to a project by applying agreed rules.

35 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

69. Which statement describes best the meaning of the term cost baseline?
A cost baseline is always created by translating time-phased cost information into cost data on activity or
work-package level.
A cost baseline is an approved time-phased budget that will be used to measure and monitor cost
performance on the project.
Data to draw a cost baseline can be easily generated and updated as necessary from information related to
actual project cost.
A cost baseline is usually displayed in the form of an inverse S-curve drawn from the beginning of the
project until data date.

See references
Marked for review

70. Which is not true in regard of RoI (return on investment) for a project?

It defines the cumulated net income from an investment at a given point in time or during a defined period.

It includes investment, direct and indirect costs and may include allowances for capital cost, depreciation,
risk of loss, and/or inflation.
It is most commonly stated as a percentage of the investment or as a dimensionless index figure.

It is the time when cumulated net income is equal to the investment.

36 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

71. A project sponsor requested earned value data on two concurrent projects from the project managers. Both
projects are regarded as equally important and strategically beneficial and have been finished by over 80%. He
received the following information:

Project A:
PV: $1,800,000
EV: $2,300,000
AC: $2,100,000

Project B:
PV: $2,000,000
EV: $1,500,000
AC: $1,600,000

The sponsor considers to shift some resources from project A to project B to speed up the second project which is
currently behind schedule.

What is the most likely outcome of such a measure?

Changing team assignments during late course of a project typically increases cost efficiency.

Changing team assignments during late course of a project typically increases time efficiency.

According to the law of diminishing returns, the consolidated cost variance of the two projects will decrease.

According to the law of diminishing returns, the consolidated cost variance of the two projects will increase.

See references Marked for review

72. Which of the following statements describes best the relationship of quality and grade?

Low grade is always a problem; low quality may be overcome by a good rework and repair process.

Grade is a category or rank given to entities having different functional requirements but the same need for
quality.
Both quality and grade can often be improved through intelligent measuring, testing and examining.

Low quality is always a problem as it bears on the ability of an item to meet requirements; low grade may
sometimes be acceptable.

37 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

73. Network templates which contain only portions of a network are often referred to as

Sub-networks or fragment networks

Subprojects

Programs

WBS items

See references Marked for review

74. You have been asked to calculate the internal rate of return (IRR) of a project? What will you assess?

The time period needed to pay back the investment from a project when future income is discounted.

The inherent discount rate or investment yield rate produced by the project's deliverables over a
pre-defined period of time.
The rate of negative risk that can be accepted for a project without turning the expected net present value
negative.
The expected benefit from a project’s deliverable calculated as a percentage of the original investment over
a specified time period.

38 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

See references
Marked for review

75. You just created the following network logic diagram to describe the planned flow of activities for your project
which will start tomorrow:

Which potential inconsistency in the diagram should you solve right now?

Activity E is open ended ( a "dangle") in relation to the finish milestone path convergence.

Activity F is open ended in relation to the path divergence after the start milestone.

You cannot calculate a critical path when lags and/or leads are calculated in percent.

Activities E to F need another task drawn as a hammock to calculate level of effort.

Reset all answers Solve Sample Test Print Sample Test

Result: of 75, %

Notes:
- After clicking the Solve Sample Test button, the correct answers will be highlighted in blue color above in the questions & answers section.
- PMI made a decision in 2006 to not publish passing scores for the exams any more. The actual score is estimated to be between 70% and 75%. I
recommend to target 75% results or better in this and all other difficult prep tests you are taking, 82% in simple tests.

I am...
...generally interested in the PMP certification.

...on my way to pass the PMP exam.

...already certified as a PMP.

Finished? Click here to send your feedback to me.

Help your friends find this free service easier by clicking:

143 Tweet 84 Like 149 Send XING Follow Share

More Providers of Free PMP (+CAPM) Preparation


Questions
Christelle P. from Canada mailed Oct 11 2003:

"I passed the test! Thanks for the 75 prep questions. The only way to succeed is to write tons of practice exams!"

So true! In 2002, I was the only provider of free PMP exam prep questions on the web. Today, you can find thousands
of them on the web.

Below are links to many providers with more than 3,000 free prep items (questions and answering options); more than
4,000 for PMI members:

# of
Level of
free
Provider URL Comment difficulty
test
(explain)
items
Ajith Namboothiri www.ajithn.com 208 Requires registration. Number
of questions may grow, as
visitors are invited to add
further questions. Many
questions of CAPM exam
style.
La Tha 206-free-pmp-exam-questions.blogspot.com 206
CertChamp www.certchamp.com 200
CertGear www.certgear.com 6 Free trial of CertGear's exam
simulator.

39 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

Certification. certification.about.com 20 Questions based on


about.com Whizlabs' Exam Simulator
software trial.
EdWel Programs www.edwel.com 200 Requires registration
Head First Labs www.headfirstlabs.com 200 Online practice exam from the
authors of Head First PMP
book. A PDF file with 2MB for
download.
MeasureUp www.measureup.com 7 Simulates a test environment
online similar to the original
environment.
My PMP www.mypmp.ie 90 Simulates a test environment H
online similar to the original
environment.
Oliver F. www.oliverlehmann.com 175 PDF file (app. 1MB) for H
Lehmann, PMP download.
Just like the real thing:
Questions are written against
the PMP Examination
Content Outline and
reference to a current project
management source.
www.oliverlehmann-training.de 175 German language aid for the H
175 questions.
www.oliverlehmann.com 75 The 75 questions above, with H
a timer in the title bar.
itunes.apple.com/de/app/xzams-pmp-sample 30 30 free questions for Apple H
/id399303897?mt=8 iPhone and iPad.
market.android.com/details?id=com.digit.pmpexamfree 30 30 free questions for Android H
smartphones and tablets.
PMP Preparation in Google+ New PMP prep question H
posted and discussed from
time to time.
Project Management, PMI, PMP Certification in Visitors submit new PMP prep H
Google+ questions and discuss them.
www.oliverlehmann.com 164 CAPM Prep Questions: Not (CAPM)
quite the PMP exam style, but
also helpful for your
preparation.
CAPM® Virtual Study Group 50 For CAPM preparation: (CAPM)
Attendees are invited to post
own questions. Also helpful
for PMP preparation.
Registration required.
OSP International www.free-pm-exam-questions.com 110 My friend Cornelius Fichtner
LLC and his company are happy
to help project managers
pass the PMP exam.
Registration required.
free.pm-exam-simulator.com 90 Simulators help get familiar H
with MC exam environments.
PassTheProjectExam passtheprojectexam.com 431 Simple simulator
PMConnection www.pmconnection.com 10
PMExam.com www.pmexam.com ? Order their free Daily Digest H
as an e-mail service. A great
resource with intelligent
questions.
PMPerfect.com www.pmperfect.com 10 Nice little simulator for the H
real test. Good questions.
PMPQuest.com www.pmpquest.com 12
PMP Question pmpbank.googlepages.com 200 Good, difficult questions. H
Bank
PM Study www.pmstudy.com 50 200 free questions after
optional registration.
www.pmstudy.com 15 Registration needed (CAPM)
PMTI www.4pmti.com 15 Registration required.
Pmzilla www.pmzilla.com 155 Registration required.
Practical PM www.mosaicprojects.com.au 30 Come as an Excel file.
Pty. Ltd. www.mosaicprojects.com.au 25 CAPM Prep Questions. Not
quite the PMP exam style, but
also helpful for your
preparation.
PreparePM www.preparepm.com 165 High quality questions, which H
simulate the real test very
well.
Project PMP sites.google.com/site/pgmpguide/ 480 H
ProXalt www.proxalt.com 20 Registration required.

40 of 41 03/13/2013 01:35 AM
Test time: 016:50:40 - Total test time: 90 Min. Testing tim... http://www.oliverlehmann.com/pmp-self-test/75-free-ques...

SSI Logic, pmi.books24x7.com +1000 Free (for PMI members) H


Christopher Scordo, online version of the book
PMP, ITIL through PMI's eReads and
Reference. Commercial
version available in stores.
Simplilearn www.simplilearn.com 200 Registration required. Tough H
stuff. Good.
Test Prep www.testprepreview.com 15
Review
Threon www.threon.com 13 H
Trial Exams www.trial-exams.com/ 30 Registration required H
Tutorials Point www.tutorialspoint.com 200
University High School www.slideshare.net 150 (CAPM)
Fresno
Voight Project www.voightps.com 500 My friend and colleague Dr. H
Solutions Roger Voight has a large
body of free questions. Many
of them are also helpful for
CAPM candidates.
You need MS Internet
Explorer to open them.
Whizlabs www.whizlabs.com 52 Digest for exam simulator.
H
Registration required.

* Level of difficulty marked with H: If you achieve 75% in these tests, you should be well prepared for the real exam. Raise the
number to 82% for the other tests.

Preparation seminars with Vorbereitungsseminare mit


Oliver F. Lehmann, PMP Oliver F. Lehmann, PMP

Help your friends find this free service easier by clicking:

143 Tweet 84 Like 149 Send XING Follow Share

Sponsors:
FREE Download for learning and
instruction.

Insight tree supports project


selection and helps you become a decision
tree expert.

"PMI", "PMP", PgMP", "CAPM", "PMBOK" are marks of the Project Management Institute (PMI) which are registered in the United States of America
and in other nations
PMI has not participated in the creation of this self assessment test and has not reviewed it for correctness.
This test is for self assessment only and no guaranty is given for passing the PMP® exam.
Some of the names of companies and their products listed and linked to on this page are marks which are registered in various countries.
© 2004-2007, all rights reserved. The owner of this website is not responsible for contents of external pages to which he placed hyperlinks. Contact:
oliver@oliverlehmann.com
Advertisment

41 of 41 03/13/2013 01:35 AM

Das könnte Ihnen auch gefallen