Beruflich Dokumente
Kultur Dokumente
in partial fulfillment for the award of the degree of BACHELOR OF ENGINEERING in MANUFACTURING ENGINEERING
DEPARTMENT OF MANUFACTURING ENGINEERING COLLEGE OF ENGINEERING, GUINDY ANNA UNIVERSITY CHENNAI::CHENNAI 600 025 MAY 2010
i
[Type text]
Department of Manufacturing Engg. College of Engineering, Guindy Anna University Chennai Chennai 600025
Department of Manufacturing Engg. College of Engineering, Guindy Anna University Chennai Chennai 600025
ii
[Type text]
ABSTRACT
Degree Branch Month and year of submission Course Title of the project : Bachelor of Engineering : Manufacturing Engineering : May 2010 : MN483 Project Work : Optimization of Material Handling in roof sheet assembly for Railway coaches Name of the students : Abinesh Maran. T Vasanthi. R Venkatraj. N Vignesh. M Name and Designation of guide : Dr. M.Omkumar Senior Lecturer, Dept. Of Manufacturing Engineering, College Of Engineering, Guindy Anna University, Chennai Chennai 600 025 20061401 20061436 20061438 20061439
The topic deliberated here mainly deals with the optimization of the production process at the Integral Coach Factory, Chennai. The crux of the topic here is that the amount of material handled in the shop floor is generally 9 times more than that
iii
[Type text]
is actually used to produce the final product. Hence this project is aimed at reducing the work in progress inventory to the least. Also, to device a method to store the work in progress inventory (steel sheets). This project includes optimizing algorithms, facility planning for efficient production and systematic study on various storage techniques for steel sheets to finally zero in on the most economical way of storage not compromising on quality and safety, therefore helping the organization in increasing the productivity, reducing the cost and reducing scrap in the form of rust. Date: Place: Chennai ABINESH MARAN. T 20061401
VASANTHI. R 20061436
VENKATRAJ. N 20061438
VIGNESH. M 20061439
iv
[Type text]
ACKNOWLEDGEMENT
We would like to sincerely thank Dr.M.OMKUMAR, senior lecturer , Department of Manufacturing Engineering for his invaluable guidance, support, encouragement and keen interest, which helped us in the successful completion of our project.
We wish to thank Dr.T.V.MOORTHY, professor and head, Department of Manufacturing Engineering, for providing support towards the completion of the project.
We solemnly thank Dr.S.GOWRI, Professor, project coordinator and Mr.G.SHAKTHINATHAN, Lecturer, Department of Manufacturing Engineering, for their valuable suggestions.
We are very much thankful to Mr.RAMAKRISHNAN, sectional engineer, ICF, for his immense care and guidance from the start of the project and till the completion of it.
We also wish to express our hearty thanks to all the faculty members of Department of Manufacturing Engineering for their time being help and encouragements towards the successful completion of our project.
[Type text]
TABLE OF CONTENTS
CHAPTER NO. TITLE ABSTRACT LIST OF FIGURES LIST OF TABLE 1. 1.1 2. INTRODUCTION PAGE NO. iii ix x
Plant layout Objective of Plant Layout Factors Affecting Plant Layout Types of Plant Layout and Function Process Layout
[Type text]
Relationship Chart Steps of ALDEP Data Collected Relationship Chart for Data collected Filling The Cells
MATERIAL HANDLING
5.1
Material Handling Equipment 5.1.1 Transport Equipment 5.1.2 5.1.3 5.1.4 5.1.5 Positioning Equipment Unit Load Formation Equipment Storage Equipment Identification and Control Equipment Principles of MHE Automatic Guided Vehicles
5.2 5.3
vii
[Type text]
5.3.1 5.3.2 5.3.3 5.3.4 5.3.5 5.3.6 5.3.7 5.3.8 5.3.9 5.3.10 6 6.1 6.2 6.2.1 6.2.2 6.2.3 6.3
7
Navigation Wired Sensor Guide Tape Steering Control Path Decision Frequency Select Mode Path Select Mode Magnetic Tape Mode Vehicle Types Common AGV Applications
GALVINIZING PROCESS
Types of Surface Protection Elements of Galvinizing Process Surface Prepartion Galvinizing Inspection Benefits of Galvinizing Process
CONCLUSION REFERENCE
viii
[Type text]
LIST OF FIGURES FIGURE No. 2.1 2.2 4.1 4.2 5.1 5.2 TITLE Stack of materials Assembly fixture Existing layout Proposed machine cell layout Transport equipment AGV moving in shop floor PAGE No.
ix
[Type text]
LIST OF TABLES TABLE No. 2.1 4.1 4.2 4.3 TITLE Assembly time Closeness value Area of each machine cell Relationship chart PAGE No.
CHAPTER 1 INTRODUCTION
Fig 2.1 Stack of materials Another problem is that work in process is not routed progressively, which means the machines required for processing are not sequentially placed that leads to multiple transactions of the same material back and forth. Hence there is a huge loss of time in this process. So, the Overall production rate is 1400 coaches per year. The number of shifts taken, hrs per shift and the number of laborers for different types of coaches is given in table 2.1.
2
No. of shifts 3 3 3 3
No. of laborers 10 10 10 10
Table 2.1 Assembly time The following calculation quantifies the above: Consider BG (Broad Gauge): No. of sheets required = 7*3 = 21 Total hrs = 20.1 Laborers: 4 fitters and 6 welders 20.1hrs distributed for structure building, handling, and welding, hammering and finishing operations. The above quantification is only for the assembly and prior to each part of the assembly, the respective forming and fabrication must be done within the scheduled time. The assembly fixture for the roof sheet is shown in fig 2.2.
2.2 PROBLEMS
The efficiency of material handling system at present, in the existing shop floor layout is less than 10% i.e., the material handled is nine times the material being processed. A lot of human effort is being exploited in the handling of the WIP. This leads to huge lead times and at a point of time either the machine or the WIP is Idle within the shop floor.
To increase the rate of production. This can be achieved by reducing the WIP which in turn is brought about by optimizing the process layout. To reduce the number of accidents which is possible by devising a proper material handling equipment which carries the material from the start till the end progressively and reducing the manual handling
To reduce the level of inventories. To reduce the overall material handling time. Implement a new material handling system for hand ling roof sheets.
2.5 SUMMARY
This chapter explains the current existing scenario in the shop floor for the manufacture of roof sheets and also lists out the various problems faced by the workers, both directly as well as indirectly during the manufacturing process. The main aim and objective of this project is also discussed in detail in this chapter.
activity since it determines the efficiency. Generally what is being achieved is arrangement of work areas and equipment which is the most economical and at the same time safe and satisfying employees. Plant Layout is concerned with the analysis, planning, and design of the physical facilities utilized in the production of goods and services. Material Handling deals with that phase of the operations which involves the movements of the material used in carrying on the activities of the enterprises. No two aspects of industrial activity are more closely related. Actually, Material Handling is a Major part of nearly all Plant Layout work. This close relationship is emphasized in the following definition of Plant Layout: Plant Layout may be defined as planning and integrating the paths of the component parts of a product to obtain the most effective and economical inter relationships between men, equipment and the movement of material from receiving, through fabrication, to the shipment of the finished product, (H.A.HARDING, 1997). Plant layout planning includes decisions regarding the physical allocation of the economic activity centers in a facility. An economic activity center is any entity occupying space. The objective of plant layout planning is a more effective work flow at the facility, allowing workers and equipment being more productive. Facility layout techniques apply to the case where several physical means have to be located in a certain area, either industrial processes or services. The objective of the chapter is not only plant layout but re-layout also (most common situation for a company). To carry out an appropriate plant layout, its important to take into account the business strategic and tactical objectives. Example: space requirements / cost per m2 in Malls;
accessibility/ privacy in offices. To make a decision about layout planning, 4 different questions must have an answer: Which centers do we have to consider? How much space and capacity is required for each center? If there is not enough space, productivity may be reduced. Too much space is expensive and may also reduce productivity. How must the space be configured at each center? Space quantity, shape and the elements of the work center are related to each other. Where should each center be located at within the facility? The allocation of the different centers may affect productivity. The plant layout process starts at an aggregate level, taking into account the different departments. As soon as we get into the details, the different issues arise, ant the original configuration may be changed through a feedback process. Most (if not all of them) layouts are designed properly for the initial conditions of the business, although as long as the company grows and has to be adapted to internal and external changes, a re-layout is necessary.
The reasons for a re-layout are based on 3 types of changes: Changes in production volumes Changes in processes and technology Changes in the product
Grinding (5)
Milling (1)
Welding
Assembly
(3)
(4)
(4)
(6)
(6)
Drill (2)
Grinder (3)
Assembly (4)
Grinder (2)
Miler (3)
Lathe (4)
Welding (5)
(c) Through wider of labor supply 4) Easier control (a) Of production allows less paper work. (b) Over workers allows easier supervision
inputs
11
12
3.7 SUMMARY:
This chapter gives the basic definition for plant layout and explains the various types of plant layouts in detail along with their pictorial representations and advantages. This chapter also explains the procedure and the relevant data required in order to design a new plant layout or even to modify the existing plant layout in order to overcome the disadvantages in the existing layout. Finally this chapter explains the flow of operations in the shop floor for the manufacturing of roof sheets.
14
Automated Layout DEsign Program (ALDEP) is a construction type algorithm. This algorithm uses basic data on facilities and builds a design by successively placing the department in the layout. After placing all the departments in the layout a score is computed. This is nothing but the sum of the closeness rating values of different neighboring department in the layout. This algorithm is repeated for a prespecified number of times and the best layout is selected based on the maximum layout score. The basic data required for this algorithm are listed below 1. Total number of department 2. Area of each department 3. Length and width of layout 4. Closeness rating of various pairs of department in the form of Relation chart 5. Minimum department preference ( MDP) value. 6. Sweep width 7. Number of iterations to be performed 8. Location and size of each restricted area in the layout if present.
15
Closeness Absolutely necessary Especially important Important Ordinary closeness OK Unimportant Not desirable
Notation A E I O U X
Value 64 16 04 01 00 -1024
16
List B contains the unselected departments whose relationship values in relation to the lastly selected departments are greater than or equal to the MDP value. Step3. Is the List B empty? If so, go to step 4; otherwise, go to step5. Step4. Select a department randomly from List A and place it in the layout. Go to step 6. Step5. Select a department from List B which has the maximum REL value in relation to the lastly selected department and place it in the layout. Step6. Whether all departments are placed in the layout? If not go to step2; if yes, go to step7. Step7. Compute the score of the layout. Step8. Is the score of the layout more than the score of the current best layout? If yes, update the new layout as the current best layout and store the corresponding score. Otherwise, drop the new layout. Step9. Is the current iteration number I=N? I f yes, go to step 10; otherwise, increment the iteration number by one (I=I+1) and go to step 1. Step10. Print the current best layout and the corresponding score.
17
DEPARTMENT NAME Cut To length Machine Profile Bending Seam Welding Press Break 1 Press Break 2 Assembly
AREA in Sq.Ft 115 x 32 = 3680 ~ 3600 25 x 40 = 1200 30 x 52 = 780 ~ 800 24 x 25 = 600 24 x 25 = 600 80x 40 = 3200
NUMBER OF SQUARES 36 12 8 6 6 32
18
cut to machine Profile Bending Seam Welding Press Break 1 Press Break 2 Assembly
O I E E E 0
Assumptions:
Each machine in the shop floor is assigned a number and this number is used to represent the particular machine in the ALDEP table as shown in the iterations. 1 - Cut to length machine 2 - Profile bending 3 - Seam welding
19
List:
There are two lists A and B. list A contains the machines having least proximity values (o,u) and list B contains the machines having maximum proximity values (a,e,i). List A {o,u} List B {a,e,i}
Relationship values:
A E I O U 64 16 04 01 00
20
21
1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1
2 2 1 1 1 1 1 1 1 1
2 2 1 1 1 1 1 1 1 1
2 2 2 2 3 3 3 3 4 4
2 2 2 2 3 3 3 3 4 4
6 6 6 6 6 6 5 5 5 4
6 6 6 6 6 6 5 5 5 4
6 6 6 6 6 6 6 6 6 6
6 6 6 6 6 6 6 6 6 6
Relationship Score:
1 2 = 64 2 3 = 64 2 6 = 04 3 6 = 16 3 1 = 16 4 1 = 64 43=1 45=4 5 6 = 16
For cell 1: list A {6}, List B {2, 3, 4, 5} For cell 2: list A {4, 5}, List B {3, 6} For cell 3: list A {6}, List B {4, 5} For cell 4: list A {6}, List B {5}
4 6 = 16 1 3 = 16 Total : 281
22
4.6 EXPLANATION:
Iteration 1 gives the existing distribution of the machine cells in the shop floor. The pictorial representation of the existing shop floor is given in fig 4.2. The entire shop floor area and the area occupied by each machine along with the area for material storage are measured. The common factor from all the individual machine cell area is removed and tabular grids are drawn for the remaining area. In our case, 100 sq feet is taken as the common area factor and the remaining total are is calculated to be 100 sq feet. A 10x10 tabular grid is constructed, wherein each cell represents 1 sq feet. The grid is now filled with numbers, which are used to represent each machine cell as explained in assumption. The tabular grid is filled column wise taking two cells of a row at a time and also the filling is done in a continuous way starting from the first two cells of the first row and ending with the last two cells of the last row. The machines are then place in the same order along the shop floor. The best layout can be identified by trying all possible iterations and calculating the relationship score for each iteration. The maximum score corresponds to the most optimized layout. The first machine cell is selected randomly and the area occupied is filled along the tabular grid. Based on the closeness relationship between the filled machine cell and the remaining machine cells, two lists are created. They are known as list A and list B. list A consists of the machine cells having least closeness relationship with the previously filled machine cell and list B consists of machine cells having the maximum closeness relationship with the previously filled machine cell. For instance iteration 1 is started by filling the tabular grid with number 1, which corresponds to the Cut to Length Machine. Now the list A for Cut to Length machine contains the assembly cell and list B consists of the remaining machines. Now, among the machine cells in list B, the one with maximum closeness value with machine cell 1 is selected and filled along the tabular grid. In this way the tabular grid is filled completely with all the machine cells. From the filled tabular grid, the machines which are in direct contact are identified and the relationship values are added together in order to calculate the total score for example: in iteration 1, machines 1 and 2 are in direct contact with each other and there corresponding closeness notation is A, which corresponds to a value of 64. Similarly all the closeness values of the machines which are in direct contact with each other are added and the final score is computed. The final score for iteration 1 is 281. In this way all possible iterations score were calculated and the highest score obtained was 313, which corresponds to iteration 3. Hence
23
iteration 3 is considered to be the most optimized machine cell layout and its corresponding machine locations are shown in fig 4.2.
Relationship Score
24
Relationship Score
25
4.7 SUMMARY:
This chapter deals with the algorithm used to modify the current layout into an optimized one. This chapter gives a detailed introduction about the ALDEP algorithm and explains the step by step procedure for using it. The various data collected from the shop floor, which are used as input to the algorithm, are presented using figures and tables. A pictorial representation of the existing and the suggested optimized layout along with its tabular grid diagram and explanation is also given in this chapter.
27
Material Handling involves the movement of material, manually or mechanically in batches or one item at a time within the Plant. The movement may be horizontal, vertical or combination of horizontal or vertical. Material Handling is concerned with motion, time, quantity and space. Basically Material Handling is the art of implementing movement-economically and safely.
28
Fig.5.1 Transport Equipment The major subcategories of transport equipment are: Conveyors- Equipment used to move materials over a fixed path between specific points. Cranes- Equipment used to move materials over variable paths within a restricted area. Industrial Trucks- Equipment used to move materials over variable paths, with no restrictions on the area covered by the movement (i.e., unrestricted area).
30
the standardization of equipment and methods, the combination of material handling methods and the consideration of safety hazards. 7. The length and number of moves of material should be kept to a minimum. Movement paths should be studies for the possibility of reducing "backtracking" and length of moves, resulting in better utilization of equipment and personnel. 8. Equipment capacities should never be exceeded. Overloading causes excessive wear of equipment and creates accident potential. 9. All materials handling activities should be analyzed for improvement possibilities by elimination, combination or simplification. Combination of operations may result in the simplification and reduction of the number of times material must be handled. 10. The selection of MHE is based on the economies of operation. Greater payloads for each handling operation will result in less handling cost per piece. 11. The "physical state" of materials is a factor in determining MHE. The three physical states of material - solid, liquid and gas - determine the method of containment (pack). This, in turn, influences the selection of MHE. 12. The shortest distance between two given points is a straight line - utilize a straight line flow of materials whenever possible. The time to move materials can be reduced by using a straight line flow. 13. Materials should move continuously along any production line. Choppy or broken flow causes confusion and delay. Most shipping and receiving operations should operate on the principle of continuous flow. 14. All materials handling operations should follow a defined method. The standardization of the method will provide a basis for determining handling requirements. 15. Short, irregular moves lend themselves to manual materials handling. When moves are short, irregular and load capacity of people is not exceeded, it may be more economical to use manpower. 16. Whenever practicable materials should be prepositioned for the handling operations. Prepositioning places containers in position to facilitate picking up and/or moving and materials so they do not obstruct other materials.
31
17. Whenever practicable, materials should be moved in a horizontal plane or with the aid of gravity. The ideal lifting position is at the waist. The nearer to the waist that a container or part can be picked up and disposed, the greater will be the efficiency.
32
5.3.1 NAVIGATION
AGVs in a FMS are used to transport an object from point A to point B. AGVs navigate manufacturing areas with sensors. There are two main sensors AGVs use for navigation, a wired and a wireless sensor.
The other type of steering used is steered wheel control AGV. This type of steering is similar to a cars steering. It is more precise in following the wire program than the differential speed controlled method. This type of AGV has smoother turning but cannot make sharp turns in tight spots. Steered wheel control AGV can be used in all applications; unlike the differential controlled. Steered wheel control is used for towing and can also at times have an operator control it.
34
AGVS Towing Vehicles were the first type introduced and are still a very popular type today. Towing vehicles can pull a multitude of trailer types and have capacities ranging from 8,000 pounds to 60,000 pounds.
AGVS Unit Load Vehicles are equipped with decks, which permit unit load transportation and often automatic load transfer. The decks can either be lift and lower type, powered or non-powered roller, chain or belt decks or custom decks with multiple compartments.
AGVS Pallet Trucks are designed to transport palletized loads to and from floor level; eliminating the need for fixed load stands.
AGVS Fork Truck has the ability to service loads both at floor level and on stands. In some cases these vehicles can also stack loads in rack.
Light Load AGVS are vehicles which have capacities in the neighborhood of 500 pounds or less and are used to transport small parts, baskets, or other light loads though a light manufacturing environment. They are designed to operate in areas with limited space.
35
Repetitive movement of materials over a distance Regular delivery of stable loads Medium throughput/volume When on-time delivery is critical and late deliveries are causing inefficiency Operations with at least two shifts Processes where tracking material is important.
Fig 5.2 AGV moving in shopfloor. A few examples of typical leasing costs for different size AGV systems: 1 vehicle CHEP forklift type AGV system with up to 20 load and unload positions and a travel distance of up to 100 meters. Monthly cost for 5 years, with no residual: Rs 2,09,500/month 3 vehicle CHEP forklift type AGV system with up to 50 load and unload Positions and a travel distance of up to 200 meters. Monthly cost for 5 years, with no residual: Rs 4,61,000/month
36
5 vehicle CHEP forklift type AGV system with up to 100 load and unload positions and a travel distance of up to 300 meters. Monthly cost for 5 years, with no residual: Rs 7,12,250/month
5.4 SUMMARY:
This chapter gives a basic definition for material handling and explains in detail the various means of material handling inside shop floor. The main area of focus in this chapter is the AGV, it explains the various types of AGVs their advantages and rent per month. Finally this chapter concludes with the specifications and cost of the AGV proposed suiting the conditions of the factory.
38
6.2 MECHANISM
The mechanism with which the hydraulically actuated table moves, such that the roof sheets are stored vertically inside the mobile bin is explained below
39
6.3 SUMMARY:
This chapter discusses the storage mechanism for the automated vertical storage of the roof sheet in order to reduce the handling time and automate the material handling. This includes the design, construction and working of the mobile bin and the storage table mechanism.
41
The surface preparation step in the galvanizing process has its own built-in means of quality control in that zinc simply will not react with a steel surface that is not perfectly clean. Any failures or inadequacies in surface preparation will be immediately apparent when the steel is withdrawn from the molten zinc because the unclean areas will remain uncoated. Immediate corrective action is taken. Surface preparation for galvanizing typically consists of three steps: caustic cleaning, acid pickling, and fluxing.
1. Caustic Cleaning - A hot alkali solution often is used to remove organic contaminants such as dirt, paint markings, grease, and oil from the metal surface. Epoxies, vinyl, asphalt, or welding slag must be removed before galvanizing by grit blasting, sand blasting, or other mechanical means. 2. Pickling - Scale and rust normally are removed from the steel surface by pickling in a dilute solution of hot sulfuric acid or ambient temperature hydrochloric acid. 3. Fluxing - Fluxing is the final surface preparation step in the galvanizing process. Fluxing removes oxides and prevents further oxides from forming on the surface of the metal prior to galvanizing and promotes bonding of the zinc to the steel or iron surface.
7.2.2 GALVANIZING
In this step, the material is completely immersed in a bath consisting of a minimum of 98% pure molten zinc. The bath chemistry is specified by the American Society for Testing and Materials (ASTM) in Specification B 6. The bath temperature is maintained at about 850 F (454 C). Fabricated items are immersed in the bath long enough to reach bath temperature. The articles are withdrawn slowly from the galvanizing bath and the excess zinc is removed by draining, vibrating, and/or centrifuging.
43
7.2.3 INSPECTION
The two properties of the hot dip galvanized coating that are closely scrutinized after galvanizing are coating thickness and coating appearance. A variety of simple physical and laboratory tests may be performed to determine thickness, uniformity, adherence, and appearance.
44
7.4 SUMMARY:
This chapter deals with the concept of galvanization in order to protect the roof sheets from the effect of the atmosphere. This explains the various types and elements of galvanization process and also covers the various advantages of this process..
45
CONCLUSION
Through this project we were able to analyse the existing plant layout and various material handling techniques present at the integral coach factory. The major areas addressed here and solved were reduction in the WIP inventories, change in the existing plant layout thereby reducing the operation and assembly time for the same number of roof sheet assemblies or for the same time increase in the number being produced. Though the entire WIP inventory cannot be brought down to zero, we have suggested a technique to protect them from the effect of atmosphere thereby preventing corrosions. We have also suggested a new material handling technique in order to reduce the overall material handling time thereby increasing the productivity from 1400 coaches in the year 2009-2010 to more than 2000 post implementation. The significant improvements made are: Change in the plant layout, thereby decreasing the distance between the work centers, using ALDEP algorithm Increasing the overall productivity by 21.89% Reducing the Idle time of the machines thereby decreasing the overall WIP inventory. Devising a new material handling system bringing it close to automation. Suggestion of Galvanization process for the protection of roof sheets from corrosion.
46
REFERENCE
Bley. H and Zenner C. (2005), Handling of process and resource variants in the digital factory CIRP Journal of Manufacturing Systems, No 34 H. 2, p. 187-194. Bley.H, Fritz.J and Zenner.C (2006) Digital factory in automobile industry vol 101, no 12, p 19-23. Blumenau.J and Wuttke.C (2005), Application of the digital factory in the ramp up of production systems by using online-data vol 54, no 34(3), p. 241-245. Bracht.U and Masurat.T (2005), The Digital Factory between vision and reality vol 56, no 4, p. 325-338. Cai,J and Weyrich.M (2004), Digital factory triggered virtual machining process planning for power train production in extended enterprise vol 32, no 3, p 332-342. Cai,J and Weyrich.M (2004), Supplier integrated power train machining process planning in digital factory vol 19, no: 4, p. 565-572. Hummel.V and Westkmper, E (2006), Factory Life Cycle Management vol 107, no 4, p. 178-182. Gausemeier, J and Stollt,G (2006), Digital factory and virtual production vol 101, no 1-2, p. 28-34. ICF official website www.icf.gov.in.
47