Beruflich Dokumente
Kultur Dokumente
Table of Contents
ii
2.
3. 4. 5.
Check the horizontal error and vertical error of the cabinet. Check all the screws, flat washers, and spring washers. Check the sanitation in and out of the cabinet.
6.
Check whether the front door can open and close easily.
Remarks Measure the horizontal and vertical errors using a horizontal bar.
3. 4.
Check the encapsulation of the feeder window Check the antenna installation.
The feeder window is properly encapsulated. The antenna installation meets the engineering requirements. For example, the installation positions, azimuth angle, and pitch angle of antennas. (1) All the connectors of the outdoor jumpers are waterproof and encapsulated. The waterproof curves of the jumpers are made. The bending radius of the jumper is no less than 20 times the diameter. The TMA is installed near the antenna. For the connectors on both sides of the TMA, the ones connecting the antenna face up, and those connecting the feeders face down. The connectors on one side of the TMA face down. The TMA is well grounded. The cable is securely connected. The feed is normal. The lightning protection grounding card is properly grounded. The feeders are properly grounded.
5. (1) (2)
Check the Tower Mounted Amplifier (TMA) and the feed. TMA location Connectors GMA grounding Cable between the DATU and the Bias-Tee
(3) (4)
7.
Remarks None.
Remarks For the installation positions of boards, see the engineering design.
2.
Remarks For the installation positions of the boards, refer to the engineering document.
2. (1) (2)
3.
4.
(1) (2)
5.
The cables laid in the cabling trough need not be tied. They need be laid in and along the trough with no crossover. If needed, the cables are tied in the entrance and exits or the turning points. When the trunk cables are laid overhead or under-floor, the curves must be made at the bottom of the cabling rack with extra part. Both ends of the trunk cables and fibers are attached with engineering labels. The labels used by the BTS3012AE are made by Huawei and attached 20 mm behind the plugs. (1) (2) The plugs of the fibers are intact. The fibers are not tight at the curving points; pairs of fibers are tied neatly; the fibers out of the cabinet are coated with corrugated plastic tubes, both ends of which are tied securely; the space between the cable ties are consistent; the fibers do not bear weight.
6.
7.
8. (1) (2)
Remarks None.
4.
The power cables and GND cables are separate to other cables with the extra parts cut and no coil.
Remarks None.
2.
(2)
Remarks The principles of lightning protection are as follows: 1. Protocols and standards ITU-T K.11 (1993) Principles of Protection Against Overvoltage and Overcurrents ITU-T K.27 (1996) Bonding Configurations and Earthing Inside a Telecommunication Building ETS 300 253 (1995) Equipment Engineering; Earthing and bonding of telecommunication equipment in telecommunication centers 2. Grounding Check the protection grounding using visual observation. The results must meet the following requirements: The neutral metal components (except the screws that are insulated from the live components) are packed as a whole and then securely connected to the protection grounding terminals. The size of the screws of the protection grounding terminals must be no less than M4. The identification of protection grounding must meet international standards, for example, PE, and symbols. 3. Lightning protection The lightning protection between the conductors of the grounding terminals with different phases is normal. The lightning protection between the grounding terminals and the neutral terminals is normal.
Remarks
Objective To verify RRU fibers a not cross connected Network diagram None Prerequisites The BTS is powered on and running normally after system commissioning. Expected Result Fibers are connecting correctly; corresponding sector fiber is connected to corresponding sector RRU.
Procedure Option 1: (1) Manually power off sector 1 RRU, and then confirm LED for sector is off at BBU. (2) Repeat above step for sector 2 and 3. Option 2: (1) Request RAN engineer to Block sector 2 and sector 3 (2) Make test call on sector 1, confirm you call is on sector 1 using compass and scrambling code. (3) Repeat above step for sector 2 and 3. Remarks If onsite engineer is unable to access RRU then process with option 2. If fibers are crossed, then correct connection.
Remarks
Procedure
1.
Remarks None
Remarks None.
Procedure (1) (2) (3) (4) (5) (6) (7) Calibrate Power Meter before testing Ask Huawei Engineer to block U900 Power off MRFU or MRRU Connect the RF power meter to the TX/RX port of MRFU or MRRU. Set power meter to correct test frequency bandwidth Power on MRFU or MRRU Start output power test.
Remarks 1. 2. The impedance of RRUs or RFUs RF output port is 50 Connect power meter to TX/RX port directly.
2.
3.
10
11
12
13
the detailed procedure show the following diagram Remarks To make test calls on all sectors to New Zealand Emergency services 111.
14
15
T03-03 SMS
T03-0301 Short Message Service
Objective Verify that the BTS system supports Short Message Service. Networking diagram None. Prerequisites The BTS is working normally. Test MS. Procedure Use the test MS lock onto sector1 and send an SMS to another MS. Test MS lock onto sector 1 and receive SMS from another MS. Repeat procedure for sector 2 and sector 3. Remarks None. Expected result SMS successfully sent and received.
T03-04 PS Call
T03-0401 PS Data Services
Objective Verify that the BTS system supports basic data services. Networking diagram None. Prerequisites The BTS is working normally. The test MS/datacard supports the GPRS/EDGE service. The PCU data configuration is complete. The SIM card in the test MS is valid and supports data services. The data service settings for the test MS are correct. Procedure Use the test MS to log in to a specified website on sector 1 and perform and downlink and uplink speed test. Repeat procedure for sector 2 and sector 3. Remarks None. Expected result The MS can log in to the website and browse web pages. Upload: 100kbps and above Download: 200kbps and above
16
2. 3.
Remarks The tests should cover handoffs between cells in the same site and different sites
17