Sie sind auf Seite 1von 10

Thermal Overload Operating Times calculation Spreadsheet This spreadsheet provides a method to calculate the thermal overload operating

time. The thermal overload operating time includes four items: 1.alarm operating time 2. trip operating time 3. alarm reset time 4. trip reset time The user is required to enter the settings, and for each stage (except the last stage) the equivalent current applied. The duration also needs to be entered if pre-heat and/or pre-cool is required. There are four sheets in this spreadsheet. They are described as follows: cold This sheet applies when the conditions below are met: 1. The relay's initial injection current is zero. 2. Apply a current above I> for the relay to trip. The trip and alarm times are displayed. The trip time is automatically entered into the duration in this stage. (stage 1) 3. When the relay trips, the injection current is automatically removed by the spreadsheet. The expected reset times are displayed (stage 2) pre-heat This sheet applies when the conditions below are met: 1: The relay's initial injection current is zero. 2. Apply a current for a duration which is not sufficient to trip the relay (stage 1) 3. Increase the current above I> for the relay to trip. The trip and alarm times are displayed. The trip time is automatically entered into the duration in this stage (stage 2) 4. When the relay trips, the injection current is automatically removed by the spreadsheet. The expected reset times are displayed. (stage 3) pre-heat&cool This sheet applies when the conditions below are met: 1: The relay's initial injection current is zero. 2. Apply a current for a duration which is not sufficient to trip the relay. (stage 1) 3. Decrease the injection current for a certain duration. (stage 2) 4. Increase the current above I> for the relay to trip. The trip and alarm times are displayed The trip time is automatically entered into the duration in this stage. (stage 3) 5. When the relay trips, the injection current is automatically removed by the spreadsheet. The expected reset times are displayed (stage 4)

thermal ceiling This sheet applies when the conditions below are met: 1: The relay's initial injection curret is zero. 2: Apply a current above the I> for the relay to get to the thermal ceiling. The expected minimum duration of Stage1 displayed. (St 3: Decrease the current under I>, wait the relay trip reset. The expected reset time displayed. (Stage 2) In each sheet, there is also an instruction to use the spreadsheet. In general, the yellow boxes are required to enter data, the red boxes display the calculated results.

VERSION CONTROL Issue A.1

Author(s) Ping Ye / Tony Yip

Reason for change Initial draft.

Date 30-10-

m duration of Stage1 displayed. (Stage 1)

RELAY SETTINGS I> (In) Alarm (%) Heating time constant (s) Cooling time constant (s) M Factor

1.2 100 60 60 0

APPLIED CURRENT AND DURATION 1. Intial current assumed to zero. 2. Enter the I1 & I2 in the yellow boxes of stage1 to produce Ieq which should be greater than I> setting. 3. The expected alarm & trip time and alarm reset & trip reset time will be displayed in the red boxes. stage1 - Trip I1 (In) I2 (In) 1st stage Ieq (In) 1st stage Duration (s) stage2 - Reset 2nd stage Ieq (In) 2nd stage Duration (s)

2.4 0 2.4 17.2609243

Alarm operating time (s) Trip operating time (s) Theta1 when trip Alarm reset time (s) Trip reset time (s) Theta2 when trip resets

17.26092435 17.26092435 1 3.077597663 3.077597663 0.95

0 3.07759766

RELAY SETTINGS I> (In) Alarm (%) Heating time constant (s) Cooling time constant (s) M Factor

1.2 90 3600 60 0

APPLIED CURRENT AND DURATION 1. Intial current assumed to zero. 2. Enter the I1 & I2 in the yellow boxes of stage1 to produce a Ieq which is less than I> setting. Also enter the duration of this stage. 3. Enter the I1 & I2 in the yellow boxes of stage2 to produce a Ieq which is greater than I> setting. 4. The expected alarm & trip time and alarm reset & trip reset time will be displayed in the red boxes. stage1 - Heating I1 (In) I2 (In) 1st stage Ieq (In) 1st stage Duration (s)

0.5 0 0.5 800 Theta1 of the pre- heat 0.034594201

stage2 - Trip I1 (In) I2 (In) 2nd stage Ieq (In) 2nd stage Duration (s)

2.4 0 2.4 1004.38526

Alarm operating time (s) Trip operating time (s) Theta2 when trip

886.3419012 1004.385263 1

stage3 - Reset 3rd stage Ieq (In) 3rd stage Duration (s)

0 3.07759766

Alarm reset time (s) Trip reset time (s) Theta3 when trip resets

9.75113577 3.077597663 0.95

RELAY SETTINGS I> (In) Alarm (%) Heating time constant (s) Cooling time constant (s) M Factor

1.2 90 60 60 0

APPLIED CURRENT AND DURATION 1. Intial current assumed to zero. 2. Enter the I1 & I2 in the yellow boxes of stage1 to produce a Ieq which is less than I> setting. Also enter the duration of this stage. 3. Enter the I1 & I2 in the yellow boxes of stage2 to produce a Ieq which is less than Ieq of the stage1. Also enter the duration of this stage. 4. Enter the I1 & I2 in the yellow boxes of stage3 to produce a Ieq which is greater than I> setting. 5. The expected alarm & trip time and alarm reset & trip reset time will be displayed in the red boxes. stage1- Heating I1 (In) I2 (In) 1st stage Ieq (In) 1st stage Duration (s) stage2 - Cooling I1 (In) I2 (In) 2nd stage Ieq (In) 2nd stage Duration (s) stage3 - Trip I1 (In) I2 (In) 3rd stage Ieq (In) 3rd stage Duration (s) stage4 - Reset 4th stage Ieq (In) 4th stage Duration (s)

0.5 0 0.5 600 Theta1 after pre-heat 0.5 0 0.5 60 Theta2 after cooling 2 0 2 22.9049817 0.173608212 0.173603229

Alarm operating time (s) Trip operating time (s) Theta3 when trip Alarm reset time (s) Trip reset time (s) Theta4 when trip resets

19.62148771 22.9049817 1 9.75113577 3.077597663 0.95

0 3.07759766

RELAY SETTINGS I> (In) Alarm (%) Heating time constant (s) Cooling time constant (s) M Factor

1.2 90 60 600 0

APPLIED CURRENT AND DURATION 1. Intial current assumed to zero. 2. Enter the I1 & I2 in the yellow boxes of stage1 to produce Ieq which should be greater than I> setting. 3. The expected time to the thermal ceilig and reset time will be displayed in the red boxes.

stage1 - Thermal Ceiling I1 (In) I2 (In) 1st stage Ieq (In) 1st stage Duration (s) stage2 - Reset 2nd stage Ieq (In) 2nd stage Duration (s) 8 0 8 6

minimum duration (s) thermal ceiling

5.658640768 4

0.1 865.912095

Trip reset time (s) Theta2 when trip resets

865.9120954 0.95

Das könnte Ihnen auch gefallen