Date: 11/8/2013
Well Name: Bibiyana -19 Slot: 7 Rig: WDI 801 End Date:
Total Time: 20.67 Time from Spud: 20.06 Days Since Last DAFW / RI Case :
TVD End (mKB): 2,761.43
Bibiyana
Actual Start Date
Bangladesh
Actual End Date
6/13/2013 4,410
Total AFE Amount (Cost)
7/19/2013
AFE/WBS Number
3,865.89 22,183,123
100794 Safety/Inspections
Date Safety Check Tour Des
11/8/2013 00:00 11/8/2013 00:00 11/8/2013 00:00 11/8/2013 04:00 11/8/2013 06:00 11/8/2013 06:00 11/8/2013 06:30 11/8/2013 06:30 11/8/2013 06:30 11/8/2013 10:00 11/8/2013 10:00 11/8/2013 11:00 11/8/2013 11:30 11/8/2013 12:00 11/8/2013 12:15 11/8/2013 12:15 11/8/2013 14:00 11/8/2013 14:00 11/8/2013 14:30 11/8/2013 15:00 11/8/2013 16:00 11/8/2013 17:00 11/8/2013 18:30 11/8/2013 18:30
Pre-Tour Safety Meeting Pre-Job Meeting Pre-Job Meeting Pre-Job Meeting Pre-Job Meeting Pre-Job Meeting Pre-Tour Safety Meeting Pre-Job Meeting Pre-Job Meeting Pre-Job Meeting PTW Audit Safety Procedures Pre-Tour Safety Meeting Pre-Job Meeting Pre-Job Meeting Pre-Job Meeting Pre-Job Meeting Pre-Job Meeting PTW Audit Rig Floor Pre-Job Meeting Safety Meeting Pre-Tour Safety Meeting Pre-Job Meeting
Night Night Night Night Day Day Day Day Day Day Day Day Day Day Day Day Day Day Day Day Day Day Night Night Night Night Night Night
RADAR, Ops, Tnt#08 & GEMS#08 @BYWP Gen. Crane Lifting @BYWP Gen. Forklift Ops @BYWP Welding, cutting, grinding at Workshop @BYWP(PTW) Gen. Crane Lifting @BYWP Diesel transfer @BYWP(PTW) w/Kamal Ent., RADAR Cards, Tnt#08 @BYWP Gen. Forklift Ops @BYWP Gen. Housekeeping (K/E) @BYWP Service centrifuge by NOV@BYWP (PTW) General hot work at workshop@BYWP T-Card Audit RADAR, Ops, Tnt#08 & GEMS#08 @BYWP Welding, cutting, grinding at Workshop @BYWP(PTW) Gen. Crane Lifting @BYWP Gen. Forklift Ops @BYWP Check seat and valve of mud pump 2 @ BYWP (PTW) Cleaning slug tank @ BYWP (PTW) Check valve & seat at MP-2@BYWP PPE audit at Rig floor,mud tank,de-watering unit@B Using camera at rig site @ BYWP (PTW) Ops. Review, Tnt#08 @BYWP w/Kamal Ent., RADAR Cards, Tnt#08 @BYWP Gen. Crane Lifting @BYWP Gen. Housekeeping (K/E) @BYWP T-Card Audit Cleaning mud tank@BYWP General hot work at workshop@BYWP
Incident Desc
11/8/2013 18:30 Pre-Job Meeting 11/8/2013 19:30 Safety Procedures 11/8/2013 22:00 PTW Audit 11/8/2013 22:30 PTW Audit Safety / Environmental Incidents
Incident Cat.
Page 1/6
Date: 11/8/2013
Well Name: Bibiyana -19 Slot: 7 Rig: WDI 801 End Date:
Total Time: 20.67 Time from Spud: 20.06 Days Since Last DAFW / RI Case :
Daily Operations
Report Start Date Report End Date
11/8/2013 00:00
Daily Field Est Total (Cost) Cum Field Est To Date (Cost) Daily Mud Field Est (Cost) Cum Mud Cost to Date (Cost)
11/9/2013 00:00
Drilling Hours (hr) Cum Rotating Hrs on Casing
215,105
Status at Reporting Time Operations Summary
5,173,558
2,595
486,016
Pumped 15bbls base oil. Continued POOH 67m to surface. Drain BOP stack. Pick up landing Jt and measure landing point. Lay out same. Rig up TRS. PJSM before RIH 9-5/8" casing. Pick up 9 5/8 casing shoe and started RIH. Lay down joint no 7. Dropped 9 5/8 casing in the hole "91m". Rig down 9 5/8" casing running equipment. Pick up and make up fishing tools and RIH. Fill up and break circulation every 15 stands. Tag top of fish @ 2540m, unsuccessful. Second attempt to Catch fish (Successful) at 2586m. POOH from 2586m with fish and continued to 2181m.
Comments
00:00 - 05:00: Continue to trip out the hole wet with 9 5/8" casing fish. F/2181 T/646m
Max Drill Gas Required Matls next day Avg Background Gas Head Count
147.0 Halliburton batch mixer in customs. CCTV: driller has camera for derrick,stabbing board, mud pump. STP recorder non-operational Drillers MD Totco monitor at Rig floor, Not in service. No ETA. Iron Roughneck spinners, not in service because of bad hydraulic leak. No spare seals on location. Having to use standalone spinners. Drillers rig floor communciation hands free microphone not working. No ETA. No back up flow line encoder for SLS. MD Totco flowline indicator not reading. WDI flowline sensor three weeks ETA. No ETA from SLS. Safety Observation Cards
Observation Typ # Rpts Com
67 While fixing flexible hose on TD, some one was about to move very closely on that area. As hose vibrate it might hit him.Stopped him and told him to move in a safe place. He agreed and did so.Tenet #2 MD. AMIR HOSSAIN-WDI-Floor man
Contact
Daily Contacts Shayne Atkins Stephen Joubert Randy Roberts Kitichai Leekitchakorn Mahbubur Rahman Ismail Hossain Time Log
Start Time End Time Phase Activity Dur (hr) Unsched Event? UE Time (hr) UE Ref No. Com
1.00 18
Trouble shoot and repair Draworks. Problem with parking break. Rack back last stand of HWT. Rack back LWD. Soft break motor stab. Lay out motor and bit. Pull W/B. Pick up wash toll and wash well head and BOP stack. Clean off the rig floor. Change out elevators and pick up landing jt and perform test run to establish landing depth. Lay out same. Rig up TRS 9 5/8" casing running equipment, including Spider elevators and 500t slips. Held Safety meeting.
Page 2/6
Date: 11/8/2013
Well Name: Bibiyana -19 Slot: 7 Rig: WDI 801 End Date:
Total Time: 20.67 Time from Spud: 20.06 Days Since Last DAFW / RI Case :
Time Log
Start Time End Time Phase Activity Dur (hr) Unsched Event? UE Time (hr) UE Ref No. Com
06:00
09:00
INTCSG2, DRILL
CSGRUN
3.00
Make up and run 9 5/8" shoe track. Test floats. Makeup 7 jts and RIH. While making up joint#7 the connection failed to pass criteria for the jam unit to accept it as good. Broke out connection and laid down joint #7. While coming down to latch onto joint#6 in rotary elevators were lowered over stump in table. TRS operator functioned wrong control on ISIS system and opened slips. Nothing functioned at this stage due to safety device built into system. When they realized they had not closed the elevators they then functioned the switch to close the elevators. The air was applied to the elevators to function them closed at the same time sent signal to slips to open as the switch had not been put back into the closed position. The slips opened at the same time as the elevators were closing and the string fell down hole. Fish lost down hole: Shoe joint, casing joint, FC joint and 5 x casing joints=91.49m
Rig down and lay out TRS 9 5/8" casing running equipment. Discuss and prepare fishing BHA. Pick up fishing BHA for fishing 9 5/8" casing. Trip in the hole with Fishing BHA Tag resistance @ 2545m. Pick up and record parameters. Attempt to screw into fish, With slow pump rate. While screwing into fish oveserved pump pressure building. At 900psi fish came free and moved down hole. Suspect the float or shoe are plugged off. Continue to trip in and tag fish @ 2586. Pick up on strign leavign 5k WOB. Rotate string left and observe string weight drop and pressure increase. Believe pin now inside box. Stop pump with 380psi trapped in string. Screwed into fish to15k of rotary torque. Picked up and pressure did not bled off. Continue to pick up until decrease drag was seen. Pressure was bled off and continued tripping out the hole. Observed 80 k overpull on first two stands. Drag came of quickly. Trip out the hole with 9 5/8" casing fish wet F/ 2586 m T/ 2181 m.
SSE
20:30
21:00
INTCSG2, DRILL
FISH
0.50 Yes
0.50 19
21:00 Personnel
00:00
INTCSG2, DRILL
TOH
3.00 Yes
3.00 19
Company
Total Headcount
Chevron Weatherford Weatherford Weatherford Aker-Kvaerner Weatherford Halliburton Weatherford MI Swaco Gyrodata Inc Weatherford NOV - Fluids Services HAL - Wireline Weatherford Page 3/6
15 17 Rig Expat 45 Rig National 22 1 3 6 2 2 0 6 Shamolima Catering Wellhead Eng LWD/MWD Cementing DD Mud Engineers Gyrodata TRS
Date: 11/8/2013
Well Name: Bibiyana -19 Slot: 7 Rig: WDI 801 End Date:
Total Time: 20.67 Time from Spud: 20.06 Days Since Last DAFW / RI Case :
Personnel
Company Total Headcount SSE
Weatherford Chevron Smith International Weatherford Chevron Weatherford Weatherford Chevron Weatherford Weatherford Chevron Weatherford Weatherford Mud Checks
Date Depth (MD) (mKB) Depth (TVD) (mKB) Mud/Brine Type
0 1 3 0 0 0 0 0 11 0
Ayun ent PetroBangla Inspection Completion/Liner hands WWT BanglaCat Bangla Industrial Hunting Casing NOV Tech WWS
11/8/2013
Flow Line Temperature (C) Vis 3rpm
3,038.0
Fluid Density (lb/gal)
2,761.43
Gel 10 sec (lbf/100ft)
NAF
Gel 10 min (lbf/100ft)
Active Pit
Gel 30 min (lbf/100ft)
MI Swaco
YP Calc (lbf/100ft)
11.20
Vis 6rpm
16.0
Vis 300rpm
28.0
Vis 600rpm
31.0
Funnel Viscosity (s/qt)
20
PV Calc (Pas)
10
pH Low Gravity Solids (lb/bbl) Chlorides (mg/L)
11
CaCl2 (mg/L)
50
Electric Stability (V)
80
Water Phase Salinity (mg/L)
69
ROC (Wet) (% by wt) (lb/lb) Retort NAF by Volume (%)
58,500
High Gravity Solids (lb/bbl) Corrected Solids (%)
269,526.00 16.28
API Filtrate (cc/30min) API Filter Cake (1/32")
620.0
Retort Solids (% by Volume) (%)
322,300
Retort Water by Volume (%)
42.85
NAF/Water Ratio NaCl (mg/L)
168.71
18.75
HTHP Filtrate (cc/30min)
19.25
HTHP Filter Cake (1/32")
62.00 1
Visibility (km)
3.4
T Low (C)
Support Vessels
Vessel Name Vessel Type Arrival Date Depart Date Note
Unscheduled Events
Reference No. Start Date End Date Event Type Unsch Maj Cat Unsch Detail Description Accountable Party Contractor
18
11/8/2013 01:00
NPT
RREQ
DW HOIST
Problems with draworks parking break. Droped shoe 9 5/8" shoe track and 6 jts of casing in the hole.
Rig Contractor
Weatherford Accessories, Drilling Weatherford Casing & Tubing Running, Tubular Running
On Loc
19
NPT
FSH
OH
Rig Contractor
11/8/2013
Date
20.0
Received
15.0
Consumed
80.0
Cum On Loc
Diesel
11/8/2013
15,341.0
138,483.0
Page 4/6
Date: 11/8/2013
Well Name: Bibiyana -19 Slot: 7 Rig: WDI 801 End Date:
Total Time: 20.67 Time from Spud: 20.06 Days Since Last DAFW / RI Case :
1b
Nozzles (1/32")
0.28
String Length (m)
1-1-WT-S-X-I-CT-TD 236.94
1.24
Max Nominal OD (in)
8.8 812.000
18/18/18/18/18
String Components
SK5519, 8" Hyperline Motor w/12"UBHS, 11-3/4" Stabilizer, NM XO Sub, 8 1/4"LWD - MFR, 8 1/4"HEL, NM XO Sub, 8" NMDC Long, XO Sub, HWDP, Drilling Jars - Hydraulic, HWDP
Comment
String/BHA Components
Item Des Len (m) Mass/Len (lb/ft)
HWDP Drilling Jars - Hydraulic HWDP XO Sub 8" NMDC Long NM XO Sub 8 1/4"HEL 8 1/4"LWD - MFR NM XO Sub 11-3/4" Stabilizer 8" Hyperline Motor w/12"UBHS Drilling Parameters
Wellbore Depth Start (MD) (mKB) TVD Start (mKB) Depth End (MD) (mKB) TVD End (mKB) Drill Time (hr)
159.41 9.68 28.05 1.10 9.22 0.91 6.90 9.02 0.91 2.47 8.99
On Btm Drl Ti Interval ROP (m/hr)
49.30 49.30
Original Hole
Cum Depth Drilled (mKB)
2,931
Cum Drilling Time (hr)
2,671.63
Flow Rate (gpm)
3,038
Weight on Bit (1000lbf)
2,761.43
RPM (rpm)
8.50
Stand Pipe Pressure (psi)
7.97
Drill Str Wt (1000lbf)
963
PU Str Wt (1000lbf) Drilling Torque
109.00
String Wt (1000lbf)
770 30
Length (m) String Length (m)
22
Slack-Off String Weight (1000lbf)
4,100.0
25.0
------211.78 Drive Sub, Float Sub, 1x5''DP, Bumper Sub, Fishing jar, 6-1/2'' DC, HWDP
Comment
6.500
HWDP 6-1/2'' DC Fishing jar Bumper Sub 1x5''DP Float Sub Drive Sub Drilling Parameters
Wellbore Depth Start (MD) (mKB) TVD Start (mKB) Depth End (MD) (mKB) TVD End (mKB) Drill Time (hr)
49.30
Original Hole
Cum Depth Drilled (mKB) PU Str Wt (1000lbf)
3,038
Cum Drilling Time (hr) Drilling Torque
2,761.43
Flow Rate (gpm) String Wt (1000lbf)
3,038
Weight on Bit (1000lbf)
2,761.43
RPM (rpm)
0.00
Stand Pipe Pressure (psi)
0.00
Drill Str Wt (1000lbf)
27 Casing Strings
Casing Description Set Depth (MD) (mKB) Set Depth (TVD) (mKB) Run Date
Intermediate Casing 1
Comment
1,799
1,763.31
9/25/2013
Page 5/6
Date: 11/8/2013
Well Name: Bibiyana -19 Slot: 7 Rig: WDI 801 End Date:
Total Time: 20.67 Time from Spud: 20.06 Days Since Last DAFW / RI Case :
Casing Components
Top Depth (MD) (mKB) Btm Depth (MD) (mKB) Len (m) Jts Item Des OD (in) ID (in)
Tubing Strings
Tubing Description Comment Set Depth (MD) (mKB) Set Depth (TVD) (mKB) Run Date
Tubing Components
Top (mKB) Btm (mKB) Len (m) Jts Item Des OD (in) ID (in)
BOP Test
Date Com
10/29/2013 Wellbores
Wellbore Name
Shell test BOPs and related equipment to 250/5k psi, ok, Full BOP test was done on 22 October'13.
Kick Off Depth (mKB)
35
Page 6/6