Beruflich Dokumente
Kultur Dokumente
ENGINEERING DIVISION
59 Town Hall Square FALMOUTH MASSACHUSETTS 02540 Tel: (508) 495-7430 Fax: (508) 495-7435
June 15, 2010 Jennifer L. McKay, Conservation Administrator Conservation Commission Town of Falmouth 59 Town Hall Square Falmouth, MA 02540 Dear Jennifer: The Town of Falmouth Department of Public Works Engineering Division (the DPW) is requesting permission to perform preliminary maintenance to a culvert located under Gardiner Road in front of house #55. The DPW will be filing a Notice of Intent to replace the pipe with the work to be performed in the fall. We will have to seek temporary construction and permanent maintenance easements on two parcels to the south of the road because the end of the culvert lies outside of the Gardiner Road right-of-way and within these two properties. In the meantime, we would like to alleviate the flooding occurring on the north side of the road by performing maintenance to get the culvert flowing freely again. The work would be performed in three phases as follows: Phase I Pipe Exposure Phase I would involve locating and exposing the ends of the existing culvert. On the north side, a backhoe and shovels would be used to expose the pipe end and an extension piece would be added to extend the pipe end out into the flooded area and prevent clogging. On the south side, the end of the pipe would be exposed by hand and the area around the outlet would be dug out slightly to prevent clogging. A few shovelfuls of riprap would be placed in the depression to minimize erosion. Construction Sequence (Someone from the Engineering Department to be onsite during all work operations) Notify Dig Safe a minimum of 72 working hours before construction. Notify the Town of Falmouth Water and Wastewater Departments. Both departments will need to mark out their utilities. Install Turbidity Barrier on the north side in a 10 foot radius from the area of work, shore to shore. Install haybales and siltfence in the mosquito ditch 10 feet from the area of work. Before any construction commences, the Conservation Commission and Engineering Department will inspect the site. Expose culvert end on north side. All spoils will be removed from the site. Install 4 foot extension to culvert on north side. Expose culvert on south side. All spoils will be removed from the site. Excavate 1 foot below pipe approximately 2-5 square feet in area. Backfill excavated area with rip rap. Remove any collected sediment at haybales. The Conservation Commission and Engineering Department will inspect the site at the end of Phase I. Traffic will have to be rerouted for Phase I. The anticipated time of construction is a single work day. Police details would be utilized as required. Residences along this portion of Gardiner Road will be allowed access.
This letter laid out our plans to clean out a pipe under the road and within an environmentally sensitive area.
Please see the attached sketch for further information and details. Some of the proposed work will be performed outside of the Gardiner Road right-of-way and will require permission from the property owners. The Engineering Department will coordinate with the property owners. Also the residents at #s 37, 61, 67, 46, 50, 58, 60, and 66 will be notified prior to commencement of work so that coordination of access to their properties can be provided during the construction days. Sincerely,
Scott Schluter Staff Engineer Town of Falmouth Department of Public Works Engineering Division Cc: Raymond Jack, Director of Public Works Peter M. McConarty, Acting Town Engineer John T. Lyons, Superintendent of Highways Michael S. Souza, Assitant Superintendent of Highways Leonard Johnson, President 300 Committee, 0 Gardiner Road James J. Robinson, Trustee, 55 Gardiner Road John Doane, Superintendent Cape Cod Mosquito Control Project
LOCUS
0+00 10
0+60
1 ANCHOR SLOT
2 OVERLAP
3 ANCHOR AT WALL
18"
4 JUNCTION
This project involved the design and permitting of replacing a collapsed pipe under a road near a seawall. The concerns were the implications to the hydraulics and hydrology of the wetlands.
6"
5 TERMINAL FOLD
1 2 4
5
-5
NOTE: EROSION CONTROL MATERIAL TO BE NORTH AMERICAN GREEN SC 150 OR APPROVED EQUAL.
CULVERT
59 Town Hall Square FALMOUTH MASSACHUSETTS 02540 Tel: (508) 495-7430 Fax: (508) 495-7435
May 26, 2010 Jennifer McKay Conservation Commission Administrator Town of Falmouth 59 Town Hall Square Falmouth, MA 02540 Dear Ms McKay:
This project involved coming up with a solution to a parking lot that was flooded out every rain storm. High groundwater and sensitive wetland resource areas were obstacles to the solution. I designed a detention swale/basin with an outlet that reduced peak discharge, provided first flush treatment, and allowed some infiltration to reduce volumes discharging to the nearby salt pond. This project was in the public eye and ended up impressing the Townspeople. It was a cooperative effort between Engineering and the DPW who constructed it. We laid out the work in the field and assisted them in interpreting and completing the design.
Attached please find supplemental calculations for the Mill Road street reconstruction project to amend the Order of Conditions # 25-3568 as you requested. Included in this packet are the following documents: Existing and Proposed Drainage Area Plans (2 sheets) Existing and Proposed Stormwater Calculations Water Quality Calculations Soil Survey Map
The purpose of the new information is to provide an outlet to the previously approved design plans. The original design relied upon exfiltration of the storm water. Given the existing soils and proximity of the seasonal high groundwater to the elevations around the site, exfiltration will not work. The current situation on the site consists of the roadway and sidewalk have been reconstructed minus the final surfaces, the roadside swale has been shaped (the finish surfaces and 6 drain pipe have not been constructed), and the proposed basin was partially excavated in early fall of 2009. Construction was halted during the winter season. During this time we have observed that the swale system conveys the storm water to the basin, keeping the Mill Road surface dry, even during several large storm events. The issue is that the basin is not exfiltrating and has overtopped during some storm events. The basin has maintained water at various depths since construction, never completely emptying. The proposed revisions are an effort to drain the basin. The bottom of the basin will be raised to elevation 2.5 ft which puts it above groundwater levels recorded in the nearby monitoring wells. The sediment sumps and low flow channels are slightly lower and will likely have water during high tide events, therefore those bottom surfaces are proposed to be rip rap. The top of the basin will maintain the current elevation of 3.0 ft as well as the current location of the top of the excavation. The proposed outlet consists of recycled granite curbing sections set at elevation 2.5 ft which will convey storm water to a 12 foot wide grass lined swale prior to discharge into Salt Pond. Given the complications of the
Ms McKay May 24, 2010 Page 2 topography, existing soil types, high groundwater, and space constraints, we feel the design revisions meet the Stormwater Management Standards to the maximum extent practicable where full compliance is not met. The following is a summary of the results: Stormwater Calculations
Design Point Salt Pond 2 Yr-24 Hr Design Storm Existing Proposed Peak: 2.45 cfs Peak: 2.69 cfs Vol:0.39 af Vol:0.423 af 10 Yr-24 Hr Design Storm Existing Proposed Peak: 8.77 cfs Peak: 8.40 cfs Vol:0.94 af Vol:0.98 af 100 Yr-24 Hr Design Storm Existing Proposed Peak: 24.45 cfs Peak: 22.69 cfs Vol:2.23 af Vol:2.28 af
10. All illicit discharges to the stormwater management system are prohibited. The previously approved illicit discharge statement still applies.
We look forward to meeting with the board to discuss the design plans and calculations at your earliest convenience so the original Order of Conditions can be amended and construction can proceed prior to the start of the beach season allowing the parking lot be opened to the public. Sincerely,
These are Water Quality Volume calculations I did for this project.
LOCUS
PLANTING SCHEDULES
SECTION A-A
SECTION C-C
1.0
1.1 Introduction
PROJECT NARRATIVE
Notice of Intent
Submitted Pursuant to M.G.L. Chapter 131, Section 40 (MA Wetlands Protection Act) and the Code the Town of Falmouth Chapter 235, and the Town of Falmouth Wetlands Regulations FWR 10.00
The Town of Falmouth Department of Natural Resources (FDNR) is filing this Notice of Intent (NOI) for approval to replace an existing failing fishway and roadway above the fishway under the Massachusetts Wetlands Protection Act (M.G.L. Chapter 131, Section 40), 310 CMR 10 Wetlands Protection, the Code of the Town of Falmouth Chapter 235, and the Town of Falmouth Wetlands Regulations FWR 10.00. 1.2 Project Site
The project site is located within the right-of-way of Bay Road (this portion is an unimproved private way) and partially on the lots known as #126, #131, and #138 Bay Road and #123 Chester Street in North Falmouth, MA (the Site); Town of Falmouth Assessors Map 05 Section 03 Parcel 007A Lot 12, Map 05 Section 03 Parcel 009 Lot 000, Map 05 Section 03 Parcel 010A Lot 13, and Map 05 Section 03 Parcel 007 Lot 000, respectively as shown on Figure 1 Locus Map and Figure 1A 2009 Orthophotos in Appendix A. The fishway connects Rands Canal to an unamed stream fed from Cedar Lake; Rands Canal is connected to Megansett Harbor which is part of Buzzards Bay in the Atlantic Ocean. The Site is not located in an area designated as a Water Resource Protection District, Wildlife Corridor, or Coastal Pond Overlay District as shown on Figure 2 Town of Falmouth Overlay Districts in Appendix A. The Site is not located in protected areas designated by the Natural Heritage and Endangered Species Program as shown on Figure 3 Natural Heritage and Endangered Species Program Mapping in Appendix A. A portion of the Site (the end of the fish ladder) is located within an area mapped as Designated Shellfish Growing Areas as shown on Figure 4 Shellfish Suitability Areas in Appendix A. The Site is not located within a State mapped ACEC, ORWs or Zone II as shown on Figure 5 ACEC, ORWs, and Zone II in Appendix A. As required by the Natural Resources Conservation Service, the proposed design utilizes the North American Vertical Datum of 1988 (NAVD88). The Site is located within a FEMA mapped Zone A12 (EL 14 NGVD29, EL 13.15 NAVD88) as shown on Figure 6 FEMA Flood Map 25521100001G in Appendix A.
Submitted to:
Submitted by:
Prepared by:
To determine tidal data, elevations of high tide on February 11, 2011 at 1:19 PM were taken. Based on the Tide Tables and Chappaquoit Point Tidal Station (see Appendix C), Mean HigherHigh Water, Mean High Water, Mean Low Water, and Mean Lower-Low Water were determined and placed on the plans. The Mean Low Water boundary was taken from taken from Dock License Plan No. 7546 for Thomas L. Kennedy recorded at the Barnstable County Registry of Deeds Book 543 Page 74. The proposed plans can be found in Appendix E.
Town of Falmouth DPW Engineering Division 416 Gifford Street Falmouth, MA 02540
Notice of Intent
Page 1
November 7, 2011
1.3
Proposed Project
In addition to the fishway and roadway appurtenances, two existing water services will be abandoned and the two residences will be reconnected to another water main in the area (work scheduled for this fall, 2011), an existing gas line will be relocated to meet the new roadway grades and alignment, and an existing telephone pole has already been relocated off the proposed new roadway surface. Funds for the reconstruction of this fishway are being provided by Federal Grant money through the American Recovery and Reinvestment Act as part of the Cape Cod Water Resources Restoration Project. The project is a coordinated effort between the Town of Falmouth Department of Natural Resources, Department of Public Works Engineering Division, Department of Public Works Highway Department, Conservation Commission, Town Counsel, Water Department; United States Department of Agriculture Natural Resources Conservation Service; Massachusetts Division of Marine Fisheries; United States Fish and Wildlife Service; Mass Bays Program; National Grid; NSTAR; abutters to the project, and neighbors on this portion of Bay Road. 1.4 Resource Area Determination and Impacts
In 2004 the Massachusetts Division of Marine Fisheries, in Technical Report TR-16 A Survey of Anadromous Fish Passage in Coastal Massachusetts Part 2. Cape Cod and the Islands, rated the fishway between Cedar Lake and Rands Canal in North Falmouth in poor condition with inefficient passage (see Appendix A). The Applicant is proposing to remove and reconstruct this failing fishway and the roadway above it. The fishway is comprised of a fish ladder which is considered a notched weir-pool configuration made of concrete with steel plates. It is approximately 77 linear feet in length, and 3.1 feet in width and has 14 baffles. Upstream of the ladder is a culvert that runs under Bay Road to the unnamed stream fed by Cedar Lake. The culvert enters under Bay Road through a concrete and stone headwall on the upstream end, and exits through a concrete retaining wall on the downstream end. The culvert is a 30 corrugated metal pipe, 27 linear feet in length, set at a 6.6% slope and contains internal baffles to further assist fish access to the stream leading to Cedar Lake. The culvert is prone to clogging which requires FDNR staff to climb into the 30 culvert to clear the debris. The concrete structure of the fishway is eroding and portions have fallen apart. A fence dividing the roadway from the vertical drop at the culvert exit headwall has fallen and there are no protective measures at the vertical drop of the culvert upstream end. The roadway edge over the culvert is poorly defined and extremely narrow, preventing two cars passing in opposite direction. There is evidence of frequent erosion from Bay Road into the stream due to the poor condition of the dirt surface of this portion of Bay Road.
Some of the resource areas within and adjacent to the project site were delineated by Peter McConarty (USACOE Wetland Delineator Certificate Program Certified), Acting Town Engineer of the Town of Falmouth DPW Engineering Division as well as Mark Kasprzyk, Conservation Commission Agent of the Town of Falmouth Conservation Commission. Other resource areas were determined from tidal data. The Town of Falmouth Department of Public Works Engineering Division located flagged resource areas via on-the-ground survey methods. 1.4.1 Land Under the Ocean (10.25) Land Under the Ocean starts at Mean Low Water (MLW) and extends seaward. The Mean Low Water line was taken from Dock License Plan No. 7546 for Thomas L. Kennedy recorded at the Barnstable County Registry of Deeds Book 543 Page 74 (see Appendix C). The Town of Falmouth requires a 75 foot Zone A (No Disturb) followed by 25 feet of Zone B (outer buffer) for Land Under the Ocean. 310 CMR 10.25 requires no buffer zone for this resource area.
The goal of this project is to replace the fish ladder and culvert and restore the migration of river herring and American eel as well as other catadromous and anadromous fish to this fishway. In addition, this portion of Bay Road will be reconstructed, improving stormwater management, and erosion and sedimentation into the stream. Some of the existing culvert and roadway lies outside of the Bay Road right-of-way; the proposed design will realign the road, culvert and headwalls so they will be situated within the right-of-way.
Since Bay Road is a dead end road and there are 11 residences that rely on crossing the stream as the only access their lots, Bay Road must be kept open for travel during construction. In order to facilitate this, the project has been broken into two phases consisting of constructing one-half of the roadway width in each phase. Because of the required phasing, the portion of Bay Road immediately above the fishway will be expanded in width to 28 feet, providing two lanes from the current 12+/- width. This will allow one lane to be constructed while the other is in use. The additional width will make Bay Road safer by providing an area where vehicles going in opposite directions can pass each other. The inclusion of guardrails will be an additional safety benefit over the existing conditions.
Currently the fish ladder is accessed via a severely eroded path from the roadway down the coastal bank to the fish ladder. In order to mitigate erosion on the coastal bank leading down to the fishway and to provide access to the fish ladder, a new wood observation deck and stairs will be constructed.
The proposed project includes replacement of portions of the fish ladder currently located within Land Under the Ocean, but will be limited to the existing fish ladder alignment plus some additional temporary disturbance for construction. The proposed erosion and sediment controls will protect resource areas adjacent to the construction area. The project will not have an adverse effect on the Land Under Water Resource and in fact, should improve the resource area by encouraging growth of catadromous and anadromous fish populations utilizing the repaired fishway for reproduction migration. In addition to this benefit, the existing collapsing fish ladder will be removed eliminating concrete and steel currently eroding into Rands Canal.
The new culvert under Bay Road will be set at a shallow slope (0.5%) and embedded slightly to encourage migration of eel species. The proposed culvert will be larger at 48 to provide adequate water depth. The fish ladder and culvert were designed to work together to provide the best conditions for species using the ladder.
Notice of Intent
Page 2
Notice of Intent
Page 3
Proposed Buffer Disturbance 41 sf 218 sf 39 sf Proposed Buffer Disturbance Existing Fish Ladder within the Resource Area Temporary Construction Disturbance within the Resource Area Proposed Fish Ladder within the Resource Area 1.4.4 Land Containing Shellfish (10.34) <1 cy
75 Zone A: 2,431 sf
25 Zone B: 2,930 sf
The downstream end of the existing fish ladder lies within the flagged Salt Marsh. Since the fish ladder will be replaced, work will be done within the Salt Marsh, but will be limited to the existing fish ladder alignment plus some temporary disturbance for construction. A large portion of the salt marsh is populated with phragmites. When completed, the new fish ladder will not be falling into the Salt Marsh like the current fishway does and construction disturbance will help control the pragmites population. Therefore, this project should be considered an improvement to the Salt Marsh.
Coastal Bank was determined in the field, flagged by Peter McConarty, and adjusted/verified by Mark Kaspryzk. The Town of Falmouth requires a 50 foot Zone A (No Disturb) followed by 50 feet of Zone B (outer buffer) for Coastal Bank. 310 CMR 10.30 requires a 100 foot buffer for this resource area.
The proposed project includes work along the coastal bank where the existing fishway crossed under Bay Road. The existing Coastal Bank includes the retaining wall/headwall over the culvert under Bay Road. Since the new culvert and retaining wall location will be moved to within the Bay Road right-of-way, the existing Coastal Bank will be realigned in this area. The move also impacts slopes of the Coastal Bank leading down to the upstream end of the fish ladder. A portion of the new slopes leading down to the fishway will be graded 2.5:1 and reinforced with rip rap to control erosion (The existing slope in this area is 1.5:1 without erosion control). The new retaining wall and associated grading will be an improvement over the existing failing retaining wall and eroding slopes leading to the fishway and Rands Canal.
The downstream end of the fishway falls within an area considered Land Containing Shellfish as shown on Figure 4 Shellfish Suitability Areas in Appendix A. The delineation of this area falls within Land Under the Ocean which is defined by MLW as described in Section 1.4.1 of this report. The Town of Falmouth requires no buffer to Land Containing Shellfish. 310 CMR 10.34 requires no buffer for Land Containing Shellfish.
50 Zone A: 7,390 sf
50 Zone B: 1,476 sf
A portion of the downstream end of the existing fishway lies within an area that may contain shellfish. Since the fishway will be replaced, work will be done within Land Containing Shellfish, but will be limited to the existing fishway footprint below MLW plus some additional temporary disturbance for construction. Shellfish species found within the limit of work will be relocated under the guidance of the Shellfish Constable. There should be no impact on shellfish communities as a result of replacing the existing fishway.
The boundaries of the Salt Marsh were determined in the field by Mark Kasprzyk. The Town of Falmouth requires a 100 foot Zone A (No Disturb) for Salt Marshes. 310 CMR 10.32 requires a 100 foot buffer for this resource area.
Notice of Intent
Page 4
Notice of Intent
Page 5
I had to determine the Mean Higher-High Water, Mean High Water, Mean Low Water, and Mean Lower-Low Water elevations based on observed tidal data.
blsf
Prepared by HydroCAD SAMPLER 1-800-927-7246 www.hydrocad.net
HydroCAD 9.10 Sampler s/n S13691 2010 HydroCAD Software Solutions LLC
blsf
Prepared by HydroCAD SAMPLER 1-800-927-7246 www.hydrocad.net
HydroCAD 9.10 Sampler s/n S13691 2010 HydroCAD Software Solutions LLC
This report was prepared with the free HydroCAD SAMPLER, which is licensed for evaluation and educational use only. For actual design or modeling applications you must use a full version of HydroCAD which may be purchased at www.hydrocad.net. Full programs also include complete printed documentation, technical support, training materials, and additional features which are essential for actual design work.
This report was prepared with the free HydroCAD SAMPLER, which is licensed for evaluation and educational use only. For actual design or modeling applications you must use a full version of HydroCAD which may be purchased at www.hydrocad.net. Full programs also include complete printed documentation, technical support, training materials, and additional features which are essential for actual design work.
Surf.Area (sq-ft) 253 458 639 882 1,097 1,219 1,452 1,608 1,933 2,559 2,897 3,455 4,381 6,718 7,919 9,230 9,537
Surf.Area (sq-ft) 237 413 573 811 1,016 1,185 1,323 1,543 1,788 2,147 2,338 3,078 5,050 6,649 8,053 9,640 9,788
Volume Calculations
-2 -1 0 1 2 3 4 5 6 7 8 9 10 11 12 13 13.15 Total 0 350 546 757 988 1157 1334 1529 1768 2239 2726 3172 3909 5508 7310 8566 1407 43266
This is a by the foot volume analysis for filling in Bordering Land Subject to Flooding.
Bordering Land Subject To Flooding Existing Volume Proposed Volume Elevation (cubic feet) (cubic feet) Delta (cubic feet)
0 321 491 689 912 1099 1253 1432 1664 1965 2242 2700 4024 5831 7340 8835 1457 42255 0 -29 -55 -68 -76 -58 -81 -97 -104 -274 -484 -472 115 323 30 269 50 -1011
The Town of Falmouth DPW Engineering Division has prepared a detailed design of the stormwater management system in conjunction with the proposed replacement of an existing failing fishway at Bay Road in North Falmouth, Massachusetts. Included in this report are the methods that will be employed to prevent any potential adverse hydrologic impacts as well as water quality impacts due to the proposed construction. The objective of this Stormwater Management Program is to direct and collect a portion of the stormwater runoff through a drainage channel and to distribute it to an infiltration pit developed in accordance with the MassDEP Stormwater Management Standards. The remaining portions of the site will be directed and collected through drainage channels that will distribute the runoff to the unnamed stream between Rands Canal and Cedar Lake (the unnamed stream) in a controlled manner. The proposed stormwater quality mitigation measures include a drainage channel and a leaching basin. The supporting hydrologic and hydraulic calculations for the proposed project are included as Appendices to this report. This project is considered a mix of new construction and a redevelopment project; therefore Stormwater Management Standards are required only to the maximum extent practicable for Standards 2, 3, and the pretreatment and structural best management practice requirements of Standards 4, 5, and 6 for the redevelopment portion. Every effort was made to meet the Standards. The new construction portion of the project involves the widening of Bay Road by more than one lane over the fish ladder; the remaining portions of the project are considered redevelopment as they involve replacement of an existing fish ladder and the addition of stormwater management appurtenances to an existing roadway widened by a few feet. 1.1 Design Point Summary
A description of the pre-development and post-development drainage characteristics follows. Generally, this project attempted to match post-development characteristics to the predevelopment state. The use of stormwater BMPs, along with careful site planning resulted in an improvement in the drainage characteristics as a result of the proposed project.
1.1.1 Pre-Development Drainage Characteristics
The existing site is the portion of Bay Road adjacent to Rands Canal located in North Falmouth, Massachusetts. The site slopes from the north and the south down towards wetlands around Rands Canal and the unnamed stream between the canal and Cedar Lake. The majority of the project area is within the Bay Road roadway surface and the existing fishway structures. The total existing watershed area for the pre-development stormwater runoff analysis consists of 0.83 acres. The total watershed area is divided into two drainage areas (HydroCAD subcatchments). A time of concentration flow path was developed and land cover areas were determined for each drainage area. The pre-development stormwater runoff from these areas flows to one Design Point where the peak rates of runoff are compared to the post-development conditions runoff. Design Point 1 is Rands Canal.
Town of Falmouth DPW Engineering Division 4
Drainage Area 1 (HydroCAD Subcatchment DA1) flows overland to the freshwater wetlands to the east of Bay Road. Drainage Area 2 (HydroCAD Subcatchment DA2) flows overland to the salt water resource areas west of Bay Road. Both the freshwater wetlands and the salt water resource areas discharge to the Design Point (HydroCAD Reach RANDS), Rands Canal.
Table 1: Design Point 1 Summary
Runoff Comparison at Rands Canal Storm Event 2 Yr cfs 0.77 0.55 1.18 2.02 1.52 2.19 10 Yr cfs 25 Yr cfs 100 Yr cfs 3.11 3.11 100 Yr Volume cf 10,062 8,930
The Existing Conditions Drainage Area Plan (see Appendix B) indicates the boundaries of the pre-development drainage areas and the time of concentration flow paths utilized in the calculations. The pre-development drainage calculations can be found in Appendix C. Pre-Development Post-Development
1.1.2
The proposed project consists of the replacement of an existing failing fishway and the roadway surface of Bay Road above it. A stormwater infiltration pit is proposed to contain some of the runoff from upper portion of Bay Road. The stormwater management facilities have been designed to attenuate peak discharge increases in stormwater runoff due to construction of the project and to provide groundwater recharge approximating existing conditions. The postdevelopment design watershed area is divided into three drainage areas for a total of 0.86 acres. The increase in area of 0.03 acres is due to the proposed grading of the site which will alter drainage divides. 1.3 Stormwater Checklist
A review of the analysis and subsequent calculations in this report indicate reductions in peak stormwater discharge from the site will be realized upon completion of the project due to this Stormwater Management Program. Accordingly, no impact or increase in the frequency or extent of flooding downstream from the site due to the construction of the project is expected.
As in the pre-development conditions, stormwater runoff from Drainage Area 100 (DA100) will flow to freshwater wetlands to the east of Bay Road. Stormwater runoff from Drainage Area 101 (DA101) will flow to a proposed infiltration pit with an overflow that will discharge to the freshwater wetlands to the east of Bay Road. As in the pre-development conditions, stormwater runoff from Drainage Area 200 (DA200) will flow overland to the salt water resource areas west of Bay Road. Both the freshwater wetlands and the salt water resource areas discharge to the Design Point (HydroCAD Reach RANDS), Rands Canal.
The Proposed Conditions Drainage Plan (see Appendix B) indicates the boundaries of the predevelopment drainage areas and the time of concentration flow paths utilized in the calculations. The post-development drainage calculations can be found in Appendix D.
1.2
Pre and post development runoff summaries are provided below. Detailed calculations and descriptions can be found in later sections of this report.
1.2.1
Peak stormwater runoff flows from the site for the 2, 10, 25, and 100-year storm have been calculated for pre-development and post-development conditions. The increase in stormwater runoff due to the development of the site has been determined and will be mitigated through the use of an on-site stormwater infiltration pit. A runoff comparison between pre-development and post-development conditions at each Design Point is shown below.
LEGEND
DRAINAGE DIVIDE TIME OF CONCENTRATION PATH DA# FW SW RANDS RANDS CANAL SALT WATER WETLANDS FRESHWATER WETLANDS DRAINAGE AREA DA# FW SW RANDS IP1
LEGEND
DRAINAGE DIVIDE TIME OF CONCENTRATION PATH DRAINAGE AREA FRESHWATER WETLANDS SALT WATER WETLANDS RANDS CANAL INFILTRATION PIT
TOWN OF FALMOUTH
TOWN OF FALMOUTH
Subcat
Reach
DA1
FW
I used HydroCAD for the analysis between existing and proposed drainage characteristics.
Pond
Link
RANDS
DA2
SW
existing
Prepared by Town of Falmouth, DPW, Engineering
HydroCAD 9.10 s/n 07153 2010 HydroCAD Software Solutions LLC
Subcatchment DA1: Subcatchment DA2: Reach FW: Reach RANDS: Reach SW:
Flow (cfs)
Drainage Diagram for existing Prepared by Town of Falmouth, DPW, Engineering, Printed 5/23/2011
existing
Prepared by Town of Falmouth, DPW, Engineering
HydroCAD 9.10 s/n 07153 2010 HydroCAD Software Solutions LLC
Time span=0.00-72.00 hrs, dt=0.01 hrs, 7201 points Runoff by SCS TR-20 method, UH=SCS Reach routing by Stor-Ind+Trans method - Pond routing by Stor-Ind method
Runoff Area=19,633 sf 31.18% Impervious Runoff Depth=1.43" Flow Length=310' Tc=5.0 min CN=77 Runoff=0.77 cfs 0.054 af Runoff Area=16,635 sf 11.43% Impervious Runoff Depth=0.28" Flow Length=221' Tc=7.7 min CN=53 Runoff=0.04 cfs 0.009 af Inflow=0.77 cfs 0.054 af Outflow=0.77 cfs 0.054 af Inflow=0.77 cfs 0.063 af Outflow=0.77 cfs 0.063 af Inflow=0.04 cfs 0.009 af Outflow=0.04 cfs 0.009 af
Runoff by SCS TR-20 method, UH=SCS, Time Span= 0.00-72.00 hrs, dt= 0.01 hrs Type III 24-hr 2-YR Rainfall=3.50"
Area (sf) 3,975 3,185 2,937 595 8,941 19,633 13,511 6,122
CN 72 98 98 36 68 77
Description Dirt roads, HSG A Paved parking, HSG A WETLANDS HSG D Woods, Fair, HSG A <50% Grass cover, Poor, HSG A Weighted Average 68.82% Pervious Area 31.18% Impervious Area
Total Runoff Area = 0.833 ac Runoff Volume = 0.063 af Average Runoff Depth = 0.90" 77.88% Pervious = 0.648 ac 22.12% Impervious = 0.184 ac
Tc Length Slope Velocity Capacity Description (min) (feet) (ft/ft) (ft/sec) (cfs) 0.3 25 0.0400 1.44 Sheet Flow, Smooth surfaces n= 0.011 P2= 3.50" 0.9 25 0.0500 0.47 Sheet Flow, Fallow n= 0.050 P2= 3.50" 1.2 260 0.0500 3.60 Shallow Concentrated Flow, Unpaved Kv= 16.1 fps Total, Increased to minimum Tc = 5.0 min 2.4 310
Subcatchment DA1:
Hydrograph
0.85 0.8 0.75 0.7 0.65 0.6 0.55 0.5 0.45 0.4 0.35 0.3 0.25 0.2 0.15 0.1 0.05 0 0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 52 54 56 58 60 62 64 66 68 70 72 Time (hours)
Runoff
Runoff=0.77 cfs @ 12.08 hrs Type III 24-hr 2-YR Rainfall=3.50" Runoff Area=19,633 sf Runoff Volume=0.054 af Runoff Depth=1.43" Flow Length=310' Tc=5.0 min CN=77
Subcat
DA100
Reach
FW
Pond
Link
IP1
DA101
RANDS
DA200
SW
proposed
Prepared by Town of Falmouth, DPW, Engineering
HydroCAD 9.10 s/n 07153 2010 HydroCAD Software Solutions LLC
Flow (cfs)
Drainage Diagram for proposed Prepared by Town of Falmouth, DPW, Engineering, Printed 5/23/2011
Subcatchment DA100:
Hydrograph
0.6 0.55 0.5 0.45 0.4 0.35 0.3 0.25 0.2 0.15 0.1 0.05 0 0 2 4 6
proposed
Prepared by Town of Falmouth, DPW, Engineering
HydroCAD 9.10 s/n 07153 2010 HydroCAD Software Solutions LLC
Runoff by SCS TR-20 method, UH=SCS, Time Span= 0.00-72.00 hrs, dt= 0.01 hrs Type III 24-hr 2-YR Rainfall=3.50"
Runoff=0.54 cfs @ 12.12 hrs Type III 24-hr 2-YR Rainfall=3.50" Runoff Area=21,219 sf Runoff Volume=0.043 af Runoff Depth=1.06" Flow Length=176' Tc=7.6 min CN=71
Area (sf) 2,679 1,113 0 0 3,123 6,915 5,802 1,113 Tc Length (min) (feet) 0.3 25 0.3 25 93 44
CN 72 98 98 36 68 74
Description Dirt roads, HSG A Paved parking, HSG A Wetlands HSG D Woods, Fair, HSG A <50% Grass cover, Poor, HSG A Weighted Average 83.90% Pervious Area 16.10% Impervious Area
8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 52 54 56 58 60 62 64 66 68 70 72 Time (hours)
1.0 0.1
1.7
187
Slope Velocity Capacity Description (ft/ft) (ft/sec) (cfs) 0.0400 1.44 Sheet Flow, Smooth surfaces n= 0.011 P2= 3.50" 0.0500 1.57 Sheet Flow, Smooth surfaces n= 0.011 P2= 3.50" 0.0100 1.61 Shallow Concentrated Flow, Unpaved Kv= 16.1 fps 0.0711 9.23 3.22 Pipe Channel, 8.0" Round Area= 0.3 sf Perim= 2.1' r= 0.17' n= 0.013 Corrugated PE, smooth interior Total, Increased to minimum Tc = 5.0 min
3/9/2011
1. Total Area of Project = 0.86 ac 2. Total Impervious Cover= 0.08 ac 3. Water Quality Volume? Discharge into shellfish growing areas and cold-water fisheries, therefore volume to be treated = 1" x total impervious area of post developed site.
WQV = 1" X Total Impervious Cover = 1" X 0.08 = 0.08 ac-in = 0.01 ac-ft
4. Compute Recharge Volume (ReV) Hydrologic Ic Vol. to ReV ReV Soil Group (Impervious Recharge =Ic X Vol. Area) to Recharge (ac) (in) (ac.-in) (cf) A 0.08 0.40 0.03 116.16 B 0.00 0.25 0.00 0.00 C 0.00 0.10 0.00 0.00 D 0.00 0.00 0.00 0.00 Totals 0.08 116.16 *Ic = Area of impervious cover of proposed site within hydrologic soil group. 116.16 CUBIC FEET OF RUNOFF MUST BE RECHARGED
5. Compute Rooftop Runoff. Total Roof Area= 0 ac Runoff = Total Roof Area X First Flush >>> = 0 ac-in = 0.00 ac-ft 1 in
Assume 15 diameter leaching basin (7 Basin + 4 stone). 100 yr storm volume = .055 af in 24 hours = 2,396 cf/day = 17,923 gal/day. Assume 5.55x10^3 m/yr = 50 ft/day. (Table 5.2 Sand) Assume 27% Specific Yield. (Table 4-39 Sand) 35 foot deep boring, assuming could have gone further before bedrock, use 35 feet for thickness. 24 hours storm = 0.003 years
6. How much of the recharge volume can be met by infiltrating the roof? Remainder to be infiltrated = Rev - Roof Runoff = 116.16 0.00 = 116.16 cf No roof to recharge.
7. Total volume of Water to be treated for water quality? Volume of Water to be Treated = WQV-RR = 0.01 0.00 = 0.01 ac-ft = 290.4 cf 290 CUBIC FEET OF RUNOFF MUST BE TREATED FOR WATER QUALITY From HydroCAD, Infiltration Pit volume = 409 CF (Static Method)
8. Capture Area Adjustment Total Impervious Cover= 0.08 ac Impervious Discharging to Infiltration= 0.03 ac Total/Discharged = 2.67 Rev * (Total/Discharged) = 310 cf From HydroCAD, Infiltration Pit volume = 409 CF (Static Method)
Groundwater mound will not raise into the leaching basin for a 100 year storm volume.
INSTRUCTIONS: 1. In BMP Column, click on Blue Cell to Activate Drop Down Menu 2. Select BMP from Drop Down Menu 3. After BMP is selected, TSS Removal and other Columns are automatically completed.
Location: B BMP1
Subsurface Infiltration Structure
DA-101
0.00
0.20
0.00
0.20
0.00
0.20
0.00
0.20
0.00
0.20
0.00
0.20
0.00
0.20
0.00
0.20 Separate Form Needs to be Completed for Each Outlet or BMP Train
80%
*Equals remaining load from previous BMP (E) which enters the BMP
DA-3 (FE2) Wetlands USE 1/2 100 YEAR STORM INFLOW TO REACH FW USE 1/2 100 YEAR STORM INFLOW TO REACH FW
DA-3 (FE2)
DA-2 (FE1)
LOCATION FROM TO
Wetlands
Wetlands
CALC BY: SCS DATE: 4/12/2011 CHECK BY: DATE: DESIGN STORM: 25 Year/100 Year
1.33
1.33
1.33
1.33
0.80
LOCATION A
FROM TO Q (Actual) (ft/s) 0.80 1.33 1.33 1.33 1.33
B
Size (ft) 0.67 0.67 0.67 0.67 0.67
C
So ft/ft)
D
n (-)
E
Q (Full) (ft/s) 3.21 2.83 2.22 2.83 2.22
PIPE DESIGN F G
d (ft) 0.2270 0.3210 0.3720 0.3210 0.3720 (deg) 142.80 175.76 166.68 175.76 166.68
H
A (ft) 0.105 0.166 0.200 0.166 0.200
I
WP (ft) 0.83 1.02 1.12 1.02 1.12
J
Rh (ft) 0.13 0.16 0.18 0.16 0.18
K
Q (ft/s) 0.80 1.33 1.33 1.33 1.33
L
V (ft/s)
M
Inv (1) (ft) 15.60 12.50 9.10 12.50 9.10
N
Inv (2) (ft) 12.50 7.00 6.90 7.00 6.90
R
Cover (2) (ft.) 1.8 0.3 -0.6 0.3 -0.6
Ground Ground Cover Elev. (1) Elev. (2) (1) (ft) (ft) (ft.) 17.25 15.00 11.00 15.00 11.00 15.00 8.00 7.00 8.00 7.00 1.0 1.8 1.2 1.8 1.2
Pipe Slope Length (ft) (ft/ft) 44 100 65 100 65 0.070 0.055 0.034 0.055 0.034
DA 1 DA 2 DA 3 DA 1+2 DA 3 A B C D E F G H I J
0.070 0.013 0.055 0.013 0.034 0.013 0.055 0.013 0.034 0.013 K L M N O P Q R S T
Scour Calculations
Design flowrate target Pipe diameter Pipe slope (from T) Manning's roughness coefficient Pipe full flow capacity depth of design flow in pipe Used for calculating flow area Flow area Wetted perimeter Hydraulic radius
calculated flowrate calculated velocity Upstream invert Downstream invert Upstream ground elevation Downstream ground elevation Upstream cover over pipe Downstream cover over pipe Length of pipe Calculated slope of pipe
scour
Prepared by Town of Falmouth, DPW, Engineering
HydroCAD 9.10 s/n 07153 2010 HydroCAD Software Solutions LLC
Routing by Stor-Ind+Trans method, Time Span= 0.00-72.00 hrs, dt= 0.01 hrs / 2 Max. Velocity= 4.84 fps, Min. Travel Time= 0.0 min Avg. Velocity = 4.84 fps, Avg. Travel Time= 0.0 min Peak Storage= 4 cf @ 0.41 hrs Average Depth at Peak Storage= 0.30' Bank-Full Depth= 0.50', Capacity at Bank-Full= 5.08 cfs 0.00' x 0.50' deep channel, n= 0.033 Side Slope Z-value= 3.0 '/' Top Width= 3.00' Length= 13.0' Slope= 0.1538 '/' Inlet Invert= 7.00', Outlet Invert= 5.00'
FE1
FE2
Summary for Reach FE2:
Inflow Outflow = = 1.33 cfs @ 1.33 cfs @ 0.00 hrs, Volume= 0.27 hrs, Volume= 7.915 af, Incl. 1.33 cfs Base Flow 7.914 af, Atten= 0%, Lag= 16.2 min
Routing by Stor-Ind+Trans method, Time Span= 0.00-72.00 hrs, dt= 0.01 hrs / 2 Max. Velocity= 4.30 fps, Min. Travel Time= 0.1 min Avg. Velocity = 4.30 fps, Avg. Travel Time= 0.1 min Peak Storage= 5 cf @ 0.27 hrs Average Depth at Peak Storage= 0.32' Bank-Full Depth= 0.50', Capacity at Bank-Full= 4.33 cfs 0.00' x 0.50' deep channel, n= 0.033 Side Slope Z-value= 3.0 '/' Top Width= 3.00' Length= 17.0' Slope= 0.1118 '/' Inlet Invert= 6.90', Outlet Invert= 5.00'
Subcat
Reach
Pond
Link
Drainage Diagram for scour Prepared by Town of Falmouth, DPW, Engineering, Printed 9/26/2011
HydroCAD 9.10 s/n 07153 2010 HydroCAD Software Solutions LLC
SECTION: 31 00 00 EARTHWORK
Part 1 General
a. Geotechnical laboratory test reports on borrow material. b. Daily geotechnical field reports indicating in-place density tests. c. One proctor test indicating the optimum moisture-maximum density curve for each type of soil encountered.
1.1. SCOPE A. This Section of the Specifications includes excavations of normal depth in earth for trenches, pavements and structures; backfilling such excavations to the extent required; filling; and rough grading.
1.2. A. B. C. D. E. F. G. H. I. J. K. L. M.
RELATED WORK Section 31 05 13 Soils for Earthwork Section 31 05 16 Aggregates for Earthwork Section 31 05 19.13 Geotextiles for Earthwork Section 31 05 19.19 Geogrids for Earthwork Section 31 14 13.13 Soil Stripping Section 31 22 13 Rough Grading Section 31 22 16.13 Roadway Subgrade Reshaping Section 31 22 19 Finish Grading Section 31 23 16.16 Structural Excavation for Minor Structures Section 31 23 16.26 Rock Removal Section 32 11 23 Aggregate Base Courses Section 32 15 40 Crushed Stone Surfacing Section 32 91 19.13 topsoil Placement and Grading
I had to create all of the Specifications for this job because the Town did not have standard Specifications to fit this project.
1.6. QUALITY ASSURANCE A. Testing and Observation: The Town shall provide a Geotechnical Consultant to perform on-site observation and testing during the excavation and backfilling for this work. The services of the Geotechical Consultant shall include, but not be limited to the following: a. Observation during excavation and dewatering for the fish ladder. b. Observation during excavation and dewatering for the culvert. c. Observation during excavation and dewatering for the wing walls. d. Laboratory testing and analysis of fill materials specified as required. B. The Geotechnical Consultant shall immediately report to the Engineer in writing if at any time in his opinion the work does not conform to the Construction Documents. C. The Geotechnical Consultant presence does not include the supervision or direction of the actual work by the Contractor, his employees, or agents. Neither the presence of the Geotechnical Consultant nor any observations and testing performed by him, nor any notice or failure to give notice, shall excuse the Contractor from defects discovered in his work.
1.3. REFERENCES A. ASTM D1557 - 09 Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3 (2,700 kN-m/m3))
1.4. MEASUREMENT AND PAYMENT A. Payment for Earth Excavation work shall be included in Roadway Reconstruction, Culvert Replacement, Wing Wall Placement, Storm Drainage, Fish Ladder Replacement, and Site Demolition. B. There will be no compensation for Unauthorized Excavation or remedial work due to Unauthorized Excavation. C. Payment for Additional Excavation shall be based on a Unit Cost (cy) basis. D. Payment for Rock Excavation shall be based on a Unit Cost (cy) basis.
1.5. SUBMITTALS A. Test Reports for excavation in the fish ladder, culvert, and wing wall areas:
Town of Falmouth Department of Public Works Engineering Division
1.7. EXCAVATION CLASSIFICATIONS A. Earth Excavation or Excavation consists of removal of materials encountered to the subgrade elevations indicated and subsequent reuse or disposal of the materials removed. All excavation is classified as earth excavation unless it otherwise meets the classifications provided below for unauthorized excavation, additional excavation, or rock excavation. B. Unauthorized Excavation consists of removal of materials beyond indicated subgrade elevations or dimensions without specific direction of the Engineer. Unauthorized excavation, as well as remedial work directed by the Engineer, shall be at the Contractors expense. a. Under the fish ladder, culverts, and wingwalls, fill unauthorized excavations to the proper elevations with lean concrete or compacted fill approved by the Geotechnical Consultant. Elsewhere, backfill and compact unauthorized excavations as specified for the excavations of the same class, otherwise directed by the Engineer. C. Additional Excavation consists of removal of materials beyond the indicated subgrade elevations or dimensions with the specific direction of the Engineer. Additional Excavation directed by the Engineer shall be based on a Unit Cost basis. a. When Excavation has reached required subgrade elevations, notify the Engineer and Geotechnical Consultant who will assess the subgrade conditions. b. If unsuitable materials are encountered at required subgrade elevations, carry excavations down to firm natural ground and replace excavated material as recommended by the Geotechnical Consultant and directed by the Engineer.
Town of Falmouth Department of Public Works Engineering Division
EXISTING AA ##
CBDH SB DH LP UP
W
LEGEND
RESOURCE AREA FLAG CONCRETE BOUND w/ DRILL HOLE STONE BOUND DRILL HOLE
PROPOSED
SO
D G W
OHW
98
98X5
GAS LINE WATER LINE OVERHEAD WIRES CONTOUR SPOT GRADE 98 98X50
IP
CB
CATCH BASIN/LEACHING BASIN FLARED END OUTLET HYDRANT GAS VALVE WATER VALVE EXISTING TREE LINE TREE TO REMAIN TREE/SHRUB TO BE REMOVED <5" CALIPER TREE TO BE REMOVED >5" CALIPER LIMIT OF WORK ROADWAY LAYOUT LINES PROPERTY LINES
This project involved the design and permitting for a new fish ladder. This included regrading the roadway over the ladder and including stormwater measures to appease the Conservation Commission. I designed, prepared the drawings, got the permits, and produced construction documents for all portions of this project with the exception of the fish ladder itself.
H
Y D
ELEVATION
CHANGE (CF)
-2
-1
350
321
-29
546
491
-55
757
689
-68
988
912
-76
1157
1099
-58
1334
1253
-81
1529
1432
-97
1768
1664
-104
2239
1965
-274
2726
2242
-484
3172
2700
-472
10
3909
4024
115
11
5508
5831
323
12
7310
7340
30
13
8566
8835
269
13.15
1407
1457
50
TOTAL
43,266
42255
-1011
STATION
NORTHING
EASTING
5035.0187
5171.2678
0+00
5410.8072
5044.3237
PI 0+64.76
5348.2310
5060.2279
PI 1+26.37
5286.7898
5064.7702
PI 1+65.33
5248.5329
5072.1361
PC 1+99.10
5217.5631
5085.5940
PI 2+36.29
5185.9322
5105.1341
PC 3+81.70
5071.8434
5195.2970
4+62
5013.6288
5250.5946
EXISTING TREE LINE TREE TO REMAIN TREE/SHRUB TO BE REMOVED <5" CALIPER TREE TO BE REMOVED >5" CALIPER
LEGEND
* * * * *
EASTING 5171.2678 5044.3237
CLEAR AND GRUB WITHIN LIMIT OF WORK. REMOVE INDICATED TREES WITHIN LIMIT OF WORK. ROUGH GRADE TRAVEL LANE FOR PHASE 1. ROUGH GRADE GRASS DRAINAGE CHANNEL. ROUGH GRADE WIDENED ROAD FOR TRAVEL LANE FOR PHASE 2.
STATION
NORTHING
5035.0187
I split the construction into 3 phases so that the dead end Bay Road would remain open for traffic at all times.
5060.2279 5064.7702 5072.1361
0+00
5410.8072
PI 0+64.76
5348.2310
PI 1+26.37
5286.7898
PI 1+65.33
5248.5329
PC 1+99.10
5217.5631
PI 2+36.29
5185.9322
PC 3+81.70
5071.8434
* * * *
CLEAR AND GRUB WITHIN LIMIT OF WORK. REMOVE INDICATED TREES WITHIN LIMIT OF WORK. ROUGH GRADE TRAVEL LANE FOR PHASE 1. ROUGH GRADE WIDENED ROAD FOR TRAVEL LANE FOR PHASE 2.
4+62
5013.6288
STATION1+00 TO 2+00
* * * * * * * * * *
CLEAR AND GRUB WITHIN LIMIT OF WORK. REMOVE INDICATED TREES WITHIN LIMIT OF WORK. ROUGH GRADE TRAVEL LANE FOR PHASE 1. ROUGH GRADE WIDENED ROAD FOR TRAVEL LANE FOR PHASE 2. REMOVE ABANDONED UTILITY POLE (TO BE COORDINATED WITH NSTAR) CONSTRUCT EQUIPMENT ACCESS TO FISH LADDER. REMOVE PORTION OF EXISTING CULVERT. REMOVE EAST WALL. REMOVE ABANDONED WATER LINES AS REQUIRED. REALIGN BANK AS REQUIRED.
EXISTING AA ##
CBDH SB DH LP UP
W
LEGEND
RESOURCE AREA FLAG CONCRETE BOUND w/ DRILL HOLE STONE BOUND DRILL HOLE
PROPOSED
D G W
OHW
LIGHT POLE UTILITY POLE WATER VALVE DRAIN LINE GAS LINE WATER LINE OVERHEAD WIRES
IP
STATION
NORTHING
EASTING
5035.0187
Y D
5171.2678
CATCH BASIN/LEACHING BASIN FLARED END OUTLET HYDRANT GAS VALVE WATER VALVE LIMIT OF WORK ROADWAY LAYOUT LINES
0+00
5410.8072
5044.3237
PI 0+64.76
5348.2310
5060.2279
PI 1+26.37
5286.7898
5064.7702
PI 1+65.33
5248.5329
5072.1361
PC 1+99.10
5217.5631
5085.5940
PI 2+36.29
5185.9322
5105.1341
PC 3+81.70
5071.8434
5195.2970
4+62
5013.6288
5250.5946
I chose to utilize precast concrete wall sections for a fast construction. I designed the crossing to be two lanes to provide a place where cars can pass in opposite directions, something they can't do on the rest of the road. TOWN OF FALMOUTH DEPARTMENT OF PUBLIC WORKS
The interface between phases was critical since the stream is always flowing and the new pipe was higher, a larger diameter, and at a much shallower slope. I determined where the two pipe bottoms met and set that as the phase1/ phase2 interface. The crossing widths fell into place after this was set. Phase3 interface was simply where the wall and the fish ladder meet.
FISH LADDER CENTERLINE CONTROL (SEE STRUCTURAL PLANS FOR FULL ALIGNMENT)
FISH LADDER STATION (L:) BEGIN L:75+00 ROADWAY STATION AND OFFSET NORTHING EASTING
1+61.33, 22.32'R
5049.4598
5248.2434
END L:1+40
1+85.82, 37.10'L
5244.5261
5114.3342
These cross sections show how the phases fit, allowing stream flow at all times. Continuous stream flow enables fish species to travel to and from the ocean and the pond.
My design improved the road's vertical geometry without increasing flood zone filling. I moved the low point in the road away from the crossing to allow for positive drainage.
50% 30% 20% HYDROSEED AT A RATE OF 250#/ACRE APPLY 16-25-12 FERTILIZER AT A RATE OF 275 #/ACRE AT THE TIME OF SEEDING
LOLIUM PERENNE BRIGHTSTAR RYEGRASS VARIOUS SPECIES TURF TYPE TALL FESCUE
IN ADDITION, NATIVE CAPE COD SEDGES EXAMPLES INCLUDE: CAREX CRINITA (AWNED SEDGE), CAREX ECHINATA (STAR SEDGE), CAREX INTUMESCENS (BLADDER SEDGE), CAREX LURIDA (SALLOW SEDGE), CAREX PENSYLVANICA (PENNSYLVANIA SEDGE) HYDROSEED AT A RATE OF 3#/ACRE
MIX BY TURF LINKS INC. (OR APPROVED EQUAL) 35% PERENNIAL RYE GRASS 5% GUINNESS KENTUCKY BLUEGRASS 5% MERIT KENTUCKY BLUEGRASS 20% EPIC CREEPING RED FESCUE 35% FINE LAWN SUPREME TALL FESCUE
SINGLE NET STRAW BLANKET BY NORTH AMERICAN GREEN (OR APPROVED EQUAL)
I chose all the details, modified our standard notes as required, and created some new details.
SEED AT A RATE OF 12# PER 1,000SF APPLY 17-17-17 50% XCU (SLOW RELEASE) FERTILIZER AT A RATE OF 10 #/1,000 SF AND SULFATE AND POTASH AT A RATE OF 10#/1,000 SF BOTH AT THE TIME OF SEEDING INSTALL 1.5# PHOTODEGRADABLE POLYPROPYLENE TOP NET 100% FIBER MATRIX AFTER SEEDING AND FERTILIZING.
I had to come up with all of these details. There was a lot of tight tolerances to fit the walls and to keep the stream flow going at all times. I had to come up with a temporary connection between phase 1 and phase 2 work for the pipe.
I had to come up with a way to add stop logs to both ends of the pipes.
416 Gifford Street Falmouth, Massachusetts 02540 Tel: (508) 457-2543 Fax: (508) 548-1537
May 5, 2011 Jennifer McKay Conservation Commission Administrator Town of Falmouth Conservation Commission 59 Town Hall Square Falmouth, MA 02540 Dear Jennifer:
This is the transmittal for an RDA involving stormwater issues in two areas of the DPW Building's driveway.
On behalf of the Town of Falmouth Department of Public Works (DPW), the Town of Falmouth Department of Public Works Engineering Division (Engineering) is filing this Request for Determination of Applicability for drainage improvements at the DPW facility on Gifford Street. The goal of this project is to make emergency repairs to an existing drainage system in close proximity to the Town of Falmouth fuel facilities that the DPW maintains. Currently there is a leaching catch basin with an overflow to a Bordering Vegetated Wetland (BVW) to the south of the facility. There is no protection of the BVW in this system in the event of a fuel or oil spill. This project will address this issue by adding a fuel/oil capturing device. The project involves removing the existing leaching basin and replacing it with a Stormceptor EOS (Extended Oil Storage System) unit that is designed to capture and separate hydrocarbons from stormwater runoff. The existing leaching basin will be relocated approximately 8 feet downstream and connected to the new Stormceptor EOS unit with 10 HDPE pipe. The existing 10 CMP outlet from the existing leaching basin will be reconnected to the new location. The existing outlet near the BVW is just over 2 feet below grade. The end of the pipe has been exposed in a very small excavation to allow clearing of the pipe when it plugs up. The plans are to cut this pipe back approximately 2 feet from the end and to expand the excavation to 5 foot diameter, centered on the new end of the pipe. The excavation will then be lined with filter fabric and back filled with crushed stone. In addition to the drainage structure reconfiguration, approximately 209 linear feet of cape cod berm is proposed to positively direct stormwater runoff to the Stormceptor EOS unit, and approximately 253 square feet of pavement will be removed from behind utility pole #644B. None of this work would result in an increase in stormwater flows (a very slight decrease will be realized due to the pavement removal). This work is critical in protecting the BVW should a spill occur at the fuel filling facility. A lot of work has recently been done at the abutting Lawrence Lynch facility adjacent to this BVW and our proposed work would only enhance the BVW. This area is currently being monitored for past underground storage tanks that were removed when the DPW Facility addition along with the parking lot and the stormwater system in question was constructed in 2005. The upgrade to this stormwater system will only be an improvement. Attached to this application we have included a 40 scale plan showing the proposed work, a Locus and an Aerial Map, several GIS maps, and information on the Stormceptor EOS system.
P:\Private\Projects\0-Town Facilities\Public Works Facility\2011\DPW Drainage\Reports\RDA\RDA transmittal.doc
September 6, 2012
We are filing the Request for Determination of Applicability because we do not believe the Wetlands Protection Act and the Stormwater Management Standards contained therein apply to this project based on the following arguments: None of the work is proposed within the BVW, only buffer area work is proposed. 310 CMR 10.02(2)(b)1.f. o We are removing existing pavement and replacing it with loam and seed and erosion and sedimentation controls are proposed. 310 CMR 10.02(2)(b)2. a. We are filing a Request for Determination of Applicability. b. The BVW was delineated during a Notice of Intent by the abutter as shown on the plan entitled Plan of Proposed Stormwater System by Holmes and McGrath Inc, dated November 14, 2007 and last revised 3/15/10. c. Slopes in the buffer zones are less than 15%. d. None of the buffer zone is located within NHESP mapped habitat area. e. None of the buffer zone borders an Outstanding Resource Water. f. We are proposing work within 50 feet of the BVW. g. We are reducing the impervious surface and all alterations within 50 feet of the BVW is temporary and will be returned to natural conditions. h. Erosion and sedimentation controls are proposed; although they are within 50 feet of the resource area they are placed to protect the BVW to the maximum extent practicable. i. The project will increase compliance of the existing stormwater system with the Stormwater Management Standards with the addition of the Stormceptor EOS unit. j. This work is within previously developed area with the exception of the last 16 feet which falls within a brush line. The other remaining portions of the project are either existing paved or lawn surfaces. Based on the above reasoning, we respectfully request a Negative Determination of Applicability for the proposed work at the DPW Facility. Please do not hesitate to contact me with any questions, comments or concerns. Sincerely,
Peter M. McConarty Acting Town Engineer Department of Public Works Engineering Division