Sie sind auf Seite 1von 122

BASIS AND CONSIDERATION Contractor's profit Overhead expenses VAT Foreman Head mason Mason Skilled labour /Helper

Ordinary labour Rod binder Machine operator Diesel operated rig operator Helper to diesel operated rig operator Plumber Carpenter Lime Bamboo Bailing-out water Palisading Bamboo driving G.I. wire Sal ballah Nails and gazals etc Wooden plank 40 grade rod Bricks Fine sand 1.2 F.M sand 2.5 Sylhet sand Cement Form work place & remove Breaking brick chips Bitumenous coating Crushed stone chips Scaffolding 1/2" plaster on walls (1:4) Marble dust / powder Concrete mixer machine Concrete vibrator Fuel & lubricant for mixer machine, Vibrator, pump etc. Water pump for concreting or similar purpose Supplying & fixing Rupban or equivalent sheet and hessian tape (where necessary) for making watertight sufficiently Bamboo props in/c top supports Salballah props in/c top supports 2" dia M.S. pipe 1.5" dia M.S. pipe 2" dia G.I. pipe 10% 3.50% 4.50% Tk. 250.00 Tk. 180.00 Tk. 150.00 Tk. 120.00 Tk. 100.00 Tk. 180.00 Tk. 160.00 Tk. 300.00 Tk. 150.00 Tk. 160.00 Tk. 160.00 Tk. 20.00 Tk. 4.00 Tk. 1,000.00 Tk. 17.08 Tk. 6.63 Tk. 50.00 Tk. 30.00 Tk. 40.00 Tk. 360.00 Tk. 22,660.00 Tk. 3,100.00 Tk. 625.00 Tk. 990.00 Tk. 1,330.00 Tk. 250.00 Tk. 6.00 Tk. 550.00 Tk. 150.00 Tk. 6,500.00 Tk. 3.00 Tk. 6.95 Tk. 12.00 Tk. 500.00 Tk. 385.00 Tk. 350.00 Tk. Tk. Tk. Tk. Tk. Tk. Tk. Each Each Each Each Each Each Each Each Each Each Each kg. rft. day sft. rft. kg. rft. kg. cft. ton % 0 Nos. % cft. % cft. % cft. bag sft. % cft. % sft. % cft. sft. sft. Per kg. Per day Per day Per day

150.00 Per day 1.00 Per sft. 40.00 350.00 80.00 60.00 80.00 Each Each rft. rft. rft.

1.5" dia G.I. pipe 3/4" G.I. pipe 1/2" dia G.I. pipe Adjustable mechanism in/c top and bottom plate 1/8" thick 4" x 2" M.S. box channel Prop with adjustable mechanism in/c top and bottom plate Turn-buckle in/c tie-rod Garjan, Jam, local sal: sized timber M.S. sheet M.S. rod: 60 grade M.S. angle, T and Z-section, M.S. channel etc. M.S. bar and F.I. bar (non-structural) Fabrication cost of steel shutter for form work Nut, bolt, j-hook Spot welding Running welding Hire charge of cast in situ pile boring complete rig set in/c fuel, lubricant, bentonite covering the cost of mobilization, demobilization, maintenance, spares, stand-byes and insurance coverage etc. Hire charge of pre-cast pile driving complete rig set in/c -do-do- etc. Hire charge of pre-cast micro pile driving complete rig set in/c -do-do- etc. Hire charge of load testing devices in/c hydraulic fluid: up to 125 ton capacity -do -do-: up to 275 ton capacity Truck fare in Dhaka city in/c loading unloading. Filling and stitching empty gunny bags Load testing result sheet preparation Empty gunny bags One layer brick-flat soling 1/2" thick cement plaster with neat finish Hire charge of diesel hammer mounted completed rig set. Lifting and movement of crane for diesel mounted hammer up to site Truck fare in/c loading-unloading by truck for carrying diesel hammer mounted rig for driving precast pile (excluding crane) Diesel Copper sheer for construction expansion Aluminium sheet for construction expansion Counter-sunk revet Polythene sheet Surki Stone lime Brick work in superstructure (1:6) Concrete (1:2:4)

Tk. 72.00 Tk. 33.00 Tk. 25.00 Tk. 320.00 Tk. 74.00 Tk. 1,300.00 Tk. 250.00 Tk. 710.00 Tk. 23,920.00 Tk. 24,120.00 Tk. 19,195.00 Tk. 17,010.00 Tk. 30.00 Tk. 60.00 Tk. 150.00 Tk. 2.00

rft. rft. rft. rft. rft. Set Set cft. Ton Ton Ton Ton sft. kg. % spot inch

Tk. 4,500.00 Per day Tk. 6,000.00 Per day Tk. 3,000.00 Per day Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. 4,500.00 5,500.00 800.00 4.00 1,000.00 20.00 11.71 8.82 10,000.00 Per test Per test Per trip Per bag Per test Each sft. sft. Per day

Tk. 25,000.00 Per set per site Tk. 4,000.00 Per trip

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

17.25 70.00 40.00 20.00 117.00 24.00 5.00 64.44 89.91

liter sft. sft. Each % sft. cft. kg. cft. cft.

4" dia HCI pipe MAANCO/NISSAN/NANAKHI/GENERAL Brand 4" dia HCI pipe (SNC) 4" dia uPVC pipe: National Polymer brand Full size bamboo for scaffoldinf 1.5 mm thick corrugated fibre glass 0.45 mm thick C.I. sheet: CAMEL Brand 0.45 mm thick C.I. sheet: GALCO STEEL 0.45 mm thick coloured C.I. sheet: GALCO STEEL 0.27 mm thick 6'-0" x 18" ridging: GALCO STEEL 0.27 mm thick 6'-0" x 18" coloured ridging: GALCO STEEL 1.5 mm thick fibre glass sheet ridging Water-proofing PVC membrane Primer for laying PVC membrance on wall Water reducing chemical admixture in concrete: Type - A Retarding chemical admixture in concrete: Type - B Accelerating chemical admixture in concrete: Type C Water-reducing and retarding chemical admixture in concrete: Type - D Water-reducing and accelerating chemical admixture in concrete: Type - E Water-reducing high range chemical admixture in concrete: Type - F Water-reducing high range and retarding chemical admixture in concrete: Type - G

Tk. Tk.

600.00 515.00

6' - 0" long pc. 6' - 0" long pc. rft. Each Per sft. Per ton Per ton Per ton Per pc. Per pc. Per rft. Per sqm. Per liter Per liter

Tk. 45.15 Tk. 80.00 Tk. 36.00 Tk. 35,500.00 Tk. 35,500.00 Tk. 50,000.00 Tk. 90.00 Tk. 115.00 Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. 62.00 500.00 420.00 140.00

120.00 Per liter 150.00 Per liter 130.00 Per liter 140.00 Per liter 145.00 Per liter 135.00 Per liter

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

07. RCC WORK 08. PILE WORK 09. MS FABRICATION WORK 10. EXPANSION/BEARING JOINT 11. LIME TERRACING & WATER PROFING WORK 12. CI SHEET ROOFING
ANALYSIS FOR ITEM NO. 41(a) R.C.C. work (1:2:4) complete excluding the cost of reinforcement and its fabrication in individual and continuous footings of column at plinth level with brick chips. Considering 100 cft. of work A. Cost of concrete a) Bricks for chips (@ 90 cft for % cft. concrete). b) Breaking cost of chips in/c screening c) Sand (F.M. 1.2) d) Sand (F.M. 2.5) 765 Nos. 90 cft. 22.5 cft. 22.5 cft. @ @ @ @ @ @ Tk. Tk. Tk. Tk. Tk. Tk. 3,100.00 Per % 0 Nos. = Tk. 550.00 Per % cft. = Tk. 990.00 1,330.00 250.00 100.00 Per % cft. = Tk. Per % cft. = Tk. Per bag = Tk. each = Tk. L.S. = Tk. Total = Tk. 2,371.50 495.00 222.75 299.25 4,500.00 700.00 50.00 8,638.50

e) Cement 18 bags f) Labour for 28 days curing @ 1/4 labour per day 7 Nos. g) Local carriage, sundries, T & P B. Labour, machinery, fuel and lubricant for casting

Considering 600 cft. concreting work


a) Head mason b) Mason c) Skilled labour: i ) Feeding cement ii) Feeding sand iii) Feeding chips in/c screening Total = d) Ordinary labour i) bag cutting ii) Belcha iii) Lifting iv) Pouring v) On the way vi) Poking vii) Watering Total = e) Mixture machine hire charge 1 No. 4 Nos. 1 2 3 6 1 3 9 9 9 2 1 34 1 No. Nos. Nos. Nos. No. Nos. Nos. Nos. Nos. Nos. No. Nos. day
- 142 -

@ @

Tk. Tk.

180.00 150.00

each = Tk. each = Tk.

180.00 600.00

Tk.

120.00

each = Tk.

720.00

@ @

Tk. Tk.

100.00 500.00

each = Tk. Per day = Tk.

3,400.00 500.00

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

f) Vibrator machine hire charge 1 day Fuel and lubricant for mixture machine & vibrator g) 1 day

@ @

Tk. Tk.

385.00 350.00

Per day = Tk.

385.00 350.00 6,135.00 1,022.50

Per day = Tk. Total of (B) = Tk. Cost for 100 cft. of work = Tk.

C.

Cost of shuttering Considering 6'-0'' x 6'-0'' Base (D=14'', d=10'') Volume of concrete: 6'-0" x 6'-0" x 1'-0" = 36.00 cft.(approx) i ) Cost of shuttering wood: Planks required: 4 x 6'-0" x 1'-0" x 1" = 2.00 cft 15% for batten, supports & wastage = 0.30 cft. = 2.30 cft. @ Tk. Using 6 times @ Tk. Labour for shuttering in/c making, placing & removing: ii) 24 sft. @ Tk. iii) Supplying & fixing rupban or equivalent sheet and hessian tape @ Tk.

360.00 60.00 6.00

Per cft. Per cft. = Tk. Per sft. = Tk.

138.00 144.00

(where necessary) for making water-tight sufficiently 24 sft. iv) Nails and wires etc.

Per sft. L.S. Total of (C) Cost for 100 cft. of work

1.00

= = = =

Tk. Tk. Tk. Tk.

24.00 25.00 331.00 919.44

Abstract of cost for 100 cft. of work (A) (B) (C) Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering Contractor's profit Overhead expenses VAT = = = Total = 10.00% = 3.50% = 4.50% Grand total Rate per cft. Rate per cum. Tk. 8,638.50 Tk. 1,022.50 Tk. 919.44 Tk. 10,580.44 Tk. 1,058.04 Tk. 370.32 Tk. 12,008.80 Tk. 540.40 Tk. 12,549.20 Tk. 125.49 Tk. 4,431.68

=
= = =

Say,

Tk.

4,432 .00 Per cum.

ANALYSIS FOR ITEM NO. 41(b) R.C.C. work (1:2:4) complete excluding the cost of reinforcement and its fabrication in raft/mat with brick chip Considering 100 cft. of work
- 143 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

A. B. C.

i)

ii) iii)

iv)

Cost of concrete Labour, machinery, fuel & lubricant for casting Cost of shuttering: Assuming 30'-0'' x 30'-0'' x 4'-0'' raft: Vol of concrete: 30'-0'' x 30'-0'' x 4'-0'' = 3600.00 cft. Cost of shuttering wood Planks & batten reqd.: Plank: 4 x 30'-0'' x 4'-0'' x 1.5'' = 60.00 cft. Add 15% for supports & wastage = 9.00 cft. 69.00 cft. @ Using 6 times @ Labour for shuttering in/c making, placing & removing: 4 x 30'-0" x 4'-0"= 480 sft. @ Supplying & fixing rupban or equivalent sheet and hessian tape (where necessary) for making water-tight sufficiently 480 sft. @ Nails and wires

Same as item No. 41(a) Same as item No. 41(a)

= Tk. = Tk.

8,638.50 1,022.50

Tk. Tk. Tk.

360.00 60.00 6.00

Per cft. Per cft. = Tk. Per sft. = Tk.

4,140.00 2,880.00

Tk.

Per sft. L.S. Total of (C) Cost of 100 cft. of work.

1.00

= = = =

Tk. Tk. Tk. Tk.

480.00 500.00 8,000.00 222.22

Abstract of cost for 100 cft. of work (A) (B) (C) Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering Contractor's profit Overhead expenses VAT = = = Total = 10.00% = 3.50% = 4.50% Grand total Rate per cft. Rate per cum. Tk. 8,638.50 Tk. 1,022.50 Tk. 222.22 Tk. 9,883.22 Tk. 988.32 Tk. 345.91 Tk. 11,217.45 Tk. 504.79 Tk. 11,722.24 Tk. 117.22 Tk. 4,139.62

=
= = =

Say,

Tk.

4,140 .00 Per cum.

ANALYSIS FOR ITEM NO. 41(c) R.C.C. work (1:2:4) complete excluding the cost of reinforcement and its fabrication in foundation beam with brick chip Considering 100 cft. of work A. B. Cost of concrete Labour, machinery, fuel & lubricant for casting

Same as item No. 41(a) Same as item No. 41(a)

= Tk. = Tk.

8,638.50 1,022.50

- 144 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

C.

i)

ii) iii)

iv)

Cost of shuttering: Assuming 10'-0'' x 3'-0'' x 1'-6'' beam: Vol of concrete: 10'-0'' x 3'-0'' x 1'-6'' = 45.00 cft. Cost of shuttering wood Planks & batten reqd.: 2 x 10'-0'' x 3'-0'' x 1.5'' = 7.50 cft. 2 x 4 x 3'-0'' x 0'-3'' x 1.5'' = 0.75 cft. Tie: 4 x 1'-9'' x 0'-3'' x 1.5'' = 0.22 cft. = 8.47 cft. Add 15% for supports & wastage = 1.27 cft. 9.74 cft. @ Tk. Using 6 times @ Tk. Labour for shuttering in/c making, placing & removing: 75 sft. @ Tk. Supplying & fixing rupban or equivalent sheet and hessian tape (where necessary) for making water-tight sufficiently 75 sft. @ Tk. Nails and wires

360.00 60.00 6.00

Per cft. Per cft. = Tk. Per sft. = Tk.

584.40 450.00

Per sft. L.S. Total of (C) Cost for 100 cft. of concrete

1.00

= = = =

Tk. Tk. Tk. Tk.

75.00 25.00 1,134.40 2,520.89

Abstract of cost for 100 cft. of work (A) (B) (C) Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering Contractor's profit Overhead expenses VAT = = = Total = 10.00% = 3.50% = 4.50% Grand total Rate per cft. Rate per cum. Tk. 8,638.50 Tk. 1,022.50 Tk. 2,520.89 Tk. 12,181.89 Tk. 1,218.19 Tk. 426.37 Tk. 13,826.45 Tk. 622.19 Tk. 14,448.64 Tk. 144.49 Tk. 5,102.66

=
= = =

Say,

Tk.

5,103 .00 Per cum.

ANALYSIS FOR ITEM NO. 42 R.C.C. work (1:2:4) complete excluding the cost of reinforcement and its fabrication in Padestals, column capitals, lift walls and walls with brick chips and wooden shutter. Considering 100 cft. of work A. B. C Cost of concrete Labour, machinery, fuel & lubricant for casting Cost of shuttering Assuming 10'-0" x 12'' x 12'' column
- 145 -

Same as item No. 41(a) Same as item No. 41(a)

= Tk. = Tk.

8,638.50 1,022.50

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

Volume of concrete i ) Cost of shuttering woods: Planks & batten reqd.: 2 x 10'-0'' x 1'-3'' x 1.5'' = 2 x 10'-0'' x 1'-0'' x 1.5'' = 4 x 2 x 1'-6" x 3'' x 1.5'' = = Add 5% wastage= = ii) iii) iv)

10 cft.

v)

3.12 cft. 2.50 cft. 0.375 cft. 5.995 cft. 0.30 cft. 6.30 cft. @ Tk. Using 6 times @ Tk. Bamboo Props in/c inclined support 4 Nos. @ Tk. Using 6 times @ Tk. Labour for shuttering in/c making, placing & removing: 40 sft @ Tk. Supplying & fixing rupban or equivalent sheet and hessian tape (where necessary) for making water-tight sufficiently 40 sft @ Tk. Nails and wires

360.00 60.00 60.00 10.00 6.00

Per cft. = Tk. each = Tk. each = Tk. Per sft. = Tk.

378.00 18.00 40.00 240.00

Per sft. L.S. Total of (C) Cost for 100 cft. of work

1.00

= = = =

Tk. Tk. Tk. Tk.

40.00 25.00 741.00 7,410.00

Abstract of cost for 100 cft. of work (A) Cost of concrete (B) Labour, machinery, fuel and lubricant for casting (C) Cost of shuttering Contractor's profit Overhead expenses VAT = = = Total = 10.00% = 3.50% = 4.50% Grand total Rate per cft. Rate per cum. Tk. 8,638.50 Tk. 1,022.50 Tk. 7,410.00 Tk. 17,071.00 Tk. 1,707.10 Tk. 597.49 Tk. 19,375.59 Tk. 871.90 Tk. 20,247.49 Tk. 202.47 Tk. 7,150.23

=
= = =

(a) Below plinth level and in ground floor

Say,

Tk.

7,150 .00 Per cum.

(b) (c) (d)

Add for each addl. floor upto 5th floor: @ 1.25 Nos. lab per % cft. in/c charges Add for each addl. floor from 6th floor to 9th floor: @ 1.75 Nos. lab per % cft.in/c charges Add for each addl. floor for 10th floor & above: @ 2.0 Nos. lab. per % cft. in/c charges

Per cum = Tk. Per cum = Tk. Per cum = Tk.

52.36 73.30 83.77

ANALYSIS FOR ITEM NO. 43

- 146 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in tie beams and lintels with brick chips and wooden shutter Considering 100 cft. of work A. B. C

i)

ii) iii)

iv)

v)

Same as item No. 41(a) Cost of concrete Labour, machinery, fuel and lubricant for casting Same as item No. 41(a) Cost of shuttering: Assuming 10'-0'' x 10'' x 9'' beam Vol of concrete: 6.25 cft. Cost of shuttering wood Planks & batten reqd.: 2 x 10'-0'' x 0'-10'' x 1.5'' = 2.08 cft. 9 x 1'-1'' x 0'-2'' x 1.5'' = 0.20 cft. = 2.28 cft. Add 15% for door/window openings & 0.34 cft. wastage= = 2.62 cft. @ Tk. 360.00 Per cft. Using 6 times @ Tk. 60.00 Per cft. Bamboo props in/c inclined supports: 2 Nos. @ Tk. 40.00 each Using 6 times @ Tk. 6.67 each Labour for shuttering in/c making, placing & removing: 2 x 10'-0'' x 0'-10'' = 16.67 sft. 1 x 3'-0'' x 10'' = 2.50 sft. = 19.17 sft. @ Tk. 6.00 Per sft Supplying & fixing rupban or equivalent sheet and hessian tape (where necessary) for making water-tight sufficiently 19.17 sft. @ Tk. 1.00 Per sft Nails and wires L.S. Total of (C) Cost for 100 cft. of work
Abstract of cost for 100 cft. of work (A) Cost of concrete (B) Labour, machinery, fuel and lubricant for casting (C) Cost of shuttering Contractor's profit Overhead expenses VAT

= Tk. = Tk.

8,638.50 1,022.50

= Tk. = Tk.

157.20 13.34

= Tk.

115.02

= = = =

Tk. Tk. Tk. Tk.

19.17 25.00 329.73 5,275.68

= = = Total = 10.00% = 3.50% = 4.50% Grand total Rate per cft. Rate per cum.

=
= = =

Tk. 8,638.50 Tk. 1,022.50 Tk. 5,275.68 Tk. 14,936.68 Tk. 1,493.67 Tk. 522.78 Tk. 16,953.13 Tk. 762.89 Tk. 17,716.02 Tk. 177.16 Tk. 6,256.41

(a) Below plinth level and in ground floor


- 147 -

Say,

Tk.

6,256 .00 Per cum.

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

(b) (c) (d)

Add for each addl. floor upto 5th floor: @ 1.25 Nos. lab. per % cft.in/c charges Add for each addl. floor from 6th floor to 9th floor: @ 1.75 Nos. lab. per % cft.in/c charges Add for each addl floor for 10th floor & above: @ 2.0 Nos. lab. per % cft. in/c charges

Per cum = Tk. Per cum = Tk. Per cum = Tk.

52.36 73.30 83.77

ANALYSIS FOR ITEM NO. 44 R.C.C. work (1:2:4) complete excluding the cost of reinforcement and its fabrication in Tee beams, Ell beams and Rectangular beams etc with brick chips and wooden shutter. Considering 100 cft. of work. A. B. C Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering Assuming 20'-0'' x 1'-6'' x 1'-0'' beam Volume of concrete= 30 cft. Cost of shuttering wood: plank & batten: i) 2 x 20'-0'' x 1'-6'' x 1.5''= 7.50 cft. 1 x 20'-0'' x 1'-3'' x 1.5''= 3.13 cft. 9 x 1'-6'' x 0'-3'' x 1.5''= 0.42 cft. 2 x 9 x 1'-4.5'' x 2'' x 1.5'' = 0.52 cft. = 11.57 cft. Add 5% wastage= 0.58 cft. 12.15 cft. Using 6 times ii) Bamboo props in/c bracket supports 5 Nos. Using 6 times iii) Salbullah props up to 4 m long in/c inclined supports etc.: 5 Nos. Using 8 times

Same as item No. 41(a) Same as item No. 41(a)

= Tk. = Tk.

8,638.50 1,022.50

@ @ @ @ @ @

Tk. Tk. Tk. Tk. Tk. Tk.

360.00 60.00 60.00 10.00 350.00 43.75 40.00

Per cft. Per cft. = Tk. each each = Tk. each each = Tk. Per kg. = Tk.

729.00 50.00

218.75 40.00

iv) Nails: 1.00 kg @ Tk. v) Labour for shuttering in/c making, placing & removing: For side & bottom, 2 x 20'-0'' x 1'-6'' = 60 sft. 1 x 20'-0'' x 1'-0'' = 20 sft. = 80 sft. @ Tk. vi) Supplying & fixing rupban or equivalent sheet and hessian tape (where necessary) for making water-tight sufficiently 80 sft. @ Tk.

6.00

Per sft. = Tk.

480.00

1.00

Per sft. = Tk. Total of (C) = Tk. Cost for 100 cft. = Tk.

80.00 1,597.75 5,325.83

- 148 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

Abstract of cost for 100 cft. of work (A) (B) (C) Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering Contractor's profit Overhead expenses VAT = = = Total = 10.00% = 3.50% = 4.50% Grand total Rate per cft. Rate per cum. Tk. 8,638.50 Tk. 1,022.50 Tk. 5,325.83 Tk. 14,986.83 Tk. 1,498.68 Tk. 524.54 Tk. 17,010.05 Tk. 765.45 Tk. 17,775.50 Tk. 177.76 Tk. 6,277.59

=
= = =

(a) Below plinth level and in ground floor

Say,

Tk.

6,278 .00 Per cum.

(b) (c) (d)

Add for each addl. floor upto 5th floor: @ 1.25 Nos. lab. per % cft. in/c charges Add for each addl. floor from 6th floor to 9th floor: @ 1.75 Nos. lab. per % cft. in/c charges Add for each addl. floor for 10th floor & above: @ 2.0 Nos. lab. per % cft. in/c charges

Per cum = Tk. Per cum = Tk. Per cum = Tk.

52.36 73.30 83.77

ANALYSIS FOR ITEM NO. 45 R.C.C. work (1:2:4) complete excluding the cost of reinforcement and its fabrication in floor and roof slab with brick chips and wooden shutter. Considering 100 cft. of work A. B. C. Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering Assuming 10'-0'' x 10'-0'' x 4.5'' slabs Volume of concrete: 37.5 cft. i) Planks: 70% of slab area: 0.70 x 10'-0'' x 10'-0'' x 1'' = 5.83 cft. 4 x 10'-0" x 4.5" x1.5"= 1.90 cft. 7.7 cft. Add 5% wastage 0.4 cft. 8.10 @ Using 6 times @ ii) Batten: Garjan 5 x 10'-0" x 3" x 2" = 2.08 cft. Add 5% wastage 0.10 cft. 2.18 cft. @
- 149 -

Same as item No. 41(a) Same as item No. 41(a)

= Tk. = Tk.

8,638.50 1,022.50

Tk. Tk.

360.00 60.00

Per cft. Per cft. = Tk.

486.00

Tk.

710.00

Per cft.

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

iii) 16 BWG M.S. sheet

iv) v) vi)

vii)

Using 6 times Tk. 110 sft. = 280.5 Ibs. @ Tk. Using 16 times @ Tk. Bamboo props in/c bracket: 25 Nos. @ Tk. Using 6 times @ Tk. Nails: 1 kg @ Tk. Labour for shuttering in/c making, placing & removing: 10' - 0'' x 10' - 0'' = 100 sft. 4 x 10'-0" x 4.5"= 15 sft. = 115 sft. @ Tk. Supplying & fixing rupban or equivalent sheet and hessian tap (where necessary) for making shutter water-tight sufficiently. 115 sft. @ Tk.

118.33 10.85 0.68 60.00 10.00 40.00

Per cft. = Tk. Per Ibs. Per Ibs. = Tk. each each = Tk. Per kg. = Tk.

257.96

190.74 250.00 40.00

6.00

Per sft. = Tk.

690.00

1.00

Per sft. = Tk. Total of (C) = Tk. Cost for 100 cft. = Tk.

115.00 2,029.70 5,412.53

Abstract of cost for 100 cft. of work (A) Cost of concrete (B) Labour, machinery, fuel and lubricant for casting (C) Cost of shuttering Contractor's profit Overhead expenses VAT = = = Total = 10.00% = 3.50% = 4.50% Grand total Rate per cft. Rate per cum. Tk. 8,638.50 Tk. 1,022.50 Tk. 5,412.53 Tk. 15,073.53 Tk. 1,507.35 Tk. 527.57 Tk. 17,108.45 Tk. 769.88 Tk. 17,878.33 Tk. 178.78 Tk. 6,313.62

=
= = =

(a) Below plinth level and in ground floor

Say,

Tk.

6,314 .00 Per cum.

(b) (c) (d)

Add for each addl. floor upto 5th floor: @ 1.25 Nos. lab. per % cft. in/c charges Add for each addl. floor from 6th floor to 9th floor: @ 1.75 Nos. lab. per % cft. in/c charges Add for each addl. floor for 10th floor & above: @ 2.0 Nos. lab. per % cft. in/c charges

Per cum = Tk. Per cum = Tk. Per cum = Tk.

52.36 73.30 83.77

ANALYSIS FOR ITEM NO. 46 R.C.C. work (1:2:4) complete excluding the cost of reinforcement and its fabrication in Waffle or Ribbed floor/roof slab with brick chips and wooden shutter. Considering 100 cft. of work

- 150 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

A. Cost of concrete or 100 cft. B. Labour, machinery, fuel & lubricants etc C. Shuttering cost: Slab area: 32'-10" x 22'-10", spacing of ribs: 2'-0" c/c both ways. Vol. of concrete: Beam: 2 x 32'-10" x 1'-8" x 2'-6"= 274.21 cft. 2 x 19'-6" x 1'-8" x 2'-6"= 162.83 cft. Slab: 1 x 29'-6" x 19'-6" x 0'-3"= 143.81 cft. Rib: 8 x 29'-6" x 2'-3" x 0'-6"= 265.50 cft. 14 x 15'-6" x 2'-3" x 0'-6"= 244.13 cft. 1090.48 cft. Cost of form work: i. Qty. of wood per box: Plank: 2 x 2'-0" x 2'-3" x 1"= 0.75 cft. 2 x 1'-10" x 2'-3" x 1"= 0.69 cft. 1 x 2'-0" x 2'-0" x 1"= 0.33 cft. Batten: 4 x 2'-3" x 2" x 3"= 0.38 cft. Block to fix the box on the platform: 4 x 6" x 2" x 2"= 0.06 cft. Batten to tie the box against movement: 4 x 1'-0" x 2" x 1"= 0.06 cft. = 2.27 cft. Add wastage 5%= 0.11 cft. 2.38 cft. Qty. of wood for 135 Nos. boxes= 321.3 cft. @ Deduct salvage value: ii. Qty. of wood per beam: Side of beam: 2 x (22'-10" +32'-10") x 2'-6" x 1.5"= 34.80 cft. Batten, vertical: 50 x 2'-6" x 2" x 2"= 3.47 cft. Inclined: 50 x 3'-3" x 2" x 2"= 4.51 cft. = 42.78 cft. Add wastage 5%= 2.14 cft. = 44.92 cft. @ iii. Wood for platform: Plank: 1 x 32'-10" x 22'-10" x 1.5"= Runner: 16 x 26'-10" x 3" x 2"= = Add wastage 5%= =

Same as item No. 41(a) Same as item No. 41(a)

= Tk. = Tk.

8,638.50 1,022.50

Tk.

360.00 Per cft.

= Tk. 115,668.00 -25% = Tk. -28,917.00

Tk.

360.00 Per cft. Using 6 times

= Tk.

2,695.20

93.76 17.89 111.65 5.58 117.23

cft. cft. cft. cft. cft.

Tk.

360.00 Per cft. Using 6 times 1,300.00 each Using 30 times

= Tk.

7,033.80

iv. 2" dia steel prop in/c Adjustable mechanism: 165

Nos.

Tk.

= Tk.

7,150.00

- 151 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

v. 5/8" dia M.S. rod for bracing: 10 x 36'-10"= 14 x 26'-10"= = Add wastage 5%= = =

36.84 375.76 412.6 20.63 433.23 450.56

rft. rft. rft. rft. rft. Ibs

Tk.

vi. Nails and wires 25 kg @ vii. Cost for making, placing & removing formwork: Platform: 1 x 36'-10" x 26'-10"= 988.7856 sft. Beam: 2 x (32'-10" + 22'-10") x 2'-6"= 278.4 sft. Box: 135 x 2'-0" x 2'-0"= 540 sft. 135 x 4 x 2'-0" x 2'-3"= 2700 sft. = 4507.19 sft. @ Tk. viii. Supplying & fixing rupban or equivalent sheet and hessian tape (where necessary) for making water-tight sufficiently 4507.19 sft. @ Tk.

10.94 Per Ibs Using 20 times Tk. 40.00 Per kg.

= Tk. = Tk.

246.46 1,000.00

6.00 Per sft.

= Tk. 27,043.14

= Tk. 4,507.19 = Tk. 136,426.79 Formwork and shuttering cost for 100 cft. = Tk. 12,510.71

1.00 Per sft.

Abstract of cost for 100 cft. of work (A) Cost of concrete (B) Labour, machinery, fuel, lubricants etc. for casting (C) Shuttering cost Contractor's profit Overhead expenses VAT = = = Total = 10.00% = 3.50% = 4.50% Grand total Rate per cft. Rate per cum. Tk. 8,638.50 Tk. 1,022.50 Tk. 12,510.71 Tk. 22,171.71 Tk. 2,217.17 Tk. 776.01 Tk. 25,164.89 Tk. 1,132.42 Tk. 26,297.31 Tk. 262.97 Tk. 9,286.79

=
= = =

(a) Below plinth level and in ground floor

Say,

Tk.

9,287 .00 Per cum.

(b) (c) (d)

Add for each addl. floor upto 5th floor: @ 1.25 Nos. lab. per % cft. in/c charges Add for each addl. floor from 6th floor to 9th floor: @ 1.75 Nos. lab. per % cft. in/c charges Add for each addl. floor for 10th floor & above: @ 2.0 Nos. lab. per % cft. in/c charges

Per cum = Tk. Per cum = Tk. Per cum = Tk.

52.36 73.30 83.77

ANALYSIS FOR ITEM NO. 47

- 152 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

R.C.C. work (1:2:4) complete excluding the cost of reinforcement and its fabrication in sunshade, cornice, railing, drop walls etc. for all floors (av. 3'' thick) with brick chips and wooden shutter. Considering 100 cft. of work A. B. C. Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering: Assuming 3" thick 10'-0" x 3'-0" = 30 sft. drop wall

Same as item No. 41(a) Same as item No. 41(a)

= Tk. = Tk.

8,638.50 1,022.50

Volume of concrete: 10'-0" x 3'-0" x 0'-3"(av) = 7.5 cft. i ) Cost of shuttering wood: Planks and batten 2 x 10'-0" x 3'-0" x 0'-1" = 5.00 cft. 2 x 3 x 3'-0" x 0'-3" x 0'-2" = 0.75 cft. 1 x 10'-0" x 5" x 1"= 0.34 cft. 3 x 1'-6" x 0'-3" x 0'-2" = 0.19 cft. = 6.28 cft. Add 5% wastage = 0.31 cft. 6.59 cft. Using 6 times ii) Bamboo struts in/c inclined supports 8.0 Nos. Using 6 times

iii) Nails and wires 1.0 kg iv) Labour for shuttering in/c making, placing & removing: 2 x 10'-0'' x 3'-0" = 60 sft. 1 x 10'-0" x 3"= 2.5 sft. = 62.5 sft. @ Tk. v) Supplying & fixing rupban or equivalent sheet and hessian tape (where necessary) for making water-tight sufficiently 62.5 sft. @ Tk.

@ @ @ @ @

Tk. Tk. Tk. Tk. Tk.

360.00 60.00 30.00 5.00 40.00

Per cft. Per cft. = Tk. each each = Tk. Per kg = Tk.

395.40 40.00 40.00

6.00

Per sft. = Tk.

375.00

Per sft. = Tk. Total of (C) = Tk. Cost for 100 cft. of work = Tk.

1.00

62.50 912.90 12,172.00

Abstract of cost for 100 cft. of work (A) Cost of concrete (B) Labour, machinery, fuel and lubricant for casting (c) Cost of shuttering Contractor's profit Overhead expenses VAT = = = Total = 10.00% = 3.50% = 4.50% Grand total Rate per cft. Rate per sft. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. 8,638.50 1,022.50 12,172.00 21,833.00 2,183.30 764.16 24,780.46 1,115.12 25,895.58 258.96 64.74

=
= = =

- 153 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

(a) Below plinth level and in ground floor Say, Tk.

Per sqm = Tk. 697 . 00 Per sqm.

696.86

(b) (c) (d)

Add for each addl. floor upto 5th floor: @ 1/12 No. lab. Per sqm in/c charges Add for each addl. floor from 6th floor to 9th floor: @ 1/8 No. lab. per sqm in/c charges Add for each addl. floor for 10th floor & above: @ 1/6 No. lab. per sqm in/c charges

Per sqm. = Tk. Per sqm. = Tk. Per sqm. = Tk.

9.88 14.83 19.77

ANALYSIS FOR ITEM NO. 48 R.C.C. work (1:2:4) complete excluding the cost of reinforcement and its fabrication in stair case slab and steps with brick chips and wooden shutter. Considering 100 cft. of work A. B. C. Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering: Assuming 8'-9" long & 4'-0" wide stair Volume of concrete 8'- 9" x 4'-0" x 0'-6" = 17.50 cft. 1/2 x 9 x 4'-0" x 0'-10" x 0'-6" = 7.56 cft. = 25.06 cft. Cost of shuttering wood: planks and batten 1 x 8'-9" x 4'-0" x 0'-1.5" = 4.38 cft. 9 x 4'-0" x 0'-6" x 0'-1.5" = 2.25 cft. 2 x 8'-9" x 1'-1.5" x 1.5" = 2.46 cft. 5 x 4'-0" x 3" x 2"= 0.83 cft. 2 x 5 x 1'-1.5" x 3" x 2" = 0.47 cft. 1 x 8'-9" x 3" x 2" = 0.36 cft. 10.75 cft. Add wastage 5%= 0.54 cft. 11.29 cft. Using 6 times Bamboo props in/c bracket: 10 Nos. Using 6 times Nails: 1.00 kg Labour for shuttering in/c making, placing & removing: 1 x 8'-9" x 4'-0" = 35 sft. 9 x 4'-0" x 0'-6" = 18.00 sft. 2 x 8'-9" x 1'-1.5" = 19.60 sft. = 72.6 sft. Supplying & fixing rupban or equivalent sheet
- 154 -

Same as item No. 41 (a) Same as item No. 41 (a)

= Tk. = Tk.

8,638.50 1,022.50

i)

ii) iii) iv)

@ @ @ @

Tk. Tk. Tk. Tk. Tk.

360.00 60.00 40.00 6.67 40.00

Per cft. Per cft. = Tk. each each = Tk. Per kg. = Tk.

677.40 66.70 40.00

Tk.

6.00

Per sft. = Tk.

435.60

v)

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

and hessian tape (where necessary) for making water-tight sufficiently 72.6 sft. @ Tk.

Per sft. = Tk. Total of (C) = Tk. Cost for 100 cft. of work = Tk.

1.00

72.60 1,292.30 5,156.82

Abstract of cost for 100 cft. of work (A) Cost of concrete (B) Labour, machinery, fuel and lubricant for casting (C) Cost of shuttering Contractor's profit Overhead expenses VAT = = = Total = 10.00% = 3.50% = 4.50% Grand total Rate per cft. Rate per cum. Tk. 8,638.50 Tk. 1,022.50 Tk. 5,156.82 Tk. 14,817.82 Tk. 1,481.78 Tk. 518.62 Tk. 16,818.22 Tk. 756.82 Tk. 17,575.04 Tk. 175.75 Tk. 6,206.61

=
= = =

(a) Below plinth level and in ground floor

Say,

Tk.

6,207 .00 Per cum.

(b) (c) (d)

Add for each addl. floor upto 5th floor: @ 1.25 Nos. lab. per % cft. in/c charges Add for each addl. floor from 6th floor to 9th floor: @ 1.75 Nos. lab. per % cft. in/c charges Add for each addl. floor for 10th floor & above: @ 2.0 Nos. lab. per % cft. in/c charges

Per cum = Tk. Per cum = Tk. Per cum = Tk.

52.36 73.30 83.77

ANALYSIS FOR ITEM NO. 49(a) R.C.C work with brick chips and wooden shutter (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in individual and continuous footings of column at plinth level. Cosidering 100 cft. of work Cost of concrete Brick for chips: @ 83 cft. of chips per % cft. of concrete & 8.5 Nos. of bricks per cft. of chips. @ @ @ @ @ @ Tk. Tk. Tk. Tk. Tk. Tk. 3,100.00 Per % 0 Nos. = 550.00 Per % cft. = 990.00 Per % cft. = 1,330.00 Per % cft. = 250.00 each = 100.00 L.S. Tk. Tk. Tk. Tk. Tk. 2,188.60 456.50 205.43 275.98 5,500.00 700.00 50.00 9,376.51

A. a) b) c) d) e) f)

706 Nos. Breaking bricks in/c screening 83 cft. Sand (F.M. 1.2) 20.75 cft Sand (F.M. 2.5) 20.75 cft. Cement 22 bags Labour for 28 days curing: @ 1/4 No. of labour per day. 7 Nos. g) Local carriage, sundries, T & P

each = Tk. = Tk. Total = Tk.

- 155 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

B. C.

Labour, machinery, fuel and lubricant for casting Shuttering cost

Same as item No. 41 (a) Same as item No. 41 (a)

= Tk. 1,022.50 = Tk. 919.44 Total = Tk. 11,318.45 Contractor's profit 10.00% = Tk. 1,131.85 Overhead expenses 3.50% = Tk. 396.15 Tk. 12,846.45 VAT 4.50% = Tk. 578.09 Grand total = Tk. 13,424.54 Rate per cft. = Tk. 134.25 Rate per cum. = Tk. 4,741.04 Tk. 4,741 .00 Per cum.

Say,

ANALYSIS FOR ITEM NO. 49(b) R.C.C. work with brick chips and wooden shutter (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in raft/mat Considering 100 cft. of wrk A. B. C. Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering

Same as item No. 49(a) Same as item No. 41(a) Same as item No. 41(b)
Contractor's profit Overhead expenses VAT

= = = Total = 10.00% = 3.50% =

4.50% Grand total Rate per cft. Rate per cum.

=
= = =

Tk. 9,376.51 Tk. 1,022.50 Tk. 222.22 Tk. 10,621.23 Tk. 1,062.12 Tk. 371.74 Tk. 12,055.09 Tk. 542.48 Tk. 12,597.57 Tk. 125.98 Tk. 4,448.98

Say,

Tk.

4,449 .00 Per cum.

ANALYSIS FOR ITEM NO. 49(c) R.C.C. work with brick chips and wooden shutter (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in foundation beam Considering 100 cft. of work A. B. C. Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering

Same as item No. 49(a) Same as item No. 41(a) Same as item No. 41(c)
Contractor's profit Overhead expenses

= = = Total = 10.00% = 3.50% =

Tk. 9,376.51 Tk. 1,022.50 Tk. 2,520.89 Tk. 12,919.90 Tk. 1,291.99 Tk. 452.20 Tk. 14,664.09

- 156 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

VAT

4.50% Grand total Rate per cft. Rate per cum.

659.88 = Tk. 15,323.97 = Tk. 153.24 = Tk. 5,411.67

= Tk.

Say,

Tk.

5,412 .00 Per cum.

ANALYSIS FOR ITEM NO. 50 R.C.C. work with brick chips and using wooden shutter (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in Padestals, column capitals, lift walls and walls. Considering 100 cft. of work A. B. C. Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering

Same as item No. 49(a) Same as item No. 41(a) Same as item No. 42
Contractor's profit Overhead expenses VAT

= = = Total = 10.00% = 3.50% =

4.50% Grand total Rate per cft. Rate per cum.

=
= = =

Tk. 9,376.51 Tk. 1,022.50 Tk. 7,410.00 Tk. 17,809.01 Tk. 1,780.90 Tk. 623.32 Tk. 20,213.23 Tk. 909.60 Tk. 21,122.83 Tk. 211.23 Tk. 7,459.59

(a) Below plinth level and in ground floor

Say,

Tk.

7,460 .00 Per cum.

(b) (c) (d)

Add for each addl. floor upto 5th floor: @ 1.25 Nos. lab. per % cft. in/c charges Add for each addl. floor from 6th floor to 9th floor: @ 1.75 Nos. lab. per % cft. in/c charges Add for each addl. floor for 10th floor & above: @ 2.0 Nos. lab. per % cft. in/c charges

Per cum = Tk. Per cum = Tk. Per cum = Tk.

52.36 73.30 83.77

ANALYSIS FOR ITEM NO. 51 R.C.C. work with brick chips and using wooden shutter (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in tie beams and lintels. Considering 100 cft. of work A. B. C Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering

Same as item No. 49(a) Same as item No. 41(a) Same as item No. 43

= = = Total =

Tk. 9,376.51 Tk. 1,022.50 Tk. 5,275.68 Tk. 15,674.69

- 157 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

Contractor's profit Overhead expenses

10.00% = Tk. 1,567.47 3.50% = Tk. 548.61 Tk. 17,790.77 VAT 4.50% = Tk. 800.58 Grand total = Tk. 18,591.35 Rate per cft. = Tk. 185.91 Rate per cum. = Tk. 6,565.41 6,565 .00 Per cum.

(a) Below plinth level and in ground floor

Say,

Tk.

(b) (c) (d)

Add for each addl. floor upto 5th floor: @ 1.25 Nos. lab. per % cft. in/c charges Add for each addl. floor from 6th floor to 9th floor: @ 1.75 Nos. lab. per % cft. in/c charges Add for each addl. floor for 10th floor & above: @ 2.0 Nos. lab. per % cft. in/c charges

Per cum = Tk. Per cum = Tk. Per cum = Tk.

52.36 73.30 83.77

ANALYSIS FOR ITEM NO. 52 R.C.C. work with brick chips and using wooden shutter (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in Tee beams, Ell beams and Rectangular beams etc. Considering 100 cft. of work A. B. C. Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering

Same as item No. 49(a) Same as item No. 41(a) Same as item No. 44
Contractor's profit Overhead expenses VAT

= = = Total = 10.00% = 3.50% =

4.50% Grand total Rate per cft. Rate per cum.

=
= = =

Tk. 9,376.51 Tk. 1,022.50 Tk. 5,325.83 Tk. 15,724.84 Tk. 1,572.48 Tk. 550.37 Tk. 17,847.69 Tk. 803.15 Tk. 18,650.84 Tk. 186.51 Tk. 6,586.60

(a) Below plinth level and in ground floor

Say,

Tk.

6,587 .00 Per cum.

(b) (c) (d)

Add for each addl. floor upto 5th floor: @ 1.25 Nos. lab. per % cft. in/c charges Add for each addl. floor from 6th floor to 9th floor: @ 1.75 Nos. lab. per % cft. in/c charges Add for each addl. floor for 10th floor & above: @ 2.0 Nos. lab. per % cft. in/c charges

Per cum = Tk. Per cum = Tk. Per cum = Tk.

52.36 73.30 83.77

ANALYSIS FOR ITEM NO. 53 R.C.C. work with brick chips and using wooden shutter (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in floor and roof slab etc.
- 158 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

Considering 100 cft. of work A. B. C. Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering

Same as item No. 49(a) Same as item No. 41(a) Same as item No. 45
Contractor's profit Overhead expenses VAT

= = = Total = 10.00% = 3.50% =

4.50% Grand total Rate per cft. Rate per cum.

=
= = =

Tk. 9,376.51 Tk. 1,022.50 Tk. 5,412.53 Tk. 15,811.54 Tk. 1,581.15 Tk. 553.40 Tk. 17,946.09 Tk. 807.57 Tk. 18,753.66 Tk. 187.54 Tk. 6,622.98

(a) Below plinth level and in ground floor

Say,

Tk.

6,623 .00 Per cum.

(b) (c) (d)

Add for each addl. floor upto 5th floor: @ 1.25 Nos. lab. per % cft. in/c charges Add for each addl. floor from 6th floor to 9th floor: @ 1.75 Nos. lab. per % cft. in/c charges Add for each addl. floor for 10th floor & above: @ 2.0 Nos. lab. per % cft. in/c charges

Per cum = Tk. Per cum = Tk. Per cum = Tk.

52.36 73.30 83.77

ANALYSIS FOR ITEM NO. 54 R.C.C. work with brick chips and using wooden shutter (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in sunshade, cornice, railing, drop walls etc. for all floors (av. 3" thick). Considering 100 cft. of work A. B. C. Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering

Same as item No. 49(a) Same as item No. 41(a) Same as item No. 47
Contractor's profit Overhead expenses VAT

= = = Total = 10.00% = 3.50% =

4.50% Grand total Rate per cft. Rate per sft.

=
= = =

Tk. 9,376.51 Tk. 1,022.50 Tk. 12,172.00 Tk. 22,571.01 Tk. 2,257.10 Tk. 789.99 Tk. 25,618.10 Tk. 1,152.81 Tk. 26,770.91 Tk. 267.71 Tk. 66.93 720.43

(a) Below plinth level and in ground floor Say, Tk.

Per sqm = Tk. 720 .00 Per sqm.

- 159 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

(b) (c) (d)

Add for each addl. floor upto 5th floor: @ 1/12 Nos. lab. per sqm in/c charges Add for each addl. floor from 6th floor to 9th floor: @ 1/8 Nos. lab. per sqm in/c charges Add for each addl. floor for 10th floor & above: @ 1/6 Nos. lab. per sqm in/c chareges

Per sqm. = Tk. Per sqm. = Tk. Per sqm. = Tk.

9.88 14.83 19.77

ANALYSIS FOR ITEM NO. 55 R.C.C. work with brick chips and using wooden shutter (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in stair case slab and steps. Considering 100 cft. of work A. B. C. Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering

Same as item No. 49(a) Same as item No. 41(a) Same as item No. 48
Contractor's profit Overhead expenses VAT

= = = Total = 10.00% = 3.50% =

4.50% Grand total Rate per cft. Rate per cum.

=
= = =

Tk. 9,376.51 Tk. 1,022.50 Tk. 5,156.82 Tk. 15,555.83 Tk. 1,555.58 Tk. 544.45 Tk. 17,655.86 Tk. 794.51 Tk. 18,450.37 Tk. 184.50 Tk. 6,515.62

(a) Below plinth level and in ground floor


(b) (c) (d)

Say,

Tk.

6,516 .00 Per cum.


Per cum = Tk. Per cum = Tk. Per cum = Tk. 52.36 73.30 83.77

Add for each addl. floor upto 5th floor: @ 1.25 Nos. lab. per % cft. in/c charges Add for each addl. floor from 6th floor to 9th floor: @ 1.75 Nos. lab. per % cft. in/c charges Add for each addl. floor for 10th floor & above: @ 2.0 Nos. lab. per % cft. in/c charges

ANALYSIS FOR ITEM NO. 56(a) R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in individual and continuous footings of column, at plinth level with stone chips using steel shutter and prop. Considering 100 cft. of work A. a) b) c) d) Cost of concrete: 19 mm down crushed stone chips 83 Sand (F.M. 2.5) 41.5 Cement 22 Labour for 28 days curing: @ 1/4 labour per day. 7 e) Local carriage, sundries, T & P

cft. cft. bags. Nos

@ @ @ @

Tk. Tk. Tk. Tk.

6,500.00 1,330.00 250.00 100.00 L.S.

Per % cft. = Tk. Per % cft. = Tk. Per bag. = Tk. each = Tk. = Tk.

5,395.00 551.95 5,500.00 700.00 50.00

- 160 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

B. C.

Labour, machinery, fuel and lubricant for casting Cost of shuttering Assuming 8'-0" x 8'-0" Base (D= 21", d=15") Volume of concrete: 8'-0" x 8'-0" x 1'-6" (approx.)= 96 cft.

Same as item No. 41(a)

Total (A) = Tk. = Tk.

12,196.95 1,022.50

(a) 1.5" x 1.5" x 1/4" M.S. angle for frame: 2 x 2 x 8'-0= 2 x 2 x 8'-3"= 2 x 4 x 1'-3"= Add 5% wastage= @ 2.34 Ibs per rft =

32.00 33 10.00 75.00 3.75 78.75 184.28

rft. rft. rft. rft. rft. rft. Ibs. rft. rft. rft. Ibs. sft. sft. sft. sft. sft. Ibs. sft. kg.

Tk.

8.71 Per Ib.

= Tk.

1,605.08

(b) 1.5" x 1/4" F.I. bar for stiffner (9" c/c) in frame : 4 x 5 x 1'-3"= 25.00 Add 5% wastage= 1.25 26.25 @ 1.70 Ibs per rft.= 44.625 (c) 1/12" thick steel plate to cover frame: 2 x 8'-0"x 1'-3"= 20.00 2 x 8'-3" x 1'-3"= 20.625 40.63 Add 5% wastage= 2.03 42.66 @ 3.4 Ibs per sft = 145.044 (d) Fabrication cost for steel shutter: 40.63 (e) Cost of nuts, bolts, J-hook etc. 1

Tk.

7.71 Per Ib.

= Tk.

344.06

@ @ @

Tk. Tk. Tk.

Per Ib. Per sft. Per kg. Total Considering use for 16 times

10.85 30.00 60.00

= = = = =

Tk. Tk. Tk. Tk. Tk.

1,573.73 1,218.90 60.00 4,801.77 300.11

(f) Labour cost for fitting fixing steel shutter and props in position and removing after concreting etc. 40.63 sft. (g) Hessian for water-tight for 40.63 sft. (h) Cost for support against sides:

@ @

Tk. Tk.

6.00 0.50

Per sft. = Tk. Per sft. = Tk.

243.78 20.32 50.00 614.21 639.80

L.S. = Tk. Grand total = Tk. Cost for per % cft. = Tk. Abstract of cost for 100 cft. of work

(A) Cost of concrete (B) Labour, machinery, fuel and lubricant for casting (C) Cost of shuttering Contractor's profit Overhead expenses
- 161 -

= = = Total = 10.00% = 3.50% =

Tk. 12,196.95 Tk. 1,022.50 Tk. 639.80 Tk. 13,859.25 Tk. 1,385.93 Tk. 485.07

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

VAT

4.50% Grand total Rate per cft. Rate per cum.

Tk. 15,730.25 707.86 = Tk. 16,438.11 = Tk. 164.38 = Tk. 5,805.08

= Tk.

Say,

Tk.

5,805 .00 Per cum.

ANALYSIS FOR ITEM NO. 56(b) R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in raft/mat with stone chips using steel shutter and prop Considering 100 cft. of work A. B. C. Cost of concrete: Labour, machinery, fuel and lubricant for casting Cost of shuttering Assuming raft/mat: 30'-0" x 30'-0" x 4'-0" Volume of concrete: 30'-0" x 30'-0" x 4'-0"= 3600 cft. Considering panel 6'-0" x 2'-0" = 12 sft. 2 " x 2" x 1/4" angle for frame: 2 x 6'-0"= 12.00 rft. 2 x 2'-0"= 4.00 rft. 16.00 rft. Add 5% wastage= 0.80 rft. 16.80 rft. @ 3.2 Ibs per rft. = 53.76 Ibs 2" x 1/4" F.I. bar 1 x 6'-0"= 6.00 rft. 3 x 2'-0"= 6.00 rft. 12.00 rft. Add 5% wastage= 0.60 rft. 12.60 rft. @ 1.70 Ibs per rft. = 21.42 Ibs. 1/12" thick steel plate 1 x 6'-0" x 2'-0"= 12.00 sft. Add 5% wastage= 0.6 sft. 12.60 sft. @ 3.4 Ibs per sft.= 42.84 Ibs. Fabrication cost of steel shutter: 12.00 sft. Cost of nuts, bolts, J-hooks etc. 1.00 kg.

Same as item No. 56(a) Same as item No. 41(a)

= Tk. = Tk.

12,196.95 1,022.50

(a)

Tk.

8.71

Per Ib. = Tk.

468.25

(b)

Tk.

7.71

Per Ib. = Tk.

165.15

(c)

(d) (e)

@ @ @

Tk. Tk. Tk.

Per Ibs. Per sft. Per kg. Total Considering use for 16 times

10.85 30.00 60.00

= = = = =

Tk. Tk. Tk. Tk. Tk.

464.81 360.00 60.00 1,518.21 94.89

(f) Labour cost for fitting fixing steel shutter and props in position and removing after concreting etc.
- 162 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

1 x 6'-0" x 2'-0"= 12.00 (g) Cost for support against sides: 1.5" dia pipe: 2 x 5'-0"= 10.00 2" x 2" x 1/4"angle: @ 3.19 Ibs per rft. 2 x 3'-0"= 6.00 = 19.14

sft. rft. rft. Ib

@ @

Tk. Tk.

6.00 60.00

Per sft. = Tk. Per rft. = Tk.

72.00 600.00

(h) Hessian for water-tight for

Per Ib = = Considering use for 30 times = 12.00 sft. @ Tk. 0.50 Per sft. = Grand total = Shuttering cost per sft = Shuttering cost for 4 x 30'-0" x 4'-0"=480 sft = Cost per % cft. = Abstract of cost for 100 cft. of work

Tk.

8.71

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

166.71 766.71 25.56 6.00 198.45 16.54 7,939.20 220.53

(A) Cost of concrete (B) Labour, machinery, fuel and lubricant for casting (C) Cost of shuttering

Same as item No. 56(a) Same as item No. 41(a)

Contractor's profit Overhead expenses VAT

= = = Total = 10.00% = 3.50% =

4.50% Grand total Rate per cft. Rate per cum.

=
= = =

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

12,196.95 1,022.50 220.53 13,439.98 1,344.00 470.40 15,254.38 686.45 15,940.83 159.41 5,629.56

Say,

Tk.

5,630 .00 Per cum.

ANALYSIS FOR ITEM NO. 56(c) R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in foundation beam with stone chips using steel shutter and prop Considering 100 cft. of work A. B. C. Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering Assuming size of beam: 20'-0" x 3'-0" x 1'-6" Volume of concrete: 20'-0" x 3'-0" x 1'-6"= 90 cft.

Same as item No. 56(a) Same as item No. 41(a)

= Tk. = Tk.

12,196.95 1,022.50

(a) 2 " x 2" x 1/4" angle for frame: 2 x 2 x 20'-0"= 2 x 3 x 2 x 3'-0"=

80.00 rft. 36.00 rft. 116.00 rft.


- 163 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

(b)

(c)

(d) (e)

5.80 rft. 121.80 rft. @ 3.2 Ibs per rft. = 389.76 Ibs 1.5" x 1/4" F.I. bar for stiffner and tie between side shutter. 2 x 20'-0"= 40.00 rft. 2 x 3 x 6 x 3'-0"= 108.00 rft. 1 x 5 x 1'-10"= 9.20 rft. 157.20 rft. Add 5% wastage= 7.86 rft. 165.06 rft. @ 1.28 Ibs per rft. = 211.28 Ibs. 1/12" thick steel plate for covering steel frame: 2 x 20'-0" x 3'-0"= 120.00 sft. Add 5% wastage= 6 sft. 126.00 sft. @ 3.4 Ibs per sft.= 428.4 Ibs. Fabrication cost of steel shutter: 120.00 sft. Cost of nuts, bolts, J-hooks etc. 4.00 kg.

Add 5% wastage=

Tk.

8.71

Per Ib. = Tk.

3,394.81

Tk.

7.71

Per Ib. = Tk.

1,628.97

@ @ @

Tk. Tk. Tk.

Per Ibs. Per sft. Per kg. Total Considering use for 16 times

10.85 30.00 60.00

= = = = =

Tk. Tk. Tk. Tk. Tk.

4,648.14 3,600.00 240.00 13,511.92 844.50 2,160.00 72.00

(f) 1.5" dia M.S. pipe for propping (for inclined support) 2 x 3 x 6'-0" = 36 rft. (g) Labour cost for fitting fixing steel shutter and props in position and removing after concreting etc. 2 x 20'-0" x 3'-0"= 120.00 sft. Hessian for making shutter water-tight (h) 120.00 sft. (i) Cost for support against sides

60.00 Per rft. = Tk. Considering use for 30 times = Tk.

@ @

Tk. Tk.

6.00 0.50

Per sft. = Tk. Tk. Tk. Tk. Tk.

720.00 60.00 50.00 1,746.50 1,940.56

Per sft. = = Grand total = Cost per % cft. =

Abstract of cost for 100 cft. of work (A) Cost of concrete (B) Labour, machinery, fuel and lubricant for casting (C) Cost of shuttering

Same as item No. 56(a) Same as item No. 41(a)


Contractor's profit Overhead expenses VAT

= = = Total = 10.00% = 3.50% =

4.50% Grand total Rate per cft. Rate per cum.

=
= = =

Tk. 12,196.95 Tk. 1,022.50 Tk. 1,940.56 Tk. 15,160.01 Tk. 1,516.00 Tk. 530.60 Tk. 17,206.61 Tk. 774.30 Tk. 17,980.91 Tk. 179.81 Tk. 6,349.99

Say,

Tk.

6,350 .00 Per cum.

- 164 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

ANALYSIS FOR ITEM NO. 56(d)

R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in Padestals, column, column capitals lift walls and walls with stone chips using steel shutter and prop. Considering 100 cft. of work A. B. C. Cost of concrete: Labour, machinery, fuel and lubricant for casting Cost of shuttering Assuming 10'-0" x 12" x 12" Column Volume of concrete: 10'-0" x 12" x 12"= 10 cft.

Same as item No. 56(a) Same as item No. 41(a)

= Tk. = Tk.

12,196.95 1,022.50

(a) 1.5" x 1.5" x 1/4" angle for frame 4 x 2 x 10'-0"= 2 x 3 x 1'-4"= 2 x 3 x 1'-0"= Add 5% wastage= = 2.34 Ibs per rft = (b) 1.5" x 1/4" F.I. bar for stiffner 2 x 8 x 1'-4"= 2 x 8 x 1'-0"= = Add 5% wastage=

80.00 7.98 6.00 93.98 4.699 98.68 230.91 21.28 16.00 37.28 1.86 39.14 50.10

rft. rft. rft. rft. rft. rft. Ibs. rft. rft. rft. rft. rft. Ibs.

Tk.

8.71

Per Ib. = Tk.

2,011.23

@ 1.28 Ib. per rft= (c) 1/12" thick steel plate for covering frame 2 x 10'-0" x 1'-4"= 26.60 sft. 2 x 10'-0" x 1'-0"= 20.00 sft. 46.60 sft. Add 5% wastage= 2.33 sft. 48.93 sft. @ 3.4 Ibs per sft.= 166.362 Ibs. (d) Fabrication cost of steel shutter: 2 x 10'-0" x 1'-4"= 26.67 sft. 2 x 10'-0" x 1'-0"= 20.00 sft. 46.67 sft. (e) Cost of nuts, bolts, J-hooks etc. 1.5 kg

Tk.

7.71

Per Ib. = Tk.

386.27

Tk.

10.85

Per Ib. = Tk.

1,805.03

@ @

Tk. Tk.

Per sft. Per kg. Total Considering use for 16 times 60.00

30.00 60.00

= = = =

Tk. Tk. Tk. Tk.

1,400.10 90.00 5,692.63 355.79 1,920.00

(f) 1.5" dia M.S. pipe for propping 4 x 8'-0"=

32.00 rft.
- 165 -

Tk.

Per rft. = Tk.

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

(g) Turn-buckle in/c tie-rod

2.00 Nos.

Tk.

(h)

Labour cost for fitting fixing steel shutter and props @ @ Tk. Tk.

each = Tk. Total = Tk. Considering use for 30 times = Tk.

250.00

500.00 2,420.00 80.67

in position and removing after concreting etc. 4 x 10'-0" x 1'-0"= 40.00 sft. (i) Hessian for water-tight for 40.00 sft.

6.00 0.50

Per sft. Per sft. Grand total Cost per % cft.

= = = =

Tk. Tk. Tk. Tk.

240.00 20.00 696.46 6,964.60

Abstract of cost for 100 cft. of work (A) Cost of concrete (B) Labour, machinery, fuel and lubricant for casting (C) Cost of shuttering Contractor's profit Overhead expenses VAT (a) Below plinth level and in ground floor = = = Total = 10.00% = 3.50% = 4.50% Grand total Rate per cft. Rate per cum. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. 12,196.95 1,022.50 6,964.60 20,184.05 2,018.41 706.44 22,908.90 1,030.90 23,939.80 239.40 8,454.41

=
= = =

Say,
(b) (c) (d) Add for each addl. floor upto 5th floor: @ 1.25 Nos. lab. per % cft. in/c charges

Tk.

8,454 .00 Per cum.


Per cum = Tk. Per cum = Tk. Per cum = Tk. 52.36 73.30 83.77

Add for each addl. floor from 6th floor to 9th floor: @ 1.75 Nos. lab. per % cft. in/c charges Add for each addl. floor for 10th floor & above: @ 2.0 Nos. lab. per % cft. in/c charges

ANALYSIS FOR ITEM NO. 56(e) R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in beams and lintels with stone chips using steel shutter and prop. Considering 100 cft. of work A. B. C. Cost of concrete: Labour, machinery, fuel and lubricant for casting Cost of shuttering Assuming 10'-0" x 10" x 9" lintels or tie beams Volume of concrete: 10'-0" x 10" x 9"= 6.25 cft. 1.5" x 1.5" x 3/16 angle for frame

Same as item No. 56(a) Same as item No. 41(a)

= Tk. = Tk.

12,196.95 1,022.50

(a)

- 166 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

2 x 2 x 10'-0"= 25% x 2 x 10'-0"= 2 x 2 x 2 x 10"= Add 5% wastage @ 1.79 Ibs per rft.= 1.5" x 3/16" F.I. bar for stiffner 2 x 6 x 10"= 1 x 2 x 1'-1"= Tie: 1 x 3 x 1-1"= Add 5% wastage= @ 0.956 Ibs per rft.= 1/12" thick steel plate (@ 3.4 Ibs per sft.) 2 x 10'-0" x 10"= 25% x 10'-0" x 1'-1"= Add wastage 5%= = (d) (e) Cost of nuts, bolts, J-hooks etc. Fabrication cost of steel shutter

40.00 5.00 6.67 51.67 2.58 54.25 97.11 10.00 2.17 3.25 15.42 0.771 16.19 15.48 16.67 2.7 19.37 0.97 20.34 69.16 1.00 19.37

rft. rft. rft. rft. rft. rft. Ibs. rft. rft. rft. rft. rft. rft. Ibs. sft. sft. sft. sft. sft. Ibs. kg. sft.

Tk.

8.71 Per Ib.

= Tk.

845.83

(b)

Tk.

7.71 Per Ib.

= Tk.

119.35

(c)

@ @ @

Tk. Tk. Tk.

Per Ib. Per kg. Per sft. Total Considering use for 16 times

10.85 60.00 30.00

= = = = =

Tk. Tk. Tk. Tk. Tk.

750.39 60.00 581.10 2,356.67 147.29 840.00 28.00

(f)

1.5" dia M.S. pipe for propping: 2 x 7'-0"=

14 rft.

Tk.

60.00 Per rft. = Tk. Considering use for 30 times = Tk.

(g)

(i)

Labour cost for fitting fixing steel shutter and props in position and removing after concreting etc. 2 x 10'-0" x 10"= 16.67 sft. 25% x 10'-0" x 10"= 2.083 sft. 18.75 sft. Hessian for water-tight for 18.75 sft.

@ @

Tk. Tk.

6.00 0.50

Per sft. Per sft. Grand total Cost per % cft.

= = = =

Tk. Tk. Tk. Tk.

112.50 9.38 297.17 4,754.72

Abstract of cost for 100 cft. of work (A) Cost of concrete (B) Labour, machinery, fuel and lubricant for casting (C) Cost of shuttering Contractor's profit Overhead expenses VAT
- 167 -

= = = Total = 10.00% = 3.50% =

Tk. 12,196.95 Tk. 1,022.50 Tk. 4,754.72 Tk. 17,974.17 Tk. 1,797.42 Tk. 629.10 Tk. 20,400.69 4.50% = Tk. 918.03

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

(a) Below plinth level and in ground floor

Grand total = Tk. Rate per cft. = Tk. Rate per cum. = Tk. Say, Tk. 7,529 .00 Per cum.
Per cum = Tk. Per cum = Tk. Per cum = Tk.

21,318.72 213.19 7,528.80

(b) (c) (d)

Add for each addl. floor upto 5th floor: @ 1.25 Nos. lab. per % cft. in/c charges Add for each addl. floor from 6th floor to 9th floor: @ 1.75 Nos. lab. per % cft. in/c charges Add for each addl. floor for 10th floor & above: @ 2.0 Nos. lab. per % cft. in/c charges

52.36 73.30 83.77

ANALYSIS FOR ITEM NO. 56(f) R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in Tee beams, Ell beams and Rectangular beams with stone chips using steel shutter and prop. Considering 100 cft. of work A. B. C. Cost of concrete: Labour, machinery, fuel and lubricant for casting Cost of shuttering Assuming 20'-0" x 1'-6" x 1'-0" beams Volume of concrete: 30 cft.

Same as item No. 56(a) Same as item No. 41(a)

= Tk. = Tk.

12,196.95 1,022.50

(a) 1.5" x 1.5" x 1/4" M.S. angle for frame 2 x 3 x 20'-0" = 2 x 3 x 2 x 1'-6"= 1 x 3 x 2 x 1'-4"= Add 5% wastage= = @ 2.34 Ibs per rft.= (b) 1.5" x 1/4" F.I. bar for stiffner and tie: 1 x 2 x 20'-0"= 2 x 3 x 4 x 1'-6"= 1 x 3 x 6 x 1'-4"= 6 x 1'-4"= Add 5% wastage= = @ 1.28 Ibs per rft.= (c) 1/12" steel plate for covering frame 2 x 20'-0" x 1'-6"= 1 x 20'-0" x 1'-4"=

120 18 7.98 145.98 7.30 153.28 358.68 40.00 36.00 23.94 7.98 107.92 5.40 113.32 145.05

rft. rft. rft. rft. rft. rft. Ibs. rft. rft. rft. rft. rft. rft. rft. Ibs.

Tk.

8.71

Per Ib. = Tk.

3,124.10

Tk.

7.71

Per Ib. = Tk.

1,118.34

60.00 sft. 26.60 sft. 86.60 sft.


- 168 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

Add 5% wastage= @ 3.40 Ibs per sft. (d) Fabrication cost for steel shutter: (e) Cost of nuts, bolts, J-hooks etc.

4.33 90.93 309.16 86.60 4

sft. sft. Ibs sft. kg.

@ @ @

Tk. Tk. Tk.

Per Ib. Per sft. Per kg. Total Considering use for 16 times

10.85 30.00 60.00

= = = = =

Tk. 3,354.39 Tk. 2,598.00 Tk. 240.00 Tk. 10,434.83 Tk. 652.18

(f) Props: (10 Nos.) (i) 2" dia M.S. pipe: 1 x 7'-0"= (ii) 1.5" dia M.S. pipe: 1 x 7'-0"=

7.00 rft. 7.00 rft. (iii) Adjustable mechanism in/c top and bottom plates: 1.00 No.

@ @

Tk. Tk. Tk.

80.00 60.00 320.00

Per rft. = Tk. Per rft. = Tk. = = = = =

560.00 420.00

each Total Cost for 10 Nos. prop Sub-Total Considering use for 30 times

Tk. 320.00 Tk. 1,300.00 Tk. 13,000.00 Tk. 14,300.00 Tk. 476.67

(g) Labour cost for fitting fixing steel shutter and props in position and removing after concreting etc.: 2 x 20'-0" x 1'-6"= 60.00 sft. 1 x 20'-0" x 1'-0"= 20.00 sft. = 80.00 sft. (h) Hessian for water-tight for 80.00 sft.

@ @

Tk. Tk.

6.00 0.50

Per sft. Per sft. Grand total Cost per % cft.

= = = =

Tk. Tk. Tk. Tk.

480.00 40.00 1,648.85 5,496.17

Abstract of cost for 100 cft. of work (A) Cost of concrete (B) Labour, machinery, fuel and lubricant for casting (C) Cost of shuttering Contractor's profit Overhead expenses VAT (a) Below plinth level and in ground floor = = = Total = 10.00% = 3.50% = 4.50% Grand total Rate per cft. Rate per cum. Tk. 12,196.95 Tk. 1,022.50 Tk. 5,496.17 Tk. 18,715.62 Tk. 1,871.56 Tk. 655.05 Tk. 21,242.23 Tk. 955.90 Tk. 22,198.13 Tk. 221.98 Tk. 7,839.22

=
= = =

Say,
(b) (c) (d) Add for each addl. floor upto 5th floor: @ 1.25 Nos. lab. per % cft. in/c charges

Tk.

7,839 .00 Per cum.


Per cum = Tk. Per cum = Tk. Per cum = Tk. 52.36 73.30 83.77

Add for each addl. floor from 6th floor to 9th floor: @ 1.75 Nos. lab. per % cft. in/c charges Add for each addl. floor for 10th floor & above: @ 2.0 Nos. lab. per % cft. in/c charges

- 169 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

ANALYSIS FOR ITEM NO. 56(g) R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in floor and roof slab with stone chips using steel shutter and prop. Considering 100 cft. of work A. B. C. Cost of concrete: Labour, machinery, fuel and lubricant for casting Cost of shuttering Assuming 20'-0 x 16'-0" x 6" Slabs Volume of Concrete: 20'-0" x 16'-0" x 5"= 133.33 cft.

Same as item No. 56(a) Same as item No. 41(a)

= Tk. = Tk.

12,196.95 1,022.50

4" x 2" Steel box channel with 1/8" thick steel plate: Break-up for 20 rft. steel box channel: (i) 1/8" thick steel plate: 20'-0" x 2 (4"+2")= 20.00 sft. Add 5% wastage= 1.00 sft. = 21.00 sft. @ 5.10 Ibs per sft.= 107.10 Ibs. (ii) Cutting and bending: 20.00 rft. (iii) Welding and grinding: 20.00 rft.

@ @ @

Per Ib. Per rft. Per rft. Total Cost of per rft. of box channel. Say, Tk. 74 .00 per rft.

Tk. Tk. Tk.

10.85 3.00 12.50

= = = = =

Tk. Tk. Tk. Tk. Tk.

1,162.04 60.00 250.00 1,472.04 73.60

(a) 1/12" thick steel plate: (3.4 Ibs per sft.) 1 x 20'-0" x 16'-0"= Add 5% wastage= = (b)

320.00 16.00 336.00 1142.40

sft. sft. sft. Ibs.

Tk.

10.85 Per Ib. = Tk. 12,395.04 Considering use for 16 times = Tk. 774.69

4" x 2" steel box channel under steel plate: 1" c/c in long direction and below 2'-0" c/c in short direction 18 x 21'-0"= 378.00 rft. 11 x 17'-0"= 187.00 rft. 565.00 rft.

Tk.

74.00 Per rft. = Tk. 41,810.00 Considering use for 30 times = Tk. 1,393.67

(c) Steel shutter around roof slab: (i) 1" x 1" x 1/8" angle for frame 2 x 20'-2"=

40.33 rft.

- 170 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

2 x 16'-0"= 4 x 2 x 5"= Add 5% wastage= @ 0.8 Ibs per rft.= (ii) 1/8" F.I. bar for stiffner 2 x 11'-0"= 2 x 12'-0"= Add 5% wastage= @ 0.425 Ibs per rft.= (iii) 1/12" steel plate to cover frame 2 x 20'-2" x 5" = 2 x 16'-0" x 5" =

32.00 3.33 75.66 3.78 79.44 63.55 22.00 24.00 46.00 2.30 48.30 20.53

rft. rft. rft. rft. rft. Ibs. sft. sft. sft. rft. rft. Ibs. sft. sft. sft. sft. sft. Ibs. sft. kg.

Tk.

8.71

Per Ib. = Tk.

553.52

Tk.

7.71

Per Ib. = Tk.

158.29

16.81 13.33 30.14 Add 5% wastage= 1.51 31.65 @ 3.4 Ibs per sft.= 107.61 (iv) Fabrication steel shutter for around slab: 30.14 (d) Cost of nuts, bolts, J- hooks etc. 12.00

@ @ @

Tk. Tk. Tk.

10.85 30.00 60.00

Per Ib. = Tk. = = = = Tk. Tk. Tk. Tk.

1,167.57 904.20 720.00 3,503.58 218.97 560.00 420.00 320.00 1,300.00

Per sft. Per kg. Total Considering use for 16 times

(e) Props: (88 Nos.) (i) 2" dia M.S. pipe: 1 x 7'-0"= (ii) 1.5" dia M.S. pipe: 1 x 7'-0"=

7.00 rft. Tk. 80.00 Per rft. 7.00 rft. @ Tk. 60.00 Per rft. (iii) Adjustable mechanism in/c top and bottom plates and locking arrangements etc.: 1.00 No. @ Tk. 320.00 each Total for 1 set complete prop.

= Tk. = Tk. = Tk. = Tk.

Cost for 88 Nos. prop = Tk. 114,400.00 (g) 2" dia M.S. pipe for cross bracing: 9 x 18'-0"= 162.00 rft. @ Tk. 80.00 Per rft. = Tk. 12,960.00 Sub-total = Tk. 127,360.00 Considering use for 30 times = Tk. 4,245.33 (h) Labour cost for fitting fixing steel shutter and props in position and removing etc.: 20'-0" x 16'-0"= 320.00 sft. 2 x (20'-0" + 16'-0") x 5"= 30.00 sft. = 350.00 sft. (i) Hessian tap for making shutter water-tight 350.00 sft.

@ @

Tk. Tk.

6.00 0.50

Per sft. = Tk.

2,100.00 175.00 8,907.66 6,680.91

Per sft. = Tk. Grand total = Tk. Cost per % cft. = Tk.

- 171 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

Abstract of cost for 100 cft. of work (A) Cost of concrete (B) Labour, machinery, fuel and lubricant for casting (C) Cost of shuttering Contractor's profit Overhead expenses VAT (a) Below plinth level and in ground floor = = = Total = 10.00% = 3.50% = 4.50% Grand total Rate per cft. Rate per cum. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. 12,196.95 1,022.50 6,680.91 19,900.36 1,990.04 696.51 22,586.91 1,016.41 23,603.32 236.03 8,335.40

=
= = =

Say,
(b) (c) (d) Add for each addl. floor upto 5th floor: @ 1.25 Nos. lab. per % cft. in/c charges

Tk.

8,335 .00 Per cum.


Per cum = Tk. Per cum = Tk. Per cum = Tk. 52.36 73.30 83.77

Add for each addl. floor from 6th floor to 9th floor: @ 1.75 Nos. lab. per % cft. in/c charges Add for each addl. floor for 10th floor & above: @ 2.0 Nos. lab. per % cft. in/c charges

ANALYSIS FOR ITEM NO. 56(h) R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in sunshade, cornice, railing, drop walls etc for all floors etc. (av. 3" thick) with stone chips using steel shutter and prop. Considering 100 cft. of work A. B. C. Cost of concrete: Labour, machinery, fuel and lubricant for casting Cost of shuttering Assuming 10'-0" x 3'-0"= 30 sft. sun-shade Volume of concrete: 10'-0" x 3'-0" x 3"= 7.5 cft. 1.5" x 1.5" x 3/16" M.S. angle for frame (a) 2 x 10'-3"= 20.50 rft. 2 x 2 x 3'-1.5"= 12.50 rft. 33.00 rft. Add 5% wastage= 1.65 rft. = 34.65 rft. @ 1.79 Ibs per rft= 62.02 Ibs. (b) 1.5" x 3/16" F.I. bar for stiffner: 2 x 10'-3"= 20.50 rft. 2 x 3 x 0'-3"= 1.50 rft. = 22.00 rft. Add 5% wastage= 1.10 rft.
- 172 -

Same as item No. 56(a) Same as item No. 41(a)

= Tk. = Tk.

12,196.95 1,022.50

Tk.

8.71

Per Ibs. = Tk.

540.19

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

= @ 0.96 Ibs per rft.= (c) 1/12" thick steel plate 1 x 10'-0" x 3'-0"= Add 5% wastage= @ 3.4 Ibs per sft.= (d) Fabrication steel shutter: (e) Cost of nuts, bolts, J- hooks etc.

23.10 rft. 22.18 Ibs. 30.00 1.50 31.50 107.10 30.00 0.50 sft. sft. sft. Ibs. sft. kg

Tk.

7.71

Per Ibs. = Tk.

171.01

@ @ @

Tk. Tk. Tk.

Per Ibs. Per sft. Per kg. Total Considering use for 16 times

10.85 30.00 60.00

= = = = =

Tk. Tk. Tk. Tk. Tk.

1,162.04 900.00 30.00 2,803.24 175.20

(f) Wooden side shutter: 1 x 10'-0" x 3" x 1.5"= 2 x 3'-1.5" x 3" x 1.5"= = Add 5% wastage= 4" x 2" box channel under steel (g) shutter 4 x 4'-0"=

0.31 0.20 0.51 0.03 0.54

cft. cft. cft. cft. cft.

@ Tk. 360.00 Considering use for 6 times @ Tk.

Per cft. = Tk. 32.40

16 rft.

74.00 Per rft. = Tk. 39.47

Considering use for 30 times (h) 2"/1.5" dia M.S. props in/c adjustable mechanism with top and bottom plate etc. 4 Nos. Considering use for 30 times (i) Labour for fitting and fixing steel shutter & props in position as required.: 1 x 10'-0" x 3'-0"= 30.00 sft. (3'-0" + 10'-0" + 3'-0") x 3"= 4.00 sft. 34.00 sft. (j) Hessian tap for making shutter water-tight 34.00 sft. @ Tk. 1,300.00 each

= Tk.

173.33

@ @

Tk. Tk.

6.00 0.50

Per sft. = Tk.

204.00 17.00 641.40 8,552.00

Per sft. = Tk. Total of (C) = Tk. Cost per % cft. = Tk.

Abstract of cost for 100 cft. of work (A) Cost of concrete (B) Labour, machinery, fuel and lubricant for casting (C) Cost of shuttering Tk. 12,196.95 Tk. 1,022.50 Tk. 8,552.00 Tk. 21,771.45 Contractor's profit Tk. 2,177.15 Overhead expenses Tk. 762.00 Tk. 24,710.60 VAT 4.50% = Tk. 1,111.98 Grand total = Tk. 25,822.58 Rate per cft. = Tk. 258.23 = = = Total = 10.00% = 3.50% =

- 173 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

Rate per sft. = Tk. (a) Below plinth level and in ground floor Say, Tk. Per sqm = Tk. 695 .00 Per sqm.

64.56 694.92

(b) (c) (d)

Add for each addl. floor upto 5th floor: @ 1/12 No. lab. per sqm in/c charges Add for each addl. floor from 6th floor to 9th floor: @ 1/8 No. lab. per sqm in/c charges Add for each addl. floor for 10th floor & above: @ 1/6 No. lab. per sqm in/c charges

Per sqm. = Tk. Per sqm. = Tk. Per sqm. = Tk.

9.88 14.83 19.77

ANALYSIS FOR ITEM NO. 56(i) R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in stair case slab and steps with stone chips using steel shutter and prop. Considering 100 cft. of work A. B. C.

Same as item No. 56(a) Cost of concrete: Labour, machinery, fuel and lubricant for casting Same as item No. 41(a) Cost of shuttering Assuming 8'-9" long & 4'-0" wide stair Volume of concrete: 8'- 9" x 4'-0" x 0'-6" = 17.50 cft. 1/2 x 9 x 4'-0" x 0'-10" x 0'-6" = 7.56 cft. = 25.06 cft. (a) 1.5" x 1.5" x 1/4" M.S. angle for frame for slab and sides: 1 x 8 x 8'-9"= 70.00 rft. 1 x 5 x 4'-4"= 21.65 rft. 2 x 2 x 1'-0"= 4.00 rft. = 95.65 rft. Add 5% wastage= 4.78 rft. = 100.43 rft. @ 2.34 Ibs per rft.= 235.01 Ibs. @ Tk. 8.71 Per Ib. (b) 1" x 1" x 1/8" M.S. angle for steps: 9 x 2 x 4'-0"= 72.00 rft. 9 x 2 x 6"= 9.00 rft. 2 x 9 x 1'-0" = 18.00 rft. = 99.00 rft. Add 5% wastage= 4.95 rft. = 103.95 rft. @ 0.8 Ibs per rft = 83.16 Ibs. @ Tk. 8.71 Per Ib. (c) 1.5" x 1/4" thick F.I. bar for stiffner and tie for frame for slab and side: Stiffner: 5 x 8'-9"= 43.75 rft. 7 x 4'-4"= 30.31 rft. 2 x 7 x 1'-0" = 14.00 rft. Tie between two sides: 2 x 4'-4" = 8.67 rft.
- 174 -

= Tk. = Tk.

12,196.95 1,022.50

= Tk.

2,046.94

= Tk.

724.32

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

96.73 rft. 4.84 rft. 101.57 rft. @ 1.28 Ibs per rft.'= 130.01 Ibs. (d) 1" x 1/8" F.I. bar for stiffner for frame for steps: 9 x 1 x 6"= 4.5 rft. Add 5% wastage= 0.23 rft. = 4.73 rft. (@ 0.425 Ibs per rft.)= 2.01 Ibs. (e) 1/12" thick steel plate for covering frame: 1 x 8'-9" x 4'-4"= 37.89 sft. 2 x 8'-9" x 1'-0"= 17.50 sft. 9 x 4'-0" x 6"= 18.00 sft. = 73.39 sft. Add 5% wastage= 3.6695 sft. = 77.06 sft. @ 3.4 Ibs. per rft.= 262.00 Ibs. (f) Cost of nut, bolts, J-hooks etc. 2.5 kg (g) Cost for fabrication of steel shutter: 73.39 sft. Add 5% wastage=

Tk.

7.71

Per Ib. = Tk.

1,002.38

Tk.

7.71

Per Ib. = Tk.

15.50

@ @ @

Tk. Tk. Tk.

Per Ib. Per kg. Per sft. Total Considering use for 16 times

10.85 60.00 30.00

= = = = =

Tk. Tk. Tk. Tk. Tk.

2,842.70 150.00 2,201.70 8,983.54 561.47

(h) 2"/1.5" dia M.S props in/c adjustable mechanism with top and bottom plate and locking arrangement etc.: 8 Nos. (i) 1.5" x 1.5" x 1/4" M.S. angle as cross bar: 4 x 5'-0"= 20.00 rft. Add 5% wastage= 1.00 rft. 21.00 rft. @ 2.34 Ib per rft = 49.14 Ibs. (j) Labour cost for fitting fixing steel shutter and props in position and removing etc.: 1 x 8'-9" x 4'-0"= 35.00 sft. 2 x 8'-9" x 1'-0"= 17.50 sft. 9 x 4'-0" x 6"= 18.00 sft. = 70.50 sft. (k) Hessian for water-tight for 70.50 sft.

Tk.

1,300.00

each = Tk. 10,400.00

Tk.

Per Ib. = Tk. Total = Tk. Considering use for 30 times = Tk.

8.71

428.01 10,828.01 360.93

@ @

Tk. Tk.

6.00 0.50

Per sft. Per sft. Grand total Cost per % cft.

= = = =

Tk. Tk. Tk. Tk.

423.00 35.25 1,380.65 5,509.38

Abstract of cost for 100 cft. of work (A) Cost of concrete (B) Labour, machinery, fuel and lubricant for casting (C) Cost of shuttering
- 175 -

= Tk. 12,196.95 = Tk. 1,022.50 = Tk. 5,509.38

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

(a) Below plinth level and in ground floor

Total = Tk. 18,728.83 Contractor's profit 10.00% = Tk. 1,872.88 Overhead expenses 3.50% = Tk. 655.51 Tk. 21,257.22 VAT 4.50% = Tk. 956.57 Grand total = Tk. 22,213.79 Rate per cft. = Tk. 222.14 Rate per cum. = Tk. 7,844.87 Say, Tk. 7,845 .00 Per cum.
Per cum = Tk. Per cum = Tk. Per cum = Tk. 52.36 73.30 83.77

(b) (c) (d)

Add for each addl. floor upto 5th floor: @ 1.25 Nos. lab. per % cft. in/c charges Add for each addl. floor from 6th floor to 9th floor: @ 1.75 Nos. lab. per % cft. in/c charges Add for each addl. floor for 10th floor & above: @ 2.0 Nos. lab. per % cft. in/c charges

ANALYSIS FOR ITEM NO. 56(j) R.C.C work (1:1.5:3) complete excluding the cost of reinforcement and its fabrication in Waffle and ribbed floor or floor slab with stone chips using steel shutter and prop. Considering 100 cft. of work A. B. C. Cost of concrete: Labour, machinery, fuel and lubricant for casting Cost of shuttering

Same as item No. 56(a) Same as item No. 41(a) Same as item No. 46
Contractor's profit Overhead expenses VAT

= = = Total = 10.00% = 3.50% =

(a) Below plinth level and in ground floor

4.50% Grand total Rate per cft. Rate per cum.

=
= = =

Tk. 12,196.95 Tk. 1,022.50 Tk. 12,510.71 Tk. 25,730.16 Tk. 2,573.02 Tk. 900.56 Tk. 29,203.74 Tk. 1,314.17 Tk. 30,517.91 Tk. 305.18 Tk. 10,777.43

Say,
(b) (c) (d) Add for each addl. floor upto 5th floor: @ 1.25 Nos. lab. per % cft. in/c charges

Tk.

10,777 .00 Per cum.


Per cum = Tk. Per cum = Tk. Per cum = Tk. 52.36 73.30 83.77

Add for each addl. floor from 6th floor to 9th floor: @ 1.75 Nos. lab. per % cft. in/c charges Add for each addl. floor for 10th floor & above: @ 2.0 Nos. lab. per % cft. in/c charges

- 176 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

ANALYSIS FOR ITEM NO. 56 M32(a) Reinforced cement concrete works in 1:1.25:2.5 (high strength concrete) with approved high range admixture excluding the cost of reinforcement and its fabrication, in individual and continuous footings of column, at plinth level with stone chips using steel shutter and prop (excluding cost of admixure and mix design). Break-up for 100 cft. A. Cost of materials (a) 19 mm down well graded crushed stone chips 80 cft. (b) Well graded Sylhet sand (F.M. 2.5) 40 cft. (c) Cement 25.25 bags (d) Local carriage, sundries, T & P (e) Labour 28 days curring: @ 1/4 No. labour per day. 7 Nos. B. C. Labour, machinery, fuel and lubricant for casting Cost of shuttering

@ @ @

Tk. Tk. Tk.

6,500.00 1,330.00 250.00

Per % cft. Per % cft. Per bag L.S.

= = = =

Tk. Tk. Tk. Tk.

5,200.00 532.00 6,312.50 50.00

Tk.

each = Tk. 700.00 Tk. 12,794.50 Same as item No. 41(a) = Tk. 1,022.50 Same as item No 56(a) = Tk. 639.80 Total = Tk. 14,456.80 Contractor's profit 10.00% = Tk. 1,445.68 Overhead expenses 3.50% = Tk. 505.99 Tk. 16,408.47 VAT 4.50% = Tk. 738.38 Grand total = Tk. 17,146.85 Rate per cft. = Tk. 171.47 Rate per cum. = Tk. 6,055.46 Tk. 6,055 .00 Per cum.

100.00

Say,

ANALYSIS FOR ITEM NO. 56 M32(b) Reinforced cement concrete works in 1:1.25:2.5 (high strength concrete) with approved high range admixture excluding the cost of reinforcement and its fabrication, in raft/mat with stone chips using steel shutter.

(excluding cost of admixure and mix design).


Considering 100 cft. of work A. B. C. Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering

Same as item No. 56 M32(a) Same as item No. 41(a) Same as item No. 56(b)

= = = Total =

Tk. 12,794.50 Tk. 1,022.50 Tk. 220.53 Tk. 14,037.53

- 177 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

Contractor's profit Overhead expenses

10.00% = Tk. 1,403.75 3.50% = Tk. 491.31 Tk. 15,932.59 VAT 4.50% = Tk. 716.97 Grand total = Tk. 16,649.56 Rate per cft. = Tk. 166.50 Rate per cum. = Tk. 5,879.95 5,880 .00 Per cum.

Say,

Tk.

ANALYSIS FOR ITEM NO. 56 M32(c) Reinforced cement concrete works in 1:1.25:2.5 (high strength concrete) with approved high range admixture excluding the cost of reinforcement and its fabrication, in foundation beam with stone chips using steel shutter.

(excluding cost of admixure and mix design).


Considering 100 cft. of work A. B. C. Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering

Same as item No. 56 M32(a) Same as item No. 41(a) Same as item No. 56(c)
Contractor's profit Overhead expenses VAT

= = = Total = 10.00% = 3.50% =

4.50% Grand total Rate per cft. Rate per cum.

=
= = =

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

12,794.50 1,022.50 1,940.56 15,757.56 1,575.76 551.51 17,884.83 804.82 18,689.65 186.90 6,600.37

Say,

Tk.

6,600 .00 Per cum.

ANALYSIS FOR ITEM NO. 56 M32(d) Reinforced cement concrete works in 1:1.25:2.5 (high strength concrete) with approved high range admixture excluding the cost of reinforcement and its fabrication, in Padestals, column, column capitals, lift walls and walls with stone chips using steel shutter. (excluding cost of admixure and mix design). Considering 100 cft. of work A. B. C. Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering

Same as item No. 56 M32(a) Same as item No. 41(a) Same as item No. 56(d)

= = = Total =

Tk. 12,794.50 Tk. 1,022.50 Tk. 6,964.60 Tk. 20,781.60

- 178 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

Contractor's profit Overhead expenses

(a) Below plinth level and in ground floor

10.00% = Tk. 2,078.16 3.50% = Tk. 727.36 Tk. 23,587.12 VAT 4.50% = Tk. 1,061.42 Grand total = Tk. 24,648.54 Rate per cft. = Tk. 246.49 Rate per cum. = Tk. 8,704.79 8,705 .00 Per cum.
Per cum = Tk. Per cum = Tk. Per cum = Tk. 52.36 73.30 83.77

Say,
(b) (c) (d) Add for each addl. floor upto 5th floor: @ 1.25 Nos. lab. per % cft. in/c charges

Tk.

Add for each addl. floor from 6th floor to 9th floor: @ 1.75 Nos. lab. per % cft. in/c charges Add for each addl. floor for 10th floor & above: @ 2.0 Nos. lab. per % cft. in/c charges

ANALYSIS FOR ITEM NO. 56 M32(e) Reinforced cement concrete works in 1:1.25:2.5 (high strength concrete) with approved high range admixture excluding the cost of reinforcement and its fabrication, in tie beams with stone chips using steel shutter.

(excluding cost of admixure and mix design).


Considering 100 cft. of work A. B. C. Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering

Same as item No. 56 M32(a) Same as item No. 41(a) Same as item No. 56(e)
Contractor's profit Overhead expenses VAT

= = = Total = 10.00% = 3.50% =

(a) Below plinth level and in ground floor

4.50% Grand total Rate per cft. Rate per cum.

=
= = =

Tk. 12,794.50 Tk. 1,022.50 Tk. 4,754.72 Tk. 18,571.72 Tk. 1,857.17 Tk. 650.01 Tk. 21,078.90 Tk. 948.55 Tk. 22,027.45 Tk. 220.27 Tk. 7,778.84

Say,
(b) (c) (d) Add for each addl. floor upto 5th floor: @ 1.25 Nos. lab. per % cft. in/c charges

Tk.

7,779 .00 Per cum.


Per cum = Tk. Per cum = Tk. Per cum = Tk. 52.36 73.30 83.77

Add for each addl. floor from 6th floor to 9th floor: @ 1.75 Nos. lab. per % cft. in/c charges Add for each addl. floor for 10th floor & above: @ 2.0 Nos. lab. per % cft. in/c charges

ANALYSIS FOR ITEM NO. 56 M32(f)

- 179 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

Reinforced cement concrete works in 1:1.25:2.5 (high strength concrete) with approved high range admixtureexcluding the cost of reinforcement and its fabrication, in Tee beams Ell beams and Rectangular beams with stone chips using steel shutter. (excluding cost of admixure and mix design). Considering 100 cft. of work A. B. C. Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering

Same as item No. 56 M32(a) Same as item No. 41(a) Same as item No. 56(f)
Contractor's profit Overhead expenses VAT

= = = Total = 10.00% = 3.50% =

(a) Below plinth level and in ground floor

4.50% Grand total Rate per cft. Rate per cum.

=
= = =

Tk. 12,794.50 Tk. 1,022.50 Tk. 5,496.17 Tk. 19,313.17 Tk. 1,931.32 Tk. 675.96 Tk. 21,920.45 Tk. 986.42 Tk. 22,906.87 Tk. 229.07 Tk. 8,089.61

Say,
(b) (c) (d) Add for each addl. floor upto 5th floor: @ 1.25 Nos. lab. per % cft. in/c charges

Tk.

8,090 .00 Per cum.


Per cum = Tk. Per cum = Tk. Per cum = Tk. 52.36 73.30 83.77

Add for each addl. floor from 6th floor to 9th floor: @ 1.75 Nos. lab. per % cft. in/c charges Add for each addl. floor for 10th floor & above: @ 2.0 Nos. lab. per % cft. in/c charges

ANALYSIS FOR ITEM NO. 56 M32(g) Reinforced cement concrete works in 1:1.25:2.5 (high strength concrete) with approved high range admixture excluding the cost of reinforcement and its fabrication in floor and roof slab with stone chips using steel shutter.

(excluding cost of admixure and mix design).


Considering 100 cft. of work A. B. C. Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering

Same as item No. 56 M32(a) Same as item No. 41(a) Same as item No. 56(g)
Contractor's profit Overhead expenses VAT

= = = Total = 10.00% = 3.50% =

(a) Below plinth level and in ground floor

4.50% Grand total Rate per cft. Rate per cum.

=
= = =

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

12,794.50 1,022.50 6,680.91 20,497.91 2,049.79 717.43 23,265.13 1,046.93 24,312.06 243.12 8,585.78

Say,

Tk.

8,586 .00 Per cum.

- 180 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

(b) (c) (d)

Add for each addl. floor upto 5th floor: @ 1.25 Nos. lab. per % cft. in/c charges Add for each addl. floor from 6th floor to 9th floor: @ 1.75 Nos. lab. per % cft. in/c charges Add for each addl. floor for 10th floor & above: @ 2.0 Nos. lab. per % cft. in/c charges

Per cum = Tk. Per cum = Tk. Per cum = Tk.

52.36 73.30 83.77

ANALYSIS FOR ITEM NO. 56 M32(h) Reinforced cement concrete works in 1:1.25:2.5 (high strength concrete) with approved high range admixturee excluding the cost of reinforcement and its fabrication in stair case slab and steps with stone chips using steel shutter. (excluding cost of admixure and mix design). Considering 100 cft. of work A. B. C. Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering

Same as item No. 56 M32(a) Same as item No. 41(a) Same as item No. 56(i)
Contractor's profit Overhead expenses VAT

= = = Total = 10.00% = 3.50% =

(a) Below plinth level and in ground floor

4.50% Grand total Rate per cft. Rate per cum.

=
= = =

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

12,794.50 1,022.50 5,509.38 19,326.38 1,932.64 676.42 21,935.44 987.09 22,922.53 229.23 8,095.26

Say,
(b) (c) (d) Add for each addl. floor upto 5th floor: @ 1.25 Nos. lab. per % cft. in/c charges

Tk.

8,095 .00 Per cum.


Per cum = Tk. Per cum = Tk. Per cum = Tk. 52.36 73.30 83.77

Add for each addl. floor from 6th floor to 9th floor: @ 1.75 Nos. lab. per % cft. in/c charges Add for each addl. floor for 10th floor & above: @ 2.0 Nos. lab. per % cft. in/c charges

ANALYSIS FOR ITEM NO. 56 M32(i) Reinforced cement concrete works in 1:1.25:2.5 (high strength concrete ) with approved high range admixtureexcluding the cost of reinforcement and its fabrication in Waffle / Ribbed floor / Roof slab with stone chips using steel shutter. (excluding cost of admixure and mix design). Considering 100 cft. of work. A. B. C. Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering

Same as item No. 56 M32(a) Same as item No. 41(a) Same as item No. 46

= = = Total =

Tk. 12,794.50 Tk. 1,022.50 Tk. 12,510.71 Tk. 26,327.71

- 181 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

Contractor's profit Overhead expenses

(a) Below plinth level and in ground floor

10.00% = Tk. 2,632.77 3.50% = Tk. 921.47 Tk. 29,881.95 VAT 4.50% = Tk. 1,344.69 Grand total = Tk. 31,226.64 Rate per cft. = Tk. 312.27 Rate per cum. = Tk. 11,027.82

Say,
(b) (c) (d) Add for each addl. floor upto 5th floor: @ 1.25 Nos. lab. per % cft. in/c charges

Tk.

11,028 .00 Per cum.


Per cum = Tk. Per cum = Tk. Per cum = Tk. 52.36 73.30 83.77

Add for each addl. floor from 6th floor to 9th floor: @ 1.75 Nos. lab. per % cft. in/c charges Add for each addl. floor for 10th floor & above: @ 2.0 Nos. lab. per % cft. in/c charges

ANALYSIS FOR ITEM NO. 57(a) R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in individual and continuous footings of column at plinth level with stone chips using steel shutter. Considering 100 cft. of work A. Cost of Concrete a) 19 mm down size crushed stone chips 90 b) Sand (F.M. 2.5) 45 c) Cement 18 d) Labour for 28 days curing: @ 1/4 labour per day 7 Local carriage, sundries, T & P e) B. C. cft. cft. bag Nos. @ @ @ @ Tk. Tk. Tk. Tk. 6,500.00 1,330.00 250.00 100.00 Per % cft. = Tk. Per % cft. = Tk. Per bag. = Tk. 5,850.00 598.50 4,500.00

Labour, machinery, fuel and lubricant for casting Cost of shuttering

each = Tk. 700.00 L.S. = Tk. 50.00 Total of A. = Tk. 11,698.50 Same as item No. 41(a) = Tk. 1,022.50 Same as item No. 56(a) = Tk. 639.80 Total = Tk. 13,360.80 Contractor's profit 10.00% = Tk. 1,336.08 Overhead expenses 3.50% = Tk. 467.63 Tk. 15,164.51 VAT 4.50% = Tk. 682.40 Grand total = Tk. 15,846.91 Rate per cft. = Tk. 158.47 Rate per cum. = Tk. 5,596.37 Tk. 5,596 .00 Per cum.

Say,

- 182 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

ANALYSIS FOR ITEM NO. 57(b) R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in raft/mat with stone chips using steel shutter. Considering 100 cft. of work A. B. C. Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering

Same as item No. 57(a) Same as item No. 41(a) Same as item No. 56(b)
Contractor's profit Overhead expenses VAT

= = = Total = 10.00% = 3.50% =

4.50% Grand total Rate per cft. Rate per cum.

=
= = =

Tk. 11,698.50 Tk. 1,022.50 Tk. 220.53 Tk. 12,941.53 Tk. 1,294.15 Tk. 452.95 Tk. 14,688.63 Tk. 660.99 Tk. 15,349.62 Tk. 153.50 Tk. 5,420.85

Say,

Tk.

5,421 .00 Per cum.

ANALYSIS FOR ITEM NO. 57(c) R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in foundation beam with stone chips using steel shutter. Considering 100 cft. of work A. B. C. Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering

Same as item No. 57(a) Same as item No. 41(a) Same as item No. 56(c)
Contractor's profit Overhead expenses VAT

= = = Total = 10.00% = 3.50% =

4.50% Grand total Rate per cft. Rate per cum.

=
= = =

Tk. 11,698.50 Tk. 1,022.50 Tk. 1,940.56 Tk. 14,661.56 Tk. 1,466.16 Tk. 513.15 Tk. 16,640.87 Tk. 748.84 Tk. 17,389.71 Tk. 173.90 Tk. 6,141.28

Say,

Tk.

6,141 .00 Per cum.

- 183 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

ANALYSIS FOR ITEM NO. 57(d) R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in Padestals, column, column capitals, lift walla and walls with stone chips using steel shutter. Considering 100 cft. of work A. B. C. Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering

Same as item No. 57(a) Same as item No. 41(a) Same as item No. 56(d)
Contractor's profit Overhead expenses VAT

= = = Total = 10.00% = 3.50% =

(a) Below plinth level and in ground floor

4.50% Grand total Rate per cft. Rate per cum.

=
= = =

Tk. 11,698.50 Tk. 1,022.50 Tk. 6,964.60 Tk. 19,685.60 Tk. 1,968.56 Tk. 689.00 Tk. 22,343.16 Tk. 1,005.44 Tk. 23,348.60 Tk. 233.49 Tk. 8,245.70

Say,
(b) (c) (d) Add for each addl. floor upto 5th floor: @ 1.25 Nos. lab. per % cft. in/c charges

Tk.

8,246 .00 Per cum.


Per cum = Tk. Per cum = Tk. Per cum = Tk. 52.36 73.30 83.77

Add for each addl. floor from 6th floor to 9th floor: @ 1.75 Nos. lab. per % cft. in/c charges Add for each addl. floor for 10th floor & above: @ 2.0 Nos. lab. per % cft. in/c charges

ANALYSIS FOR ITEM NO. 57(e) R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in tie beams and lintels with stone chips using steel shutter. Considering 100 cft. of work A. B. C. Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering

Same as item No. 57(a) Same as item No. 41(a) Same as item No. 56(e)
Contractor's profit Overhead expenses VAT

= = = Total = 10.00% = 3.50% =

(a) Below plinth level and in ground floor

4.50% Grand total Rate per cft. Rate per cum.

=
= = =

Tk. 11,698.50 Tk. 1,022.50 Tk. 4,754.72 Tk. 17,475.72 Tk. 1,747.57 Tk. 611.65 Tk. 19,834.94 Tk. 892.57 Tk. 20,727.51 Tk. 207.28 Tk. 7,320.09

- 184 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

Say,
(b) (c) (d) Add for each addl. floor upto 5th floor: @ 1.25 Nos. lab. per % cft. in/c charges

Tk.

7,320 .00 Per cum.


Per cum = Tk. Per cum = Tk. Per cum = Tk. 52.36 73.30 83.77

Add for each addl. floor from 6th floor to 9th floor: @ 1.75 Nos. lab. per % cft. in/c charges Add for each addl. floor for 10th floor & above: @ 2.0 Nos. lab. per % cft. in/c charges

ANALYSIS FOR ITEM NO. 57(f) R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in Tee beams Ell beams and Rectangular beams with stone chips using steel shutter. Considering 100 cft. of work A. B. C. Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering

Same as item No. 57(a) Same as item No. 41(a) Same as item No. 56(f)
Contractor's profit Overhead expenses VAT

= = = Total = 10.00% = 3.50% =

(a) Below plinth level and in ground floor

4.50% Grand total Rate per cft. Rate per cum.

=
= = =

Tk. 11,698.50 Tk. 1,022.50 Tk. 5,496.17 Tk. 18,217.17 Tk. 1,821.72 Tk. 637.60 Tk. 20,676.49 Tk. 930.44 Tk. 21,606.93 Tk. 216.07 Tk. 7,630.51

Say,
(b) (c) (d) Add for each addl. floor upto 5th floor: @ 1.25 Nos. lab. per % cft. in/c charges

Tk.

7,631 .00 Per cum.


Per cum = Tk. Per cum = Tk. Per cum = Tk. 52.36 73.30 83.77

Add for each addl. floor from 6th floor to 9th floor: @ 1.75 Nos. lab. per % cft. in/c charges Add for each addl. floor for 10th floor & above: @ 2.0 Nos. lab. per % cft. in/c charges

ANALYSIS FOR ITEM NO. 57(g) R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in floor and roof slab with stone chips using steel shutter. Considering 100 cft. of work A. B. C. Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering
- 185 -

Same as item No. 57(a) Same as item No. 41(a) Same as item No. 56(g)

= Tk. = Tk. = Tk.

11,698.50 1,022.50 6,680.91

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

(a) Below plinth level and in ground floor

Total = Tk. 19,401.91 Contractor's profit 10.00% = Tk. 1,940.19 Overhead expenses 3.50% = Tk. 679.07 Tk. 22,021.17 VAT 4.50% = Tk. 990.95 Grand total = Tk. 23,012.12 Rate per cft. = Tk. 230.12 Rate per cum. = Tk. 8,126.69 Say, Tk. 8,127 .00 Per cum.
Per cum = Tk. Per cum = Tk. Per cum = Tk. 52.36 73.30 83.77

(b) (c) (d)

Add for each addl. floor upto 5th floor: @ 1.25 Nos. lab. per % cft. in/c charges Add for each addl. floor from 6th floor to 9th floor: @ 1.75 Nos. lab. per % cft. in/c charges Add for each addl. floor for 10th floor & above: @ 2.0 Nos. lab. per % cft. in/c charges

ANALYSIS FOR ITEM NO. 57(h) R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in sunshade, cornice, railing, drop walls etc. For all floors (av. 3" thick) with stone chips using steel shutter. Considering 100 cft. of work A. B. C. Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering

Same as item No. 57(a) Same as item No. 41(a) Same as item No. 56(h)
Contractor's profit Overhead expenses VAT

= = = Total = 10.00% = 3.50% =

4.50% Grand total Rate per cft. Rate per sft.

=
= = =

Tk. 11,698.50 Tk. 1,022.50 Tk. 8,552.00 Tk. 21,273.00 Tk. 2,127.30 Tk. 744.56 Tk. 24,144.86 Tk. 1,086.52 Tk. 25,231.38 Tk. 252.31 Tk. 63.08 678.99

(a) Below plinth level and in ground floor Say, Tk.

Per sqm = Tk. 679 .00 Per sqm.

(b) (c) (d)

Add for each addl. floor upto 5th floor: @ 1/12 No. lab. per sqm in/c charges Add for each addl. floor from 6th floor to 9th floor: @ 1/8 No. lab. per sqm in/c charges Add for each addl. floor for 10th floor & above: @ 1/6 No. lab. per sqm in/c charges

Per sqm. = Tk. Per sqm. = Tk. Per sqm. = Tk.

9.88 14.83 19.77

- 186 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

ANALYSIS FOR ITEM NO. 57(i) R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in stair case slab and steps with stone chips using steel shutter. Considering 100 cft. of work A. B. C. Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering

Same as item No. 57(a) Same as item No. 41(a) Same as item No. 56(i)
Contractor's profit Overhead expenses VAT

= = = Total = 10.00% = 3.50% =

(a) Below plinth level and in ground floor

4.50% Grand total Rate per cft. Rate per cum.

=
= = =

Tk. 11,698.50 Tk. 1,022.50 Tk. 5,509.38 Tk. 18,230.38 Tk. 1,823.04 Tk. 638.06 Tk. 20,691.48 Tk. 931.12 Tk. 21,622.60 Tk. 216.23 Tk. 7,636.16

Say,
(b) (c) (d) Add for each addl. floor upto 5th floor: @ 1.25 Nos. lab. per % cft. in/c charges

Tk.

7,636 .00 Per cum.


Per cum = Tk. Per cum = Tk. Per cum = Tk. 52.36 73.30 83.77

Add for each addl. floor from 6th floor to 9th floor: @ 1.75 Nos. lab. per % cft. in/c charges Add for each addl. floor for 10th floor & above: @ 2.0 Nos. lab. per % cft. in/c charges

ANALYSIS FOR ITEM NO. 57(j) R.C.C work (1:2:4) complete excluding the cost of reinforcement and its fabrication in Waffle / Ribbed floor / Roof slab with stone chips using steel shutter. Considering 100 cft. of work. A. B. C. Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering

Same as item No. 57(a) Same as item No. 41(a) Same as item No. 46
Contractor's profit Overhead expenses VAT

= = = Total = 10.00% = 3.50% =

(a) Below plinth level and in ground floor

4.50% Grand total Rate per cft. Rate per cum.

=
= = =

Tk. 11,698.50 Tk. 1,022.50 Tk. 12,510.71 Tk. 25,231.71 Tk. 2,523.17 Tk. 883.11 Tk. 28,637.99 Tk. 1,288.71 Tk. 29,926.70 Tk. 299.27 Tk. 10,568.72

- 187 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

Say,
(b) (c) (d) Add for each addl. floor upto 5th floor: @ 1.25 Nos. lab. per % cft. in/c charges

Tk.

10,569 .00 Per cum.


Per cum = Tk. Per cum = Tk. Per cum = Tk. 52.36 73.30 83.77

Add for each addl. floor from 6th floor to 9th floor: @ 1.75 Nos. lab. per % cft. in/c charges Add for each addl. floor for 10th floor & above: @ 2.0 Nos. lab. per % cft. in/c charges

ANALYSIS FOR ITEM NO. 58(a)-i Extra rate over the rate of RCC works in columns, capitals, liftwalls & walls where the free height of the structure exceeds 4 meter [rate is considered for the height of each addl. 4 (four) meter or part] Considering 100 cft. of work a) b) c) d) e) f) Extra head mason 0.1 No. Extra mason 0.2 No. Extra skilled labour 0.2 No. Extra ordinary labour 1 No. Extra for local carriage, storage & sundries Extra for scaffolding [5% of item No. 56(d) (C)] @ @ @ @ Tk. Tk. Tk. Tk. 180.00 150.00 120.00 100.00 each each each each L.S. L.S. Total 10.00% 3.50% 4.50% Grand total Rate per cft. Rate per cum. = = = = = = = Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. 18.00 30.00 24.00 100.00 10.00 348.23 530.23 53.02 18.56 601.81 27.08 628.89 6.29 222.13

Contractor's profit Overhead expenses VAT

= = =
= = =

Say,

Tk.

222 .00 Per cum.

ANALYSIS FOR ITEM NO. 58(a)-ii Extra rate over the rate of RCC works in Tee beams, Ell beams and rectangular beams where the free height of the structure exceeds 4 meter (rate is considered for each addl. meter height) Considering 100 cft. of work a) b) c) d) e) f) Extra head mason 0.1 Extra mason 0.2 Extra skilled labour 0.2 Extra ordinary labour 1 Extra for local carriage, storage & sundries Extra for scaffolding [10% of item No. 56 (f) (C)] No. No. No. No. @ @ @ @ Tk. Tk. Tk. Tk. 180.00 150.00 120.00 100.00 each each each each L.S. L.S. = = = = = = Tk. Tk. Tk. Tk. Tk. Tk. 18.00 30.00 24.00 100.00 10.00 549.62

- 188 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

Contractor's profit Overhead expenses

Total = Tk. 10.00% = Tk. 3.50% = Tk. Tk. VAT 4.50% = Tk. Grand total = Tk. Rate per cft. = Tk. Rate per cum. = Tk. 307 .00 Per cum.

731.62 73.16 25.61 830.39 37.37 867.76 8.68 306.53

Say,

Tk.

ANALYSIS FOR ITEM NO. 58(a)-iii Extra rate over the rate of RCC works in floor / roof slab, cantilever slab, waffle slab and drop panels where the free height of the structure exceeds 4 meter (rate is considered for each addl. meter height) Considering 100 cft. of work a) b) c) d) e) f) Extra head mason 0.1 No. Extra mason 0.2 No. Extra skilled labour 0.2 No. Extra ordinary labour 1 No. Extra for local carriage, storage & sundries Extra for scaffolding [5% of item No. 56(j) (C)] @ @ @ @ Tk. Tk. Tk. Tk. 180.00 150.00 120.00 100.00 each each each each L.S. L.S. Total 10.00% 3.50% 4.50% Grand total Rate per cft. Rate per cum. = = = = = = = Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. 18.00 30.00 24.00 100.00 10.00 625.54 807.54 80.75 28.26 916.55 41.24 957.79 9.58 338.32

Contractor's profit Overhead expenses VAT

= = =
= = =

Say,

Tk.

338 .00 Per cum.

ANALYSIS FOR ITEM NO. 58(b)-i Supply and use of water reducing chemical admixture in concrete: Type - A Considering 1 liter a) Cost of admixture 1 liter b) Carriage, safe storage, mixing & sundries etc. @ Tk. 140.00 each L.S. Total 10.00% = Tk. = Tk. = Tk. = Tk. 140.00 3.00 143.00 14.30

Contractor's profit
- 189 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

Overhead expenses

3.50% = Tk. Tk. VAT 4.50% = Tk. Grand total = Tk. Rate per liter. = Tk. 170 .00 Per liter

5.01 162.31 7.30 169.61 169.61

Say,

Tk.

ANALYSIS FOR ITEM NO. 58(b)-ii Supply and use of retarding chemical admixture in concrete: Type - B Considering 1 liter a) Cost of admixture 1 liter Carriage, safe storage, mixing & sundries etc. b) @ Tk. = Tk. = Tk. = Tk. Contractor's profit = Tk. Overhead expenses = Tk. Tk. VAT 4.50% = Tk. Grand total = Tk. Rate per liter. = Tk. Tk. 146 .00 Per liter 120.00 each L.S. Total 10.00% 3.50% 120.00 3.00 123.00 12.30 4.31 139.61 6.28 145.89 145.89

Say,

ANALYSIS FOR ITEM NO. 58(b)-iii Supply and use of accelerating chemical admixture in concrete: Type - C Considering 1 liter a) Cost of admixture 1 liter b) Carriage, safe storage, mixing & sundries etc. @ Tk. = Tk. = Tk. = Tk. Contractor's profit = Tk. Overhead expenses = Tk. Tk. VAT 4.50% = Tk. Grand total = Tk. Rate per liter. = Tk. Tk. 181 .00 Per liter 150.00 each L.S. Total 10.00% 3.50% 150.00 3.00 153.00 15.30 5.36 173.66 7.81 181.47 181.47

Say,

- 190 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

ANALYSIS FOR ITEM NO. 58(b) - iv Supply and use of water-reducing and retarding chemical admixture in concrete: Type - D Considering 1 liter a) Cost of admixture 1 liter b) Carriage, safe storage, mixing & sundries etc. @ Tk. = Tk. = Tk. = Tk. Contractor's profit = Tk. Overhead expenses = Tk. Tk. VAT 4.50% = Tk. Grand total = Tk. Rate per liter. = Tk. Tk. 158 .00 Per liter 130.00 each L.S. Total 10.00% 3.50% 130.00 3.00 133.00 13.30 4.66 150.96 6.79 157.75 157.75

Say,

ANALYSIS FOR ITEM NO. 58(b)-v Supply and use of water-reducing and accelerating chemical admixture in concrete: Type - E Considering 1 liter a) Cost of admixture 1 liter b) Carriage, safe storage, mixing & sundries etc. @ Tk. = Tk. = Tk. = Tk. Contractor's profit = Tk. Overhead expenses = Tk. Tk. VAT 4.50% = Tk. Grand total = Tk. Rate per liter. = Tk. Tk. 170 .00 Per liter 140.00 each L.S. Total 10.00% 3.50% 140.00 3.00 143.00 14.30 5.01 162.31 7.30 169.61 169.61

Say,

ANALYSIS FOR ITEM NO. 58(b)-vi Supply and use of water-reducing high range chemical admixture in concrete: Type - F Considering 1 liter a) Cost of admixture 1 liter b) Carriage, safe storage, mixing & sundries etc.
- 191 -

Tk.

145.00

each = Tk. L.S. = Tk.

145.00 3.00

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

Contractor's profit Overhead expenses

Total = Tk. 10.00% = Tk. 3.50% = Tk. Tk. VAT 4.50% = Tk. Grand total = Tk. Rate per liter. = Tk. 176 .00 Per liter

148.00 14.80 5.18 167.98 7.56 175.54 175.54

Say,

Tk.

ANALYSIS FOR ITEM NO. 58(b)-vii

Supply and use of water-reducing high range and retarding chemical admixture in concrete: Type - G Considering 1 liter a) Cost of admixture 1 liter b) Carriage, safe storage, mixing & sundries etc. @ Tk. = Tk. = Tk. = Tk. Contractor's profit = Tk. Overhead expenses = Tk. Tk. VAT 4.50% = Tk. Grand total = Tk. Rate per liter. = Tk. Tk. 164 .00 Per liter 135.00 each L.S. Total 10.00% 3.50% 135.00 3.00 138.00 13.80 4.83 156.63 7.05 163.68 163.68

Say,

ANALYSIS FOR ITEM NO. 58(c)-i

Water-proofing membrane on external surface of primed vertical or inclined wall /on plastered and primed backwall and concrete cast against membrane (excluding cost of back fill/brick wall on back/plaster when membrane laid on back-wall and concrete cast against membrane)
Considering 10 sqm. of work 1. Cost of primer on the surface to be bonded 1 liter 2. Cost of membrane in/c 10% wastage and laping 11 sqm. 3. Cost for laying membrance in/c cleaning surface a) Foreman 0.50 No. @ @ Tk. Tk. 500.00 250.00 Per sqm. = Tk. each = Tk. 5,500.00 125.00 @ Tk. 420.00 Per liter = Tk. 420.00

- 192 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

b) Skilled labour 0.50 No. c) Ordinary Labour 1 No. Local carriage, storage, tools & plant, sundries etc. d)

@ @

Tk. Tk.

120.00 100.00

Contractor's profit Overhead expenses VAT

each each L.S. Total 10.00% 3.50%

= = = =

= =

4.50% = Grand total = Rate per sqm. =

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

60.00 100.00 50.00 6,255.00 625.50 218.93 7,099.43 319.47 7,418.90 741.89

Say,

Tk.

742 .00 Per sqm..

ANALYSIS FOR ITEM NO. 58(c)-ii

Water-proofing membrane on made up surface below the floor or below the horizontal surfaces with temporary protective cover using polysterene/1.5" thick sand-cement mortar in 4:1 /or by equally effective alternative (rate is excluding the cost of protective cover).
Considering 10 sqm. of work 1. Cost of membrane in/c 10% wastage and laping 11 sqm. 3. 4. a) b) c) Cost for laying membrance in/c cleaning surface Foreman 0.25 No. Skilled labour 0.25 No. Ordinary Labour 0.5 No. Local carriage, storage, tools & plant, sundries etc. @ @ @ @ Tk. Tk. Tk. Tk. 500.00 250.00 120.00 100.00 Per sqm. = Tk. each each each L.S. Total 10.00% 3.50% = = = = = Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. 5,500.00 62.50 30.00 50.00 50.00 5,692.50 569.25 199.24 6,460.99 290.74 6,751.73 675.17

Contractor's profit Overhead expenses VAT

= =

4.50% = Grand total = Rate per sqm. =

Say,

Tk.

675 .00 Per sqm.

ANALYSIS FOR ITEM NO. 58(c)-iii

Water-proofing membrane on the floor or on the horizontal surfaces with permanent protective cover & wearing coarse (Rate is excluding the cost of protective cover and wearing coarse)

- 193 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

Considering 10 sqm of work 1. Cost of membrane in/c 15% wastage and laping 11.5 sqm. 2. Cost for laying membrance in/c cleaning surface a) Foreman 0.25 No. b) Skilled labour 0.25 No. c) Ordinary Labour 0.5 No. d) Local carriage, storage, tools & plant, sundries etc.

@ @ @ @

Tk. Tk. Tk. Tk.

500.00 250.00 120.00 100.00

Per sqm. = Tk. each each each L.S. Total 10.00% 3.50% = = = = = Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

5,750.00 62.50 30.00 50.00 50.00 5,942.50 594.25 207.99 6,744.74 303.51 7,048.25 704.83

Contractor's profit Overhead expenses VAT

= =

4.50% = Grand total = Rate per sqm. =

Say,

Tk.

705 .00 Per sqm.

ANALYSIS FOR ITEM NO. 58(d)

20 mm thick water-proofing work in masonry or concrete surface with sand-cement mortar mixed with specified
admixure Considering 10 sqm. of work 1. 2. 3. 4. a) b) c) d) 5) Sand (F.M. 1.2) 7.5 cft. @ Tk. 990.00 Cement 3.25 bags @ Tk. 250.00 Admixture 4.50 liter. @ Tk. 140.00 Mixing and laying Head mason 0.5 No. @ Tk. 180.00 Mason 2 Nos. @ Tk. 150.00 Skilled labour 2 Nos. @ Tk. 120.00 Ordinary labour 1 No. @ Tk. 100.00 Carriage, storage, tools & plant, safety provisions, scaffolding, sundries etc. Contractor's profit Overhead expenses VAT Per % cft. = Tk. Per bag. = Tk. Per liter = Tk. each each each each L.S. Total 10.00% 3.50% = = = = = = Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. 74.25 812.50 630.00 90.00 300.00 240.00 100.00 50.00 2,296.75 229.68 80.39 2,606.82 117.31 2,724.13 272.41

= =

4.50% = Grand total = Rate per sqm. =

Say,

Tk.

272 .00 Per sqm.

- 194 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

8. PILE WORK
ANALYSIS FOR THE ITEM No. 59

Drilling /Boring including equipment and labour for cast-in-situ piling


(a) A. 400 mm dia Considering executing 400 mm /16 inch dia & 20 meter long pile in 1 day.

1. Hire charge of rig set in/c fuel, lubricant, bentonite, mobilization, demobilization, maintenance and insurance coverage etc. 1 day @ 2. Foreman/supervisor 1 No. @ 3. Skilled labour 3 No. @ 4. Ordinary labour 6 No. @

Tk. Tk. Tk. Tk.

4,500.00 250.00 120.00 100.00

Contractor's profit Overhead expenses VAT

Per day each each each Total 10.00% 3.50%

= = = = =

= =

4.50% =

Rate per meter = Say, Tk. 339 .00 Per rm

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

4,500.00 250.00 360.00 600.00 5,710.00 571.00 199.85 6,480.85 291.64 6,772.49 338.62

Considering executing 400 mm /16 inch dia 29 meter long pile in 2 days. B. 1. Hire charge of rig set in/c fuel, lubricant, bentonite, mobilization, demobilization, maintenance and insurance coverage etc. 2 days @ Tk. 2. Foreman/supervisor 2 Nos. @ Tk. 3. Skilled labour 6 Nos. @ Tk. 4. Ordinary labour 12 Nos. @ Tk.

4,500.00 250.00 120.00 100.00

Contractor's profit Overhead expenses VAT

Per day each each each Total 10.00% 3.50%

= = = = =

= =

4.50% =

Rate per meter = Say, Tk. 467 .00 Per rm

Tk. 9,000.00 Tk. 500.00 Tk. 720.00 Tk. 1,200.00 Tk. 11,420.00 Tk. 1,142.00 Tk. 399.70 Tk. 12,961.70 Tk. 583.28 Tk. 13,544.98 Tk. 467.07

So, extra cost for each addl. meter boring and length up to 30m = (B-A)/9 = Tk.
- 195 -

14.22

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

Say, (b) A. 450 mm dia

Tk.

14 .00 Per meter

Considering executing 450 mm / 18 inch dia & 20 meter pile in 1.125 days

1. Hire charge of rig set in/c fuel, lubricant, bentonite, mobilization, demobilization, maintenance and insurance coverage etc. 1.125 days @ 2. Foreman/supervisor 1.125 Nos. @ 3. Skilled labour 4.5 Nos. @ 4. Ordinary labour 7.875 Nos. @

Tk. Tk. Tk. Tk.

4,500.00 250.00 120.00 100.00

Contractor's profit Overhead expenses VAT

Per day each each each Total 10.00% 3.50%

= = = = =

= =

4.50% =

Rate per meter = Say, Tk. 396 .00 Per rm

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

5,062.50 281.25 540.00 787.50 6,671.25 667.13 233.49 7,571.87 340.73 7,912.60 395.63

Considering executing 450mm /18 inch dia & 29 meter long pile in 2.25 days B. 1. Hire charge of rig set in/c fuel, lubricant, bentonite, mobilization, demobilization, maintenance and insurance coverage etc. 2.25 days @ Tk. 2. Foreman/supervisor 2.25 Nos. @ Tk. 3. Skilled labour 7.875 Nos. @ Tk. 4. Ordinary labour 18 Nos. @ Tk.

4,500.00 250.00 120.00 100.00

Contractor's profit Overhead expenses VAT

Per day each each each Total 10.00% 3.50%

= = = = =

= =

4.50% =

Rate per meter = Say, Tk. 549 .00 Per rm

Tk. 10,125.00 Tk. 562.50 Tk. 945.00 Tk. 1,800.00 Tk. 13,432.50 Tk. 1,343.25 Tk. 470.14 Tk. 15,245.89 Tk. 686.07 Tk. 15,931.96 Tk. 549.38

So, extra cost for each addl. meter boring and length up to 29 m= (B-A)/9 = Tk. Say, (c) A. 500 mm dia Considering executing 500 mm /20 inch dia & 20 meter long pile in 1.25 days. Tk. 17 .00 Per meter

17.00

1. Hire charge of rig set in/c fuel, lubricant, bentonite, mobilization,


- 196 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

demobilization, maintenance and insurance coverage etc. 1.25 2. Foreman/supervisor 1.25 3. Skilled labour 3.75 4. Ordinary labour 10

days Nos. Nos. Nos.

@ @ @ @

Tk. Tk. Tk. Tk.

4,500.00 250.00 120.00 100.00

Contractor's profit Overhead expenses VAT

Per day each each each Total 10.00% 3.50%

= = = = =

= =

4.50% =

Rate per meter = Say, B. Tk. 438 .00 Per rm

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

5,625.00 312.50 450.00 1,000.00 7,387.50 738.75 258.56 8,384.81 377.32 8,762.13 438.11

Considering executing 500 mm /20 inch dia & 29 meter long pile in 2.5 days

1. Hire charge of rig set in/c fuel, lubricant, bentonite, mobilization, demobilization, maintenance and insurance coverage etc. 2.5 days @ 2. Foreman/supervisor 2.5 Nos. @ 3. Skilled labour 7.5 Nos. @ 4. Ordinary labour 17.5 Nos. @

Tk. Tk. Tk. Tk.

4,500.00 250.00 120.00 100.00

Contractor's profit Overhead expenses VAT

Per day each each each Total 10.00% 3.50%

= = = = =

= =

4.50% =

Rate per meter = Say, Tk. 594 .00 Per rm

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

11,250.00 625.00 900.00 1,750.00 14,525.00 1,452.50 508.38 16,485.88 741.86 17,227.74 594.06

So, extra cost for each addl. meter boring and length up to 29 m= (B-A)/9 = Tk. Say, Tk. 17 .00 Per meter

17.33

(d) A.

550 mm dia Considering executing 550 mm/22 inch dia & 20 meter pile in 1.375 days.

1. Hire charge of rig set in/c fuel, lubricant, bentonite, mobilization, demobilization, maintenance and insurance coverage etc. 1.375 days @ 2. Foreman/supervisor 1.375 Nos. @ 3. Skilled labour 4.125 Nos. @ 4. Ordinary labour 12.375 Nos. @

Tk. Tk. Tk. Tk.

4,500.00 250.00 120.00 100.00

Per day each each each Total

= = = = =

Tk. Tk. Tk. Tk. Tk.

6,187.50 343.75 495.00 1,237.50 8,263.75

- 197 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

Contractor's profit Overhead expenses

10.00% = Tk. 3.50% = Tk. Tk. VAT 4.50% = Tk. Tk. Rate per meter = Tk. 490 .00 Per rm

826.38 289.23 9,379.36 422.07 9,801.43 490.07

Say,

Tk.

Considering executing 550 mm /22 inch dia & 29 meter long pile in 2.75 days B. 1. Hire charge of rig set in/c fuel, lubricant, bentonite, mobilization, d emobilization, maintenance and insurance coverage etc. 2.75 days @ Tk. 2. Foreman/supervisor 2.75 Nos. @ Tk. 3. Skilled labour 13.75 Nos. @ Tk. 4. Ordinary labour 27.5 Nos. @ Tk.

4,500.00 250.00 120.00 100.00

Contractor's profit Overhead expenses VAT

Per day each each each Total 10.00% 3.50%

= = = = =

= =

4.50% =

Rate per meter = Say, Tk. 714 .00 Per rm

Tk. 12,375.00 Tk. 687.50 Tk. 1,650.00 Tk. 2,750.00 Tk. 17,462.50 Tk. 1,746.25 Tk. 611.19 Tk. 19,819.94 Tk. 891.90 Tk. 20,711.84 Tk. 714.20

So, extra cost for each addl. meter boring and length up to 29 m= (B-A)/9 = Tk. Say, Tk. 25 .00 Per meter (d) 600 mm / 24 inch dia pile

24.89

Considering executing 600 mm / 24 inch dia & 20 meter long pile in 1.5 days. A. 1. Hire charge of rig set in/c fuel, lubricant, bentonite, mobilization, demobilization, maintenance and insurance coverage etc. 1.50 days @ Tk. 2. Foreman/supervisor 1.50 Nos. @ Tk. 3. Skilled labour 4.50 Nos. @ Tk. 4. Ordinary labour 9.00 Nos. @ Tk.

4,500.00 250.00 120.00 100.00

Contractor's profit Overhead expenses VAT

Per day each each each Total 10.00% 3.50%

= = = = =

= =

4.50% =

Rate per meter =

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

6,750.00 375.00 540.00 900.00 8,565.00 856.50 299.78 9,721.28 437.46 10,158.74 507.94

- 198 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

Say, Considering executing 600 mm /24 inch dia & 29 meter pile in 3 days. B. 1. Hire charge of rig set in/c fuel, lubricant, bentonite, mobilization, demobilization, maintenance and insurance coverage etc. 3.00 days @ 2. Foreman/supervisor 3.00 Nos. @ 3. Skilled labour 15.00 Nos. @ 4. Ordinary labour 24.00 Nos. @

Tk.

508 .00 Per rm

Tk. Tk. Tk. Tk.

4,500.00 250.00 120.00 100.00

Contractor's profit Overhead expenses VAT

Per day each each each Total 10.00% 3.50%

= = = = =

= =

4.50% =

Rate per meter =

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

13,500.00 750.00 1,800.00 2,400.00 18,450.00 1,845.00 645.75 20,940.75 942.33 21,883.08 754.59

Say,

Tk.

755 .00 Per rm 27.44

So, extra cost for each addl. 1 m boring up to 29 meter = (B-A)/9 = Tk. Say, Tk. 27 .00 Per meter

ANALYSIS FOR ITEM NO. 60

Casting of cast in situ bored pile with reinforced cement concrete works (1 : 1.5 : 3) to give a minimum cylinder
crushing strength of 20 Mpa. Considering 100 cft. of work

A. (a) (b) (c) (d) (e) B. (a) (b) (c) (d)

Cost of materials 19 mm down crushed stone chips 83 cft. Sand (Sylhet) 41.5 cft. Cement 22 bag. Local carriage, storage, sundries, tools & plants Add wastage & overflow & increase in diameter

@ @ @

Tk. Tk. Tk.

6,500.00 1,330.00 250.00

Per % cft. Per % cft. Per bag. L.S. Sub-Total 10% Total (A)

= = = = =

Tk. Tk. Tk. Tk. Tk. = Tk. = Tk.

5,395.00 551.95 5,500.00 300.00 11,746.95 1,174.70 12,921.65

Labour, machinery hire charge etc for 2 Nos. 16" dia, 65'-0" long pile: 191 cft. casting in 0.67 day Foreman 0.67 No. @ Tk. 250.00 Helper to foreman 0.67 No. @ Tk. 120.00 Mixture machine operator 0.67 No. @ Tk. 160.00 Skilled labour
- 199 -

each = Tk. each = Tk. each = Tk.

167.50 80.40 107.20

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

(i) Feeding cement 0.67 No. @ (ii) Feeding sand 1.0 No. @ (iii) Feeding chips 2.0 Nos. @ (e) Ordinary labour (i ) bag cutting 0.67 No. @ (ii) Belcha 2.0 Nos. @ (iii) Pouring bucket 2.0 Nos. @ (iv) Pouring to tremie pipe 2.0 Nos. @ (v) Watering 2.0 Nos. @ (f) Mixture machine hire charge 0.67 day @ (g) Hire charge of cast in situ pile driving rig set for pouring concrete. 0.67 day @

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

120.00 120.00 120.00 100.00 100.00 100.00 100.00 100.00 500.00 4,500.00

each = Tk. each = Tk. each = Tk. each each each each each Per day = = = = = = = = = = = Tk. Tk. Tk. Tk. Tk. Tk.

80.40 120.00 240.00 67.00 200.00 200.00 200.00 200.00 335.00

Per day Total (B) Cost for 100 cft Total cost for 100 cft. (A+B) Cost per cft. of work Contractor's profit 10.00% Overhead expenses 3.50% VAT

= =

4.50% = Rate per cft. = Rate per cum. =

Tk. 3,015.00 Tk. 5,012.50 Tk. 2,624.35 Tk. 15,546.00 Tk. 155.46 Tk. 15.55 Tk. 5.44 Tk. 176.45 Tk. 7.94 Tk. 184.39 Tk. 184.39 Tk. 6,511.73

Say,

Tk.

6,512 .00 Per cum

ANALYSIS FOR ITEM NO. 61 Providing and making point welding Considering 1 point welding

(a) Welding charge

1 Point

Tk. 1.50 Contractor's profit Overhead expenses

Per Point = Tk. 10.00% = Tk. 3.50% = Tk. Tk. VAT 4.50% = Tk. Total = Tk. Rate per point = Tk. 1.78 Per point

1.50 0.15 0.05 1.70 0.08 1.78 1.78

Say,

Tk.

- 200 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

ANALYSIS FOR ITEM NO. 62 Providing and making joint welding of min. 300 mm length Considering 1 inch of welding

(a) Welding charge

inch @

Tk. 2.00 Contractor's profit Overhead expenses VAT

Per inch = Tk. 10.00% = Tk. 3.50% = Tk. Tk. 4.50% = Tk. Total = Tk.

2.00 0.20 0.07 2.27 0.10 2.37

Say,

Tk.

2.37 Per inch

ANALYSIS FOR ITEM NO. 63 Labour for breaking head of cast-in-situ bored pile/pre-cast driven pile Considering 1 cum. of work (a) Skilled labour 10 Nos. @ (b) Repairing of pile head in/c materials (c) Straightening and bending of pile bars, removing the debris to a safe distance, tools & plant, sundries etc. Tk. 120.00 each = Tk. L.S. = Tk. L.S. Total 10.00% 3.50% 4.50% Grand total Rate per cft. Rate per cum. = Tk. = Tk. = Tk. = Tk. Tk. = Tk. = Tk. = Tk. = Tk. 1,200.00 100.00 100.00 1,400.00 140.00 49.00 1,589.00 71.51 1,660.51 47.02 1,660.51

Contractor's profit Overhead expenses VAT

Say,

Tk.

1,661 .00 Per cum.

ANALYSIS FOR ITEM NO. 64(a) Conducting static load testfor the cast in situ / precast pile providing required scaffolding.

- 201 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

For 25 tonne load for 1 test (a) Mobilization and demobilization of testing equipment (5 ton) by truck 2 trips @ Tk. (b) Platform making: i) Foreman 2 Nos. @ Tk. ii) Skilled labour 6 Nos. @ Tk. iii) Ordinary labour 12 Nos. @ Tk. (c) Hire charge of load testing equipment (joist, jacks and other necessary devices in/c caliberation charges, hydraulic fluid etc.) 1 test @ Tk. (d) Cost of empty gunny bags (taking 2 times use) 450 bags. @ Tk. (e) Cost of local sand as loading materials (taking 2 times use ) 450 cft @ Tk. (f) Cost of labour for bag filling, stitching, loading & unloading: 900 bags @ Tk. (h) Preparation of result in standard form in triplicate 1 test @ Tk. (i ) Other incidental charge

800.00 250.00 120.00 100.00

Per trip = Tk. each = Tk. each = Tk. each = Tk.

1,600.00 500.00 720.00 1,200.00

4,500.00 10.00 312.50 4.00 1,000.00

Per test = Tk. Per bag = Tk. Per % cft. = Tk. Per bag = Tk. Per test L.S. Total 10.00% 3.50%

4,500.00 4,500.00 1,406.25 3,600.00

Contractor's profit Overhead expenses VAT

= Tk. 1,000.00 = Tk. 300.00 = Tk. 19,326.25 = Tk. 1,932.63 = Tk. 676.42 Tk. 21,935.30 4.50% = Tk. 987.09 Grand total = Tk. 22,922.39

Say,

Tk.

22,922 .00 Per test

ANALYSIS FOR ITEM NO. 64(b) Conducting static load testfor the cast in situ / pre-cast pile providing required scaffolding. For 75 ton load for 1 No. of test (a) Mobilization and demobilization of load testing equipment (10 ton) by truck 3 trips @ Tk. 800.00 (b) Platform making: i) Foreman 2 Nos. @ Tk. 250.00 ii) Skilled labour 6 Nos. @ Tk. 120.00 iii) Ordinary labour 12 Nos. @ Tk. 100.00 (c) Hire charge of load testing equipment (joist, jacks and other necessary devices in/c caliberation charges, hydraulic fluid etc.) 1 test @ Tk. 4,500.00 (d) Cost of empty gunny bags (taking 2 times use)
- 202 -

Per trip = Tk. each = Tk. each = Tk. each = Tk.

2,400.00 500.00 720.00 1,200.00

Per test = Tk.

4,500.00

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

(e) (f) (h) (i )

1350 bags. @ Cost of local sand as loading materials (taking 2 times use) 1350 cft @ Cost of labour for bag filling, stitching, loading & unloading: 2700 bags @ Preparation of result in standard form in triplicate 1 test @ Other incidental charges

Tk. Tk. Tk. Tk.

10.00 312.50 4.00 1,000.00

Per bag = Tk. 13,500.00 Per % cft. = Tk. 4,218.75

Per bag = Tk. 10,800.00 = Tk. 1,000.00 = Tk. 300.00 = Tk. 39,138.75 = Tk. 3,913.88 = Tk. 1,369.86 Tk. 44,422.49 4.50% = Tk. 1,999.01 Grand total = Tk. 46,421.50 Per test L.S. Total 10.00% 3.50%

Contractor's profit Overhead expenses VAT

Say,

Tk.

46,422 .00 Per test

ANALYSIS FOR ITEM NO. 64(c) Conducting static load test for the cast in situ / precast pile providing required scaffolding. For 125 ton load for 1 No. of test (a) Mobilization and demobilization of testing equipment (15 ton) by truck 4 trips @ Tk. 800.00 (b) Platform making: i) Foreman 2 Nos. @ Tk. 250.00 ii) Skilled labour 6 Nos. @ Tk. 120.00 iii) Ordinary labour 12 Nos. @ Tk. 100.00 (c) Hire charge of load testing equipment (joist, jacks and other necessary devices in/c caliberation charges, hydraulic fluid etc.) 1 test @ Tk. 4,500.00 (d) Cost of empty gunny bags (taking 2 times use) 2250 bags. @ Tk. 10.00 (e) Cost of local sand as loading materials (taking 2 times use) 2250 cft @ Tk. 312.50 (f) Cost of labour for bag filling, stitching, loading & unloading: 4500 bags @ Tk. 4.00 (h) Preparation of result in standard form in triplicate 1 test @ Tk. 1,000.00 (i ) Other incidental charges Contractor's profit Overhead expenses

Per trip = Tk. each = Tk. each = Tk. each = Tk.

3,200.00 500.00 720.00 1,200.00

Per test = Tk.

4,500.00

Per bag = Tk. 22,500.00 Per % cft. = Tk. 7,031.25

Per bag = Tk. 18,000.00 Per test L.S. Total 10.00% 3.50% = Tk. = Tk. = Tk. = Tk. = Tk. 1,000.00 500.00 59,151.25 5,915.13 2,070.29

- 203 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

VAT

Tk. 67,136.67 4.50% = Tk. 3,021.15 Grand total = Tk. 70,157.82

Say,

Tk.

70,158 . 00 Per test

ANALYSIS FOR ITEM NO. 64(d) Conducting static load test for the cast in situ / precast pile providing required scaffolding. For 175 tone load for 1 No. test (a) Mobilization and demobilization of testing equipment (20 ton) by truck 5 trips @ Tk. 800.00 (b) Platform making: i) Foreman 2 Nos. @ Tk. 250.00 ii) Skilled labour 8 Nos. @ Tk. 120.00 iii) Ordinary labour 16 Nos. @ Tk. 100.00 (c) Hire charge of load testing equipment (joist, jacks and other necessary devices in/c caliberation charges, hydraulic fluid etc.) 1 test @ Tk. 5,000.00 (d) Cost of empty gunny bags (taking 2 times use) 3150 bags. @ Cost of local sand as loading materials (taking 2 times use) (e) 3150 cft @ (f) Cost of labour for bag filling, stitching, loading & unloading: 6300 bags (h) Preparation of result in standard form in triplicate 1 test (i ) Other incidental charges @ @ Tk. Tk. Tk. Tk. 10.00 312.50 4.00 1,000.00

Per trip = Tk. each = Tk. each = Tk. each = Tk.

4,000.00 500.00 960.00 1,600.00

Per test = Tk.

5,000.00

Per bag = Tk. 31,500.00 Per % cft. = Tk. 9,843.75

Per bag = Tk. 25,200.00 = Tk. 1,000.00 = Tk. 500.00 = Tk. 80,103.75 = Tk. 8,010.38 = Tk. 2,803.63 Tk. 90,917.76 4.50% = Tk. 4,091.30 Grand total = Tk. 95,009.06 Per test L.S. Total 10.00% 3.50%

Contractor's profit Overhead expenses VAT

Say,

Tk.

95,009 . 00 Per test

ANALYSIS FOR ITEM NO. 64(e) Conducting static load test for the cast in situ / precast pile providing required scaffolding. For 225 tonne load for 1 No. test
- 204 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

(a) Mobilization and demobilization of testing equipment (25 ton ) by truck 6 trips @ Tk. 800.00 (b) Platform making: i) Foreman 2 Nos. @ Tk. 250.00 ii) Skilled labour 8 Nos. @ Tk. 120.00 iii) Ordinary labour 16 Nos. @ Tk. 100.00 (c) Hire charge of load testing equipment (joist, jacks and other necessary devices in/c caliberation charges, hydraulic fluid etc.) 1 test @ Tk. 5,000.00 (d) Cost of empty gunny bags (taking 2 times use) 4050 bags. @ Tk. 10.00 (e) Cost of local sand as loading materials (taking 2 times use) 4050 cft @ Tk. 312.50 (f) Cost of labour for bag filling, stitching, loading & unloading: 8100 bags @ Tk. 4.00 (h) Preparation of result in standard form in triplicate 1 test @ Tk. 1,000.00 (i ) Other incidental charges Contractor's profit Overhead expenses VAT

Per trip = Tk. each = Tk. each = Tk. each = Tk.

4,800.00 500.00 960.00 1,600.00

Per test = Tk.

5,000.00

Per bag = Tk. 40,500.00 Per % cft. = Tk. 12,656.25 Per bag = Tk. 32,400.00 = Tk. 1,000.00 = Tk. 500.00 = Tk. 99,916.25 = Tk. 9,991.63 = Tk. 3,497.07 Tk. 113,404.95 4.50% = Tk. 5,103.22 Grand total = Tk. 118,508.17 Per test L.S. Total 10.00% 3.50%

Say,

Tk.

118,508 . 00 Per test

ANALYSIS FOR ITEM NO. 64(f) Conducting static load test for the cast in situ / precast pile providing required scaffolding. For 275 tonne load for 1 No. of test (a) Mobilization and demobilization of testing equipment (30 ton) by truck 7 trips @ Tk. 800.00 (b) Platform making: i) Foreman 2 Nos. @ Tk. 250.00 ii) Skilled labour 8 Nos. @ Tk. 120.00 iii) Ordinary labour 16 Nos. @ Tk. 100.00 (c) Hire charge of load testing equipment (joist, jacks and other necessary devices in/c caliberation charges, hydraulic fluid etc.) 1 test @ Tk. 5,500.00 (d) Cost of empty gunny bags (taking 2 times use) 4950 bags. @ Tk. 10.00 (e) Cost of local sand as loading materials (taking 2 times use) 4950 cft @ Tk. 312.50
- 205 -

Per trip = Tk. each = Tk. each = Tk. each = Tk.

5,600.00 500.00 960.00 1,600.00

Per test = Tk.

5,500.00

Per bag = Tk. 49,500.00 Per % cft. = Tk. 15,468.75

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

(f) Cost of labour for bag filling, stitching, loading & unloading: 9900 bags @ (h) Preparation of result in standard form in triplicate 1 test @ (i ) Other incidental charges

Tk. Tk.

4.00 1,000.00

Per bag = Tk. 39,600.00 = Tk. 1,000.00 = Tk. 500.00 = Tk. 120,228.75 = Tk. 12,022.88 = Tk. 4,208.01 Tk. 136,459.64 4.50% = Tk. 6,140.68 Grand total = Tk. 142,600.32 Per test L.S. Total 10.00% 3.50%

Contractor's profit Overhead expenses VAT

Say,

Tk.

142,600 . 00 Per test

ANALYSIS FOR ITEM NO. 65(a) Pre-cast pile with reinforced cement concrete (1 : 1.5 : 3) with stone chips. Considering 40 rft. long 12" x 12" size pile Also Considering 100 rft. pile making work using 100 cft. concrete A. B. C. Cost of concrete materials Labour, machinery, fuel & lubricants for casting Cost of shuttering for 11 Nos. of pile

Same as item No. 56(a) Same as item No. 41(a)

= Tk. = Tk.

12,196.95 1,022.50

Volume of concrete: 11 x 12" x 12" x 40'-0" = 440 cft. (a) Cost of shuttering: (i) 1/12 " thick steel plate: Sides: 1 x 12 x 40'-0" x 1'-0"= Add wastage 5%= = @ 3.40 Ib per sft.= ii) 1.5 x 1.5 x 3/16" angle for frame: Sides: 2 x 12 x 40'-0"= Vertical: 12 x 41 x 1'-0"= = Add wastage 5%= @ 1.79 Ib per rft = iii) 1.5" x 3/16" F.I . Bar : @ 1'-0" c/c Stiffner: 6 x 20 x 1'-2" = Clamps: 6 x 12 x 6"= =

480.00 24.00 504.00 1713.60 960.00 492.00 1452.00 72.60 1524.60 2729.03

sft sft. sft. Ibs. rft. rft. rft. rft. rft. Ibs.

Tk.

10.85

Per Ib. = Tk. 18,592.56

Tk.

8.71

Per Ib. = Tk. 23,769.85

140.00 rft. 36.00 rft. 176.00 rft.


- 206 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

Add 5% wastage= 8.8 rft. = 184.80 rft. @ 0.956 Ibs Per rft.= 176.67 Ibs. @ iv) Cost of nuts & bolts: 20.0 kg. @ v) Manufacturing, fitting and fixing frame in/c drilling holes, welding & supplying of chemicals etc.: 12 x 40'-0" x 1'-0"= 480.00 sft. @

Tk. Tk.

7.71 60.00

Per Ib. = Tk. Per kg. = Tk.

1,362.13 1,200.00

Tk.

30.00

Per sft. = Tk. 14,400.00 Total = Tk. 59,324.54 Using 16 times = Tk. 3,707.78 Per sft. = Tk. 1,920.00 240.00 5,867.78 1,333.59

vi) Labour for fitting & fixing steel shuttering in position as required 480.00 sft. @ Tk. vii) Hessian tap for making shutter water-proof. 480.00 sft. @ Tk.

4.00

0.50 Per sft. = Tk. Total for 440 cft. = Tk. Cost for 100 cft. = Tk.

D.

Cost of bed preparation: Area of bed: 1 x 45'-0" x 15'-0"=

675.00 sft. 675.00 sft. 675.00 sft. @ @ Tk. Tk. 11.71 Per sft. = Tk. 7,904.25

a) One layer brick flat soling: b)

1/2" thick cement plaster with neat cement finishing 8.82 Per sft. = Tk. 5,953.50 Total for 440 cft. = Tk. 13,857.75 Cost for 100 cft. of work = Tk. 3,149.49 Using 8 times = Tk. 393.69 789.75 179.49

E.

Polythene as separator between pile layers during casting concrete 675.00 sft. @ Tk. 117.00 Per % sft. = Tk. Cost for 100 cft. of work = Tk. Abstract of cosr for 100 cft. of work

A. B. C. D. E.

Cost of concrete Labour, machinery, fuel and lubricant for casting Cost of shuttering Cost of bed preparation Polythene Contractor's profit Overhead expenses VAT

= = = = = Total = 10.00% = 3.50% = 4.50% Grand total Rate per cft. Rate per rft. Rate per rm.

=
= = = =

Tk. 12,196.95 Tk. 1,022.50 Tk. 1,333.59 Tk. 393.69 Tk. 179.49 Tk. 15,126.22 Tk. 1,512.62 Tk. 529.42 Tk. 17,168.26 Tk. 772.57 Tk. 17,940.83 Tk. 179.41 Tk. 179.41 Tk. 588.64

Say,
- 207 -

Tk.

589 . 00 Per rm.

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

ANALYSIS FOR ITEM NO. 65(b) Pre-cast pile with reinforced cement concrete (1 : 1.5 : 3) with stone chips. Considering 50 rft. long 14" x 14" size pile Also considering 73.5 rft. long pile making work using 100 cft. concrete A. B. C. Cost of concrete materials Labour, machinery, fuel & lubricants for casting Cost of shuttering for 11 No. of pile Volume of concrete: 11 x 14" x 14" x 50'-0" = 748.61 cft. (a) Cost of shuttering: (i) 1/12 " thick steel plate: Sides: 12 x 50'-0" x 1'-2"= Add wastage 5%= = @ 3.40 Ib per sft.= ii) 1.5 x 1.5 x 3/16" angle for frame: Sides: 2 x 12 x 50'-0"= Supports: 12 x 51 x 1'-2"= = Add wastage 5%= @ 1.79 Ib per rft.= 700.00 35.00 735.00 2499.00 1200.00 714.00 1914.00 95.70 2009.70 3597.36 sft. sft. sft. Ibs. rft. rft. rft. rft. rft. Ibs.

Same as item No. 56(a) Same as item No. 41 (a)

= Tk. = Tk.

12,196.95 1,022.50

Tk.

10.85

Per Ib. = Tk. 27,114.15

Tk.

8.71

Per Ib. = Tk. 31,333.01

iii) 1.5" x 3/16" F.I . bar: @ 1'-0" c/c Stiffner: 6 x 25 x 1'-2"= 140.00 rft. Clamps: 6 x 16 x 6"= 48.00 rft. = 188.00 rft. Add 5% wastage= 9.4 rft. = 197.40 rft. @ 0.956 Ibs Per rft.= 188.71 Ibs. @ iv) Cost of nuts & bolts:. 25 kg. @ v) Manufacturing, fitting and fixing frame in/c drilling holes, welding & supplying of chemicals etc.: 2 x 6 x 50 x 1'-2"= 700.00 sft. @

Tk. Tk.

7.71 60.00

Per Ib. = Tk. Per kg. = Tk.

1,454.95 1,500.00

Tk.

30.00

Per sft. = Tk. 21,000.00 Total = Tk. 82,402.11 Using 16 times = Tk. 5,150.13 Per sft. = Tk. 2,800.00

vi) Labour for fitting & fixing steel shuttering in position as required 700.00 sft. @ Tk. vii) Hessian tap for makin shutter water proof
- 208 -

4.00

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

700.00 sft.

Tk.

Per sft. = Tk. Total = Tk. Cost for 100 cft. of work = Tk.

0.50

350.00 8,300.13 1,108.74

D.

Cost of bed preparation: Area of bed: 1 x 55'-0" x 15'-0"= 825.00 sft. a) One layer brick flat soling: 825.00 sft. b) 1/2" thick cement plaster with neat cement finishing 825.00 sft.

@ @

Tk. Tk.

11.71 8.82

Per sft. = Tk.

9,660.75

Per sft. = Tk. 7,276.50 Total = Tk. 16,937.25 Cost for 100 cft. of work = Tk. 2,262.49 Using 8 times = Tk. 282.81 117.00 Per % sft. = Tk. Cost for 100 cft. of work = Tk. 965.25 128.94

E.

Polythene as separator between pile layers during casting concrete 825.00 sft. @ Tk.

Abstract of cosr for 100 cft. of work A. Cost of concrete B. Labour, machinery, fuel and lubricant for casting C. Cost of shuttering D. Cost of bed preparation E. Polythene Contractor's profit Overhead expenses VAT = Tk. 12,196.95 = Tk. 1,022.50 = = = Total = 10.00% = 3.50% = 4.50% Grand total Rate per cft. Rate per rft. Rate per rm. Tk. 1,108.74 Tk. 282.81 Tk. 128.94 Tk. 14,611.00 Tk. 1,461.10 Tk. 511.39 Tk. 16,583.49 Tk. 746.26 Tk. 17,329.75 Tk. 173.30 Tk. 235.78 Tk. 773.59

=
= = = =

Say,

Tk.

774 .00 Per rm.

ANALYSIS FOR ITEM NO. 65(c) Pile Shoe Considering 1 No. of pile A. Cost of materials i) 1/4" thick plate: 4 x 8" x 7"= 1.56 sft
- 209 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

Add wastage 5% = 0.08 = 1.64 @ 10.20 Ib per sft.= 16.73 ii) 5/8" dia M.S. rod connected with M.S. plate: 5 x 2'-6" = 12.50 = 13.00 B. Cost of labour

sft sft Ibs rft. Ibs

Tk.

10.85

Per Ib = Tk.

181.52

@ @

Tk. Tk.

10.28 2.00

Per Ib = Tk. Per inch = Tk. L.S. = Tk.

133.64 112.00 300.00 50.00 777.16 77.72 27.20 882.08 39.69 921.77 921.77

i) Cost of welding, grinding etc 56.00 inch ii) Manufacturing cost for making, fitting and fixing of pile shoe including cutting, shaping, sizing of M.S. plate iii) Local carriage, sundries and T & P

= Tk. = Tk. Contractor's profit = Tk. Overhead expenses = Tk. Tk. VAT 4.50% = Tk. Grand total = Tk. Rate per No. = Tk. Say, Tk. 922 .00 each

L.S. Total 10.00% 3.50%

ANALYSIS FOR ITEM NO. 65(d)-I Mobilization and demobilization of drop hammer type pre-cast pile driving rig. Considering 1 set 1. Truck fare in/c loading and unloading 2. Incidental and sundries etc. 2 trips @ Tk. 800.00 Per trip = Tk. = Tk. = Tk. = Tk. = Tk. Tk. 4.50% = Tk. Grand total = Tk. L.S Total 10.00% 3.50% 1,600.00 100.00 1,700.00 170.00 59.50 1,929.50 86.83 2,016.33

Contractor's profit Overhead expenses VAT

Say,

Tk.

2,016 .00 Per set.

ANALYSIS FOR ITEM NO. 65(d)-II

Driving of (12" x 12" x 40'-0") size pre-cast pile with drop hammer type rig .
Considering driving 20 rft. depth i) Hire charge of driving equipment in/c cost of fuel and lubricant etc. 1/6 day @ Tk.
- 210 -

6,000.00

Per day = Tk.

1,000.00

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

ii) Labour charge for pile carrying, lifting, shifting and driving etc. complete: a) Rig operator 0.25 No. @ Tk. 180.00 b) Skilled labour 0.25 No. @ Tk. 120.00 c) Ordinary labour 2.00 No. @ Tk. 100.00 Contractor's profit Overhead expenses VAT

each each each Total 10.00% 3.50%

= = = =

= =

4.50% = Grand total = Rate per rft. =

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

45.00 30.00 200.00 1,275.00 127.50 44.63 1,447.13 65.12 1,512.25 75.61 248.08

a) From 0 meter to 6 meter Say, b) From 6 meter to 12 meter add: 10% Tk.

Rate per meter = Tk. 248 . 00 Per rm. = Tk. Total = Tk. Say, Tk. 273 . 00 Per rm. = Tk. Total = Tk. Say, Tk. 300 . 00 Per rm.

24.80 272.88

c) From 12 meter to 15 meter add:

10%

27.29 300.17

ANALYSIS FOR ITEM NO. 65(d)-III

Driving of (14" x 14" x 40'-0") size pre-cast pile with drop hammer type rig
Considering driving 20 rft. depth i) Hire charge of driving equipment in/c cost of fuel and lubricant etc. 1/5 day a) Rig operator b) Skilled labour c) Ordinary labour 1/3 Nos. 1/2 Nos. 3.00 Nos. @ @ @ @ Tk. Tk. Tk. Tk. 6,000.00 180.00 120.00 100.00 Per day = Tk. each = Tk. each = Tk. each = Tk. Total = Tk. Contractor's profit Overhead expenses 10.00% = Tk. 3.50% = Tk. Tk.
- 211 -

1,200.00 60.00 60.00 300.00 1,620.00 162.00 56.70 1,838.70

ii) Labour charge for pile carrying, lifting, shifting and driving etc. complete:

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

VAT

4.50% = Tk. Grand total = Tk. Rate per rft. = Tk.

82.74 1,921.44 96.07 315.21

a) From 0 meter to 6 meter Say, b) From 6 meter to 12 meter add: 10% Tk.

Rate per meter = Tk. 315 . 00 Per rm. = Tk. Total = Tk. Say, Tk. 347 .00 Per rm. = Tk. Total = Tk. Say, Tk. 381 . 00 Per rm. = Tk. Total = Tk. Say, Tk. 454 .00 Per rm.

31.50 346.71

c) From 12 meter to 15 meter add:

10%

34.67 381.38

d) From 15 meter to 18 meter add .

10%

38.10 454.15

ANALYSIS FOR ITEM NO. 65(e)-I Mobilization and demobilzation of automatic diesel hammer mounted complete rig set. 1. 2. Lifting and carrying crane (both ways) 2 trips Truck fare (8 x 2 trips) in/c loading & unloading by crane 16 trips @ @ Tk. Tk. 25,000.00 4,000.00 Per trip = Tk. 50,000.00 = Tk. 64,000.00 = Tk. 114,000.00 = Tk. 11,400.00 = Tk. 3,990.00 Tk. 129,390.00 4.50% = Tk. 5,822.55 Grand total = Tk. 135,212.55 Per trip Total 10.00% 3.50%

Contractor's profit Overhead expenses VAT

Say, Tk.

135,213 Per set.

ANALYSIS FOR ITEM NO. 65(e)-II

- 212 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

Cost for driving pre-cast pile with automatic rig fitted with automatic diesel hammer: 12" x 12" size pile Consider 5 Nos. Pile (35'-0" each)= 53.33 meter driving in 1 day i. Hire charge of complete rig set (Crane, Hammer, Rig, Generator etc. complete.) 1 day ii. iii. iv. @ Tk. 10,000.00 Fuel, lubricant etc. Tools & plant, consumables, spares, maintenance, insurance etc. Man-power 1. Foreman 2 Nos. @ Tk. 2. Diesel operated rig driver 1 No. @ Tk. 3. Helper to rig driver 8 Nos. @ Tk. 4. Skilled labour 5 Nos. @ Tk. Per day = Tk. 10,000.00 L.S. = Tk. 1,200.00 L.S. = Tk. 1,000.00 Per day Per day Per day Per day Total 10.00% 3.50% = = = = = Tk. 500.00 Tk. 300.00 Tk. 1,200.00 Tk. 600.00 Tk. 14,800.00 Tk. 1,480.00 Tk. 518.00 Tk. 16,798.00 Tk. 755.91 Tk. 17,553.91 Tk. 329.16

250.00 300.00 150.00 120.00

Contractor's profit Overhead expenses VAT

= =

4.50% = Grand total = Rate per meter =

Say, Tk.

329 .00 per meter

ANALYSIS FOR ITEM NO. 65(e)-III Cost for driving pre-cast pile with automatic rig fitted with automatic diesel hammer: 14" x14" size Consider 4 Nos. Pile (40'-0" each)= 48.76 driving in 1 day i. Hire charge of complete Rig set (Crane, Hammer, Rig, Generator etc. complete.) ii. iii. iv. 1 day @ Tk. Fuel, lubricant etc. Tools & plant, consumables, spares, maintenance, insurance etc. Man-power 1. Foreman 2 Nos. @ Tk. 2. Diesel operated rig driver 1 No. @ Tk. 3. Helper to diesel hammer mounted rig driver 8 Nos. @ Tk. 4. Skilled labour 5 Nos. @ Tk. 10,000.00 Per day = Tk. 10,000.00 L.S. = Tk. 1,200.00 L.S. = Tk. 1,000.00 Per day = Tk. Per day = Tk. Per day Per day Total 10.00% 3.50% 500.00 300.00

250.00 300.00 150.00 120.00

Contractor's profit Overhead expenses VAT


- 213 -

= Tk. 1,200.00 = Tk. 600.00 = Tk. 14,800.00 = Tk. 1,480.00 = Tk. 518.00 Tk. 16,798.00 4.50% = Tk. 755.91

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

Grand total = Tk. Rate per meter = Tk. Say, Tk. 360 .00 per meter

17,553.91 360.01

ANALYSIS FOR ITEM NO. 66(a) 7" x 7" x 25'-0" Pile with reinforced cement concrete (1 : 1.25 : 2.5) with stone chips Considering 25 rft. long 1 No. pile Also considering 100 cft. of work A. (a) (b) (c) (d) (e) Cost of materials 19 mm down crushed stone chips 80 cft. Sylhet sand (F.M. 2.5) 40 cft. Cement 25.25 bags Local carriage, sundries, T & P Labour 28 days curring: @ 1/4 No. labour per day. 7 Nos.

@ @ @

Tk. Tk. Tk.

6,500.00 1,330.00 250.00

Per % cft. Per % cft. Per bag L.S.

= = = =

Tk. Tk. Tk. Tk.

5,200.00 532.00 6,312.50 50.00

Tk.

B. C.

Labour, machinery, fuel & lubricants for casting Cost of shuttering (for 39 No. of pile) Assuming 7" x 7" x 25'-0" pile Concrete: 39 x 7" x 7" x 25'-0"= 331.77 cft. a) Cost of steel shuttering: i) 1/12" thick steel plate: @ 3.4 Ib per sft. Sides: 40 x 25'-0" x 0'-7" = 583.33 sft. Add 5% wastage= 29.17 sft. = 612.50 sft. = 2082.50 Ibs @ ii) 1.5" x 1.5" x 3/16" M.S. angle for frame: @ 1.79 Ib per rft. Horizontal: 2 x 40 x 25'-0"= 2000.00 rft. Vertical: 26 x 40 x 0'-7"= 606.67 rft. = 2606.67 rft. Add 5% wastage= 130.334 rft. = 2737.00 rft. = 4899.23 Ibs. @ iii) 1" x 1/4" F.I. bar: @ 0.85 Ib per rft. Stiffner: 13 x 20 x 0'- 10"= 216.67 rft. Add 5% wastage= 10.83 rft. = 227.50 rft. = 193.38 Ibs @ iv) Cost of nuts & bolts: @ 3.5 kg per % sft steel shuter 20.00 kg. @
- 214 -

each = Tk. 700.00 Total = Tk. 12,794.50 Same as item No. 41(a) = Tk. 1,022.50

100.00

Tk.

10.85

Per Ib. = Tk. 22,595.13

Tk.

8.71

Per Ib. = Tk. 42,672.29

Tk. Tk.

7.71 60.00

Per Ib. = Tk. Per kg. = Tk.

1,490.96 1,200.00

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

v) Manufacturing, fitting and fixing frame in/c drilling holes, welding & supplying of chemical etc. 583.33 sft vi) Labour for fitting and fixing steel shuttering in position as required. 40 x 25'-0" x 0'-7"= 583.33 sft vii) Hessian tap for making shutter water-proof 583.33 sft D. Cost of bed preparation Area: 30'-0" x 27'-0"= 810 sft. Concrete: 39 x 7" x 7" x 25'-0= 331.77 cft. a) One layer brick flat soling: 810 sft. b) 1/2 thick cement plaster with neat cement finishing: 810 sft.

Tk.

30.00

Per sft. = Tk. 17,499.90 Sub-Total = Tk. 85,458.28 Using 16 times = Tk. 5,341.14

@ @

Tk. Tk.

4.00 0.50

Per sft. = Tk.

2,333.32 291.67 7,966.13 2,401.10

Per sft. = Tk. Total = Tk. Cost for 100 cft. = Tk.

@ @

Tk. Tk.

11.71 8.82

Per sft. = Tk.

9,485.10

Per sft. = Tk. 7,144.20 Total = Tk. 16,629.30 Cost for 100 cft. of work = Tk. 195,408.93 Using 8 times = Tk. 588.99 117.00 Per % sft. = Tk. Cost for 100 cft. of work = Tk. = = = = = Total = 10.00% = 3.50% = 4.50% Grand total Rate per cft. Rate per rft. Rate per rm Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. 947.70 285.65 12,794.50 1,022.50 2,401.10 588.99 285.65 17,092.74 1,709.27 598.25 19,400.26 873.01 20,273.27 202.73 68.96 226.26

E.

Polythene as separator between pile layers during casting concrete 810.00 sft. @ Tk.

a) b) c) d) e)

Abstract of cost for 100 cft. of work Cost of concrete Labour, machinery, fuel and lubricants for casting Cost of shuttering Cost of bed preparation Cost of polythene Contractor's profit Overhead expenses VAT

=
= = = =

Say,

Tk.

226 .00 Per rm.

ANALYSIS FOR ITEM NO. 66(b)

Driving of 7" x 7" x 25'-0" Pre-cast Pile

- 215 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

Considering 25 rft. long 1 No pile i) Hire charge of driving equipment in/c cost of fuel and lubricant etc. 1/6 day @ Tk. 3,000.00 ii) Labour charge for pile carrying, lifting, shifting and driving etc. complete: a) Rig operator 1/4 No. @ Tk. 180.00 b) Skilled labour 1 No. @ Tk. 120.00 c) Ordinary labour 2.00 Nos. @ Tk. 100.00 Contractor's profit Overhead expenses VAT

Per day = Tk. each each each Total 10.00% 3.50% 4.50% Grand total Rate per rft. Rate per rm = = = = Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

500.00 45.00 120.00 200.00 865.00 86.50 30.28 981.78 44.18 1,025.96 41.04 134.65

= = =
= = =

Say,

Tk.

135 . 00 Per rm.

ANALYSIS FOR ITEM NO. 67 Supplying and driving wooden ballah in Palisading Considering 20 rft. of work a) Cost of ballah in/c carriage 20 rft. b) Labour for driving i) Skilled labour 1 No. ii) Ordinary labour 3 Nos. c) Sundries, removing of skin, sizing and coaltaring in/c hire charge of monkey with driving arranement. @ @ @ Tk. Tk. Tk. 30.00 120.00 100.00 Per rft. = Tk. each = Tk. each = Tk. L.S. Total 10.00% 3.50% 4.50% Grand total Rate per rft. Rate per rm. = Tk. = Tk. = Tk. = Tk. Tk. = Tk. = Tk. = Tk. = Tk. 600.00 120.00 300.00 75.00 1,095.00 109.50 38.33 1,242.83 55.93 1,298.76 64.94 213.07

Contractor's profit Overhead expenses VAT

Say,

Tk.

213 .00 Per rm.

9. M.S. FABRICATION WORK


ANALYSIS FOR ITEM NO. 68(a)
- 216 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

Supplying, fabrication etc of M.S. rod in RCC works in all floors: 40 grade deformed bar with minimum fy = 276

Mpa
Considering 1 cwt of work A. i) ii) B. i) ii) iii) Cost of materials: M.S. rod: 40 grade G.I. wire Cost of labour Rod binder Helper to rod binder Local carriage, T & P etc.

1 cwt. 1 Kg 0.2 Nos. 0.75 Nos.

@ @ @ @

Tk. Tk. Tk. Tk.

1,133.00 50.00 180.00 120.00

Per cwt. = Tk. Per kg. = Tk. each each L.S. Total 10.00% 3.50% = = = = Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

1,133.00 50.00 36.00 90.00 10.00 1,319.00 131.90 46.17 1,497.07 67.37 1,564.44 1,564.44 3,128.88

Contractor's profit Overhead expenses VAT

= = =
= = =

4.50% Grand total Rate per cwt. Rate per quintal

Say,

Tk.

3,129 .00 Per quintal

ANALYSIS FOR ITEM NO. 68(b) Supplying, fabrication etc of M.S. rod in RCC works in all floors: 60 grade deformed bar with minimum fy = 415

Mpa
Considering 1 cwt of work A. i) ii) B. i) ii) iii) Cost of materials: M.S. rod: 60 grade G.I. wire Cost of labour Rod binder Helper to rod bindr Local carriage, T & P etc.

1 cwt. 1 Kg 0.2 Nos. 0.75 Nos.

@ @ @ @

Tk. Tk. Tk. Tk.

1,206.00 50.00 180.00 120.00

Per cwt. = Tk. Per kg. = Tk. each each L.S. Total 10.00% 3.50% = = = = Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

1,206.00 50.00 36.00 90.00 10.00 1,392.00 139.20 48.72 1,579.92 71.10 1,651.02 1,651.02 3,302.04

Contractor's profit Overhead expenses VAT

= = =
= = =

4.50% Grand total Rate per cwt. Rate per quintal

- 217 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

Say,

Tk.

3,302 .00 Per quintal

ANALYSIS FOR ITEM NO. 69 Mild steel work in roof truss Considering 1 cwt. of work i) ii) Cost of M.S. sections 1 cwt. @ Fabrication, fitting, fixing revetting, welding and hoisting in/c cost of revets, bolts etc, and painting complete. 1 cwt. @ Tk. 1,206.00 Per cwt. = Tk. 1,206.00

Tk.

800.00

Contractor's profit Overhead expenses VAT

Per cwt. Total 10.00% 3.50%

4.50% Grand total Rate per cwt. Rate per quintal

= Tk. = Tk. = Tk. = Tk. Tk. = Tk. = Tk. = Tk. = Tk.

800.00 2,006.00 200.60 70.21 2,276.81 102.46 2,379.27 2,379.27 4,758.54

Say,

Tk.

4,759 .00 Per quintal

10. EXPANSION JOINT AND BEARING JOINT


ANALYSIS FOR ITEM NO. 70(a) Construction of expansion joint in RCC floor/ roof slabs or beams with V-folded copper sheet. Considering 10 rft. of work A. B. C. D. Cost of (2 x 4'-0" + 2 x 3-0" + 2" av.) = 16" width copper sheet: 13.33 sft. @ Mason 1 Nos. @ Skilled labour 1 Nos. @ Cost of mastic or hot bitumenous sealing compound fill 10 rft. @

Tk. Tk. Tk. Tk.

70.00 150.00 120.00 20.00

Per sft. = Tk. each = Tk. each = Tk. = Tk. = Tk. = Tk. = Tk. Tk. 4.50% = Tk. Grand total = Tk. Per rft Total 10.00% 3.50%

933.10 150.00 120.00 200.00 1,403.10 140.31 49.11 1,592.52 71.66 1,664.18

Contractor's profit Overhead expenses VAT

- 218 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

Rate per rft. = Tk. Rate per rm = Tk. Say, Tk. 546 .00 Per rm.

166.42 546.02

ANALYSIS FOR ITEM NO. 70(b) Construction of expansion joint in RCC floor/ roof slabs or beams with V-folded Aluminium Water Stop sheet. Considering 10 rft. of work A. B. C. D. Cost of (2 x 4'-0" + 2 x 0'-3" + 2" av.) = 16" width aluminium sheet: 13.33 sft. @ Tk. Mason 1 Nos. @ Tk. Skilled labour 1 Nos. @ Tk. Cost of mastic or hot bitumenous sealing compound fill 10 rft. @ Tk.

40.00 150.00 120.00 20.00

Per sft. = Tk. each = Tk. each = Tk. Per rft Total 10.00% 3.50% 4.50% Grand total Rate per rft. Rate per rm = Tk. = Tk. = Tk. = Tk. Tk. = Tk. = Tk. = Tk. = Tk.

533.20 150.00 120.00 200.00 1,003.20 100.32 35.11 1,138.63 51.24 1,189.87 118.99 390.41

Contractor's profit Overhead expenses VAT

Say,

Tk.

390 .00 Per rm.

ANALYSIS FOR ITEM NO. 70(c) Construction of expansion joint in RCC floor/ roof slabs or beams with V-folded Aluminium Water Stop sheet

and 1/4" thick M.S. Plate..


Considering 10 rft. of work A. B. Cost of (2 x 4'-0" + 2 x 0'-3" + 2" av.) = 16" width aluminium sheet: 13.33 sft. @ Tk. Cost of 1/4" thick & 6" wide M.S. plate: @ 10.20 Ib per sft. 5.00 sft. = 51.05 Ibs @ Tk. Mason 1 Nos. @ Tk. Skilled labour 2 Nos. @ Tk. Cost of mastic or hot bitumenous sealing compound fill and fabrication of steel plate etc. 10 rft. @ Tk.

40.00

Per sft. = Tk.

533.20

C. D. E.

10.85 150.00 120.00

Per Ib = Tk. each = Tk. each = Tk.

553.89 150.00 240.00

22.00

Per rft = Tk. Total = Tk.

220.00 1,697.09

- 219 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

Contractor's profit Overhead expenses

10.00% = Tk. 3.50% = Tk. Tk. VAT 4.50% = Tk. Grand total = Tk. Rate per rft. = Tk. Rate per rm = Tk. 660 .00 Per rm.

169.71 59.40 1,926.20 86.68 2,012.88 201.29 660.43

Say,

Tk.

ANALYSIS FOR ITEM NO. 71 Providing bearing joints fixed or free with 10" x 15" x 3/8" M.S. shoe plate fitted in the truss angle. Considering 1 No. shoe plate

A.

B.

C. D.

Cost of 3/8" thick shoe plate: @ 15.31 Ib per sft. 2 x 0'-10" x 1'-3" = 2.08 sft = 31.84 Ib Cost of 2 Nos. 3/4" anchor rods: @ 1.5 Ib per rft. 2 x 4'-0" = 8 rft. = 12 Ibs Cost of counter sunk revets 10 Nos. Fabrication and fixing in position

Tk.

10.85

Per Ib. = Tk.

345.46

@ @

Tk. Tk.

10.94 20.00

Contractor's profit Overhead expenses VAT

Per Ib. each L.S. Total 10.00% 3.50%

= = = =

= =

4.50% = Grand total = Rate per No. =

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

131.28 200.00 350.00 1,026.74 102.67 35.94 1,165.35 52.44 1,217.79 1,217.79

Say,

Tk.

1,218 .00 per No.

ANALYSIS FOR ITEM NO. 72 Supplying and laying polythene sheet Considering 216 sft. of work Assuming 2 Nos. 9'-0" x 12'-0" pieces with 6" over lap to cover 216 sft. Extra length required: 2 x 9'-0" = 18 rft.

- 220 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

2 x 12'-0" = A. Cost of polythene sheet: 2 x 9'-0" x 12'-0" = Lap: 42 x 0'-6" = = Skilled labour for laying polythene:

24 rft. 42 rft. 216 21 237 1/4 sft. sft. sft. Nos.

B.

@ @

Tk. Tk.

117.00 120.00

Contractor's profit Overhead expenses VAT

Per % sft each Total 10.00% 3.50% 4.50% Grand total Rate per sft. Rate per sqm.

= Tk. = Tk. = Tk. = Tk. = Tk. Tk. = Tk. = Tk. = Tk. = Tk.

277.29 30.00 307.29 30.73 10.76 348.78 15.70 364.48 1.69 18.19

Say,

Tk.

18 .00 Per sqm.

11. LIME TERRACING AND WATER PROOFING


ANALYSIS FOR ITEM NO. 73 Average 4" thick finished lime terracing with 3/4" down graded 1st class brick chips, surki and stone lime (7:2:2) Considering 100 cft. of work A. i) ii) iii) iv) B. i) ii) iii) iv) v) vi) vii) ix) x) C. i) Cost of materials 1st class bricks 820 Nos. @ Tk. Stone lime 539.33 kg. @ Tk. 1st class surki 34.77 cft. @ Tk. Cost for breaking chips 96.47 cft. @ Tk. Labour cost Labour for slacking lime 1 No. Labour for dry mixing 2 Nos. Labour for wet mixing 7 Nos. Labour for lifting and casting 3 Nos. Labour for beating 14 Nos. Labour for 21 days curing 5.25 Nos. Labour for finishing 1 No. Total 33.25 Nos. @ Tk. Head Mason 1 No. @ Tk. Mason for finishing (300 sft.) 2 Nos. @ Tk. Miscellaneous Expenditure for making platform: soling excluding cost of bricks
- 221 -

3,100.00 Per % 0 Nos. 5.00 Per kg 24.00 Per cft. 550.00 Per % cft.

= = = =

Tk. Tk. Tk. Tk.

2,542.00 2,696.65 834.48 530.59

100.00 180.00 150.00

each = Tk. each = Tk. each = Tk. L.S. = Tk.

3,325.00 180.00 300.00 125.00

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

ii) Expenditure for providing polythene cover iii) Local carriage, storage, tools & plants, gumboot, koppa etc. Contractor's profit Overhead expenses VAT

L.S. L.S. Total 10.00% 3.50% 4.50% Grand total Rate per cft. Rate per cum.

= Tk. 100.00 = Tk. 200.00 = Tk. 10,833.72 = Tk. 1,083.37 = Tk. 379.18 Tk. 12,296.27 = Tk. 553.33 = Tk. 12,849.60 = Tk. 128.50 = Tk. 4,537.98

Say,

Tk.

4,538 .00 Per cum.

ANALYSIS FOR ITEM NO. 74 Precast ventilator with 1" thick cement mortar (1:2) including fitting fixing in position. Considering 6 sft. of work a) b) c) d) e) Cement Sand Plaster (1:4) Mason Labour 0.25 1.5 18 0.75 0.50 bag. cft. sft. Nos. Nos. @ @ @ @ @ Tk. Tk. Tk. Tk. Tk. 250.00 990.00 6.95 150.00 100.00 Per bag Per % cft. Per sft. each each Total 10.00% 3.50% 4.50% Grand total Rate per sft. Rate per sqm. = = = = = = Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. 62.50 14.85 125.10 112.50 50.00 364.95 36.50 12.77 414.22 18.64 432.86 72.14 776.51

Contractor's profit Overhead expenses VAT

= = =
= = =

Say,

Tk.

777 .00 Per sqm.

ANALYSIS FOR ITEM NO. 75 3" thick cornice of brick masonry (1:6) Considering 100 rft. of work a) 0'-3" x 0'-3" Brick work (1:6) from item No. 9 6.25 cft. Extra labour for brick moulding & plastering b) @ Tk. 64.44 Per cft. = Tk. 402.75

- 222 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

100 rft. c) (3" + 3" + 3") = 9" width and 1/2" thick cement plaster (1:6) from item No. 123(a) - I 75 sft

Tk.

10.00

Per rft. = Tk.

1,000.00

Tk.

6.95

Contractor's profit Overhead expenses VAT

Per sft. Total 10.00% 3.50% 4.50% Grand total Rate per rft. Rate per rm.

= Tk. = Tk. = Tk. = Tk. Tk. = Tk. = Tk. = Tk. = Tk.

521.25 1,924.00 192.40 67.34 2,183.74 98.27 2,282.01 22.82 74.87

Say,

Tk.

75 .00 Per rm.

ANALYSIS FOR ITEM NO. 76 Fabrication and supplying Fan hook of 5/8" dia M.S. rod in/c fitting fixing in position. Considering 1 No. fan-hook a) 5/8" dia long M.S. rod = b) Fabtication & fitting fixing in position 3.00 rft. 2.01 Ibs

Tk.

10.94

Contractor's profit Overhead expenses VAT

Say,

Tk.

40

= Tk. = Tk. = Tk. = Tk. = Tk. Tk. 4.50% = Tk. Grand total = Tk. Rate per No. = Tk. = .00 Per No.

Per Ib. L.S. Total 10.00% 3.50%

21.99 12.00 33.99 3.40 1.19 38.58 1.74 40.32 40.32

ANALYSIS FOR ITEM NO. 77 Supply, fitting & fixing M.S. flat bar clamps of size 0'-9" x 1.5" for door and windows Considering 1 No. clamp. a) Clamp: 1.5" x 1/4" size F.I. bar = b) Cost of concrete (1:2:4) c) Labour cost 0.75 rft. 0.96 Ibs. 0.1 cft.

@ @

Tk. Tk.

7.71 89.91

Per Ib. = Tk. Per cft. = Tk. L.S. = Tk.

7.40 8.99 12.00

- 223 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

Contractor's profit Overhead expenses

Total = Tk. 10.00% = Tk. 3.50% = Tk. Tk. VAT 4.50% = Tk. Grand total = Tk. Rate per No. = Tk. 34 .00 Per No.

28.39 2.84 0.99 32.22 1.45 33.67 33.67

Say,

Tk.

ANALYSIS FOR ITEM NO. 78 Fitting fixing of chowkat (frame) using rowl plug Considering work for 1 No. frame a) 1.5" x 1/4" size F.I. bar b) c) d) e) f) = 2" rowel plug 2" screw 1.5" screw Cost of drilling 2" depth Labour cost plus carpentry of regened 0.55 0.704 4 4 2 4 rft. Ibs. Nos Nos Nos Nos

@ @ @ @ @

Tk. Tk. Tk. Tk. Tk.

7.71 12.00 1.25 1.00 1.00

Contractor's profit Overhead expenses VAT

Per Ib. Per dozon each each each L.S. Total 10.00% 3.50%

= = = = = = =

= =

4.50% = Grand total = Rate per No. =

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

5.43 4.00 5.00 2.00 4.00 5.00 25.43 2.54 0.89 28.86 1.30 30.16 30.16

Say,

Tk.

30 .00 Per No.

ANALYSIS FOR ITEM NO. 79. Supplying fitting and fixing of 100 mm/4" dia cast iron rain water down pipe Considering 6' ft. long 7 pc.= 42 rft. Labour cost 1. Plumber 2. Helper to plumber

1 No. 2 Nos.

@ @

Tk. Tk.

160.00 120.00

each = Tk. each = Tk.

160.00 240.00

- 224 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

3. 4. 5. 6.

Ordinary labour Scaffolding Price per meter of pipe Fittings, clamp nails etc. for per meter

1 No. 42 rft.

@ @

Tk.

each L.S. Tk. 600.00 Per pc (6'-0") 25% Total Contractor's profit 10.00% Overhead expenses 3.50% VAT 4.50% Grand total Rate per rft. Rate per meter

100.00

= = = = =

= = =
= = =

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

100.00 100.00 4,200.00 1,050.00 5,850.00 585.00 204.75 6,639.75 298.79 6,938.54 165.20 542.02

Say,

Tk.

542 .00 Per rm

ANALYSIS FOR ITEM NO. 80 Supplying, fitting fixing of 100 mm/4" dia u-PVC rain water down pipe. Considering 60 rft.of work Labour cost 1. Plumber 2. Helper to plumber 3. Ordinary labour 4. Scaffolding 5. Price per meter of u-PVC pipe Fittings, clamp nails etc. for per meter 6.

1 No. 2 Nos. 1 No. 60 rft.

@ @ @ @

Tk. Tk. Tk. Tk.

160.00 120.00 100.00 45.15

Contractor's profit Overhead expenses VAT

each each each L.S. Per rft. 30% Total 10.00% 3.50% 4.50% Grand total Rate per rft. Rate per rm.

= = = = = = =

= = =
= = =

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

160.00 240.00 100.00 150.00 2,709.00 812.70 4,171.70 417.17 146.01 4,734.88 213.07 4,947.95 82.47 270.58

Say,

Tk.

271 .00 Per rm

12. C.I. SHEET ROOFING


ANALYSIS FOR ITEM NO. 81(a)

- 225 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

0.45 mm thick galvanized iron corrugated sheet roofing (Bangladesh made) fitted & fixed on M.S section or wooden purlin etc. [1 bundle=70-72 rft=67.00 kg.(app)= 0.067 ton covers 150 sft.] Considering 150 sft. of work Labour cost: 1. Carpenter 2. Helper to carpenter 3. Ordinary labour Bamboo for scaffolding : using 6 times 4.

3/4 No. 3/8 No. 3/4 No. 3 Nos.

@ @ @ @

Tk. Tk. Tk. Tk.

160.00 120.00 100.00 80.00

each = Tk. each = Tk. each = Tk. each = Total= Cost per sft.= Cost per sqm= Tk. Tk. Tk. Tk.

120.00 45.00 75.00 40.00 280.00 1.87 20.13

(I) Galvanized C.I. Sheet: i) Price for per sqm (4.808 kg) ii) Screws, limpet, washer etc. iii) Labour cost

1 sqm.

Tk.

Per sqm. = Tk. 3% = Tk. = Tk. Total = Tk. Contractor's profit 10.00% = Tk. Overhead expenses 3.50% = Tk. Tk. VAT 4.50% = Tk. Grand total = Tk. Rate per sqm. = Tk. Tk. 232 .00 Per sqm.

170.68

170.68 5.12 20.13 195.93 19.59 6.86 222.38 10.01 232.39 232.39

Say,

(II) i) ii) iii)

Coloured: Price for per sqm (4.808 kg) Screws, limpet, washer etc. Labour cost

1 Sqm.

Tk.

Per sqm. = Tk. 3% = Tk. = Tk. Total = Tk. Contractor's profit 10.00% = Tk. Overhead expenses 3.50% = Tk. Tk. VAT 4.50% = Tk. Grand total = Tk. Rate per sqm. = Tk. Tk. 318 .00 Per sqm.

240.40

240.40 7.21 20.13 267.74 26.77 9.37 303.88 13.67 317.55 317.55

Say,

ANALYSIS FOR ITEM NO. 81(b)

- 226 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

1.5 mm thick corrugated fibre glass sheet roofing fixed and fitted on M.S. sections or wooden purlin. Considering 150 sft. of work A. Cost of material i. Cost of fibre glass in/c 15% laping ii. Cost of fitting in/c j-hook B. Labour i. Carpenter ii. Helper to carpenter iii. Ordinary labour 3/4 No. 1/2 No. 1/2 No. 3 Nos. @ @ @ @ Tk. Tk. Tk. Tk. 160.00 120.00 100.00 80.00 each = Tk. each = Tk. each = Tk. each = Tk. Total = Tk. Contractor's profit Overhead expenses VAT 10.00% = Tk. 3.50% = Tk. Tk. 4.50% = Tk. Grand total = Tk. Rate per sft = Tk. Rate per = Tk. sqm. Say, Tk. 567 .00 Per sqm. 120.00 60.00 50.00 40.00 6,666.30 666.63 233.32 7,566.25 340.48 7,906.73 52.71 567.37 172.5 sft. @ Tk. 36.00 Per sft. = Tk. 3% = Tk. 6,210.00 186.30

iv. Bamboo (20'-0" long) for scaffolding: using 6 times

ANALYSIS FOR ITEM NO. 82(a)

Galvanized iron plain sheet ridging with galvanized bolts and nuts

Considering 9.1 (30 rft) meter. of work

i) ii) iii) iv)

Price per rm considering 10% laping Screws, limpet, washer etc. Carpenter Helper to carpenter

10.054 rm 1 No. 1 No.

@ @ @

Tk. Tk. Tk.

49.22 160.00 120.00

Contractor's profit

Per rm = 15% = each = each = Total= 10.00% =

Tk. Tk. Tk. Tk. Tk. Tk.

494.86 74.23 160.00 120.00 849.09 84.91

- 227 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

Overhead expenses

3.50% = Tk. Tk. VAT 4.50% = Tk. Grand total = Tk. Rate per rm = Tk. 110 .00 per rm

29.72 963.72 43.37 1,007.09 110.14

Say, Tk.

ANALYSIS FOR ITEM NO. 82(b)

Colored iron plain sheet ridging with galvanized bolts and nuts

Considering 9.1 (30 rft) meter. of work

i) ii) iii) iv)

Price per rm considering 10% laping 10.054 rm Screws, limpet washer etc. Carpenter Helper to carpenter 1 No. 1 No. @ @ Tk. Tk. 160.00 120.00 @ Tk. 62.89 Per rm = Tk. 15% = Tk. each = Tk. each = Tk. Total= Tk. 10.00% = Tk. 3.50% = Tk. Tk. VAT 4.50% = Tk. Grand total = Tk. Rate per rm = Tk. 632.30 94.85 160.00 120.00 1,007.15 100.72 35.25 1,143.12 51.44 1,194.56 130.65

Contractor's profit Overhead expenses

Say, Tk.

131 .00 per rm

ANALYSIS FOR ITEM NO. 82(c)

1.5 mm thick corrugated fibre glass sheet ridging

- 228 -

Analysis of Rates of P.W.D. Schedule (10th Edition), 16th October 2002

Considering 30 rft. of work A. Cost of material i. Cost of fibre glass in/c 10% laping ii. Cost of screw, washer etc. B. Labour i. Carpenter ii. Helper to carpenter 1 No. 1 No. @ @ Tk. Tk. 160.00 120.00 each = Tk. each = Tk. Total = Tk. Contractor's profit Overhead expenses VAT 10.00% = Tk. 3.50% = Tk. Tk. 4.50% = Tk. Grand total = Tk. Rate per rft= Tk. Rate per rm.= Tk. Say, Tk. 310 .00 Per rm. 160.00 120.00 2,387.38 238.74 83.56 2,709.68 121.94 2,831.62 94.39 309.69 33 rft. @ Tk. 62.00 Per rft. = Tk. 3% = Tk. 2,046.00 61.38

- 229 -

P.W.D. Schedule of Rates, 16th October, 2002 (10th Edition)

8. REINFORCED CEMENT CONCRETE WORK Item No. Description of items Unit Unit Rate

RCC (1:2:4) WITH BRICK-CHIPS & WOODEN SHUTTER 41 Reinforced cement concrete works (1:2:4) with brick-chips having minmum cylinder crushing strength 19 Mpa at 28 days on standard cylinder with cement conforming to BDS 232 & ASTM standards mixed with best quality sand [50% quantity of best local sand (F.M. 1.2) and 50% quantity of Sylhet sand or coarse sand of equivalent F.M. 2.5] and 20 mm down well graded picked jhama brick chips including breaking chips and screening, making, placing in position, making shutter watertight leak-proof properly, placing of rod in position; mixing the aggregates with mixer machine, casting in forms, compacting by vibrator machine and curing at least for 28 days, removing centering-shuttering all complete including cost of water, electricity, testing & other charges as per direction of the engineer-in-charge. a In Individual and combined footing of column. cum b In raft/mat/floor slab at plinth level. cum In Foundation beam c cum 42 Reinforced cement concrete works (1:2:4) with brick-chips having minmum cylinder crushing strength 19 Mpa at 28 days on standard cylinder with cement conforming to BDS 232 & ASTM standards mixed with best quality sand [50% quantity of best local sand (F.M. 1.2) and 50% quantity of Sylhet sand or coarse sand of equivalent F.M. 2.5] and 20 mm down well graded picked jhama brick chips including breaking chips and screening, making, placing in position, making shutter watertight leak-proof properly, placing of rod in position; mixing the aggregates with mixer machine, casting in forms, compacting by vibrator machine and curing at least for 28 days, removing centering - shuttering all complete including cost of water, electricity, testing & other charges as per direction of the engineer-in-charge. In pedestal, column, capital, lift wall and wall (Rate excluding the cost of reinforcement and its fabrication).

Tk. Tk. Tk.

4,432.00 4,140.00 5,103.00

a b c d

Below plinth Level and in Ground floor Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above

cum cum cum cum

Tk. Tk. Tk. Tk.

7,150.00 52.36 73.30 83.77

ahsan/aqa

(54)

P.W.D. Schedule of Rates, 16th October, 2002 (10th Edition)

Item No. 43

Description of items Reinforced cement concrete works (1:2:4) with brick-chips having minmum cylinder crushing strength 19 Mpa at 28 days on standard cylinder with cement conforming to BDS 232 & ASTM standards mixed with best quality sand [50% quantity of best local sand (F.M. 1.2) and 50% quantity of Sylhet sand or coarse sand of equivalent F.M. 2.5] and 20 mm down graded picked jhama brick chips including breaking chips and screening, making, placing in position, making shutter water-tight leak-proof properly, placing of rod in position; mixing the aggregates with mixer machine, casting in forms, compacting by vibrator machine and curing at least for 28 days, removing centering - shuttering all complete including cost of water, electricity, testing & other charges as per direction of the engineer-in-charge. In tie beams and lintels (Rate excluding the cost of reinforcement and its fabrication).

Unit

Unit Rate

a b c d 44

Below plinth level and in ground floor Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above Reinforced cement concrete works (1:2:4) with brick-chips having minmum cylinder crushing strength 19 Mpa at 28 days on standard cylinder with cement conforming to BDS 232 & ASTM standards mixed with best quality sand [50% quantity of best local sand (F.M. 1.2) and 50% quantity of Sylhet sand or coarse sand of equivalent F.M. 2.5] and 20 mm down well graded picked jhama brick chips including breaking chips and screening, making, placing in position, making shutter watertight leak-proof properly, placing of rod in position; mixing the aggregates with mixer machine, casting in forms, compacting by vibrator machine and curing at least for 28 days, removing centering - shuttering all complete including cost of water, electricity, testing & other charges as per direction of the engineer-in-charge. In Tee beam, Ell Beam, Rectangular Beam: Exposed breadth and width of rib to be measured only (Rate excluding the cost of reinforcement and its fabrication).

cum cum cum cum

Tk. Tk. Tk. Tk.

6,256.00 52.36 73.30 83.77

a b c d

Below plinth Level and in Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor 9th floor Add each additional floor for 10th floor & above

cum cum cum cum

Tk. Tk. Tk. Tk.

6,278.00 52.36 73.30 83.77

ahsan/aqa

(55)

P.W.D. Schedule of Rates, 16th October, 2002 (10th Edition)

Item No. 45

Description of items Reinforced cement concrete works (1:2:4) with brick chips having minmum cylinder crushing strength 19 Mpa at 28 days on standard cylinder with cement conforming to BDS 232 & ASTM standards mixed with best quality sand [50% quantity of best local sand (F.M. 1.2) and 50% quantity of Sylhet sand or coarse sand of equivalent F.M. 2.5] and 20 mm down well graded picked jhama brick chips including breaking chips and screening, making, placing in position, making shutter watertight leak-proof properly, placing of rod in position; mixing the aggregates with mixer machine, casting in forms, compacting by vibrator machine and curing at least for 28 days, removing centering - shuttering all complete including cost of water, electricity, testing & other charges as per direction of the engineer-in-charge. In Roof slab of all types, cantilever slab and drop panel, excluding floor slab of ground floor at plinth level. (Rate excluding the cost of reinforcement and its fabrication).

Unit

Unit Rate

a b c d 46

Ground floor Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor. Add for each additional floor for 10th floor & above Reinforced cement concrete works (1:2:4) with brick-chips having minmum cylinder crushing strength 19 Mpa at 28 days on standard cylinder with cement conforming to BDS 232 & ASTM standards mixed with best quality sand [50% quantity of best local sand (F.M. 1.2) and 50% quantity of Sylhet sand or coarse sand of equivalent F.M. 2.5] and 20 mm down well graded picked jhama brick chips including breaking chips and screening, making, placing in position, making shutter watertight leak-proof properly, placing of rod in position; mixing the aggregates with mixer machine, casting in forms, compacting by vibrator machine and curing at least for 28 days, removing centering - shuttering all complete including cost of water, electricity, testing & other charges as per direction of the engineer-in-charge. In waffle or ribbed floor or roof slab. (Rate excluding the cost of reinforcement and its fabrication).

cum cum cum cum

Tk. Tk. Tk. Tk.

6,314.00 52.36 73.30 83.77

a b c d

Ground floor Add for each additional floor up to 5th floor. Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above.

cum cum cum cum

Tk. Tk. Tk. Tk.

9,287.00 52.36 73.30 83.77

ahsan/aqa

(56)

P.W.D. Schedule of Rates, 16th October, 2002 (10th Edition)

Item No. 47

Description of items Reinforced cement concrete works (1:2:4) with brick-chips having minmum cylinder crushing strength 19 Mpa at 28 days on standard cylinder with cement conforming to BDS 232 & ASTM standards mixed with best quality sand [50% quantity of best local sand (F.M. 1.2) and 50% quantity of Sylhet sand or coarse sand of equivalent F.M. 2.5] and 20 mm down well graded picked jhama brick chips including breaking chips and screening, making, placing in position, making shutter watertight leak-proof properly, placing of rod in position; mixing the aggregates with mixer machine, casting in forms, compacting by vibrator machine and curing at least for 28 days, removing centering - shuttering all complete including cost of water, electricity, testing & other charges as per direction of the engineer-in-charge. In Sunshade, Cornice, Railing, Drop wall, Louver and fins: average 62 mm to 87 mm thick. (Rate excluding the cost of reinforcement and its fabrication).

Unit

Unit Rate

a b c d 48

Ground floor Add for each additional floor up to 5th floor. Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above Reinforced cement concrete works (1:2:4) with brick-chips having minmum cylinder crushing strength 19 Mpa at 28 days on standard cylinder with cement conforming to BDS 232 & ASTM standards mixed with best quality sand [50% quantity of best local sand (F.M. 1.2) and 50% quantity of Sylhet sand or coarse sand of equivalent F.M. 2.5] and 20 mm down well graded picked jhama brick chips including breaking chips and screening, making, placing in position, making shutter watertight leak-proof properly, placing of rod in position; mixing the aggregates with mixer machine, casting in forms, compacting by vibrator machine and curing at least for 28 days, removing centering - shuttering all complete including cost of water, electricity, testing & other charges as per direction of the engineer-in-charge. In Stair case slab and steps. (Rate excluding the cost of reinforcement and its fabrication).

sqm sqm sqm sqm

Tk. Tk. Tk. Tk.

697.00 9.88 14.83 19.77

a b c d

Ground floor Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor. Add for each additional floor for 10th floor & above

cum cum cum cum

Tk. Tk. Tk. Tk.

6,207.00 52.36 73.30 83.77

RCC (1:1.5:3) WITH BRICK-CHIPS & WOODEN SHUTTER

ahsan/aqa

(57)

P.W.D. Schedule of Rates, 16th October, 2002 (10th Edition)

Item No. 49

Description of items Reinforced cement concrete works (1:1.5:3) with brick-chips having minmum cylinder crushing strength 21 Mpa at 28 days on standard cylinder with cement conforming to BDS 232 & ASTM standard, best quality sand [50% quantity of best local sand (F.M. 1.2) and 50% quantity of Sylhet sand or coarse sand of equivalent F.M. 2.5] and 20 mm down well graded picked jhama brick chips including breaking chips and screening, making, placing in position, making shuttering water-tight leakproof properly, placing of rod in position; mixing the aggregates with mixer machine, casting in forms, compacting by vibrator machine and curing at least for 28 days, removing centering shuttering etc. all complete including cost of water, electricity, testing & other charges as per direction of the engineer-in-charge. In footing, raft/mat, foundation beam (Rate excluding the cost of reinforcement and its fabrication).

Unit

Unit Rate

a b c. 50

In Individual and combined footing of column. cum In raft/mat/floor slab at plinth level. cum In Foundation beam cum Reinforced cement concrete works (1:1.5:3) with brick-chips having minmum cylinder crushing strength 21 Mpa at 28 days on standard cylinder with cement conforming to BDS 232 & ASTM standard, best quality coarse sand [50% quantity of best local sand (F.M. 1.2) and 50% quantity of Sylhet sand or coarse sand of equivalent F.M. 2.5] and 20 mm down well greded picked jhama brick chips including breaking chips and screening, making, placing in position, making shuttering water-tight leakproof properly, placing of rod in position; mixing the aggregates with mixer machine, casting in forms, compacting by vibrator machine and curing at least for 28 days, removing centering shuttering etc. all complete including cost of water, electricity, testing & other charges as per direction of the engineer-in-charge. In Pedestal, column, capital, lift wall and wall. (Rate excluding the cost of reinforcement and its fabrication).

Tk. Tk. Tk.

4,741.00 4,449.00 5,412.00

a b c d

Below Plinth Level and in Ground floor Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above .

cum cum cum cum

Tk. Tk. Tk. Tk.

7,460.00 52.36 73.30 83.77

ahsan/aqa

(58)

P.W.D. Schedule of Rates, 16th October, 2002 (10th Edition)

Item No. 51

Description of items Reinforced cement concrete works (1:1.5:3) with brick-chips having minmum cylinder crushing strength 21 Mpa at 28 days on standard cylinder with cement conforming to BDS 232 & ASTM standard, best quality coarse sand [50% quantity of best local sand (F.M. 1.2) and 50% quantity of Sylhet sand or coarse sand of equivalent F.M. 2.5] and 20 mm down well graded picked jhama brick chips including breaking chips and screening, making, placing in position, making shuttering water-tight leakproof properly, placing of rod in position; mixing the aggregates with mixer machine, casting in forms, compacting by vibrator machine and curing at least for 28 days, removing centering shuttering etc. all complete including cost of water, electricity, testing & other charges as per direction of the engineer-in-charge. In Tie beam and lintel (Rate excluding the cost of reinforcement and its fabrication).

Unit

Unit Rate

a b c d 52

Ground floor Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above Reinforced cement concrete works (1:1.5:3) with brick-chips having minmum cylinder crushing strength 21 Mpa at 28 days on standard cylinder with cement conforming to BDS 232 & ASTM standard, best quality coarse sand [50% quantity of best local sand (F.M. 1.2) and 50% quantity of Sylhet sand or coarse sand of equivalent F.M. 2.5] and 20 mm down well graded picked jhama brick chips including breaking chips and screening, making, placing in position, making shuttering water-tight leakproof properly, placing of rod in position; mixing the aggregates with mixer machine, casting in forms, compacting by vibrator machine and curing at least for 28 days, removing centering shuttering etc. all complete including cost of water, electricity, testing & other charges as per direction of the engineer-in-charge. In Tee beam, Ell Beam, Rectangular Beam. (Rate excluding the cost of reinforcement and its fabrication).

cum cum cum cum

Tk. Tk. Tk. Tk.

6,565.00 52.36 73.30 83.77

a b c d

(Exposed breadth and width of rib to be measured only). Ground floor Add for each additional floor up to 5th floor. Add for each additional floor from 6th floor to 9th floor. Add for each additional floor for 10th floor & above

cum cum cum cum

Tk. Tk. Tk. Tk.

6,587.00 52.36 73.30 83.77

ahsan/aqa

(59)

P.W.D. Schedule of Rates, 16th October, 2002 (10th Edition)

Item No. 53

Description of items Reinforced cement concrete works (1:1.5:3) with brick-chips having minmum cylinder crushing strength 21 Mpa at 28 days on standard cylinder with cement conforming to BDS 232 & ASTM standard, best quality coarse sand [50% quantity of best local sand (F.M. 1.2) and 50% quantity of Sylhet sand or coarse sand of equivalent F.M. 2.5] and 20 mm down well graded picked jhama brick chips including breaking chips and screening, making, placing in position, making shuttering water-tight leakproof properly, placing of rod in position; mixing the aggregates with mixer machine, casting in forms, compacting by vibrator machine and curing at least for 28 days, removing centering shuttering etc. all complete including cost of water, electricity, testing & other charges as per direction of the engineer-in-charge. In Roof slab of all type, cantilever slab and drop panel, excluding floor slab of ground floor at plinth level. (Rate excluding the cost of reinforcement and its fabrication).

Unit

Unit Rate

a b c d 54

Ground floor. Add for each additional floor up to 5th floor. Add for each additional floor from 6th floor to 9th floor. Add for each additional floor for 10th floor & avobe Reinforced cement concrete works (1:1.5:3) with brick-chips having minmum cylinder crushing strength 21 Mpa at 28 days on standard cylinder with cement conforming to BDS 232 & ASTM standard, best quality coarse sand [50% quantity of best local sand (F.M. 1.2) and 50% quantity of Sylhet sand or coarse sand of equivalent F.M. 2.5] and 20 mm down well graded picked jhama brick chips including breaking chips and screening, making, placing in position, making shuttering water-tight leakproof properly, placing of rod in position; mixing the aggregates with mixer machine, casting in forms, compacting by vibrator machine and curing at least for 28 days, removing centering shuttering etc. all complete including cost of water, electricity, testing & other charges as per direction of the engineer-in-charge. In sunshades, cornices, railings drop walls, Louvers and fins: average 62 mm to 87 mm thick. (Rate excluding the cost of reinforcement and its fabrication).

cum cum cum cum

Tk. Tk. Tk. Tk.

6,623.00 52.36 73.30 83.77

a b c d

Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor. Add for each additional floor 10th floor & above.

sqm sqm sqm sqm

Tk. Tk. Tk. Tk.

720.00 9.88 14.83 19.77

ahsan/aqa

(60)

P.W.D. Schedule of Rates, 16th October, 2002 (10th Edition)

Item No. 55

Description of items Reinforced cement concrete works (1:1.5:3) with brick-chips having minmum cylinder crushing strength 21 Mpa at 28 days on standard cylinder with cement conforming to BDS 232 & ASTM standard, best quality coarse sand [50% quantity of best local sand (F.M. 1.2) and 50% quantity of Sylhet sand or coarse sand of equivalent F.M. 2.5] and 20 mm down well graded picked jhama brick chips including breaking chips and screening, making, placing in position, making shuttering water-tight leakproof properly, placing of rod in position; mixing the aggregates with mixer machine, casting in forms, compacting by vibrator machine and curing at least for 28 days, removing centering shuttering etc. all complete including cost of water, electricity, testing & other charges as per direction of the engineer-in-charge. In Stair case slab and steps. (Rate excluding the cost of reinforcement and its fabrication).

Unit

Unit Rate

a b c d 56

Ground floor Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor. Add for each additional floor 10th floor & above Reinforced cement concrete works (1:1.5:3) using steel material as shutter, having minmum cylinder crushing strength 25 Mpa at 28 days on standard cylinder, with cement conforming to BDS 232 & ASTM standard, best quality coarse sand [ Sylhet sand or coarse sand of equivalent F.M. 2.5], 20 mm down well graded crushed stone chips in/c breaking chips and screening through proper sieves, making, placing in position the centering shuttering, M.S. sheets, steel forms, 40 mm M.S. pipes/50 x 40 mm adjustable pipes (jug pipes) with 150 x 150 x 6 mm base plate having pipe wall thickness 2.5 to 4.5 mm, making shuttering water-tight, placing of rod in position; concrete mixing with mixer machine, casting in forms, compacting by vibrator machine and curing at least for 28 days, removing centering shuttering, all complete including cost of water, eletrcity, testing of materials and concrete & other charges as per direction of the engineer-in-charge. In Individual and combined footing of column. In raft/mat/floor slab at plinth level. In Foundation beam In pedestal, column, capital lift wall and wall: Below plinth Level and in Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above In Tie Beam and lintel : Below plinth Level and in Ground floor. Add for each additional floor up to 5th floor

cum cum cum cum

Tk. Tk. Tk. Tk.

6,516.00 52.36 73.30 83.77

RCC (1:1.5:3) WITH STONE-CHIPS & STEEL SHUTTER

a b c d i) ii) iii) iv) e i) ii)

cum cum cum cum cum cum cum cum cum

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

5,805.00 5,630.00 6,350.00 8,454.00 52.36 73.30 83.77 7,529.00 52.36

ahsan/aqa

(61)

P.W.D. Schedule of Rates, 16th October, 2002 (10th Edition)

Item No. iii) iv) f i) ii) iii) iv) g i) ii) iii) iv) h i) ii) iii) iv) i i) ii) iii) iv) j i) ii) iii) iv)

Description of items Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above In Tee Beam, Ell Beam, Rectangular Beam etc. (exposed breadth and width of ribs to be measured only). Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above In roof slab of all types, cantilever slab and drop panels (excluding floor slab of ground floor at plinth level). Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above In sunshade, cornice, railing drop wall, louver and fins (Average 62 mm to 87 mm thick). Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above In stair case slab and step. Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above In Waffle or Ribbed floor/roof slab. Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above

Unit cum cum

Unit Rate Tk. Tk. 73.30 83.77

cum cum cum cum

Tk. Tk. Tk. Tk.

7,839.00 52.36 73.30 83.77

cum cum cum cum

Tk. Tk. Tk. Tk.

8,335.00 52.36 73.30 83.77

sqm sqm sqm sqm cum cum cum cum cum cum cum cum

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

695.00 9.88 14.83 19.77 7,845.00 52.36 73.30 83.77

Tk. 10,777.00 Tk. Tk. Tk. 52.36 73.30 83.77

ahsan/aqa

(62)

P.W.D. Schedule of Rates, 16th October, 2002 (10th Edition)

Item No. 56M32

Description of items Reinforced cement concrete works (1:1.25:2.5) with approved high range admixture using steel material as shutter, having minmum cylinder crushing strength 32 Mpa at 28 days on standard cylinder, with cement conforming to BDS 232 & ASTM standard, best quality coarse sand [Sylhet sand or coarse sand of equivalent F.M. 2.5], 20 mm down well graded crushed stone chips in/c breaking chips and screening through proper sieves, making, placing in position the centering shuttering, M.S. sheets, steel forms, 40 mm M.S. pipes/50 x 40 mm adjustable pipes (jug pipes) with 150 x 150 x 6 mm base plate having pipe wall thickness 2.5 to 4.5 mm, making shuttering water-tight, placing of rod in position; concrete mixing with mixer machine, casting in forms, compacting by vibrator machine and curing at least for 28 days, removing centering shuttering, all complete including cost of water, Rate excluding the cost of reinforcement and its fabrication, adixture and mix design. Payment of these components to be made on separate items: ref. to item No. 68, 58(c) and 413 (Cement concrete, serial 5.) respectively. In Individual and combined footing of column. In raft/mat/floor slab at plinth level. In Foundation beam In pedestal, column, capital lift wall and wall: Below plinth Level and in Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above In Tie Beam and lintel : Below plinth Level and in Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above In Tee Beam, Ell Beam, Rectangular Beam etc. (exposed breadth and width of ribs to be measured only). Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above In roof slab of all types, cantilever slab and drop panels (excluding floor slab of ground floor at plinth level). Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above In stair case slab and step. Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above In Waffle or Ribbed floor/roof slab.

Unit

Unit Rate

a b c d i) ii) iii) iv) e i) ii) iii) iv) f

cum cum cum cum cum cum cum cum cum cum cum

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

6,055.00 5,880.00 6,600.00 8,705.00 52.36 73.30 83.77 7,779.00 52.36 73.30 83.77

i) ii) iii) iv) g

cum cum cum cum

Tk. Tk. Tk. Tk.

8,090.00 52.36 73.30 83.77

i) ii) iii) iv) h i) ii) iii) iv) i

cum cum cum cum cum cum cum cum

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

8,586.00 52.36 73.30 83.77 8,095.00 52.36 73.30 83.77

ahsan/aqa

(63)

P.W.D. Schedule of Rates, 16th October, 2002 (10th Edition)

Item No. i) ii) iii) iv)

Description of items Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above

Unit cum cum cum cum

Unit Rate Tk. 11,028.00 Tk. 52.36 Tk. 73.30 Tk. 83.77

ahsan/aqa

(64)

P.W.D. Schedule of Rates, 16th October, 2002 (10th Edition)

Item No. 57

Description of items

Unit

Unit Rate

a b c d i) ii) iii) iv) e i) ii) iii) iv) f i) ii) iii) iv) g i) ii) iii) iv) h i) ii) iii)

Reinforced cement concrete works (1:2:4) with stone-chips using steel material as shutter, having minmum cylinder crushing strength 22 Mpa at 28 days on standard cylinder, with cement conforming to BDS 232 & ASTM standard, best quality coarse sand [Sylhet sand or coarse sand of equivalent F.M. 2.5], 20 mm down well graded picked jhama brick chips including breaking chips and screening through proper sieves, making, placing in position the centering and shuttering, steel forms, 40 mm M.S. pipes/50 x 40 mm adjustable pipes (jug pipes) with 150 x 150 x 6 mm base plate having pipe wall thickness 2.5 to 4.5 mm, making shuttering water-tight, placing of rod in position; concrete mixing with mixer machine, casting in forms, compacting by vibrator machine and curing at least for 28 days, removing centering shuttering etc. all complete including cost of water, eletrcity, testing of materials and In Individual and combined footing of column. cum In raft/mat/floor slab at plinth level. cum In Foundation beam In pedestal, column, capital lift wall and wall: Below plinth Level and in Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above In Tie Beam and lintel Below plinth Level and in Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above In Tee Beam, Ell Beam, Rectangular Beam etc. (exposed breadth and width of ribs to be measured only). Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above In roof slab of all types, cantilever slab and drop panels (excluding floor slab of ground floor at plinth level). Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above In sunshade, cornice, railing, drop wall, louver and fins (Average 62 mm to 87 mm thick) Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor cum cum cum cum cum cum cum cum cum cum cum cum cum cum cum cum cum

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

5,596.00 5,421.00 6,141.00 8,246.00 52.36 73.30 83.77 7,320.00 52.36 73.30 83.77

Tk. Tk. Tk. Tk.

7,631.00 52.36 73.30 83.77

Tk. Tk. Tk. Tk.

8,127.00 52.36 73.30 83.77

sqm sm sqm

Tk. Tk. Tk.

679.00 9.88 14.83

ahsan/aqa

(65)

P.W.D. Schedule of Rates, 16th October, 2002 (10th Edition)

Item No. iv) i i) ii) iii) iv) j. i) ii) iii) iv) 58(a)

Description of items Add for each additional floor for 10th floor & above In stair case slab and step. Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above In Waffle or Ribbed floor/roof slab. Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above Extra rate of RCC work at free height beyond 4 m to 11 m over the rate of corresponding items of ground floor or any floor as the case may be, for additional height of auditiorium, godown, overhead water tank etc. in the RCC work of columns, capitals, wall, Tee beam, Ell beam, rectangular beam, roof slab, cantilever slab and drop panel etc. are executed at that height, as per description in corresponding item Nos. 42, 43, 44, 45, 46, 50, 51, 52, 53, 56(d), 56(e), 56(f), 56(g), 56(i), 56(j), 56M32(d), 56M32(e), 56M32(i), 57(d), 57(e), 57(f), 4 In colomn, coloumn56M32(f), capitals, 56M32(g), & walls where the free height exceeds meter (rate is considered for the free height of each additional 4 (four) meter or part beyond 4 meter) In Tee beams, Ell Beams and Rectangular beams placed beyond 4 meter height for each additional meter of free height. In floor/roof slab, Cantilever slab, Waffle slab and drop panels placed beyond 4 meter height for each meter of free height. (The rate shall be extra over the rates of corresponding items. For extra amount on height, the total height from the particular floor upto the top of casting shall be measured and then 4 meter to be deducted. Extra payment shall be admissible only when both sides of wall and beam and all sides of column are uninterruptedly free Supplying and mixing ASTM designated specified type chemical admixture from an authorized local agent or manufacturer, comply with the ASTM C-494 requirements, confirming the current compliance of the admixture to specification requirements like physical properties, uniformity & equivalence in composition etc., performance (water content, fresh concrete setting time and compressive strength) requirements, delivered in sealed water-tight containers having and confirming plainly marked the proprietary name of the admixture type under this specification, net & /or volume, manufacturing and and mixing the admixture inweight non pre-stressed cement concrete mixture in the field under the strict accordance with manufacturers recommendation and instruction, providing safety provisions in all respects etc. all complete as per instruction of Engineer-in-charge.Dose (quantity in milliliters per 50 kg bag cement) and brand with respect to particular brand of cement and particular stock of aggregates and method of use to be determined by engineer - in - charge. (Use of Supply and use of water reducing chemical admixture ASTM C-494 Type - A in concrete: The admixture to reduce quantity of mixing water required for normal workability and to maintain low water-cement (W/C) ratio for improved concrete.

Unit sqm cum cum cum cum cum cum cum cum

Unit Rate Tk. Tk. Tk. Tk. Tk. 19.77 7,636.00 52.36 73.30 83.77

Tk. 10,569.00 Tk. Tk. Tk. 52.36 73.30 83.77

i) ii) iii)

cum cum cum

Tk. Tk. Tk.

222.00 307.00 338.00

58(b)

i)

Liter

Tk.

170.00

ahsan/aqa

(66)

P.W.D. Schedule of Rates, 16th October, 2002 (10th Edition)

Item No. ii)

Description of items Supply and use of retarding chemical admixture ASTM C-494 Type - B in concrete: The admixture for retarding setting time of concrete, there by reducing shrinkage in concrete specially for concrete laid in thick layers and intended delayed construction for improved construction joints, re-concreting etc Supply and use of accelerating chemical admixture ASTM C-494 Type C in concrete: An admixture that is to accelerate the setting time and early strength gain of concrete. Supply and use of water-reducing and retarding chemical admixture ASTM C-494 Type - D in concrete: The admixture to reduce the quantity of mixing water required to produce concrete of given consistency, i.e. low water-cement (W/C) ratio and intend to retard setting time of concrete, specially for layered, thick laid concrete etc. Supply and use of water-reducing and accelerating chemical admixture ASTM C-494 Type - E in concrete: The admixture to reduce the quantity of mixing water required to produce concrete of given consistency, i.e. low water-cement (W/C) ratio and intend to accelerate setting time of concrete, and early strength gain in concrete etc. Supply and use of water-reducing high range chemical admixture ASTM C-494 Type - F in concrete: The admixture required to produce concrete of consistency by 12% or greater for higher strength of concrete.

Unit

Unit Rate

Liter

Tk.

146.00

iii)

Liter

Tk.

181.00

iv)

Liter

Tk.

158.00

v)

Liter

Tk.

170.00

vi)

vii)

58(c)

i)

ii)

iii)

Liter Supply and use of water-reducing high range and retarding chemical admixture ASTM C-494 Type - G in concrete: The admixture required to produce concrete of consistency by 12% or greater for higher strength of concrete and intend to retard setting time of concrete. Liter Supplying, best quality pliable, cold applied pre-formed self adhesive rubberised/ bituminous water proofing membrane from an authorised local agent or manufacturer, having minimum thickness 1.5 mm, lined with 2 ply cross laminated high density polyethylene film performances and properties all conforming to ASTM standards and laying, placing, fixing on made up firm and dry surfaces free from hollows, sharp protrusions, contaminates etc. laid over-lap by at least 75 mm along the edges and 125 mm at ends ensuring good initial bond with the surfaces all complete under the strict accordance with the Water-proofing membrane on external surface of primed vertical or inclined wall /on plastered and primed back-wall and concrete cast against membrane (excluding cost of back fill/brick wall on back/plaster when membrane laid on back-wall and concrete cast against membrane, which to be paid as sqm Water-proofing membrane on made up surface below the floor or below the horizontal surfaces below grades with temporary protective cover using polysterene/1.5" thick sand-cement mortar in 4:1 /or by equally effective alternative (Rate is excluding the cost of protective cover which to be paid sqm as per correspnding membrane items in this on schedule) Water-proofing the floor or on the horizontal surfaces with permanent protective cover & wearing coarse (Rate is excluding the cost of protective cover and wearing coarse which to be paid as per correspnding items sqm

Tk.

176.00

Tk.

164.00

Tk.

742.00

Tk. Tk.

675.00 705.00

ahsan/aqa

(67)

P.W.D. Schedule of Rates, 16th October, 2002 (10th Edition)

Item No. 58(d)

Description of items

Unit

Unit Rate

Water-proofing work in masonry or concrete surface with sandcement mortar mixed with specified admixure (supplied from authorized local agent or from manufacturer comply with ASTM/BS/IS requirements, confirming current compliance of the admixture to specification requirements like physical properties, uniformity and equivalence in composition, performance requirements, delivered in sealed containers having and confirming plainly marked the proprietory name of the admixture type under this specification, net weight & or volume, manufacturing and expiry date, shelve life, non aggressiveness to environment and metals in concrete etc.) under the strict accordance with manufacturer recommendations/instructions and providing safety provisions in all respect etc. on sound, firm surfaces all complete including cleaning the sqm 9. PILE WORK Boring/drilling for cast in situ pile up to the required depth and dia with minimum 6 m long temporary steel casing, true to vertical, providing bentonite slurry and maintaining water level in the hole, washing the hole for at least 30 minutes, clean the bore-hole and make the bore- hole ready for placing steel cage and concreting including hire charge of rig set with winch machine, tripoid stand, trimie pipe, cost of fuel, lubricant, mobilisation, demobilisation, maintainance, spares, standbyes, insurance coverage, water, electricity & other charges all 400 mm dia Up to 20 m Add extra cost for each additional meter beyond 20 meter up to 30 m 450 mm dia up to 20 m Add extra cost for each additional meter beyond 20 meter up to 29m 500 mm dia up to 20 m Add extra cost for each additional meter beyond 20 meter up to 29m 550 mm dia up to 20m Add extra cost for each additional meter beyond 20 meter up to 29m 600 mm dia up to 20m Add extra cost for each additional meter beyond 20 meter up to 29m Reinforced cement concrete works (1:1:5.3) in bore-hole for making cast-in-situ pile having having minimum compressive strength 21 Mpa at 28 days on standard cylinder with cement conforming to BDS 232 & ASTM standard mixed with best quality coarse sand [Sylhet sand or coarse sand of equivalent F.M.2.5], 20 mm down well graded crushed stone chips including breaking chips, screening through proper sieves, making, placing re-bar cage in position, placing & removing tri-pod as per requirement, pouring the concrete in bore-hole with the help of a tremie pipemaintaining the tremie pipe immersed in concrete by at least 1 meter throughout the period of concreting, maintaing required slump etc. mixing the aggregates with mixer machine with hoper, casting in rm rm

Tk.

272.00

59

a A B b A B c A B d A B e A B 60

rm rm rm rm rm rm rm rm

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

339.00 14.00 396.00 17.00 438.00 17.00 490.00 25.00 508.00 27.00

cum

Tk.

6,512.00

ahsan/aqa

(68)

P.W.D. Schedule of Rates, 16th October, 2002 (10th Edition)

Item No. 61

Description of items

Unit

Unit Rate

62

63

64

Providing and making point welding at contact point of the spiral binders at reasonable intervals with the main reinforcements by electric arc welding for construction of cast in situ bored pile carefully with highly oxidised electrodes making the points prominent as per direction per of the engineer-in-charge. The rate is inclusive of cost of all materials, point Tk. labour, tools, plants and equipments, cost of power, mobilisation & Providing and making welded splice by welding of minimum 300 mm length at the lap of main reinforcement in re-bar cage to be placed in bore-hole where necessary by electric arc welding with highly oxidised electrodes making the joint prominent as per direction of the engineer-incharge. (The rate is inclusive of all materials labour, tools plants and all equipments. Cost of power, mobilisation & demobilisation of the same etc. complete in all respects.) per inch Tk. Labour for breaking head of hardened cast in situ bored pile/precast pile up to a required length by any means but without damaging the rest and removing the dismantled materials such as concrete to a safe distance including scraps and cleaning concrete from steel/M.S. rods, straightening & bending of pile bars, preparation and making platform where necessary, carrying, all sorts of handling, stacking the same properly after clearing, levelling and dressing the situ and clearing the bed etc. Complete as per direction of the engineer-in-charge. (Measurement will be given for the actual pile head volume to be broken). cum Tk. Conducting static load test for the cast in situ/precast pile providing required scaffolding, bracing, jacks, pressure test gauge,loading unloading loads, kentledge and other plants and equipment including staging, mobilisation, demobilisation, hire charge, cost of gunny bags & sand and filling sacs/gunny bags for loading, recording readings & preparation of results in standard forms & other incidental charges per standard practice and procedures in/c submission of load test report, furnishing all graph and chart as per standard practice & direction of the engineer-in-charge. For 25 tonne load For 75 tonne load For 125 tonne load For 175 tonne load For 225 tonne load For 275 tonne load For intermediate loading from 25 tonne to 75 tonne for each additional tonne For intermediate loading from 75 tonne to 125 tonne for each additional tonne per test per test per test per test per test per test per test per test

1.78

2.37

1,661.00

a b c d e f 1

Tk. 22,922.00 Tk. 46,422.00 Tk. 70,158.00 Tk. 95,009.00 Tk. 118,508.00 Tk. 142,600.00

Tk.

482.32

Tk.

482.00

ahsan/aqa

(69)

P.W.D. Schedule of Rates, 16th October, 2002 (10th Edition)

Item No. 3

Description of items For intermediate loading from 125 tonne to 175 tonne for each additional tonne For intermediate loading from 175 tonne to 225 tonne for each additional tonne For intermediate loading from 225 tonne to 275 tonne for each additional tonne Pre-cast driven pile with reinforced cement concrete (1.1.5:3) having minimum compressive strength 25 Mpa at 28 days on standard cylinder with cement conforming to BDS 232 & ASTM standard mixed with best quality coarse sand (F.M.2.5), 20 mm down well graded stone chips in mixture machine in/c cost of breaking chips, screening through proper sieves, cleaning and washing, centring and shuttering with M.S sheet, M.S angle, F.I bar, nuts & bolts, preparation of bed, laying polythene, placing of reinforcement cage in position, casting, compacting by vibrators and tapered rods, curing for 28 days etc. in/c cost of water, electricity & other charges, providing pile shoe as per design & drawing, driving the pile up to the design depth as per standard practice or specified method providing head cushion, all equipments including mobilisation, demobilisation & hire charge of driving set, labour, shampering, test of materials & concrete etc. all complete as per design, drawing and Cost of cement concrete: Cost of 300 mm x 300 mm size pre-cast pile Cost of 350 mm x 350 mm size pre-cast pile Cost of pile shoe as per design & drawing Mobilization and demobilization of pre-cast pile driving rig Cost of driving 300 mm x 300 mm size pre-cast pile From 0 meter to 6 meter From 6 meter to 12 meter Fom 12 meter to 15 meter Cost of driving 350 mm x 350 mm size pre-cast pile From 0 meter to 6 meter From 6 meter to 12 meter Fom 12 meter to 15 meter Fom 12 meter to 18 meter Mobilization and demobilization of automatic diesel hammer mounted pre-cast pile driving complete rig set Cost for driving 12"x 12" size pre-cast pile with automatic rig fitted with automatic diesel hammer

Unit per test per test per test

Unit Rate

Tk. Tk. Tk.

532.00 482.00 482.00

4 5 65

(a) (b) (c) d-I d-II a) b) c) d-III a) b) c) d) e-I e-II

rm rm each

Tk. Tk. Tk.

589.00 774.00 922.00 2,016.00 248.00 273.00 300.00 315.00 347.00 381.00 454.00

per set Tk. rm rm rm rm rm rm rm set Tk. Tk. Tk. Tk. Tk. Tk. Tk.

Tk. 135,213.00

rm e-III Cost for driving 14" x 14" size pre-cast pile with automatic rig fitted with automatic diesel hammer rm

Tk.

329.00

Tk.

360.00

ahsan/aqa

(70)

P.W.D. Schedule of Rates, 16th October, 2002 (10th Edition)

Item No. 66

Description of items

Unit

Unit Rate

a b 67

Pre-cast 7" x 7" maximum 25'-0 long driven pile with reinforced cement concrete (1: 1.25: 2.5) having minimum compressive strength 30 Mpa at 28 days on standard cylinder with cement conforming to BDS 232 & ASTM standard mixed with best quality coarse sand (F.M.2.5) and 20 mm down well-graded stone chips in mixture machine, including cost of breaking chips, screening through proper sieves, cleaning and washing, centring and shuttering with M.S sheet, M.S angle, F.I bar, nuts & bolts, preparation of bed, laying polythene, placing of reinforcement cage, casting, compacting by vibrators and tapered rods, curing for 28 days etc. in/c cost of water, electricity & other charges, providing pile shoe as per design & drawing, driving the pile up to the design depth as per standard practice or specified method providing head cushion, all equipments including mobilisation, demobilisation & hire charge of driving set, shampering, test of materials & concrete etc. including carrying all complete as per direction Cost of cement concreteof the engineer-in-charge (excluding the cost Per rm Tk. Cost of driving (size: 7" x 7" up to 25 feet.) per rm Tk. Supplying and driving of locally available best wooden ballah pile having an average dia not less than 150 mm with not less than 175 mm dia at thick end and 125 mm dia at thin end in foundation/retaining purpose to a depth as per design and drawing by any method in/c all arrangement for staging, hoisting, carrying etc. Per rm Tk. 10. M.S. FABRICATION WORK Supplying, fabrication and fixing to details as per design deformed bar reinforcement in concrete in accordance with BSTI standard in/c straightening and cleaning rust, if any, bending & binding in position in/c supply of G.I. wires etc. complete in all respects in all floors.

226.00 135.00

213.00

68

(a) (b) 69

40 grade deformed bar with minimum fy = 276 Mpa, ultimate strength 482 Mpa quintal Tk. 60 grade deformed bar with minimum fy = 415 Mpa, ultimate strength 620 Mpa quintal Tk. Mild steel (Grade - A36) work in roof truss, supplying and fabrication of mild steel sections as per design. Hoisting, fitting and fixing in position with bolts and nuts or rivets or welded and providing two coats of anti-corrosive paint over a prime coat of red oxide paint (measurement to be given for solid steel section only). quintal Tk.

3,129.00 3,302.00

4,759.00

ahsan/aqa

(71)

P.W.D. Schedule of Rates, 16th October, 2002 (10th Edition)

Item No. 70

Description of items 11. EXPANSION JOINT AND BEARING JOINT Constructing expansion joints 25 mm /38 mm gap in R.C.C. floor or roof slab or beam provided with V folded copper/ aluminium water stop sheet with loop notch and inserted 75 mm concrete shoulders, the gap being filled up with mixture of hot applied bitumenous sealing compound etc. all complete as per direction of the engineer-in-charge (excluding the cost of floor shoulders and floor finishes).

Unit

Unit Rate

(a) (b) (c) 71

With copper sheet With Aluminum sheet With Aluminum sheet & 6 mm x 75 mm size MS plate. Providing bearing joints fixed or free with 250 x 375 x 10 mm M.S.(Grade - A36) shoe plate fitted in the truss angles with 16 mm dia M.S. rod counter sunk rivets, welded and anchored to 250 x 375 x 10 mm .M.S shoe plate by two Nos. 19 mm dia M.S. U rod embedded in the bed of the lintel around the reinforcement, cleaning and greasing the joints for all floors etc. all complete as per direction of engineer-incharge. Supplying and laying of single layer polythene sheet weighing one kilogram per 6.5 square meter in floor or any where below cement concrete complete in all respect as per direction of the engineer-incharge.

Rm Rm Rm

Tk. Tk. Tk.

546.00 390.00 660.00

each 72

Tk.

1,218.00

sqm 12. LIME TERRACING AND WATER PROOFING 73 Average 100 mm thick finished lime terracing with 20 mm down graded lst class brick chips (khoa), Surki from lst class bricks and lime (stone lime brought at site, not being powdered in open air and to be slaked in presence of engineer-in-charge and to be measured in volume three days after slaking for using in the mix) in the proportion 7:2:2 (brick chips : suriki : lime) including preparation of the mix on the ground by making a suitable platform under proper polythene cover. Cutting the mix twice daily with lime water (1:10) at least for 7 days until the mix attain desireable consistency. Laying the mix in proper slope, beating the same with standard `koppa' for minimum 7 days to gain maximum consolidation, making ghoondy and neat finishing with lime surki mortar ( 1:2) and for 21 providing polythene cover Precast ventilators of curing minimum 25 days mm thick of any design with cement mortar (1:4) fitted and fixed in position, finished with cement plaster (1:6) including necessary scaffolding and curing, in all floors as per direction of the engineer-in-charge. 75 x 75 mm cornice of brick masonry in cement mortar (1:6) having minimum 12 mm thick cement plaster (1:6) including scaffolding and curing at least for 7 days in all floors as per direction of the engineer-incharge. rm

Tk.

18.00

cum

Tk.

4,538.00

74

sqm 75

Tk.

777.00

Tk.

75.00

ahsan/aqa

(72)

P.W.D. Schedule of Rates, 16th October, 2002 (10th Edition)

Item No. 76

Description of items Supplying fan hook of 16 mm dia M.S. rod (one meter straight length) having rounded hook at the middle of bar in proper size so as to be concealed within fan cup in/c fabrication and fitting fixing in all floor as per direction of the engineer-in-charge.

Unit

Unit Rate

each 77 Supplying, fitting and fixing M.S. flat bar clamp of 175 x 38 x 6 mm size having bifurcated ends to door and window frames with necessary screws and encasing inside the wall with cement concrete (1:2:4) as per direction of the engineer-in-charge. each 78 Supplying, fitting and fixing M.S. flat bar clamp 150 x 38 x 6 mm size having bifurcated ends to door and window frames with royal plug. Necessary screws etc. with the help of electric drill/hammer drill in/c. cutting groove in chowkat if necessary etc. complete in all respect. as per direction of engineer-in-charge. each 13. RAIN WATER PIPE 79 Supplying 100 mm inside dia cast iron rain water down pipe, fitting & fixing in position with head and shoes, bends, trap, tee, offset, clamps and nails etc. complete in all floors as per direction of the engineer-incharge. MAANCO/NISSAN/NANAKHI/GENERAL Brand SNC Brand Supplying 100 mm inside dia best quality uPVC pipe fitting, fixed in position with head and shoes, bends, min.20 mm width F.I. Bar clamp and nails, and in/c all accessories such as round gratting/domed roof gratting bands, sockets as per direction of the engineer-in-charge. rm 14. C.I. SHEET ROOFING 81(a) Supplying, fitting & fixing 0.45 mm thick corrugated galvanized iron sheet (Bangladesh made) having min weight 80.28 kg per bundle fitted and fixed on M.S. sections with 'J' hook or wooden purlins with screws, limpet, washers and putty etc. all complete as per direction of the engineer-in-charge. Galvanised Coloured
Supplying, fitting & fixing 1.5 mm thick fibre glass sheet roofing fitted and fixed on M.S. sections with 'J' hook or wooden purlins with screws. limpet, washers and puty etc. all complete as per direction of the engineer-in -charge. 0.27 mm thick Galvanized iron plain sheet ridging with 300 mm lap on either side fitted and fixed with galvanized bolts and nuts etc. all complete as per direction of the engineer-in-charge. Galvanised Coloured: rm rm

Tk.

40.00

Tk.

34.00

Tk.

30.00

i) ii) 80

rm rm

Tk.

542.00 #REF!

Tk.

271.00

I. II.
81(b)

sqm sqm

Tk. Tk.

232.00 318.00

Tk.

567.00

82.

a b

Tk. Tk.

110.00 131.00

ahsan/aqa

(73)

P.W.D. Schedule of Rates, 16th October, 2002 (10th Edition)

Item No.
c

Description of items
1.5 mm thick plain fibre glass sheet ridging with 300 mm lap on either side fitted and fixed with galvanized bolts and nuts etc. all complete as per direction of the engineer-in-charge.

Unit

Unit Rate

rm

Tk.

310.00

ahsan/aqa

(74)

ANNEXURE - A SHORT FORM OF PWD SCHEDULE OF RATES, 16TH OCTOBER, 2002 (10TH EDITION) DETAIL DESCRIPTION OF THE ITEMS CORRESPOND TO THE RESPECTIVE ITEM IN THE SCHEDULE OF RATES

Item No. i) ii) iii) iv)

Description of items Ground floor Add for each additional floor upto 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor and above 8. REINFORCED CEMENT CONCRETE WORK

Unit sqm sqm sqm sqm

Unit Rate Tk. 1,263.00 Tk. 3.19 Tk. 6.38 Tk. 9.58

RCC (1:2:4) WITH BRICK-CHIPS & WOODEN SHUTTER 41 Reinforced cement concrete works (1:2:4) with brick-chips having minmum cylinder crushing strength 19 Mpa at 28 days on standard cylinder. In footing, raft/mat, foundation beam: (Rate excluding the cost of reinforcement and its fabrication). a b c 42 In Individual and combined footing of column. In raft/mat/floor slab at plinth level. In Foundation beam Reinforced cement concrete works (1:2:4) with brick-chips having minmum cylinder crushing strength 19 Mpa at 28 days on standard cylinder. In pedestal, column, lift floor wall and wall. Below plinth Level andcapital, in Ground Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above Reinforced cement concrete works (1:2:4) with brick-chips having minmum cylinder crushing strength 19 Mpa at 28 days on standard cylinder. In tie beams and lintels. Below plinth level and in ground floor Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above Reinforced cement concrete works (1:2:4) with brick-chips having minmum cylinder crushing strength 19 Mpa at 28 days on standard cylinder. Below plinth Level and in Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor 9th floor Add each additional floor for 10th floor & above Reinforced cement concrete works (1:2:4) with brick chips having minmum cylinder crushing strength 19 Mpa at 28 days on standard cylinder. In Roof slab of all types, cantilever slab and drop panel, excluding floor slab of ground floor at plinth level. Ground floor Add for each additional floor up to 5th floor cum cum cum Tk. Tk. Tk. 4,432.00 4,140.00 5,103.00

a b c d 43

cum cum cum cum

Tk. Tk. Tk. Tk.

7,150.00 52.36 73.30 83.77

a b c d 44 a b c d 45

cum cum cum cum

Tk. Tk. Tk. Tk.

6,256.00 52.36 73.30 83.77

cum cum cum cum

Tk. Tk. Tk. Tk.

6,278.00 52.36 73.30 83.77

a b

cum cum

Tk. Tk.

6,314.00 52.36

ahsan/aqa

(182)

ANNEXURE - A SHORT FORM OF PWD SCHEDULE OF RATES, 16TH OCTOBER, 2002 (10TH EDITION) DETAIL DESCRIPTION OF THE ITEMS CORRESPOND TO THE RESPECTIVE ITEM IN THE SCHEDULE OF RATES

Item No. Description of items c Add for each additional floor from 6th floor to 9th floor. d Add for each additional floor for 10th floor & above 46 Reinforced cement concrete works (1:2:4) with brick-chips having minmum cylinder crushing strength 19 Mpa at 28 days on standard cylinder. a Ground floor b Add for each additional floor up to 5th floor. c Add for each additional floor from 6th floor to 9th floor d Add for each additional floor for 10th floor & above. 47 Reinforced cement concrete works (1:2:4) with brick-chips having minmum cylinder crushing strength 19 Mpa at 28 days on standard cylinder. In Sunshade, Cornice, Railing, Drop wall, Louver and fins: average a Ground floor b Add for each additional floor up to 5th floor. c Add for each additional floor from 6th floor to 9th floor d Add for each additional floor for 10th floor & above 48 Reinforced cement concrete works (1:2:4) with brick-chips having minmum cylinder crushing strength 19 Mpa at 28 days on standard cylinder. a Ground floor b Add for each additional floor up to 5th floor c Add for each additional floor from 6th floor to 9th floor. d Add for each additional floor for 10th floor & above RCC (1:1.5:3) WITH BRICK-CHIPS & WOODEN SHUTTER 49 Reinforced cement concrete works (1:1.5:3) with brick-chips having minmum cylinder crushing strength 21 Mpa at 28 days on standard cylinder. a In Individual and combined footing of column. b In raft/mat/floor slab at plinth level. c. In Foundation beam 50 Reinforced cement concrete works (1:1.5:3) with brick-chips having minmum cylinder crushing strength 21 Mpa at 28 days on standard a Below Plinth Level and in Ground floor b Add for each additional floor up to 5th floor c Add for each additional floor from 6th floor to 9th floor d Add for each additional floor for 10th floor & above . 51 Reinforced cement concrete works (1:1.5:3) with brick-chips having minmum cylinder crushing strength 21 Mpa at 28 days on standard cylinder. a Ground floor b Add for each additional floor up to 5th floor c Add for each additional floor from 6th floor to 9th floor d Add for each additional floor for 10th floor & above 52 Reinforced cement concrete works (1:1.5:3) with brick-chips having minmum cylinder crushing strength 21 Mpa at 28 days on standard cylinder In Tee beam, Ell Beam, Rectangular Beam.

Unit cum cum

Unit Rate Tk. 73.30 Tk. 83.77

cum cum cum cum

Tk. Tk. Tk. Tk.

9,287.00 52.36 73.30 83.77

sqm sqm sqm sqm

Tk. Tk. Tk. Tk.

697.00 9.88 14.83 19.77

cum cum cum cum

Tk. Tk. Tk. Tk.

6,207.00 52.36 73.30 83.77

cum cum cum cum cum cum cum

Tk. Tk. Tk. Tk. Tk. Tk. Tk.

4,741.00 4,449.00 5,412.00 7,460.00 52.36 73.30 83.77

cum cum cum cum

Tk. Tk. Tk. Tk.

6,565.00 52.36 73.30 83.77

ahsan/aqa

(183)

ANNEXURE - A SHORT FORM OF PWD SCHEDULE OF RATES, 16TH OCTOBER, 2002 (10TH EDITION) DETAIL DESCRIPTION OF THE ITEMS CORRESPOND TO THE RESPECTIVE ITEM IN THE SCHEDULE OF RATES

Item No. a b c d 53

a b c d 54

a b c d 55

Description of items Ground floor Add for each additional floor up to 5th floor. Add for each additional floor from 6th floor to 9th floor. Add for each additional floor for 10th floor & above Reinforced cement concrete works (1:1.5:3) with brick-chips having minmum cylinder crushing strength 21 Mpa at 28 days on standard cylinder. In Roof slab of all type, cantilever slab and drop panel, excluding Ground floor. Add for each additional floor up to 5th floor. Add for each additional floor from 6th floor to 9th floor. Add for each additional floor for 10th floor & avobe Reinforced cement concrete works (1:1.5:3) with brick-chips having minmum cylinder crushing strength 21 Mpa at 28 days on standard cylinder. In sunshades, cornices, railings drop walls, Louvers and fins: average Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor. Add for each additional floor 10th floor & above. Reinforced cement concrete works (1:1.5:3) with brick-chips having minmum cylinder crushing strength 21 Mpa at 28 days on standard cylinder In Stair case slab and steps.

Unit cum cum cum cum

Unit Rate Tk. 6,587.00 Tk. 52.36 Tk. 73.30 Tk. 83.77

cum cum cum cum

Tk. Tk. Tk. Tk.

6,623.00 52.36 73.30 83.77

sqm sqm sqm sqm

Tk. Tk. Tk. Tk.

720.00 9.88 14.83 19.77

a Ground floor b Add for each additional floor up to 5th floor c Add for each additional floor from 6th floor to 9th floor. d Add for each additional floor 10th floor & above RCC (1:1.5:3) WITH STONE-CHIPS & STEEL SHUTTER 56 Reinforced cement concrete works (1:1.5:3) with stone chips using steel material as shutter, having minmum cylinder crushing strength 25 Mpa at 28 days on standard cylinder. a In Individual and combined footing of column. b In raft/mat/floor slab at plinth level. c In Foundation beam d In pedestal, column, capital lift wall and wall: i) Below plinth Level and in Ground floor. ii) Add for each additional floor up to 5th floor iii) Add for each additional floor from 6th floor to 9th floor iv) Add for each additional floor for 10th floor & above e In Tie Beam and lintel: i) Below plinth Level and in Ground floor. ii) Add for each additional floor up to 5th floor iii) Add for each additional floor from 6th floor to 9th floor iv) Add for each additional floor for 10th floor & above

cum cum cum cum

Tk. Tk. Tk. Tk.

6,516.00 52.36 73.30 83.77

cum cum cum cum cum cum cum cum cum cum cum

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

5,805.00 5,630.00 6,350.00 8,454.00 52.36 73.30 83.77 7,529.00 52.36 73.30 83.77

ahsan/aqa

(184)

ANNEXURE - A SHORT FORM OF PWD SCHEDULE OF RATES, 16TH OCTOBER, 2002 (10TH EDITION) DETAIL DESCRIPTION OF THE ITEMS CORRESPOND TO THE RESPECTIVE ITEM IN THE SCHEDULE OF RATES

Item No. Description of items f In Tee Beam, Ell Beam, Rectangular Beam etc. (exposed breadth and width of ribs to be measured only). i) Ground floor. ii) Add for each additional floor up to 5th floor iii) Add for each additional floor from 6th floor to 9th floor iv) Add for each additional floor for 10th floor & above g In roof slab of all types, cantilever slab and drop panels (excluding floor slab of ground floor at plinth level). i) Ground floor. ii) Add for each additional floor up to 5th floor iii) Add for each additional floor from 6th floor to 9th floor iv) Add for each additional floor for 10th floor & above h In sunshade, cornice, railing drop wall, louver and fins (Average 62 mm to 87 mm thick). i) Ground floor. ii) Add for each additional floor up to 5th floor iii) Add for each additional floor from 6th floor to 9th floor iv) Add for each additional floor for 10th floor & above i In stair case slab and step. i) Ground floor. ii) Add for each additional floor up to 5th floor iii) Add for each additional floor from 6th floor to 9th floor iv) Add for each additional floor for 10th floor & above j In Waffle or Ribbed floor/roof slab. i) Ground floor. ii) Add for each additional floor up to 5th floor iii) Add for each additional floor from 6th floor to 9th floor iv) Add for each additional floor for 10th floor & above RCC (1:2:4) WITH STONE CHIPS & STEEL SHUTTER 56M32 Reinforced cement concrete works (1:1.25:2.5) with approved high range admixture using steel material as shutter, having minmum cylinder crushing strength 32 Mpa at 28 days on standard cylinder a b c d i) ii) iii) iv) e i) ii) iii) In Individual and combined footing of column. In raft/mat/floor slab at plinth level. In Foundation beam In pedestal, column, capital lift wall and wall: Below plinth Level and in Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above In Tie Beam and lintel : Below plinth Level and in Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor

Unit cum cum cum cum

Unit Rate Tk. Tk. Tk. Tk. 7,839.00 52.36 73.30 83.77

cum cum cum cum

Tk. Tk. Tk. Tk.

8,335.00 52.36 73.30 83.77

sqm sqm sqm sqm cum cum cum cum cum cum cum cum

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

695.00 9.88 14.83 19.77 7,845.00 52.36 73.30 83.77

Tk. 10,777.00 Tk. 52.36 Tk. 73.30 Tk. 83.77

cum cum cum cum cum cum cum cum cum cum

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

6,055.00 5,880.00 6,600.00 8,705.00 52.36 73.30 83.77 7,779.00 52.36 73.30

ahsan/aqa

(185)

ANNEXURE - A SHORT FORM OF PWD SCHEDULE OF RATES, 16TH OCTOBER, 2002 (10TH EDITION) DETAIL DESCRIPTION OF THE ITEMS CORRESPOND TO THE RESPECTIVE ITEM IN THE SCHEDULE OF RATES

Item No. Description of items iv) Add for each additional floor for 10th floor & above f In Tee Beam, Ell Beam, Rectangular Beam etc. (exposed breadth and width of ribs to be measured only). i) ii) iii) iv) g Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above In roof slab of all types, cantilever slab and drop panels (excluding floor slab of ground floor at plinth level). Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above In stair case slab and step. Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above In Waffle or Ribbed floor/roof slab. Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above RCC (1:2:4) WITH STONE CHIPS & STEEL SHUTTER Reinforced cement concrete works (1:2:4) with stone-chips using steel material as shutter, having minmum cylinder crushing strength 22 Mpa at 28 days on standard cylinder. In Individual and combined footing of column. In raft/mat/floor slab at plinth level. In Foundation beam In pedestal, column, capital lift wall and wall: Below plinth Level and in Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above In Tie Beam and lintel Below plinth Level and in Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above

Unit cum

Unit Rate Tk. 83.77

cum cum cum cum

Tk. Tk. Tk. Tk.

8,090.00 52.36 73.30 83.77

i) ii) iii) iv) h i) ii) iii) iv) i i) ii) iii) iv) 57

cum cum cum cum cum cum cum cum cum cum cum cum

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

8,586.00 52.36 73.30 83.77 8,095.00 52.36 73.30 83.77

Tk. 11,028.00 Tk. 52.36 Tk. 73.30 Tk. 83.77

a b c d i) ii) iii) iv) e i) ii) iii) iv)

cum cum cum cum cum cum cum cum cum cum cum

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

5,596.00 5,421.00 6,141.00 8,246.00 52.36 73.30 83.77 7,320.00 52.36 73.30 83.77

ahsan/aqa

(186)

ANNEXURE - A SHORT FORM OF PWD SCHEDULE OF RATES, 16TH OCTOBER, 2002 (10TH EDITION) DETAIL DESCRIPTION OF THE ITEMS CORRESPOND TO THE RESPECTIVE ITEM IN THE SCHEDULE OF RATES

Item No. Description of items f In Tee Beam, Ell Beam, Rectangular Beam etc. (exposed breadth and width of ribs to be measured only). i) ii) iii) iv) g Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above In roof slab of all types, cantilever slab and drop panels (excluding floor slab of ground floor at plinth level). Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above In sunshade, cornice, railing, drop wall, louver and fins (Average 62 mm to 87 mm thick) Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above In stair case slab and step. Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above In Waffle or Ribbed floor/roof slab. Ground floor. Add for each additional floor up to 5th floor Add for each additional floor from 6th floor to 9th floor Add for each additional floor for 10th floor & above Extra rate of RCC work at free height beyond 4 m to 11 m in corresponding item In colomn, coloumn capitals, & walls where the free height exceeds 4 meter (rate to be considered for the free height of each additional 4 (four) meter and part beyond 4 meter) In Tee beams, Ell Beams and Rectangular beams placed beyond 4 meter height; for each additional meter of free height.

Unit

Unit Rate

cum cum cum cum

Tk. Tk. Tk. Tk.

7,631.00 52.36 73.30 83.77

i) ii) iii) iv) h

cum cum cum cum

Tk. Tk. Tk. Tk.

8,127.00 52.36 73.30 83.77

i) ii) iii) iv) i i) ii) iii) iv) j. i) ii) iii) iv) 58(a) i)

sqm sm sqm sqm cum cum cum cum cum cum cum cum

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

679.00 9.88 14.83 19.77 7,636.00 52.36 73.30 83.77

Tk. 10,569.00 Tk. 52.36 Tk. 73.30 Tk. 83.77

cum ii)

Tk.

222.00

cum iii) In floor/roof slab, Cantilever slab, Waffle slab and drop panels placed beyond 4 meter height, for each meter of free height. cum 58(b) Supplying and mixing ASTM designated specified type chemical admixture from an authorized local agent or manufacturer, comply with the ASTM C494 requirements.
(187)

Tk.

307.00

Tk.

338.00

ahsan/aqa

ANNEXURE - A SHORT FORM OF PWD SCHEDULE OF RATES, 16TH OCTOBER, 2002 (10TH EDITION) DETAIL DESCRIPTION OF THE ITEMS CORRESPOND TO THE RESPECTIVE ITEM IN THE SCHEDULE OF RATES

Item No. i) ii) iii) iv) v) vi) vii) 58(c) i) ii) iii) 58(d) 59 a A B b A B c A B d A B e A B 60

Description of items Supply and use of water reducing chemical admixture Type - A in concrete Supply and use of retarding chemical admixture Type - B in concrete Supply and use of accelerating chemical admixture Type - C in concrete Supply and use of water-reducing and retarding chemical admixture Type D in concrete Supply and use of water-reducing and accelerating chemical admixture Type - E in concrete Supply and use of water-reducing high range chemical admixture Type - F in concrete Supply and use of water-reducing high range and retarding chemical admixture (Type - G) in concrete

Unit liter liter liter liter liter liter liter

Unit Rate Tk. 170.00 Tk. 146.00 Tk. 181.00 Tk. Tk. Tk. Tk. 158.00 170.00 176.00 164.00

Supplying, best quality pliable, cold applied pre-formed self adhesive rubberised/ bituminous water proofing membrane having minimum thickness 1.5mm. Water-proofing membrane on external surface of inclined or vertical sqm wall (excluding cost of back fill/brick wall on back/plaster when Water-proofing membrane on made up surface below the floor or below sqm the horizontal surfaces with protective cover Water-proofing membrane on the floor or on the horizontal surfaces sqm with protective cover & wearing coarse Water-proofing work in masonry or concrete surface with sand-cement sqm mortar mixed with specified admixure 9. PILE WORK Boring/drilling for cast in situ pile up to the required depth and dia. 400 mm dia Up to 20 m Add extra cost for each additional meter beyond 20 meter up to 30 m 450 mm dia up to 20 m Add extra cost for each additional meter beyond 20 meter up to 29m 500 mm dia up to 20 m Add extra cost for each additional meter beyond 20 meter up to 29m 550 mm dia up to 20m Add extra cost for each additional meter beyond 20 meter up to 29m 600 mm dia up to 20m Add extra cost for each additional meter beyond 20 meter up to 29m Reinforced cement concrete works (1:1:5.3) in bore-hole for making cast-in-situ pile having having minimum compressive strength 19 Mpa at 28 days on standard cylinder. Providing and making point welding at contact point of the spiral binders. rm rm rm rm rm rm rm rm rm rm

Tk. Tk. Tk. Tk.

742.00 675.00 705.00 272.00

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

339.00 14.00 396.00 17.00 438.00 17.00 490.00 25.00 508.00 27.00

cum per point

Tk.

6,512.00

61

Tk.

1.78

ahsan/aqa

(188)

ANNEXURE - A SHORT FORM OF PWD SCHEDULE OF RATES, 16TH OCTOBER, 2002 (10TH EDITION) DETAIL DESCRIPTION OF THE ITEMS CORRESPOND TO THE RESPECTIVE ITEM IN THE SCHEDULE OF RATES

Item No. Description of items 62 Providing and making welded splice by welding of minimum 300 mm length at the lap of main reinforcement in re-bar cage. 63 Labour for breaking head of hardened cast in situ bored pile/precast pile up to a required length. 64 a b c d e f 1 Conducting static load test for the cast in situ/precast pile. For 25 tonne load For 75 tonne load For 125 tonne load For 175 tonne load For 225 tonne load For 275 tonne load For intermediate loading from 25 tonne to 75 tonne for each additional tonne For intermediate loading from 75 tonne to 125 tonne for each additional tonne

Unit per inch cum

Unit Rate Tk. Tk. 2.37 1,661.00

per test per test per test per test per test per test

Tk. Tk. Tk. Tk. Tk. Tk.

22,922.00 46,422.00 70,158.00 95,009.00 118,508.00 142,600.00

per test 2

Tk.

482.32

per test 3 For intermediate loading from 125 tonne to 175 tonne for each additional tonne per test 4 For intermediate loading from 175 tonne to 225 tonne for each additional tonne per test 5 For intermediate loading from 225 tonne to 275 tonne for each additional tonne per test 65 Pre-cast driven pile with reinforced cement concrete (1.1.5:3) having minimum compressive strength 25 Mpa at 28 days on standard cylinder.

Tk.

482.00

Tk.

532.00

Tk.

482.00

Tk.

482.00

(a) (b) (c) d-I d-II a) b) c) d-III a) b) c) d)

Cost of cement concrete: Cost of 300 mm x 300 mm size pre-cast pile Cost of 350 mm x 350 mm size pre-cast pile Cost of pile shoe as per design & drawing Mobilization and demobilization of pre-cast pile driving rig Cost of driving 300 mm x 300 mm size pre-cast pile From 0 meter to 6 meter From 6 meter to 12 meter Fom 12 meter to 15 meter Cost of driving 350 mm x 350 mm size pre-cast pile From 0 meter to 6 meter From 6 meter to 12 meter Fom 12 meter to 15 meter Fom 12 meter to 18 meter

rm rm each per set rm rm rm rm rm rm rm

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

589.00 774.00 922.00 2,016.00 248.00 273.00 300.00 315.00 347.00 381.00 454.00

ahsan/aqa

(189)

ANNEXURE - A SHORT FORM OF PWD SCHEDULE OF RATES, 16TH OCTOBER, 2002 (10TH EDITION) DETAIL DESCRIPTION OF THE ITEMS CORRESPOND TO THE RESPECTIVE ITEM IN THE SCHEDULE OF RATES

Item No. Description of items e-I Mobilization and demobilization of automatic diesel hammer mounted pre-cast pile driving complete rig set e-II Cost for driving 12"x 12" size pre-cast pile with automatic rig fitted with automatic diesel hammer

Unit

Unit Rate

set

Tk. 135,213.00

rm e-III Cost for driving 14" x 14" size pre-cast pile with automatic rig fitted with automatic diesel hammer rm 66 a b 67 68 (a) (b) 69 Pre-cast driven 7" x 7" x 25' - 0 pile with reinforced cement concrete (1:1.25:2.5) having minimum compressive strength 25 Mpa at 28 days on standard cylinder. Cost of cement concrete (size: 175 mm x 175 mm) Cost of driving (size: 175 mm x 175 mm) up to 8 meters Supplying and driving of locally available best wooden ballah pile. 10. M.S. FABRICATION WORK Supplying, fabrication and fixing to details as per design deformed bar reinforcement in concrete. 40 grade deformed bar with minimum fy = 276 Mpa, ultimate strength 482 Mpa 60 grade deformed bar with minimum fy = 415 Mpa, ultimate strength 620 Mpa Mild steel (Grade - A36) work in roof truss, supplying and fabrication of mild steel sections as per design. 11. EXPANSION JOINT AND BEARING JOINT Constructing expansion joints 25 mm /38 mm gap in R.C.C. floor or roof slab or beam provided with V folded copper/aluminium water stop sheet. With copper sheet With Aluminum sheet With Aluminum sheet & 6 mm x 75 mm size MS plate. Providing bearing joints fixed or free with 250 x 375 x 10 mm M.S.(Grade - A36) shoe plate. Supplying and laying of single layer polythene sheet weighing one kilogram per 6.5 square meter. 12. LIME TERRACING AND WATER PROOFING Average 100 mm thick finished lime terracing (7:2:2) with 20 mm down graded lst class brick chips (khoa), surki from lst class bricks and Precast ventilators of minimum 25 mm thick of any design. 75 x 75 mm cornice of brick masonry in cement mortar (1:6) having minimum 12 mm thick cement plaster (1:6). Supplying fan hook of 16 mm dia M.S. rod (one meter straight length).

Tk.

329.00

Tk.

360.00

Per rm Tk. each rm Tk. Per rm Tk.

226.00 135.00 213.00

quintal quintal quintal

Tk. Tk. Tk.

3,129.00 3,302.00 4,759.00

70

(a) (b) (c) 71 72

Rm Rm Rm each sqm cum sqm rm each

Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk. Tk.

546.00 390.00 660.00 1,218.00 18.00 4,538.00 777.00 75.00 40.00

73 74 75 76

ahsan/aqa

(190)

ANNEXURE - A SHORT FORM OF PWD SCHEDULE OF RATES, 16TH OCTOBER, 2002 (10TH EDITION) DETAIL DESCRIPTION OF THE ITEMS CORRESPOND TO THE RESPECTIVE ITEM IN THE SCHEDULE OF RATES

Item No. Description of items 77 Supplying, fitting and fixing M.S. flat bar clamp of 175 x 38 x 6 mm size having bifurcated ends. 78 Supplying, fitting and fixing M.S. flat bar clamp 150 x 38 x 6 mm size having bifurcated ends. 13. RAIN WATER PIPE 79 Supplying 100 mm inside dia cast iron rain water down pipe. i) NISSAN brand ii) SNC brand 80 Supplying 100 mm inside dia best quality uPVC pipe. 81(a) I. II.
81(b) 82. a b c

Unit each each

Unit Rate Tk. Tk. 34.00 30.00

rm rm rm

Tk. Tk.

542.00 #REF! 271.00

14. C.I. SHEET ROOFING Supplying, fitting & fixing 0.45 mm thick corrugated galvanized iron sheet (Bangladesh made). Galvanised Coloured
Supplying, fitting & fixing 1.5 mm thick fibre glass sheet roofing 0.27 mm thick Galvanized iron plain sheet ridging Galvanised Coloured: 1.5 mm thick plain fibre glass sheet ridging.

sqm sqm

Tk. Tk.
Tk.

232.00 318.00
567.00 110.00 131.00 310.00

rm rm rm

Tk. Tk. Tk.

ahsan/aqa

(191)

Das könnte Ihnen auch gefallen