Beruflich Dokumente
Kultur Dokumente
Abstract
The Gullfaks South, Rimfaks and Gullveig fields have been drilled, completed and tied back to the Gullfaks A platform. Production began on 10 October 1998. New technology was adopted from subsea wellhead to platform. With the exception of 3 Gullfaks South wells, the main drilling program was completed in May 2003, and the field is now in a production and maintenance phase. Although the development has proved to be challenging, the Gullfaks Satellites now provide stable production of 13 000 m3 of oil and exporting 10 MM m3 gas pr. day. This field also provide a basis for a longer life for the Gullfaks platforms, with the opportunity for extended infill drilling on the main field. Thus, the development has created added value to the overall Gullfaks area. After a troublesome start, completion operations became very efficient. Tool and equipment failures were siginificant reduced, and overall completion time reduced from 25 days to, in average, 12 days. The first intervention campaign took place last summer, and revealed some new areas that will be focused this year.
Underwater Technology Conference 2004 Bergen The present reserve estimate is 33 MSm3 oil and 39 MMS m3 gas, with identified upside potentials.
Subsea installations
In 1997-1998, a fourth-generation subsea system with 31 well slots was tied back to the Gullfaks A platform. The subsea systems has been extended to a total of 39 well slots during the Phase II development, with the L and M templates tied back to Gullfaks C. Gullfaks South lies six to 10 kilometers south of GFA and has been developed in Phase I with two four-slot templates to drain the Statfjord formation, one four-slot unit for drainage of the Brent sands and a fourth four-slot template for gas injection into both formations. In Phase II the L and M templates, each equipped with 4 slots, were installed to drain gas and condensate from the Brent sands. Located 16-18 kilometers south-west of GFA, Rimfaks is developed with two four-slot templates to drain the Statfjord and Brent formations. A third five-slot template has been installed for gas injection in both formations. Gullveig lies 11 kilometers south-west of GFA and features one two-slot template. This means that a total of ten seabed templates with 39 slots have been installed for the total Gullfaks Satellites development.
Year
[Fig 1; Production profile] The significant divergence between PDO estimates and historical production is mostly related to reservoir complexity in the main reservoir; Gullfaks South, resulting in significantly lower off takes and reserves than estimated in the PDO. In addition to this, the project struggled with completion efficiency during the first years, which is illustrated by figure 2 and 3. These challenges led to a change in strategy for the field. More emphasis was put on getting Gullveig and Rimfaks on production, and the completion programme was simplified. The data collection programmes were abandoned.
1998 1999 2000 2001 2002 2003 [Fig 2; Downtime distribution pr year]
Average completion time pr. year
70 60 50 40 Days 30 20 10 0 1998 1999 2000 2001 2002 2003
[Fig 3; Completion time; average pr. year] After Transocean Wildcat went off lease, the Borgland Dolphin was introduced in the field during spring 2002. Deepsea Trym continued working as a drilling and completion rig until May 2003. To drill all well sections, and afterwards carry out the completion work became a challenge for both rigs. The lessons learned from this 5 years period of initial completion can be summarized as follows: The single most important issue is to maintain continuity in personnel in all critical positions such as engineering, supervision, ROV, wellhead/HXT system and rig crew. The wellhead/HXT system proved to be reliable and few misruns were encountered. Successful installation is very much dependant upon skills and expertise both from the suppliers and the operators side.
Quality cost
Underwater Technology Conference 2004 Bergen The subsea pool has monitored quality cost during the last three years, and the main areas of concern based on these analysis are the control- and workover systems.
2002 2003
WH/TH
HXT
Control system
Other
[Fig 4; Quality cost - Tools] With respect to installed equipment our focus is on the tree cap design including the ball valve, and the subsea control modules. During the 2003 intervention campaign, the ball valve caused major downtime at several occations. To operate the ballvalve within required accurancy after several years of service proved to be difficult: Accurate alignment is needed to be able to pull the Crown Plug through the ball valve. The solution last year was to change out the complete Tree Cap module including Ball Valve and Crown Plug before starting downhole operations. At Gullfaks Satellites, frequent change out of Subsea Control Modules has also been experienced. This is due to instrument failures within the SCM.
Quality cost - Installed equipment
2002 2003
Manifold
Tubing hanger / CP
Topside
Wellhead
DEBRIS CAP
M ETHANO L LINE
PM V
X OV
AMV
MIV
W ELLHEAD CO NNECTO R
PW V
SERVICE LINE
W ELLHEAD SYSTEM
W O RK -O VER VALV E AN N ULUS M AST ER VALV E AN N ULUS W IN G VALV E PR O DU C TIO N MASTER VALVE PR O DU C TIO N WING VALVE C R OSS O VER VALVE SC ALE IN HIBITO R VALVE W AX IN HIBITO R VALVE M ETHAN O L INJEC TION VALVE
[Figure 6 - HXT] The most important issue is related to operation and testing of the Tree Cap Ball Valve. In order to pull the Tree Cap Crown Plug to get access to the well bore, the Ball Valve has to be open and in good alignment with the wellbore. From the first well in the campaign, this alignment turned out to become a challenge: In K-2 more than 30 hours were spent on pulling the Tree Cap Crown Plug. The problems were related to both equipment design and operational procedures. Two conclusions stand after this campaign: - The Tree Cap design with a ball valve and a plug is not optimal.
Underwater Technology Conference 2004 Bergen The operability of equipment after several years of operation is likely to have deterioted.
This summer interventions are planned with the Seawell monohull vessel, and other concepts will most likely be tested in the coming years. Our continious effort to test different concepts reflects the fact that an intervention system for subsea wells that can provide well interventions at a sustainable rate has not yet been introduced to the marked.
Underwater Technology Conference 2004 Bergen same learning curve and productivity increase onshore as has been seen in offshore operations. As most fields enter into the maintenance/intervention phase and tail production starts to become an important issue for Statoil, more focus will be put on onshore cost related to the subsea tools and equipment.
Networking
In parallell to the mindset that once triggered the subsea pool, a network for Statoils subsea engineers has been operational for several years. This network is administrated from our main office, while the participants are sitting in the various assets. The subsea network is among the most active and succsessful networks within Statoil, with bi-monthly meetings and frequent informal contact between the members. In this network both technical issues and potential collisions between operations have been solved to a mutual satisfaction for the parties involved.
Equipment upgrading
Overall, the equipment has functioned according to specifications, however, some modifications have been initiated based on operational experiences: - S-seal on Internal Tree Cap modified to better withstand forces during setting. - Tree Cap Latch Ring modified with flowby slots to ease cleaning and debris removal during setting. - Tubing Hanger Running Tool modified from 2 to 1 seal at the nose to avoid false indication of correct positioning. - Lower Landing string Assembly modified with improved type Secondary Block system. - HXT Rigidizing Tool installed below Casing Bore Protector to save one trip to wellhead.
Underwater Technology Conference 2004 Bergen would have given a 3 400 m long well. The Gulltopp well from Gullfaks A has a considerably higher risk than a subsea solution, but the overall economy is still much better for the long-reach platform well.
Subsea spud
Gullfaks
~ 8700
[Figure 7 The Gulltopp well] This example clearly indicates that subsea developments in shallow waters carries so high cost that it should be alarming for everyone in the business. The investments for both development of new prospects and interventions in exsisting wells are unaxeptably high compared with fixed installations. Low recovery factor and poor reservoir management is the result. The next issue is the availability of good locations for new templates. The Gullfaks Satellites phase I and II development has placed a total of 10 templates in the area, and good template locations from a drilling point of view may come in conflict with anchor patterns from excisting template. Another aspect of IOR is the recovery factor. On our fields with fixed installations, recovery factor has reached well above 50 %, and we are aiming at +60 %. The recovery factor for subesea developments are so far much lower; the Gullfaks Satellites have a recovery factor of 22 %.
UMBILICAL
MANIFOLD
TRIPLE PORCH
FLOWLINE
CENTRE SECTION
SKINFAKS O
RIMFAKS IOR N