NCT BACK-UP PROJECT, CHITTAGONG Work Program,10th Sept, 2011

S.l. No. Description


1 2 3 4 Segment 1A Segment 2A Segment 4 Open Deep Drain

Work Program of 10 Sept. 2011


Surcharge Material Release Surcharge Material Placement Surcharge Material Placement Bracing fixing Rebar fabrication

Achievement of 9th Sept.2011


Surcharge Material Release in progress Surcharge Material Placement in progress Surcharge Material Placement in progress

Remarks Work of previous day hampered for continuous raining.

5 6 7 8 9

Road Work Rail Relocation Electric Relocation Interlocking Block Dismantling work

Embankment Preparation Embankment Preparation Pole Erection ILB production (2 Plant) CC/RCC Dismantling work at Segment 3 & 4 ILB production (2 Plant) in progress CC/RCC Dismantling work at Segment 3 & 4 in progress Embankment Preparation in progress

(Engr.Nityananda Nandi) Project Manager

NCT BACK-UP PROJECT, CHITTAGONG Work Program,11th Sept, 2011

S.l. No. Description


1 2 3 4 Segment 1A Segment 2A Segment 4 Open Deep Drain

Work Program of 11 Sept. 2011


Surcharge Material Release Surcharge Material Placement Surcharge Material Placement Bracing fixing Rebar fabrication

Achievement of 10th Sept.2011


Surcharge Material Release in progress Surcharge Material Placement in progress Surcharge Material Placement in progress Bracing fixing in progress Rebar fabrication in progress Embankment Preparation in progress Embankment Preparation in progress Pole Erection in progress ILB production (2 Plant) in progress CC/RCC Dismantling work at Segment 3 & 4 in progress

Remarks

5 6 7 8 9

Road Work Rail Relocation Electric Relocation Interlocking Block Dismantling work

Embankment Preparation Embankment Preparation Pole Erection ILB production (2 Plant) CC/RCC Dismantling work at Segment 3 & 4

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,12th Sept, 2011

S.l. No. Description


1 2 3 4 Segment 1A Segment 2A Segment 1(part) Open Deep Drain

Work Program of 12 Sept. 2011


Surcharge Material Release Surcharge Material Placement Sub grade Preparation Bracing fixing Rebar fabrication

Achievement of 11th Sept.2011


Surcharge Material Release in progress Surcharge Material Placement in progress

Remarks

Bracing fixing in progress Rebar fabrication in progress Embankment Preparation in progress Embankment Preparation in progress Pole Erection in progress ILB production (2 Plant) in progress CC/RCC Dismantling work at Segment 3 & 4 in progress

5 6 7 8 9

Road Work Rail Relocation Electric Relocation Interlocking Block Dismantling work

Embankment Preparation Embankment Preparation Pole Erection ILB production (2 Plant) CC/RCC Dismantling work at Segment 3 & 4

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,13th Sept, 2011

S.l. No. Description


1 2 3 4 Segment 1A Segment 2A Segment 1(part) Open Deep Drain

Work Program of 13 Sept. 2011


Surcharge Material Release Surcharge Material Placement Sub grade Preparation Bracing fixing Rebar fabrication Earth Excavation(CH 850-870 & Rail Culvert adjacent)

Achievement of 12th Sept.2011


Surcharge Material Release in progress Surcharge Material Placement in progress Sub grade Preparation in progress Bracing fixing in progress Rebar fabrication in progress

Remarks

5 6

Road Work Rail Relocation

Embankment Preparation Embankment Preparation Allignment check by CPA,BRTC & Railway

Embankment Preparation in progress Embankment Preparation in progress

7 8 9 10

RCC Drainage Pipe Electric Relocation Interlocking Block Dismantling work

Plant Shifting Pole Erection ILB production (2 Plant) CC/RCC Dismantling work at Segment 3 & 4

Plant Shifting in progress Pole Erection in progress ILB production (2 Plant) in progress CC/RCC Dismantling work at Segment 3 & 4 in progress

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,13th Sept, 2011

S.l. No. Description


1 2 3 4 Segment 1A Segment 2A Segment 1(part) Open Deep Drain

Work Program of 14 Sept. 2011


Surcharge Material Release Surcharge Material Placement Sub grade Preparation Bracing fixing Rebar fabrication Earth Excavation(CH 850-870 & Rail Culvert adjacent)

Achievement of 13th Sept.2011


Surcharge Material Release in progress Surcharge Material Placement in progress Sub grade Preparation in progress Bracing fixing in progress Rebar fabrication in progress

Remarks

5 6

Road Work Rail Relocation

Embankment Preparation Embankment Preparation Allignment check by CPA,BRTC & Railway

Embankment Preparation in progress Embankment Preparation in progress

7 8 9 10 11

Sheet Pile RCC Drainage Pipe Electric Relocation Interlocking Block Dismantling work

Concrete Pouring Plant Shifting Pole Erection ILB production (2 Plant) CC/RCC Dismantling work at Segment 3 & 4

Rebar fabrication and shuttering Plant Shifting in progress Pole Erection in progress ILB production (2 Plant) in progress CC/RCC Dismantling work at Segment 3 & 4 in progress

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,15th Sept, 2011

S.l. No. Description


1 2 3 4 Segment 1A Segment 2A Segment 1(part) Open Deep Drain

Work Program of 15 Sept. 2011


Surcharge Material Release Surcharge Material Placement Sub grade Preparation Bracing fixing Rebar fabrication Earth Excavation(CH 850-870 & Rail Culvert adjacent)

Achievement of 14th Sept.2011


Surcharge Material Release in progress Surcharge Material Placement in progress Sub grade Preparation in progress Bracing fixing in progress Rebar fabrication in progress

Remarks

5 6

Road Work Rail Relocation

Embankment Preparation Embankment Preparation

Embankment Preparation in progress Embankment Preparation in progress Allignment checked by CPA,BRTC & Railway

Last day's expected progress held back for rain

7 8 9 10 11

Sheet Pile RCC Drainage Pipe Electric Relocation Interlocking Block Dismantling work

Concrete Pouring Plant Shifting Pole Erection ILB production (2 Plant) CC/RCC Dismantling work at Segment 3 & 4

Rebar fabrication and shuttering Plant Shifting in progress Pole Erection in progress ILB production in progress CC/RCC Dismantling work at Segment 3 & 4 in progress

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,21th Sept, 2011

S.l. No. Description


1 2 3 4 Segment 1A Segment 2A Segment 1(part) Open Deep Drain

Work Program of 21 Sept. 2011


Test Boring Surcharge Material Placement Sub grade Preparation Bracing fixing PC Bracing Casting Rebar fabrication CC Casting (CH 840-870 )

Achievement of 20th Sept.2011

Remarks

Surcharge Material Placement in progress Sub grade Preparation in progress Bracing fixing in progress PC Bracing Casting in Progress Rebar fabrication in progress Earth Excavation Executed Embankment Preparation in progress Embankment Preparation in progress Concrete Pouring in progress Plant Shifting in progress Pole Erection in progress ILB production in progress CC/RCC Dismantling work at Segment 3 & 4 in progress

5 6 7 8 9 10 11

Road Work Rail Relocation Sheet Pile RCC Drainage Pipe Electric Relocation Interlocking Block Dismantling work

Embankment Preparation Embankment Preparation Concrete Pouring Plant Shifting Pole Erection ILB production (2 Plant) CC/RCC Dismantling work at Segment 3 & 4

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,22th Sept, 2011

S.l. No. Description


1 2 3 4 Segment 1A Segment 2A Segment 1(part) Open Deep Drain

Work Program of 22 Sept. 2011


Test Boring Surcharge Material Placement Sub grade Preparation Bracing fixing PC Bracing Casting Rebar fabrication CC Casting (CH 840-870 )

Achievement of 21 th Sept.2011
Test Boring in progress Surcharge Material Placement in progress Sub grade Preparation in progress Bracing fixing in progress PC Bracing Casting in Progress Rebar fabrication in progress Earth Excavation Executed Embankment Preparation in progress Embankment Preparation in progress Concrete Pouring in progress Plant Shifting in progress Pole Erection in progress ILB production in progress CC/RCC Dismantling work at Segment 3 & 4 in progress

Remarks

5 6 7 8 9 10 11

Road Work Rail Relocation Sheet Pile RCC Drainage Pipe Electric Relocation Interlocking Block Dismantling work

Embankment Preparation Embankment Preparation Concrete Pouring Plant Shifting Pole Erection ILB production (2 Plant) CC/RCC Dismantling work at Segment 3 & 4

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,23th Sept, 2011

S.l. No. Description


1 2 3 4 Segment 1A Segment 2A Segment 1(part) Open Deep Drain

Work Program of 23 Sept. 2011


Test Boring Surcharge Material Placement 150 mm sand filling Bracing fixing PC Bracing Casting Rebar fabrication Rebar fabrication of Base (CH 840-870 )

Achievement of 22 th Sept.2011
Test Boring in progress Surcharge Material Placement in progress Sub grade Preparation finished Bracing fixing in progress PC Bracing Casting in Progress Rebar fabrication in progress CC casting finished Embankment Preparation in progress Embankment Preparation in progress Concrete Pouring in progress Plant Shifting in progress Pole Erection in progress ILB production in progress CC/RCC Dismantling work at Segment 2 & 3 in progress

Remarks

5 6 7 8 9 10 11

Road Work Rail Relocation Sheet Pile RCC Drainage Pipe Electric Relocation Interlocking Block Dismantling work

Embankment Preparation Embankment Preparation Concrete Pouring Plant Shifting Pole Erection ILB production (2 Plant) CC/RCC Dismantling work at Segment 2 & 3

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,24 th Sept, 2011

S.l. No. Description


1 2 3 Segment 1A Segment 2A Segment 1(part)

Work Program of 24 Sept. 2011


Preparing the ground for RCC drainage pipe placement Surcharge Material Placement Field density test for 150mm sand layer 300mm sand blanket laying

Achievement of 23 th Sept.2011
Test Boring executed Surcharge Material Placement in progress 150 mm local sand compaction executed

Remarks

Open Deep Drain

Bracing fixing PC Bracing Casting Rebar fabrication Concrete pouring of Base (CH 840-870 )

Bracing fixing in progress PC Bracing Casting in Progress Rebar fabrication in progress Rebar fabrication & Shuttering executed Embankment Preparation in progress Embankment Preparation in progress Concrete Pouring in progress Plant Shifting in progress Pole Erection in progress ILB production in progress CC/RCC Dismantling work at Segment 2 & 3 in progress

5 6 7 8 9 10 11

Road Work Rail Relocation Sheet Pile RCC Drainage Pipe Electric Relocation Interlocking Block Dismantling work

Embankment Preparation Embankment Preparation Concrete Pouring Plant Shifting Pole Erection ILB production (2 Plant) CC/RCC Dismantling work at Segment 2 & 3

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,25 th Sept, 2011

S.l. No. Description


1 2 3 Segment 1A Segment 2A Segment 1(part)

Work Program of 25 Sept. 2011


Preparing the ground for RCC drainage pipe placement Surcharge Material Placement 300 mm sand blanket laying PVD Driving

Achievement of 24 th Sept.2011
Test Boring executed Surcharge Material Placement in progress 300 mm sand blanket laying in progress

Remarks

Open Deep Drain

Bracing fixing PC Bracing Casting Rebar fabrication & Shuttering of wall (CH 840-860 ) CC Casting (CH 860-870 )

Bracing fixing in progress PC Bracing Casting in Progress Concrete Pouring of Base executed Earth excavation & Soling executed Earth excavation & Soling executed Embankment Preparation in progress Embankment Preparation in progress Concrete Pouring in progress Plant Shifting in progress Pole Erection in progress ILB production in progress CC/RCC Dismantling work at Segment 2 & 3 in progress

5 6 7 8 9 10 11 12

Open Deep Drain(Culvert adjacent portion) Road Work Rail Relocation Sheet Pile RCC Drainage Pipe Electric Relocation Interlocking Block Dismantling work

CC Casting Embankment Preparation Embankment Preparation Concrete Pouring Plant Shifting Pole Erection ILB production (2 Plant) CC/RCC Dismantling work at Segment 2 & 3

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,26 th Sept, 2011

S.l. No. Description


1 2 3 Segment 1A Segment 2A Segment 1(part)

Work Program of 26 Sept. 2011


Preparing the ground for RCC drainage pipe placement Surcharge Material Placement 300 mm sand blanket laying PVD Driving

Achievement of 25 th Sept.2011
Test Boring executed Surcharge Material Placement in progress 300 mm sand blanket laying in progress

Remarks

Open Deep Drain

Bracing fixing PC Bracing Casting Concrete pouring of wall (CH 840-860 ) Concrete pouring of Base (CH 860-870 )

Bracing fixing in progress PC Bracing Casting in Progress Rebar fabrication & shuttering executed CC executed Earth excavation & Soling executed Embankment Preparation in progress Embankment Preparation in progress Concrete Pouring in progress Plant Shifting in progress Pole Erection in progress ILB production in progress CC/RCC Dismantling work at Segment 2 & 3 in progress

5 6 7 8 9 10 11 12

Open Deep Drain(Culvert adjacent portion) Road Work Rail Relocation Sheet Pile RCC Drainage Pipe Electric Relocation Interlocking Block Dismantling work

CC Casting Embankment Preparation Embankment Preparation Concrete Pouring Plant Shifting Pole Erection ILB production (2 Plant) CC/RCC Dismantling work at Segment 2 & 3

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,27 th Sept, 2011

Description Segment 1A Segment 2A Segment 1(part)

Work Program of 27 Sept. 2011 Preparing the ground for RCC drainage pipe placement Surcharge Material Placement PVD Driving Sub grade preparation

Achievement of 26 th Sept.2011 Test Boring executed Surcharge Material Placement in progress 300 mm sand blanket compaction executed

Remarks

Open Deep Drain

Bracing fixing PC Bracing Casting Earth Excavation (CH 820-840)

Bracing fixing in progress PC Bracing Casting in Progress

Concrete pouring of wall, country side 1st lift(CH Concrete pouring of wall yard side 1st lift 840-860 ) Concrete pouring of wall yard side 1st lift (CH 860Concrete pouring of Base executed (CH 860-875 ) 875 ) Open Deep Drain(Culvert adjacent Road Work Rail Relocation Sheet Pile RCC Drainage Pipe Electric Relocation Laboratory Interlocking Block Dismantling work Rebar fabrication of Base Embankment Preparation Embankment Preparation Concrete Pouring Plant Shifting Pole Erection Mix design of C40 ILB production (2 Plant) CC/RCC Dismantling work at Segment 2 & 3 ILB production in progress CC/RCC Dismantling work at Segment 2 & 3 in progress CC Executed Embankment Preparation in progress Embankment Preparation in progress Concrete Pouring in progress Plant Shifting in progress Pole Erection in progress

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,28 th Sept, 2011


S.l. No. Description 1 2 3 Segment 1A Segment 2A Segment 1(part) Sub grade preparation Bracing fixing PC Bracing Casting 4 Open Deep Drain Earth Excavation (CH 820-840) Concrete pouring of wall, country side 1st lift(CH 840-860 ) Sub grade preparation in progress Bracing fixing in progress PC Bracing Casting in Progress Earth Excavation (CH 820-840) in progress Concrete pouring of wall yard side 1st lift Work Program of 28 Sept. 2011 Preparing the ground for RCC drainage pipe placement Surcharge Material Placement PVD Driving Achievement of 27 th Sept.2011 Test Boring executed Surcharge Material Placement in progress 300 mm sand blanket compaction executed
Remarks

Concrete pouring of wall yard side 1st lift (CH 860Concrete pouring of Base executed (CH 860-875 ) 875 ) 5 6 7 8 9 10 11 12 13 Open Deep Drain(Culvert adjacent portion) Road Work Rail Relocation Sheet Pile RCC Drainage Pipe Electric Relocation Laboratory Interlocking Block Dismantling work Rebar fabrication of Base Embankment Preparation Embankment Preparation Concrete Pouring Concrete Pouring of Pipe Circuit (33/33/11/0.44 KV ) overhead cable fixing Mix design of C40 ILB production (2 Plant) CC/RCC Dismantling work at Segment 2 & 3 ILB production in progress CC/RCC Dismantling work at Segment 2 & 3 in progress CC Executed Embankment Preparation in progress Embankment Preparation in progress Concrete Pouring in progress Plant Shifting in progress Circuit (33/33/11/0.44 KV ) overhead cable fixing in progress

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,29 th Sept, 2011


S.l. No. Description 1 2 3 Segment 1A Segment 2A Segment 1(part) Sub grade preparation Bracing fixing PC Bracing Casting 4 Open Deep Drain Earth Excavation (CH 820-840) Concrete pouring of wall, country side 1st lift(CH 840-860 ) Sub grade preparation in progress Bracing fixing in progress PC Bracing Casting in Progress Earth Excavation (CH 820-840) in progress Concrete pouring of wall yard side 1st lift Work Program of 29 Sept. 2011 Preparing the ground for RCC drainage pipe placement Surcharge Material Placement PVD Driving Achievement of 28 th Sept.2011 Test Boring executed Surcharge Material Placement in progress 300 mm sand blanket compaction executed
Remarks

Concrete pouring of wall yard side 1st lift (CH 860Concrete pouring of Base executed (CH 860-875 ) 875 ) 5 6 7 8 9 10 11 12 13 Open Deep Drain(Culvert adjacent portion) Road Work Rail Relocation Sheet Pile RCC Drainage Pipe Electric Relocation Laboratory Interlocking Block Dismantling work ILB production (2 Plant) CC/RCC Dismantling work at Segment 2 & 3 ILB production in progress CC/RCC Dismantling work at Segment 2 & 3 in progress Rebar fabrication of Base Embankment Preparation Embankment Preparation Concrete Pouring Concrete Pouring of Pipe Circuit (33/33/11/0.44 KV ) overhead cable fixing CC Executed Embankment Preparation in progress Embankment Preparation in progress Concrete Pouring in progress Concrete Pouring of Pipe in progress Circuit (33/33/11/0.44 KV ) overhead cable fixing in progress

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,1st Oct, 2011


S.l. No. Description 1 2 3 Segment 1A Segment 2A Segment 1(part) Sub grade preparation Bracing fixing PC Bracing Casting 4 Open Deep Drain Earth Excavation (CH 820-840) Concrete pouring of wall, country side 1st lift(CH 840-860 ) Sub grade preparation in progress Bracing fixing in progress PC Bracing Casting in Progress Earth Excavation (CH 820-840) in progress Concrete pouring of wall yard side 1st lift Work Program of 1st Oct. 2011 Preparing the ground for RCC drainage pipe placement Surcharge Material Placement PVD Driving Achievement of 30 th Sept.2011 Test Boring executed Surcharge Material Placement in progress 300 mm sand blanket compaction executed
Remarks

Concrete pouring of wall yard side 1st lift (CH 860Concrete pouring of Base executed (CH 860-875 ) 875 ) 5 6 7 8 9 10 11 12 13 Open Deep Drain(Culvert adjacent portion) Road Work Rail Relocation Sheet Pile RCC Drainage Pipe Electric Relocation Laboratory Interlocking Block Dismantling work ILB production (2 Plant) CC/RCC Dismantling work at Segment 2 & 3 ILB production in progress CC/RCC Dismantling work at Segment 2 & 3 in progress Rebar fabrication of Base Embankment Preparation Embankment Preparation Concrete Pouring Concrete Pouring of Pipe Circuit (33/33/11/0.44 KV ) overhead cable fixing CC Executed Embankment Preparation in progress Embankment Preparation in progress Concrete Pouring in progress Concrete Pouring of Pipe in progress Circuit (33/33/11/0.44 KV ) overhead cable fixing in progress

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,2nd Oct, 2011


S.l. No. Description 1 2 3 Segment 1A Segment 2A Segment 1(part) 150mm sand filling Bracing fixing PC Bracing Casting 4 Open Deep Drain Earth Excavation (CH 820-840) 150mm sand filling in progress Bracing fixing in progress PC Bracing Casting in Progress Earth Excavation (CH 820-840) in progress Work Program of 2nd Oct. 2011 Earth excavation for Drainage pipe laying Surcharge Material Placement PVD Driving Achievement of 1st Oct.2011 Layout fixing executed Surcharge Material Placement in progress PVD Driving in progress
Remarks

Concrete pouring of wall yard side 1st lift (CH 860Concrete pouring of Base executed (CH 860-875 ) 875 ) 5 6 7 8 9 10 11 12 13 14 Open Deep Drain(Culvert adjacent portion) Road Work Rail Relocation Sheet Pile RCC Drainage Pipe Electric Substation Electric Relocation Laboratory Interlocking Block Dismantling work ILB production (2 Plant) CC/RCC Dismantling work at Segment 2 & 3 ILB production in progress CC/RCC Dismantling work at Segment 2 & 3 in progress Rebar fabrication of Base Embankment Preparation Embankment Preparation Concrete Pouring Concrete Pouring of Pipe Earth Excavation Circuit (33/33/11/0.44 KV ) overhead cable fixing CC Executed Embankment Preparation in progress Embankment Preparation in progress Concrete Pouring in progress Concrete Pouring of Pipe in progress Layout fixing executed Circuit (33/33/11/0.44 KV ) overhead cable fixing in progress

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,3rd Oct, 2011


S.l. No. Description 1 2 3 Segment 1A Segment 2A Segment 1(part) 150mm sand filling Bracing fixing PC Bracing Casting 4 Open Deep Drain Earth Excavation (CH 800-820) Soling & CC Work (CH 820-840) 5 6 7 8 9 10 11 12 13 14 Open Deep Drain(Culvert adjacent portion) Road Work Rail Relocation Sheet Pile RCC Drainage Pipe Electric Substation Electric Relocation Laboratory Interlocking Block Dismantling work ILB production (2 Plant) CC/RCC Dismantling work at Segment 2 & 3 ILB production in progress CC/RCC Dismantling work at Segment 2 & 3 in progress Rebar fabrication of Base Embankment Preparation Embankment Preparation Concrete Pouring Concrete Pouring of Pipe Earth Excavation Circuit (33/33/11/0.44 KV ) overhead cable fixing CC Executed Embankment Preparation in progress Embankment Preparation in progress Concrete Pouring in progress Concrete Pouring of Pipe in progress Layout fixing executed Circuit (33/33/11/0.44 KV ) overhead cable fixing in progress 150mm sand filling in progress Bracing fixing in progress PC Bracing Casting in Progress Earth Excavation (CH 820-840) in progress Work Program of 3rd Oct. 2011 Earth excavation for Drainage pipe laying Surcharge Material Placement PVD Driving Achievement of 2nd Oct.2011 Layout fixing executed Surcharge Material Placement in progress PVD Driving in progress
Remarks

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,4th Oct, 2011


S.l. No. Description 1 2 3 Segment 1A Segment 2A Segment 1(part) 150mm sand filling Bracing fixing PC Bracing Casting 4 Open Deep Drain Earth Excavation (CH 800-820) Rebar fabrication (CH 820-840) 5 6 7 8 9 10 11 12 13 14 Open Deep Drain(Culvert adjacent portion) Road Work Rail Relocation Sheet Pile RCC Drainage Pipe Electric Substation Electric Relocation Laboratory Interlocking Block Dismantling work Concrete Pouring of Base Embankment Preparation Embankment Preparation Concrete Pouring Concrete Pouring of Pipe Earth Excavation Circuit (33/33/11/0.44 KV ) overhead cable fixing Cylinder Crushing of 7 days strength (40Mpa) ILB production (2 Plant) CC/RCC Dismantling work at Segment 2 & 3 ILB production in progress CC/RCC Dismantling work at Segment 2 & 3 in progress 150mm sand filling in progress Bracing fixing in progress PC Bracing Casting in Progress Earth Excavation (CH 820-840) in progress CC Executed Rebar fabrication & Shuttering executed Embankment Preparation in progress Embankment Preparation in progress Concrete Pouring in progress Concrete Pouring of Pipe in progress Layout fixing executed Circuit (33/33/11/0.44 KV ) overhead cable fixing in progress Work Program of 4th Oct. 2011 Earth excavation for Drainage pipe laying Surcharge Material Placement PVD Driving Achievement of 3rd Oct.2011 Layout fixing executed Surcharge Material Placement in progress PVD Driving in progress
Remarks

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,5th Oct, 2011


S.l. No. Description 1 2 3 Segment 1A Segment 2A Segment 1(part) 150mm sand filling Bracing fixing PC Bracing Casting 4 Open Deep Drain Soling & CC Casting (CH 800-830) 150mm sand filling in progress Bracing fixing in progress PC Bracing Casting in Progress Earth Excavation executed Work Program of 5th Oct. 2011 Earth excavation for Drainage pipe laying Surcharge Material Placement PVD Driving Achievement of 4th Oct.2011 Layout fixing executed Surcharge Material Placement in progress PVD Driving in progress
Remarks

Rebar fabrication & Shuttering of wall (CH 830-840) CC Executed 5 6 7 8 9 10 11 12 13 14 Open Deep Drain(Culvert adjacent portion) Road Work Rail Relocation Sheet Pile RCC Drainage Pipe Electric Substation Electric Relocation Laboratory Interlocking Block Dismantling work Rebar fabrication & Shuttering of wall Embankment Preparation Embankment Preparation Concrete Pouring Concrete Pouring of Pipe Earth Excavation Circuit (33/33/11/0.44 KV ) overhead cable fixing Cylinder Crushing of 7 days strength (40Mpa) ILB production (2 Plant) CC/RCC Dismantling work at Segment 2 & 3 ILB production in progress CC/RCC Dismantling work at Segment 2 & 3 in progress Concrete of Base executed Embankment Preparation in progress Embankment Preparation in progress Concrete Pouring in progress Concrete Pouring of Pipe in progress Layout fixing executed Circuit (33/33/11/0.44 KV ) overhead cable fixing in progress

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,10th Oct, 2011


S.l. No. Description 1 2 3 Segment 1A Segment 2A Segment 1(part) 150mm sand filling Bracing fixing 4 Open Deep Drain PC Bracing Casting Wall casting/2nd lift(CH 800-830) 5 6 7 8 9 10 11 12 13 14 Open Deep Drain(Culvert adjacent portion) Road Work Rail Relocation Sheet Pile RCC Drainage Pipe Electric Substation Electric Relocation Laboratory Interlocking Block Dismantling work Rebar fabrication & Shuttering of wall Embankment Preparation Embankment Preparation Concrete Pouring Concrete Pouring of Pipe Earth Excavation Circuit (33/33/11/0.44 KV ) overhead cable fixing Cylinder Crushing of 7 days strength (40Mpa) ILB production (2 Plant) CC/RCC Dismantling work at Segment 2 & 3 ILB production in progress CC/RCC Dismantling work at Segment 2 & 3 in progress Embankment Preparation in progress Embankment Preparation in progress Concrete Pouring in progress Concrete Pouring of Pipe in progress Layout fixing executed Circuit (33/33/11/0.44 KV ) overhead cable fixing in progress 150mm sand filling in progress Bracing fixing in progress PC Bracing Casting in Progress Rebar fabrication & Shuttering executed Work Program of 10th Oct. 2011 Earth excavation for Drainage pipe laying Settlement record PVD Driving PVD Driving in progress Achievement of 9th Oct.2011 Layout fixing executed
Remarks

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,11th Oct, 2011


S.l. No. Description 1 2 3 Segment 1A Segment 2A Segment-1 Work Program of 11th Oct. 2011 Earth excavation for Drainage pipe laying Settlement record 150mm sand filling Bracing fixing 4 Open Deep Drain PC Bracing Casting Wall casting/1st lift/country side (CH 800-840) 5 6 7 8 9 10 11 12 13 Open Deep Drain(Culvert adjacent portion) Road Work Rail Relocation Sheet Pile RCC Drainage Pipe Electric Substation Electric Relocation Interlocking Block Dismantling work Back filling & Rebar binding of wall Embankment Preparation Sub base work Concrete Pouring Concrete Pouring of Pipe Earth Excavation Circuit (33/33/11/0.44 KV ) overhead cable fixing ILB production (2 Plant) CC/RCC Dismantling work at Segment 2 & 3 150mm sand filling in progress Bracing fixing in progress PC Bracing Casting in Progress Rebar fabrication & Shuttering executed Back filling & Rebar binding in progress Embankment Preparation in progress Sub base work in progress Concrete Pouring in progress Concrete Pouring of Pipe in progress Layout fixing executed Circuit (33/33/11/0.44 KV ) overhead cable fixing in progress ILB production in progress CC/RCC Dismantling work at Segment 2 & 3 in progress Achievement of 10th Oct.2011 Layout fixing executed
Remarks

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program,12th Oct, 2011


S.l. No. Description 1 2 3 Segment 1A Segment 2A Segment-1 Work Program of 12th Oct. 2011 Earth excavation for Drainage pipe laying Settlement record 150mm sand filling Bracing fixing 4 Open Deep Drain PC Bracing Casting Wall casting/1st lift/country side (CH 800-840) 5 6 7 8 9 10 11 12 13 Open Deep Drain(Culvert adjacent portion) Road Work Rail Relocation Sheet Pile RCC Drainage Pipe Electric Substation Electric Relocation Interlocking Block Dismantling work Concrete Pouring of wall Embankment Preparation Sub base work Concrete Pouring Concrete Pouring of Pipe Earth Excavation Circuit (33/33/11/0.44 KV ) overhead cable fixing ILB production (2 Plant) CC/RCC Dismantling work at Segment 2 & 3 Settlement record in progress 150mm sand filling in progress Bracing fixing in progress PC Bracing Casting in Progress Rebar fabrication & Shuttering executed Rebar fabrication & Shuttering executed Embankment Preparation in progress Sub base work in progress Concrete Pouring in progress Concrete Pouring of Pipe in progress Layout fixing done Circuit (33/33/11/0.44 KV ) overhead cable fixing in progress ILB production in progress CC/RCC Dismantling work at Segment 2 & 3 in progress Achievement of 11th Oct.2011
Remarks

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA