NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 1,2012

S.l. No. Description Work Program of January 1,2012 Achievement of December 31,2011 300mm (16No) pipe Installation 1 Yard Drainage(Seg-1A) Base CC (15rm) CC casting of 2 nos gully hole and 1 no manhole Side CC (30 rm)
Remarks

RMG (Seg-1A)

Singles Laying 2nd layer(520mm thick) / Ch 78Singles Laying 1st layer(520mm thick)/Ch 78-137 137 Rebar fabrication of longitudinal sleepers (Ch 0- Rebar fabrication of longitudinal sleepers(Ch 0-78) 78) in progress
All materials of load test reached at site and preparation in progress Settlement Record in progress for 70th day Sand bagging of preloading work in progress (1200 Nos) Surcharge material placement in progress (35,000cft) Clearing & Grubbing in progress 300mm sand blanket laying in progress Back filling at Navy gate in progress Earth excavation (CH 1000-1040) in progress Rebar fabrication executed Ballast mixing & laying in progress (Ch 0-400) Sleepers & Rail bit fixing in progress Sub base material placement (2nd layer) in progress Shuttering of slab (2nd portion) in progress Concrete pouring of Sheet Pile(01 Nos) in progress Concrete pouring in progress(10Nos) Concrete Pouring (500mm dia=05Nos) Old pole removing in progress Regular Test (ILB/Cylinder) ILB production in progress (Quantity=11,800 Nos) CC Dismantling(Seg-2) in progress

3 4

Pre-cast pile driving(Seg-1A) Identify pile for load test Segment 2A Settlement Record Sand bagging for preloading work (2000 Nos)

Segment 1 Surcharge material placement (50,000 cft) Clearing & Grubbing

Segment-2 300mm sand blanket laying Back filling at Navy gate

Open Deep Drain

Earth excavation (CH 1000-1040) Wall casting at Navy gate (Ch 1100-1125) /3rd lift /yard side Ballast mixing & laying(Ch 0-600)

8 9 10 11 12 13 14 15 16 17

Rail Relocation Sleepers & Rail bit fixing(Ch 0-600) Road Type-1 Electric Sub station Sheet Pile Transverse Sleeper RCC Drainage Pipe PDB Relocation Laboratory / Field Test Interlocking Block Dismantling work Sub base material placement (2nd layer) Shuttering of slab (2nd portion) Concrete pouring of Sheet Pile(01 Nos) Concrete pouring (10 Nos) Concrete pouring(500mm=05 Nos)) Old pole removing Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 2,2012


S.l. No. 1 CC Casting of 1 no manhole. CC casting of 2 nos gully hole Description Work Program of January 2,2012 CC Casting of Cable trench. Achievement of January 1,2011 Base CC (15rm)
Remarks

RMG (Seg-1A)

Singles Laying 2nd layer(520mm thick) / Ch 78137 Rebar fabrication of longitudinal sleepers (Ch 078)

Singles Laying 2nd layer(520mm thick) / Ch 78-137 in progress Rebar fabrication of longitudinal sleepers(Ch 0-78) in progress
Preparation of load test in progress Settlement Record in progress for 71th day Sand bagging of preloading work in progress (1200 Nos) Surcharge material placement in progress (35,000cft) Clearing & Grubbing in progress 300mm sand blanket laying in progress Back filling at Navy gate in progress Earth excavation finished (CH 1000-1040) Wall casting at Navy gate (Ch 1100-1125) /3rd lift /yard side Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress(Ch 0-600) Sub base material placement (2nd layer) in progress Shuttering of slab (2nd portion) in progress Concrete pouring of Sheet Pile(01 Nos) in progress Concrete pouring in progress(10Nos) Concrete Pouring (500mm dia=05Nos) Old pole removing in progress Regular Test (ILB/Cylinder) ILB production in progress (Quantity=12,000 Nos) CC Dismantling(Seg-2) in progress

3 4

Pre-cast pile driving(Seg-1A) Preparation of load test Segment 2A Settlement Record Sand bagging for preloading work (2000 Nos)

Segment 1 Surcharge material placement (50,000 cft) Clearing & Grubbing

Segment-2 300mm sand blanket laying Back filling at Navy gate

Open Deep Drain

CC Casting (CH 1000-1040) Earth Excavation (Ch 1125-1140) Ballast mixing & laying(Ch 0-600)

8 9 10 11 12 13 14 15 16 17

Rail Relocation Sleepers & Rail bit fixing(Ch 0-600) Road Type-1 Electric Sub station Sheet Pile Transverse Sleeper RCC Drainage Pipe PDB Relocation Laboratory / Field Test Interlocking Block Dismantling work Sub base material placement (2nd layer) Shuttering of slab (2nd portion) Concrete pouring of Sheet Pile(01 Nos) Concrete pouring (10 Nos) Concrete pouring(800mm=05 Nos)) Old pole removing Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 3,2012


S.l. No. 1 Description Yard Drainage Work Program of January 3,2012 Base CC (15rm) Achievement of January 2,2011 Earth excavation (15rm)
Remarks

RMG (Seg-1A)

Singles Laying 2nd layer(520mm thick) / Ch 78137 Rebar fabrication of longitudinal sleepers (Ch 078)

Singles Laying 2nd layer(520mm thick) / Ch 78-137 in progress Rebar fabrication of longitudinal sleepers(Ch 0-78) in progress
Preparation of load test in progress Earth Excavation executed. Settlement Record in progress for 72th day Sand bagging of preloading work in progress (1200 Nos) Surcharge material placement in progress (30,000cft) Clearing & Grubbing in progress 300mm sand blanket laying in progress Back filling at Navy gate in progress CC Casting (CH 1000-1040) Wall casting at Navy gate (Ch 1100-1125) /3rd lift /yard side Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress(Ch 0-600) Sub base material placement (2nd layer) in progress Shuttering of slab (2nd portion) in progress Concrete pouring of Sheet Pile(01 Nos) in progress Concrete pouring in progress(10Nos) Concrete Pouring (500mm dia=05Nos) Old pole removing in progress Regular Test (ILB/Cylinder) ILB production in progress (Quantity=12,200 Nos) CC Dismantling(Seg-2) in progress

3 4 5

Pre-cast pile driving(Seg-1A) Preparation of load test Cable Trench (Seg-1A) Segment 2A CC Casting Settlement Record Sand bagging for preloading work (2000 Nos)

Segment 1 Surcharge material placement (50,000 cft) Clearing & Grubbing

Segment-2 300mm sand blanket laying Back filling at Navy gate

Open Deep Drain

Rebar fabrication of Base (CH 1000-1040) Earth Excavation (Ch 1125-1140) Ballast mixing & laying(Ch 0-600)

9 10 11 12 13 14 15 16 17 18

Rail Relocation Sleepers & Rail bit fixing(Ch 0-600) Road Type-1 Electric Sub station Sheet Pile Transverse Sleeper RCC Drainage Pipe PDB Relocation Laboratory / Field Test Interlocking Block Dismantling work Sub base material placement (2nd layer) Shuttering of slab (2nd portion) Concrete pouring of Sheet Pile(01 Nos) Concrete pouring (10 Nos) Concrete pouring(800mm=05 Nos)) Old pole removing Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 4,2012


S.l. No. 1 Description Work Program of January 4,2012 Side CC (30rm) Yard Drainage Pipe Installation 30 rm(300mm dia) Wall casting of 01 No Manhole Base Casting of 02 Nos Gully hole & 01 No Manhole Achievement of January 3,2011 Base CC executed (30rm)
Remarks

RMG (Seg-1A)

Singles Laying 2nd layer(520mm thick) / Ch 78-137 finished Rebar fabrication of longitudinal sleepers (Ch 0- Rebar fabrication of longitudinal sleepers(Ch 0-78) 78) in progress Ballast Laying (300mm thick) / Ch 78-137
Sand bagging for load test in progress Earth Excavation executed. Settlement Record in progress for 73th day Sand bagging of preloading work in progress (1200 Nos) Surcharge material placement in progress (30,000cft)

3 4 5

Pre-cast pile driving(Seg-1A) Sand bagging for load test Cable Trench (Seg-1A) Segment 2A CC Casting Settlement Record Sand bagging for preloading work (2000 Nos)

Segment 1

Surcharge material placement (50,000 cft) Pre-cast Bracing installation

Segment-2

Clearing & Grubbing 300mm sand blanket laying Back filling at Navy gate

Clearing & Grubbing in progress 300mm sand blanket laying in progress(500 sqm) Back filling at Navy gate in progress Rebar fabrication of Base (CH 1000-1040)

Open Deep Drain

Base casting (CH 1000-1040) Bracing fixing (6rm)

9 10 11 12 13 14 15 16 17 18

Rail Relocation Road Type-1 Electric Sub station Sheet Pile Transverse Sleeper RCC Drainage Pipe PDB Relocation Laboratory / Field Test Interlocking Block Dismantling work

Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600) Sub base material placement (2nd layer) Shuttering & Rebar binding of slab (2nd portion) Concrete pouring of Sheet Pile(01 Nos) Concrete pouring (10 Nos)

Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Sub base material placement (2nd layer) in progress Shuttering & Rebar binding of slab (2nd portion) in progress Concrete pouring of Sheet Pile(01 Nos) in progress Concrete pouring in progress(10Nos)

Concrete pouring(800mm=03 Nos,900mm=02 Nos) Concrete Pouring (800mm=03Nos & 900mm=02 Nos) Old pole removing Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2) Old pole removing in progress Regular Test (ILB/Cylinder) ILB production in progress (Quantity=10,500 Nos) CC Dismantling(Seg-2) in progress

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 7,2012


S.l. No. 1 Description Yard Drainage Work Program of January 7,2012 Base Casting of 02 Nos Gully hole & 01 No Man hole. Achievement of January 6,2011 Rebar binding of Base (02 Nos Gully hole & 01 No Man hole)
Remarks

Shingles Laying (180mm thick) / Ch 78-137


2 RMG (Seg-1A)

Longitudinal sleeper casting (Ch 0-10)


3 4 5 6 Pre-cast pile driving(Seg-1A) Sand bagging for load test Sheet Pile Driving Cable Trench (Seg-1A) Segment 2A Preparation of Pile shifting to bank. CC Casting Settlement Record Sand bagging for preloading work (2000 Nos) Surcharge material placement (50,000 cft) 8 Segment-2 Clearing & Grubbing 300mm sand blanket laying 9 Open Deep Drain CC Casting (Outlet point) Wall casting / Port side/1st lift (CH 1015-1040) 10 11 12 13 14 15 16 17 Rail Relocation Road Type-1 Electric Sub station Sheet Pile Transverse Sleeper Laboratory / Field Test Interlocking Block Dismantling work Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600) Sub base material placement (2nd layer) Shuttering & Rebar binding of slab (2nd portion) Concrete pouring of Sheet Pile(01 Nos) Concrete pouring (10 Nos) Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Ballast layer compaction (300mm thick) / Ch 78137 finished Rebar fabrication of longitudinal sleepers(Ch 0-10) finished.
Sand bagging for load test in progress

CC Casting executed. Settlement Record in progress for 77th day Sand bagging of preloading work in progress (1200 Nos) Surcharge material placement in progress (30,000cft) Clearing & Grubbing in progress 300mm sand blanket laying in progress(500 sqm) Soling executed. Rebar fabrication executed (CH 1015-1040) Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Sub base material placement (2nd layer) in progress Shuttering & Rebar binding of slab (2nd portion) in progress Concrete pouring of Sheet Pile(01 Nos) in progress Concrete pouring in progress(10Nos) Regular Test (ILB/Cylinder) ILB production in progress (Quantity=10,500 Nos) CC Dismantling(Seg-2) in progress

Segment 1

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 9,2012


S.l. No. 1 Description Work Program of January 9,2012 15 m Base CC casting (300mm) Yard Drainage(Seg-1A) Wall Casting of 03 Nos Gully hole . Rebar binding executed (wall of 03 Nos Gully hole) Achievement of January 8,2011 15m Earth Excavation

Shingles Laying (180mm thick) / Ch 78-137


2 RMG (Seg-1A)

Longitudinal sleeper casting (Ch 0-10)


3 4 5 6 Sheet Pile Driving Water Supply Line Cable Trench (Seg-1A) Segment 1 Pile shifting to bank. Leak test of 50m pipe (250mm dia) Brick masonry of wall Sand bagging for preloading work (2000 Nos) Surcharge material placement (50,000 cft) 7 Segment-2 Clearing & Grubbing PVD Driving 8 Open Deep Drain Wall casting / Navy side/2nd lift (CH 1015-1040) 9 10 11 12 13 14 15 Rail Relocation Road Type-1 Electric Sub station Sheet Pile Laboratory / Field Test Interlocking Block Dismantling work Concrete pouring of Sheet Pile(01 Nos) Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2) Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600) Sub base material placement (2nd layer)

Shingles Laying (180mm thick) / Ch 78-137 in progress Rebar fabrication of longitudinal sleepers(Ch 0-10) in progress.
Pile shifting to bank in progress 50 m pipe welding completed (250mm dia) Brick masonry of wall in progress Sand bagging of preloading work in progress (1200 Nos) Surcharge material placement in progress (30,000cft) Clearing & Grubbing in progress FDD test executed at 300mm sand blanket

Wall casting / Port side/1st lift (CH 1015-1040) Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Sub base material placement (2nd layer) in progress Slab casting of 2nd portion executed Concrete pouring of Sheet Pile(01 Nos) in progress Regular Test (ILB/Cylinder) ILB production in progress (Quantity=12,400 Nos) CC Dismantling(Seg-2) in progress

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 9,2012


Remarks

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 10,2012


S.l. No. 1 Description Work Program of January 10,2012 300mm Pipe installation(15rm) Yard Drainage(Seg-1A) Wall Casting of 03 Nos Gully hole and base casting of 02 Nos Gully hole. Achievement of January 9,2011 15 m Base CC casting executed. Wall Casting of 03 Nos Gully hole executed

RMG (Seg-1A)

Rolling of Shingles Layer (180mm thick) / Ch 78Shingles Laying (180mm thick) / Ch 78-137 finished 137 Rebar fabrication of longitudinal sleepers(Ch 0- Rebar fabrication of longitudinal sleepers(Ch 0-10) 10) in progress. in progress.
Pile shifting to bank. Leak test of 50m pipe (250mm dia) Brick masonry of wall Sand bagging for preloading work (2000 Nos) Surcharge material placement (50,000 cft) Pile shifting to bank in progress 50 m pipe welding completed (250mm dia) Brick masonry of wall in progress Sand bagging of preloading work in progress (1200 Nos) Surcharge material placement in progress (35,000cft) Clearing & Grubbing in progress PVD Driving in progress Wall casting / Navy side/2nd lift (CH 1015-1040) executed. Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Sub base material placement (2nd layer) in progress Concrete pouring of Sheet Pile(01 Nos) in progress Regular Test (ILB/Cylinder) ILB production in progress (Quantity=11,300 Nos) CC Dismantling(Seg-2) in progress

3 4 5 6

Sheet Pile Driving Water Supply Line Cable Trench (Seg-1A) Segment 1

Segment-2

Clearing & Grubbing PVD Driving Earth Excavation (CH 1040-1060)

Open Deep Drain Wall casting / Yard side/2nd lift (CH 1015-1040) Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600)

9 10 11 12 13 14

Rail Relocation Road Type-1 Sheet Pile Laboratory / Field Test Interlocking Block Dismantling work

Sub base material placement (2nd layer) Concrete pouring of Sheet Pile(01 Nos) Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 10,2012


Remarks

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 14,2012


S.l. No. 1 2 3 4 5 6 7 8 Description Yard Drainage(Seg-1A) RMG Track(Seg-1A) Seg-1A(mosque portion) Sheet Pile Driving Water Supply Line/Seg-1A Cable Trench (Seg-1A) Segment-1 Segment-2 Work Program of January 14,2012 Side CC Casting/30rm/300mm dia pipe Achievement of January 13,2011 Shuttering executed

Rebar fabrication of longitudinal sleepers(Ch 20- Rebar fabrication of longitudinal sleepers(Ch 20-30) 30) in progress. in progress. Soling work
Pile shifting to bank. Painting of Pipe & wrapping by Polythene./250mm dia Brick masonry of wall Surcharge material placement (50,000 cft) Clearing & Grubbing PVD Driving Base Casting (CH 985-1015)

Soling work in progress


Pile shifting to bank in progress Painting of Pipe & wrapping by Polythene/250mm dia in progress. Brick masonry of wall in progress Surcharge material placement in progress (40,000cft) Clearing & Grubbing in progress PVD Driving in progress Rebar binding executed. Rebar binding executed. Pre-cast Bracing Casting (02 Nos) in progress Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Sub base material placement (2nd layer) in progress Regular Test (ILB/Cylinder) ILB production in progress (Quantity=12,300 Nos) CC Dismantling(Seg-2) in progress

Open Deep Drain

Wall casting / Yard side/2nd lift (CH 1015-1040) Pre-cast Bracing Casting (06 Nos)

10 11 12 13 14

Rail Relocation Road Type-1 Laboratory / Field Test Interlocking Block Dismantling work

Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600) Sub base material placement (2nd layer) Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 14,2012


Remarks

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 15,2012


S.l. No. 1 Description Work Program of January 15,2012 Side CC Casting/30rm/300mm dia pipe Yard Drainage(Seg-1A) Wall casting of 03 Nos Gully hole and 01 No Man hole Achievement of January 14,2011 Shuttering executed Shuttering executed

2 3 4 5 6 7 8

RMG Track(Seg-1A) Seg-1A(mosque portion) Sheet Pile Driving Water Supply Line/Seg-1A Cable Trench (Seg-1A) Segment-1 Segment-2

Rebar fabrication of longitudinal sleepers(Ch 20- Rebar fabrication of longitudinal sleepers(Ch 20-30) 30) in progress. in progress. Soling work
Pile shifting to bank. Painting of Pipe & wrapping by Polythene./250mm dia Brick masonry of wall Surcharge material placement (50,000 cft) Clearing & Grubbing PVD Driving

Soling work in progress


Pile shifting to bank in progress Painting of Pipe & wrapping by Polythene/250mm dia in progress. Brick masonry of wall in progress Surcharge material placement in progress (35,000cft) Clearing & Grubbing in progress PVD Driving in progress Base Casting (CH 985-1000) Pre-cast Bracing Casting (06 Nos) in progress Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Rebar fabrication and Shuttering executed. Sub base material placement (2nd layer) in progress Regular Test (ILB/Cylinder) ILB production in progress (Quantity=12,200 Nos) CC Dismantling(Seg-2) in progress

Open Deep Drain

Base Casting (CH 1000-1015) Pre-cast Bracing Casting (06 Nos)

10 11 12 13 14 15

Rail Relocation Pre-cast Sleepers Road Type-1 Laboratory / Field Test Interlocking Block Dismantling work

Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600) Pre-cast Sleepers casting (10 Nos) Sub base material placement (2nd layer) Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 15,2012


Remarks

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 16,2012


S.l. No. 1 Description Work Program of January 16,2012 Achievement of January 15,2011 Side CC Casting/30rm/300mm dia pipe Yard Drainage(Seg-1A) Wall casting of 01 No Gully hole and 01 No Man hole Wall casting of 02 Nos Gully hole and 01 No Man hole .
Remarks

2 3 4 5 6 7 8

RMG Track(Seg-1A) Seg-1A(mosque portion) Sheet Pile Driving Water Supply Line/Seg-1A Cable Trench (Seg-1A) Segment-1 Segment-2

Rebar fabrication of longitudinal sleepers(Ch 20- Rebar fabrication of longitudinal sleepers(Ch 20-30) 30) in progress. in progress. Soling work
Pile shifting to bank. Painting of Pipe & wrapping by Polythene./250mm dia Brick masonry of wall Surcharge material placement (50,000 cft) Clearing & Grubbing PVD Driving

Soling work in progress


Pile shifting to bank in progress Painting of Pipe & wrapping by Polythene/250mm dia in progress. Brick masonry of wall in progress Surcharge material placement in progress (30,000cft) Clearing & Grubbing in progress PVD Driving in progress Base Casting (CH 1000-1015)

Open Deep Drain

Wall casting 1st lift(CH 985-1015) Pre-cast Bracing Casting (06 Nos)

10 11 12 13 14 15

Rail Relocation Pre-cast Sleepers Road Type-1 Laboratory / Field Test Interlocking Block Dismantling work

Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600) Pre-cast Sleepers casting (10 Nos) Sub base material placement (2nd layer) Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Rebar fabrication and Shuttering executed. Sub base material placement (2nd layer) in progress Regular Test (ILB/Cylinder) ILB production in progress (Quantity=13,600 Nos) CC Dismantling(Seg-2) in progress

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 17,2012


S.l. No. 1 Description Work Program of January 17,2012 02 Nos 300mm dia pipe,01 No 700mm dia pipe fixing. Shuttering & Rebar fabrication of 02 Nos Gully hole. Wall casting of 01 No Gully hole and 01 No Man hole 2 3 4 5 6 7 8 9 RMG Track(Seg-1A) Seg-1A(mosque portion) Sub-station Building Sheet Pile Driving Water Supply Line/Seg-1A Cable Trench (Seg-1A) Segment-1 Segment-2 Achievement of January 16,2011
Remarks

Yard Drainage(Seg-1A)

Rebar fabrication of longitudinal sleepers(Ch 20- Rebar fabrication of longitudinal sleepers(Ch 20-30) 30) in progress. in progress. Sand filling & Soling work Plaster work
Pile shifting to bank. Painting of Pipe & wrapping by Polythene./250mm dia Plastering of wall. Surcharge material placement (50,000 cft) Clearing & Grubbing Soling & CC work (CH 1015-1030) Surcharge material placement in progress (30,000cft) Clearing & Grubbing in progress Earth Excavation executed. Shuttering & Rebar fabrication executed. Pre-cast Bracing Casting (06 Nos) Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Pre-cast Sleepers casting (10 Nos) in progress. Sub base material placement (2nd layer) in progress Regular Test (ILB/Cylinder) ILB production in progress (Quantity=12,250 Nos) CC Dismantling(Seg-2) in progress

Sand filling & Soling work in progress Plaster work in progress.


Pile shifting to bank in progress Painting of Pipe & wrapping by Polythene/250mm dia in progress.

10

Open Deep Drain

Wall casting 1st lift(CH 985-1015) Pre-cast Bracing Casting (06 Nos)

11 12 13 14 15 16

Rail Relocation Pre-cast Sleepers Road Type-1 Laboratory / Field Test Interlocking Block Dismantling work

Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600) Pre-cast Sleepers casting (10 Nos) Sub base material placement (2nd layer) Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 18,2012


S.l. No. Description 1 Yard Drainage(Seg-1A) Shuttering & Rebar fabrication of 02 Nos Gully hole. 2 3 4 5 6 7 8 RMG Track(Seg-1A) Seg-1A(mosque portion) Sub-station Building Sheet Pile Driving Water Supply Line/Seg-1A Cable Trench (Seg-1A) Segment-1 Work Program of January 18,2012 Side CC Casting of 10rm Achievement of January 17,2011 02 Nos 300mm dia pipe,01 No 700mm dia pipe fixing. Shuttering & Rebar fabrication of 02 Nos Gully hole and 02 Nos Manhole.
Remarks

Rebar fabrication of longitudinal sleepers(Ch 30- Rebar fabrication of longitudinal sleepers(Ch 30-40) 40) in progress. in progress. Sand filling & Soling work Plaster work
Pile shifting to bank. Painting of Pipe & wrapping by Polythene./250mm dia Plastering of wall. Surcharge material placement (50,000 cft) Clearing & Grubbing

Sand filling & Soling work in progress Plaster work in progress.


Pile shifting to bank in progress Painting of Pipe & wrapping by Polythene/250mm dia in progress. Plastering of wall in progress Surcharge material placement in progress (35,000cft) Clearing & Grubbing in progress 150mm local sand laying in progress 200mm sand blanket laying in progress Soling & CC work (CH 1015-1030)

Segment-2

150mm local sand laying 200mm sand blanket laying Rebar fabrication of Base (CH 1015-1030)

10

Open Deep Drain

Rebar fabrication of Wall 1st lift(CH 985-1015)/Navy Wall casting 1st lift(CH 985-1015)/Yard Side side. Pre-cast Bracing Casting (06 Nos) Pre-cast Bracing Casting (05 Nos) Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Shuttering & Rebar fabrication executed. Sub base material placement (2nd layer) in progress Regular Test (ILB/Cylinder)

11 12 13 14 15 16

Rail Relocation Pre-cast Sleepers Road Type-1 Laboratory / Field Test Interlocking Block Dismantling work

Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600) Pre-cast Sleepers casting (10 Nos) Sub base material placement (2nd layer) Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

CC Dismantling(Seg-2) in progress

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 20,2012


S.l. No. Description 1 Yard Drainage(Seg-1A) Wall Shuttering of 02 Nos Man hole Wall casting of 02 Nos Gully hole Work Program of January 20,2012 Rebar fabrication of 03 Nos Gully hole Achievement of January 19,2011
Remarks

RMG Track(Seg-1A)

Rebar fabrication of longitudinal sleepers(Ch 30- Rebar fabrication of longitudinal sleepers(Ch 30-40) 40) in progress. in progress. Pre-cast sleepers shifting to Seg-1

3 4 5 6 7 8 9

Seg-1A(mosque portion) Service Area Sub-station Building Sheet Pile Driving Water Supply Line/Seg-1A Cable Trench (Seg-1A) Segment-1

Soling work Sub-base material laying Plaster work & Parapet shuttering
Pile shifting to bank. Painting of Pipe & wrapping by Polythene./250mm dia Plastering of wall. Surcharge material placement (50,000 cft) Clearing & Grubbing

Soling work in progress Bed preparation finished Plaster work & Parapet casting in progress.
Pile shifting to bank in progress Painting of Pipe & wrapping by Polythene/250mm dia in progress. Plastering of wall in progress Surcharge material placement in progress (35,000cft) Clearing & Grubbing in progress 150mm local sand laying in progress 200mm sand blanket laying in progress Base casting (CH 970-990) Wall casting 1st lift(CH 990-1015)/Navy Side Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Shuttering & Rebar fabrication executed. Sub base material placement (2nd layer) in progress Regular Test (ILB/Cylinder) ILB production (Quantity=11000 Nos) CC Dismantling(Seg-2) in progress

10

Segment-2

150mm local sand laying 200mm sand blanket laying Shuttering of wall (CH 1015-1030)

11

Open Deep Drain Back filling(CH 990-1015)/Navy side. Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600)

12 13 14 15 16 17

Rail Relocation Pre-cast Sleepers Road Type-1 Laboratory / Field Test Interlocking Block Dismantling work

Pre-cast Sleepers casting (10 Nos) Sub base material placement (2nd layer) Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 21,2012


S.l. No. Description 1 Yard Drainage(Seg-1A) Wall Shuttering of 02 Nos Man hole Wall Shuttering of 02 Nos Man hole in progress Work Program of January 21,2012 Rebar fabrication of 03 Nos Gully hole Achievement of January 20,2011 Rebar fabrication of 03 Nos Gully hole in progress
Remarks

RMG Track(Seg-1A)

Rebar fabrication of longitudinal sleepers(Ch 30- Rebar fabrication of longitudinal sleepers(Ch 30-40) 40) . in progress. Pre-cast sleepers shifting to Seg-1 Pre-cast sleepers shifting to Seg-1 in progress Soling work finished. Sub-base material laying finished. Plaster work & Parapet shuttering.
Pile shifting to bank in progress Plastering of wall in progress Surcharge material placement in progress (35,000cft) Clearing & Grubbing in progress 300mm sand blanket compaction finished. 200mm sand blanket laying in progress Earth excavation (CH 950-970) Back filling(CH 990-1015)/Navy side. Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Shuttering & Rebar fabrication executed. Sub base material placement (2nd layer) finished. Regular Test (ILB/Cylinder) ILB production (Quantity=12000 Nos) CC Dismantling(Seg-2) in progress

3 4 5 6 7 8

Seg-1A(mosque portion) Service Area Sub-station Building Sheet Pile Driving Cable Trench (Seg-1A) Segment-1

Rebar binding of raft foundation. Sub-base material compaction. Plaster work & Parapet casting.
Pile shifting to bank. Plastering of wall. Surcharge material placement (50,000 cft) Clearing & Grubbing

Segment-2

PVD Driving 200mm sand blanket laying Wall casting 2nd lift (CH 990-1015)/Navy Side

10

Open Deep Drain Soling & CC (CH 950-970)/Navy side. Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600)

11 12 13 14 15 16

Rail Relocation Pre-cast Sleepers Road Type-1 Laboratory / Field Test Interlocking Block Dismantling work

Pre-cast Sleepers casting (10 Nos) Field density test of sub-base. Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 22,2012


S.l. No. Description 1 Yard Drainage (Seg 1A) Work Program of January 22,2012 Man hole wall casting (01 No) Achievement of January 21,2011 Man hole wall casting (01 No)
Remarks

Concrete Pouring (CH 0-20)


2 RMG Track(Seg-1A)

Rebar fabrication of longitudinal sleepers(Ch 30-40) in progress. Pre-cast sleepers shifting to Seg-1 in progress Rebar binding of raft foundation in progress. Sub-base material laying finished. Plaster work & Parapet casting.
Pile shifting to bank in progress Plastering of wall in progress Surcharge material placement in progress (35,000cft) Clearing & Grubbing in progress 200mm sand blanket laying in progress Wall casting 2nd lift (CH 990-1015)/Navy Side Soling (CH 950-970) Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Trial Mix design (40 Mpa) ILB production (Quantity=11500 Nos) CC Dismantling(Seg-2) in progress

Pre-cast sleepers shifting to Seg-1


3 4 5 6 7 8 9 Seg-1A(mosque portion) Service Area Sub-station Building Sheet Pile Driving Cable Trench (Seg-1A) Segment-1 Segment-2

Rebar binding of raft foundation. Sub-base material compaction. Plaster work .


Pile shifting to bank. Plastering of wall. Surcharge material placement (50,000 cft) Clearing & Grubbing 200mm sand blanket laying Wall casting 2nd lift (CH 990-1015)/Yard Side

10

Open Deep Drain CC (CH 950-970) Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600)

11 12 13 14

Rail Relocation Laboratory / Field Test Interlocking Block Dismantling work

Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 23,2012


S.l. No. Description 1 2 3 4 5 6 7 8 9 Yard Drainage (Seg 1A) RMG Track(Seg-1A) Seg-1A(mosque portion) Service Area Sub-station Building Sheet Pile Driving Cable Trench (Seg-1A) Segment-1 Segment-2 Work Program of January 23,2012 Man hole wall casting (01 No) Achievement of January 22,2011 Shuttering executed.
Remarks

Rebar fabrication of longitudinal sleepers(Ch 30Concrete Pouring (CH 0-10) 40) in progress. Rebar binding of raft foundation. Sub-base material laying Plaster work .
Pile shifting to bank. Plastering of wall. Surcharge material placement (50,000 cft) Clearing & Grubbing 200mm sand blanket laying Wall casting 1st lift (CH 970-990)/Yard Side

Rebar binding of raft foundation in progress. Sub-base material laying in progress Plaster work in progress
Pile shifting to bank in progress Plastering of wall in progress Surcharge material placement in progress (30,000cft) Clearing & Grubbing in progress 200mm sand blanket laying in progress Wall casting 1st lift (CH 970-990)/Navy Side Soling & CC (CH 950-970) Ballast mixing & laying in progress (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600) Regular Test (ILB/Cylinder) ILB production (Quantity=10500 Nos) CC Dismantling(Seg-2) in progress

10

Open Deep Drain Earth Excavation (CH 935-950) Ballast mixing & laying(Ch 0-600) Sleepers & Rail bit fixing (Ch 0-600)

11 12 13 14

Rail Relocation Laboratory / Field Test Interlocking Block Dismantling work

Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 24,2012


S.l. No. Description 1 2 3 4 5 6 7 8 9 10 Yard Drainage (Seg 1A) RMG Track(Seg-1A) Seg-1A(mosque portion) Service Area Sub-station Building Segment-2A Sheet Pile Driving Cable Trench (Seg-1A) Segment-1 Segment-2 Work Program of January 24,2012 Man hole wall casting (01 No) Achievement of January 23,2011
Remarks

Rebar fabrication of longitudinal sleepers(Ch 30- Rebar fabrication of longitudinal sleepers(Ch 30-40) 40) . in progress. Rebar binding of raft foundation. Sub-base material laying & compaction Plaster work . Surcharge Removing
Pile shifting to bank. Plastering of wall. Surcharge material placement (50,000 cft) PVD Driving 200mm sand blanket laying Wall casting 2nd lift (CH 970-990)/Yard Side 200mm sand blanket laying in progress Wall casting 1st lift (CH 970-990)/Yard Side Earth Excavation (CH 935-950) In progress

Rebar binding of raft foundation in progress. Sub-base material laying & compaction in progress Plaster work in progress Surcharge Removing in progress.
Pile shifting to bank in progress Plastering of wall in progress Surcharge material placement in progress (40,000cft)

11

Open Deep Drain

Earth Excavation (CH 935-950) Bracing fixing (06 Nos)

12 13 14

Laboratory / Field Test Interlocking Block Dismantling work

Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Regular Test (ILB/Cylinder) ILB production (Quantity=13200 Nos) CC Dismantling(Seg-2) in progress

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 25,2012


S.l. No. 1 2 3 4 5 6 7 8 Description RMG Track(Seg-1A) Seg-1A(mosque portion) Service Area Sub-station Building Segment-2A Sheet Pile Driving Segment-1 Segment-2 Work Program of January 25,2012 Achievement of January 24,2011
Remarks

Rebar fabrication of longitudinal sleepers(Ch 30- Rebar fabrication of longitudinal sleepers(Ch 30-40) 40) . in progress. Rebar binding of raft foundation. Sub-base material compaction Plaster work . Surcharge Removing
Pile shifting to bank. Surcharge material placement (50,000 cft) PVD Driving 150mm local sand laying. Wall casting 2nd lift (CH 970-990)/Yard Side

Rebar binding of raft foundation in progress. Sub-base material laying finished. Plaster work in progress Surcharge Removing in progress.
Pile shifting to bank in progress Surcharge material placement in progress (35,000cft) PVD Driving in progress. 150mm local sand laying in progress. Wall casting 1st lift (CH 970-990)/Yard Side Earth Excavation (CH 935-950)

Open Deep Drain

CC ,Soling (CH 935-950) Bracing fixing (06 Nos)

10 11 12

Laboratory / Field Test Interlocking Block Dismantling work

Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling(Seg-2) in progress

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 26,2012


S.l. No. 1 2 3 4 5 6 7 8 9 10 11 12 Description RMG Track(Seg-1A) Seg-1A(mosque portion) Service Area Sub-station Building Segment-2A Sheet Pile Driving Segment-1 Segment-2 Open Deep Drain Rebar binding of Base (CH 935-970) Laboratory / Field Test Interlocking Block Dismantling work Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2) Work Program of January 26,2012 Achievement of January 25,2011
Remarks

Rebar fabrication of longitudinal sleepers(Ch 30- Rebar fabrication of longitudinal sleepers(Ch 30-40) 40) . in progress. Rebar binding of raft foundation. Lean concrete casting Bricks masonry work Surcharge Removing
Pile shifting to bank. Surcharge material placement (50,000 cft) 150mm local sand laying.

Rebar binding of raft foundation in progress.

Surcharge Removing in progress.


Pile shifting to bank in progress Surcharge material placement in progress (42,000cft) 150mm local sand laying in progress. Wall casting 2nd lift (CH 970-990)/Yard Side CC ,Soling (CH 935-950) Regular Test (ILB/Cylinder) ILB production (Quantity=14200 Nos) CC Dismantling(Seg-2) in progress

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of January 30,2012


S.l. No. 1 Description RMG Track(Seg-1A) Work Program of January 30,2012 Achievement of January 29,2011
Remarks

Rebar fabrication of longitudinal sleepers(Ch 30- Rebar fabrication of longitudinal sleepers(Ch 30-40) 40) . in progress. Base casting of 03 Nos Gully holes & wall casting of 01 No Manhole. Bricks masonry work FDD Test of 150mm local sand layer Rebar fabrication and shuttering executed. Bricks masonry work in progress.

2 3

Yard Drainage Sub-station Building

Segment-2

FDD Test of 200mm sand blanket layer


5 6 7 8 9 10 11 Segment-2A Sheet Pile Driving Segment-1 Open Deep Drain Laboratory / Field Test Interlocking Block Dismantling work

Surcharge Removing
Pile shifting to bank. Surcharge material placement (50,000 cft) Wall casting 1st lift (CH 955-970)/Navy Side Regular Test (ILB/Cylinder) ILB production (Quantity=13000 Nos) CC Dismantling (Seg-2)

Surcharge Removing in progress.


Pile shifting to bank in progress Surcharge material placement in progress (45,000cft) Wall casting 1st lift (CH 935-955)/Navy Side Regular Test (ILB/Cylinder) ILB production (Quantity=14200 Nos) CC Dismantling(Seg-2) in progress

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of February 1,2012


S.l. No. 1 2 Description RMG Track(Seg-1A) Yard Drainage Work Program of February1,2012 Achievement of January 31,2011
Remarks

Rebar fabrication of longitudinal sleepers(Ch 3040) . Net cement finishing of Gully hole. Bricks masonry work

Rebar fabrication of longitudinal sleepers(Ch 30-40) in progress.

Bricks masonry work in progress. Bricks masonry work of Safety Tank in progress.

Sub-station Building Bricks masonry work of Safety Tank. Settlement plate fixing (08 Nos)

Segment-2

300 mm sand blanket laying at remaining portion.


5 6 7 8 9 10 11 Segment-2A Segment-1 Road Type-1 Open Deep Drain Laboratory / Field Test Interlocking Block Dismantling work

300 mm sand blanket laying at remaining portion in progress. Surcharge Removing in progress.(70,000 cft)
Surcharge material placement in progress (35,000cft) Wall casting 1st lift (CH 955-970)/Yard Side Regular Test (ILB/Cylinder) ILB production (Quantity=14,500 Nos) CC Dismantling(Seg-2) in progress

Surcharge Removing
Surcharge material placement (50,000 cft) Sub-base work Wall casting 1st lift (CH 935-955)/Yard Side Regular Test (ILB/Cylinder) ILB production (Quantity=15000 Nos) CC Dismantling (Seg-2)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of February 2,2012


S.l. No. 1 2 Description RMG Track(Seg-1A) Yard Drainage Work Program of February 2,2012 Achievement of February 1,2011
Remarks

Rebar fabrication of longitudinal sleepers(Ch 3040) . Net cement finishing of Gully hole. Bricks masonry work

Rebar fabrication of longitudinal sleepers(Ch 30-40) in progress. Net cement finishing of Gully hole in progress. Bricks masonry work in progress. Bricks masonry work of Safety Tank in progress.

Sub-station Building Bricks masonry work of Safety Tank. Settlement plate fixing (08 Nos)

Segment-2

300 mm sand blanket laying at remaining portion.


5 6 7 8 9 10 11 12 Segment-2A Segment-1 Rail Relocation Road Type-1 Open Deep Drain Laboratory / Field Test Interlocking Block Dismantling work

300 mm sand blanket laying at remaining portion in progress. Surcharge Removing in progress.(70,000 cft)
Surcharge material placement in progress (35,000cft) Sub-base work in progress Wall casting 1st lift (CH 935-955)/Yard Side Regular Test (ILB/Cylinder) ILB production (Quantity=12,500 Nos) CC Dismantling(Seg-2) in progress

Surcharge Removing
Surcharge material placement (50,000 cft) Sub-base work at Navy area (CH 620-820) Sub-base work Wall casting 2nd lift (CH 950-970)/Navy Side Regular Test (ILB/Cylinder) ILB production (Quantity=15000 Nos) CC Dismantling (Seg-2)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of February 4,2012


S.l. No. 1 Description RMG Track(Seg-1A) Work Program of February 4,2012 Achievement of February 3,2011
Remarks

Rebar fabrication of longitudinal sleepers(Ch 3040) . Net cement finishing of Gully hole.

Rebar fabrication of longitudinal sleepers(Ch 30-40) in progress. Base casting of 01 Nos Gully hole & 01 No Manhole Wall casting of 02 Nos Gully hole.

Yard Drainage

Bricks masonry work Bricks masonry work of Safety Tank.


3

Bricks masonry work in progress. Bricks masonry work of Safety Tank in progress.

Sub-station Building Base casting of fuel tank. Sunshade Casting Sunshade Casting in progress. 300 mm sand blanket laying at remaining portion in progress. Surcharge Removing in progress.(50,000 cft)
Surcharge material placement in progress (50,000cft) Rail fixing at Navy area (CH 620-820) finished. Improved Sub-grade & Sub-base work in progress. Wall casting 3rd lift (CH 925-950)/Navy Side

4 5 6 7 8 9 10 11 12

Segment-2 Segment-2A Segment-1 Rail Relocation Road Type-2 Open Deep Drain

300 mm sand blanket laying at remaining portion. Surcharge Removing


Surcharge material placement (50,000 cft) Commissioning of Relocated Line. Improved Sub-grade & Sub-base work Wall casting 3rd lift (CH 950-970)/Navy Side Bracing fixing (near sub-station)

Laboratory / Field Test Interlocking Block Dismantling work

Regular Test (ILB/Cylinder) ILB production (Quantity=15000 Nos) CC Dismantling (Seg-2)

Regular Test (ILB/Cylinder) ILB production (Quantity=13,500 Nos) CC Dismantling(Seg-2) in progress

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of February 6,2012


S.l. No. 1 Description RMG Track(Seg-1A) Work Program of February 6,2012 Achievement of February 5,2011
Remarks

Rebar fabrication of longitudinal sleepers(Ch 3040) . Net cement finishing of Gully hole.

Rebar fabrication of longitudinal sleepers(Ch 30-40) in progress.

Yard Drainage

Base CC Casting of 300 mm dia pipe (40rm) Bricks masonry work & Plastering of Wall. Rebar fabrication & Shuttering of slab of septic tank. Base casting of Fuel tank. Sunshade Casting
4 5 6 7 8 9 10 11 12 Segment-2 Segment-2A Segment-1 & 2 Rail Relocation Road Type-2 Open Deep Drain Bracing fixing (near sub-station) Laboratory / Field Test Interlocking Block Dismantling work Regular Test (ILB/Cylinder) ILB production (Quantity=15000 Nos) CC Dismantling (Seg-2)

Earth excavation & Levelling. Bricks masonry work & Plastering of Wall in progress. Bricks masonry work & Plastering completed.

Sub-station Building

Sunshade Casting in progress. 300 mm sand blanket laying at remaining portion in progress. Surcharge Removing in progress.(50,000 cft)
Surcharge material placement in progress (60,000cft) Rail fixing at Navy area (CH 620-820) finished. Improved Sub-grade & Sub-base work in progress. Wall casting 3rd lift (CH 925-950)/Navy Side.

300 mm sand blanket laying at remaining portion. Surcharge Removing


Surcharge material placement (70,000 cft) Commissioning of Relocated Line. Improved Sub-grade & Sub-base work Wall casting 3rd lift (CH 950-970)/Navy Side

Regular Test (ILB/Cylinder) ILB production (Quantity=13,500 Nos) CC Dismantling(Seg-2) in progress

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of February 8,2012


S.l. No. 1 2 Description RMG Track(Seg-1A) Yard Drainage Work Program of February 8,2012 Achievement of February 7,2011
Remarks

Pre-cast Sleepers casting (10 Nos) Side CC ,40rm(300mm dia pipe) Bricks masonry work & Plastering of Wall.

Pre-cast Sleepers casting (10 Nos) Base CC,40rm Bricks masonry work & Plastering of Wall in progress. Slab Casting of Septic tank Base casting of Fuel tank

Sub-station Building

Sunshade Casting
4 5 6 7 8 9 10 11 12 13 Segment-2 Segment-2A Segment-1 & 2 Rail Relocation Boundar Wall Road Type-2 Open Deep Drain Bracing fixing (near sub-station) Laboratory / Field Test Interlocking Block Dismantling work Regular Test (ILB/Cylinder) ILB production Navy gate.

Sunshade Casting in progress. 300 mm sand blanket laying at remaining portion in progress. Surcharge Removing in progress.(50,000 cft)
Surcharge material placement in progress (60,000cft)

300 mm sand blanket laying at remaining portion. Surcharge Removing


Surcharge material placement (70,000 cft) Old line removal Bricks masonry work near sub-station Improved Sub-grade & Sub-base work Wall casting 3rd lift (CH 970-990)/Navy Side

Improved Sub-grade & Sub-base work in progress. Wall casting 3rd lift (CH 950-970)/Navy Side

Regular Test (ILB/Cylinder) ILB production in progress.

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of February 9,2012


S.l. No. 1 2 Description RMG Track(Seg-1A) Yard Drainage Work Program of February 9,2012 Achievement of February 8,2011
Remarks

Pre-cast Sleepers casting (10 Nos) Side CC ,40rm(300mm dia pipe) Bricks masonry work & Plastering of Wall. Sunshade Casting

Pre-cast Sleepers casting in progress (10 Nos) Pipe fixing executed. Bricks masonry work & Plastering of Wall in progress. Sunshade Casting in progress. 300 mm sand blanket laying in progress. Surcharge Removing in progress.(50,000 cft)
Surcharge material placement in progress (70,000cft) Old line removal in progress. Bricks masonry work near sub-station in progress. Improved Sub-grade & Sub-base work in progress.

Sub-station Building

4 5 6 7 8 9 10 11 12 13

Segment-2 Segment-2A Segment-1 & 2 Rail Relocation Boundar Wall Road Type-2 Open Deep Drain

300 mm sand blanket laying. Surcharge Removing


Surcharge material placement (70,000 cft) Old line removal Bricks masonry work near sub-station Improved Sub-grade & Sub-base work Wall casting 3rd lift (CH 970-990)/Navy Side Bracing fixing (near sub-station)

Laboratory / Field Test Interlocking Block Dismantling work

Regular Test (ILB/Cylinder) ILB production Dismantling work at Navy gate.

Regular Test (ILB/Cylinder) ILB production in progress.(10,000 Nos) Dismantling work at Navy gate in progress.

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of February 11,2012


S.l. No. 1 Description RMG Track(Seg-1A) Work Program of February 11,2012 Achievement of February 10,2011
Remarks

Pre-cast Sleepers casting (10 Nos) Side CC ,40rm(300mm dia pipe)

Pre-cast Sleepers casting in progress (10 Nos) Pipe fixing executed.

Yard Drainage

CC Castng of 2 Nos Gullyhole & 01 No Manhole. Bricks masonry work & Plastering . Sunshade Casting
4 5 6 7 8 9 10 11 12 13 Sub-base work (Seg-1A) Segment-2A Segment-1 & 2 Rail Relocation Boundar Wall Road Type-2 Open Deep Drain Bracing fixing (near sub-station) Laboratory / Field Test Interlocking Block Dismantling work FDD test of 300 mm sand blanket at Seg-2 ILB production Dismantling work at Navy gate. Regular Test (ILB/Cylinder) ILB production in progress.(10,000 Nos) Dismantling work at Navy gate in progress.

Sub-station Building

Bricks masonry work & Plastering in progress. Sunshade Casting in progress. Shingles laying (200mm) Surcharge Removing in progress.(50,000 cft)
Surcharge material placement in progress (70,000cft) Old line removal in progress. Bricks masonry work finished near sub-station . Improved Sub-grade & Sub-base work in progress. Wall casting 3rd lift (CH 990-1010)/Navy Side

Water spraying & Rolling Surcharge Removing


Surcharge material placement (70,000 cft) Old line removal Plastering of wall near sub-station Improved Sub-grade & Sub-base work Wall casting 3rd lift (CH 990-1010)/Navy Side

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of February 12,2012


S.l. No. 1 Description RMG Track(Seg-1A) Work Program of February 12,2012 Achievement of February 11,2011
Remarks

Pre-cast Sleepers casting (10 Nos) Wall casting of 01 No Manhole

Pre-cast Sleepers casting in progress (10 Nos) Side CC ,40rm(300mm dia pipe)

Yard Drainage

CC Castng of 2 Nos Gullyhole Bricks masonry work & Plastering . Sunshade Casting
4 5 6 7 8 9 10 11 12 13 14 15 Sub-base work (Seg-1A) Service Area Segment-2 Segment-2A Segment-1 & 2 Rail Relocation Boundar Wall Road Type-2 Open Deep Drain Bracing fixing (near sub-station) Laboratory / Field Test Interlocking Block Dismantling work Regular Test (ILB/Cylinder) ILB production Dismantling work at Navy gate. Regular Test (ILB/Cylinder) ILB production in progress.(11,000 Nos) Dismantling work at Navy gate in progress.

Sub-station Building

Bricks masonry work & Plastering in progress. Sunshade Casting in progress. Shingles laying (200mm)

Water spraying & Rolling Lean concrete casting(18 Mpa) PVD Driving Surcharge Removing
Surcharge material placement (70,000 cft) Old line removal Plastering of wall near sub-station Improved Sub-grade Shuttering work (CH 1010-1030)/Navy Side

300mm sand blanket completed. Surcharge Removing in progress.(50,000 cft)


Surcharge material placement in progress (70,000cft) Old line removal in progress. Bricks masonry work finished near sub-station . Improved Sub-grade work in progress. Wall casting 3rd lift (CH 990-1010)/Navy Side

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of February 12,2012


S.l. Description No. 1 Yard Drainage Work Program of February 16,2012 Achievement of February 15,2011
Remarks

Wall casting of 01 No Gully hole. CC Castng of 4 Nos Gullyhole Bricks masonry work & Plastering . Surcharge material placement (70,000 cft) Surcharge material placement PVD Driving
5 6 7 8 9 Sub-base work (Seg-1A) Service Area Seg-2A Road Type-1 Open Drain Work

2 3 4

Sub-station Building Segment-1


Segment-2

Bricks masonry work & Plastering in progress. Surcharge material placement in progress (60,000cft) Surcharge material placement in progress. PVD Driving in progress.

RTG Track area Lean concrete casting(18 Mpa) Soil boring Sub-base work.
Soling,CC work (CH 1040-1050) Regular Test (ILB/Cylinder) ILB production

Lean concrete casting(18 Mpa) in progress.

Sub-base work in progress


Earth excavation executed. Regular Test (ILB/Cylinder) ILB production in progress.(13,000 Nos)

10 Laboratory / Field Test 11 Interlocking Block

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of February 18,2012


S.l. Description No. 1 2 3 4 5 6 7 8 9 Work Program of February 18,2012 Achievement of February 17,2011
Remarks

Sub-station Building RMG Track(Seg-1A) Segment-1 Pile Load Test(up lift)


Segment-2 Sub-base work (Seg-1A) Service Area Seg-2A Road Type-1

Bricks masonry work & Plastering . Concrete pouring (16 cum) Surcharge material placement (70,000 cft) Up lift test for driven pre-cast pile (Seg-1A) Surcharge material placement PVD Driving Sub-base work for RTG Track Lean concrete casting(18 Mpa) Soil boring for sample collection Sub-base work.
Bracing welding (near Navy gate.) Wall casting CH 920-940/3rd lift/Yard side Wall casting CH 940-950/1st lift/Navy side

Bricks masonry work & Plastering in progress. Rebar binding and shuttering executed. Surcharge material placement in progress (60,000cft)

Surcharge material placement in progress. PVD Driving in progress. Sub-base work for RTG Track in progress. Lean concrete casting(18 Mpa) in progress. Soil boring for sample collection in progress. Sub-base work in progress
Earth excavation executed.

10 Open Drain Work

11 Laboratory / Field Test 12 Interlocking Block

Regular Test (ILB/Cylinder) ILB production

Regular Test (ILB/Cylinder) ILB production in progress.(12,540 Nos)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of February 19,2012


S.l. Description No. 1 Yard Drainage Work Program of February 19,2012 Achievement of February 18,2011
Remarks

Wall casting of 01 No Gully hole. CC Castng of 4 Nos Gullyhole Side CC (8rm)


2 3 4 5 6 7 8 9

Sub-station Building RMG Track(Seg-1A) RTG Track (Seg-1A) Segment-1


Segment-2 Seg-2A Road Type-1 Open Drain Work

Bricks masonry work & Plastering . Rebar binding & Shuttering. Sub-base work Settlement Record Surcharge material placement PVD Driving Soil boring for sample collection Existing Road excavation
Bracing Fixing (near Navy gate.) Wall casting CH 940-950/1st lift/Yard side

Bricks masonry work & Plastering in progress. Concrete pouring (16 cum) Sub-base work in progress Settlement Record in progress. Surcharge material placement in progress. PVD Driving in progress. Soil boring for sample collection in progress.

Earth excavation executed. Wall casting CH 920-940/3rd lift/Yard side Wall casting CH 940-950/1st lift/Navy side Regular Test (ILB/Cylinder) ILB production in progress.(12,400 Nos)

10 Laboratory / Field Test 11 Interlocking Block

Regular Test (ILB/Cylinder) ILB production

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of February 22,2012


S.l. Description No. 1 Yard Drainage 2 3 4 5 6 7 8 9 Sub-station Building RMG Track(Seg-1A) RTG Track (Seg-1A) Work Program of February 22,2012 Rebar binding of Base (04 Nos Single Gully hole) Bricks masonry work & Plastering . Rebar binding & Shuttering. Sub-base work Bricks masonry work & Plastering in progress. Rebar binding & Shuttering in progress. Sub-base work in progress Achievement of February 21,2011
Remarks

Yard Lean concrete (Seg-1A) 200mm thick lean concrete casting. Segment-1 Segment-2 Road Type-1 Open Drain Work Settlement Record Surcharge material placement Sub-base work Bracing Fixing (near Navy gate.) Wall casting CH 900-920/2nd lift/Yard side Sub-grade Preparation Regular Test (ILB/Cylinder) ILB production Regular Test (ILB/Cylinder) ILB production in progress.(11,800 Nos) Settlement Record in progress. Surcharge material placement in progress. Sub-base work in progress Bracing Fixing (near Navy gate.) in progress Rebar fabrication & Shuttering executed.

10 Truck Parking Area 11 Laboratory / Field Test 12 Interlocking Block

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of February 23,2012


S.l. Description No. 1 Yard Drainage 2 3 4 5 6 7 8 9 Sub-station Building RMG Track(Seg-1A) RTG Track (Seg-1A) Work Program of February 23,2012 Base casting (04 Nos Single Gully hole) Bricks masonry work & Plastering . Rebar binding & Shuttering. Sub-base work Achievement of February 22,2011 Rebar binding of Base (04 Nos Single Gully hole) Bricks masonry work & Plastering in progress. Rebar binding & Shuttering in progress. Sub-base work in progress 200mm thick lean concrete casting in progress. Settlement Record in progress. Surcharge material placement in progress. 150mm local sand compaction in progress. Dismantling work in progress. Sub-base work in progress Bracing Fixing (near Navy gate.) in progress Rebar fabrication & Shuttering executed. Sub-grade Preparation in progress. Regular Test (ILB/Cylinder) ILB production in progress.(9,500 Nos)
Remarks

Yard Lean concrete (Seg-1A) 200mm thick lean concrete casting. Segment-1 Segment-2 Segment-4 Segment-3 Settlement Record Surcharge material placement 150mm local sand compaction Dismantling work Sub-base work Bracing Fixing (near Navy gate.) Wall casting CH 900-920/2nd lift/Yard side Sub-grade Preparation Regular Test (ILB/Cylinder) ILB production

10 Road Type-1 11 Open Drain Work 12 Truck Parking Area 13 Laboratory / Field Test 14 Interlocking Block

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of March 1,2012


S.l. Description No. 1 Yard Drainage 2 3 4 5 6 7 8 9 Sub-station Building RMG Track(Seg-1A) RTG Track (Seg-1A) Segment-1 Segment-2 Segment-4 Segment-3 Road Type-1 Work Program of March 1,2012 Side CC (02 Nos 800mm dia) Bricks masonry work & Plastering . Concrete Pouring (16cum) Sub-base work Settlement Record Surcharge material placement 150mm local sand compaction Dismantling work 300mm Base course laying. Bracing Fixing (near Navy gate.) Wall casting CH 920-930/2nd lift/Yard side 11 Truck Parking Area 12 Laboratory / Field Test 13 Interlocking Block (02 Nos Plant) Sub-grade Preparation Regular Test (ILB/Cylinder) ILB production Bracing Fixing (near Navy gate.) in progress Rebar fabrication & Shuttering executed. Sub-grade Preparation in progress. Regular Test (ILB/Cylinder) ILB production in progress.(18,400 Nos) Bricks masonry work & Plastering in progress. Rebar binding & Shuttering in progress. Sub-base work in progress Settlement Record in progress. Surcharge material placement in progress. 150mm local sand compaction in progress. Dismantling work in progress. Achievement of February 29,2012
Remarks

10 Open Drain Work

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of March 3,2012


S.l. Description No. 1 2 3 4 5 6 7 8 9 Yard Drainage Sub-station Building RMG Track(Seg-1A) Service Area Cable trench RTG Track (Seg-1A) Segment-1 Segment-2 Segment-3 Work Program of March 3,2012 Base CC 30rm ( 300mm dia) Wall casting of 02 Nos Manhole & 02 Nos Gully hole. Bricks masonry work & Plastering . Pre-cast transverse sleepers fixing Lean concrete casting(18 Mpa) Base Casting Sub-base work Settlement Record Surcharge material placement Dismantling work 300mm Base course laying. Bracing Fixing (near Navy gate.) Shuttering of wall CH 920-930/3rd lift/Yard side Sub-grade Preparation Regular Test (ILB/Cylinder) ILB production Sub-grade Preparation in progress. Regular Test (ILB/Cylinder) ILB production in progress.(18,400 Nos) Bricks masonry work & Plastering in progress. Pre-cast transverse sleepers fixing in progress. Lean concrete casting(18 Mpa) in progress. Rebar fabrication & Shuttering executed. Sub-base work in progress Settlement Record in progress. Surcharge material placement in progress. Dismantling work in progress. 300mm Base course laying.in progress Bracing Fixing (near Navy gate.) in progress Achievement of March 2,2012
Remarks

10 Road Type-1 11 Open Drain Work 12 Truck Parking Area 13 Laboratory / Field Test 14 Interlocking Block (02 Nos Plant)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of March 25,2012


S.l. Description No. 1 2 Yard Drainage (Seg 1A) Yard Drainage (Seg 2A) Work Program of March 25,2012 Rebar binding & Shuttering of wall of Gully hole. Concrete Pouring of wall of Gully hole Yard Drainage,Pipe laying & Side cc casting Rod binding of base of Manhole. 3 Sub-station Building Platering work Lime Tracing work of slab 4 5 6 7 8 9 RMG Track(Seg-1A) Service Area Segment-1 Segment-2 Segment-3 Navy Area Rebar binding & Shuttering of Longitudinal sleepers. Sub-base work Surcharge material removing Surcharge material placement Dismantling work Surface drain work 300mm Base course laying. Base casting near road way box culvert. Column shuttering & Casting Regular Test (ILB/Cylinder) ILB production Regular Test (ILB/Cylinder) 300mm Base course laying.in progress Rebar binding & Shuttering. Platering work in progress. Lime Tracing work of slab in progress. Rebar binding & Shuttering of Longitudinal sleepers in progress. Sub-base work in progress. Surcharge material removing in progress. Surcharge material placement in progress. Dismantling work in progress. Yard Drainage,Pipe laying & Side cc casting in progress Achievement of March 24,2012 Rebar binding & Shuttering of wall of Gully hole.
Remarks

10 Road Type-1 11 Open Drain Work 12 Boundary Wall 13 Laboratory / Field Test Interlocking Block (02 Nos 14 Plant)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of March 27,2012


S.l. Description No. Segment-1A 1 2 3 Yard Drainage RMG Track Sub-station Building Work Program of March 27,2012 Achievement of March 26,2012
Remarks

Rebar binding & Shuttering of wall of Gully hole. Concrete Pouring of wall of Gully hole (02 Nos) Concrete Pouring (02 Nos span) Platering work Lime Tracing work of slab

Rebar binding & Shuttering of wall of Gully hole.

Rebar binding & Shuttering executed. Platering work in progress. Lime Tracing work of slab in progress. Rebar binding & Shuttering in progress.

Service Area

Rebar binding & Shuttering .

Segment-2A 1 Yard Drainage Pipe laying & Side cc casting Base of Manhole(02 Nos). CC casting of Gullyhole(02 Nos) Segment-1 1 1 Surcharge Surcharge Surcharge material removing Surcharge material placement Surcharge material removing in progress. Surcharge material placement in progress. Segment-2 Pipe laying & Side cc casting in progress Rebar binding & Shuttering executed.

Segment-3 1 Dismantling Existing pavement dismantling Existing pavement dismantling in progress.

Segment-4 1 PVD PVD Driving

Navy Area 1 2 3 Surface drain work Cable Laying Main gate Brick masonry work Earth excavation Layout fixing & Earth excavation for column Brick masonry work in progress

Road Type-1 1 Base Course(300mm) Crushed stone laying. Crushed stone laying in progress.

Open Deep Drain Work 1 1 1 Chainage (920-930) Chainage (1-50) Interlocking Block Base casting Column shuttering & Casting Compressive strength test Rebar binding & Shuttering. Column shuttering & Casting in progress Boundary Wall Laboratory / Field Test

Sheet Pile Driving 1 2 Hammer Installation Site Clearance Hammer Installation at bank site Bank site clearing.

Interlocking Block Production 1 ILB production ILB production in progress(12400 Nos)

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of March 28,2012


S.l. Description No. Segment-1A 1 Yard Drainage 2 RMG Track 3 Sub-station Building 4 Service Area Segment-2A 1 Yard Drainage Work Program of March 28,2012 Achievement of March 27,2012 Concrete Pouring of wall of Gully hole (02 Nos) executed. Concrete Pouring (02 Nos span) executed. Platering work in progress. Lime Tracing work of slab in progress. Rebar binding & Shuttering in progress. Pipe laying & Side cc casting in progress Rebar binding & Shuttering executed. Remarks

Rebar binding & Shuttering . Platering work Lime Tracing work of slab Rebar binding & Shuttering . Pipe laying & Side cc casting Base of Manhole(02 Nos). CC casting of Gullyhole(02 Nos) Surcharge material removing Surcharge material placement Existing pavement dismantling PVD Driving Brick masonry work Earth excavation Layout fixing & Earth excavation for column

Segment-1 1 Surcharge Segment-2 1 Surcharge Segment-3 1 Dismantling Segment-4 1 PVD Navy Area 1 Surface drain work 2 Cable Laying 3 1 1 1 1 Main gate Road Type-1

Surcharge material removing in progress. Surcharge material placement in progress. Existing pavement dismantling in progress. PVD Driving in progress. Brick masonry work in progress Earth excavation in progress.

Base Course(300mm) Crushed stone laying. Chainage (720-730) Chainage (1-50) Interlocking Block Earth excavation Column shuttering & Casting Compressive strength test

Crushed stone laying in progress.

Open Deep Drain Work Boundary Wall Column shuttering & Casting in progress Laboratory / Field Test Sheet Pile Driving 1 Hammer Installation Hammer Installation at bank site 2 Site Clearance Bank site clearing. Interlocking Block Production 1 ILB production

Hammer Installation at bank site in progress. Bank site clearing in progress No production due to mechanical fault.

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of March 29,2012 S.l. Description No.
Segment-1A 1 Yard Drainage 2 RMG Track 3 Sub-station Building 4 Service Area 5 Cable Trench work Segment-2A 1 Yard Drainage

Work Program of March 29,2012

Achievement of March 28,2012

Remarks

Rebar binding & Shuttering . Platering work Lime Tracing work of slab Rebar binding & Shuttering . Soling & Rebar binding. Pipe laying & Side CC casting Base Casting of Gullyhole(02 Nos).

Rebar binding & Shuttering in progress. Platering work in progress. Lime Tracing work of slab in progress. Rebar binding & Shuttering in progress. Soling & Rebar binding in progress. Pipe laying & Side CC casting in progress Rebar binding & Shuttering executed.

Segment-1 1 Surcharge Segment-2 1 Surcharge Segment-3 1 Dismantling Segment-4 1 PVD Navy Area 1 Surface drain work 2 Cable Laying 3 Main gate Road Type-1

Surcharge material removing Surcharge material placement Existing pavement dismantling PVD Driving Brick masonry work Earth excavation Layout fixing & Earth excavation for column

Surcharge material removing in progress. Surcharge material placement in progress. Existing pavement dismantling in progress. PVD Driving in progress. Brick masonry work in progress Earth excavation in progress.

1 Base Course(300mm) Crushed stone laying. Open Deep Drain Work 1 1 1 Chainage (720-730) Chainage (1-50) Interlocking Block Base casting. Column shuttering & Casting Compressive strength test Boundary Wall Laboratory / Field Test

Crushed stone laying in progress. Rebar binding & Shuttering executed.

Compressive strength test Hammer Installation at bank site in progress. Bank site cleaning in progress No production due to mechanical fault.

Sheet Pile Driving 1 Hammer Installation Hammer Installation at bank site 2 Site Cleaning Bank site cleaning. Interlocking Block Production 1 ILB production

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA

NCT BACK-UP PROJECT, CHITTAGONG Work Program of March 31,2012 S.l. Description No.
Segment-1A 1 Yard Drainage 2 RMG Track 3 Sub-station Building RTG Track 4 Service Area 5 Cable Trench work Segment-2A 1 Yard Drainage

Work Program of March 31,2012


Concrete pouring of wall(01 no Gullyhole) Rebar binding & Shuttering . Platering work Lime Tracing work of slab Sub-base work Rebar binding & Shuttering . Shuttering & Rebar binding. Pipe laying & Side CC casting Base Casting of Manhole(02 Nos). CC work of Gullyhole. Surcharge material removing Surcharge material placement Existing pavement dismantling Sand blanket laying Brick masonry work Earth excavation Layout fixing & Earth excavation for column

Achievement of March 30,2012


Shuttering of wall (01 no Gullyhole) Rebar binding & Shuttering in progress. Platering work in progress. Lime Tracing work of slab in progress. Sub-base work in progress. Rebar binding & Shuttering in progress. Shuttering & Rebar binding in progress. Pipe laying & Side CC casting in progress Rebar binding & Shuttering executed.

Remarks

Segment-1 1 Surcharge Segment-2 1 Surcharge Segment-3 1 Dismantling Segment-4 1 200mm sand blanket Navy Area 1 Surface drain work 2 Cable Laying 3 1 1 1 1 Main gate Road Type-1

Surcharge material removing in progress. Surcharge material placement in progress. Existing pavement dismantling in progress.

Brick masonry work in progress Earth excavation in progress.

Base Course(300mm) Crushed stone laying. Chainage (720-730) Chainage (1-50) Interlocking Block Wall casting. Column shuttering & Casting Compressive strength test

Crushed stone laying in progress. Rebar binding & Shuttering executed.

Open Deep Drain Work Boundary Wall Laboratory / Field Test Compressive strength test Hammer Installation at bank site in progress. Bank site cleaning in progress ILB production (11,860 Nos) Sheet Pile Driving 1 Hammer Installation Hammer Installation at bank site 2 Site Cleaning Bank site cleaning. Interlocking Block Production 1 ILB production

Project Manager NCT Back-up/PBL

Sub Assistant Engineer-1 NCT Back-up/CPA

Sub Assistant Engineer-2 NCT Back-up/CPA

Assistant Engineer NCT Back-up/CPA