Sie sind auf Seite 1von 31

Hawar Highway Improvement (from Jaw to Al Dour)

No. Item Description Unit Quantity Rate Amount


BD.
CLASS A: GENERAL ITEMS
Contractual requirements
A1 Performance bond (clause (.1) sum 3,000.000
A2 Insurance of the Works (as clause 21.1 sum 1,500.000
A3 Third party insurance (as clause 23.1) sum 1,000.000
A4 Insurance against damage to persons and property sum 1,000.000
(as clause 24.2)

Specified requirements
Accommodation for the Engineer's staff

A5 Establishment and removal of offices as described sum 3,000.000

A6 Maintenance of offices wks 26 75.000 1,950.000

Services for the Engineer's staff

A7 Establishment and removal of telephones/fax as sum 200.000


specification clause 104
A8 Maintenance of telephones/fax wks 26 25.000 650.000

Equipment for use by the Engineer staff

A9 Establishment and removal of office equipments as sum 2,500.000


described
A10 Maintenance of office equipments wks 26 25.000 650.000
A11 Establishment and removal of surveying equipment as
described sum 500.000
A12 Maintenance of surveying equipment wks 26 15.000 390.000
A13 Testing of material sum 1,000.000
A14 Testing of the works sum 2,000.000
Temporary works
A15 Installation and removal of traffic diversions as sum 1,000.000
described
A16 Maintenance of traffic diversions. wks 26 25 650.000
A17 Establishment and removal of plastic Water-filled traffic barrier sum 1 10,000.000
in accordance with the "interim specification for plastic water
filled traffic barrier"

Class A
29 To Collection BD 30,990.000

Page 1 of 31
Hawar Highway Improvement (from Jaw to Al Dour)

Number Item Description Unit Quantity Rate Amount


BD
A18 Maintenance of plastic water-filled traffic barriers as wk 26 20.000 520.000
described
A19 Establishment and rtemoval of traffic safety control as described sum 1,000.000
A20 maintenanace of traffoc safety and control as described wk 26 25.000 650.000
A21 Establishment and removal of mobile electronic varaible
message sign (VMS) equipment as described sum 23,600.000

A22 maintenance of VMS eqipment wks 26 25.000 650.000


A23 Establishment and removal of mobile electronic directional
arrows (DA) equipment as described sum 7,900.000
A24 Maintenance of DA equipment wks 26 25.000 650.000

A25 Establishment and removal of sign boards as described nr 2 400.000 800.000


A26 Maintenance of signj boards wk 26 20.000 520.000

Photographs
A27 Provision of digital camera for use on site as described nr 1 250.000 250.000
A28 Set of selected digital photographs as described nr 100 3.000 300.000

As built drawings
A29 Provide a set of "As-Built" drawings upon sum 600.000
completion of the contract. For this purpose
the contractor will be supplied with a set of
negatives of all the drawings for his use and
the final set to the Engineer shall show the
co-ordinates of all the ducts, the depth, the
size and the number of pipes, whether they
are utilised, and all other information relating
to the road positioning and heights, etc.
NOTE : The issue of the Certificate of
Practical Completion will depend on the
satisfactory supply of the above drawings
to the Engineer

Class A
30 To Collection BD 37,440.000

Page 2 of 31
Hawar Highway Improvement (from Jaw to Al Dour)
Number Item Description Unit Quantity Rate Amount
BD.
Provisional sums
Daywork
A30 Labour sum 1,000.000
Percentage adjustment to provisional sum for day work labour 100.000
A31 materials sum 1,000.000
Percentage adjustment to provisional sum for day work material 100.000
A32 Plant sum 1,000.000
Percentage adjustment to provisional sum for day work plant 100.000

Other Provisional Sums

A33 Allow for the relocation of existing street lighting posts sum 35,000.000
A34 Relocation of overhead electrical cables sum 25,000.000
Other cahrges and profits % 12,500.000
A35 Relocation of underground electrical cables sum 20,000.000
A36 Earthwork in connection with relocationna nd diversion of
water supply sum 20,000.000

A37 Allow for the relocation of telephone cable netwrok


by Batelco sum 25,000.000

Class A
31 To Collection BD 140,800.000

Page 3 of 31
Hawar Highway Improvement (from Jaw to Al Dour)

COLLETION From
Page

29 30,990.000
30 37,440.000
31 140,800.000

Class A - Total to Grand Summary


32 209,230.000

Page 4 of 31
Hawar Highway Improvement (from Jaw to Al Dour)

Number Item Description Unit Quantity Rate Amount


BD.

CLASS B : GROUND INVESTIGATION

Trial pits and trenches

Number in material other than rock

B1 Minimum plan area at bottom of excavation


1 m2 ; maximum depth not exceeding 1m nr 50 10.000 500.000

B2 Maximum length at bottom of excavation


5m ; maximum depth not exceeding 1m nr 50 16.000 800.000

B3 Minimum plan area at bottom of excavation 1m2; maximum nr 50 20.000 1,000.000


depth 1-2m

B4 Maximum length at bottom of excavation 5m nr 50 50.000 2,500.000


maximum depth 1m - 2m
number in material which includes rock
B5 minimum plan area at bottom of excavation 1m2; maximum depth nr 50 40.000 2,000.000
1-2m
B6 Maximum length at bottom of excavation 5m m 50 50.000 2,500.000
maximum depth 1m - 2m
B7 depth in material other than rock m 300 15.000 4,500.000

B8 Depth in rock m 200 35.000 7,000.000

B9 depth backfilled, selected excavated material m 300 6.000 1,800.000

Class B
33 22,600.000

Page 5 of 31
Hawar Highway Improvement (from Jaw to Al Dour)

Number Item Description Unit Quantity Rate Amount


BD.

CLASS B : GROUND INVESTIGATION

33 22,600.000

Class B
34 22,600.000

Page 6 of 31
Hawar Highway Improvement (from Jaw to Al Dour)

Number Item Description Unit Quantity Rate Amount


BD.

CLASS D : DEMOLITION AND SITE


CLEARANCE
General clearance

D1 General site clearance ha 9.00 50.000 450.000


Other structures
Break out and remove from site
D2 Existing precast concrete kerb; size 125mm x 250mm; including m 280.00 1.500 420.000
foundationn and backing
D3 Existing speed hump nr 5.00 10.000 50.000
D4 Existing square concrete slabs m2 36 2.000 72.000
Remove and relocate
D5 Existing plam trees nr 91 60.00 5,460.000
D6 Existing sign board (as directed by the S.O 5.50m clearance nr 1 -
to be maintained)
D7 xisting electricity/lighting poles nr 49 60.00 2,940.000

D8 Existing temporaray fence m 200 40.00 8,000.000

Remove and set aside for re-use


D9 Paving blocks; 60mm thick m2 32 2.00 64.000
D10 Paving blocks; 80mm thick m2 795 2.50 1,987.500

Remove form site


D11 Existing garden / plants m2 6020 3.00 18,060.000
Pipeline (including any bed and surround) and disposal
D12 Gully and surround; includig sealing off 150mm pipe and nr 5 75.00 375.000
backfilling with concrete

Class D
35 To Collection BD 37,878.500

Page 7 of 31
Hawar Highway Improvement (from Jaw to Al Dour)

Number Item Description Unit Quantity Rate Amount


BD.

CLASS D: DEMOLITION AND SITE CLEARANCE

35 37,878.500

Class B
36 37,878.500

Page 8 of 31
Hawar Highway Improvement (from Jaw to Al Dour)

Number Item Description Unit Quantity Rate Amount


BD.
Class E: Earth works
Excavation for cuttings
E1 Material other than top soil, rock or artificial
hard material m3 10797 0.700 7,557.900
E2 Rock m3 550 10.000 5,500.000
E3 Asphalt exposed at the commencing surface m3 373 4.000 1,492.000
Excavation ancillaries
Preparation of excavated surfaces
E4 Material other than top soil, rock or artificial
hard material m2 5100 0.250 1,275.000
Disposal of excavated material
E5 Material other than top soil, rock or artificial
hard material m3 10797 0.600 6,478.200
E6 rock m3 550 0.600 330.000
E7 asphalt m3 373 0.600 223.800
Filling
Embanlment
E8 imported dredged fill type B m3 4850 6.000 29,100.000
General
E9 Regulating type B; depth 150-200mm m2 2630 0.900 2,367.000

to stated depth or thickness


imported crushed run in capping layer;

E10 thickness 200mm m2 12574 1.600 20,118.400


imported crushed run in capping layer; inclined at
an angle of 10 to 45 degrees from the horizontal
E11 thickness 200mm m2 610 1.800 1,098.000
Filling Ancillaries
Trimming of filled surfaces
E12 material other than top soil, rock or artificial hard m2 15609 0.250 3,902.250
material

Class E
37 To Collection BD 79,442.550

Page 9 of 31
Hawar Highway Improvement (from Jaw to Al Dour)

Number Item Description Unit Quantity Rate Amount


BD.
E13 Material other than top soil, rock or artificial
hard material; inclined at an angle of 10 to 45 degrees from the m2 2288 0.350 800.800
horizontal

Preparation of formation in filled areas


E14 Material other than top soil, rock or artificial
hard material m2 18837 0.250 4,709.250
E15 Material other than top soil, rock or artificial m2 4576 0.350 1,601.600
hard material; inclined at an angle of 10 to 45 degrees from the
horizontal
Work in connectin with the service protection
E16 Exacation of exposed services m3 700 7.000 4,900.000
E17 Excavation to proposed services; in trenches m3 690 8.000 5,520.000
E18 Disposalof excavated material m3 1390 2.000 2,780.000
E19 Filling around exposed services with TYPE B material m3 690 6.000 4,140.000
E20 Filling to cable/service protection; 50mm thik with fine sand m2 659 1.200 790.800
E21 Filling to cable/service protection; 100mm thik with fine sand m2 2335 2.400 5,604.000
E22 Provision of concrete; as specification clause 518 m3 727 40.000 29,080.000
E23 Placing of concrete as protection to service; bed not exceeding m3 727 7.000 5,089.000
150mm thick

Class E
38 To Collection BD 65,015.450

Page 10 of 31
Hawar Highway Improvement (from Jaw to Al Dour)

COLLETION From
CLASS E: EARTHWORKS Page

37 79,442.550
38 65,015.450

39 144,458.000

Page 11 of 31
Hawar Highway Improvement (from Jaw to Al Dour)

Number Item Description Unit Quantity Rate Amount


BD.

CLASS I : PIPE WORK - PIPES

Unplasticised polyvinyl chloride (uPVC) pipes as specification


clause 501.3

nominal bore 250mm


I1 In trenches; depth not exceeding 1.5m m 1606 15.000 24,090.000
nominal bore 300-600mm 3way
I2 In trenches; depth 1.5-2m m 48 60.000 2,880.000
Nominal bore 150mm
I3 In trenches; depth not exceeding 1.5m m 1012 12.000 12,144.000

Class K To Collection BD 39,114.000


40

Page 12 of 31
Hawar Highway Improvement (from Jaw to Al Dour)

COLLETION From
CLASS I: PIPE WORK - PIPES Page

40 39,114.000

41 39,114.000

Page 13 of 31
Hawar Highway Improvement (from Jaw to Al Dour)

Number Item Description Unit Quantity Rate Amount


BD.
CLASS J: PIPE WORK - FITTING AND VALVES
Unplasticised polyvinyl chloride (uPVC) pipes as general
specification clause 501.3
Bends
JI niminal bore 200mm nr 10 12.000 120.000
Junctions and branches
J2 nominal bore 200mm nr 95 17.000 1,615.000

Class K To Collection BD 1,735.000


42

Page 14 of 31
Hawar Highway Improvement (from Jaw to Al Dour)

COLLETION From
CLASS J: PIPE WORK - FITTING AND VALVES Page

42 1,735.000

43 1,735.000

Page 15 of 31
Hawar Highway Improvement (from Jaw to Al Dour)

Number Item Description Unit Quantity Rate Amount


BD.
CLASS K: PIPE WORK - MANHOLE AND PIPE WORK
ANCILLARIES
Manhole (depth measured to invert level)
In situ concrete chamber type 'D' as standard detail SD1.5
K1 depth not exceeding 1.5m nr 41 300.000 12,300.000
K2 depth 1.5-2m nr 1 375.000 375.000
K3 depth 2.-2.5m nr 2 450.000 900.000
Soakaways (depth measured to top of base cover)
in situ concrete
depth 3.5 - 4m
In situ concrete chamber type 'E' as standard detail SD1.6
including RTR liner
depth 2 - 2.5m
Soakaway (depth measured to top of base cover as standard
detail SD 3.70)
Brick
K4 depth 1.5-2m nr 1 700.000 700.000
K5 depth 2-2.5m nr 1 750.000 750.000
K6 depth 2.5-3m nr 1 800.000 800.000
K7 depth 3 - 3.5m nr 1 850.000 850.000
K8 depth 3.5 - 4m nr 1 900.000 900.000
Gullies
K9 Plastic with in-situ concrete surround as standard detail nr 146 100.000 14,600.000
SD3.10
Ducts, uPVC pipe BS 3506(except class 'O') spigot and socket
flexible joints in srevice ducts; as standard detail 5.06 & 5.07
Service duct 2 way 100mm pipes
K10 In trenches, depth not exceeding 1.5m m 184 6.000 1,104.000
service duct ; 4 way 150mm pipes
K11 In trenches, depth not exceeding 1.5m m 454 15.000 6,810.000
K12 in trenches depth not exceeding 1.5m m 48 23.000 1,104.000
Crossings
High voltage cable
K13 to be crossed by 4 x 150mm duct nr 48 40.200 1,929.600
K14 to be crossed by 2 x 100mm duct nr 19 24.000 456.000

Class K To Collection BD 43,578.600


44

Page 16 of 31
Hawar Highway Improvement (from Jaw to Al Dour)

Number Item Description Unit Quantity Rate Amount


BD.

K15 to be crossed by 6 x 150mm duct nr 5 42.000 210.000


-
Other pipework ancillaries

K16 Duct marker blocks; precast concrete; stamp coded with duct nr 72 7.000 504.000
type; as standard detail SRCD 5.08a

Class K To Collection BD 714.000


45

Page 17 of 31
Hawar Highway Improvement (from Jaw to Al Dour)

COLLETION From
CLASS K: PIPE WORK - MANHOLE AND Page
PIPE WORK ANCILLARIES

44 43,578.600
45 714.000

46 44,292.600

Page 18 of 31
Hawar Highway Improvement (from Jaw to Al Dour)

Number Item Description Unit Quantity Rate Amount


BD.

CLASS L : PIPE WORK - SUPPORTS AND


PROTECTION, ANCILLARIES
Extras to excavation and backfilling
In manhole and other chambers
L1 excavation of rock m3 1986 12 23,832.000
Surrounds

Imported granular material as General Specification


Clause 504.2 and as Standard Details SD 3.1,
SRCD 5.06, 5.07, 5.08 and 5.09
L2 to 4 way 150mm duct m 454 24.000 10,896.000
L3 to 2 way 100mm duct m 184 16.000 2,944.000
L4 to 6 way 150mm duct m 48 36.000 1,728.000

Concrete class 20/20 as General Specification


Clause 504.5 and Standard Details SD 3.1,
SRCD 5.06, 5.07, 5.08 and 5.09 ;
L5 to 4 way 150mm duct m 512 60.000 30,720.000
L6 to 2 way 100mm duct m 207 30.000 6,210.000
L7 to 6 way 150mm duct m 54 80.000 4,320.000

Class L To collection BD 80,650.000


47

Page 19 of 31
Hawar Highway Improvement (from Jaw to Al Dour)

COLLETION From
CLASS L: SUPPORTS AND PROTECTION Page
ANCILLARIES

47 80,650.000

48 80,650.000

Page 20 of 31
Hawar Highway Improvement (from Jaw to Al Dour)

Number Item Description Unit Quantity Rate Amount


BD.
CLASS R : ROADS AND PAVINGS
Sub - Bases
Modified material 'A' (Road Base) material
R1 depth 200mm m2 6083 1.300 7,907.900
R2 Regulating Type; 100 - 150mm m2 920 0.900 828.000
Type B dredged material
R3 depth exceeding 300mm m2 4439 1.130 5,016.070
Sub-bases, flexible road bases and surfacing ;
as General Specification Section 900
Asphalt base course type B28; imported aggregate
R4 depth 75mm m2 10320 3.510 36,223.200
Asphalt wearing course GW20 (TM5)
R5 depth 50mm m2 35661 2.340 83,446.740
R6 Goefabric: poly felt type PGM 14 m2 3186 0.600 1,911.600

R7 Road oil sprayed on sub-base as described m2 31840 0.150 4,776.000

R8 Tack coat sprayed on asphalt surface as described m2 24141 0.200 4,828.200


305,608.540
R9 Removal of flexible surface by cold planning m2 4262 35.000 149,170.000
Vertical saw cut asphalt
R10 Depth exceeding 100mm and not exceeeding 150mm m 2967 1.000 2,967.000
R11 Regulating course of asphalt type GW20 (TM5) m3 441 47.000 20,727.000
R12 EXTRA OVER asphalt surfacing; any type (Including GW20 m2 386 0.800 308.800
(TM5) and thickness; for laying by hand
R13 Speed humps as standard detail SRCD 10.07; complete nr 5 250.000 1,250.000
including yellow paint; for 7.5 metre carriageway

Class R To collection BD 319,360.510


49

Page 21 of 31
Hawar Highway Improvement (from Jaw to Al Dour)

Number Item Description Unit Quantity Rate Amount


BD.

Kerbs, channels and edgings as General Specification


Clasue 1001
Precast concrete kerbs; half battered; 125 x 250mm; as
standard detail SRCD 10.01 and 10.02
R14 straight or curved to radius exceding 12m m 5244 7.000 36,708.000

R15 curved to radius not exceeding 12m m 280 9.000 2,520.000


R16 dropped kerbs as standard detail SRCD 10.04, 10.05 m 24 10.000 240.000
and 10.06

Precast concrete kerbs; half battered 125 x 250mm, as


standard detail SRCD 10.08, laid flat
R17 straight or curved to radius exceeding 12m m 110 9.000 990.000
Precast concrete edgings 50 x 150mm; as standard detail
SRCD 10.01 and SRCD 10.2
R18 staright or curved to radius exceeding 12m m 1903 11.000 20,933.000
R19 curved to radius not exceeding 12m m 417 15.000 6,255.000
Light duty pavements
Granular base type A
R19 depth: 150mm m2 9533 1.100 10,486.300
Road base material
R21 depth 200mm m2 4439 1.500 6,658.500
Rectangular concrete paving blocks 200 x 100mm laid to
herringbone pattern with unifrom joints; on and including 30mm
sand bed
Colour RED
R22 thickness 60mm m2 9533 6.000 57,198.000
Rectangular concrete paving blocks 200 x 100mm laid to
herringbone pattern with unifrom joints; on and including 30mm
sand bed; FROM PREVIOSLY SET ASIDE
Colour RED
R23 thickness 60mm m2 32 3.000 96.000

Class R To collection BD 142,084.800


50

Page 22 of 31
Hawar Highway Improvement (from Jaw to Al Dour)

Number Item Description Unit Quantity Rate Amount


BD.
Ancillaries
Traffic Singns

R24 Code 2: Give Way 900mm nr 3 58.000 174.000


R25 Code 3 : No Entry; 600mm nr 5 48.000 240.000
R26 Code 4 - One - Way Traffic 500 x 650mm nr 19 48.000 912.000
R27 Code 5 : Keep Right; 600, 450 x 900mm nr 15 68.000 1,020.000
R28 Code 6: Vehicle may pass either side 450x700mm nr 7 65.000 455.000
R29 Code8: Turn Left/Right Chevron; 600 x 1800 nr 11 85.000 935.000
R30 Code 9: Turn Right; 600mm nr 1 48.000 48.000
R31 Code 14: Bend to Right Ahead 900mm nr 4 58.000 232.000
R32 Code 26: Double bend, first to right 900mm nr 2 58.000 116.000
R33 Code 15: Pedestrian crossing ahead; 900mm nr 2 58.000 116.000
R34 Code 16: Pedestrian Route; 600 x 600mm nr 4 48.000 192.000
R35 Code 17: Traffic Signal Ahead; 1200 x 1200x 600mm nr 6 120.000 720.000
R36 Code 18: Round about Ahead; 1200 & 1200 x 900mm nr 2 135.000 270.000
R37 Code 19: Two Way Traffic: 900mm nr 19 58.000 1,102.000
R38 Code 24: Maximum Speed Limit; 900mm nr 1 58.000 58.000
R39 Code 29: Speed Humps Ahead; 900, 300 x 900 mm nr 1 85.000 85.000
R40 Code 72: Road Name Sign; 900mm nr 1 125.000 125.000
Surface marking
non-reflective road studs
R41 die-cast aluminium; as described nr 5718 4.000 22,872.000
Reflecting road studs
R42 ceramic road studs; as described nr 300 1.300 390.000
R43 intermittent warning lines; 0.10m mm wide m 48 0.425 20.400

Class R To collection BD 30,082.400


51

Page 23 of 31
Hawar Highway Improvement (from Jaw to Al Dour)

Number Item Description Unit Quantity Rate Amount


BD.

R44 Give way line at roundabout; broken line of 1m mark,1m m 18 0.850 15.300
gap and 0.20m wide
R45 Broken line of 4.0m mark, 2.0m gap and width of 0.1m m 48 0.425 20.400
R46 Intermittent center line m 369 0.425 156.825
R47 Chevron lines; 100mm wide m 150 0.425 63.750
Hand or machine applied white thermoplastic road markings
R48 letters and shapes; arrows; as standard details drawing nr 40 6.700 268.000
R49 bus lay by edge/line; broken ;lines of 1.0m mark, 1.0m gap m 404 0.425 171.700
R50 Stop line solid line of 0.40m width mark up to m 127 1.700 215.900
R51 Speed humps markings as per detail design nr 5 53.000 265.000
Paint to kerbs as described -
R52 to exposed faces of kerb; black & yellow m 5244 0.325 1,704.300

Class R To collection BD 2,881.175


52

Page 24 of 31
Hawar Highway Improvement (from Jaw to Al Dour)

COLLETION From
Page

49 319,360.510
50 142,084.800
51 30,082.400
52 2,881.175

53 494,408.885

Page 25 of 31
Hawar Highway Improvement (from Jaw to Al Dour)

Number Item Description Unit Quantity Rate Amount


BD.

CLASS X : MISCELLANEOUS WORK


Fences
Metal Sfety Barriers
X1 Open Box Beam safety barriers (OBB) DOUBLE SIDED m 813 41 33,333.000

X2 Drainage to structures above ground


excavate for drainage ditch; maximum depth not exceeding
400mm m 3422 3.000 10,266.000
Others
X3 Provision and laying of 1 x 600mm pipes culvert as drainage nr 1 6000.000 6,000.000
off let to SRCD 5.05; Maximum length not exceeding 24m

X4 Provision and laying of 1 x 600mm pipes culvert as drainage nr 1 5800.000 5,800.000


off let to SRCD 5.05; Maximum length not exceeding 22m

X5 Provision and laying of 3 x 600mm pipes culvert as drainage nr 1 10000.000 10,000.000


off let to SRCD 5.05; Maximum length not exceeding 45m

X6 Provision and laying of 1 x 300mm pipes culvert as drainage nr 1 5000 5,000.000


off let to SRCD 5.05; Maximum length not exceeding 18m

X7 Provision and laying of 1 x 450mm pipes culvert as drainage nr 1 4500 4,500.000


off let to SRCD 5.05; Maximum length not exceeding 15m
Box Culvert
X8 Provide and place reinforced in situ concrete Class A nr 1 8000 8,000.000

Class X Total to Grand Summary


54 82,899.000

Page 26 of 31
Hawar Highway Improvement (from Jaw to Al Dour)

Number Item Description Unit Quantity Rate Amount


BD.

X9 Provide and place reinforced in situ concrete Class A nr 1 7500 7,500.000

X10 Mortared rip rap; 300mm thick m2 300 20 6,000.000

X11 Mortared rip rap; 150mm thick nominal size stone laid in full m2 200 14.000 2,800.000
class 1 mortar bed

Class X Total to Grand Summary


55 16,300.000

Page 27 of 31
Hawar Highway Improvement (from Jaw to Al Dour)

COLLECTION

CLASS X: MISCELLANEOUS WORK


From Page 54 82,899.000

From Page 55 16,300.000

Class Y Total to Grand Summary


56 99,199.000

Page 28 of 31
Hawar Highway Improvement (from Jaw to Al Dour)

Number Item Description Unit Quantity Rate Amount


BD.
CLASS Y : SEWER AND WATER MAIN
RENOVATION AND ANCILLARY WORKS
Existing manholes
Adjust levels of matalwork to surface boxes,
gullies and manholes, medium or heavy duty;
in foot paths or carriage way asphalt surfacing
metal work area 0.10 M2
Y1 raised not exceeding 150mm nr 17 12.000 204.000
Y2 raised 150 to 300mm nr 13 15.000 195.000
Y3 raised 300 to 450mm nr 3 18.000 54.000

Y4 lowered not exceeding 150mm nr 8 12.000 96.000


Y5 raised 150 to 300mm nr 4 15.000 60.000

Class Y Total to Grand Summary


57 609.000

Page 29 of 31
Hawar Highway Improvement (from Jaw to Al Dour)

COLLECTION

CLASS Y:
From Page 57 609.000

Class Y Total to Grand Summary


58 609.000

Page 30 of 31
Hawar Highway Improvement (from Jaw to Al Dour)

GRAND SUMMARY

CLASS DESCRIPTION From Page Amount


BD.

CLASS A GENERAL ITEMS 32 209,230.000

CLASS B GROUND INVESTIGATION 34 22,600.000

CLASS D DEMOLITION & SITE CLEARANCE 36 37,878.500

CLASS E EARTH WORKS 39 144,458.000

CLASS I: PIPE WORK - PIPES 41 39,114.000

CLASS J PIPE WORK - FITTING AND VALVES 43 1,735.000

CLASS KPIPEWORK - MANHOLES & PIPEWORK


ANCILLARIES 46 44,292.600

CLASS L PIPEWORK - SUPPORT AND PROTECTION,


ANCILLARIES 48 80,650.000

CLASS R ROADS AND PAVINGS 53 494,408.885

CLASS X MISCELLANEOUS ITEMS 56 99,199.000

CLASS Y SEWER & WATER MAIN RENOVATION &


ANCILLARY WORKS 58 609.000
Sub - Total 1,174,174.985
ADJUSTMENT ITEM
Deduction in adjustment of the total of the Bill Of Quantities which shall be
deemed to apply uniformly to all rates in the Bill Of Quantities for
the purpose of valuations and variations.
Note:- Provisional sums remain at their full value and are not affected
by any adjustment shown here.
Sub - Total 1,174,174.985

GENERAL CONTINGENCY ALLOWANCE


Allow 10% for General Contingency Allowance , to be expended in whole
or in part as expressly directed in writing by the Engineer. 117,417.499

TOTAL TO FORM OF TENDER 1,291,592.484

Page 31 of 31