Beruflich Dokumente
Kultur Dokumente
A truck cycle includes at least following elements: Load Haul Dump Return Spot at the shovel There is a range of times required to perform these five functions, depending upon : operator efficiency Weather
OPERATION ANALYSIS
Equipment condition Method of analyzing the times is to use an average time , realizing there will be rates of production above and below the average. Contractor shall determine the range of times required for each element of the operation and top perform the entire cycle.
OPERATION ANALYSIS
If the density of the air is reduced because of altitude, the quantity of oxygen in a given volume of air will be less than for the same volume of air at the sea level. As each cylinder of an engine draws in a given volume of air prior to firing stroke, there will be necessary to reduce the quantity of fuel supplied to an engine at high altitudes. This is usually done by adjusting the carburetor. The effect on the engine is to reduce the power.
Contd
The effect of loss in power due to altitude may be eliminated by the installation of a supercharger. This is a mechanical unit which will increase the pressure of the air supplied to the engine, thus permitting sea-level performance at any altitude. If equipment is to be used at high altitudes for long periods of times, the increased performance probably will more than pay for the installed cost of a supercharge.
A contractor who has established production rates for his equipment at or near sea level will make a serious mistake if he uses those production rates in bidding a job to be constructed at a high altitude. He must install superchargers or apply a correction factor, which is more fully explained under the subjects of trucks and tractors.
Contd..
He may reduce the depth of penetration of the dipper into the face in order to fill the dipper in one stroke. This will increase the time for a cycle. He may start digging above the base of the face, and then remove the lower portion of the face latter. He may run the dipper up the full height of the face and let the excess earth spill down to the bottom of the face, to be picked up later.
The choice of any of above 3 procedures will result in some lost time, based on the time required to fill the dipper when it is digging at optimum depth.
The optimum depth varies with the class of material and the size of the dipper.
Contd
Job conditions may be classified as Excellent, good, fair and poor. The re is no uniform standards which may be used as a guide in classifying a job. Each job planner must used his own judgment and experience in deciding which condition best represents his job.
The effect of management conditions on the output of a power shovel The owner of a shovel may take following steps to improve management conditions so as to improve the output the shovel ;
Greasing and lubricating the shovel frequently. Checking the shovel parts that are subject to the greatest wear, and replacing worn parts while the shovel is not being operated, as at the end of a shift.
Replacing badly worn wire rope between shifts. Replacing dull dipper teeth with sharp ones, as required. Giving the shovel a major overhaul between jobs, if necessary. Keeping at the job extra parts that are subject to the greatest wear.
Contd
Keeping the pit floor clean and smooth to permit better truck spotting and to reduce the angle of swing. Providing adequate trucks of the correct size to eliminate lost time in loading and waiting for trucks. Paying a bonus to the crew for production in excess of an agreed amount to encourage high production.
Illustration
On one such project, where the cost was exceeding the estimate, an analysis was made to determine methods of reducing cost of excavating and hauling the earth. The material was common earth. The analysis of the operations revealed the following information :
Size of power shovel, 1.5 cu yd. Depth of cut, 12 ft. Angle of swing, 1200 Size of trucks, 6 cu yd bm Round-trip time for a truck, 19 min\ No. of trucks 18
The time spent by shovel in cleaning up the floor of the pit, moving, and undergoing repairs reduced the actual excavating time to about 30 min per hr.
Contd
The floor of pit was rough, muddy, and heavily rutted because of inadequate drainage, which reduced the efficiency of the hauling units. The output averaged 108 cu yd per hr. The direct cost of excavating and hauling the earth was determined as follows ; Shovel, operator and oiler =$87.50 per hr Trucks and driver, 8 @ $28.80 = 232.40 per hr Direct overhead and supervision = 31.20 per hr Total cost = sum of above three = $ 349.10 per hr Cost per cu yd, $349.10 / 108 = $3.23
Contd
The analysis indicates that the output could be increased by taking the following steps :
Use a small bulldozer to keep the floor of the pit clean and well drained. Reduce the depth of cut to the optimum. Reduce the angle of swing to 750 by improving the floor of the pit. Improve the job conditions to good by proper maintenance of the pit and haul roads and by excavating at optimum depth.
Improve the management conditions to good by properly servicing the equipment at the end of the shifts and by paying a bonus of $0.04 per cu yd, to be divided among the workers, for all production in excess of 120 cu yd per hr. Reduce the round trip time of the trucks to 15 min by improving the haul road and the pit floor. Provide additional trucks to haul the increased output of the shovel.
Contd
If the recommended steps are taken, the probable output of the shovel will be as follows :
Estimated actual excavating time, 50 min per hr. Ideal output, 240 cu yd per hr Depth-swing factor, 1.07 Job-management factor, 0.75 Probable output, 240 X 1.07 X 0.75 = 193 cu yd per hr
The no. of trucks required to haul the earth will be calculated as follows :
Assume trucks operate 50 min per hr. No. of trips per hr truck, 50/15 =3.33 Volume hauled per hr per truck, 3.33 X 6 = 20 cu yd No. of trucks needed, 193 / 20 = 9.6. Hence Ten trucks are needed.
Contd
The revised direct cost of excavating and hauling the earth will be as follows :
Shovel, operator and oiler =$ 87.50 per hr Trucks and drivers, 10 @ $28.80 = 288 per hr Direct overhead and supervision = 31.20 per hr Cost of bulldozer and operator = 27.75 per hr Cost of bonus, 73 cu yd @ $ 0.04 = 2.92 per hr Total cost = sum of above = $ 437.37 per hr Cost per cu yd, $437.37/193 = $ 2.24 Net reduction in the cost per cu yd, $3.23-$2.24 = $ 0.09
This saving is sufficiently large to demonstrate the financial effect of applying intelligent engineering in the selection of equipment and in analyzing an operation. The failure to apply engineering analysis and in operation of a project is one reason why a contractor may complete a project with a loss, while another will complete a similar project with a profit.
The effect of the depth of cut and the angle of swing on the output of a Dragline % of Angle of Swing, in degree optimum 30 45 60 75 90 120 150 depth 20 1.06 0.99 0.94 0.90 0.87 0.81 0.75 40 60 80 100 120 140 1.17 1.08 1.24 1.13 1.29 1.17 1.32 1.19 1.29 1.17 1.25 1.14 1.02 0.97 0.93 0.85 0.78 1.06 1.01 0.97 0.88 0.80 1.09 1.04 0.99 0.90 0.82 1.11 1.05 1.00 0.91 0.83 1.09 1.03 0.98 0.90 0.82 1.06 1.00 0.96 0.88 0.81
Contd
A 2-cu-yd short-boom dragline is to be used to excavate hard tough clay. The depth of cut will be 15.4 ft, and the angle of swing will be 1200. Determine the probable output of the dragline if there are no other factors to affect the output. Solution : The percent of optimum depth, (15.4/11.8) X 100 = 130. Using previous table , the correction factor is 0.89. The probable output will be 195 X 0.89 = 173 cu yd per hr. For a 50-min hour the probable output will be; output = 0.83 X 173 = 143 cu yd.
The effect of job and management conditions on the output of a dragline The effect of job and management conditions on the output of a dragline will be about the same as for a power shovel.
The effect of the size of the Bucket and Length of the Boom on the Output of a Dragline In selecting the size and type bucket, the dragline and bucket should be matched properly in order to obtain the best action and the greatest operating efficiency, which will produce the greatest output of material. Buckets are generally available in three types: light-duty, medium-duty, and heavy-duty. Light-duty buckets are used for excavating materials which are dug easily, such as sandy loam, sandy clay, or sand.
Medium duty buckets are used for general excavating service such as digging clat, soft shale, or loose gravel. Heavy-duty buckets are used for mine stripping, handling blasted rock, and excavating hardpan and highly abrasive materials. Buckets are sometimes perforated to permit excess water to drain form the loads.
Contd
The normal size of a dragline bucket is based on its struck capacity, which is expressed more accurately in cubic feet. In selecting the most suitable size bucket for use with a given dragline, it is desirable to know the weight of the loosened material to be handled, expressed in pounds per cubic foot. While it is desirable to use the largest size bucket possible in the interest of increasing the output, care should exercised to see that the combined weight of the load and the bucket does not exceed the safe load recommended for the dragline.
Contd
Size cu yd Struck Weight of Dimension capacity medium duty In inch bucket Cu ft L W B 32 39 47 60 2945 3300 3750 4825 48 45 27 49 45 31 53 48 32 54 51 38
1 1.25 1.5 2
Illustration
The importance of this analysis uses previous table. Assume that the material to be handled has a loose weight of 90 lb per cu ft. The use of a 2-cu-yd mediumduty bucket will be considered. If the dragline is to be operated with an 80-ft boom at a 400 angle, the maximum safe load will be 8600 lb. The approximate weight of the bucket and its load will be
Taking Bucket = 4825 lb ( Medium-duty bucket) Earth, 60 cu ft @ 90 lb per cu ft = 5400 lb Combined weight =sum of above two = 10,225 lb Maximum safe load = 8600 lb
Contd
As this weight will exceed the safe load on the dragline, it will be necessary to use a smaller bucket. Trying a 1.5 cu yd bucket, whose combined weight will be
Bucket = 3750 lb Earth, 47 cu ft @ 90 lb per cu ft = 4230 lb Combined weight = 7980 lb
If a 1.5 cu yd bucket is used, it may be filled to heaping capacity, without exceeding the safe load of the dragline.
If a 70 ft boom, whose maximum safe load is 11,000 lb, will provide sufficient working range for excavating and disposing of the earth, a 2 cu yd bucket may be used and filled to heaping capacity. The reduced cycle time, in using the 70 ft boom, will probably offset the increased time required to fill the 2 cu yd bucket. The ratio of the output resulting from the use of a 70 ft boom and a 2 cu yd bucket, compared with a 1.5 cu yd bucket, should be approximately as follows; Output ratio, (60 cu ft / 47 cu ft ) X 100 = 127 % Increase in output = 27%
Contd
The previous example illustrates the importance of analyzing a job prior to selecting the size excavator to be used. The haphazard selection of equipment can result in a substantial increase in the cost of handling of earth.
The effect of the class of material and the size of the bucket on the cost of excavating earth with a dragline
120 105 90 75 60 45 30 15 0 0 3/8 1/2 3/4 1 1.25 1.5 Dragline size, cu yd 2 2.5 D C B A Excavating cost, cents per cu yd, bank measure Class of materials A, B, C, D A : Moist loam or sandy clay B : Good common Earth C: Hard, tough clay D: Wet sticky clay