MG3 PROJECT ADDENDUM 5 CONTENTS LIST S-1651-00-CL-0070 REV: 01 Page 1

PROJECT SPECIFICATION

REVISION DATE ORIG BY APP BY

01 APR 05 WK WK

D1

D2

D3

D4

MG3 PROJECT PROJECT SPECIFICATION ADDENDUM 5 CONTENTS LIST

SECTION 1.

SUBJECT GUIDANCE NOTES ON ADDENDUM 5

ATTACHMENT 1

ADDENDUM 5 - INDEX

ATTACHMENT 2

ADDENDUM 5 TABULATED COMMENTS

DSN:
W:\Project\Petronas\1651\Gen\28Shared\ITB Addendum 5\S-1651-00-CL-0070-Rev 01.doc

MG3 PROJECT S-1651-00-CL-0070 REV: D1 Page 2 of 8 ADDENDUM 5 CONTENTS LIST

PROJECT SPECIFICATION

1.0 1.1

GUIDANCE NOTES ON ADDENDUM 5 Addendum Format The MG3 Invitation To Bid package has been amended by the addition of the items enclosed in the Addendum 5 CD attached to this folder. Documents which have been included in this Addendum fall into three groups:

New documents which have been issued for the first time and support the existing package.

Revised documents where changes have been identified by a revision mark in the left margin. The convention followed is to show the document revision, such as D2, and the vertical line tracked change marking. For example, Changed text

D2

Tabulated comments where specific requirements in existing documents have been amended although the whole document has not been amended and re-issued in an Addendum. These tabulated comments are included in Attachment 2 of this document.

All documents are provided in PDF format and if Bidders search for the revision at which the document is issued (D2, D3 etc), Acrobat will identify pages which contain revised sections. 1.2 Addendum Index The index has been provided in Attachment 1 of this document and also as an XL file on the CD. A short description of the amendment has been included for clarity but full details on the changes are enclosed in the revised documents. The XL file will be of use to Bidders as it includes a hyperlink to the document location in the CD. 1.3 Addendum Item Numbering All items in Addendum 1 are numbered 1.1, 1.2, 1.3 etc. For ADDENDUM 5, items will be numbered 5.1, 5.2, 5.3 etc. The same numbering practice will follow on any further Addendum. 1.4 Major Addendum Scope Addendum 5 includes the specification for:

The deletion of Intermediate and Final Product Tanks: T-7243, T-7244, T-7542, T7543 and T-7541. General ITB addendum items. Tabulated addendum comments, refer to Attachment 2.

W:\Project\Petronas\1651\Gen\28Shared\ITB Addendum 5\S-1651-00-CL-0070-Rev 01.doc

MG3 PROJECT ADDENDUM 5 CONTENTS LIST PROJECT SPECIFICATION S-1651-00-CL-0070 REV: D1 PAGE: 3

ATTACHMENT 1 MG3 EPCC ITB ADDENDUM 5 INDEX


PETRONAS MG3 EPCC ITB ADDENDUM NO. 5 INDEX R = Wholly revised document N = Newly issued document
GENERAL MG3 ADDENDUM 5 ITEMS Addendum Item No. 5.10 5.11 5.12 DESCRIPTION OF CHANGE Additional Design Requirements (multidisciplinary) Fire and Gas Detection and Protection Specification Fire Fighting Facilities (Unit 65 Modification) HYPERLINK TO DOCUMENT OR TABULATED COMMENT S-1651-00-NV-1017 Rev D3 FORMAT Corresponding ITB CD Section

S-1651-00-SP-0011 Rev D2 S-1651-00-NV-2093 Rev D2

VALUE ENGINEERING WORKSCOPE GENERAL ENGINEERING Addendum DESCRIPTION OF CHANGE Item No. 5.21 Scope of Work and Design Basis

HYPERLINK TO DOCUMENT OR TABULATED COMMENT

FORMAT

Corresponding ITB CD Section

S-1651-00-NV-2540

PROCESS ENGINEERING Addendum DESCRIPTION OF CHANGE Item No. 5.301 5.302 5.303 5.304

HYPERLINK TO DOCUMENT OR TABULATED COMMENT

FORMAT

Corresponding ITB CD Section

5.305 5.306 5.307 5.308 5.309

Process Flow Schemes D-1651-75-20-0003 Rev D2 D-1651-75-23-0003 Rev D2 Material Selection Diagrams Design Pressure and Temperature Diagra D-1651-75-22-0003 Rev D2 Process Engineering Flow Schemes PMC D-1651-75-25-0001 Rev D3 PMC D-1651-75-25-0002 Rev D3 PMC D-1651-75-25-0006 Rev D3 PMC D-1651-75-25-0007 Rev D2 Licensor 04-142-4Z Licensor 04-128-3A Licensor 04-128-4B Licensor 04-128-4C Licensor 04-128-5H Licensor 04-128-3I Licensor 04-095-3J Line List S-1651-75-26-0001 Rev D2 S-1651-72-EL-0001 Rev D2 Equipment List Instrument Summary Sheets -

N N N N N N N N N N N N N N N N N N

S-1651-75-EL-0001 Rev D2 S-1651-75-PS-0015 Rev D3

MECHANICAL ENGINEERING Addendum DESCRIPTION OF CHANGE Item No. 5.40 5.41 Plot Plan: MG3 Process Complex Overall Site Plan

HYPERLINK TO DOCUMENT OR TABULATED COMMENT

FORMAT

Corresponding ITB CD Section

D-1651-00-01-0002 Rev D3 D-1651-00-01-0001 Rev D5

W:\Project\Petronas\1651\Gen\28Shared\ITB Addendum 5\S-1651-00-CL-0070-Rev 01.doc

MG3 PROJECT S-1651-00-CL-0070 REV: D1 Page 4 of 8 ADDENDUM 5 CONTENTS LIST

PROJECT SPECIFICATION

ATTACHMENT 2 MG3 EPCC ITB ADDENDUM 5 TABULATED COMMENTS

W:\Project\Petronas\1651\Gen\28Shared\ITB Addendum 5\S-1651-00-CL-0070-Rev 01.doc

MG3 PROJECT ADDENDUM 5 CONTENTS LIST S-1651-00-CL-0070 REV: 01 Page 1 of 5 5

PROJECT SPECIFICATION

ADDENDUM 5 ITEM

ITB VOLUME NO.

SECTION

SUB-SECTION

DESCRIPTION OF CHANGE

5.01

CD 1

C, II, 9.4

S-1651-00-NV2094 and S-1651-00-NV2014 ( and other general documents)

Original : Effluent Treatment System Upgrade scope Revised : The ETS Upgrade is to be deleted from the MG3 scope and BIDDERs are to proceed only with the Effluent PreTreatment Facility.

C, II, 14