EPC Contractor Erection Contractor Erection Sub Contractor : : : BGR Energy Systems Limited. ALSTOM T&D India Ltd. RB Electrical & Mechanical Works
ALSTOM came to Site and Started to work from September 4, 2013 (04.09.2013).
Works Completed:
Marking Core Cutting CB Box Shifting Anchor Bolt Fixing Structure Checking CB Erection CT Box Shifting and Testing CB Alignment CT Erection Single phase feeder disconnector Cable Laying Bus duct Enclosure for Common Point Disconnector Erection of Double Bus bar Common Point disconnector Cable tray Erection VT Box Shifting and Testing Line VT Support Structure Erection Bus EMVT Support Structure Erection Erection of BUS EMVT Erection of Bay VT GIB Marking and Core drilling GIB Structure Erection
Marking: Marking was started on Sep 4, 2013. All four References are marked with Co Ordinates given in the drawings. Centre Point for all bays was marked and Axis for all 3 poles is marked with Total Station.
Work Description
Marking
5 Days
Core Cutting: It was started consequently after the completion of Axis Marking. We have to do 12 no. of holes for 1 breaker. We have 3 breakers for 1 bay. Totally we have 9 bays 1 bay - 3 breakers = 36 no. of holes 9 bays 27 breakers = 324 no. of holes M18 Core Cutting bit was used to Core out the Concrete. Work Description Time taken to complete
Core cutting
4 days
CB Box Unpacking and Shifting: CB Boxes are started to unpack and shift inside GIS building from 9th day onwards. All 27 Breakers are unpacked outside GIS and shifted inside. Work Description CB Box Shifting Time taken to complete 8 days.
Anchor Bolt Fixing: Chemical Stud Capsules M16*125 are packed inside the drilled hole to strengthen the bolt with concrete and Fastened with Anchor bolts. M16 Anchor bolts are fixed for all bases. Work Description Time taken to complete
3 Days
CB Erection A day after Anchor bolt fixing, CB Base Structure Erection is completed within two days. CB Positioning is taken place after Base Structure Erection from Bay 1 Bay 9. Totally we have 27 breakers for 9 bays (3 breakers for Each Bay). Work Description Time taken to complete
4 days
CB Alignment: CB Alignment was started after completion of CB Erection. During marking time, we have marked the point based on which CB is going to align. CB Alignment tool was fixed at the top of Breaker. The Top level of the Breakers for all bay is 2327mm from 0 level. Work Description Time taken to complete
CB Alignment
6 days
Current Transformer Erection: CTs are started to erect consequently after the completion of CB Alignment. Here we are having four types of CTs based on its core. Work Description Time taken to complete
CT Erection
6 days
Bay
Line 1 Line 2 GT 1 Bus Reactor 1 Bus Coupler ST 1 ST 2 GT 2 Bus Reactor 2
Core Details
F1 F1 N2 F1 F1 F1 F1 N2 F1 F1 F1 F1 N2 N5 F1 F1 F1 F1 N4 F3 F3 F1 F1 N2 F1 F1 F6 F6 N9 N8 F7 F7 F6 F6 N9 N8 F7 F7 F1 F1 N2 N5 F1 F1 F1 F1 N4 F3 F3
6 days
Cable laying:
Cable laying was started parallel after the completion of Current transformer and Single feeder Disconnector and is progress.
Bay
Bay 1 - Line 1 Bay 2 - Line 2 Bay 3 - GT 1 Bay 4 Bus Reactor 1 Bay 5 - Bus Coupler Bay 6 ST 1 Bay 7 ST 2 Bay 8 GT 2 Bay 9 Bus Reactor 2
Cables Laid
27 Cables are laid and Glanded 27 Cables are laid and Glanded 30 Cables are laid and Glanded 27 Cables are laid and Glanded 42 Cables are laid and Glanded 30 Cables are laid and Glanded 30 Cables are laid and Glanded 30 Cables are laid and Glanded 27 Cables are laid and Glanded
64 Cables
64 Cables
6 days
Coupling:
Bus Coupling is done as a parallel activity with the erection of Double bus bar disconnetor erection for Bay 1 and bay 2. Work Description Time taken to complete
Erection of Double bus bar disconnector and coupling of Bay 1 and Bay 2
6 days
4 days
3 days
Line VT Erection:
Line VTs are erected for Bay 1 Line 1. The Angle which supports the line VT is not found at site. So we constructed Scaffolding arrangement to provide extra support to Line EMVT and it takes half a day time to complete. Work Description Time taken to complete
2 days.
Back Charging was planned on January, 2014 All works should be completed including LV Commissioning on December 31, 2013. HV Test should start from January 1, 2014. Works are completed and has to be completed for Back Charging of 400kV GIS.
LCC Erection Bay 1 Comp Bay 2 Comp Bay 3 Comp Bay 4 Comp Bay 5 Comp Bay 6 Comp Bay 7 Comp Bay 8 Comp Bay 9 Comp
CB Erection for Bay 1 to Bay 9 Bay 1 Comp Bay 2 Comp Bay 3 Comp Bay 4 Comp Bay 5 Comp Bay 6 Comp Bay 7 Comp Bay 8 Comp Bay 9 Comp
CT erection for Bay 1 to Bay 9 Bay 1 Comp Bay 2 Comp Bay 3 Comp Bay 4 Comp Bay 5 Comp Bay 6 Comp Bay 7 Comp Bay 8 Comp Bay 9 Comp
Single feeder disconnector with high speed and low speed earth switch Bay 1 Comp Bay 2 Comp Bay 3 Comp Bay 4 Comp Bay 5 NA Bay 6 Comp Bay 7 Comp Bay 8 Comp Bay 9 Comp
Double bus bar disconnector Common Point Bay 1 Comp Bay 2 Comp Bay 3 Not Comp Bay 4 Not Comp Bay 5 Not Comp Bay 6 Not Comp Bay 7 Not Comp Bay 8 Not Comp Bay 9 Not Comp
Coupling Bay 1 Comp Bay 2 Comp Bay 3 Not Comp Bay 4 Not Comp Bay 5 Not Comp Bay 6 Not Comp Bay 7 Not Comp Bay 8 Not Comp Bay 9 Not Comp
Bay VT Bay 1 Comp Bay 2 Not Comp Bay 3 Not Comp Bay 4 NA Bay 5 NA Bay 6 Not Comp Bay 7 Not Comp Bay 8 Not Comp Bay 9 NA
GIB Marking and Core cutting Bay 1 NA Bay 2 In Progress Bay 3 In Progress Bay 4 NA Bay 5 ---------Bay 6 In Progress Bay 7 NA Bay 8 NA Bay 9 NA
GIB Bus duct and Bushing Erection Bay 1 NA Bay 2 Not Comp Bay 3 Not Comp Bay 4 NA Bay 5 ---------Bay 6 Not Comp Bay 7 NA Bay 8 NA Bay 9 NA
Single Feeder Disconnector with low speed earth switch Bay 1 NA Bay 2 NA Bay 3 NA Bay 4 NA Bay 5 Not Comp Bay 6 NA Bay 7 NA Bay 8 NA Bay 9 NA
Cabling Cable laying: Bay 1 In progress Bay 2 In progress Bay 3 In progress Bay 4 In progress Bay 5 In progress Bay 6 In progress Bay 7 In progress Bay 8 In progress Bay 9 In progress
Cable termination Bay 1 Not Comp Bay 2 Not Comp Bay 3 Not Comp Bay 4 Not Comp Bay 5 Not Comp Bay 6 Not Comp Bay 7 Not Comp Bay 8 Not Comp Bay 9 Not Comp
Earthing Bay 1 In Progress Bay 2 In Progress Bay 3 Not Comp Bay 4 Not Comp Bay 5 Not Comp Bay 6 Not Comp Bay 7 Not Comp Bay 8 Not Comp Bay 9 Not Comp
Manpower Requirement
3 2 3 4 2 2 2
Designation
Fitter Electrician, Helper Electrician Fitter Fitter, Helper Fitter Electrician, helper
Totally 18 Manpower are needed. (Excluding supervisor) Now we have 9 nos. of manpower from RB Elect and Mech works. Supervisor - 1 Fitter 5 Electrician 2 Helper 1 Still we need 10 more manpower at site. Electrician 3 Fitter 5 Helper 2
Work has been carrying over for 65 days from September 4, 2013 (Including delays) 65 Accident free days, Zero Man hour lost. No near miss accident.