Name of Work :- C.R. to N.R. Building at Surendranagar (R & B Division Office) (Prov.

Alluminium Partition in A/C Branch Part-I)

Name of Work :- C.R. to N.R. Building at Surendranagar (R & B Division Office) (Prov. Alluminium Partition in A/C Branch Part-II)

Name of Work :- C.R. to N.R. Building at Surendranagar (R & B Division Office) (Prov. Alluminium Partition in Executive Engineer Chamber)

Name of Work :- C.R. to N.R. Building at Surendranagar (R & B Division Office) (Prov. Alluminium Partition in Budget & Computer Room Part-I)

Name of Work :- C.R. to N.R. Building at Surendranagar (R & B Division Office) (Prov. Alluminium Partition in Budget & Computer Room Part-II)

Name of Work :- C.R. to N.R. Building at Surendranagar (R & B Division Office) (Providing PVC Flooring & False Ceiling)

Name of Work :- C.R. to N.R. Building at Surendranagar (R & B Division Office) (Providing Toilet Block in Ex. Engr. Chamber)

Name of Work :- C.R. to Resi. Building 60 Qtr. at Surendranagar

Name of Work :- C.R. to Resi. Building of Judicial Quarter at Surendranagar

3 C.R. to N.R. Building at Surendranagar (R & B Division Office) (Prov. Alluminium Partition in A/C Name of Work :Branch Part-I)

SCHEDULE - B
Item Quantities No. Estimated but may be more or less [1] 1 [2] 35.50 Sqmt. Providing and [3] fixing powder coated [4] 2794.16 [5] Rs. Two Thousand Seven Hundred Ninty Four and Paise Sixteen Only. [6] Sqmt. [7] 99192.68 Item of works In Figures Estimated rates In Words Unit Total Amount according to estimated of quantities

alluminium Partition Partly panneled and Partly Glazed and Partly fixed for doors with frame size 101.60 x 44.45mm with Wt. 1.608 Kg / Rmt. with 5mm thick plain glass smoke gray and 12mm thick both side pre laminated Nova sheet panel including approved rubber binding clips etc. complete

Total

99192.68

I / We am/are willing to carry out the work at ......................................................... % above / below (Should be written in figures and words) of the estimated rates mentioned above. Amount of my/our tender works out as under. Estimated amount Put to tender Rs. Add.. % above Rs. Total Rs. In words (Please strike out whichever is not applicable) Estimated amount Put to tender Rs.. Rs.. Deduct.... % below Net Rs.. In words.

NOTES :[1] All work shall be carried out as per Public works Deptt. Hand Book and other specification or as directed [2] All the columns in schedule should be filled in INK and the total of entires in the last column should be strike by the contractor under his signature. [3] Rates quoted include clearance of site (Prior commence of work and as its colse respects in all hold good for work under all conditions, site moisture weather etc. [4] The contractor shall exhibit a Board as per Govt. No.806/3277/1657 Dt. 26-04-78 (guj) RGR-No.TNC-1090/24-C Dated 29-11-90 and GR. Dt. 18-11-91. involved at sitewith in any payment as directed by Engineer - in - Charge. [5] [6] The contractor shall state even "NIL" percent of no reduction as offered In RCC Items where there is change of grade mix or change as per actual mix design the difference of cement consumption shall be added / deducted from rate of original item due to rate of star rate mentioned in the tender.

Signature of Contractor

Deputy Executive Engineer R & B Sub Division No. 1 Surendranagar

File : 198740225.xls.ms_office

4 C.R. to N.R. Building at Surendranagar (R & B Division Office) (Prov. Alluminium Partition in A/C Name of Work :Branch Part-II)

SCHEDULE - B
Item Quantities No. Estimated but may be more or less [1] 1 [2] 22.50 Sqmt. Providing and [3] fixing powder coated [4] 2794.16 [5] Rs. Two Thousand Seven Hundred Ninty Four and Paise Sixteen Only. [6] Sqmt. [7] 62868.60 Item of works In Figures Estimated rates In Words Unit Total Amount according to estimated of quantities

alluminium Partition Partly panneled and Partly Glazed and Partly fixed for doors with frame size 101.60 x 44.45mm with Wt. 1.608 Kg / Rmt. with 5mm thick plain glass smoke gray and 12mm thick both side pre laminated Nova sheet panel including approved rubber binding clips etc. complete

9.25 Sqmt.

Providing

and

fixing

Powder

coated

3951.12

Rs. Three Thousand Nine Hundred Fifty One and Paise Twelve Only.

Sqmt.

36547.86

Alluminium Partly Panelled and Partly Glazed and Partly fixed single shutters for doors with shutter frame size 101.60 x 44.45mm with Wt. 1.608 Kg / Rmt. and Bottom & Middle rail 44.45 x 114 mm with Wt. of 1.836 Kg / Rmt. with 5mm thick plain glass and 12mm thick both side laminated Nova Teak Sheet panel including approved rubber binding clips locks

fixtures and fastening etc. complete Total 99416.46

I / We am/are willing to carry out the work at ......................................................... % above / below (Should be written in figures and words) of the estimated rates mentioned above. Amount of my/our tender works out as under. Estimated amount Put to tender Add.. % above Total Rs. Rs. Rs. Estimated amount Put to tender Deduct.... % below Net Rs.. Rs.. Rs..

In words (Please strike out whichever is not applicable) Signature of Contractor

In words.

Deputy Executive Engineer R & B Sub Division No. 1 Surendranagar

File : 198740225.xls.ms_office

5 NOTES :[1] [2] [3] [4] [5] [6] All work shall be carried out as per Public works Deptt. Hand Book and other specification or as directed All the columns in schedule should be filled in INK and the total of entires in the last column should be strike by the contractor under his signature. Rates quoted include clearance of site (Prior commence of work and as its colse respects in all hold good for work under all conditions, site moisture weather etc. The contractor shall exhibit a Board as per Govt. No.806/3277/1657 Dt. 26-04-78 (guj) RGR-No.TNC-1090/24-C Dated 29-11-90 and GR. Dt. 18-11-91. involved at sitewith in any payment as directed by Engineer - in - Charge. The contractor shall state even "NIL" percent of no reduction as offered In RCC Items where there is change of grade mix or change as per actual mix design the difference of cement consumption shall be added / deducted from rate of original item due to rate of star rate mentioned in the tender.

Signature of Contractor

Deputy Executive Engineer R & B Sub Division No. 1 Surendranagar

File : 198740225.xls.ms_office

6 C.R. to N.R. Building at Surendranagar (R & B Division Office) (Prov. Alluminium Partition in Name of Work :Executive Engineer Chamber)

SCHEDULE - B
Item Quantities No. Estimated but may be more or less [1] 1 [2] 30.00 Sqmt. Providing and [3] fixing powder coated [4] 2794.16 [5] Rs. Two Thousand Seven Hundred Ninty Four and Paise Sixteen Only. [6] Sqmt. [7] 83824.80 Item of works In Figures Estimated rates In Words Unit Total Amount according to estimated of quantities

alluminium Partition Partly panneled and Partly Glazed and Partly fixed for doors with frame size 101.60 x 44.45mm with Wt. 1.608 Kg / Rmt. with 5mm thick plain glass smoke gray and 12mm thick both side pre laminated Nova sheet panel including approved rubber binding clips etc. complete

4.00 Sqmt.

Providing

and

fixing

powder

coated

3636.00

Rs. Three Thousand Six Hundred Thirty Six Only.

Sqmt.

14544.00

alluminium Partly panneled and Partly Glazed and Partly fixed double shutters for doors with frame size 101.60 x 44.45mm with Wt. 1.608 Kg / Rmt. and shutters size 44.45 x 47.62mm with Wt. of 1.505 Kg / Rmt. with 5mm thick plain glass / Smoke Grey and 12mm thick both side laminated Nova Teak sheet panel including approved rubber binding clips locks fixtures and fastening etc. complete

Total

98368.80

I / We am/are willing to carry out the work at ......................................................... % above / below (Should be written in figures and words) of the estimated rates mentioned above. Amount of my/our tender works out as under. Estimated amount Put to tender Add.. % above Total Rs. Rs. Rs. Estimated amount Put to tender Deduct.... % below Net Rs.. Rs.. Rs..

In words (Please strike out whichever is not applicable) Signature of Contractor

In words.

Deputy Executive Engineer R & B Sub Division No. 1 Surendranagar

File : 198740225.xls.ms_office

7 NOTES :[1] [2] [3] [4] [5] [6] All work shall be carried out as per Public works Deptt. Hand Book and other specification or as directed All the columns in schedule should be filled in INK and the total of entires in the last column should be strike by the contractor under his signature. Rates quoted include clearance of site (Prior commence of work and as its colse respects in all hold good for work under all conditions, site moisture weather etc. The contractor shall exhibit a Board as per Govt. No.806/3277/1657 Dt. 26-04-78 (guj) RGR-No.TNC-1090/24-C Dated 29-11-90 and GR. Dt. 18-11-91. involved at sitewith in any payment as directed by Engineer - in - Charge. The contractor shall state even "NIL" percent of no reduction as offered In RCC Items where there is change of grade mix or change as per actual mix design the difference of cement consumption shall be added / deducted from rate of original item due to rate of star rate mentioned in the tender.

Signature of Contractor

Deputy Executive Engineer R & B Sub Division No. 1 Surendranagar

File : 198740225.xls.ms_office

8 C.R. to N.R. Building at Surendranagar (R & B Division Office) (Prov. Alluminium Partition in Name of Work :Budget & Computer Room Part-I)

SCHEDULE - B
Item Quantities No. Estimated but may be more or less [1] 1 [2] 35.50 Sqmt. Providing and [3] fixing powder coated [4] 2794.16 [5] Rs. Two Thousand Seven Hundred Ninty Four and Paise Sixteen Only. [6] Sqmt. [7] 99192.68 Item of works In Figures Estimated rates In Words Unit Total Amount according to estimated of quantities

alluminium Partition Partly panneled and Partly Glazed and Partly fixed for doors with frame size 101.60 x 44.45mm with Wt. 1.608 Kg / Rmt. with 5mm thick plain glass smoke gray and 12mm thick both side pre laminated Nova sheet panel including approved rubber binding clips etc. complete

Total

99192.68

I / We am/are willing to carry out the work at ......................................................... % above / below (Should be written in figures and words) of the estimated rates mentioned above. Amount of my/our tender works out as under. Estimated amount Put to tender Add.. % above Total Rs. Rs. Rs. Estimated amount Put to tender Deduct.... % below Net Rs.. Rs.. Rs..

In words (Please strike out whichever is not applicable) NOTES :[1] [2] [3] [4] [5] [6]

In words.

All work shall be carried out as per Public works Deptt. Hand Book and other specification or as directed All the columns in schedule should be filled in INK and the total of entires in the last column should be strike by the contractor under his signature. Rates quoted include clearance of site (Prior commence of work and as its colse respects in all hold good for work under all conditions, site moisture weather etc. The contractor shall exhibit a Board as per Govt. No.806/3277/1657 Dt. 26-04-78 (guj) RGR-No.TNC-1090/24-C Dated 29-11-90 and GR. Dt. 18-11-91. involved at sitewith in any payment as directed by Engineer - in - Charge. The contractor shall state even "NIL" percent of no reduction as offered In RCC Items where there is change of grade mix or change as per actual mix design the difference of cement consumption shall be added / deducted from rate of original item due to rate of star rate mentioned in the tender.

Signature of Contractor

Deputy Executive Engineer R & B Sub Division No. 1 Surendranagar

File : 198740225.xls.ms_office

9 C.R. to N.R. Building at Surendranagar (R & B Division Office) (Prov. Alluminium Partition in Name of Work :Budget & Computer Room Part-II)

SCHEDULE - B
Item Quantities No. Estimated but may be more or less [1] 1 [2] 17.00 Sqmt. Providing and [3] fixing powder coated [4] 2794.16 [5] Rs. Two Thousand Seven Hundred Ninty Four and Paise Sixteen Only. [6] Sqmt. [7] 47500.72 Item of works In Figures Estimated rates In Words Unit Total Amount according to estimated of quantities

alluminium Partition Partly panneled and Partly Glazed and Partly fixed for doors with frame size 101.60 x 44.45mm with Wt. 1.608 Kg / Rmt. with 5mm thick plain glass smoke gray and 12mm thick both side pre laminated Nova sheet panel including approved rubber binding clips etc. complete

13.00 Sqmt.

Providing

and

fixing

Powder

coated

3951.12

Rs. Three Thousand Nine Hundred Fifty One and Paise Twelve Only.

Sqmt.

51364.56

Alluminium Partly Panelled and Partly Glazed and Partly fixed single shutters for doors with shutter frame size 101.60 x 44.45mm with Wt. 1.608 Kg / Rmt. and Bottom & Middle rail 44.45 x 114 mm with Wt. of 1.836 Kg / Rmt. with 5mm thick plain glass and 12mm thick both side laminated Nova Teak Sheet panel including approved rubber binding clips locks

fixtures and fastening etc. complete Total 98865.28

I / We am/are willing to carry out the work at ......................................................... % above / below (Should be written in figures and words) of the estimated rates mentioned above. Amount of my/our tender works out as under. Estimated amount Put to tender Add.. % above Total Rs. Rs. Rs. Estimated amount Put to tender Deduct.... % below Net Rs.. Rs.. Rs..

In words (Please strike out whichever is not applicable) Signature of Contractor

In words.

Deputy Executive Engineer R & B Sub Division No. 1 Surendranagar

File : 198740225.xls.ms_office

10 NOTES :[1] [2] [3] [4] [5] [6] All work shall be carried out as per Public works Deptt. Hand Book and other specification or as directed All the columns in schedule should be filled in INK and the total of entires in the last column should be strike by the contractor under his signature. Rates quoted include clearance of site (Prior commence of work and as its colse respects in all hold good for work under all conditions, site moisture weather etc. The contractor shall exhibit a Board as per Govt. No.806/3277/1657 Dt. 26-04-78 (guj) RGR-No.TNC-1090/24-C Dated 29-11-90 and GR. Dt. 18-11-91. involved at sitewith in any payment as directed by Engineer - in - Charge. The contractor shall state even "NIL" percent of no reduction as offered In RCC Items where there is change of grade mix or change as per actual mix design the difference of cement consumption shall be added / deducted from rate of original item due to rate of star rate mentioned in the tender.

Signature of Contractor

Deputy Executive Engineer R & B Sub Division No. 1 Surendranagar

File : 198740225.xls.ms_office

11 C.R. to N.R. Building at Surendranagar (R & B Division Office) (Providing PVC Flooring & False Name of Work :Ceiling)

SCHEDULE - B
Item Quantities No. Estimated but may be more or less [1] 1 [2] 54.00 Sqmt. [3] Providing and fixing 1.5mm thick P.V.C. Flooring type homogenous P.V.C. unroll from carpet including labour, materials of adhesive solution etc. complete 2 54.00 Sqmt. Providing and fixing PVC False ceilling consisting of 600mm x 600mm, 3mm thick PVC Sheet used as panel insert in a frame work made using anodized alluminium "T" section of sizes 25mm x 25mm, 19 gauge or 1mm thick in squre pattern of Grid sizes of 600 x 600mm. The alluminium framework is supported from the ceilling with the help of G.I. hook and G.I. wire 6mm M.S. reds of required sizes to maintain proper level etc. The alluminium framework is 1007.98 Rs. One Thousand Seven and Paise Ninty Eight Only. Sqmt. 54430.92 [4] 505.00 [5] Rs. Five Hundred Five Only. [6] Sqmt. [7] 27270.00 Item of works In Figures Estimated rates In Words Unit Total Amount according to estimated of quantities

supported on side wall with the use of alluminium "L" section of size 25 x 25mm angles etc. complete as per direction of Engineer-in-Charge. (c) PVC Plain Colour False Ceilling with Fulsh type with allu. Frame Total 81700.92

I / We am/are willing to carry out the work at ......................................................... % above / below (Should be written in figures and words) of the estimated rates mentioned above. Amount of my/our tender works out as under. Estimated amount Put to tender Add.. % above Total Rs. Rs. Rs. Estimated amount Put to tender Deduct.... % below Net Rs.. Rs.. Rs..

In words (Please strike out whichever is not applicable) Signature of Contractor

In words.

Deputy Executive Engineer R & B Sub Division No. 1 Surendranagar

File : 198740225.xls.ms_office

12 NOTES :[1] [2] [3] [4] [5] [6] All work shall be carried out as per Public works Deptt. Hand Book and other specification or as directed All the columns in schedule should be filled in INK and the total of entires in the last column should be strike by the contractor under his signature. Rates quoted include clearance of site (Prior commence of work and as its colse respects in all hold good for work under all conditions, site moisture weather etc. The contractor shall exhibit a Board as per Govt. No.806/3277/1657 Dt. 26-04-78 (guj) RGR-No.TNC-1090/24-C Dated 29-11-90 and GR. Dt. 18-11-91. involved at sitewith in any payment as directed by Engineer - in - Charge. The contractor shall state even "NIL" percent of no reduction as offered In RCC Items where there is change of grade mix or change as per actual mix design the difference of cement consumption shall be added / deducted from rate of original item due to rate of star rate mentioned in the tender.

Signature of Contractor

Deputy Executive Engineer R & B Sub Division No. 1 Surendranagar

File : 198740225.xls.ms_office

13 C.R. to N.R. Building at Surendranagar (R & B Division Office) (Providing Toilet Block in Ex. Engr. Name of Work :Chamber)

SCHEDULE - B
Item Quantities No. Estimated but may be more or less [1] 1 [2] [3] Dismentling doors, windows, ventilators etc. (wood or steel) shutters including chowkhats architraves, holdfasts and other attachment etc. complete and stacking them 9.00 Nos. 4.00 Nos. within all lead and lift. (i) Not exceeding 3 Sq.M. in area. 43.43 Rs. Forty Three and Paise Forty Three Only Rs. Fifty Eight and Paise Fifty Eight Only. Nos. 390.87 [4] [5] [6] [7] Item of works In Figures Estimated rates In Words Unit Total Amount according to estimated of quantities

(ii) Exceeding 3 Sq.M. in area.

58.58

Nos.

234.32

2.00 Cum.

Demolition of Brick work and stone masonry including stacking of serviceable materilas and disposal of unserviceable materials with all lead and lift. (ii) In Cement Mortar.

127.26

Rs. One Hundred Twenty Seven and Paise Twenty Six Only.

Cum.

254.52

14.00 Sqmt.

Dismentaling tiled or stone floors laid in mortar including stacking of serviceable materilas and disposal of unserviceable materials with all lead and lift.

11.16

Rs. Eleven and Paise Sixteen Only.

Sqmt.

156.24

3.00 Cum.

Brickwork using common

burnt clay

1553.38

building bricks having crushing strength not less than 35 kg./Sq.Cm. in Super Structure in Cement Mortar 1:6 (1- Cement : 6 -fine sand) (B) Conventional

Rs. One Thousand Five Hundred Fifty Three and Paise Thirty Eight Only

Cum.

4660.14

14.00 Sqmt.

Providing and laying Ceramic Flooring tiles 8mm thick in flooring treads of stes and landings laid on a bed of 12mm thick Cement Mortar 1:3 (1-Cement : 3-Coarse Sand) Finished with flush Pointing in white cement.

590.85

Rs. Five Hundred Ninty and Paise Eighty Five Only

Sqmt.

8271.90

File : 198740225.xls.ms_office

14 [1] 6 [2] 16.00 Sqmt. [3] Providing and laying white /colour glazed tiles 6mm thick in skrting risers of steps and dedo on 10mm thick cement plaster 1:3 (1cement : 3-coarse sand) and jointed with white cement slurry 7 27.00 Sqmt. Providing 15mm thick cement plaster in single coat on brick/concrete walls for interior plastering upto floor two level and finished even and smooth in (ii) Cement mortar 1:4 (1-cement :4-sand) with floating coat of neat cement slurry. 8 1.00 Nos Providing and fixing wash down water closet (European type, W.C. Pan) with integral P or S trap including jointing the trap with soil pipe in Cement Mortar 1:1 (1Cement : 1-fine sand) with plastic seat cover & 10 Lit. PVC flusing Tank (A) vitreous China Pattern : (i) in white colour 9 1.00 Nos Providing and fixing urinals of approved quality including connection the urinal with waste pipe tap etc. including 32mm dia CP brass waste pipe and water spreader etc complete. 10 1.00 Nos Providing and fixing wash basin with single hole piller tap with C.I. or M.S. brackets painted while incl. cutting holes incl. M.I. Fisher union, pillar tap, stop cock, PVC connection and PVC wash pipe etc. complete.(ii) Flat back wash basin 550 x 400mm dia (i) In white colour. 11 1.00 Nos. Providing and fixing 600mm x 450mm bevelled edge mirrror of superior glass mounted on 6mm thick A.C. sheet or plywood sheet and fixing to wooden pluge with C.P. brass screws and washers. 12 1.00 Nos. Providing and fixing C.P. brass towel rail comlete with C.P. brass brackets fixed to wooden plugs with C.P. brass scews. (B) 600mm x 20mm size. 328.25 Rs. Three Hundred Twenty Eight and Paise Twenty Five Only. Nos. 328.25 489.85 Rs. Four Hundred Eighty Nine and Paise Eighty Five Only. Nos. 489.85 1288.76 Rs. One Thousand Two Hundred Eighty Eight and Paise Seventy Six Only. Nos 1288.76 949.40 Rs. Nine Hundred Forty Nine and Paise Forty Only. Nos 949.40 2157.36 Rs. Two Thousand One Hundred Fifty Seven and Paise Thirty Six Only Nos 2157.36 86.86 Rs. Eighty Six and Paise Eighty Six Only. Sqmt. 2345.22 [4] 601.96 [5] Rs. Six Hundred One and Paise Ninty Six Only. [6] Sqmt. [7] 9631.36

File : 198740225.xls.ms_office

15 [1] 13 [2] 3.00 Nos. [3] Providing and fixing cast iron (Spun) Nahni trap of the following nominal diameter of self cleaning design with C.I. screaed down or higned grating including cost of cutting and making good the walls and floor 100mm inlet and 50mm outlet. 14 1000.00 Providing and fixing P.V.C. water storage Ltr tank ISI Mark with necessary G.I. Fitting over flow pipe, boll valve, clamp , nipple etc.including placing on terrace as directed 15 15.00 Rmt. Providing and fixing to wall, ceiling and floor galvanised Mild steel tubes (Medium grade) of the following nominal bore, tube fitting and clamps including making good the wall ceiling and floor. (A) 15mm 16 15.00 Rmt. Providing and fixing to wall, ceiling and floor galvanised Mild steel tubes (Medium grade) of the following nominal bore, tube fitting and clamps including making good the wall ceiling and floor. (C) 25mm 17 1.00 Nos. Providing and fixing Gun metal check or non-return fullway wheel valve. (C) 25mm dia. 18 1.00 Nos. Providing and fixing Gun metal check or non-return fullway wheel valve. (A) 15mm dia. 19 10.00 Rmt Providing and fixing to level for slop concealed type PVC pipe fitting of the 110mm dia. low density of 10.00 Kg/cm2 working pressure. Polythene pipe complete with special flange compression type fitting bend, reducers with necessary heighting, guarding, barricating clips, etc.complete.
File : 198740225.xls.ms_office

[4] 251.49

[5] Rs. Two Hundred Fifty One and Paise Forty Nine Only.

[6] Nos.

[7] 754.47

4.54

Rs. Four and Paise Fifty Four Only.

Ltr

4540.00

112.11

Rs. One Hundred Twelve and Paise Eleven Only.

Rmt.

1681.65

192.91

Rs. One Hundred Ninty Two and Paise Ninty One Only.

Rmt.

2893.65

338.35

Rs. Three Hundred Thirty Eight and Paise Thirty Five Only.

Nos.

338.35

204.02

Rs. Two Hundred Four and Paise Two Only.

Nos.

204.02

252.50

Rs. Two Hundred Fifty Two and Paise Fifty Only.

Rmt

2525.00

16 [1] 20 [2] 4.00 No [3] Construction of brick masonry chamber for underground C.I inspection chamber and bends with brick having crushing strength not less than 35 Kg/Cm2 in C.M. 1:5.and R.C.C. cover with frame 455 mm x 610 mm internal dimensions, having 5 MT load carrying capacity and R.C.C top slab with 1:2:4 mix( 1- cement : 2 -coarse sand:4 graded stone aggregate 20 mm size ) foundation concrete 1:5:10 inside plaster 15 mm thick with cement mortar 1:3 finished smooth with a floating coat of neat cement on walls and bed concrete etc. Complete inside dimensions 455 mm x 610 mm and 450 mm deep for single pipe line. 21 45.00 Rmt. Providing and laying (to level or slopes) and jointing with stiff mixture of Cement Mortar in proportion 1:1, Salt glazed stoneware pipes including testing of pipes and joints complete. 150mm dia. 22 2.00 Nos. Providing and fixing screw down bib taps of following size. (A) Brass screw down bib tap polished bright. (i) 15mm dia. 23 173.00 Sqmt. Distempeing (Two coats) with oil bound distemper of approved brand and 33.83 Rs. Thirty Three and Paise Eighty Three Only Sqmt. 5852.59 106.05 Rs. One Hundred Six and Paise Five Only. Nos. 212.10 156.55 Rs. One Hundred Fifty Six and Paise Fifty Five Only. Rmt. 7044.75 [4] 1473.59 [5] Rs. One Thousand Four Hundred Seventy Three and Paise Fifty Nine Only [6] No [7] 5894.36

manufacture and of required shade on wall surfaces to give an even shade, over and including a priming coat with distemper primer of approved brand and manufacture after thoroughly brushing the surface free from mortar dropping and other foreign matter and also including preparing the surface even and sand papered smooth.

File : 198740225.xls.ms_office

17 [1] 24 [2] 12.60 Sqmt. Providing and [3] fixing powder coated [4] 2794.16 [5] Rs. Two Thousand Seven Hundred Ninty Four and Paise Forteen Only. [6] Sqmt. [7] 35206.42

alluminium Partition Partly panneled and Partly Glazed and Partly fixed for doors with frame size 101.60 x 44.45mm with Wt. 1.608 Kg / Rmt. with 5mm thick plain glass smoke gray and 12mm thick both side pre laminated Nova sheet panel including approved rubber binding clips etc. complete

Total

98305.55

I / We am/are willing to carry out the work at ......................................................... % above / below (Should be written in figures and words) of the estimated rates mentioned above. Amount of my/our tender works out as under. Estimated amount Put to tender Add.. % above Total Rs. Rs. Rs. Estimated amount Put to tender Deduct.... % below Net Rs.. Rs.. Rs..

In words (Please strike out whichever is not applicable) NOTES :[1] [2] [3] [4] [5] [6]

In words.

All work shall be carried out as per Public works Deptt. Hand Book and other specification or as directed All the columns in schedule should be filled in INK and the total of entires in the last column should be strike by the contractor under his signature. Rates quoted include clearance of site (Prior commence of work and as its colse respects in all hold good for work under all conditions, site moisture weather etc. The contractor shall exhibit a Board as per Govt. No.806/3277/1657 Dt. 26-04-78 (guj) RGR-No.TNC-1090/24-C Dated 29-11-90 and GR. Dt. 18-11-91. involved at sitewith in any payment as directed by Engineer - in - Charge. The contractor shall state even "NIL" percent of no reduction as offered In RCC Items where there is change of grade mix or change as per actual mix design the difference of cement consumption shall be added / deducted from rate of original item due to rate of star rate mentioned in the tender.

Signature of Contractor

Deputy Executive Engineer R & B Sub Division No. 1 Surendranagar

Name of Work :- C.R. to N.R. Building at Surendranagar (R & B Division Office) (Prov. Polished Kotah Stone Flooring)

File : 198740225.xls.ms_office

18

SCHEDULE - B
Item Quantities No. Estimated but may be more or less [1] 1 [2] 218.00 Sqmt. [3] Providing and laying polished Kota stone slab flooring over 20mm (Average) thick base of cement mortar 1:6 (1-cement : 6coarse sand) laid over and jointed with grey cement slurry including rubbing and [4] 456.52 [5] #NAME? [6] Sqmt. [7] 99521.36 Item of works In Figures Estimated rates In Words Unit Total Amount according to estimated of quantities

polishing etc. complete. Total 99521.36

I / We am/are willing to carry out the work at ......................................................... % above / below (Should be written in figures and words) of the estimated rates mentioned above. Amount of my/our tender works out as under. Estimated amount Put to tender Rs. Add.. % above Rs. Total Rs. In words (Please strike out whichever is not applicable) Estimated amount Put to tender Rs.. Rs.. Deduct.... % below Net Rs.. In words.

NOTES :[1] All work shall be carried out as per Public works Deptt. Hand Book and other specification or as directed [2] All the columns in schedule should be filled in INK and the total of entires in the last column should be strike by the contractor under his signature. [3] Rates quoted include clearance of site (Prior commence of work and as its colse respects in all hold good for work under all conditions, site moisture weather etc. [4] The contractor shall exhibit a Board as per Govt. No.806/3277/1657 Dt. 26-04-78 (guj) RGR-No.TNC-1090/24-C Dated 29-11-90 and GR. Dt. 18-11-91. involved at sitewith in any payment as directed by Engineer - in - Charge. [5] [6] The contractor shall state even "NIL" percent of no reduction as offered In RCC Items where there is change of grade mix or change as per actual mix design the difference of cement consumption shall be added / deducted from rate of original item due to rate of star rate mentioned in the tender.

Signature of Contractor

Deputy Executive Engineer R & B Sub Division No. 1 Surendranagar

File : 198740225.xls.ms_office

19

File : 198740225.xls.ms_office

20

File : 198740225.xls.ms_office

21

File : 198740225.xls.ms_office

22

File : 198740225.xls.ms_office

23

File : 198740225.xls.ms_office

24

File : 198740225.xls.ms_office

25

File : 198740225.xls.ms_office

26

File : 198740225.xls.ms_office

27

2250

File : 198740225.xls.ms_office

Name of Work :- C.R. to N.R. Building at Surendranagar (R & B Division Office)


(Providing Toilet Block in Ex. Engr. Chamber)

REQUIREMENT OF CEMENT
Item No. [1] 4 [2] Brickwork using common burnt clay building bricks .Cement Mortar 1:6 (1- Cement : 6 -fine 5 6 7 20 sand) (B) Conventional Providing and laying Ceramic Flooring tiles 8mm thick in flooring .. Providing and laying white /colour glazed tiles 6mm thick in skrting risers of steps and dedo Providing 15mm thick cement plaster in single coat on brick/concrete walls . Construction of brick masonry chamber for underground C.I inspection chamber and bends 21 with brick . Providing and laying (to level or slopes) and jointing with stiff mixture of Cement Mortar in proportion 1:1, . Total i.e. Say 1137.00 1.14 1.15 Kg. M.T. M.T. [3] 3.00 Cum. 14.00 Sqmt. 16.00 Sqmt. 27.00 Sqmt. 4.00 Nos. 45.00 Rmt. 3.23 Rmt. 145.35 71.12 Nos. 284.48 8.47 Sqmt. 228.69 9.52 Sqmt. 152.32 10.44 Sqmt. 146.16 Description of Item Qty Rate of Consumption in Kg. [4] 60.00 [5] Cum. [6] 180.00 Per Required Cement

Deputy Executive Engineer R & B Sub Division No. 1 Surendranagar

Name of Work :- C.R. to N.R. Building at Surendranagar (R & B Division Office)


(Prov. Polished Kotah Stone Flooring)

REQUIREMENT OF CEMENT
Item No. [1] 4 [2] Providing and laying polished Kota stone slab flooring over 20mm (Average) thick base of cement mortar 1:6 Total i.e. Say 2616.00 2.62 2.65 Kg. M.T. M.T. [3] 218.00 Sqmt. Description of Item Qty Rate of Consumption in Kg. [4] 12.00 [5] Sqmt. [6] 2616.00 Per Required Cement

Deputy Executive Engineer R & B Sub Division No. 1 Surendranagar

30

Name of Work :- C.R. to N.R. Building at Surendranagar (R & B Division Office) (Prov. Alluminium Partition in A/C Branch Part-I) Index to Specification Sr. Item of Work Volume Page Specification No. No. No. Item No.No. [1] [2] [3] [4] [5] I As per Separate Sheet Attached 1 Providing and fixing powder coated alluminium Partition Partly panneled and Partly Glazed and Partly fixed for doors with frame size 101.60 x 44.45mm with Wt. 1.608 Kg / Rmt. with 5mm thick plain glass smoke gray and 12mm thick both side pre laminated Nova sheet panel including approved rubber binding clips etc. complete

Remarks. [6]

Signature of Contractor

Deputy Executive Engineer R & B Sub Division No. 1 Surendranagar

31

Name of Work :- C.R. to N.R. Building at Surendranagar (R & B Division Office) (Prov. Alluminium Partition in A/C Branch Part-II) Index to Specification Sr. Item of Work Volume Page Specification No. No. No. Item No.No. [1] [2] [3] [4] [5] I As per Separate Sheet Attached 1 Providing and fixing powder coated alluminium Partition Partly panneled and Partly Glazed and Partly fixed for doors with frame size 101.60 x 44.45mm with Wt. 1.608 Kg / Rmt. with 5mm thick plain glass smoke gray and 12mm thick both side pre laminated Nova sheet panel including approved rubber binding clips etc. complete 2 Providing and fixing Powder coated Alluminium Partly Panelled and Partly Glazed and Partly fixed single shutters for doors with shutter frame size 101.60 x 44.45mm with Wt. 1.608 Kg / Rmt. and Bottom & Middle rail 44.45 x 114 mm with Wt. of 1.836 Kg / Rmt. with 5mm thick plain glass and 12mm thick both side laminated Nova Teak Sheet panel including approved rubber binding clips locks fixtures and fastening etc. complete I As per Separate Sheet Attached

Remarks. [6]

Signature of Contractor

Deputy Executive Engineer R & B Sub Division No. 1 Surendranagar

32

Name of Work :- C.R. to N.R. Building at Surendranagar (R & B Division Office) (Prov. Alluminium Partition in Executive Engineer Chamber) Index to Specification Sr. Item of Work Volume Page Specification No. No. No. Item No.No. [1] [2] [3] [4] [5] I As per Separate Sheet Attached 1 Providing and fixing powder coated alluminium Partition Partly panneled and Partly Glazed and Partly fixed for doors with frame size 101.60 x 44.45mm with Wt. 1.608 Kg / Rmt. with 5mm thick plain glass smoke gray and 12mm thick both side pre laminated Nova sheet panel including approved rubber binding clips etc. complete 2 Providing and fixing powder coated alluminium Partly panneled and Partly Glazed and Partly fixed double shutters for doors with frame size 101.60 x 44.45mm with Wt. 1.608 Kg / Rmt. and shutters size 44.45 x 47.62mm with Wt. of 1.505 Kg / Rmt. with 5mm thick plain glass / Smoke Grey and 12mm thick both side laminated Nova Teak sheet panel including approved rubber binding clips locks fixtures and fastening etc. complete I As per Separate Sheet Attached

Remarks. [6]

Signature of Contractor

Deputy Executive Engineer R & B Sub Division No. 1 Surendranagar

33

Name of Work :- C.R. to N.R. Building at Surendranagar (R & B Division Office) (Prov. Alluminium Partition in Budget & Computer Room Part-I) Index to Specification Sr. Item of Work Volume Page Specification No. No. No. Item No.No. [1] [2] [3] [4] [5] I As per Separate Sheet Attached 1 Providing and fixing powder coated alluminium Partition Partly panneled and Partly Glazed and Partly fixed for doors with frame size 101.60 x 44.45mm with Wt. 1.608 Kg / Rmt. with 5mm thick plain glass smoke gray and 12mm thick both side pre laminated Nova sheet panel including approved rubber binding clips etc. complete

Remarks. [6]

Signature of Contractor

Deputy Executive Engineer R & B Sub Division No. 1 Surendranagar

34

Name of Work :- C.R. to N.R. Building at Surendranagar (R & B Division Office) (Prov. Alluminium Partition in Budget & Computer Room Part-II) Index to Specification Sr. Item of Work Volume Page Specification No. No. No. Item No.No. [1] [2] [3] [4] [5] I As per Separate Sheet Attached 1 Providing and fixing powder coated alluminium Partition Partly panneled and Partly Glazed and Partly fixed for doors with frame size 101.60 x 44.45mm with Wt. 1.608 Kg / Rmt. with 5mm thick plain glass smoke gray and 12mm thick both side pre laminated Nova sheet panel including approved rubber binding clips etc. complete 2 Providing and fixing Powder coated Alluminium Partly Panelled and Partly Glazed and Partly fixed single shutters for doors with shutter frame size 101.60 x 44.45mm with Wt. 1.608 Kg / Rmt. and Bottom & Middle rail 44.45 x 114 mm with Wt. of 1.836 Kg / Rmt. with 5mm thick plain glass and 12mm thick both side laminated Nova Teak Sheet panel including approved rubber binding clips locks fixtures and fastening etc. complete I As per Separate Sheet Attached

Remarks. [6]

Signature of Contractor

Deputy Executive Engineer R & B Sub Division No. 1 Surendranagar

35

Name of Work :- C.R. to N.R. Building at Surendranagar (R & B Division Office) (Providing PVC Flooring & False Ceiling) Index to Specification Sr. Item of Work Volume Page Specification No. No. No. Item No.No. [1] [2] [3] [4] [5] I As per Separate Sheet Attached 1 Providing and fixing 1.5mm thick P.V.C. Flooring type homogenous P.V.C. unroll from carpet including labour, materials of adhesive solution etc. complete 2 Providing and fixing PVC False ceilling consisting of 600mm x 600mm, 3mm thick PVC Sheet used as panel insert in a frame work made using anodized alluminium "T" section of sizes 25mm x 25mm, 19 gauge or 1mm thick in squre pattern of Grid sizes of 600 x 600mm. The alluminium framework is supported from the ceilling with the help of G.I. hook and G.I. wire 6mm M.S. reds of required sizes to maintain proper level etc. The alluminium framework is supported on side wall with the use of alluminium "L" section of size 25 x 25mm angles etc. complete as per direction of Engineer-in-Charge. (c) PVC Plain Colour False Ceilling with Fulsh type with allu. Frame I As per Separate Sheet Attached

Remarks. [6]

Signature of Contractor

Deputy Executive Engineer R & B Sub Division No. 1 Surendranagar

36

Name of Work :- C.R. to N.R. Building at Surendranagar (R & B Division Office) (Providing Toilet Block in Ex. Engr. Chamber) Index to Specification Volume Page Specification No. No. Item No.No. [3] [4] [5]

Sr. Item of Work No. [1] [2] 1 Dismentling doors, windows, ventilators etc. (wood or steel) shutters including chowkhats architraves, holdfasts and other attachment etc. complete and stacking them within all lead and lift. (i) Not exceeding 3 Sq.M. in area. (ii) Exceeding 3 Sq.M. in area. 2 Demolition of Brick work and stone masonry including stacking of serviceable materilas and disposal of unserviceable materials with all lead and lift. (ii) In Cement Mortar. 3 Dismentaling tiled or stone floors laid in mortar including stacking of serviceable materilas and disposal of unserviceable materials with all lead and lift. Brickwork using common burnt clay building bricks having crushing strength not less than 35 kg./Sq.Cm. in Super Structure in Cement Mortar 1:6 (1- Cement : 6 -fine sand) (B) Conventional Providing and laying Ceramic Flooring tiles 8mm thick in flooring treads of stes and landings laid on a bed of 12mm thick Cement Mortar 1:3 (1-Cement : 3-Coarse Sand) Finished with flush Pointing in white cement.

Remarks. [6]

I I I

133 133 130

20.49 (I) 20.49 (II) 20.11 (I)

131

20.23

I I

44 46

6.13 (B) 6.19 (B)

84

14.29

Work shall be carried out in Ceramic Tiles flooring instead of white glazed tiles flooring

37

[1] [2] 6 Providing and laying white /colour glazed tiles 6mm thick in skrting risers of steps and dedo on 10mm thick cement plaster 1:3 (1-cement : 3-coarse sand) and jointed with white cement slurry 7 Providing 15mm thick cement plaster in single coat on brick/concrete walls for interior plastering upto floor two level and finished even and smooth in (ii) Cement mortar 1:4 (1cement :4-sand) with floating coat of neat cement slurry. Providing and fixing wash down water closet (European type, W.C. Pan) with integral P or S trap including jointing the trap with soil pipe in Cement Mortar 1:1 (1-Cement : 1-fine sand) with plastic seat cover & 10 Lit. PVC flusing Tank (A) vitreous China Pattern : (i) in white colour Providing and fixing urinals of approved quality including connection the urinal with waste pipe tap etc. including 32mm dia CP brass waste pipe and water spreader etc complete. Providing and fixing wash basin with single hole piller tap with C.I. or M.S. brackets painted while incl. cutting holes incl. M.I. Fisher union, pillar tap, stop cock, PVC connection and PVC wash pipe etc. complete.(ii) Flat back wash basin 550 x 400mm dia (i) In white colour.

[3] I

[4] 84

[5] 14.32

[6] Work shall be carried out in White/Colour glazed tiles

I I

105,106 106

17.58 (II) 17.69

The work shall be carried out in 15mm thickness instead of 10mm thickness with floating coat of cement lime slurry in 1:1 proportion for G.F. The Rate shall be paid for complete item in Sqmt. basis

146

23.112(A)(I)

The work shall be carried out with PVC flushing 10 lit. Capacity & ISI Tank of approved quality with fittings and plastic sheet and cover. The rate shall be paid for complete item on No. basis after testing

I I

152 149

22.124 (A) 23.135 (A)

Work shall be carried out 32mm dia. PVC West pipe and 15mm dia. C.P. Brass water Spreader Wash basin shall be of selected coloured. Rate includes all cost of materials, labour.

10

I I I I I I

148 149 149 151 151 153

23.127 23.135 (A) 23.136 (A) 23.95 (A) 23.96 (A) 23.134

38

[1] [2] 11 Providing and fixing 600mm x 450mm bevelled edge mirrror of superior glass mounted on 6mm thick A.C. sheet or plywood sheet and fixing to wooden pluge with C.P. brass screws and washers. 12 Providing and fixing C.P. brass towel rail comlete with C.P. brass brackets fixed to wooden plugs with C.P. brass scews. (B) 600mm x 20mm size. 13 Providing and fixing cast iron (Spun) Nahni trap of the following nominal diameter of self cleaning design with C.I. screaed down or higned grating including cost of cutting and making good the walls and floor 100mm inlet and 50mm outlet. Providing and fixing P.V.C. water storage tank ISI Mark with necessary G.I. Fitting over flow pipe, boll valve, clamp , nipple etc.including placing on terrace as directed Providing and fixing to wall, ceiling and floor galvanised Mild steel tubes (Medium grade) of the following nominal bore, tube fitting and clamps including making good the wall ceiling and floor. (A) 15mm Providing and fixing to wall, ceiling and floor galvanised Mild steel tubes (Medium grade) of the following nominal bore, tube fitting and clamps including making good the wall ceiling and floor. (C) 25mm

[3]
I

[4]
150

[5]
23.143

[6]

150

23.144 (B)

146

23.87

14

II

As per Attached

15

141

23.2 (A)

16

141

23.2 (C)

39

[1] [2] 17 Providing and fixing Gun metal check or non-return fullway wheel valve. (C) 25mm dia. 18 Providing and fixing Gun metal check or non-return fullway wheel valve. (A) 15mm dia. 19 Providing and fixing to level for slop concealed type PVC pipe fitting of the 110mm dia. low density of 10.00 Kg/cm2 working pressure. Polythene pipe complete with special flange compression type fitting bend, reducers with necessary 20 heighting, guarding, barricating clips, etc.complete. Construction of brick masonry chamber for underground C.I inspection chamber and bends with brick having crushing strength not less than 35 Kg/Cm2 in C.M. 1:5.and R.C.C. cover with frame 455 mm x 610 mm internal dimensions, having 5 MT load carrying capacity and R.C.C top slab with 1:2:4 mix( 1- cement : 2 -coarse sand:4 -graded stone aggregate 20 mm size ) foundation concrete 1:5:10 inside plaster 15 mm thick with cement mortar 1:3 finished smooth with a floating coat of neat cement on walls and bed concrete etc. Complete inside dimensions 455 mm x 610 mm and 450 mm deep for single pipe line. Providing and laying (to level or slopes) and jointing with stiff mixture of Cement Mortar in proportion 1:1, Salt glazed stoneware pipes including testing of pipes and joints complete. 150mm dia.

[3] I

[4] 152

[5] 23.99 (C)

[6]

152

23.99 (A)

144

23.8(E)

Item shall be carried out for PVC Pipe 110mm dia. 10 Kg/cm2 instead of 50mm dia. 6 Kg./Cm2

163

24.44 (I)

The work shall be carried out with C.C. cover of load carrying capacity of 5.0 M.T. instead of C.I. Cover

21

155

24.1 (B)

40

[1] [2] 22 Providing and fixing screw down bib taps of following size. (A) Brass screw down bib tap polished bright. (i) 15mm dia. 23 Distempeing (Two coats) with oil bound distemper of approved brand and manufacture and of required shade on wall surfaces to give an even shade, over and including a priming coat with distemper primer of approved brand and manufacture after thoroughly brushing the surface free from mortar dropping and other foreign matter and also including preparing the surface even and sand papered smooth. Providing and fixing powder coated alluminium Partition Partly panneled and Partly Glazed and Partly fixed for doors with frame size 101.60 x 44.45mm with Wt. 1.608 Kg / Rmt. with 5mm thick plain glass smoke gray and 12mm thick both side pre laminated Nova sheet panel including approved rubber binding clips etc. complete

[3] I

[4] 151

[5] 23.92 (A)(I)

[6]

116

18.44

24

II

As per Attached

Signature of Contractor

Deputy Executive Engineer R & B Sub Division No. 1 Surendranagar

41

Name of Work :- C.R. to N.R. Building at Surendranagar (R & B Division Office) (Prov. Polished Kotah Stone Flooring) Index to Specification Sr. Item of Work Volume Page Specification No. No. No. Item No.No. [1] [2] [3] [4] [5] 1 Providing and laying polished Kota stone slab flooring over I 86 14.43 (A) 20mm (Average) thick base of cement mortar 1:6 (1-cement : 6coarse sand) laid over and jointed with grey cement slurry including rubbing and polishing etc. complete.

Remarks. [6]

Signature of Contractor

Deputy Executive Engineer R & B Sub Division No. 1 Surendranagar

Name of Work :- C.R. to N.R. Building at Surendranagar (R & B Division Office) (Prov. Alluminium Partition in A/C Branch Part-I)

RECAPITULATION SHEET
Sr. No. 1 A B -1 2 Particulars 2 Technical Sectioned Amount Items put to tender as per Sch_B Items not put to tender 0.50% W.C Rounding Amount 3 99700.00 99192.68

495.96 11.36

99700.00
Perusal Sanctioned vide Executive Engineer, R & B Division, Surendranagar Vide Letter No.PB/B/Perusal/ Rs.

99700.00

99700.00

Deputy Executive Engineer R & B Sub Division No. 1 Surendranagar

Name of Work :- C.R. to N.R. Building at Surendranagar (R & B Division Office) (Prov. Alluminium Partition in A/C Branch Part-II)

RECAPITULATION SHEET
Sr. No. 1 A B -1 2 Particulars 2 Technical Sectioned Amount Items put to tender as per Sch_B Items not put to tender 0.50% W.C Rounding Amount 3 99950.00 99416.46

497.08 36.46

99950.00
Perusal Sanctioned vide Executive Engineer, R & B Division, Surendranagar Vide Letter No.PB/B/Perusal/ Rs.

99950.00

99950.00

Deputy Executive Engineer R & B Sub Division No. 1 Surendranagar

Name of Work :- C.R. to N.R. Building at Surendranagar (R & B Division Office) (Prov. Alluminium Partition in Executive Engineer Chamber)

RECAPITULATION SHEET
Sr. No. 1 A B -1 2 Particulars 2 Technical Sectioned Amount Items put to tender as per Sch_B Items not put to tender 0.50% W.C Rounding Amount 3 98850.00 98368.80

491.84 -10.64

98850.00
Perusal Sanctioned vide Executive Engineer, R & B Division, Surendranagar Vide Letter No.PB/B/Perusal/ Rs.

98850.00

98850.00

Deputy Executive Engineer R & B Sub Division No. 1 Surendranagar

Name of Work :- C.R. to N.R. Building at Surendranagar (R & B Division Office) (Prov. Alluminium Partition in Budget & Computer Room Part-I)

RECAPITULATION SHEET
Sr. No. 1 A B -1 2 Particulars 2 Technical Sectioned Amount Items put to tender as per Sch_B Items not put to tender 0.50% W.C Rounding Amount 3 99700.00 99192.68

495.96 11.36

99700.00
Perusal Sanctioned vide Executive Engineer, R & B Division, Surendranagar Vide Letter No.PB/B/Perusal/ Rs.

99700.00

99700.00

Deputy Executive Engineer R & B Sub Division No. 1 Surendranagar

Name of Work :- C.R. to N.R. Building at Surendranagar (R & B Division Office) (Prov. Alluminium Partition in Budget & Computer Room Part-II)

RECAPITULATION SHEET
Sr. No. 1 A B -1 2 Particulars 2 Technical Sectioned Amount Items put to tender as per Sch_B Items not put to tender 0.50% W.C Rounding Amount 3 99400.00 98865.28

494.33 40.39

99400.00
Perusal Sanctioned vide Executive Engineer, R & B Division, Surendranagar Vide Letter No.PB/B/Perusal/ Rs.

99400.00

99400.00

Deputy Executive Engineer R & B Sub Division No. 1 Surendranagar

Name of Work :- C.R. to N.R. Building at Surendranagar (R & B Division Office)


(Providing PVC Flooring & False Ceiling)

RECAPITULATION SHEET
Sr. No. 1 A B -1 2 Particulars 2 Technical Sectioned Amount Items put to tender as per Sch_B Items not put to tender 0.50% W.C Rounding Amount 3 82100.00 81700.92

408.50 -9.42

82100.00
Perusal Sanctioned vide Executive Engineer, R & B Division, Surendranagar Vide Letter No.PB/B/Perusal/ Rs.

82100.00

82100.00

Deputy Executive Engineer R & B Sub Division No. 1 Surendranagar

Name of Work :- C.R. to N.R. Building at Surendranagar (R & B Division Office)


(Providing Toilet Block in Ex. Engr. Chamber)

RECAPITULATION SHEET
Sr. No. 1 A B -1 2 Particulars 2 Technical Sectioned Amount Items put to tender as per Sch_B Items not put to tender 0.50% W.C Rounding Amount 3 98800.00 98305.55

491.53 2.92

98800.00
Perusal Sanctioned vide Executive Engineer, R & B Division, Surendranagar Vide Letter No.PB/B/Perusal/ Rs.

98800.00

98800.00

Deputy Executive Engineer R & B Sub Division No. 1 Surendranagar

Name of Work :- C.R. to N.R. Building at Surendranagar (R & B Division Office)


(Prov. Polished Kotah Stone Flooring)

RECAPITULATION SHEET
Sr. No. 1 A B -1 2 Particulars 2 Technical Sectioned Amount Items put to tender as per Sch_B Items not put to tender L.S. W.C Rounding Amount 3 99950.00 99521.36

400.00 28.64

99950.00

99950.00

Technically Sanctioned vide Deputy Executive Engineer, R & B Sub Division No. 1, Surendranagar vide letter No. City-1/23 Dtd. 27-05-2008 Rs. 99950.00

Deputy Executive Engineer R & B Sub Division No. 1 Surendranagar

on No. 1, Surendranagar

Name of Work :- C.R. to N.R. Building at Surendranagar (R & B Division Office) (Providing Toilet Block in Ex. Engr. Chamber)
TEST SCHEDULE Name of Laboratary Test

Sr. No. 1 1

Description of Item No. 2 --

Materials to be tested 3 Cement

Total Qty 4 1.15 M.T

Test required 6 15 Kg/ (1-Test) 50 M.T.

Total Nos. of Tests 7 1 No.

Remars

5 (1) Consistancy Test (2) Setting time (3) Comp. strength (4) Soundness (5) Specific gravity (6) Chemical analysis (7) Fineness Test (1) Fineness Modulas (2) Specific gravity (3) Clay and Fine silt conte (4) Water absorption

8 As Specified in Sp. Books

Sand for all items pertaining to sand

Sand

--

1 Test / Working season or change of river

As required during execution of work 2 Nos.

As Specified in Sp. Books

Signature of Contractor

Deputy Executive Engineer R & B Sub Division No. 1 Surendranagar

Name of Work :- C.R. to N.R. Building at Surendranagar (R & B Division Office) (Prov. Polished Kotah Stone Flooring)
TEST SCHEDULE Name of Laboratary Test

Sr. No. 1 1

Description of Item No. 2 --

Materials to be tested 3 Cement

Total Qty 4 2.65 M.T

Test required 6 15 Kg/ (1-Test) 50 M.T.

Total Nos. of Tests 7 1 No.

Remars

5 (1) Consistancy Test (2) Setting time (3) Comp. strength (4) Soundness (5) Specific gravity (6) Chemical analysis (7) Fineness Test (1) Fineness Modulas (2) Specific gravity (3) Clay and Fine silt conte (4) Water absorption

8 As Specified in Sp. Books

Sand for all items pertaining to sand

Sand

--

1 Test / Working season or change of river

As required during execution of work 2 Nos.

As Specified in Sp. Books

Signature of Contractor

Deputy Executive Engineer R & B Sub Division No. 1 Surendranagar

Name of Work :- C.R. to N.R. Building at Surendranagar (R & B Division Office)


(Providing Toilet Block in Ex. Engr. Chamber)

Quantity of Material to be brought by Agency


Particulars Approximate by Quantity M.T

[1] Cement

1.15 M.T.

Signature of Contractor

Deputy Executive Engineer R & B Sub Division No. 1 Surendranagar

Name of Work :- C.R. to N.R. Building at Surendranagar (R & B Division Office)


(Prov. Polished Kotah Stone Flooring)

Quantity of Material to be brought by Agency


Particulars Approximate by Quantity M.T

[1] Cement

2.65 M.T.

Signature of Contractor

Deputy Executive Engineer R & B Sub Division No. 1 Surendranagar