Sie sind auf Seite 1von 122

2005 IST Group.

All rights reserved

Seismic Isolation Project for Mitchell Hall


Supervised by: Prof. Dr. Oral Bykztrk Graduate Students: Leonardo Duenas John Kelly Tai Chieh Wu

May 2001

PRESENTATION OVERVIEW
PART 1
INTRODUCTION, INVESTIGATION, REHABILITATION OPTIONS

PART 2
ANALYSIS OF EXISTING FIXED BASE STRUCTURE

PART 3
DESIGN OF BASE ISOLATION

PART 4
ANALYSIS OF ISOLATED STRUCTURE COMPARISON (PART 2)

PART 5
REALISATION CONSTRUCTION SEQUENCE AND COST ESTIMATION
2005 IST Group

MISSION STATEMENT
To repair and retrofit Mitchell Hall for seismic upgrade.

It is required that it remain SERVICEABLE - 100 year period of return and INTACT 475 period of return. Superstructure restored aesthetically and functionally.
2005 IST Group

Elevation of Mitchell Hall

2005 IST Group

TYPICAL FLOOR PLAN

2005 IST Group

BUILDING DESCRIPTION

30 x 15 m footprint
Exterior walls : 0.6 m thick un-reinforced concrete Columns : Concrete encased I-Sections Floor Slabs : Structural slabs resting on mild steel beams
2005 IST Group

INVESTIGATION
Visual Inspection
Initial assessment of internal and external members/surfaces

Non-Destructive Testing
Detection of faults not visible to the naked eye Voids, Discontinuities Measure of material properties Extent of internal crack propagation

Historical Research and Analysis


Supported by Photographic records

2005 IST Group

CAUSES OF DETERIORATION

2005 IST Group

PREVIOUS SEISMIC ACTIVITY


Magnitude 7.4 on the Richter Scale, near Izmit, at 15.9 km depth, August 1999 Multiple shocks; 125 200 km surface rupture, up to 4.9m right lateral offset, up to 2m vertical offset Tectonic subsidence or landsliding liquefaction and settlement) Urban earthquake - fault displacements beneath buildings and bridges
2005 IST Group

(in

addition

to

NORTH ANATOLIAN FAULT

2005 IST Group

STRUCTURAL DAMAGE

2005 IST Group

REHABILITATION OPTIONS

Structural Stiffening vs. Base Isolation


2005 IST Group

STRUCTURAL STIFFENING

Cement Injections Use of Composite Materials to improve existing infrastructure e.g. Composite wrapping/confinement of columns

Conduit tying (Building Confinement) Installation of Shear Walls Post Tensioning of external walls Gunite / Shotcrete Diagonal Bracing Systems

2005 IST Group

CONCRETE REPAIR METHODS


Grout Injections in a structural floor slab.

Wrapping of concrete column with composite material

2005 IST Group

CONCRETE REPAIR METHODS

Use of Shear Walls to resist induced seismic loading


2005 IST Group

STRUCTURAL STIFFENING
Induced Moments Internal Outriggers =>Stiffening System Post-Tensioning

3 ft thick masonry wall (unreinforced)

Ground-Anchors

Building Section
2005 IST Group

STRUCTURAL STIFFENING
Advantages
-Most economic and widely used method in Europe. -Involves repair of existing infrastructure. e.g. Composite wrapping of columns Shotcrete walls

Disadvantages
-Involves major intrusion upon existing infrastructure. -May not be a sufficient solution in itself. -Restricted building access during construction. -Irreversible.
2005 IST Group

BASE ISOLATION

Concept - Isolate the superstructure from the foundation. Two ways to approach - Install rubber bearings or friction sliding system
2005 IST Group

BASE ISOLATION

f

A Elastic strategy
y

A y u

A* Base Isolation
2005 IST Group

Plastic strategy

BASE ISOLATION
Advantages
- Isolates Building from ground motion.
=> Minimal repair of superstructure

- Building can remain serviceable throughout construction. - Does not involve major intrusion upon existing superstructure.

Disadvantages
- Costly. Is challenging to implement in an efficient manner. - Costly to connect utilities to building (flexible connections). - Must allow for building displacements.
2005 IST Group

PRESENTATION OVERVIEW
PART 1
INTRODUCTION, INVESTIGATION, REHABILITATION OPTIONS

PART 2
ANALYSIS OF EXISTING FIXED BASE STRUCTURE

PART 3
DESIGN OF BASE ISOLATION

PART 4
ANALYSIS OF ISOLATED STRUCTURE COMPARISON (PART 2)

PART 5
REALISATION CONSTRUCTION SEQUENCE AND COST ESTIMATION
2005 IST Group

FUNDAMENTAL PERIOD
Ta = C t * hn
Ct = hn = Coefficient of structural system Height [m]

3/4

Ct =

0.018

Weak seismic resistance System

hn =

15

Height From the bottom of top floor

Ta = 0.1372

s
2005 IST Group

BASE SHEAR FORCE


Z * I *C Vs = *W Rw
Z= I= S= C= I= Z= Seismic Zone Factor Importance coefficient 1.2 2.75 1 0.4 Special ocupation Seismic zone factor

C
S= W=

1 . 25 * S T 2 /3

Site coefficient Seismic dead load

Medium-dense to dense soil

Rw = M=

4 1,800,000 kg

Shear walls masonry Seismic load

Vs =

4,950

kN

2005 IST Group

WIND LOAD
F = Ce * Cq * qs * I w * Ae
F= Cq = Ce = Wind Force [kN] Pressure Coefficient Coefficient of exposure qs = Iw = Ae = Dynamic wind pressure Importance factor Effective area

qs =

0.786

kN/m2

10 - 20 m 130 kph

Height range Wind Velocity Length Height

Ae =

450

m2

30 m 15 m

Cq =

1.2

Prismatic structure H <= 2b

Ce = Iw =

1.73 1

Exposure D Special occupancy structures

F=

734

kN
2005 IST Group

FLOOR DISTRIBUTION
2005 IST Group

NODE DEFINITION
2005 IST Group

3D - MODEL

2005 IST Group

FIXED CONDITION

2005 IST Group

2005 IST Group

Station
ARELK (ARC) AMBARLI (ATS) BOTA (BOT) EKMECE (CNA) HAVA ALANI (DHM) YAPI KRED (YKP) YARIMCA (YPT) FATH (FAT) HEYBELADA (HAS) BURSA (BUR)

Peak Ground Acceleration Max-Horizontal Max-Vertical


211.365 mg 252.564 mg 98.877 mg 177.307 mg 90.210 mg 41.07 mg 322.205 mg 189.392 mg 110.230 mg 100.891 mg 83.252 mg 80.078 mg 23.560 mg 57.678 mg 55.115 mg 27.100 mg 241.089 mg 131.714 mg 143.494 mg 48.218 mg
2005 IST Group

[North - South] Yarimca Sacaled Record


300

200

100

0 -20 0 -100 20 40 60 80 100 120 140

mg

-200

-300

-400

-500

Seconds
2005 IST Group

FFT N-S
22000 20000 18000

Amplitude [ H(w) ]

16000 14000 12000 10000 8000 6000 4000 2000 0 0 2 4 6 8 10 12 14 16

Frequency [Hz]

2005 IST Group

[Vertical] Yarimca Sacaled Record


400

300

200

100

mg

0 -20 -100 0 20 40 60 80 100 120 140

-200

-300

-400

Seconds
2005 IST Group

FFT UP
16000 14000 12000

Amplitude [ H(w) ]

10000 8000 6000 4000 2000 0 0 2 4 6 8 10 12 14 16

Frequency [Hz]

2005 IST Group

Max Displacement: 0.60 m

Max Displacement: 0.43 m

2005 IST Group

SPECTRAL ACCELERATION [N-S]

2005 IST Group

Stresses in Z direction - Compression

2005 IST Group

Stresses in X direction - Compression

2005 IST Group

Shear Stresses in Y-Z direction

2005 IST Group

END ZONE

END ZONE
2005 IST Group

Maximum Displacement: 0.084 m

COMPRESSIONAL FORCES
2005 IST Group

PRESENTATION OVERVIEW
PART 1
INTRODUCTION, INVESTIGATION, REHABILITATION OPTIONS

PART 2
ANALYSIS OF EXISTING FIXED BASE STRUCTURE

PART 3
DESIGN OF BASE ISOLATION

PART 4
ANALYSIS OF ISOLATED STRUCTURE COMPARISON (PART 2)

PART 5
REALISATION CONSTRUCTION SEQUENCE AND COST ESTIMATION
2005 IST Group

FIXED BASE vs. ISOLATED

2005 IST Group

CONCEPT OF BASE ISOLATION

2005 IST Group

BASE ISOLATION

2005 IST Group

THEORY OF BASE ISOLATION SYSTEM


Base Isolation system can be modified as a 2-DOF system
M Us+Ub+Ug

Ks, Cs Mb Ub+Ug Kb, Cb Ug

2005 IST Group

THEORY OF BASE ISOLATION SYSTEM (Cont.)


Governing Equation:
m u s + c u s + kus = m(u g + ub )
Us Us

..

..

..

1.000

1.000

First Mode

Second Mode
2005 IST Group

RUBBER BEARINGS

2005 IST Group

FRICTION PENDULUM SYSTEM

2005 IST Group

PRELIMINARY DESIGN PROCEDURE


DEFINE GUIDELINES SELECT OPTIMAL ISOLATORS

OBTAIN PROPERTIES

COMPUTE EFFECTIVE STIFFNESS & BASE SHEAR

BACK CALCULATE AND CHECK RESULT

ESTIMATE DESIGN PARAMETERS

SET UP TARGET BUILDING PERIOD AND BUILDING DISPLACEMENT


2005 IST Group

PRELIMINARY DESIGN
References:
Uniform Building Code (UBC), 1997 Edition. Design of Seismic Isolated Structures, J. M. Kelly, 1999.

Two Approach to Seismic Hazard:


Design Basis Earthquake (DBE) Maximum Capable Earthquake (MCE)

Isolation Design Data:


Building Weight : 1,800,000 (Kg) = 4,000 (Kips) Estimate All Dynamic Parameters

2005 IST Group

PRELIMINARY DESIGN Procedure


DEFINE GUIDELINES SELECT OPTIMAL ISOLATORS

OBTAIN PROPERTIES

COMPUTE EFFECTIVE STIFFNESS & BASE SHEAR

BACK CALCULATE AND CHECK RESULT

ESTIMATE DESIGN PARAMETERS

SET UP TARGET BUILDING PERIOD AND BUILDING DISPLACEMENT


2005 IST Group

DESIGN RESPONSE SPECTRA


1.2 Fixed-Based Period 1

Spectral Accerlation (g)

0.8

0.6 Ca/T 0.4 Design Period 0.2

0 0 To 0.5 Ts 1 1.5 2 2.5 Period (sec) 3 3.5 4 4.5 5

Target Building Period : TD = 2.5 (s) TM = 3.0 (s)


2005 IST Group

PRELIMINARY DESIGN PROCEDURE


DEFINE GUIDELINES SELECT OPTIMAL ISOLATORS

OBTAIN PROPERTIES

COMPUTE EFFECTIVE STIFFNESS & BASE SHEAR

BACK CALCULATE AND CHECK RESULT

ESTIMATE DESIGN PARAMETERS

SET UP TARGET BUILDING PERIOD AND BUILDING DISPLACEMENT


2005 IST Group

DESIGN DATA
Effective Stiffness & Base Shear
Keff = 70 kips/in (12,000 kN/m) Base Shear Below Interface = 940 kips (4200 kN) Above Isolation Interface = 470 kips (2100 kN)

Loading Condition:
80% of the weight Taken by the external wall 20% of the weight Taken by the internal columns

Design Parameters:
Max. Displacement 18 in. (46 cm) Effective Stiffness average 3 kips/in (500 kN/m) per isolator
2005 IST Group

PRELIMINARY DESIGN PROCEDURE


DEFINE GUIDELINES SELECT OPTIMAL ISOLATORS

OBTAIN PROPERTIES

COMPUTE EFFECTIVE STIFFNESS & BASE SHEAR

BACK CALCULATE AND CHECK RESULT

ESTIMATE DESIGN PARAMETERS

SET UP TARGET BUILDING PERIOD AND BUILDING DISPLACEMENT


2005 IST Group

CENTER ZONE

2005 IST Group

DETAIL OF ISOLATORS
Information Resources : DIS Incorporated Description Select same size of Isolators
Diameter : 29.5 (in) Height : 18 (in)
Isolator Properties Displacement (in) Effective Stiffness (kips/in) Energy Dissipation per Cycle (kips-in) Damping Ratio Load Capacity (kips) Numbers C29.5-18-L0-S 20 2.2 0 0.02 230 16 C29.5-18-L1-S 20 3.5 1520 0.23 223 8
2005 IST Group

PRELIMINARY DESIGN PROCEDURE


DEFINE GUIDELINES SELECT OPTIMAL ISOLATORS

OBTAIN PROPERTIES

COMPUTE EFFECTIVE STIFFNESS & BASE SHEAR

BACK CALCULATE AND CHECK RESULT

ESTIMATE DESIGN PARAMETERS

SET UP TARGET BUILDING PERIOD AND BUILDING DISPLACEMENT


2005 IST Group

ISOLATORS LOCATION

Natural Rubber Bearing

Lead-Plug Rubber Bearing


2005 IST Group

ISOLATOR HYSTERESIS LOOP

2005 IST Group

2005 IST Group

PRESENTATION OVERVIEW
PART 1
INTRODUCTION, INVESTIGATION, REHABILITATION OPTIONS

PART 2
ANALYSIS OF EXISTING FIXED BASE STRUCTURE

PART 3
DESIGN OF BASE ISOLATION

PART 4
ANALYSIS OF ISOLATED STRUCTURE COMPARISON (PART 2)

PART 5
REALISATION CONSTRUCTION SEQUENCE AND COST ESTIMATION
2005 IST Group

FIXED BASE VS. ISOLATED

Fixed Base

Isolated
2005 IST Group

3D ISOLATED MODEL
2005 IST Group

3D ISOLATED MODEL

2005 IST Group

Stresses in Z direction Compression FIXED

2005 IST Group

Stresses in Z direction Compression ISOLATED

2005 IST Group

Shear Stresses in Y-Z direction FIXED

2005 IST Group

Shear Stresses in Y-Z direction ISOLATED

2005 IST Group

FIXED MODEL

2005 IST Group

ISOLATED MODEL
2005 IST Group

PRESENTATION OVERVIEW
PART 1
INTRODUCTION, INVESTIGATION, REHABILITATION OPTIONS

PART 2
ANALYSIS OF EXISTING FIXED BASE STRUCTURE

PART 3
DESIGN OF BASE ISOLATION

PART 4
ANALYSIS OF ISOLATED STRUCTURE COMPARISON (PART 2)

PART 5
REALISATION CONSTRUCTION SEQUENCE AND COST ESTIMATION
2005 IST Group

CONSTRUCTION

2005 IST Group

A Base Isolated Structure

2005 IST Group

INITIAL STATE

2005 IST Group

BASEMENT EXCAVATION
Dig out basement Insert retaining walls
Prevents excessive

bearing

2005 IST Group

2005 IST Group

2005 IST Group

MOAT EXCAVATION
Insert Lateral Supports Place Ring Beams
Lateral constraint Longitudinal Constraint Provide for connection

detailing
2005 IST Group

2005 IST Group

2005 IST Group

PROVISION OF RIGID LAYER


A rigid layer is required directly above and below the soft (isolation) layer. Insert hydraulic jacks

2005 IST Group

2005 IST Group

2005 IST Group

PUNCH ISOLATOR CAVITIES


Load up hydraulic jacks Lock caps Punch holes

2005 IST Group

2005 IST Group

2005 IST Group

INSTALL ISOLATORS
Teams
Demolition Steel Welding Jacking Craning Grouting Concrete

2005 IST Group

2005 IST Group

2005 IST Group

SITE LOGISTICS
4.5 ft

C rane

S ection from W est side to enable access

Isolator u nit

R ails
50 ft

57 ft

C ut C olum ns

D esired Location

100 ft

105 ft
2005 IST Group

INSTALLATION TEAMS
TEAM
Demolition:

TASK
Concrete cutting, and chipping from columns to expose steel (2 days) Welding/bolting of collars and corbels to columns /walls to facilitate jacking, and setting up of temporary bracing system (1 3 days) Operation of jacks and maintaining correct pressure distribution over building (1/2 day) Lower isolators into building and manipulate into place (1 3 days) Connect the isolators to the building as specified by manufacturers (1 2) Finish on cut outs and columns, ensure good connection and stability against future cracking. (1 2 days)
2005 IST Group

Steel:

Jacking: Craning: Grouting:

Concrete:

FLAT JACKING THE ISOLATORS

Standard jacks Oil transfusion jacks


2005 IST Group

2005 IST Group

2005 IST Group

2005 IST Group

IMAGES OF INSTALLED ISOLATORS

2005 IST Group

2005 IST Group

2005 IST Group

2005 IST Group

2005 IST Group

2005 IST Group

2005 IST Group

UTILITIES

Sewer Connection

Gasline
2005 IST Group

CONNECTION DETAILING

2005 IST Group

RETROFITTING STAIRS

2005 IST Group

COST DISTRIBUTION

Isolators

10% 14%

Excavation
20%

Dem olition

Instalation
10% 10% 36%

Structural im provem ent


Sundries

$1,269,050
(New Structure US$4,000,000)

2005 IST Group

Low Cost Strategies

Columns Matrix of Rubber bearings Connecting beams

Walls

Longitudinal rubber bearings in matrix configuration


2005 IST Group

Low Cost Strategies


Dispersed phase (Reinforcement) Interphase

Continuous phase (Matrix)

Composite plates

Reinforcing scheme

Multidirectional continuous fiber composite


2005 IST Group

Low Cost Strategies


Internal space is never restricted at any floor

Columns placed in the same external or internal wall-axes

Columns in charge of single floors.

Set of independent isolators

Load distribution to independent sets of isolators 2005 IST Group Local Fabrication

BASE ISOLATION (Ball System)


mg

2r

N
Spherical groove

Rigid ball mg

N 2005 IST Group

BASE ISOLATION

Universal Linear Slider High Damping Rubber Synthetic Rubber Bearings

2005 IST Group

Comparison between NRB, HSR and ULS

2005 IST Group

Cost Trend for New Construction

2005 IST Group

2005 IST Group

2005 IST Group

2005 IST Group

2005 IST Group

http://web.mit.edu/~jpkelly/www /index.htm

2005 IST Group

2005 IST Group

2005 IST Group

Das könnte Ihnen auch gefallen