Sie sind auf Seite 1von 23

Project

Work
Thk
Length
Exc.Area
Exc.Vol.
Mob
Work Duration
No.of Panel
Length of Panel
Total wk (MC)
Panel/wk (Based MCP)
Prod.rate, m3
No.of Rigs
Grab
1.2 BC Cutter
SURS DWALL
Soil Profile
104
Fill
557
KF
209
GVI
174
GV
52
GIV
35
GIII
0
GII
1132 Total area, m3
Increased Qty

Normal

Normal

Dwall
0.8

Dwall
1.2

1.0
112
2,781
2,225

1.2
666
29,128
34,953

20
5.62
31.00

119
5.60
31.00

2
2
326
1,857
131
468
0
0
0
2,781

Phase 1

Phase 2

Dwall
0.8

14

Phase 3

Dwall
1.2

55
69.00
13.00
5.31

0.8

G.Total
1.2

21
27
8
3.38

0.8

1.2
779
31,909
37,179
#REF!
#REF!
139
80
31

43
43
10
4

1.18
4
2
2

2
2
2,536
15,798
3,397
4,848
909
808
831
29,128

\\vboxsrv\conversion_tmp\scratch_2\201400549.xlsx.ms_office

163
1,498
0
468
0
0
0
2,128

1,223
7,073
1,488
1,688
741
332
262
12,809

163
359
131
0
0
0
0
653

423
2,884
673
934
57
190
0
5,161

0
0
0
0
0
0
0
0

889
5,841
1,235
2,226
112
286
569
11,158

2,862
17,655
3,527
5,316
909
808
831
31,909
Diff

-2,659

1.0 m Dwall Panel


Zone A
Block 1

Phase 1

Phase 2

Phase 3

N Value
0
<20
30-60
60-100
>100
RQD 30-80
RQD 100

Panel Length
(m)
Fill (m)
KF (m)
GVI (m)
GV (m)
GIV (m)
GIII (m)
GII (m)

N Value
0
<20
30-60
60-100
>100
RQD 30-80
RQD 100
N Value
0
<20
30-60
60-100
>100
RQD 30-80
RQD 100

Zone A
Block 2

Zone A
Block 3

Zone A1

65.29
2.00
18.50
6.50
-

Panel Length
Fill (m)
KF (m)
GVI (m)
GV (m)
GIV (m)
GIII (m)
GII (m)

Panel Length
Fill (m)
KF (m)
GVI (m)
GV (m)
GIV (m)
GIII (m)
GII (m)

Zone A
Block 1

Zone A
Block 2

Zone A
Block 3

1.2m Dwall Panel

Phase 1

Phase 2

N Value
0
<20
30-60
60-100
>100
RQD 30-80
RQD 100

Panel Length
(m)
Fill (m)
KF (m)
GVI (m)
GV (m)
GIV (m)
GIII (m)
GII (m)

N Value
0
<20
30-60
60-100
>100
RQD 30-80

Panel Length
Fill (m)
KF (m)
GVI (m)
GV (m)
GIV (m)
GIII (m)

49.75
3.00
22.00
4.00
3.00
4.50
1.00

19.95
3.00
25.50
2.00
3.50
2.50
1.00

22.80
3.00
22.00
3.00
1.00

19.43
3.00
21.30
6.40
2.80
1.00

33.68
3.00
20.00
5.00
1.00

16.58
3.00
20.00
5.00
1.00

16.06
3.00
18.00
6.50
3.50
2.50
1.50
2.00

38.87
2.50
18.00
4.50
6.50
1.50
1.00
3.00

Phase 2

Phase 3

RQD 100

GII (m)

N Value
0
<20
30-60
60-100
>100
RQD 30-80
RQD 100

Panel Length
Fill (m)
KF (m)
GVI (m)
GV (m)
GIV (m)
GIII (m)
GII (m)

5.70
3.00
21.00
11.00
1.00
1.00

Zone A2

Zone B

Zone C

Zone D

Zone D1

Total
Other Area

14.51
2.20
20.00
3.00
-

32.65
5.00
11.00
4.00
-

Zone B Zone C

Zone D

Zone A2

(m)

79.80
4.20
38.50
9.50
-

32.65
5.00
11.00
4.00
-

112.45

Zone D1

Total
Other Area
1/F-E

39.38
3.00
20.00
2.50
13.50
2.00
1.00
-

11.14
2.00
22.00
10.00
7.00
3.00

38.87
5.00
11.50
4.50

29.02
3.00
16.00
6.00
5.00
1.50
1.00

(m)
B1-C1

23.32
5.00
19.00
7.00

308.59
35.50
215.30
47.00
48.40
20.30
11.50
8.00

3.00
-

47.16
3.00
20.00
2.50
13.50
1.00
1.00

20.21
3.00
22.50
9.50
7.00
3.00

117.63
9.00
60.00
12.50
13.50
1.00
3.00

21.25
4.00
14.00
1.00

15.00

16.06
3.00
21.00
2.00
1.00

154.43
3.00
21.75
3.50
10.50
1.00

31.09
3.00
16.00
9.00
5.00
3.00
2.00
5.00

11.40
3.00
22.50
10.00
4.50

239.93
19.00
116.25
35.50
22.00
3.00
15.00
666.15

Total
(m2)
5.7

Nos
of
Panels

14
162.50
1,498.07
467.92
6
163.25
359.15
130.60
0
2,781.48

Total
(m2)
5.7

20

Nos
of
Panels

55
1,019.58
5,894.51
1,240.33
1,407.00
617.30
276.71
218.69
21
352.89
2,403.13
561.20
778.13
47.16
158.05

43
741.04
4,867.25
1,029.14
1,855.22
93.27
238.37
474.20
24,273.15

119

103.33mrl
100.00mRL

95.00mRL

90.00mRL

85.00mRL

80.00mRL

75.00mRL

70.00mRL

65.00mRL

DT/2009

a2

ABB222

a1

60.00mRL

55.00mRL

50.00mRL

Legend
Fill
Kallang Formation
Granite GVI
Granite GV
Granite GIV
`

Granite GIII
Granite GII

DT/2118/VST,PZS

ABH220

3
4
5
6

a4

ABH214

ABH218

7
9

a5

103.33mrl
100.00mRL

a4

d1

b8

SECTIONAL ELEVATION ON LOW LEVEL DIAPHRAGM WALL FOR SURS AT GRID LINE d1-b8-a4

TOP OF DIAPHRAGM WALL

90.00mRL

ABH214

DT/2008/VST,PZS

ABH213

ABH215

95.00mRL

85.00mRL

80.00mRL

75.00mRL

70.00mRL

SURS FORMATION LEVEL


65.00mRL

DWALL TOEL LEVEL

60.00mRL

6m TOE LEVEL EXTENDED


BELOW SURS FORMATION LEVEL
55.00mRL

Legend
Fill

Granite GIII

Kallang Formation

Granite GII

Granite GVI

Diaphragm Wall Panel

Granite GV
Granite GIV
`

60m

50m

40m

30m

20m

0m

10m

50.00mRL

b9

d2
103.33mrl
100.00mRL

b10

SECTIONAL ELEVATION ON LOW LEVEL AND FULL HEIGHT DIAPHRAGM WALL FOR SURS AT GRID LINE d2-b9-b10

TOP OF DIAPHRAGM WALL

90.00mRL

DT/2008/VST,PZS

ABH 212

ABH214

95.00mRL

85.00mRL

80.00mRL

75.00mRL

70.00mRL

SURS FORMATION LEVEL


65.00mRL

DWALL TOEL LEVEL

60.00mRL

6m TOE LEVEL EXTENDED


BELOW SURS FORMATION LEVEL
55.00mRL

Legend
Fill

Granite GIII

Kallang Formation

Granite GII

Granite GVI

Diaphragm Wall Panel

Granite GV
Granite GIV

60m

50m

40m

30m

20m

0m

10m

50.00mRL

Bill of Quantities
Downtown Line Stage 2 C920 Project, Singapore

Option A - SURS with Diaphragm Wall

DIAPHRAGM WALL WORKS


ITEM

DESCRIPTION

UNIT

QTY

RATE

AMOUNT

All Quantities are Provisional


1.0 Mobilisation & Demobilisation & Maintenance

Remarks
-

L/S

2,451,690.00

Sub-Total $

2,451,690.00

2.0 Guide Wall Construction


2.1 Constructing 300mmx1200mm Guidewall

790

280.00

2.2 Removal of Guidewall

790

40.00

Sub-Total $

221,200.00 Included Material


31,600.00 Included Disposal

252,800.00

3.0 Diaphragm Wall (1200mm thick)


3.1 Exacavation on Soil & Rock (GIII Granite at 1.0m socketing)

m3

26,135

405.00

10,584,675.00 Included Disposal

3.2 Extra Over for Rock Excavation ( GIII Granite)


3.3 Concreting

m3

800

650.00

520,000.00 Included Disposal

m3

26,135

25.00

653,375.00 Material by Maincon

3.4 Rebar Fabrication & Installation

ton

6,011

250.00

1,502,762.50 Material by Maincon

3.5 Place LSS Type I for Backfilling

m3

1.00

70.00

4.1 Exacavation on Soil & Rock (GIII Granite at 1.0m socketing)

m3

2,328

455.00

1,059,240.00 Included Disposal

4.2 Extra Over for Rock Excavation ( GIII Granite)

m3

56

455.00

25,480.00 Included Disposal

4.3 Concreting

m3

2,328

40.00

93,120.00 Material by Maincon

133,860.00 Material by Maincon

Rate Only

4.0 Diaphragm Wall (1000mm thick)

4.4 Rebar Fabrication & Installation

ton

535

250.00

4.5 Place LSS Type I for Backfilling

m3

1.00

70.00

Rate Only Included Material

5.0 Diaphragm (SURS) Wall (1200mm thick)


5.1 Exacavation on Soil & Rock (GIII Granite at 1.0m socketing)

m3

6,105

405.00

2,472,525.00 Included Disposal

5.2 Extra Over for Rock Excavation (GII and GIII Granite)

m3

1,263

1,705.00

2,153,415.00 Included Disposal

5.3 Concreting

m3

1,060

25.00

26,500.00 Material by Maincon

5.4 Rebar Fabrication & Installation

ton

244

250.00

60,950.00 Material by Maincon

5.5 Place LSS Type I for Backfilling

m3

6,308

70.00

Sub-Total $

441,560.00 Included Material


19,727,462.50

6.0 Hacking and Trimming Works


6.1 Hacking and trimming of Diaphragm Wall to Design COL

884

350.00

309,400.00 Included Disposal


-

Acceptance Works in Requirements To LTA's M&W


7.0 Specification
7.1 Sonic Coring Works

No

1.00

5,000.00

Rate Only

7.2 Sonic Logging Works

No

1.00

3,000.00

Rate Only

8.0 Other Works


8.1 Coupler Installation (Labour Only)
Installation of 150mm dia.black pipe for Inclinometer Works by
8.2 Others
Installation of 150mm dia.black pipe for Fissured Grouting Works by
8.3 Others
8.4 Indstallation of H-Beam into Diaphragm Wall T-Panel (Labour Only)

Rate Only Material by Maincon

No

1.00

5.00

1.00

45.00

Rate Only Included Material

No

1.00

45.00

Rate Only Included Material

No

1.00

1,000.00

Sub-Total $

Rate Only Material by Maincon

309,400.00
-

TOTAL $

22,741,352.50

Bill of Quantities
Downtown Line Stage 2 C920 Project, Singapore
DIAPHRAGM WALL WORKS
ITEM

DESCRIPTION
All Quantities are Provisional
1.0 Mobilisation & Demobilisation & Maintenance

Option B - Pre-Boring Works on SURS


UNIT
L/S

QTY

RATE
1

AMOUNT
-

Sub-Total $
2.0 Guide Wall Construction
2.1 Constructing 300mmx1200mm Guidewall
2.2 Removal of Guidewall

m
m

790
790

$
$

280.00
40.00

$
$

Sub-Total $

Remarks

2,451,690.00
2,451,690.00
221,200.00 Included Material
31,600.00 Included Disposal
252,800.00

3.0 Diaphragm Wall (1200mm thick)


3.1 Exacavation on Soil & Rock (GIII Granite at 1.0m socketing)
3.2 Extra Over for Rock Excavation ( GIII Granite)

m3
m3

26,135
800

$
$

405.00
650.00

$
$

3.3 Concreting

m3

26,135

25.00

653,375.00 Material by Maincon

3.4 Rebar Fabrication & Installation

ton

6,011

250.00

1,502,762.50 Material by Maincon

3.5 Place LSS Type I for Backfilling

m3

1.00

70.00

4.1 Exacavation on Soil & Rock (GIII Granite at 1.0m socketing)

m3

2,328

455.00

1,059,240.00 Included Disposal

4.2 Extra Over for Rock Excavation ( GIII Granite)

m3

56

455.00

25,480.00 Included Disposal

4.3 Concreting

m3

2,328

40.00

93,120.00 Material by Maincon

133,860.00 Material by Maincon

10,584,675.00 Included Disposal


520,000.00 Included Disposal

Rate Only Included Material

4.0 Diaphragm Wall (1000mm thick)

4.4 Rebar Fabrication & Installation

ton

535

250.00

4.5 Place LSS Type I for Backfilling

m3

1.00

70.00

5.1 Pre-Boring on Soil & Rock (GIII Granite at 1.0m socketing)

m3

6,105

405.00

2,472,525.00 Included Disposal

5.2 Extra Over for Rock Pre-Boring (GII GIII Granite)

m3

1,263

650.00

820,950.00 Included Disposal

5.3 Concreting

m3

1,060

25.00

Rate Only Included Material

5.0 Pre-Boring (SURS) Wall (127m Length)

5.4 Rebar Fabrication & Installation

ton

244

250.00

5.5 Place LSS Type I for Backfilling

m3

6,308

70.00

Sub-Total $

26,500.00 Material by Maincon


60,950.00 Material by Maincon
441,560.00 Included Material

18,394,997.50

6.0 Hacking and Trimming Works


6.1 Hacking and trimming of Diaphragm Wall to Design COL

884

350.00

309,400.00 Included Disposal


-

Acceptance Works in Requirements To LTA's M&W


7.0 Specification
7.1 Sonic Coring Works

No

1.00

5,000.00

Rate Only Included Material

7.2 Sonic Logging Works

No

1.00

3,000.00

Rate Only Included Material

No

1.00

5.00

8.0 Other Works


8.1 Coupler Installation (Labour Only)

Rate Only Material by Maincon

Installation of 150mm dia.black pipe for Inclinometer Works by


8.2 Others
Installation of 150mm dia.black pipe for Fissured Grouting Works by
8.3 Others

1.00

45.00

Rate Only Included Material

No

1.00

45.00

Rate Only Included Material

8.4 Indstallation of H-Beam into Diaphragm Wall T-Panel (Labour Only)

No

1.00

1,000.00

Sub-Total

Rate Only Material by Maincon

309,400.00
-

TOTAL $

21,408,887.50

Das könnte Ihnen auch gefallen