Sie sind auf Seite 1von 13

ESTIMATING LABOR UNIT DATA FOR CONCRETE CONSTRUCTION

M
uch has been said about concrete and its wide range of usage in the construction field, but all too little has been said of the cost of labor for the installation of this important material. It is absurd simply to say that a unit or block of work is worth so many dollars because it cost your company a certain price for the same type of work on a previous project of the same nature. To the limited field of literature on the subject of labor units for the placement of concrete, a comprehensive new book has been added: Estimators General Construction Manhour Manual, compiled by John S. Page, and published by the Gulf Publishing Company of Houston, Texas. It covers, among other things, the placement of concrete in various forms and under va ri o u s conditions. This comprehensive information provides an authoritative source of data on labor units in manhours that will prove valuable to the general construction contractor, as well as architectural, engineering and plant personnel concerned with construction labor cost. As an estimating tool there are two features which particularly contribute to this book: (1) It covers practically every type of concrete construction that will be encountered on residential, commercial and industrial building including forms, reinforcing steel, and concrete placement. (2) Each table of manhour units contains adequate explanations of the specific operations covered. By special permission of the publishers, Concrete Construction is privileged to present a portion of the manhour unit data relating to its field. the crews The six classifications of production elements are: general economy, project supervision, labor relations, job conditions, equipment conditions and weather conditions. Using the scale indicated by the five numbered ranges above, the estimator evaluates each of the six factors in percentages and obtains the average of these six percentages in order to determine the overall productivity efficiency of his crews on the particular project under consideration. As an example let us assume that the estimator rates these six production elements as follows: 1. General Economy 75% 2. Project Supervision 3. Labor Relations 4. Job Conditions 5. Equipment 6. Weather 70% 65% 60% 70% 50%

PRODUCTIVITY FACTORS
To intelligently use the manhour unit data presented in these tables, the user must give consideration to several factors that tend to affect the productive efficiency of his crews as compared to the productive efficiency of the crews upon whose efforts the table units are based. To assist the user in making these adjustments, the author reports that the tables are based upon a productivity efficiency rate of 70 percent, which he considers average. As a guide to the basis he used in arriving at this percentage, he classifies productivity efficiency into five ranges as follows: 1. Very Low 10- 40% 2. Low 3. Average 4. Very Good 41- 60% 61- 80% 81- 90%

Total 390% Since there are six elements involved, we must now divide the total percentage by the number of elements to arrive at an average percentage of productivity: 390 percent 6 = 65 percent average productivity efficiency. As previously mentioned, the manhour tables are based on an average productivity efficiency of 70 percent; thus these units would have to be increased 5 percent above the tabulated values in order to be applicable to the project under consideration.

EVALUATING THE DATA


Instead of increasing each of the manhour units by 5 percent and then multiplying by the hourly composite rate of the crew, it is much simpler to increase the hourly composite pay rate of the crew by 5 percent (that is, multiply it by 1.05) in order to obtain the adjusted rate, and then to apply this figure directly to the various manhour units which appear in the tables for a given operation. For example, let us assume that our considered project has a certain amount of formwork and that we will need four (4), eight-man crews and that only one general foreman will be needed to head the four crews: General Carpenter Foreman $3.94 per hour Carpenter Foreman $3.69 per hour Journeyman Carpenter $3.44 per hour Laborer $1.95 per hour Truck Driver $2.03 per hour
Note: General foreman and foreman are dead weight since they do not work with their tools; however they must be considered and charged to the composite crews.

5. Excellent 91-100% Before an overall productivity efficiency is obtained, the estimator must first arrive at estimates of six important production elements that will affect the efficiency of

CREW FOR COMPOSITE RATE: One General Foreman One Foreman Five Carpenters Two Laborers One Truck Driver Total for 60 hours
$214.32

WHAT THE TABLES COVER


The author of these manhour tables points out specifically what has been taken into account in determining these values. The user should study the notes that accompany each table. Also, it is to be especially noted that the tables presented include allowances for labor involved for handling, hauling and installing where applicable, but do not cover the cost of the materials and equipment itself; nor do they include any allowance for overhead cost or profit.

2 hours @ $3.94$ 7.88 8 hours @ $3.69$ 29.52 8 hours @ $3.44$137.60 8 hours @ $1.95$ 31.20 4 hours @ $2.03$ 8.12 $214.32

60 = $3.572 composite manhour rate

For the project under consideration, with the productivity efficiency rated at 65 percent, the manhour rate would be evaluated by multiplying $3.572 by 1.05, which equals $3.75: composite rate for 65 percent productivity. Simply by multiplying the number of manhours estimated for a given block or item of work by the arrived at composite rate, a total estimated direct labor cost, in dollar value, can easily and accurately be obtained, whether it be now or ten years from now and for any geographical location in the world.

The labor unit tables on this and the following pages are reprinted from Estimators General Construction Manhour Tables copyrighted 1961 by Gulf Publishg Company, Box 2608, Houston 1, Texas.

Footing & Heavy Mat Forms


MANHOURS PER SQUARE FOOT Footing form manhours are based on using 2-inch by 12-inch material properly braced and anchored. If footing height is to be greater than one foot, add twenty-five percent to manhours for each additional foot or fraction. Assume heavy mat forms to be made of 2-inch material at least 3 feet high. If mats are to be greater than 3 feet in height, add 10 percent for each additional foot or fraction. Manhours in all of these tables are for initial set-up of one use. If forms are to be re-used, eliminate manhours for fabrication and apply Re-Use Factor manhours on page 5. Manhours in these tables do not ever include the placement or setting of anchor bolts or miscellaneous embedded steel items. See respective tables for these charges. Item Continuous Wall Type Fabricate Erect Strip & clean Total Spread Type Fabricate Erect Strip & clean Total Heavy Mat or Pile Cap Fabricate Erect Strip & clean Total Carpenter

Manhours Laborer Truck Driver .001 .001 .002 Total

.030 .026 .008 .064

.008 .008 .015 .031

.038 .035 .024 .097

.038 .029 .008 .075

.008 .015 .015 .038

.001 .001 .002

.046 .045 .024 .115

.035 .054 .008 .097

.010 .022 .023 .055

.001 .001 .002

.045 .077 .032 .154

Manhours

Foundation, Tilt-Up Walls& Grade Beams


MANHOURS PER SQUARE FOOT Manhours are based on the use of plyform material with studs and whalers of 2-inch material properly placed and the necessary holes drilled for form ties where required. Grade beam form manhours are for side forms only, with the assumption that ground will form the bottom of beam. Tilt-up wall forms are based on being fabricated and placed on level accessible location.

Item Grade Beams Fabricate Erect Strip & clean Total

Carpenter

Laborer

Truck Driver .001 .001 .002

Total

.023 .036 .008 .067

.008 .011 .015 .034

.031 .048 .024 .103

Foundation or Basement Walls Fabricate .038 Erect .042 Strip & clean .007 Total .082 Tilt-Up Walls Fabricate Erect Strip & clean Total

.007 .011 .015 .033

.001 .001 .002

.040 .054 .023 .117

.030 .026 .008 .064

.008 .008 .015 .031

.001 .001 .002

.038 .035 .024 .097

Manhours Item Carpenter Laborer Truck Driver .001 .001 .002 Total

Wood Pier Forms


MANHOURS PER SQUARE FOOT Manhours are for the use of plywood fabricated forms with 2-inch by 4-inch wood clamps or metal clamps as the case may be and include all necessary bracing and anchoring.

Using 2X4 Lumber Clamps Fabricate .030 Erect .026 Strip & clean .008 Total .064 Using Metal Clamps Fabricate Erect Strip & clean Total

.008 .008 .015 .031

.038 .035 .024 .097

.038 .029 .008 .075

.008 .015 .015 038

.001 .001 .002

.046 .045 .024 .115

Manhours

Metal Wall Forms for Continuous Foundations


MANHOURS PER SQUARE FOOT Manhours are based on the installation of prefabricated metal panel forms with the necessary whalers, bracing and anchors made of 2-inch materials. Re-use Factor for re-oiling of forms should be applied for each re-use of forms.

Item

Carpenter

Laborer

Truck Driver .002 .002 .004

Total

Foundation Walls to 8' High Erect & brace .053 Strip & clean .011 Total .064 Foundation Walls 8' to 12' High Erect & brace Strip & clean Total .051 .010 .061

.021 .023 .044

.076 .036 .112

.020 .022 .042

.002 .002 .004

.073 .034 .107

Manhours Item Carpenter Laborer Truck Driver .001 .001 .002 Total

Fiber Tube Pier Forms


MANHOURS PER LINEAR FOOT Manhour units cover the complete installation of fiber tubing as listed, including the fabrication and installation of necessary 1- and 2-inch planking for bracing and anchoring and the stripping of all items after initial concrete set. 12" Round Fabricate & erect Strip Total 24" Round Fabricate & Erect Strip Total 30" Round Fabricate & Erect Strip Total 30" Round Fabricate & Erect Strip Total .050 .008 .058 .008 .008 .016

.059 .017 .076

.052 .008 .060

.008 .008 .016

.001 .001 .002

.061 .017 .078

.054 .008 .062

.008 .008 .016

.001 .001 .002

.063 .017 .080

.056 .008 .064

.008 .008 .016

.001 .001 .002

.065 .017 .082

Manhours Item Carpenter Laborer Truck Driver .003 .003 .006 Total

Metal Wall Forms for Continuous Above Grade Walls


MANHOURS PER SQUARE FOOT Manhours are based on the installation of prefabricated metal panel forms with the necessary whalers, bracing and anchors made of 2-inch materials. Re-use Factor for re-oiling of forms should be applied for each re-use of forms. Manhours in this and following tables do not include scaffolding allowance.

Walls Ground to 8' High Erect & Brace Strip & clean Total Walls 8' to 16' High Erect & Brace Strip & clean Total Walls 16' to 20' High Erect & Brace Strip & clean Total

.059 .012 .071

.023 .031 .054

.085 .046 .131

.066 .014 .080

.026 .035 .061

.003 .003 .006

.095 .052 .147

.078 .017 .095

.031 .041 .072

.003 .003 .006

.112 .061 .173

Manhours Item Carpenter Laborer Truck Driver .002 .002 .004 Total

Continuous Wood Wall Forms


MANHOURS PER SQUARE FOOT Manhours are based on the use of plywood panels with 2-inch studs and whalers properly placed and the necessary drilled holes for form ties as required. If forms are to be re-used, eliminate fabrication manhours and apply Re-use Factor manhours. Walls Ground to 8' High Fabricate Erect Strip & clean Total Walls 8' to 16' High Fabricate Erect Strip & clean Total Walls 16' to 20' High Fabricate Erect Strip & clean Total .030 .045 .007 .082 .008 .012 .029 .049

.038 .059 .038 .135

.030 .051 .009 .090

.008 .013 .033 .054

.002 .002 .004

.038 .066 .044 .148

.030 .060 .010 .100

.008 .016 .039 .063

.002 .002 .004

.038 .078 .051 .167

Re-Use Factors
Re-use factor manhours are average for the minor replacement or repair of all types of wood forming. The manhours shown should be substituted for the initial fabrication manhours for all form work, in accordance with its estimated re-uses. If major repairs are required for reuse of form work, it should be charged at initial fabrication cost for that particular type of form work. Manhours Item Repairs First Re-use Repairs Second Re-use Repairs Third Re-use Repairs Subsequent Re-uses Oiling after each use Carpenter .01 .02 .03 .04 Laborer .003 .004 .006 .007 .005 Total .013 .024 .036 .047 .005

Manhours Item Laborer Carpenter Oper. Engr. .03 .03 Oiler Total

Footings
MANHOURS PER CUBIC YARD Manhours include complete placement and vibration of concrete for the items listed. Manhours in this and following tables do not include necessary craft stand-by time, fabrication of special ramps or finishing of concrete.

Continuous Wall Type Chute Buggies Crane & bucket Conveyor & buggy Spread Type Footings Chute Buggies Crane & bucket Conveyor & buggy Heavy Mat or Pile Cap Chute Buggies Crane & Bucket

.46 .60 .81 .70

.03 .03

.03

.49 .60 .87 .73

.53 .70 .88 .79

.04

.03 .03

.06

.57 .70 .94 .82

.35 .75 .38

.05

.06

.06

.40 .75 .50

Manhours Item Grade Beams Chute Buggies Crane & bucket Conveyor & buggy Laborer Carpenter Oper. Engr. _ .03 .07 Oiler Total

Foundation Walls & Grade Beams


MANHOURS PER CUBIC YARD Manhours include necessary set-up, placement and vibration of concrete.

.55 .91 .94 .91

.04

.03

.59 .91 1.00 .98

Foundation or Basement Walls Chute .55 Buggies 1.00 Crane & bucket .99 Conveyor & buggy 1.00

.04

.04 .07

.04

.59 1.00 1.07 1.07

Manhours

Piers
MANHOURS PER CUBIC YARD Manhours include set-up time and the placement and vibration of concrete for square and round piers as described. Additional allowance has been given to the placement of concrete in round piers due to the fact that additional care must be taken in this type of formwork.

Item Square Piers Chute Buggies Crane & bucket Conveyor & buggy Round Piers Chute Buggies Crane & bucket Conveyor & buggy

Laborer

Carpenter

Oper. Engr. _ .06 .10

Oiler Total

.70 .96 1.02 .96

.05

.06

.75 .96 1.14 1.06

.74 1.00 1.07 1.00

.05

.06 .11

.06

.79 1.00 1.19 1.11

Manhours Item Walls Ground to 8' High Hoist & buggies Crane & bucket Crane, bucket & buggies Conveyor & buggies Walls 8' to 16' High Hoist & buggies Crane & bucket Crane, bucket & buggies Walls 16' to 20' High Hoist & buggies Crane & bucket Crane, bucket & buggies Carpenter Laborer Truck Driver .07 .09 Total

Above Grade Walls


MANHOURS PER CUBIC YARD Manhours are for the placing and vibration of concrete for the described walls. Manhours do not include the fabrication, erection or dismantling of hoist or the finishing of concrete.

.88 .62 .68 .59

.16 .07 .09 .07

1.04 .76 .86 .66

1.17 .83 .91

.16 .07 .09

.07 .09

1.33 .76 1.09

1.46 1.04 1.14

.16 .07 .09

.07 .09

1.62 1.18 1.32

Manhours Item Carpenter Laborer Truck Driver .001 .001 .002 Total

Wood Column Forms


MANHOURS PER SQUARE FOOT Manhours include all necessary labor for the actual fabrication, erecting and stripping of exterior and interior columns as outlined using plywood side with 1- and 2-inch planking for necessary clamps, bracing and anchoring.

Exterior Columns Fabricate Erect Strip & clean Total Interior Columns Fabricate Erect Strip & clean Total

.029 .052 .010 .091

.013 .026 .026 .065

.042 .079 .037 .158

.036 .065 .010 .111

.013 .033 .026 .072

.001 .001 .002

.049 .099 .037 .185

Manhours Item 12" Round Fabricate & erect Strip Total 24" Round Fabricate & erect Strip Total 30" Round Fabricate & erect Strip Total 36" Round Fabricate & erect Strip Total Carpenter Laborer Truck Driver .001 .001 .002 Total

Fiber Tube Column Forms


MANHOURS PER LINEAR FOOT Manhours include time limitations for the complete fabrication and erection of 1- and 2-inch materials for bracing and anchoring as well as the erection of all fiber tubing, bracing and the removal of anchoring and stripping of all components after initial concrete set.

.040 .006 .046

.006 .006 .012

.047 .013 .060

.042 .006 .048

.006 .006 .012

.001 .001 .002

.049 .013 .062

.046 .006 .052 .050 .006 .056

.006 .006 .012 .006 .006 .012

.001 .001 .002 .001 .001 .002

.053 .013 .066 .057 .013 .070

Manhours Item Carpenter Laborer Truck Driver .001 .001 .002 Total

Radial & Retaining Wood Wall Forms


MANHOURS PER SQUARE FOOT Manhours are based on the use of plywood panels with 2-inch studs and whalers properly placed and the necessary drilled holes for form ties as required.

Radial Walls to 4' High Fabricate Erect Strip & clean Total Radial Walls 4' to 12' High Fabricate Erect Strip & clean Total Retaining Wall to 10' High Fabricate Erect Strip & clean Total

.049 .064 .010 .123

.010 .017 .022 .049

.059 .082 .033 .174

.059 .077 .012 .148

.012 .020 .026 .058

.001 .001 .002

.071 .045 .024 .115

.036 .047 .007 .090

.007 .013 .016 .036 Manhours

.001 .001 .002

.043 .061 .024 .128

Columns
MANHOURS PER CUBIC YARD Manhours are for the placing and vibrating of the listed types of columns. Additional allowance has been given to the placement of round columns due to the fact that additional care must be taken in this type of formwork. Manhours do not include craft standby time, the fabrication, installation and dismantling of hoist or the finishing of concrete.

Item Exterior Square Columns Hoist & buggies Crane, bucket & buggies Interior Square Columns Hoist & buggies Crane, bucket & buggies Round Columns (Interior) Hoist & buggies Crane, bucket & buggies Column Caps Hoist & buggies Crane, bucket & buggies

Laborer

Oper. Engr. .14 .08

Oiler r .08

Total

1.43 .99

1.57 1.15

1.79 1.24

.16 .10

.10

1.95 1.44

1.87 1.30

.17 .11

.11

2.04 1.52

Tilt-Up Concrete Panels


MANHOURS PER SQUARE FOOT Manhours include the placement and vibration of concrete and the finishing, curing and erection of panels. Manhours are based on the placing of concrete in pre-erected forms on a flat level location easily accessible for both placing and erection operations. Placing concrete manhours are based on placing concrete direct from ready mix truck into forms. Manhours do not include the fabrication, erection or stripping of forms.

2.40 1.95

.15 .12

.12

2.55 2.19

Manhours Item Pre-Cast Panels 6" Thick Place Concrete Finish & Cure Erect Panels Laborer Cement Finisher .015 Iron Worker .120 Total

.147 .002

.147 .017 .120

Manhours Item Square Beams Fabricate Erect Strip & clean Total Shored Beam & Girder Fabricate Erect Strip & clean Total Carpenter Laborer Truck Driver .001 .001 .002 Total

Wood Beam & Girder Forms


MANHOURS PER SQUARE FOOT Manhours are based on the use of plywood and 1- and 2-inch planking materials all properly braced and anchored. Sufficient time has been allowed to cover the outlined operations and necessary items of labor operations.

.038 .071 .008 .117

.011 .026 .023 .060

.049 .098 .032 .179

.032 .088 .017 .137

.013 .035 .045 .093

.001 .001 .002

.045 .124 .063 .232

Hung from Steelbeam & Girder Fabricate .027 Erect .073 Strip & clean .014 Total .114

.011 .029 .037 .077 Manhours

.001 .001 .002

.038 .103 .052 .193

Item

Laborer

Carpenter

Radial & Retaining Walls


MANHOURS PER CUBIC YARD Manhours include set-up time and the placement and vibration of concrete for the items outlined. Manhours do not include craft standby time, the fabrication of chutes or the finishing of concrete.

Oper. Engr. .07

Oiler Total

Radial Walls to 4' High Chute Crane & bucket

.55 .65

.04

.07

.59 .79

Radial Walls 4' to 12' High Crane & bucket .85 Conveyor .70 Retaining Wall to 10' High Crane & Bucket 1.10 Conveyor .90

.09 .07

.09

1.03 .77

Manhours

.10 .09

.10

1.30 .99

Item

Laborer

Carpenter

Oper. Engr. .19 .11

Oiler Total

Floor Slabs, Beams & Girders


MANHOURS PER CUBIC YARD Manhours include set-up time and placement and vibration of concrete as outlined. Manhours do not include hoist or chute fabrication or hoist erection or finishing of concrete.

Square Beams & Girder Hoist & buggies Crane ,bucket & buggies Elevated Floor Slabs Hoist & buggies Crane ,bucket & buggies Ground Floor Slab Chute Buggies Crane & Bucket

1.88 1.43

.11

2.07 1.65

1.56 1.09

.16 .10

.10

1.72 1.29

.41 .87 1.10

.04

.10

.10

.45 .87 1.30

Manhours Item Carpenter Laborer Truck Driver .001 .001 .002 .001 .001 .002 .001 .001 .002 Total

Wood Forms for Elevated Slabs


MANHOURS PER SQUARE FOOT Manhours are based on the use of plywood and properly sized timbers as required for bracing and supporting. Sufficient time has been allowed to cover the outlined operations and necessary items of labor operations.

Flat Slab with Wood Shores Make-up & erect Strip & clean Total

.067 .004 .071

.036 .036 .072 .030 .036 .066 .009 .020 .029 Manhours

.104 .041 .145 .074 .041 .115 .051 .026 .077

Flat Slab with Adjustable Shores Make-up & erect .043 Strip & clean .004 Total .047 Flat Slab Hung from Steel Fabricate & erect Strip & clean Total .041 .005 .046

Item

Carpenter

Laborer

Truck Driver .002 .002 .002 .006 .002 .002 .002 .006

Total

Metal Floor Pan Forms


MANHOURS PER SQUARE FOOT Manhours are based on the installation of prefabricated metal pan forms with the necessary size timber supports.

Metal Pan with Adjustable Shores Cut & erect lumber .040 Erect pans & shores .010 Strip & clean Total .050 Metal Pan with Wood Shores Cut & erect lumber .050 Erect pans & shores .010 Strip & clean Total .060

.023 .015 .018 .056 .040 .015 .018 .073 Manhours

.065 .027 .020 .112 .092 .027 .020 .139

Item

Carpenter

Laborer

Truck Driver .01 .01 .01 .01 .01 .01 .01 .01

Total

Equipment Foundations Simple Layout


MANHOURS PER SQUARE FOOT Manhours are based on the fabrication and installation of 2-inch materials for formwork to 18 inches high, and plywood sheathing for forms to 4 feet high, all properly braced and anchored in place. A simple layout is that of a small square pad placed either integral with floor or over preset dowels left purposely in preplaced floor for this reason.

Square Pads 6" to 18" High Ground Floor Build in place .14 Strip & clean .01 Total .15

.03 .03 .06

.18 .04 .22 .20 .05 .25 .22 .06 .28 .24 .07 .31

Square Pads 6" to 18" High Elevated Floors Build in place .16 .03 Strip & clean .01 .04 Total .17 .07 Square Pads to 4' High Ground Floor Fabricate & erect .17 Strip & clean .02 Total .19 Square Pads to 4' High Elevated Floors Fabricate & erect .19 Strip & clean .02 Total .21 .04 .04 .08 .04 .05 .09

Equipment Foundations Complex Layout


Bulky, Offset, Skewed and Angled MANHOURS PER SQUARE FOOT Complex foundation manhours are average for all sizes and shapes and are based on the use of 1- and 2-inch planking, plywood sheathing and minor sheet metal cuts and bends. A complex layout is that of a large and bulky foundation with many offsets, skews and angles, such as a foundation for a turbo-generator.

Manhours Item Carpenter Laborer Truck Driver .02 .02 Total

Average All Heights & Sizes Fabricate & erect Strip & clean Total Tank Cradle Forms Build in place Strip & clean Total

.20 .05 .25

.08 .12 .20

.30 .17 .47

.13 .01 .14

.04 .03 .07

.01 .01 .02

.19 .04 .23

Manhours Item Unload, Sort & Pile Rods Fabricate Cut and Bend 1/2' round and larger 3/8' round and smaller Place loose without tieing 3/4" round or larger 5/8" round and smaller Place and Tie Rods Walls, columns, etc. Floors Average All Operations All sizes without tieing With tieing Item Welded Wire Mesh Cut & Place Per Ton 1.75 6.00 11.48 7.25 8.78 16.50 22.10 18.51 29.79 Manhours per 100 sq ft .80 Per cwt 0.0875 0.3000 0.5740 0.3625 0.4390 0.8250 1.1050 0.9250 1.4900

Rods & Mesh


MANHOURS PER UNITS LISTED The manhours cover necessary time for the various operations listed.

Hook Type Anchor Bolt Installation


MANHOURS EACH Manhours are based on overall length of anchor bolt from end to end including hook and are average for all heights. Manhours are for installation of template and bolt, or bolt and sleeve, as the case may be, for the size and length outlined. All bolts 78 inch and larger are assumed to be sleeved and those smaller than 78 inch round are assumed to be without sleeves. Manhours in this and following tables do not include fabrication of bolts or field engineering time spent aligning and checking bolts. For sizes not listed, take the next highest listing.

Size 0' 8
1 3 1 5

Manhours Each For Overall Length 1' 0" .15 .15 .15 .20 .20 1' 6" .20 .20 .25 .25 .28 .40 .40 .48 .50 .55 2' 0" .20 .20 .28 .28 .30 .43 .45 .50 .55 .58 .65 .70 .75 2' 6" .30 .35 .45 .48 .50 .55 .60 .68 .73 .78 3' 0" .33 .38 .48 .50 .53 .58 .65 .70 .75 .78 3' 6" .50. .53 .5 .60 .668 .75 .78 .80 4' 0" .53 .58 .65 .70 .73 .78 .80 .85

4"

.15 .15 .15 .15 .18

8"

2"

8"

3 7

4"

8"
1

1" 1 4" 1 2" 1 4" 2" 2 4" 2 2"


1 1 3 1

Size

Manhours Each For Overall Length 4' 6 5' 0" .98 1.00 1.10 1.15 1.25 1.28 1.33 1.40 5' 6" 1.10 1.15 1.25 1.28 1.33 1.40 1.45 1.48 6' 0" 1.15 1.25 1.28 1.33 1.40 1.45 1.48 1.53 6' 6" 1.23 1.28 1.30 1.38 1.43 1.50 1.55 1.60 7' 0" 1.30 1.38 1.40 1.43 1.50 1.58 1.60 1.63 7' 6" 1.35 1.40 1.45 1.48 1.55 1.60 1.63 1.68 8' 0" 1.40 1.54 1.50 1.58 1.60 1.65 1.68 1.70

Hook Type Anchor Bolt Installation


MANHOURS EACH Manhours are based on overall length of anchor bolt from end to end including hook and are average for all heights. All bolts listed are assumed to be sleeved. For sizes not listed in this and following tables, take the next highest listing.

8"
1

.90 .93 .95 .98 1.00 1.10 1.15 1.25

1" 1 4" 1 2" 134" 2" 2 4" 2 2"


1 1 1

Equipment Foundations
MANHOURS PER CUBIC YARD Manhours are for the placement and vibration of concrete for the items listed. Square pad manhours are based on placing of square pads to 4 feet high either integral with floor or over pre-set dowels on pre-placed floor. Offset, skewed or angled manhours are based on that of placing a large and bulky foundation with offsets or angles or both. Item Square Pads Crane & bucket Crane, bucket & buggies Offset, Skewed & Angled Crane & bucket Crane, bucket & buggies Laborer

Manhours Oper. Engr. .19 .25 Oiler r .19 .25 Total

1.50 2.00

1.88 1.50

2.44 3.25

.38 .50

.38 .50

3.20 4.25

Item

Manhours Cement Finisher

Integral Topping

Topping Finish
MANHOURS PER SQUARE FOOT Manhours are for topping finish and include mixing and stand-by time where required. Manhours do not include the placing and vibrating of main floors.

2" by hand

.029 .018 .068 .022

2" by machine

1" by hand 1" by machine Separate Topping


1

2" by hand

.036 .018 .068

2" by machine

1" by hand

Manhours Surface Finish Cement Finisher .045 .030 .015 .030 .001 .003 .003 .002 .250 Laborer .003 .025 Total .045 .030 .015 .030 .001 .003 .006 .002 .500

Concrete Finish
MANHOURS PER SQUARE FOOT Manhours are for the types of finish noted and include all necessary operations. In most areas, craft jurisdiction prevents laborers from helping cement finishers. Should this be the case, use total hours as listed for cement finisher hours. Carborundum Rub Remove Fins or Ties Point & Patch Machine Trowel & Hand Burnish Hand Steel Trowel Woodfloat Broom Screeding Off Cure & Protect Grout Column Bases (1")

PUBLICATION #C620129
Copyright 1962, The Aberdeen Group All rights reserved

Das könnte Ihnen auch gefallen