Beruflich Dokumente
Kultur Dokumente
JOHN SIMPSON
Chairman
PAGE
GENERAL
1.1 Tenderer to inform himself 3
1.5 Addenda 4
1.12 Sub-contractor(s) 5
MANHOLE LOCATION
GENERAL
[This approach to
the return of the 1.3Tender return
Tender may not be
appropriate. The
Engineer should One set of completed documents and
check the enclosures (Clause 1.2) shall be
Employer's returned in the envelope provided
procedures for without any added words or identifying
letting contracts]. marks thereon to the address stated in
[The period to be Clause 6.2 of the Schedule by the time
allowed for the and date stated in Clause 6.3 of the
Tenderer to prepare Schedule.
his tender should
normally be 4 The second set of the documents shall be
weeks. This period retained by the Tenderer.
may be altered if 1.4Interpretation and qualified tenders
the Engineer so
decides].
The Tenderer shall make no alteration to
the documents. Qualifications in the
nature of statements, or interpretation
of Contract Documents should, if
possible, be avoided by referring them
to the Engineer during the tender period
(Clause 6.1). A qualified tender will
not be admitted.
1.5Addenda
1.6Late tenders
1.8Fixed price
1.10Acceptance of tenders
1.11Arithmetical errors
1.12Sub-contractor(s)
MANHOLE LOCATION
1.14Sample work
2.1 Definitions 9
2.12 Nuisance 14
2.13 Accident 14
2.14 Insurance 15
2.24 Copyright 20
7
8
2. CONDITIONS OF CONTRACT
2.1Definitions
2.2Engineer's Representative
2.4Contract documents
2.5General obligations
� Highway Authority
�
Any other organisation as listed in
Clause 6.13.
2.5.5 The Contractor shall comply with the
MAFF guidance note "Precautions to
prevent the spread of Animal and Poultry
Diseases - Code of Practice for Civil
Engineers, Surveyors and Contractors's",
1974 together with the relevant Code of
Practice for the exercise of works
powers by water and sewerage undertakers
on land, approved by the Secretary of
State under Section 182 of the Water
Industry Act 1991.
[Under Item (c) the 2.6Acceptance, commencement, programme and
Engineer would contract period
normally certify
payment against
Bill Items. The 2.6.1 Within 21 calendar days after the
Engineer may wish written acceptance of his tender the
to make it the Contractor shall, if requested by the
Contractor's Engineer in Clause 6.5, submit to the
responsibility for Engineer for his approval a programme
locating the showing the way in which he proposes to
manhole covers. If carry out the Survey. The Engineer will
so this should be provide the Contractor with the
stated in Clause necessary drawings etc. to enable the
6.22]. programme to be achieved. The programme
shall indicate the times when the
Contractor will be working in streets.
2.8Employer's responsibilities
2.12Nuisance
2.13Accident
2.14Insurance
2.15Liquidated damages
22
Contractor.
2.19Forfeiture
23
2.20.1 The Employer shall be entitled
to terminate the Contract and to recover
from the Contractor the amount of any
loss resulting from any such termination
if the Contractor shall have practised
collusion in tendering for the Contract
or shall have employed any corrupt or
illegal practice in the obtaining or
execution of the Contract.
3.7 Traffic
3.8 Police notification
3.9 Manholes
3.13 Noise
3.14 Metric measurements
MANHOLE LOCATION
[The Contractor
should inform the
Engineer of any
request(s) for
additional
information to be
gathered during the
Contract by a third
party]
3. SPECIFICATION
GENERAL
3.1Extent of survey
3.2Location
3.3Survey units
3.4Survey vehicle
3.5Supply of water
3.7Traffic
3.8Police notification
3.9Manholes
3.11Advance notice
3.13Noise
3.14Metric measurements
MANHOLE LOCATION
3.16Employer's responsibilities
3.18Accuracy of inspection
33
(b)all manholes and ancillary structures shall be
shown and a note reference shall be provided.
3.19Base maps
34
The site check shall comprise a
resurvey of 5 manholes from each 100
record sheets submitted randomly
selected by the Engineer and checked
against the results obtained by the
Contractor in the initial survey. The
check shall include the reproving of all
associated pipework lengths. The
Contractor shall supply a survey team to
carry out the quality control check
under the supervision of the Engineer,
and a person appointed by the Contractor
as his representative.
[The Engineer
should complete the
Amount column in
the Dayworks
Schedule before
inviting tenders]
SECTION 4 - PREAMBLE TO THE BILL OF
QUANTITIES
GENERAL
MANHOLE LOCATION
GENERAL
4.2Stated quantities
4.4Rates to include
4.4.1 Rates shall be deemed to include
for complying with the whole of the
Contractor's obligations under the
Contract.
4.5Unpriced items
4.6Preliminary item
40
4.8.2 The Bill of Quantities has been prepared on the
basis that manholes are situated within the curtilage of
the public highway (ie in public roads, footpaths or
verges). Where the Contractor has to undertake surveys
which are not within the curtilage of the highway,
separate items have been included in the Bill of
Quantities to enable the Contractor to claim additional
payment in respect of any additional costs of access
and/or liaising with land owners or tenants.
4.9Working hours
41
by reason of traffic conditions or rates of flow which
cannot reasonably be dealt with by other means.
4.10Dayworks rates
4.10.2 The rates for dayworks shall include for all items
covered by the Bill rates.
4.10.3 Expenditure on dayworks will only be on the
instructions of the Engineer.
4.11Dayworks quantities
4.14Engineer's instructions
4.15Provisional items
4.15.1 Provisional items will only be used on the written
instruction of the Engineer.
4.16Fixed price
4.17Term contracts
4.18Parked vehicles
5.2 Dayworks 43
Summary 44
45
46
5.1
- Measured work
Total carried to
47
5.1 - Measured work (continued)
5.1.25 No.
Extra over items 5.1.13 to
5.1.16 for gaining access/
5.1.2liaising for manhole off Item
the public highway.
Manhole accessible by
conventional drive vehicle.
48
5.2 - Dayworks
5.2.2 10 hour
Day shift, Saturday shift
5.2.3
Day shift, 10 hour
Sunday/Statutory shift
5.2.4 Holidays
10 hour
Night shift, Monday shift
5.2.5 to Friday 10 hour
shift
5.2.6
Night shift, Saturday 10 hour
shift
5.2.7
Night shift, hour
5.2.8 Sunday/Statutory
Holidays hour
49
SUMMARY
Amount
� p
TOTAL �
------------
SECTION 6 - INFORMATION AND INSTRUCTION SCHEDULE
50
NUMBER
A. ADDRESSES 47
B. CALENDAR OF EVENTS 47
6.5 Programme 47
6.10 Employer 49
6.11 Engineer 49
6.12 Location of survey 49
6.14 Samples 50
D. FINANCIAL INFORMATION 51
51
6.23 Additional quality control procedures 52
G. STATEMENT 52
A. ADDRESSES
6.1 Enquiries about the
tender documents
shall be addressed to:
.......................................................................
52
.......................................................................
Tel No.:
.......................................................................
.......................................................................
.......................................................................
B. CALENDAR OF EVENTS
6.3 Time and last date for
return of tender
documents:
.......................................................................
* Delete as appropriate.
(ii) Subject to sewer availability, the
Survey is to be carried out in the following order:
(leave blank if not applicable).
.......................................................................
.......................................................................
6.6 The Contractor will be required to commence the Survey
53
within:
........................................(Tick as appropriate).
NOTE:
.......................................................................
.......................................................................
.......................................................................
.......................................................................
etc.)
.......................................................................
.......................................................................
.......................................................................
55
6.13 Liaison arrangements. (This item may be left blank
at the time of Tender but must be completed on the award
of the Contract):
..............................................................
..............................................................
Tel:
..............................................................
..............................................................
..............................................................
Tel:
..............................................................
..............................................................
..............................................................
..............................................................
..............................................................
6.14 The Tenderer shall provide the following samples
.................................................................
56
..................................................................
..................................................................
..................................................................
..................................................................
D. FINANCIAL INFORMATION:
Survey
�....................
Survey Report
�....................
57
6.18 The minimum value of each contract to
be listed under the references in the statement of
experience shall be �.................
E. OPERATIONS INFORMATION
..................................................................
.......................................................................
.......................................................................
.......................................................................
.......................................................................
.......................................................................
.......................................................................
.......................................................................
58
.......................................................................
.......................................................................
.......................................................................
.......................................................................
.......................................................................
.......................................................................
F. GENERAL
.......................................................................
.......................................................................
.......................................................................
.......................................................................
.......................................................................
.......................................................................
.......................................................................
.......................................................................
.......................................................................
.......................................................................
G. STATEMENT
59
model contract document approved for use by the Water
Services Association Sewers and Water Mains Committee in
1993, except as follows:
Clause No.
Change Made.
.........................................................
.........................................................
.........................................................
.........................................................
.........................................................
.........................................................
.........................................................
.........................................................
..........................................................
.........................................................
Signed: ............................................
Designation: .................................
Date: .............................................
H. MANHOLE SURVEY
(c) Level each manhole cover frame (at the lowest point
on its
upper surface). Y/N*
60
detail and pipe
length details as indicated in Section 3.1. Y/N*
(l) Additional
items:.................................................................
.......................................................................
.......................................................................
.......................................................................
.......................................................................
.......................................................................
.......................................................................
.......................................................................
.......................................................................
.......................................................................
.......................................................................
.......................................................................
61
.......................................................................
CONTRACT: .........................
SURVEY WORKS
To: ..........................................................
................................................................
................................................................
................................................................
Gentlemen,
Having examined the documents for the above mentioned Survey,
we offer to undertake the Survey in conformity with the
drawings, Conditions of Contract, Specification, Bill of
Quantities and Schedule for such sum as may be determined in
accordance with the Contract.
62
Yours faithfully
................................................ Signature
Duly Authorised Signatory
...................................................... Status
........................................................ Date
Name of Firm:
...............................................................
Registered address:
................................................................
................................................................
.
................................................................
Address for
correspondence:
................................................................
(if different
from above)
................................................................
................................................................
................................................................
Telephone No.
................................................................
63
64
SECTION 8 - NON-COLLUSIVE TENDERING CERTIFICATE
(to be completed by Tenderers)
.......................................................................
Signature
Duly Authorised Signatory
.......................................................................
Status
.......................................................................
Date
Name of Firm:
................................................
Registered Address:
................................................
65
................................................
................................................
Telephone No.:
................................................
66
67
APPENDICES
(g)
Sources of Information
68
69
APPENDIX A - ACKNOWLEDGEMENT OF RECEIPT OF
TENDER DOCUMENTS
Contract:
.......................................................................
I/We acknowledge receipt of the following Tender Documents
relating to the above.
1. Instructions to Tenderers.
2.
General Conditions of Contract.
3. Specification.
Date......................... Signed:
..................................................
Director/Partner/Secretary
Tenderer's Name:
....................................................
....................................................
....................................................
....................................................
.................Post Code...................
Telephone No:
....................................................
70
71
APPENDIX B - ORDNANCE SURVEY MAPS AND PLANS
The 1:1250 scale plan is based on the national grid and ground
features are shown to scale. The plans show administrative
boundaries, parliamentary boundaries, and relief by means of
bench marks and spot heights. The series forms the largest
scale published by the Ordnance Survey and it is intended that
they will cover all towns with a population of above 20,000
together with a number of other urban areas. Each plan
represents an area of 500m square and carries the national
grid at 100m intervals (actual size 0.4m x 0.4m).
The 1:2500 national grid series will eventually cover the
whole of Great Britain other than moorland and mountain areas.
It is similar to the 1:1250 in format and where 1:1250 plans
exist it is a direct photograph reduction from the larger
scale.
72
update information in the area in which the Survey is to be
carried out.
83
84
APPENDIX C - GENERAL NOTES ON DRAINS AND SEWERS
INTRODUCTION
HIGHWAY DRAINS
(c)
Highway drains discharging into public sewers are
required to be notified to the Engineer and will only be
surveyed if the Engineer directs.
FORMER SECTION 24 SEWERS
85
access alleyways.
(a) These sewers are not vested in the undertaker and are not
to be surveyed unless the Engineer directs.
PRIVATE SEWERS
FIGURES
Field sheet
Pipeline details
Standard symbols for map overlays
DISTRICT TOWN/
COUNCIL PARISH
LOCATION
YEAR
CONSTRUCTED S 24 APPLIES DATE OF SURVEY
OTHER
COVER CIRCULAR SQUARE TRIANG RECT DIA
N N
88
FIELD SHEET
AREA .................................................................
LOCATION .............................................................
FSC GRAV P/MAIN SYPHON
SEWER ................................................................
COVER C S T R O HD MD LD
OPENING X
CONDITION OK W R Reset repl.......................
Red Slab Taper OPENING X OK AR
SHAFT ................................................................
ACCESS ...Step Irons Ladder....................OK AR........
......................................................................
OK AR
BENCHING/CHANNEL .....................................................
COVER LEVEL
INCOMING PIPES
IL Depth U/S M
A
B
C
D
E
F
G
D/S MH No. OUTGOING PIPES
X
Y
LOCATION SKETCH
PIPELINE DETAILS Length..................... Gradient........
Surface 2nd Road Main Road Trunk Road Rlwy Rld G
PIPELINE DETAILS
PIPE LENGTH
REFERENCE
CLASS
MATERIAL
REMARKS
APPENDIX E - MODEL WEEKLY REPORT FORM
M.H.'s Levelled
M.H.'s Plotted
Lampholes Surveyed
Overflows, Penstocks, Outfalls
M.H.'s in Private Land
Employees Signature.....................................................
APPENDIX F - REFERENCING OF BURIED OR UNCHARTED
MANHOLES TO NWC STANDARD
2.
100 METRE GRID CO-ORDINATE
The 100 metre grid in which the reference point occurs
is allocated a number of referring to the last digit of
the easting and northing of the 100 metre grid square.
For example, when the easting and the northing of the
square is 135 and 811 respectively, the first two digits
of the detail reference number will be 51.
. 5101
811
. 7001
. 6001
0 . 5003 . 7002
. .
5001 5002
81000
5 6 7
13500 136 137
Drawing No. A
APPENDIX G - SOURCES OF INFORMATION
2.
WATER AUTHORITIES ASSOCIATION/ WATER RESEARCH CENTRE.
Sewerage Rehabilitation Manual. WAA/WRc Second edition
1986.
8.
INSTITUTION OF CIVIL ENGINEERS. Arbitration Procedure.
ICE 1983.
Nick Orman
Technical Secretary
WSA/FWR Sewerage Working Group
WRc Swindon
Frankland Road
Blagrove
Swindon
SN5 8YF
##################################################################################
##################################################################################
##################################################################################
##################################################################################
##################################################################################
##################################################################################
##################################################################################
##################################################################################
##################################################################################
##################################################################################
##################################################################################
##################################################################################
##################################################################################
##################################################################################
##################################################################################
##################################################################################
#####