Sie sind auf Seite 1von 72

Use of Fly Ash for Road & Embankment Construction

Presentation by

Sudhir Mathur
Head Geotechnical Engineering Division Central Road Research Institute, New Delhi

Major Road Construction Programmes


National Highway Development Programme (NHDP) Pradhan Mantri Gram Sadak Yojna (PMGSY)

Necessity of alternate materials


Large quantities of construction materials required Scarcity of good quality aggregates / soil for road construction Waste and marginal materials like flyash Disposal and environmental problem

Properties of Fly ash


Major constituents - Oxides of silica, aluminum,
iron, calcium & magnesium

Favourable properties for embankment & road construction - Pozzolanic nature


Light weight, Non plastic High shear strength Ease of compaction Self hardening Amenable to stabilization High permeability Faster rate of consolidation

Utilization of Fly ash


Construction of embankments / backfills Stabilization of subgrade and sub-base Construction of semi-rigid / rigid pavements

Engineering Properties of Fly ash


Parameter Specific Gravity Plasticity Maximum Dry Density (gm/cc) Optimum Moisture Content (%) Cohesion (kN/m2) Angle of Internal Friction () Coefficient of Consolidation Cv (cm2/sec) Compression index Cc Permeability (cm/sec) Partcle Size Distribution (% of materials) Clay size fraction Silt size fraction Sand size fraction Gravel size fraction Coefficient of Uniformity Range 1.90 2.55 Non-Plastic 0.9 1.60 18-38 Negligible 300 - 400 1.75 x 10-5 - 2.01 x 10-3 0.05 0.4 8 x 10-6 - 7 x 10-4 1 10 8 85 7 90 0 10 3.1 10.7

Physical Characteristics for Flyash as Pozzolana

Physical Characteristics for Flyash as Pozzolana

Indian Roads Congress Special Publication 58 Guidelines For Use Of Flyash In Road Embankment
Published in 2001

Guidelines for Use of Fly ash in Road Embankments


These guidelines provide salient details regarding design and construction of road embankments using fly ash
Site investigations Characterization of materials Detailed design Clearing and grubbing Stripping and storing top soil Setting out Dewatering Compacting the ground supporting embankment Handling and transportation of fly ash Spreading and compaction

Fly Ash for Road Embankment


Earth Cover Bottom ash or Pond ash Earth Cover

Typical cross section of fly ash road embankment

Bituminous Top

Shoulder Granular Layer 0.5m minimum


FLYASH

Selected
Earth Cover

FLYASH

1-3m

FLYASH

Natural Ground Level

Typical cross section of fly ash road embankment

Approach Embankment for Second Nizamuddin Bridge at Delhi


Length of embankment - 1.8 km Height varies from 6 to 9 m Ash utilized - 1,50,000 cubic metre Embankment opened to traffic in 1998 Instrumentation installed in the embankment showed very good performance Approximate savings due to usage of fly ash is about Rs.1.00 Crore

Design Consideration
The following major factors weighted heavily while designing the fly ash embankment

Adverse site condition location of site in flood plain area Low specific gravity of fly ash- may lose strength under submergence Non availability of specific data and specifications of using fly ash as structural fill

Approach Embankment for Nizamuddin Bridge

Slope stability analysis of fly ash embankment (Different side cover thickness)
Details 6 m high embankment, 1 m side cover throughout 1.5 m side cover throughout 2 m side cover upto mid height and remaining portion 1 m cover 2 m side cover throughout Case I Factor of safety Case I -Case II 1.05

1.30 1.42

1.20 1.36

1.48

1.41

Fly ash saturated upto mid height

Case II Fly ash saturated upto top level

Approach Embankment for Second Nizamuddin Bridge at Delhi

Spreading of pond ash

Second Nizamuddin Bridge Approach Embankment

Compaction of pond ash

Stone pitching for slope protection

Second Nizamuddin Bridge Approach Embankment

Traffic plying on the embankment

Approach Embankment for Nizamuddin Bridge

Instrumentation Following instruments installed for monitoring performance of embankment Magnetic settlement gauges for settlement Pressure cells for base pressure Pore pressure transducers for pore water pressure measurement

Installation of pressure cells

Second Nizamuddin Bridge Approach Embankment

Installation of settlement gauge under progress

Approach Embankment for Nizamuddin Bridge

Inferences from instrumentation data No settlement of the embankment structure (fly ash fill) No pressure variation with in embankment body No change in saturation level of fly ash fill

Techno-Economic Advantages
Direct saving of about Rs.One Crore in second Nizamuddin Bridge project for PWD Additional savings to Vidyut Board, saving of precious top soil In road projects savings to the extent of 15-20 per cent can be achieved Savings depend on cost of transportation of fly ash

Fly ash Embankment from G.T Road to Kajouri chowk, Delhi


0.6 m x 0.8 m parapet wall Foot 1.2 path
m H.F.L 2.0 1 6m 2.3 m 0.5 m 1m 1.5 m 1.6 m 1.5 m 4.0 m

.3 m (drain) ((drain)

7.0 m

Existing carriage way Existing Embankme nt Stone pitching to be removed Ground level

Pond ash0.2 m

0.15 m, M15 concrete

Filter 0.2 m, thick

Weep holes at 12m c/c

Parameter bulk c

Pond ash 1.56 kg/cm2 0 33o

Earth cover 2.0 kg/cm2 0.15 kg/cm2 28o

Sub soil 1.8 kg/cm2 0 30o

Stone pitching, 0.3 m thick

Intermediate soil layers (0.2 m compacted thickness)

Sat.condition

Factor of safety With Earthquake Without Earthquake 1.7 1.35

At H.F.L Sudden drawdown

1.06 1.2

Filter material by the side of toe wall

Stone pitching on filter material

Drainage system in the embankment

USE OF POND ASH FOR ROAD EMBANKMENT


(Four-laning work on NH-6, Dankuni to Kolaghat, Km 17 to 72, West Bengal)

Four-laning work on NH-6, Dankuni to Kolaghat,

AGENCIES INVOLVED

National Highways Authority of India Client M/s ICT, India and SNC-LALALIN,Canada Consultant M/s Road builders (M) Shd.Bhd, Malaysia - Contractor

Four-laning work on NH-6, Dankuni to Kolaghat,

TYPICAL ROAD FEATURES/CONDITIONS OF THE PROPOSED ROAD

Length of road - 60 km Height of embankment - 2 to 4 m Water logged conditions Soft sub-soil conditions

Four-laning work on NH-6, Dankuni to Kolaghat,

Existing carriage way

Typical Cross-section of Existing Highway

Four-laning work on NH-6, Dankuni to Kolaghat,

EXISTING CONDITION OF ROAD

Four-laning work on NH-6, Dankuni to Kolaghat,

EXISTING CONDITION OF ROAD OTHER SIDE

Four-laning work on NH-6, Dankuni to Kolaghat,

PRELIMINARY INVESTIGATION AND ASSESSMENT OF SITE CONDITIONS Medium to High rainfall Water table is high Waterlogged conditions Subsoil generally weak
Silty clay or clayey soil up to 20 m depth SPT values in the range of 2 to 5 C = 0.25 kg/cm2, = 0o

Four-laning work on NH-6, Dankuni to Kolaghat,

NEED FOR ALTERNATIVE MATERIAL Earth proposed in contract document.


Earth requirement approx. 2.0 million cum.

Haul distance more than 100 km. High transportation cost Delays expected in the completion of the project

Four-laning work on NH-6, Dankuni to Kolaghat,

LABORATORY AND FIELD INVESTIGATIONS


Characterisation of soil and fly ash Sub-soil investigations Stability analysis with soil and fly ash as fill materials Evaluation of data to arrive at appropriate methodologies for construction

Four-laning work on NH-6, Dankuni to Kolaghat,

ARRANGEMENT FOR DEWATERING OF STAGNANT WATER

Four-laning work on NH-6, Dankuni to Kolaghat,

CONDITION OF THE GROUND AFTER DEWATERING

Four-laning work on NH-6, Dankuni to Kolaghat,

PROPOSED ALTERNATIVES FOR CONSTRUCTION

Median

Improved Subgrade of compacted thickness not less than 50 cm Granular sub-base Soil cover (1.5 m thick) Fly ash in compacted layers of 200 mm thickness 2m 2m

2 1

Min. 0.5 m

Existing embankment

Sand or bottom ash min. 0.5 m thick Temporary pond ash Proposed berm of pond ash bund after completion of embankment

Geotextile

Four-laning work on NH-6, Dankuni to Kolaghat,

SPREADING OF GEOTEXTILE OVER SOFT GROUND

Four-laning work on NH-6, Dankuni to Kolaghat,

SPREADING OF GEOTEXTILE OVER SOFT GROUND

Four-laning work on NH-6, Dankuni to Kolaghat,

SPREADING OF FLY ASH OVER GEOTEXTILE

Four-laning work on NH-6, Dankuni to Kolaghat,

SPREADING OF FLY ASH OVER GEOTEXTILE

Four-laning work on NH-6, Dankuni to Kolaghat,

COMPACTION OF FLY ASH OVER GEOTEXTILE LAID ON SOFT GROUND, (WORK ON THIS PROJECT IS IN PROGRESS)

Kalindi Road Project

SCPT Test In Progress

General Site Condition

Subsoil Investigation in Progress

Reinforced Fly ash Embankment


Fly ash - better backfill material for reinforced embankments Polymeric reinforcing materials - Geogrids, friction ties, geotextiles Construction sequence - similar to reinforced earth structures

Okhla Flyover Approach Embankment


First geogrid reinforced fly ash approach embankment constructed in the country Length of embankment - 59 m Height varied from 5.9 to 7.8 m Ash utilised - 2,700 cubic metre Opened to traffic in 1996 Performance has been very good

Okhla Flyover Approach Embankment


Facing Panels Filter M edium G eogrids

Pond Ash Fill

7.8 m to 5.9 m

7.8 m R einforced Foundation Mattress of B ottom ash

Erection of facing panels

Okhla Flyover Approach Embankment

Rolling of pond ash

Support provided to facing panels during construction

Okhla Flyover Approach Embankment

Laying of geogrids

Hanuman Setu Flyover Approach Embankment

Geogrid reinforced fly ash approach embankment Length of embankment - 138.4 m Height varied from 3.42 m to 1.0 m Opened to traffic in 1997

Reinforced Retaining Wall at Sarita Vihar Flyover

Sarita Vihar Flyover Approach Embankment


Length of embankment - 90m Max height - 5.25 m Embankment opened to traffic in Feb 2001 Polymeric friction ties used for reinforcement

Laying of friction ties

Sarita Vihar Flyover Reinforced Approach Embankment

Arrangement of friction ties before laying pond ash

Compaction of pond ash using static and vibratory rollers

Sarita Vihar Flyover Reinforced Approach Embankment

Compaction using plate vibrator near the facing panels

Design of Reinforced Flyash Embankment


Height of Wall 8m Reinforcing Material Geogrid Back Fill Soil and Flyash Design of Wall- BS 8006-1995 Checks made- Internal and External Stability - F.S. against Sliding - F.S. against overturning - F.S against bearing capacity - F.S. against rupture - F.S. against pullout

No of Layers = 16
7.4 6.8 6.2

No of Layers = 12

7 6.2
Vertical Sp acing (m)

Vertical Spacing (m)

5.6 5 4.4

5.4 4.6

Soil

3.8 3.4 3 2.6 2.2 1.8 1.4 1 0.6 0.2 4 6 8

Fly Ash

3.8 3.2 2.6 2 1.4 0.8 0.2 6 8

Length of geogrid (m)

Length of geogrid (m)

F.S. Sliding F.S. Overturning Bearing Pressure

1.97 4.10 259 KN/m2

2.18 4.50 179 KN/m2

Slope Failure of High Embankment of Noida- Greater Noida Expressway

Noida-Greater Noida Expressway

Salient features of site


Height of embankment varies from 3m to8m Approximately 23 km stretch Six Lane Carriageway with Median Side shoulders 1.5m Paved & 1m Unpaved Flyash covered with Good Earth

Cross-Section Proposed for NOIDAGREATER NOIDA Express Highway

Causes and types of Failure Heavy Runoff from six lane carriageway discharged water on side slopes Sandy Silty soil was used as cover without proper slope protection Severe Erosion on superelevated sections Absence of longitudinal kerb channel and chutes allowed water to drain off along slope

Types of Failure
Failures observed on both sides of slope More pronounced on d/s side Deep cavities were observed exposing fly ash at many locations Undermining caused caving in of road pavement

Causes of Failure
Heavy flow of water intersected side slopes inspite of grass turfing Deep pits in slope to provide foundation for crash barrier and electric poles Pits were loosely backfilled

Immediate Preventive Measures


Prevention of flow of water in side slopes by providing soil filled up bags through out the slope Filling of soil in erosion gullies Filling of soil filled bags in deep cavities

Long Term Remedial Measures


Compaction of Side Slopes Provision of Toe Walls Provision of Kerb Channel Provision of Chutes Provision of drains in Medians Provision of Stone Pitching along with Filter (Granular/Geotextile)

Remedial Measures

IRC Guidelines / Specifications


Guidelines available on pavement construction
IRC 60 Tentative guidelines for use of lime fly ash concrete as pavement base or subbase IRC 68 Tentative guidelines on cement fly ash concrete for rigid pavement construction IRC 74 Tentative guidelines for lean cement concrete and lean cement fly ash concrete as a pavement base or subbase IRC 88 Recommended practice for lime fly ash stabilised soil as base or subbase in pavement construction

Conclusions
Ideally suited as back fill material for urban/ industrial areas and areas with weak sub soils Higher shear strength leads to greater stability Design is similar to earth embankments Intermediate soil layers for ease of construction and to provide confinement Side slope erosion needs to be controlled by providing soil cover Can be compacted under inclement weather conditions Use of vibratory rollers is preferred

In road projects savings to the extent of 15-25 per cent can be achieved. Savings depend on cost of transportation of fly ash Coarse ash is suitable as a fill material, finer part of the ash (fly ash) collected in dry form can be used to replace cement Fly ash collection and handling techniques need to be improved Use of ash for all road projects in the vicinity of thermal power plant should be made mandatory Conservation of conventional construction materials is possible by adopting fly ash for road construction

Thank you

Das könnte Ihnen auch gefallen