Beruflich Dokumente
Kultur Dokumente
CONSTRUCTION
Date: 17/09/2011
Engineering Consultants:
Rev. A0
Main Contractor:
COYNE ET BELLIER
Bureau d'Ingnieurs Conseils
A0 Revision
17/09/11 Date
MLH Drafted
MBD Checked
MDC Approved
Main Contractor:
Engineering Consultants:
Engineering Consultants:
COYNE ET BELLIER
Bureau d'Ingnieurs Conseils
CONSTRUCTION
NG Dam - Monitoring of NG dam
Project Document Number: File Name: C-CO-C-AGD-TR-014-A0.doc
C-CO-C-AGD-TR-014-A0
THXP
Page i
TABLE OF CONTENTS
1. 2. 3.
INTRODUCTION REFERENCES MAIN INSTRUMENTS 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 1.10 General Water pressure vibrating wire cells (electrical piezometers) PC Stand pipe piezometers PZ and DPZ Pendulums (plumb-lines) - PLD and PLV Thermometers T Levelling studs LS Surface movement markers MM Joint opening device JM V-Notch weirs for seepage measurement - MW Reservoir water level
1 1 2 2 4 6 9 12 15 15 15 16 17 18 18 19 19 19 20 21 22 22 22 22 23
September 2011
PRINCIPLE OF THE MONITORING 2.1 2.2 2.3 a) b) c) d) e) f) g) h) Data to be collected Visual inspection Data processing Water pressure vibrating wire cells (electrical piezometers) PC Stand pipe piezometers PZ and DPZ Pendulums (plumb-lines) - PLD and PLV Thermometers T Levelling studs LS Surface movement markers MM Joint opening device JM V-Notch weirs for seepage measurement MW
Coyne et Bellier
C-CO-C-AGD-TR-014-A0.doc
THXP
Page ii
i) 3
23 24
MEASURING FREQUENCY
Appendix A: Monitoring system location Appendix B: Monitoring system - SISGEO Instruction Manual Appendix C: Devices Certificate Appendix D: Drilling and Verticality tests of Invert pendulums
C-CO-C-AGD-TR-014-A0.doc
Coyne et Bellier
September 2011
THXP
Page iii
TABLE OF FIGURES
Figure 1: Dam monitoring - Instrument layout (plan view) ...................................................... 3 Figure 2: Section PC1 on the RB, ch. 0+160.......................................................................... 4 Figure 3: Section PC2 on the RB, ch. 0+220.......................................................................... 4 Figure 4: Section PC3 on the spillway, ch. 0+273 .................................................................. 5 Figure 5: Section PC4 on the spillway, ch. 0+328 .................................................................. 5 Figure 6: Section PC5 on the LB, ch. 0+385 .......................................................................... 5 Figure 7: Section PC6 on the LB, ch. 0+434 .......................................................................... 5 Figure 8: PZ 0+070 on the RB ............................................................................................... 6 Figure 9: PZ 0+110 on the RB ............................................................................................... 6 Figure 10: PZ 0+160 on the RB ............................................................................................. 6 Figure 11: DPZ 0+196 on the RB........................................................................................... 6 Figure 12: PZ 0+217.5 on the RB .......................................................................................... 6 Figure 13: PZ 0+230.5 and DPZ 0+235 on the RB................................................................. 6 Figure 14: DPZ 0+300 on the spillway ................................................................................... 7 Figure 15: PZ 0+347.4 and DPZ 0+350 on the LB ................................................................. 7 Figure 16: PZ 0+419 and DPZ 0+416 on the LB .................................................................... 7 Figure 17: PZ 0+440 on the LB .............................................................................................. 7 Figure 18: PZ 0+468 on the LB ch. 0+468 ......................................................................... 8 Figure 19: PZ 0+510.5 on the LB ch. 0+510.50................................................................... 8 Figure 20: The Pendulums elevation layout ........................................................................ 9 Figure 21: Cartesian axis system at the top of the hole........................................................ 10 Figure 22: Borehole profile survey ....................................................................................... 10 Figure 23: Detection of wire position at Hi depth .................................................................. 10 Figure 24: Detecting of the X and Y components at i depth.................................................. 11 Figure 25: Example of hole free section diagram ................................................................. 11 Figure 26: Thermometers Layout ...................................................................................... 12 Figure 27: Thermometers at ch. 0+160 ................................................................................ 13 Figure 28: Thermometers at ch. 0+211 ................................................................................ 13 Figure 29: Thermometers at ch. 0+290 ................................................................................ 13 Figure 30: Thermometers at ch. 0+330 ................................................................................ 13 Figure 31: Thermometers at ch. 0+354 ................................................................................ 13 Figure 32: Thermometers at ch. 0+374 ................................................................................ 13 Figure 33: Thermometers at ch. 0+411 ................................................................................ 14 Figure 34: Thermometers at ch. 0+450 ................................................................................ 14 Figure 35: Typical section - topographic monitoring ............................................................. 16 Figure 36: Studs for precision levelling and V-Notch weirs- Upstream view ......................... 16 Figure 37: Surface movement markers and stud - Downstream view................................... 17 Figure 38: Layout................................................................................................................. 17 Figure 39: Vibrating-wire piezometers.................................................................................. 19 Figure 40: Four reading positions......................................................................................... 21 Figure 41: 3D-joint meters and Dial gauge........................................................................... 22
Table 1: Data to be collected ............................................................................................... 18 Table 3: Monitoring of the dam during the first year or during period of brutal variation of water level (>5m in one week) and/or water discharge on the spillway ................................ 24 Table 4: Monitoring of the dam after the first year and with stable water level...................... 25
C-CO-C-AGD-TR-014-A0.doc
Coyne et Bellier
September 2011
THXP
Appendix
1. INTRODUCTION
This technical note describes the monitoring system of NG Dam. Its aim is to be part of the dam Operation and Maintenance Manual, regarding the monitoring system. Nota: the yellow part of this report will be updated later on with the as built drawings.
2. REFERENCES
[1] Employers Requirements Part A Paragraph 5.3 NG Dam, Spillway and low level outlet [2] Employers Requirements Part B Paragraph 4, 4.15 Design of drainage features and pressure relief well [3] C-CO-D-AGE-SP-002 NG Dam Instrumentation Technical Specifications [4] C-CM-C-MNG-QA-060 NG Dam Instrumentation Qualification dossier [5] C-CO-D-ADG-CA-001 Definition of NG Dam Monitoring system [6] C-CO-C-AGD-EQ-003 to 028 NG dam instrumentation drawings [7] C-CO-E-AGD-EQ-005, 006, 013 to 017 As Built - NG dam instrumentation drawings [8] C-CO-C-AGD-TR-007 NG Dam First impounding of NG dam reservoir [9] C-CO-C-AGD-CA-002 NG Dam Stability analysis of the dam [10] C-CO-C-AGD-CA-011 - Modeling of the underground water flow through the foundation of the dam [11] C-CO-C-AGD-TR-009 NG Dam - Adaptation of monitoring equipments for beginning of the impounding [12] INTERNATIONAL STANDARD - ISO 1438:2008 - Hydrometry Open channel flow measurement using thin-plate weirs
C-CO-C-AGD-TR-014-A0.doc
Coyne et Bellier
September 2011
THXP
Appendix
Main instruments
1.1
General
The following measuring devices are to be considered to monitor the NG dam (see [6] and [7]):
Dam monitoring: 25 Pressure cells (vibrating wire piezometer) 10 piezometers, D/S toe open pipe 5 direct piezometers from gallery with manometer 3 Direct pendulums 3 Invert pendulums 42 Thermometers PC PZ DPZ PLD PLV T
Water control: 6 seepage measuring weirs (V-Notch) Water level indicator: o o U/S (intake powerhouse) Reservoir Water Level D/S (Spillway LB abutment) Tail Water Level RWL TWL MW
Each device, drain and block is clearly identified and numbered. Technical description of the devices, provided by the supplier Sisgeo can be found in appendix.
C-CO-C-AGD-TR-014-A0.doc
Coyne et Bellier
September 2011
THXP
Appendix
THXP
Appendix
1.2
Vibrating wire piezometers are installed in the foundation at the locations shown on the Figure 1. Foundation cells are installed in 90 mm diameter boreholes at elevations shown on Figure 2 to Figure 7. These piezometers are required to monitor uplift pressures on the dam foundation particularly during the first filling and subsequently. The majority of the pressure cells are located at the contact dam/foundation to monitor the pore-water pressure in the nearest vicinity of the NG dam. The few PC cells in the deeper foundation are required to monitor uplift pressures on the dam foundation and to confirm the efficiency of the grout curtain and the drainage of the deep foundation. At each chainage, switch terminal boxes are placed in order to connect the Pressure cells (6 boxes in the lower gallery, 2 boxes in the upper gallery).
Figure 3: Section PC2 on the RB, ch. 0+220 PC2-PC3 and PC2-PC1 shall be inverted
C-CO-C-AGD-TR-014-A0.doc
Coyne et Bellier
September 2011
THXP
Appendix
C-CO-C-AGD-TR-014-A0.doc
Coyne et Bellier
September 2011
THXP
Appendix
1.3
15 nos. stand pipe piezometers are installed to monitor the water pressure condition in NG Dam foundation, completing and cross-checking data recorded by the vibrating wire cells. Foundation stand pipe are installed in 120 mm diameter boreholes at elevations shown on Figure 8 to Figure 19. These piezometers are: drilled (vertical) from natural ground at downstream dam toe (10 units), and to be read with a water depth portable measuring probe PZ. drilled from the gallery, inclined, closed by a manometer, (5 units) DPZ.
Piezometers consist of a porous intake connected to the ground surface by a riser pipe. The pore water pressure can be observed by the use of different measuring system, in NG dam a manual system has been foreseen by means of sounding lead.
C-CO-C-AGD-TR-014-A0.doc
Coyne et Bellier
September 2011
THXP
Appendix
Figure 17: PZ 0+440 on the LB Figure 16: PZ 0+419 and DPZ 0+416 on the LB
C-CO-C-AGD-TR-014-A0.doc
Coyne et Bellier
September 2011
THXP
Appendix
C-CO-C-AGD-TR-014-A0.doc
Coyne et Bellier
September 2011
THXP
Appendix
1.4
Pendulum monitoring devices are installed in different profile of the dam, as shown on the Figure 1. Each profile shall be equipped with an inverted pendulum, allowing to control the displacement of the dam base compared to the foundation, and a direct pendulum to control the displacement of the top of the dam in comparison with the dam base. Total of 3 direct and 3 indirect pendulums, with reading devices are installed in the dam. One intermediated reading is performed on the direct pendulum at ch. 0+366. See Figure 20.
Figure 20: The Pendulums elevation layout After the installation of the casing of the invert pendulums, a verticality test was made in order to check the borehole profile survey. The most important aspect is to be sure that the steel wire doesnt touch the hole wall.
C-CO-C-AGD-TR-014-A0.doc
Coyne et Bellier
September 2011
THXP
Appendix
The following procedure was implemented: 1) At the top of the casing, two wires were installed in order to obtain a simple cartesian axis system that will give the position of the hole center.
Figure 21: Cartesian axis system at the top of the hole 2) A piece of steel with concrete inside, hung from a 3 mm diameter steel wire fixed at the gallery roof, was placed inside the hole. 3) The distance h between the pulley axis and the grid on the top of the hole was measured. 4) The weight was stopped every meter in the borehole. For each depth i, the measurements Xi and Yi, distance of the wire from the two axes, were recorded (see Figure 23).
5) On a graph, the position of the hole centers in the horizontal plane at each depths is calculated according to the following formula:
Cx i =
(h + H i ) X i h
and
Cy i =
( h + H i )Yi h
C-CO-C-AGD-TR-014-A0.doc
Coyne et Bellier
September 2011
THXP
Appendix
Figure 24: Detecting of the X and Y components at i depth 6) Once reported the center hole positions at each depth, its possible to draw the related circumferences. The area common to all circumferences is the hole free section and the coordinometer have to be mounted exactly over it.
C-CO-C-AGD-TR-014-A0.doc
Coyne et Bellier
September 2011
THXP
Appendix
1.5
Thermometers T
Thermometers installed in different sections of the dam, as shown on the drawings. The Thermometers read 2-hourly for the first week after installation, 6-hourly for the next three weeks and daily for the next five months. The reading is then on a weekly basis. The Thermometers control the peak temperature during setting of the concrete and later on allows to understand when the dam has reached is maturity, and that the temperature in its body is only influenced by the external seasonal and water from the reservoir temperatyre effect. Total of 42 Thermometers are installed in the dam (Temperature range: 5 - 50 C). Switch terminal boxes shall be placed in order to connect the Thermometers. See Figure 26 to Figure 34.
THXP
Appendix
C-CO-C-AGD-TR-014-A0.doc
Coyne et Bellier
September 2011
THXP
Appendix
C-CO-C-AGD-TR-014-A0.doc
Coyne et Bellier
September 2011
THXP
Appendix
1.6
Levelling studs LS
Lines of levelling studs are placed on different dam locations. Levelling studs are located, according to the drawings [6], as follows: 6 levelling downstream heel; 22 levelling along the galleries, one per block, fixed to the roof; 23 levelling studs on the dam crest (one per block).
A total of 51 levelling studs are provided (see Figure 35, Figure 36 and Figure 37).
1.7
Lines of survey points are located as defined on the drawing [6], at different places of the dam. The survey points are the supports for corner prisms able of reflecting signals from the total station and are securely fixed to the dam. The survey points are placed on the downstream face of the dam and on the dam crest at various emplacements (see Figure 35 and Figure 37). A total of 20 supports for corner prism and the total station device are provided. Two reference survey pillars are installed on both banks at the locations indicated on the drawing [6].
1.8
Joint opening devices (3D) allowing read the opening of dam vertical joints in three directions are installed in upper and lower gallery at the location indicated on the drawing [6]. The number of 3D joint opening device have been modified due to adjustment of the monitoring installation to allow impounding to proceed while monitoring apparatus are still under installation. A total of 34 3D joint meters are installed (21 in the upper gallery and 13 in the lower gallery).
C-CO-C-AGD-TR-014-A0.doc
Coyne et Bellier
September 2011
THXP
Appendix
1.9
The measurement canal bottom has a 1-3% slope towards the weir axis. perfectly vertical and perpendicular in relation to the canal axis.
The staff gauge is fixed at the wall of the stilling basin. The measurement will be carried out with manual readings of the H value, directly on the staff gauge. 6 (six) seepage measurements are installed in the dam galleries as shown on the drawing [6], in order to measure seepage in the dam (see Figure 35 and Figure 36): two seepage measurement on gallery weirs in the upper gallery; four seepage measurement on both sides of the sump pit in the lower gallery. The purpose of the weir is to measure the instantaneous flow. Level variations will be measured by means of water level measuring rod staff gauge (manual measurement of the basin variations).
Figure 36: Studs for precision levelling and V-Notch weirs- Upstream view
C-CO-C-AGD-TR-014-A0.doc
Coyne et Bellier
September 2011
THXP
Appendix
C-CO-C-AGD-TR-014-A0.doc
Coyne et Bellier
September 2011
THXP
Appendix
2.1
Data to be collected
The data collected for the monitoring are: manual measures: o 15 piezometers: 10 piezometers, D/S toe open pipe 5 direct piezometers from gallery with manometer o o o o o o 14 coordinates from the pendulums 51 levelling data (vertical displacement Z) 60 (= 3 X 20) topographic data (X, Y and Z) 102 (= 3 x 34) data from the 9 3Djoint-meters 6 seepage measuring weirs (V-Notch) water level upstream and downstream PZ DPZ PLD & PLV LS MM JM MW RWL & TWL
Electrical measures first with data logger: o o 25 Pressure Cells (vibrating wire piezometer) 42 Thermometers PC T
Meteorological data: o o minimum and maximum temperature daily rain Number of data 25 15 8 (2 x 4) 6 (2 x 3) 42 51 (Z) 60 (X, Y & Z) 33 (11 x 3) 6 2
Measure Uplift pressure Water table Displacement of the top of the dam in comparison with the dam base Displacement of the dam base compared to the foundation Temperature inside the RCC Topo: Vertical displacement Topo: Movement of the dam Monitoring of joints Leakage monitoring Water level US and DS
Device 25 pressure cells 15 piezometers 3 direct pendulums (included one intermediated reading) 3 invert pendulums 42 Thermometers 51 studs 20 movement markers 9 3Djoint-meters 6 seepage measuring weirs (V-Notch) 2 staff gauges Table 1: Data to be collected
Reading Automatic Manual Manual Manual Automatic Manual Manual Manual Manual Automatic & Manual
C-CO-C-AGD-TR-014-A0.doc
Coyne et Bellier
September 2011
THXP
Appendix
2.2
Visual inspection
Visual inspections consist in checking the galleries, the toe of the dam, the outlet of the joints and all other particular points in order to: detect coming of water and cracks, follow the behaviour of the drain curtain,
For the active drains, the drain where a discharges bigger than 2 l/min occurs should be regularly measured and be added as a monitored data in the inspection report.
2.3
Data processing
Prior the impounding, a first reading was done in order to confirm the formulas, coefficients and calibration parameters and in order to value their plausibility.
Figure 39: Vibrating-wire piezometers The square of the resonate frequency of the gauge wire is directly proportional to the pressure applied on the diaphragm. Two coils, one with a magnet, another with a pole piece, are located close to the wire. In use, a pulse of varying frequency is applied to the coils and this causes the wire to vibrate primarily at its resonant frequency. When excitation ends, the wire continues to vibrate and a sinusoidal signal, at the resonant frequency, is induced in the coils and transmitted to the readout unit where it is conditioned and displayed. To convert the instrument reading to pressure we have:
C-CO-C-AGD-TR-014-A0.doc
Coyne et Bellier
September 2011
THXP
Appendix
P=
Where P = Pressure in kPa;
L I0 S
Io = Frequency-squared (f) reading taken before installation with the instrument in air (Hz x 10-3); L S = = Instrument (f) reading (Hz x 10 -3); Linear conversion factor reported on the calibration certificate [digit/kPa].
WL = z +
Where WL = z P = = Water level in m.a.s.l;
P 9.81
WL = z +
Where WL = z P = = Water level in m.a.s.l;
P 10 .2
C-CO-C-AGD-TR-014-A0.doc
Coyne et Bellier
September 2011
THXP
Appendix
Xa = Xb =
With
Ya =
Yb =
X = axis upstream (-) / downstream (+) Y = axis right bank (-) / left bank (+)
The current readings on the 4 positions are Lx1, Lx2, Ly1, Ly2, Lx3, Lx4, Ly3 and Ly4 in mm.
Figure 40: Four reading positions The actual displacement of the pendulum is than calculated as follows (in mm):
Xt =
1 Lx1 + Lx 2 Lx + Lx 4 Xa + 3 X b 2 2 2 1 Ly1 + Ly 2 Ly 3 + Ly 4 Yt = Y + Y a b 2 2 2
Coyne et Bellier September 2011
C-CO-C-AGD-TR-014-A0.doc
THXP
Appendix
d) Thermometers T
The temperature of the RCC is directly measured by the readout in C.
e) Levelling studs LS
Prior impounding, one initial topographic operation (Z) was carried out. It is used as a reference data. The readings of the levelling studs in the Dam crest and in the gallery are made manually with the staff gauge and the total station, starting from one pillar and finishing in the second pillar.
Figure 41: 3D-joint meters and Dial gauge Once mounted on the wall, the joint metes feel the same changes of position of the crack being the supporting frame placed on one side of the crack and the prism on the other side.
C-CO-C-AGD-TR-014-A0.doc
Coyne et Bellier
September 2011
THXP
Appendix
The reading consists in periodical measurements of the position between prism and fram along three perpendicular axes. From the reading, the variations of the relative position in the space between the two sides of the crack are computed. Readings are taken by a dial gauge in mm (see Figure 41).
1m
The Kindsvater-Shen formula (see [12]) for triangular notch weirs is:
Q = Cd
Where Q = Cd = g = = flow [m3/s];
8 5/ 2 tan 2 g he 15 2
coefficient of discharge equal to 0.58; angle of the V-notch equal to 45 ; gravity acceleration [m/s] effective head (height of the water surface from the apex of the V) [m].
he =
C-CO-C-AGD-TR-014-A0.doc
Coyne et Bellier
September 2011
THXP
Appendix
MEASURING FREQUENCY
The first year and after the period of brutal variation of water level (>5m in one week) and/or water discharge on the spillway shall be strengthening monitored. Series of measures shall be tightened:
First years or period of brutal variation of water level (>5m in one week) and/or water discharge on the spillway
Devices
PC PZ & DPZ PLD PLV T LS MM JM MW RWL & TWL 25 pressure cells One series per week 15 piezometers 3 direct pendulums One series per week 3 invert pendulums 42 thermocouples 51 levelling studs 20 surface movement markers 11 3Djoint-meters One series per month
Frequency
One topographic and levelling campaign every month (during the first year)
4 seepage measuring weirs Two series per week 2 staff gauges One series per day
Table 2: Monitoring of the dam during the first years or during period of brutal variation of water level (>5m in one week) and/or water discharge on the spillway
C-CO-C-AGD-TR-014-A0.doc
Coyne et Bellier
September 2011
THXP
Appendix
After the first years, and during period when the water level is stable, we recommend to implement the following measurement frequency during the exploitation of the dam:
Frequency
4 seepage measuring weirs One series every 15 days 2 staff gauges One series per day
Table 3: Monitoring of the dam after the first years and with stable water level The notion of first years and the reading frequencies are tentative and will be updated as per actual site conditions by the engineering consultant in charge of the monitoring.
C-CO-C-AGD-TR-014-A0.doc
Coyne et Bellier
September 2011
THXP
Appendix
TABLE OF APPENDICES
A Monitoring system location B Monitoring system - SISGEO Instruction Manual C Devices Certificate D Drilling and Verticality tests of Invert pendulums
C-CO-C-AGD-TR-014-A0.doc
Coyne et Bellier
September 2011
THXP
Appendix
Anchor
Reading plate
412.47
Pulley
459.18
Installation date
To be installed 05/08/2011
direct inverted interm direct inverted direct inverted 380.92 381.42 362.02 362.52 379.00 379.50
429.1
419.2
412.7
401.0
390.0
381.0
401.5
408.3
418.4
427.8
429.3
420.0
413.0
401.3
390.3
381.3
402.0
408.6
418.7
428.1
420.54
418.1
401.502 430.13
437.32
439.82 449.03
C-CO-C-AGD-TR-014-A0.doc
Coyne et Bellier
September 2011
Cells
PC1-PC1 0+160 384 415 9 264.7 24.7 9 534.6 24.1 8 402.9 25.6 9 476.0 20 -8.54358 30/06/11
PC4-PC4 0+385 392 392 10 274.4 29.7 10 512.4 32 10 183.0 30 10 472.0 21 -4.82147 02/12/10 21 -6.33048 02/12/10 9 016.0 25.1 25.7 10397.0 21 -5.01449 28/05/11 7 628.3 9532.0 27.2 24.7 8 989.2 10417.8 10272.3 28.2 9595.8 28.4 10274.0 21 -5.52646 29/05/11 25.3 25.4 27.6 7 625.9 9542.7 9657.3 377 383.4 389.3 377.9 9127.0 23.8 9984.8 24.1 9120.3 23.8 9964.0 22 -3.67491 28/05/11 377 383.2 388.9 377.7 395.8 396.1 8979.6 29.7 9283.6 28.4 8865.7 26.5 9244.0 21 -5.01504 11/06/11 384.9 385.0 9671.5 25.6 10361 30.5 9644.6 262.0 10359.0 21 -4.97963 09/06/11 409.74 410.04 8 783.3 36.9 9 655.5 38.4 8 813.4 26.5 9 630.0 21 -8.52289 11/06/11 396.77 397.07 7 060.4 24.4 9 079.1 28.2 7 096.7 26.3 9 030.0 20 -8.81527 11/06/11 PC4-PC5 PC5-PC1 PC5-PC2 PC5-PC3 PC5-PC4
PC1-PC2 0+220 390 390 9 868.9 29.1 10 298.7 17.4 9 890.3 27.1 10 297.0 21 -4.04189 16/03/11
PC5-PC5
PC1-PC3 0+273 374 374 9 620.1 25.2 10 643.0 25 9 614.4 25.2 10 660.0 22 -4.90809 02/12/10
PC6-PC1
PC2-PC1 390 390 10 611.3 30.9 11 027.0 26 10 565.9 31 11 062.0 21 -5.5358 02/12/10
PC6-PC2 PC6-PC3 0+434 410.36 410.47 7 480.8 26.5 8 479.1 25 7 436.7 25.9 8 405.0 21 -8.93759 04/06/11 412.4 412.45 9 571.1 27.7 10 250.0 24.5 9 447.9 27.9 10 212.0 21 -8.34727 04/06/11
PC2-PC2 374 374 10 153.9 25.2 11 097.2 24 10 152.3 25.2 11 118.0 21 -4.36706 02/12/10
PC6-PC4
PC2-PC3
PC3-PC1
PC3-PC2
PC3-PC3
PC3-PC4
PC3-PC5
THXP
ch.
Borehole head (m.a.s.l) 412.7 8 988.3 26.7 9 264.2 28.2 9 082.6 26.4 9 563.0 20 -9.60173 05/05/11 07/05/11 05/05/11 16/03/11 -9.17367 -9.33791 -5.37929 20 21 21 9 663.0 10 067.0 9 193.0 28.3 26.7 26.7 9 638.4 9 364.5 8 356.1 29.2 28.6 18.9 9 842.6 9 641.2 9 172.8 9 683.2 9 506.7 8 344.6 402 412 402 384
425.85
10 644.3
8 556.5
T C
26.2
10 629.5
9 604.4
C-CO-C-AGD-TR-014-A0.doc
T C
24.1
4. Pressure cells
10 417.2
8 489.1
T C
25.6
10 604.0
9 546.0
T C
21
-8.5854
-9.60403
30/06/11
30/06/11
Coyne et Bellier
Cells
PC4-PC1
PC4-PC2
ch.
376
387
376
387
8256.80
8 815.3
T C
26
26.8
9 396.7
9 527.5
T C
24.3
24.2
8 361.6
9 422.0
T C
25.6
26.7
9 368.0
9 533.0
T C
21
21
-4.79312
-4.88015
Appendix
September 2011
05/03/11
07/03/11
THXP
Appendix
1. Instruction Manuel Piezometers 2. Instruction Manuel Direct and Inverted Pendulums 3. Instruction Manuel Optical Coordinometer 4. Instruction Manuel Thermometers 5. Instruction Manuel Joint-Meters 6. Instruction Manuel Flow Meter 7. Instruction Manuel Cable Splicing Kit 8. SISGEO Catalogue
C-CO-C-AGD-TR-014-A0.doc
Coyne et Bellier
September 2011
THXP
Appendix
C-CO-C-AGD-TR-014-A0.doc
Coyne et Bellier
September 2011
THXP
Appendix
C-CO-C-AGD-TR-014-A0.doc
Coyne et Bellier
September 2011
Invert pendulum at ch. 0+233 Distance between the pulley and the top of the hole: 26/07/2011 Deviation Deviation Deviation Depth bottom bottom Direction top EST SOUTH m mm mm mm 1 Est 3 3.6 3.6 1 South 3 2 Est 3 4.3 4.3 2 South 3 3 Est 3 4.9 4.9 3 South 3 4 Est 3 5.5 5.5 4 South 3 5 Est 3 6.2 6.2 5 South 3 6 Est 3 6.8 6.8 6 South 3 7 Est 3 7.4 7.4 7 South 3 8 Est 3 8.0 8.0 8 South 3 9 Est 3 8.7 8.7 9 South 3 10 Est 3 9.3 9.3 10 South 3 11 Est 3 9.9 9.9 11 South 3 12 Est 3 10.6 10.6 12 South 3 13 Est 3 11.2 14.9 13 South 4 14 Est 3 11.8 11.8 14 South 3 15 Est 3 12.5 16.6 15 South 4 16 Est 3 13.1 17.4 16 South 4 17 Est 3 13.7 13.7 17 South 3 18 Est 3 14.3 14.3 18 South 3 19 Est 3 15.0 20.0 19 South 4 20 Est 3 15.6 20.8 20 South 4 21 Est 3 16.2 16.2 21 South 3 22 Est 3 16.9 16.9 22 South 3 23 Est 3 17.5 17.5 23 South 3 24 Est 3 18.1 18.1 24 South 3 25 Est 3 18.8 18.8 25 South 3 26 Est 3 19.4 19.4 26 South 3 27 Est 3 20.0 20.0 27 South 3 28 Est 3 20.6 20.6 28 South 3 29 Est 3 21.3 21.3 29 South 3 30 Est 3 21.9 21.9 30 South 3 31 Est 3 22.5 22.5 31 South 3 32 Est 3 23.2 23.2 32 South 3 4.76 m
Deviation - Est
Deviation (mm) 0 0 5 10 15 20 25
10
Depth (m)
15
20
25
30
35
Deviation - South
Deviation (mm) 0 0 5 10 15 20 25
10
Depth (m)
15
20
25
30
35
Invert pendulum at ch. 0+364 Distance between the pulley and the top of the hole: 22/06/2011 Deviation Deviation Deviation Depth bottom bottom Direction top EST SOUTH m mm mm mm 1 Est 0 0.0 0.0 1 South 0 2 Est 0 0.0 0.0 2 South 0 3 Est 0 0.0 0.0 3 South 0 4 Est 0 0.0 0.0 4 South 0 5 Est 0 0.0 0.0 5 South 0 6 Est 0 0.0 0.0 6 South 0 7 Est 0 0.0 0.0 7 South 0 8 Est 0 0.0 0.0 8 South 0 9 Est 0 0.0 0.0 9 South 0 10 Est 0 0.0 0.0 10 South 0 11 Est 0 0.0 0.0 11 South 0 12 Est 0 0.0 0.0 12 South 0 13 Est 0 0.0 0.0 13 South 0 14 Est 0 0.0 0.0 14 South 0 15 Est 0 0.0 0.0 15 South 0 16 Est 0 0.0 0.0 16 South 0 17 Est 0 0.0 0.0 17 South 0 18 Est 0 0.0 0.0 18 South 0 19 Est 0 0.0 0.0 19 South 0 20 Est 0 0.0 0.0 20 South 0 21 Est 0 0.0 0.0 21 South 0 22 Est 0 0.0 0.0 22 South 0 23 Est 0 0.0 0.0 23 South 0 24 Est 0 0.0 0.0 24 South 0 25 Est 0 0.0 0.0 25 South 0 26 Est 0 0.0 0.0 26 South 0 27 Est 0 0.0 0.0 27 South 0 28 Est 0 0.0 0.0 28 South 0 29 Est 0 0.0 0.0 29 South 0 30 Est 0 0.0 0.0 30 South 0 31 Est 0 0.0 0.0 31 South 0 32 Est 0 0.0 0.0 32 South 0 4.91 m
Deviation - Est
Deviation (mm) 0 0 0 0 1 1 1
10
Depth (m)
15
20
25
30
35
Deviation - South
Deviation (mm) 0 0 0 0 1 1 1
10
Depth (m)
15
20
25
30
35
Invert pendulum at ch. 0+416 Distance between the pulley and the top of the hole: 15/07/2011 Deviation Deviation Deviation Depth bottom bottom Direction top EST SOUTH m mm mm mm 1 Est 0 0.0 2.5 1 South 2 2 Est 0 0.0 2.9 2 South 2 3 Est 0 0.0 3.4 3 South 2 4 Est 0 0.0 3.9 4 South 2 5 Est 0 0.0 4.3 5 South 2 6 Est 0 0.0 4.8 6 South 2 7 Est 0 0.0 0.0 7 South 0 8 Est 0 0.0 0.0 8 South 0 9 Est 0 0.0 3.1 9 South 1 10 Est 1 3.3 6.7 10 South 2 11 Est 1 3.6 7.1 11 South 2 12 Est 1 3.8 7.6 12 South 2 13 Est 1 4.0 8.0 13 South 2 14 Est 1 4.3 8.5 14 South 2 15 Est 0 0.0 9.0 15 South 2 16 Est 0 0.0 0.0 16 South 0 17 Est 0 0.0 0.0 17 South 0 18 Est 0 0.0 0.0 18 South 0 19 Est 0 0.0 0.0 19 South 0 20 Est 0 0.0 0.0 20 South 0 21 Est 0 0.0 0.0 21 South 0 22 Est 0 0.0 6.1 22 South 1 23 Est 0 0.0 6.3 23 South 1 24 Est 0 0.0 13.2 24 South 2 25 Est 0 0.0 6.8 25 South 1 26 Est 0 0.0 7.0 26 South 1 27 Est 0 0.0 7.3 27 South 1 28 Est 0 0.0 15.0 28 South 2 29 Est 0 0.0 15.5 29 South 2 30 Est 0 0.0 16.0 30 South 2 31 Est 0 0.0 16.4 31 South 2 32 Est 0 0.0 16.9 32 South 2 4.30 m
Deviation - Est
Deviation (mm) 0 0 1 2 3 4 5
10
Depth (m)
15
20
25
30
35
Deviation - South
Deviation (mm) 0 0 5 10 15 20
10
Depth (m)
15
20
25
30
35