Beruflich Dokumente
Kultur Dokumente
Lecture 1 Introduction To Rock Engineering CIVL6078 (September 2009) Different Classes of Problems in Rock Engineering
Areas of Application in Rock Mechanics: Rock Slope Engineering Foundation on Rock Rock Fall Hazard Tunnelling in Rock Cavern in Rock Blasting in Rock Mining in Rock Bursting in Rock Areas Require Fundamental Principles in Rock Mechanics: In-site Stresses Rock Mass Properties Joint Properties Stress Strain Behavior Stabilization Measures: Rock Bolts, Cables, Buttresses, Shotcrete Seepage in Rock
2
Data on Debris Mobility for Different Mechanisms and Scales of Landslides in Hong Kong 3
10
11
Mound of debris
During the filling of the Vajont reservoir the toe of the slope on Mount Toc was submerged and this precipitated a slide. The very rapid descent of the slide material displaced the water in the reservoir causing a 100 m high wave to overtop the dam wall. The dam itself was largely undamaged.
12
The town of Longarone, located downstream of the Vajont dam, before the Mount Toc failure in October 1963.
The remains of the town of Longarone after the flood caused by the overtopping of the Vajont dam as a result of the Mount Toc failure. More than 2000 persons were killed in this flood.
13
A wedge failure controlled by intersecting structural features in the rock mass forming the bench of an open pit mine.
14
16
17
18
19
20
Comparison between risks of fatalities due to rockfalls with published and proposed acceptable risk criteria.
21
22
23
24
25
26
27
The Importance of Structurally Controlled Instability must be Recognized Geological Data Collection
28
Joint
29
30
Scanner or
31
32
33
34
35
36
37
38
39
Foundation in Rock
40
41
42
43
Barton (1989)
44
Relative size of the opening to the jointing system Transition from isotropic intact rock specimen to highly anisotropic rock mass (controlled by joints) to isotropic heavily jointed rock mass 45
46
47
48
49
50
Tunnelling in Rock
51
52
Hughes (2002)
53
Hughes (2002)
54
Hughes (2002)
55
Smooth Circular Lined Water Supply Tunnel to: Reduce hydraulic friction losses Withstand high internal pressure for hydroelectric project Prevent contamination from groundwater ingress
Pakianathan (2002)
56
57
58
18
A
1
B A-A
12 8 5 13 14 15
C B-B
16 11 18 12 10
C-C
17
1 Cutting wheel 2 Excavation chamber 3 Main drive shaft 4 Gearbox assembly 5 Electric drive motor
6 Screw conveyor 7 Screw conveyor drive 8 Steering cylinder 9 Articulation seal 10 Hydraulic tank
11 Electric motor 12 Main electric panel 13 ELS Laser target 14 Telescopic cylinder 15 Gate valve
59
60
61
62
63
64
65
66
Toll Plaza
Slip-Road Bridges
67
Northbound Southbound
SHT Details: Dual Three-lane 1km long 10 Cross-passages (100m c/c) Opening Size: Span 19m, Height 11m Full face area: ~ 160 sq. m
68
Horseshoe Area =
Coarse-grained GRANITE with local intrusion of Basalt and Rhyolite dykes (typically 2m thk., with sharp boundary) Mantle of weathered rock (thk. = 5-55m) Typical Joint Characteristics: closely to medium spaced, rough stepped planar, extremely narrow with surface staining Lai Chi Kok-Tolo Channel Fault sub-parallel to SHT Subvertical Minor Fault to cut across SHT (Dip/Strike: 80/300-350)
69
Northbound Tunnel
Typically Grade II Granite (occasional Grade III) Typical rock cover 30-50m (Shallow rock cover <6m at Portals) Local weak zones (20-30m wide) GWL typically at R/H level (GWL at tunnel invert at portal)
70
Top Bench Top Heading & Bench (from South) Full face Top heading allow easy access for roof support, limit opening size
Pilot
Pilot and Stopping (from North) More Sensitive receivers (charge weight limited, tunnel advancement limited) Pilot tunneling as exploration
71
(Waterproofing works and Permanent Lining works to be carried out after certain advancement of tunnel excavation)
72
73
Charging
74
Stemming Firing/detonation
Delayed blasting to minimize vibration
75
Firing/detonation
Blast Screen Blast Door
76
77
CLP Pylon
Woodcrest Hill
Keng Hau Road Residential WSD TUNNELS and Water Treatment Plant
78
Structures and Utilities Assessment based on Condition Inspection, published guidelines and consultation with affected owners/operators
Structure/Utility Buildings* CLP Pylon WSD Tunnel WSD watermain Tai Po Road and associated services Max PPV (mm/s) 25 25 13 25 25 Reference General Specs vol.1 General Specs vol.1 Set by WSD Set by WSD General Specs vol.1
*for Keng Hau Road residential and Luk Hop Village, a conservative limit of 5mm/s and 10mm/s respectively has been adopted.
79
Estimation of Allowable Charge Weight per Delay (W) Empirical Vibration Attenuation Equation (United States Bureau of Mines) PPV = K {D/ sq. rt (W)}^A
where PPV = Peak Particle Velocity (mm/s) D = distance between the blast and the receiver W = Allowable Charge Weight per Delay K & A = Site specific variables
Based on Data from Mines & Quarries Division (GEO), K = 1032 & A = -1.22 (95% confidence level) Site Specific K & A to be verified from Trial Blast results by regression analysis with continuous refinement during Production Blast
80
Air Overpressure
Empirical Equation (United States Bureau of Mines) Pa (kPa) = K (D/W^A)^B,
where A = -0.33, B = -1.1, K = 2.49 Pa = 120 dB Human discomfort Pa = 140 dB structural damage
But Pa can be influenced by weather and disturbance subjective to human perception Air overpressure monitored at residential areas
81
Level Alert
Alarm
80%
Blast Effect to be reviewed & Blast Design to be agreed Blast ceased, no work until approved Mitigation Measures implemented
Action
100%
82
Science Art
0% 100%
25% 75%
50% 50%
75% 25%
100% 0%
83